Dep-34.17.10.30-Blast Resilient and Blast Resistant Control Buildings
Dep-34.17.10.30-Blast Resilient and Blast Resistant Control Buildings
DEP 34.17.10.30-Gen.
September 2002
(DEP Circulars 27/07 and 62/08 have been incorporated)
This document is restricted. Neither the whole nor any part of this document may be disclosed to any third party without the prior written consent of Shell Global
Solutions International B.V. and Shell International Exploration and Production B.V., The Netherlands. The copyright of this document is vested in these companies. All
rights reserved. Neither the whole nor any part of this document may be reproduced, stored in any retrieval system or transmitted in any form or by any means
(electronic, mechanical, reprographic, recording or otherwise) without the prior written consent of the copyright owners.
DEP 34.17.10.30-Gen.
September 2002
Page 2
PREFACE
DEPs (Design and Engineering Practice) publications reflect the views, at the time of publication, of:
Shell Global Solutions International B.V. (Shell GSI)
and
Shell International Exploration and Production B.V. (SIEP)
and
Shell International Chemicals B.V. (SIC)
and
other Service Companies.
They are based on the experience acquired during their involvement with the design, construction, operation and
maintenance of processing units and facilities, and they are supplemented with the experience of Group Operating
companies. Where appropriate they are based on, or reference is made to, international, regional, national and industry
standards.
The objective is to set the recommended standard for good design and engineering practice applied by Group
companies operating an oil refinery, gas handling installation, chemical plant, oil and gas production facility, or any other
such facility, and thereby to achieve maximum technical and economic benefit from standardization.
The information set forth in these publications is provided to users for their consideration and decision to implement.
This is of particular importance where DEPs may not cover every requirement or diversity of condition at each locality.
The system of DEPs is expected to be sufficiently flexible to allow individual operating companies to adapt the
information set forth in DEPs to their own environment and requirements.
When Contractors or Manufacturers/Suppliers use DEPs they shall be solely responsible for the quality of work and the
attainment of the required design and engineering standards. In particular, for those requirements not specifically
covered, the Principal will expect them to follow those design and engineering practices which will achieve the same
level of integrity as reflected in the DEPs. If in doubt, the Contractor or Manufacturer/Supplier shall, without detracting
from his own responsibility, consult the Principal or its technical advisor.
The right to use DEPs is granted by Shell GSI, SIEP or SIC, in most cases under Service Agreements primarily with
companies of the Royal Dutch/Shell Group and other companies receiving technical advice and services from Shell GSI,
SIEP, SIC or another Group Service Company. Consequently, three categories of users of DEPs can be distinguished:
1) Operating companies having a Service Agreement with Shell GSI, SIEP, SIC or other Service Company. The
use of DEPs by these operating companies is subject in all respects to the terms and conditions of the relevant
Service Agreement.
2) Other parties who are authorized to use DEPs subject to appropriate contractual arrangements (whether as part
of a Service Agreement or otherwise).
3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2)
which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said
users comply with the relevant standards.
Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI, SIEP
and SIC disclaim any liability of whatsoever nature for any damage (including injury or death) suffered by any company
or person whomsoever as a result of or in connection with the use, application or implementation of any DEP,
combination of DEPs or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI,
SIEP or other Service Company. The benefit of this disclaimer shall inure in all respects to Shell GSI, SIEP, SIC and/or
any company affiliated to these companies that may issue DEPs or require the use of DEPs.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall
not, without the prior written consent of Shell GSI and SIEP, be disclosed by users to any company or person
whomsoever and the DEPs shall be used exclusively for the purpose for which they have been provided to the user.
They shall be returned after use, including any copies which shall only be made by users with the express prior written
consent of Shell GSI, SIEP or SIC. The copyright of DEPs vests in Shell GSI and SIEP. Users shall arrange for DEPs to
be held in safe custody and Shell GSI, SIEP or SIC may at any time require information satisfactory to them in order to
ascertain how users implement this requirement.
All administrative queries should be directed to the DEP Administrator in Shell GSI.
DEP 34.17.10.30-Gen.
