Sabas GRP Liner Spec v4
Sabas GRP Liner Spec v4
1.0 INTRODUCTION
This specification is constructed to cover the rehabilitation of large gravity sewers, pipelines
and culvert structures through the use of glass reinforced plastic (GRP) pipe segments.
The document has been constructed to provide materials that comply with both performance
requirements and prescriptive provisions of WIS 4-34-02. However, that well tried and tested
document was published in 1986 and this specification is designed to update references
contained within WIS 4-34-02, to provide for the use of ASTM and ISO standards where they
are most appropriate, and to utilise tools available within the most current GRP standards in
use within industry. The standard relies on the following primary source documents:
prEN 13121-3:2003: GRP Tanks and vessels for use above ground.
Design & workmanship.
C Glass Glass reinforced fibres formed from a low-soda borosilicate glass, regarded
as chemical resistant, primarily used for overlay or surfacing mats.
Effective The distance between planes normal to the unit axis and passing through
Length of unit the real end points of the lining unit
Lining section A discrete length of circumferentially continuous sewer lining which may be
either a single pipe lining unit or a combined pair of segmental linings units
Out of The maximum distance between the real end surface and a plane normal to
Squareness of the unit axis and passing through the real end point (See Figure 2.1 –
unit end Section through nominally straight unit (Diagrammatic Only))
Out of The maximum radial distance between the lining inner surface and any line
Straightness parallel to the unit axis touching the lining inner surface (See Figure 2.1 –
Section through nominally straight unit (Diagrammatic Only))
Pipe Lining Circular or non-circular sewer lining that has no longitudinal joints.
Real Corner The two points at each end of a lining segment at which the real end surface
Points meets the lines along which the inner surface of the lining is intended to be
jointed longitudinally to the adjacent lining segment (See Figure 2.1 –
Section through nominally straight unit (Diagrammatic Only))
Real End Point The extreme point on the real end surface (See Figure 2.1 – Section
through nominally straight unit (Diagrammatic Only))
Real End A surface joining the points against which the inner surface of the lining is
Surface intended to be jointed to the next lining section (See Figure 2.1 – Section
through nominally straight unit (Diagrammatic Only))
Segmental Circular or non-circular sewer lining that is made up from pairs of upper and
Lining lower segments, which are joined longitudinally at their springings.
Springings The highest point at each side of an installed lining where the tangent to the
internal surface is vertical
Total major The distance between the crown and the invert of a lining section
Axis length
Type II Design This procedure is applicable to the design of pipe linings forming no reliable
bond to the grout or old sewer. The design assumption is that the lining
eventually bears the full load from the ground and traffic. The lining system is
designed to act as a flexible pipe with the old sewer, annulus grout and soil
providing the necessary support to maintain stability to both circular and non
circular linings.
Unit Axis For a pipe lining section, the unit axis is a line passing through the centroids of
the real end surfaces. For a segment, the unit axis is a line passing through
the mid point of lines joining the real corner points at each end of the segment
(See Figure 2.1 – Section through nominally straight unit (Diagrammatic Only))
OUT OF STRAIGHTNESS
(SEGMENTS ONLY)
Surface tissue, where used, shall be manufactured from C glass glassfibre or synthetic
polyester fibres.
All glassfibre reinforcement shall have a surface treatment compatible with the lining
manufacturing process and the matrix resins. Glassfibre shall be E glass 90/10 unidirectional
(UD) matting to ISO 2113 combined with stitch bonded chopped strand mat (CSM) to ISO
2559, whereby 1 layer of CSM shall separate layers of UD matting to maintain laminar shear
strength in accordance with the requirements of prEN 13121-3:2001. The E type glass shall
be orientated with the fabric Warp laid in the ‘hoop’ direction to derive maximum pipe
stiffness and strength; the material shall be in accordance with the requirements of D4029-
04. It shall contain no more than 0.2% moisture by weight as supplied; it shall be
uncontaminated and protected to the point of use.
