03 - RN31543EN50GLA0 - Radio Network Planning Process

Uploaded by

KHOA NGUYEN DANG
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 23

Nokia Academy

Radio network planning process

RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Module Objectives

At the end of the module you will be able to:


• Explain the radio network planning process
• Explain the main steps in dimensioning process

5 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Radio Network Planning Process

- Radio Network Planning process


- Radio Network Dimensioning process
- Appendix

6 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Radio network planning phases

PRE- DETAILED POST-


PLANNING PLANNING PLANNING

Dimensioning Configuration Coverage & Capacity Parameter Post-launch


Planning Planning Planning optimisation
Requirements &
strategy for Node-B Propagation measurements Area/cell Measurement
coverage, Configuration Coverage prediction specific surveys
capacity &
quality Load estimation Handover Statistical
Antenna line Traffic distribution strategies performance
configuration Planned Service & QoS analysis
PER SERVICE definition other RRM
 Quality
Power budget  Efficiency
 Network
Site selection & planning  Availability
configuration PER SERVICE Pre-launch
optimisation
Site
acquisition Measurements

7 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Radio network planning tasks
Site selection & planning
- Practical site selection based on target site locations & available sites
- Site implementation plan
- Actual site locations & implementation plans

Configuration Planning
- Configuration planning is related to possible configurations as well as feature implementation
- Future configuration takes into account the possibility to expand

Coverage & Capacity Planning


- is very much tied to Site selection & Configuration planning
- Coverage requirements needs to be met
- Capacity requirements estimated + future expansions

Parameter planning
- Initial parameter configuration
- Scrambling code plan, neighbour plan
- Detailed parameter planning
- Optimised/verified parameter plan

8 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Planning tasks & network
- Pre-planning activities are high especially when operator is Greenfield or deploying a new technology

- Main focus in existing networks are in coverage & capacity as well as configuration planning

- Optimisation is always recommended to be done and kept as a very important task of network operation

9 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Overall planning and optimisation process

• The overall Planning Process can be described with the following figure:

Performance
PerformanceMonitoring
Monitoring
System Radio Network Pre-launch Post-launch Capacity
Dimensioning Planning Optimisation Optimisation Evolution
• Site selection • 3G neighbor list • 3G neighbor list • RF carriers
• Node B count & • Site design • 2G neighbor list • 2G neighbor list • Sectorisation
configuration • 3G neighbor list • 4G neighbor list • 4G neighbor list • ROC to CEC
System modules
• Adapter count & • 2G neighbor list • Antenna tilts
• Antenna tilts • Node B power
• 4G neighbor list • Local area parameter
configuration • Local area parameter • Baseband proc.
• Scrambling codes tuning
• Transmission capacity tuning • Transmission
• Location areas • Additional sites
& configuration •
• HSPA/HSPA+
Routing areas • User experience
• URA areas • New Features
optimisation
• Microcells

Link budget analysis Wide area parameter tuning

10 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Radio Network Planning Process

- Radio Network Planning process


- Radio Network Dimensioning process
• Dimensioning process
• Traffic dimensioning (DCH + HSDPA, DCH + HSPA)
- Appendix
• Dimensioning in case of Rel99 traffic only

11 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Radio Network Dimensioning process – Basics

Dimensioning process can be split in high level steps:


• Input data: has big influence on whole result
• Cell Plan: needs to follow customer input & system performance
• UTRAN Network Plan: needs to follow customer requirements and also detailed mapping to planned network conditions
• UTRAN Final Network: is the result from the iterative analysis of inputs, performance values and also area &
requirement mapping

Fixed Network
Plan - UTRAN

Final Network
Input Data

Cell Plan

UTRAN
12 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.
Input Data
Input data includes for example:
• Traffic model & capacity requirements
• Coverage Requirements
• Quality Requirements
- similarly customer might have special requirements (e.g. road, train coverage)
- when number of sites is fixed, the traffic model, capacity/coverage and quality requirements are not used as input
- More as an output of estimation (i.e. what can be achieved with X number of sites)

13 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Traffic Model – Nokia Standard
NOKIA Standard Traffic Model (Basic Assumptions) can be used:
- purpose of having a default traffic model is to have information about the traffic demand available if
there is no detailed traffic model provided for network dimensioning
- NOKIA Standard Traffic Model reflects average situation in real networks and is defined:
- assuming a ‘standard’ subscriber
- using all accounted services in parallel – the service split is applied on a traffic demand basis (no
split on a subscriber basis)
UMTS Traffic Evolution:
the current NOKIA view on the evolution of traffic demand for a set of identified key services in UMTS.
These key services considered in the traffic model are:
 Speech service
 Data services like web browsing, email or file download
 Video telephony
UMTS Traffic Evolution is based on the traffic snapshots from commercial networks and internal assumptions for Subscriber
traffic growth

See ``Dimensioning WCDMA RAN: Traffic Modeling (DN0979695)`` from RU50 Customer Documentation

14 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Cell Plan

Cell Planning includes


• offered traffic & its distribution
• link budget  coverage
• maximum air interface capacity
• Node B Hardware configuration

Cell coverage is dependent on:


• Frequencies
• System performance
• Antennas
• Environment characteristics

Cell capacity is dependent on:


• Traffic model
HW configuration is dependent on:
• Frequencies
• Cell coverage, sectorisation, # of carriers
• selected features
• Selected features & capacity requirements

