Individual Assignment #1 - Network Diagram Exercise

The document provides instructions for a project network exercise. It asks the student to: 1) Draw arrows to indicate the logical flow of the network 2) Fill in durations for each activity 3) Conduct forward and backward passes to calculate start/end dates 4) Identify the critical path It includes a work breakdown structure (WBS) with activities, predecessors, and durations.

Uploaded by

veenajkumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
655 views

Individual Assignment #1 - Network Diagram Exercise

The document provides instructions for a project network exercise. It asks the student to: 1) Draw arrows to indicate the logical flow of the network 2) Fill in durations for each activity 3) Conduct forward and backward passes to calculate start/end dates 4) Identify the critical path It includes a work breakdown structure (WBS) with activities, predecessors, and durations.

Uploaded by

veenajkumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Project Network Exercise

Name:

Student ID:

Complete the exercise. You will need to:

1. Draw in the arrows that indicate the logical flow of the network.
2. Fill in the durations.
3. Conduct a forward pass of the network.
4. Conduct a backward pass of the network.
5. Clearly indicate the critical path.

WBS
ID Activity Predecessor Duration
A Order review 1
B Order parts A 6
C Produce parts A 4
D Design parts A 1
E Software Dev. A 3
F Manufacture parts B,C 6
G Assemble D,E 4
H Test F,G 9
B ES ID EF
SL
LS DUR LF

C F

A H

D G

E Name

Student ID
Project Network Exercise

Name:

Student ID:

Complete the exercise. You will need to:

1. Draw in the arrows that indicate the logical flow of the network.
2. Fill in the durations.
3. Conduct a forward pass of the network.
4. Conduct a backward pass of the network.
5. Clearly indicate the critical path.

WBS
ID Activity Predecessor Duration
A Order review 2
B Order parts A 5
C Produce parts A 7
D Design parts A 9
E Software Dev. A 5
F Manufacture parts B 1
G Assemble C, D, E 3
H Test F,G 1
B ES ID EF
SL
LS DUR LF

C F

A H

D G

E Name

Student ID
Project Network Exercise

Name:

Student ID:

Complete the exercise. You will need to:

1. Draw in the arrows that indicate the logical flow of the network.
2. Fill in the durations.
3. Conduct a forward pass of the network.
4. Conduct a backward pass of the network.
5. Clearly indicate the critical path.

WBS
ID Activity Predecessor Duration
A Order review 3
B Order parts A 4
C Produce parts A 8
D Design parts A 10
E Software Dev. A 6
F Manufacture parts B, C, D 2
G Assemble E 5
H Test F,G 3
B ES ID EF
SL
LS DUR LF

C F

A H

D G

E Name

Student ID
Project Network Exercise

Name:

Student ID:

Complete the exercise. You will need to:

1. Draw in the arrows that indicate the logical flow of the network.
2. Fill in the durations.
3. Conduct a forward pass of the network.
4. Conduct a backward pass of the network.
5. Clearly indicate the critical path.

WBS
ID Activity Predecessor Duration
A Order review 4
B Order parts A 3
C Produce parts A 2
D Design parts A 5
E Software Dev. A 4
F Manufacture parts B,C 7
G Assemble D,E 2
H Test F,G 4
B ES ID EF
SL
LS DUR LF

C F

A H

D G

E Name

Student ID