2.2.3 Aggregate
Aggregate when used as a part of the structural wall shall be clean, washed, high grade
silica sand containing no less than 95% silica and a size range between 0.05mm and 5mm
with an upper limit of 20% of the glass reinforced wall thickness. Aggregate shall contain no
more than 0.2% moisture by weight when tested in accordance with the method described in
ASTM C566-97(2004).
2.2.4 Filler
Any filler shall consist of clean inert material (e.g. silica) with a particle size below 0.05m and
shall be used only as a resin extender. Fillers shall be free from contaminants such as
sodium chloride, calcium chloride or potassium chloride and contain not more than 0.2%
moisture by weight when tested in accordance with the method described in ASTM C566-
97(2004) or BS 812-109:1990.
2.2.5 Resins
Isophthalic polyester resin complying with the requirements of Type B or C of BS 3532: 1990
or vinyl-ester resins shall be used. All resins shall be supplied pre-accelerated by the resin
manufacturer with the catalysation process undertaken in accordance with the resin
manufacturer’s instructions.
Cured resins, as cast singly without reinforcement, shall have an elongation at break greater
than 2.5% when tested in accordance with ASTM D638-03 or BS 2782-3:Methods 320A to
320F:1976. Resins “flexibilised” by the addition of plasticisers shall not be used.
Uncatalysed liquid polyester resins shall have an acid value of 20 or below when tested in
accordance with BS EN ISO 2114:2000, BS 2782-4:Method 432B:2000, or equivalence
when tested in accordance with ASTM D2690-98. A hydroxyl value of less than 30 when
tested in accordance with BS EN ISO 2554:1999, BS 2782-4:Method 432C:1997, or
equivalence when tested in accordance with ASTM E222.
Dyes and pigments shall not normally be included in the lining materials. Painting or any
other obscuration of the surface shall be limited to any marking or other process required by
this specification.
NOTE Coloration for the purposes of resin mix control may be permitted but only when approve by the resin
supplier.
2.3. CONSTRUCTION
2.3.1 General
All sewer linings shall be manufactured with the following elements (See Figure 2.3.1 – Liner
Construction):
I a single protective layer (SPL) consisting of either a veil layer (VL) or resin
layer (RL),
II a barrier layer (BL)
III a glass reinforced wall comprised of two outer reinforcing layers with a central
polymer mortar core
IV a rough backing to provide a bond between the lining and annulus grout
(necessary for Type I composite designs only)
Note 1: An optional non-slip invert coating may be provided additional to the resin rich liner.
SingleProtection
Layer Non-slip invert (optional)
Note 2 Barrier
Layer
Note 2: Whereby the SPL and BL, jointly form the corrosion protection liner.
The CPL (See Figure 2.3.1 – Liner Construction), comprised of the SPL and BL, shall
contain no filler or aggregate and shall have a maximum thickness of 1.5mm.
The thickness shall be a minimum of 0.25 and a maximum of 0.6 mm. The SPL shall consist
of a suitable RL comprised of a suitable flexible resin as per the raw material requirements of
EN 13121-2:2003. In the case that a VL is used, the resin system shall be added up to 10%
by weight of surface tissue.
The BL shall be manufactured from a suitable resin system reinforced with fibres of between
20-30% content by mass. Reinforcement shall be in the form of E or E type glass chopped
fibres, chopped strand mat or synthetic fibres.
The structural wall shall be made up from resin impregnated layers of E type glassfibre
separated by a polymer mortar core. The fibre reinforced skins shall include resin with a
quantity of fine fillers; the core element shall be comprised of filler and aggregates bound by
a resin matrix. The same resin, applied to the whole structural wall element in a single
application, shall be employed in both the reinforcing and core layers.
If an additional application of material is required for ‘Type I’ linings to pass the shear bond
strength requirements of clause 2.8, it shall consist of an inert material uniformly distributed
over the external surface and bonded using a suitable compatible resin.
If a non-slip invert coating is applied to the resin rich liner it shall be bonded to the cured
lining unit using a suitable compatible resin.