September 2002
Page 3
TABLE OF CONTENTS
1. INTRODUCTION ........................................................................................................5
1.1 SCOPE........................................................................................................................5
1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS .........5
1.3 DEFINITIONS .............................................................................................................5
1.4 ABBREVIATIONS .......................................................................................................7
1.5 CROSS-REFERENCES .............................................................................................7
1.6 SUMMARY OF REVISIONS FROM PREVIOUS EDITION........................................8
2. LOCATION AND BLAST LOAD DESIGN CONSIDERATIONS CONTROL
BUILDING/FAR ..........................................................................................................9
2.1 LOCATION CONSIDERATIONS ................................................................................9
2.2 BLAST LOAD DESIGN CONSIDERATIONS AND INFORMATION ..........................9
3. GENERAL DESIGN CONSIDERATIONS................................................................11
3.1 SIZE OF THE CONTROL BUILDING/FAR...............................................................11
3.2 STRENGTH OF BUILDINGS....................................................................................11
3.3 NOISE LEVELS ........................................................................................................11
3.4 VIBRATION LEVELS FOR THE COMPUTER ROOM .............................................12
3.5 PLANNING OF ACTIVITIES .....................................................................................12
4. LAY-OUT OF THE BUILDINGS ...............................................................................13
4.1 LAY-OUT OF THE CONTROL BUILDING ...............................................................13
4.2 LAY-OUT OF THE FAR ............................................................................................15
5. DETAILED DESIGN CONSIDERATIONS FOR CONTROL BUILDINGS AND
FARs.........................................................................................................................17
5.1 GENERAL .................................................................................................................17
5.2 BASIC DESIGN REQUIREMENTS ..........................................................................18
5.3 BASIS FOR CALCULATION.....................................................................................20
5.4 MATERIAL PROPERTIES........................................................................................27
5.5 STRUCTURAL DESIGN ...........................................................................................30
5.6 ANCILLARY AND ARCHITECTURAL ITEMS ..........................................................37
6. HEATING, VENTILATING AND AIR CONDITIONING ............................................44
7. ELECTRICAL INSTALLATION................................................................................44
7.1 GENERAL .................................................................................................................44
7.2 SOCKET OUTLETS..................................................................................................44
7.3 INSTRUMENT ELECTRICITY SUPPLY...................................................................44
8. TELECOMMUNICATIONS .......................................................................................44
9. FIRE-FIGHTING FACILITIES/FIRE PROTECTION/FIRE AND GAS
DETECTION .............................................................................................................45
9.1 GENERAL .................................................................................................................45
9.2 FIRE EXTINGUISHERS ...........................................................................................45
9.3 FIRE AND GAS DETECTION...................................................................................45
9.4 FIRE PROTECTION .................................................................................................45
10. REFERENCES .........................................................................................................47
11. BIBLIOGRAPHY ......................................................................................................49
APPENDICES
APPENDIX 1 TYPICAL LOCATION OF CONTROL BUILDING ...........................................50
APPENDIX 2 TYPICAL LAY-OUT OF CONTROL BUILDING ..............................................51
APPENDIX 3 TYPICAL CROSS SECTIONS OF CONTROL BUILDING..............................52
APPENDIX 4 BIRD'S EYE VIEW OF A CONTROL BUILDING ............................................53
DEP 34.17.10.30-Gen.
September 2002
Page 4
1. INTRODUCTION
1.1 SCOPE
This DEP specifies requirements and gives recommendations for the design, siting and
construction of new control buildings and field auxiliary rooms (FARs) in order to minimise
the damage in the event of an explosion of a vapour cloud or fire, caused by equipment
failure or due to incorrect operation of a plant.
It is a revision of the previous publication of the same number, titled "Reinforced Control
Buildings/Field Auxiliary Rooms", dated January 1990.
This DEP provides additional requirements for these buildings, over and above the general
requirements for buildings as stated in DEP 34.17.00.32-Gen.
This DEP is intended for use by civil engineers and/or architects involved in the design and
engineering of new control buildings and FARs in onshore oil, gas and chemical production
facilities. It is not applicable to offshore facilities.
This DEP may also be used for other buildings subject to explosion and/or fire.
For control buildings, it is important that sufficient protection for operators and electronic
equipment is provided so that in the event of a calamity, the building may remain functional
and emergency actions can be taken to minimise the spread of danger and secondary
damage.
For FARs, it is only essential to protect the electronic equipment as such. These buildings
are normally unmanned.
1.3 DEFINITIONS
Peak Side-on Over-Pressure - Initial peak pressure rise, above ambient, produced by a
shock wave or a pressure wave as felt by a flat surface orientated parallel to the direction of
wave propagation.
Plastic Region - The deformation range from ultimate capacity up to failure of the element.