15 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Cell Plan & Example inputs for coverage, capacity & HW
• Basic information needed for dimensioning
- frequency (e.g. 2100, 1900, 850) Antenna gain
- Clutter type (e.g. dense urban, urban, suburban, rural). MHA usage
- Subscribers, subscribers/area # of sectors
- Total area to be covered [ km2] # of sectors
• UE information
- UE type: transmit power (dBm) & possible antenna gain (dB)
- Body loss Feeder losses

• Node B information
- Node B type (e.g. noise figure) Pilot transmit power
- Antenna & antenna gains Noise Figure
- cable loss UL/DL (MHA usage) Transmit power
- # of carriers, # of sectors
Antenna gain
- Node B output power (40W/20W) CPICH EIRP Frequency
Body Loss
• HSPA information Noise Figure
- HSDPA associated DCH Path loss & margins Output power
- Scheduling algorithm (e.g. RR or PF) cell range calculation # of carriers
- Number of codes, 5/10/15
- Number of HSDOA/HSUPA users & L1 throughput
• Link budget gains & margins per clutter
- Antenna height BS / UE
- Location probability, Indoor location probability
- Building penetration loss
- Coverage limiting Standard deviation
• Area & capacity factors
- service, UL DPCH (16/64/128/384), HSDPA (cell edge throughput) or HSUPA (cell edge throughput) & Planned load

16 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


UTRAN Network Plan  Final network

- Based on cell plan


- Incl. traffic modeling
- Noticing also environment characteristics & special requirements
- Main inputs:
• Area size
• Number of sites & configurations
• Detailed access interface configuration & connections

17 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Coverage & capacity dimensioning
- Dimensioning process main parts:
• Coverage dimensioning  Link Budget
• Capacity dimensioning  Air Interface and Baseband capacity
- Link budget & Capacity dimensioning are connected to each other via the air interface load
- Iterations may be needed to get both right

Capacity for:
• DCH services
Coverage based on:
• HSDPA
• DCH services • HSUPA
• HSDPA Coverage Capacity • Voice over HSPA
• HSUPA dimensioning dimensioning • Service (e.g.DCH)
• Voice over HSPA impact on other services
(e.g.HSPA)
• Spreading Code capacity

Link budget Capacity

18 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Radio Network Planning Process

- Radio Network Planning process


- Radio Network Dimensioning process
• Dimensioning process
• Traffic dimensioning (DCH, DCH + HSDPA, DCH + HSPA)
- Appendix
• Dimensioning in case of Rel99 traffic only

19 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Dimensioning in case of Rel99 & HSDPA traffic
- Link Budget calculation for:
• DCH Channels
• HSDPA cell edge throughput Many issues impacts
on inside cell throughput
- DCH Link Budget calculation:
• for bearers for which coverage is requested
• using default or project specific parameters
- HSDPA Link Budget calculation
• for max. cell edge throughput
- Cell edge condition is always worst case
- Throughput is still limited by many issues
• UE capability
• Features
• Interference At cell edge ~350 kbps, macro cell
• Available power & code tree Mean cell throughput
(1 transimttion upto 15 codes)
cell edge
3,5
- Identification of the limiting bearer in UL & DL (incl. HSDPA link)
• The one with the smallest cell range 3,0

Same distance can


- Optional: Calculation of CPICH Link Budget in relation with the 2,5
mean totally
limiting bearer

data rate [Mb/s]


2,0 different conditions
- Capacity & equipment calculation
1,5
• among R99 limitation (e.g. total number of sites available)
• HSDPA capacity  SINR 1,0

• HSDPA with lower priority than R99 CS services 0,5


• HSDPA features impact on capacity + needed HW
0,0
0,45 0,6 0,75 0,9 1,05 1,2 1,35
antenna distance [km]

20 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Dimensioning in case of Rel99 & HSPA traffic
- DCH Link Budget calculation
• Identification: limiting UL bearer (incl. HSUPA link) & DL (incl. HSDPA link)
• For bearers for which coverage is requested
• The one with the smallest cell range
• Using default or project specific parameters
• HSUPA: new challenges on dimensioning
- HSDPA Link Budget calculation
• HSUPA is sharing capacity between other UL services
• for max. cell edge throughput ( Rel’99 & HSDPA traffic)
• HSUPA equipment dimensioning differs from R99 & HSDPA
• Using default or project specific parameters
• When network HSPA services are increasing commonly additional carrier is
- HSUPA Link Budget calculation
needed (higher HSPA demand)
• For cell edge throughput
• Using default or project specific parameters

21 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Radio Network Planning process - Summary

• Planning process can be divided to 3 main phases:


• Pre-planning
• Detailed planning
• Successful dimensioning depends on sufficient & accurate input data
• Even best dimensioning results provides only an estimate

22 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Radio Network Planning Process

- Radio Network Planning process


- Radio Network Dimensioning process
• Dimensioning process
• Traffic dimensioning (DCH + HSDPA, DCH + HSPA)
- Appendix
• Dimensioning in case of Rel99 traffic only

23 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Dimensioning in case of Rel99 traffic only
- DCH Link Budget calculation
• For bearers for which coverage is requested
• Using default or project specific parameters
- Identification of the limiting bearer in UL & DL Coverage Capacity
• The one with the smallest cell range dimensioning dimensioning
- Optional: Calculation of CPICH Link Budget in relation with the limiting bearer
- Usage of the Link Budget results to the Capacity dimensioning
• How many sites available within certain loading assumptions
- Capacity & equipment calculation

24 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.


Thank You !

25 RN31543EN50GLA0 ©2014 Nokia Solutions and Networks. All rights reserved.