NOTE Non slip inserts should be specified with care as they might compromise the durability
or performance of the lining unit.
At the edges and ends of all lining segments and sections the structural wall shall be sealed
with a suitable compatible epoxy resin (with suitable hardening system). The resin shall be
pigmented black to ensure that a visual check can be used to determine full resin coverage.
As per WIS 4-34-02, Appendix H, this requirement enables lining materials to be suitably
marked with the “4-34-02” nomenclature.
As part of the quality assurance procedures the manufacturer shall keep records of the
following against the individual serial numbers of output product:
• raw material batch details, including source, acceptance test records, purchase dates
and shelf-life at time of use;
• computerised mixing records;
• negative mould pressure at commencement of infusion;
• maximum pressure during the manufacturing process; and,
• confirmation of resin draw for each injection.
NOTE Some rectification or repair is permitted under WIS 4-34-02, (See 10.7 and Table
Appendix G of that Specification).
2.6. DIMENSIONS
2.6.1 Section length
Lining sections shall be manufactured to within a tolerance of ±10mm of the nominal overall
or effective lengths specified by or agreed with the purchaser provided that the sum of the
lining section required.
A pair of segments intended to fit together to form a lining section shall not differ in effective
length by more than 3mm.
b.) Segments
The tolerance on the width between the longitudinal joints and the depth from the unit axis to
the crown or invert of the lining shall be 1% or ± 5mm (whichever is the lesser) of the
nominal value specified by or agreed with the purchaser.
2.6.4 Out-of-Squareness
c.) Out-of-straightness
The out-of-straightness of a unit shall be no more than the lesser of 0.3 % or 5mm of its
effective length.
2.7. JOINTS
a.) Longitudinal joints Type I (where used)
Longitudinal joints applied within a ‘Type I’ composite system shall be constructed and
sealed so as to present the inclusion of grout during liner installation. The jointing system
shall also be designed with the grouting system to provide sufficient rigidity to ensure that
the deflection to span ratio experienced during the placement of grout is less than 3% as per
the serviceability requirements of the SRM.
The joint shall be a lap type joints reinforced with pre-formed strips (which shall conform to
the shape of the lining body), manufactured from E-glass reinforcement and a compatible
epoxy lining system, and bonded to the body of the lining units. The lining units shall be
designed so that the reinforcing strips sit flush with the inside body of the lining unit and do
not protrude nor extend beyond the inner surface of the lining body.
The joints shall be sealed with a fail-safe sealing process whereby a ‘sealing gap’ is formed
through the provision of a longitudinal channel created at connecting edges of the joints;
along the entire length of the longitudinal joint-section. The sealing gap shall be filled only
after the provision, bonding and curing (to the extent of 90% of full peel strength determined
in accordance with the resin suppliers guidelines) of the reinforcing strips. The sealing gap
shall be filled with a flexible 1-part polyurethane resin system, resistant to the sewer
environment for which they are intended. The sealing gap shall be injected from a single
point with weep-holes provided at the extremities of the longitudinal joint to provide visual
confirmation that the sealing gap is fully filled. Vacuum points may be provided, through the
use of an air ejector and vacuum cup system, at the weep points to assist in the sealing
process if required.
Joint compliance shall be demonstrated by the testing of off-cuts of the installed lining
system. Joint sections shall be subjected to testing, in accordance with ASTM D790-00 or
BS 2782-10:Method 1005:1977, EN 63:1977, to determine the flexural properties of the joint.
The bending moment resistance of the joint and equivalent stiffness (considered against the
thickness of the lining wall and not against the thickness of the joint section for calculation
purposes), shall be in excess of that required under the design of the lining system.
Compounds
Rigid setting or flexible compounds used to caulk or seal the gap between lining units shall
be resistant to the sewer environment for which they are intended, and shall be suitable for
installation within a confined space taking safety aspects into consideration.