Positive Phase - The portion of the pressure time history where the pressure is above
ambient pressure.
Pressure Wave - A blast wave that produces a gradual rise in pressure.
Reflected Over-Pressure - The rise in pressure produced by a shock wave or a pressure
wave as felt by a flat surface oriented perpendicular to the direction of wave propagation.
Resistance-Deflection Function - The value of the stress in a structural element as the
deformation is increased from zero through the elastic range, the elastic-plastic range,
ultimate capacity, and finally to failure of the element.
Safety Glass - Laminated glass panes, consisting of two layers of normal glass (3 mm
thick), with an inner layer of polyvinyl butyral (1.9 mm thick).
Shock Wave - A blast wave that produced a near instantaneous rise in pressure.
Sideways - The lateral movement of a structure due to vertical or horizontal loads.
Strain Energy - The energy stored within a structural element deformed due to the
application of loads. The value of strain energy is the area under the resistance-deflection
function.
Strain Hardening - The observed increase in strength as a material is deformed well into
the plastic range.
Strain Rate - The speed at which a load is applied to material. The higher the strain rate,
the higher the observed material strength.
Strength Increase Factor - The ratio of actual to nominal strength of a material. This factor
takes into account conservatism in the manufacturing process.
Support Rotation - A measure of the blast absorbing capacity of a structural element. This
is the same as hinge rotation except that the angle is computed at the member’s support
location.
Ultimate Capacity - The load applied to a structural element as the final plastic hinge, or
collapse mechanism, is formed.
Ultimate Strength - A method of design in which structural members are proportioned by
total section capacities rather than by extreme fibre allowable stresses.
Amended per
Circular 62/08
Very toxic (substances) - substances that are very hazardous for the environment or
human health, as specified in DEP 01.00.01.30-Gen. (which also identifies "toxic"
substances by reference to chemical substances databases).
1.4 ABBREVIATIONS
DIF - Dynamic Increase Factor
MDOF - Multi Degree Of Freedom
SDOF - Single Degree Of Freedom
SIF - Strength Increase Factor
1.5 CROSS-REFERENCES
Where cross-references to other parts of the DEP are made, the referenced section
number is shown in brackets. Other documents referenced by this DEP are listed in (10).
DEP 34.17.10.30-Gen.
September 2002
Page 8
In the chapters hereof, detailed information and requirements shall be given, but the
following common requirements apply to both the control building and the FAR (and if
applicable to other buildings) and shall be taken into consideration:
1. For blast loading (peak side-on over-pressure) < 5 kPa or an impulse < 200 kPa-ms,
no additional design requirements for resilient or blast resistance are required.
Laminated safety glass shall be used.
2. For blast loading (peak side-on over-pressure) between 5 kPa and 20 kPa (estimated
duration between 50 ms and 150 ms), resilience in the structure and structure
components shall be provided. Laminated safety glass shall be used and the pane
area shall be < 1 m2. Blast resistant doors shall be used.
3. For blast loading (peak side-on over-pressure) between 20 kPa and 45 kPa (estimated
duration between 50 ms and 150 ms), enhanced resilience in the structure and
structure components shall be provided. Laminated safety glass shall be used and the
pane area shall be < 1 m2. Enhanced blast resistant doors shall be used.
DEP 34.17.10.30-Gen.
September 2002
Page 10
4. For blast loading (peak side-on over-pressure) between 45 kPa and 65 kPa (estimated
duration between 50 ms and 150 ms), blast resistance shall be required for structure
and structure components. Laminated safety glass and catch bars shall be used and
the pane area shall be < 0.25 m2. Enhanced blast resistant doors shall be used.
5. For blast loading (peak side-on over-pressure) > 65 kPa, the Principal shall be
consulted.
6. If subject to potential fragment impacts (caused by explosions) and at a distance less
than 200 m, the outer walls and roof shall be made of reinforced concrete.
7. Where there are prevailing winds, the building shall be located upwind of the prevailing
wind direction. Special attention shall be paid to the distance between bitumen blowing
facilities and the building to avoid any fouling due to spraying bitumen.
8. The building shall not be located on a lower level than surrounding plants and tank
farms. It shall be located away from vibrating or noise-producing equipment, e.g.,
controlled steam vents, heavy-duty pumps and compressors; see
DEP 34.17.00.32-Gen.
