Problems Long Term Const Contracts
Problems Long Term Const Contracts
JOURNAL ENTRIES
a.) Input Measure - Percentage of Completion (Cost-to-cost) Const in Progress
20x3 20x4 20x5 Materials Inventor
Initial Contract Price 528,000.00 528,000.00 528,000.00
Variation - 12,000.00 12,000.00
Total Contract Price 528,000.00 540,000.00 540,000.00 Accts Receivable
Actual Cost Incurred each year 126,048.00 238,032.00 127,920.00
Add: Costs Incurred in Prior Year(s) - 126,048.00 364,080.00
Total Costs Incurred to date 126,048.00 364,080.00 492,000.00 Cash
Est. Cost to Complete 358,752.00 253,968.00 -
Total Estimated Cost at Completion 484,800.00 492,000.00 492,000.00
Est. Total Gross Profit 43,200.00 48,000.00 48,000.00 Construction Costs
Multiply by %age of Completion 26.00% 74% 100% Const in Progress
Gross Profit Earned to date 11,232.00 35,520.00 48,000.00
Less: Gross Profit earned In prior Year(s) - 11,232.00 35,520.00
Gross Profit Earned This year 11,232.00 24,288.00 12,480.00 Contract Billings
Accts Receivable
Cash
Construction Costs
Const in Progress
Contract Billings
Nota Bene:
The Difference between the CIP and CB is a Contract Asset when CIP is greater than CB account.
The Difference between the CIP and CB is a Contract Liability when CB is greater than CIP account.
20x5
6,000.00
121,920.00
156,000.00
192,000.00
140,400.00
540,000.00
20x5
6,000.00
121,920.00
156,000.00
192,000.00
175,920.00
540,000.00
CAHPTER 10 - LONG-TERM CONSTRUCTION CONTRACTS
Contract Billings
Cash
Construction Costs
Contract Billings
1,000,000.00 1,500,000.00
Accts Receivable 1,000,000.00 1,500,000.00
1,000,000.00 1,500,000.00
Accts Receivable 1,000,000.00 1,500,000.00
Construction Costs 1,500,000.00 1,300,000.00
Const in Progress 200,000.00 100,000.00
Construction Revenue 1,300,000.00 1,200,000.00
Nota Bene:
The Difference between the CIP and CB is a Contract Asset when CIP is greater than CB account.
The Difference between the CIP and CB is a Contract Liability when CB is greater than CIP account.
Note further:
Observe that, under both methods, in case of anticipated contract losses,
the CIP account would be the same.
CIP account.
CAHPTER 10 - LONG-TERM CONSTRUCTION CONTRACTS
1.) P50.0M - Construction in Progress is the total of Costs and GP. So if the CIP per Balance sheet is P50.00M, so is
4.) Percentage of Completion = 50.00M Alternative way to compute for %age of completion w
150.00M costs is not given in the problem.
= 33.33%
sheet is P50.00M, so is the Revenue.