The lining shall meet the minimum requirements of either the lesser of the requirements of
WIS 4-34-02, or those stipulated under the system design, given in Figure 2.1 – Section
through nominally straight unit (Diagrammatic Only) when tested in accordance with those
clauses indicated. These parameters will be used for the structural design of the lining
system.
WIS 4-34-02
Property Minimum requirements Clause
covering test
Short term flexural As agreed with purchaser and not less than 9.2
(bending) modulus* 5,000 Nmm-2
Long term flexural As agreed with purchaser and not less than 9.3
(bending) modulus* 2,500 Nmm-2
Long term permissible Greater than or equal to 0.5% where a test 9.4
flexural (bending) strain* fluid of water is used or greater than or
equal to 0.3% where a test fluid of acid is
used
Long term tensile As agreed with purchaser but not less than 9.5
strength* 12.0 Nmm-2
The lining unit shall meet the requirements of Table 1.8.1 - Lining Performance
Requirements when tested in the appropriate manner as follows:
The short term flexural modulus shall be determined in accordance with the procedures
described in ASTM D790-00 or BS 2782-10:Method 1005:1977, EN 63:1977 from coupons
cut from the hoop (bending) direction and having a radius of curvature greater than 250mm
(near the springings) and using a testing speed of 10 mm/min.
NOTE when comparing lining units of a particular size but of different moduli and thickness,
the value of E, time’s t can be a useful guide to relative stiffness.
Determine the long-term flexural modulus, (which is equal to the creep modulus at 50 years)
in accordance with the requirements of WIS 4-34-02 Appendix C using coupons cut from the
hoop direction and having a radius of curvature greater than 250mm.
The lining system shall have demonstrated chemical corrosion resistance, as required by the
control test provisions of ASTM D3262-04, tested in accordance with the procedures or
ASTM D3681.
The lining materials shall achieve the minimum beam strength requirements of ASTM
D3262-04. For testing and calculation purposes, in the case of non-circular linings, the
maximum dimension, either width or height, shall be taken as an equivalent diameter for the
purposes of ASTM D3262-04 Table 7.
Tensile testing of the SABAS laminate presents specific problems due to the tensile strength
of the material on what are predominately thick laminates (t>10 mm). As noted in the SABAS
design manual, and from experience, it has been found that in normal sewer applications the
design is limited by the shear bond strength and not tensile strength of the liner.
Notwithstanding this, the long-term tensile strength shall be determined in accordance with
the methodologies of prEN 13121-3:2001, whereby:
Each layer of the composite, comprising the two outer GRP skins and inner core, shall be
analysed to determine their tensile strength. No contribution to this property should be
considered from the surface and barrier layers.
The design factor, K, shall be determined in accordance with clause 7.8.4 of pr EN 13121-
3:2001 as follows:
K = 2 x A1 x A2 x A3 x A4 x A5
Where, the factors of safety for the GRP liner design are based upon the methodology
prescribed prEN 13121-3:2001, clause 7.8.4.1. Under this arrangement the following factors
are to be used:
A1 Effect of manufacturing and quality control level, a value of 1 shall be taken when
the maximum allowable load is determined by testing actual samples of the
individual layers within the structural liner.
A3 = 1 + 0.4[(TD-20)/(HDT-40)]
A4 The derivation of partial design factor of 1 relating to the none dynamic nature of
the loading. For liners with a depth of cover of less than 0.5m this factor will
require further investigation.
A5 The derivation of partial design factor of 1.75 based upon the data provided in
Figure 7.8.4.5 for the conservative laminate construction assumed.
Therefore,
K = 2 x 1 x 1.1 x A3 x 1 x 1.75
As per Table 3 of prEN 13121-3:2001, the tensile strength contribution from the GRP
structural wall skins, TSs, shall be (confirmed by testing to derive partial design factor A1):
Therefore,
TSs = 500 x 60 x 0.9 Nmm-2 per kg/m2
The core component tensile strength contribution, TSc, shall be calculated in accordance with
the following formula:
TS = K x (TSs.mr+TSc)/t Nmm-2
Where, t = lining wall thickness excluding the surface and barrier layers
mr = weight of reinforcing per m2.