9. The building shall preferably be located close to centres of major operational
importance, and where appropriate, centrally with regard to future extensions. If future
extensions are possible, space shall be reserved for possible extension of the building
itself. The building should be located close to activities requiring regular local
supervision.
10. For those plants where operating personnel also act as fire-fighting crew, allocated
parking spots next to the control building shall be provided.
DEP 34.17.10.30-Gen.
September 2002
Page 11
When the noise level generated in the computer room is high, double-glazed (sealed)
windows shall be used, to attenuate the transmission of noise to other areas in the building,
whilst still allowing visual communication with the control room.
4.1.1 General
The control building will normally comprise:
- the control room;
- the computer room;
- a training/conference room;
- a supervisory area adjacent to the control room;
- an auxiliary instrument and computer room, if required;
- the electrical equipment and battery room;
- the heating, ventilating and air-conditioning machine room;
- the first-aid compartment (provision of a separate room for first-aid depends on other
first-aid facilities, e.g. medical centre/staffed during office hours/ permanent);
- the plant laboratory, if necessary;
- the offices and social amenities (mess room, wash, locker and toilet rooms - it is not
always necessary to provide locker and washing facilities as part of the control building);
- air sluice(s).
NOTES: 1) To minimise the number of people near potential hazards, and to reduce the size of control
buildings, a general site laboratory shall not be part of the control building. The general site
laboratory shall be located, if possible, near the administration area and in a non-major hazard
area. This laboratory can be built in accordance with DEP 34.17.00.32-Gen.
2) Provision of office space in the control building should be determined per project, taking into
account the local organisation (including future plans) and local needs. Office space can vary,
depending on whether only shift personnel (supervisors) or all operations personnel (day
assistants, plant manager, engineering and technology personnel involved with plant operation on
at least a daily basis) are to be accommodated.
3) If sufficient space is not available, a basement may be designed. All utilities and E/I equipment
should be located in the basement.
4.1.8 Interconnections
The shift supervisor shall have a view from his office into the control room and equally the
operators shall be able to see the control room from the mess room, thus affording quick
visual communication, whenever necessary.
The plant laboratory shall be visible from the control room through windows, to allow visual
communication between the operators and laboratory personnel.
DEP 34.17.10.30-Gen.
September 2002
Page 15
There shall be no direct connection between the control room (and the basement if
provided) and the other rooms in the building by direct doors, by slots in walls, or via the
drainage system with exception of the following rooms:
- office (for shift supervisor);
- mess room;
- computer auxiliary room (computer office).
All other rooms shall be connected with the control room and its basement via air locks or
corridors (with at least 2 doors to pass).
Each room in which people work, and where there is a chance of fire or gas accumulation,
shall have two exits, located so that the chance of being trapped is minimal. The width of
doors and passages shall comply with the applicable regulations, permitting free and easy
exit in emergencies, as well as easy transportation of equipment.
The plant laboratory, where provided, shall have no direct communication with the rest of
the building through doors, movable windows or hatches, to prevent gases from entering
the control room. The laboratory shall have two doors: one entrance door to a corridor or air
lock of the control building, and one emergency exit door direct to the outside.
Gas cylinders that may be required for the laboratory shall be kept outside the building.
4.2.1 General
The building will normally comprise:
- the process control and safeguarding room;
- the electrical equipment and battery room (if necessary);
- the heating, ventilating and air-conditioning machine room (if necessary);
- the room for Uninterrupted Power Supply (UPS) equipment (if necessary).
NOTES : 1) The building shall normally be unmanned and therefore no offices shall be designed to
accommodate personnel.
2) If the FAR is also used to provide facilities for field operators (e.g. a remote control room) a central
access by means of an air lock shall be provided to maintain the required overpressure inside the
building.
The entrance to the air-conditioning machine room shall be located in such a way that the
air-conditioning maintenance personnel can reach the HVAC machine room without having
to pass through the instrument or electrical areas.
DEP 34.17.10.30-Gen.
September 2002
Page 17
5.1 GENERAL
The civil engineering of the buildings shall be in accordance with the requirements of this
DEP, DEP 34.17.00.32-Gen. and local building regulations. Unless otherwise specified
and/or agreed by the Principal, the more stringent requirements shall be followed.
A general arrangement drawing showing the internal layout of the building shall be
prepared in close consultation with the Principal.
A recognised (registered) architect or engineer shall be engaged to design and co-ordinate
the buildings and their installations. The choice of architect requires prior approval of the
Principal.
