No. of Days / Unit of Quanity
No. of Days / Unit of Quanity
Total Mandays 40
TOTAL DIRECT COST: 22,800.00
UNIT COST: 1,256.20
A. Materials
RENTAL RATE /
PRICE COMPONENT NO. NO. OF DAYS Mandays AMOUNT SUB-TOTAL TOTAL
UNIT COST
A. Materials :
B. Labor:
Engineer 1 5 5 800.00 4,000.00
Foreman 1 5 5 650.00 3,250.00
Laborer 4 5 20 350.00 7,000.00
14,250.00
Total Mandays 30
A. Materials
Total Mandays 21
37,292.96
B. Labor
Engineer 1 6 6 800.00 4,800.00
Foreman 1 6 6 650.00 3,900.00
Carpenter 2 6 12 550.00 6,600.00
Laborer 4 6 24 350.00 8,400.00
Steelman 2 6 12 550.00 6,600.00
Mason - - - 550.00 -
30,300.00
Total Mandays 60
B. Labor
Total Mandays 70
Total Mandays 88
Area = 65 sq.m.
A. Materials
4" x 4" Plastic junction box with cover 25 pcs 70.00 1,750.00
2 SQ. MM WIRE ROYU 150 MTRS. BOX 4 box 2,750.00 11,000.00
Pin light w/ CFL bulb 22 pcs 140.00 3,080.00
50 watts LED light 7 pcs 500.00 3,500.00
1 gang switch 1 pcs 100.00 100.00
2 gang switch 5 pcs 120.00 600.00
3 gang switch 1 pcs 140.00 140.00
2 gang C.O. 8 pcs 120.00 960.00
ground rod w/ clamp, 5/8 x 3m 1 pcs 500.00 500.00
PVC Pipe Orange 20 mm dia 50 MTRS 3 pcs 850.00 2,550.00
25 mm r.s.c. 3 mtrs. 200.00 600.00
electric tape, big 15 pcs 120.00 1,800.00
60 amp breaker w/ panel 1 pcs 5,000.00 5,000.00
15 amp Plug in type C.B. 3 pcs 450.00 1,350.00
20 amp Plug in type C.B. 3 pcs 600.00 1,800.00
30 amp Plug in type C.B. 1 pcs 800.00 800.00
Miscellaneaous 1 lot 5,000.00 5,000.00
Meter to house wiring (Electric Cooperative) 1 lot 5,000.00 5,000.00
45,530.00
B. Labor
Mandays 24 20,400.00
Mandays 30
19,500.00
TOTAL DIRECT COST: 48,775.00
UNIT COST: 48,775.00
Mandays 52
32,600.00
Mandays 48
33,000.00
TOTAL DIRECT COST: 209,742.50
UNIT COST: 209,742.50
Prepared by:
TEDDIE C. CAMBE
LICENSE NO. 0128764
BREAKDOWN OF COST ESTIMATE (FULLY FURNISHED)
Cost
Item No. Description Quantity Unit Total / Item
Materials Labor
101 Structural Excavation 18.15 cu.m. - 22,800.00 22,800.00
102 Concreting of Foundation, Starter Column 6.43 cu.m. 33,296.46 26,000.00 59,296.46
103 Earth Fill and Gravel Fill 54.06 cu.m. 33,452.10 14,250.00 47,702.10
103-1 Concreting of Column Lift 1.69 cu.m. 24,450.35 21,750.00 46,200.35
103-2 Concreting of Slab on Fill 6.76 cu.m. 26,966.97 11,400.00 38,366.97
103-3 Concreting of Beams & Column Drop 3.62 cu.m. 37,292.96 30,300.00 67,592.96
104 Masonry Works 182.51 cu.m. 82,707.12 23,555.00 106,262.12
104-1 Plastering Works (Ground Floor) 284.37 sq.m. 19,305.38 45,650.00 64,955.38
105 Ceiling Works (Specialty) 1.00 lot - - 77,040.00
106 Doors & Window Installation 1.00 lot - - 81,800.00
107 Electrical Works (Ground Floor) 1.00 - 45,530.00 20,400.00 65,930.00
108 Plumbing Works @ Ground Floor 1.00 - 30,920.00 19,500.00 50,420.00
109 Painting Works, Tile Works 1.00 - 85,040.00 32,600.00 117,640.00
110 Roof Framing 1.00 - 176,742.50 33,000.00 209,742.50
Sub Total 1,055,748.84
Contractors Profit & Over Head 105,574.88
Total Construction Cost 1,161,323.73
Prepared by:
TEDDIE C. CAMBE
LICENSE NO. 0128764
BREAKDOWN OF COST ESTIMATE (ROUGH FURNISHED)
Cost
Item No. Description Quantity Unit Total / Item
Materials Labor
101 Structural Excavation 18.15 cu.m. - 22,800.00 22,800.00
102 Concreting of Foundation, Starter Column 6.43 cu.m. 33,296.46 26,000.00 59,296.46
103 Earth Fill and Gravel Fill 54.06 cu.m. 33,452.10 14,250.00 47,702.10
103-1 Concreting of Column Lift 1.69 cu.m. 24,450.35 21,750.00 46,200.35
103-2 Concreting of Slab on Fill 6.76 cu.m. 26,966.97 11,400.00 38,366.97
103-3 Concreting of Beams & Column Drop 3.62 cu.m. 37,292.96 30,300.00 67,592.96
104 Masonry Works 182.51 cu.m. 82,707.12 23,555.00 106,262.12
104-1 Plastering Works (Ground Floor) 284.37 sq.m. - - -
105 Ceiling Works (Specialty) 1.00 lot - - -
106 Doors & Window Installation 1.00 lot - - 81,800.00
107 Electrical Works (Ground Floor) 1.00 - 45,530.00 20,400.00 65,930.00
108 Plumbing Works @ Ground Floor 1.00 - 11,420.00 19,500.00 30,920.00
109 Painting Works, Tile Works 1.00 - - - -
110 Roof Framing 1.00 - 109,412.50 22,000.00 131,412.50
Sub Total 698,283.46
Contractors Profit & Over Head 69,828.35
Total Construction Cost 768,111.81
Prepared by:
TEDDIE C. CAMBE
LICENSE NO. 0128764