The lining unit shall be tested in accordance with the method described in WIS 4-34-02
Appendix D and shall attain the minimum requirement given in Table 1.8.1 - Lining
Performance Requirements.
A sample panel having a rough-backing representative of those tested shall be retained for
quality control comparisons.
A minimum of five samples from the full design wall thickness of each lining test unit
(excluding any rough backing or non slip coating) shall be fully analysed in accordance with
Appendix E of WIS 4-34-02 and the results declared. The values shall form the control
values for quality control purposes.
The required sampling frequency for quality control tests is given in WIS 4-34-02 Appendix
F. Where destructive tests are specified the remaining useful portion of a complying unit
(trimmed square) may be offered for sale, appropriately marked "undersize".
2.10.2 Dimensions
The overall length, effective length, cross section, out-of-squareness and out-of-straightness
of each test sample, where specified, shall be determined using a method of measurement
accurate to the nearest millimetre and shall comply with the requirements of WIS 4-34-02
clause 2.6.
Wall thickness and resin rich liner thickness shall be determined at a minimum of five
locations in each test sample using a method of measurement accurate to the nearest 0.l
mm, by measuring cut surfaces through the lining wall. The cut surfaces shall be smoothed
sufficiently for the different layers to be delineated. The resin rich liner thickness shall be
measured using a suitable optical (magnifying) technique. Each measurement shall comply
with the requirements of clause 2.6. Generally the locations of cores shall include:
NOTE Where the process does not produce distinct layer boundaries a relaxation in
precision will be considered.
The surfaces shall not be tacky to the touch. Each test specimen shall be tested in
accordance with the method described in ASTM2583 or BS 2782-10:Method 1001:1977, EN
59:1977, at a minimum of five points, away from the invert, and shall have a hardness not
less than the minimum declared by the manufacturer at the time of confirmation of the order,
for the resin system used.
In the absence of a suitable objective test method each test unit shall be compared visually
with a panel retained from the type tests. If it is equivalent in respect of particle shape, size
and surface distribution (or other bonding key) it shall be deemed to have adequate shear
bond strength. If it differs appreciably it shall be rejected.
Samples shall be tested by the method prescribed above shall comply with the requirements
of Table 1.8.1 - Lining Performance Requirements.
When tested by the method prescribed in 2.9.7 the disposition of the laminates or zones and
the constituents within them shall correspond to those of the type tested liners. The
percentage by mass of the constituents and the masses of glass per unit surface area shall
not deviate from the declared control values by more than ± 10% (of each numerical value).
2.10.7 Appearance
The internal and external surfaces of each lining unit shall be examined visually for freedom
from defects. Where practicable this shall occur prior to application of any rough backing or
non-slip surface coating. Types of defect and final allowable limits are given in WIS 4-34-02,
Table 2, Appendix G.
Where lining units are intended for use in a septic or aggressive sewer environment, where
a non slip invert is applied or where the lining is intended for use in particular environments
or with high temperature effluents, the lining system shall have demonstrated chemical
corrosion resistance, as required by the control test provisions of ASTM D3262-04, tested in
accordance with the procedures or ASTM D3681.
Unless otherwise required by this specification the test measurements shall be conducted at
a temperature of 15 ± 10°C.
For type testing in air (or in any cases of disagreement) specimens shall be kept in air 15
± 10°C for not less than 88 hours prior to testing.
For quality control testing specimens shall be kept in air at 15 ± 10°C for not less than 12
hours after they are considered to be cured.
NOTE The preferred temperature for conditioning and testing plastics materials is 23 ± 2°C.
GRP Liners shall be manufactured in a closed mould injection system to ensure the
production of high quality components and repeatability of physical properties.
All structural layers of the GRP liner shall be produced in a single-injection process whereby
structural core elements and reinforcing layers are formed in a singular resin infusion step.