DEP 34.17.10.30-Gen.
September 2002
Page 18
5.2.4 Roof
The roof shall be well insulated, but shall not be covered with gravel or loose concrete tiles
as these will fly in the event of an explosion. On the roof, only the air intake and exhaust
facilities (penthouse) of maximum height 1.8 m, fresh air intake stack, aerials, TV cameras
and similar equipment are permitted.
The related response criteria for ductility ratio and rotation are given in (5.5.4). For the
design of Control Buildings and FARs the low response range shall apply. Other ranges
may be used to determine the response range of existing buildings.
DEP 34.17.10.30-Gen.
September 2002
Page 19
For the pressure wave, an idealised equivalent pressure load may be used, as indicated
below.
Nomenclature:
P = Pressure in kPa
Pso = Peak incident over-pressure in kPa
Amended per
Circular 27/07
t = time in s or ms
td = positive phase duration in s or ms
tr = rise time in s or ms
Table of equivalent load coefficient (Ce), derived from TM 5-1300; see (11).
Lw/L 0.5 0.6 0.7 0.8 0.9 1 2 3 4 5 6 7 8 9 10
Ce 0.23 0.28 0.32 0.4 0.42 0.45 0.6 0.7 0.8 0.95 1 1 1 1 1
Note 1. Lw is the blast wave length and is U x td. L is the length of the structural element, in the direction of the
travelling blast wave.
Note 2. If the blast wave is travelling perpendicular to the span, then L shall be equal to a nominal unit width of the
structural element.
Note 3. An element of e.g. 1 m may be taken or in case over-pressure is needed, the entire width of the wall shall
be taken into account. The value of Ce then becomes less than one and the value of Pa may be reduced.
The rise time will become significant.
These effects shall be quantified from the time history dynamic analysis of the structural
components by performing a dynamic analysis method. For simple cases the “Single
Degree Of Freedom” (SDOF) may be used, but normally computer software based on the
“Finite Element Analysis Methods”, e.g., STAAD III, shall be used.
DIF
Stress Type Reinforcing Bars Concrete Masonry
(Fdy/Fy) (Fdu/Fu) (f’dc/f’c) (f’dm/f’m)
Note 1: Live loads which will be normally blown away by a blast wave and live loads, e.g.,
personnel and furniture which will not increase the inertia of a supported member,
shall not be included in the mass calculation. This means that in most cases the
reduction factor will be zero.
2. The blast load combination may consider either the direct loads or their effects. In
combining blast load effects with those from static dead and live loads, the time
dependence of the blast loading shall be taken into consideration.
3. Wind and seismic loads shall not be combined with blast loading.
4. Rebound effects shall be computed and combined with the effects of negative phase
blast loads, if any, based on time dependent response.
5.5.4.1 Parameters
Structural members shall be designed based on maximum response (deformation)
consistent with the performance requirements or permissible damage level specified in
(5.2.6). Deformation limits shall be expressed as ductility ratio (µ), support rotation (θ), or
frame sideway, as appropriate.
Response Range(2)
Element Type Low Medium High
µa θ µa θ µa θ
Beams, Girths, Purlins 3 2 10 6 20 12
(1) 1.5 1 2 1.5 3 2
Frame members
Single Sheet Metal Panels 1.75 1.25 3 2 6 4
Open-Web Joists 1 1 2 1.5 4 2
Plates 5 3 10 6 20 12
Notes:
1 Sideways deflection (δ) limits for steel frames: 2. Response parameter:
Low = H/50, (H = story height) µa = Allowable ductility ratio
Notes:
(1) Shear controls when shear resistance is less than 120 % of flexural resistance.
(2) Stirrups are required for support rotations greater than 2 degrees.
(3) Ductility ratio = 0.05 (ρ - ρ’), where ρ and ρ’ are the tension and compression reinforcement ratios,
respectively. Ductility ratio shall be < 10.
5.5.5.1 General
Ultimate strength (Limit State) methods shall be used for designing structural components
for blast resistance. The ultimate strength capacity shall be determined in accordance with
the applicable codes, practices and guides as specified, subject to the following additional
requirements:
1. In-plane and secondary bending stresses shall be accounted for in the design.
2. Interaction of forces in two directions, including biaxial bending, shall be considered.
Information may be obtained from "Design of Blast Resistant Buildings in Petrochemical
Facilities", see (10).