An injection of a resinous polymer mortar mixture, into a cavity created between dry
reinforcing fabric layers, shall form the structural core element. Resin shall be drawn from
the polymer mortar mixture into the dry reinforcing layers. The directionally biased
reinforcement is used, care shall be taken to ensure that the high strength direction is
correctly aligned to give the designed balance of hoop and longitudinal strength The use of a
single resin system providing both the polymer matrix for the polymer mortar core and the
polymer matrix within the fibre reinforced skins shall be required to ensure that maximum
shear strength and compatibility is achieved between the composite layers.
Resin system and polymer mortar mixing shall be controlled by automated batching plant.
Hand application of corrosion protective layers shall be carried out strictly in accordance with
the provisions of EN 13121-2:2003.
All raw materials shall be tested at a frequency sufficient to ensure consistency and
compliance with this specification. The manufacturer shall adequately supervise all stages of
production and keep records of the raw material batches used and products made each
work shift or day. Manufacture shall be under environmental conditions compatible with
producing satisfactory linings and raw materials shall be stored and used in compliance with
the recommendations of their manufacturers.
Reinforcement materials shall be stored in dry conditions. The lining manufacturer shall be
familiar with the changes in viscosity, gel times, etc., which may occur during storage of the
resin, and make appropriate allowances in the lining manufacturing process. Resin stored in
original unopened containers shall not be used after the resin manufacturer's stated limiting
date in accordance with BS 3532: 1990.
The guidance of the resin manufacturer shall be sought on the useful life of resin delivered
by tanker. Tanks used for bulk storage of polyester resin must be inspected regularly and
checked for contaminants Materials and temperatures in the working environment shall not
be less than 15°C. All laminating work shall be discontinued if the air temperature falls below
15°C or if the dew point is reached (condensation occurs), whichever is the higher.
NOTE A relaxation to 10°C (or the dew point) may be permitted if final cure is effected application of heat.
2.12.2 Inspection
In addition to the manufacturer's own inspection and supervision, the purchaser or his
appointed inspecting authority shall have access at all reasonable times to those parts of the
manufacturer's works purchaser and to all relevant test records.
2.12.3 Certification
The manufacturer shall, on request, furnish the purchaser or purchaser's representative, with
copies of a signed certificate for each size and classification of lining units stating that the
construction and testing of lining units supplied comply with the requirements of this
specification and giving details of minimum performance parameters agreed with the
purchaser.
If required by the purchaser, the quality control test, results or a suitable summary shall be
provided with the certificate. A typical certificate is shown in Appendix H of WIS 4-34-02.
2.13. MARKING
All lining units shall be indelibly marked at each end on the inside face. No method of
marking shall prejudice the performance of the lining in service. The marking shall give the
following information:
b.) the number WIS 4-34-02. The marking of the number 4-34-02 on products produced to
this specification may only be applied by manufacturers covered by a third party
certification scheme acceptable to WRc,
c.) Identification of the shift, productions line and date of manufacture. Coding of this
information is permitted provided that the meaning of the code is available on request,
d.) the words "GRP TYPE IC SEWER LINING" or "GRP TYPE IIC SEWER LINING", as
appropriate.
Lining units shall be handled, stored and transported in such a way as to prevent damage
before receipt by the purchaser.
2.15. REFERENCES
This specification makes reference to the latest edition of the following publications (except
where otherwise indicated), including all addenda and revisions: Sewerage Rehabilitation
Manual published by the Water Research Centre.
ASTM C566-97 Standard Test Method for Total Evaporable Moisture Content of
Aggregate by Drying
ASTM D2690-98 Standard Test Method for Isophthalic Acid in Alkyd and Polyester
Resins
ASTM Standard Test Methods for Hydroxyl Groups Using Acetic Anhydride
E222-00(2005)e1 Acetylation
ASTM D790-00 Standard Test Methods for Flexural Properties of Unreinforced and
Reinforced Plastics and Electrical Insulating Materials