3. Dynamic strength properties shall be used to reflect increased material strength under
rapidly applied loads.
DEP 34.17.10.30-Gen.
September 2002
Page 33
4. Load and resistance factors shall be taken as equal to 1.0 in all blast load combinations.
5. Composite sections may be used for design; however, adequate rebound resistance
shall be provided to ensure satisfactory response under rebound or negative phase
loads.
6. Components shall be adequately laterally braced to prevent premature buckling failure
during the positive and rebound response.
7. Connections shall be designed for 120 % of the member's controlling resistance (flexure
or shear, whichever is lower). Except as noted for reinforced concrete members, the
deformation limits indicated in Tables 6, 7, and 8 are based on flexure controlled
resistance. To use these limits, the member's shear capacity shall be at least 120 % of
the flexural capacity.
8. Design for compression elements, such as load bearing walls and columns, should
consider bending effects including secondary effect* (P-delta effects) and slenderness.
Note *: The secondary effect on shears, axial forces and moments of frame members induced by the vertical loads
acting on the laterally displaced building system.
to centre. It is preferable for the wall and roof thickness to be between the limits of
250 mm and 400 mm in order to facilitate the placing of the required reinforcing bars.
If the dynamic calculation indicates that more reinforcement is required, it shall be
prvided. Strength reductions and reductions of development lengths are not allowed.
Criteria intended to reduce cracking at service load levels shall not be applied to load
combinations which include blast loads.
8. Shear reinforcement shall be applied in beams only and shall be a combination of
stirrups and horizontal side bars. This combination is known as web reinforcement.
The web reinforcement requirements are:
• When the shear stress is less than 1.3 N/mm2, web reinforcement is not required.
• When the shear stress is more than 1.3 N/mm2 but less than 4.5 N/mm2, web
reinforcement will be required for this acting shear stress minus 1.3 N/mm2.
At least 50 % of the bottom main reinforcement shall extend over the face of the support
providing a good anchorage between the supports.
9. In general, special attention shall be paid to ensure continuity and a minimum of local
stress concentration. Adequate lapping of reinforcement is required.
10.Pre-stressed concrete shall not be used, due to its non-ductile behaviour.
4. Oversize washers should be provided for wall panel anchorage screws to prevent failure
due to rebound or negative phase loads.
5. Symmetric, closed sections shall be used wherever possible.
footings and floor grade slabs shall be based on the coefficient of friction determined by
the geotechnical study. The normal force shall be taken as the sum of the dead loads
and the vertical load associated with the ultimate resistance of the roof. Frictional
resistance of floating slabs shall not be used.
3. Where only passive resistance, frictional resistance, vertical piles, or battered piles are
used to support the lateral blast loading, the resistance shall be taken as 80 % of the
ultimate static value. However, if two or more of these resistances are used to support
the lateral blast loads, the lateral capacity shall be limited to 67 % of the combined
ultimate static resistance.
*Note: The following categories shall be used to determine the requirements for blast resistant or resilient doors.
Category I: The door shall be operable after the loading event, and pre-established design criteria for
stress, deflection, and the limitation of permanent deformation shall not be exceeded. This
category shall be specified if the door should be required to withstand repeated blasts or if
entrapment of personnel is of concern and the door is a primary exit to the building.
Category II Non-catastrophic failure is permitted. The door assembly remains in the opening. No major
structural failure occurs in the panel structure, the restraining hardware system, the frame or
the frame anchorage that would prevent the door assembly from providing a barrier to blast
wave propagation. However the door will be rendered inoperable. This category should only
be specified if entrapment of personnel is not a possibility.
Category III Non-catastrophic failure is permitted. The door assembly remains in the opening. No major
structural failure occurs in the panel structure, the restraining hardware system, the frame or
the frame anchorage that would prevent the door assembly from providing a barrier to blast
wave propagation. However the door will be rendered inoperable. This category should only
be specified if entrapment of personnel is not a possibility.
Category IV Outward rebound force and resulting hardware failure is acceptable.
2. In buildings large enough to require more than one exit door according to the
requirements in local building codes, at least two doors shall be designated as exit
doors for the purpose of limiting the damage to these doors when subjected to blast
loads. Designated exit doors shall not be located on the same side of the building.
3. Doors, doorframes, and door hardware shall be designed for the performance criteria
and applied blast loads specified in (Appendix 7).
4. Outward opening doors shall be provided at two sides of the control building for ease of
access to process areas and shall seat against the frame under the positive phase blast
wave. Air locks shall be installed to maintain the required over-pressure inside the
building. All outer doors shall be provided with automatic door closers.
5. Means of escape, including emergency exit(s), shall be provided from at least three
sides of the control building. The emergency exit(s) shall be installed at the rear side of
the building, not facing the process area. If only to be used for emergencies, the exit
door does not need an air lock.
DEP 34.17.10.30-Gen.
September 2002
Page 38
6. No windows shall be provided in the outer doors; only small peepholes shall be provided
to check, in the event of fire, that the area outside the door is safe to permit evacuation
of the building.
7. The outer and inner doors shall have a good seal between door and frame to maintain
the different pressures between the various rooms and the outside of the building.
8. There are no special requirements for blast resistant or resistant inner doors of airlock
systems.
9. Blast door Manufacturers shall provide calculations or test data to verify adequate blast
resistance and door performance for the design load conditions.
10.Manually operated exit doors shall not exceed a maximum opening force of 25 N
(measured at the door handle) or shall meet the requirements of the local building codes
for the maximum opening force. Power-operated doors shall be used for exit doors that
exceed the maximum opening force.
11.Equipment (Double) access doors shall be designed so that instrumentation, computer
equipment and air-conditioning equipment etc. can be transported into the control room
basement and FARs. The size of these equipment doors will depend on the dimensions
of the equipment but they shall be at least 1.8 m x 2.5 m. When not in use, equipment
doors shall be bolted to the steel doorframe and the seal shall be air-tight. If the
doorway is also to be used as a passageway, a single door shall be installed in the
equipment door, and the seal shall be airtight when the door is closed.
5.6.2 Windows
The design of window frames and anchorage shall be included. The following requirements
shall be applied:
5.6.2.7 Elevation
The underside of external windows in the plant laboratory and offices shall be 1 m above
the finished floor level.
5.6.3 Openings
Large openings in the building envelope, such as intake ducts, shall be designed to prevent
entry of excessive blast pressures. The following shall be taken into account:
1. Blast valves, blast attenuators, or other devices shall be used to limit excessive blast
pressure entry into the structure. Test data and calculation shall substantiate
performance of the blast valve or attenuator.
2
2. Blast valves shall be provided for openings greater than 0.1 m in any surface in which
the peak applied pressure is greater than 0.07 MPa. Blast dampers may be used for
these openings if the peak applied pressure is greater than 0.035 MPa.
5.6.4 Penetrations
Wall and roof penetrations in reinforced concrete and masonry shall be sleeved. Sleeves
shall be anchored with a minimum of 2 each M16 diameter with 100 mm long headed
studs.
Penetrations in metal clad structures shall be anchored with substantial framing attached to
structural steel members.
5.6.6.1 To avoid the potential for hazardous debris, large non-structural features such as canopies
and signs on the building exterior shall be minimised. However, small items such as
instruments, fire alarms, lights, strobes and beacons may be mounted on the exterior walls.
5.6.6.2 Roof and wall mounted equipment (e.g. HVAC equipment) should be avoided. If approved
by Principal, such equipment shall be securely anchored and the supporting structural
components shall be specifically designed for actual equipment dynamic loads when
subjected to the blast.
DEP 34.17.10.30-Gen.
September 2002
Page 41
5.6.6.3 Equipment and other items mounted on the exterior surfaces (walls or roof) of the building
shall be designed similar to the structural components if they are to withstand the applied
blast loads. The reactions from such items shall be considered in the design of the
supporting structural components.
5.6.6.4 The stack for fresh air intake on the penthouse shall be designed for wind loading only. The
height of the stack (level of air intake) shall be 12 m above plant level. Blast
valves/dampers shall not be installed in this air intake, but shall be installed in the
reinforced concrete roof floor.
5.6.7.1 Instrumentation or electrical equipment shall not be mounted on the interior face of walls
subjected to blast loads without the written approval of the Principal.
5.6.7.2 All fixed floor supported items, such as lockers, electrical cabinets, racks, etc. shall have a
minimum clearance from exterior walls equal to the maximum calculated lateral blast load
deflection. The maximum deflection shall consider both the overall building sideways plus
any wall component(s) deflection and shall be computed based on the maximum blast
loads defined in (Appendix 7). Supports and anchorage for such equipment shall be
designed to resist a lateral force equal to 20 % of the equipment weight.
5.6.8 Floors
shall ensure that the panels remain in place, even when adjacent panels have been
removed.
5.6.10.2 Ceilings
The aluminium grid ceiling in the control room shall be constructed in such a way that the
panels are secured in position and cannot fall down during an explosion.
This applies also to the lighting fixtures, etc.
DEP 34.17.10.30-Gen.
September 2002
Page 43
The building shall be provided with a system for heating, ventilating and air conditioning, as
specified in DEP 31.76.10.10-Gen.
Certain aspects of particular relevance for the improved safety of the building in the event
of external explosions are described below.
Explosion protection valves, mounted in a concrete box on top of the building (penthouse),
shall protect the air intake and the air exhaust openings. During an explosion the blast-
resistant valves shall close automatically and protect the building against over-pressure or
suction through the ventilation ducting. These valves shall open automatically when the
pressure is back to normal.
Air-cooled condensers shall be located next to the building at grade level and not on top of
the building; see (Appendix 1).
7. ELECTRICAL INSTALLATION
7.1 GENERAL
The electrical installation for power and lighting, etc., shall be in accordance with
DEP 33.64.10.10-Gen. Illumination/lighting shall be designed in such a way as to avoid
refelection/glaring on computer screens.
In addition, the following requirements related to socket outlets and instrument electricity
supply shall apply.
The plant telecommunication (radio, telephone, paging and CCTV) system shall be in
accordance with DEP 32.71.00.10-Gen.
DEP 34.17.10.30-Gen.
September 2002
Page 45
9.1 GENERAL
The fire-fighting systems shall be in accordance with DEP 80.47.10.30-Gen.,
DEP 80.47.10.31-Gen. and the requirements specified below.
9.4.1 General
For explanations of terms used and tests mentioned in this DEP, see BS 476.
Where ventilation or other ducts or piping/cabling pass through roofs, walls or floors, the
surrounding gaps shall be closed air- and water- tight by non-combustible materials and
constructed in such a way as to allow essential thermal movements.
The layout of the building shall be such that the maximum travel distance from any point of
a floor in the building to the nearest exit of that floor is 25 m.
Insulation materials used inside and outside the building shall be e.g. mineral wool blankets
with galvanised wire netting and with no flammable materials attached to them (used in wall
cladding, ceilings, partition walls, etc.). As an exception to this, built-up bituminous roofing
felt, glass fibre based, is allowed but should, where possible, be avoided.
Staircases shall be separated from corridors by automatic closing doors. These doors shall
be smoke-tight.
- floors shall have a smoke and fire resistance period of minimum one hour. Raised floors
(computer floors) shall have a smoke and fire resistance period of half an hour.
NOTE: All penetrations, both inside and outside, shall be well sealed according to the required fire resistance.
10. REFERENCES
SHELL STANDARDS
Index to DEP publications and standard DEP 00.00.05.05-Gen.
specifications
Amended per
Circular 62/08
Definition of temperature, pressure and toxicity levels DEP 01.00.01.30-Gen.
Noise control DEP 31.10.00.31-Gen.
Heating, ventilating and air-conditioning for plant DEP 31.76.10.10-Gen.
buildings
Fire, gas and smoke detection systems DEP 32.30.20.11-Gen
Plant telecommunication DEP 32.71.00.10-Gen.
Electrical engineering guidelines DEP 33.64.10.10-Gen.
Geotechnical and foundation engineering DDD 34.11.00.12-Gen.
Design and engineering of buildings DEP 34.17.00.32-Gen.
Reinforced concrete foundations and structures DEP 34.19.20.31-Gen
Steel structures DEP 34.28.00.31-Gen
Assessment of the fire safety of onshore installations DEP 80.47.10.30-Gen.
Active fire protection systems and equipment for DEP 80.47.10.31-Gen.
onshore facilities
Office Safety of HSE HSE 004: June, 1986
AMERICAN STANDARDS
Design of Blast Resistant Buildings in Petrochemical ASCE
Facilities
Issued by:
American Society of Civil Engineers
1801 Alexander Bell Drive
Reston, VA 20191 USA
BRITISH STANDARDS
Fire tests on building materials and structures -
UK
DUTCH STANDARDS
Method for the Determination of Possible Damage to TNO Green Book
People and Objects Resulting from Releases of
Hazardous Materials (CPR 16E-1992)
Issued by:
Sdu Uitgeverij Plantijstraat
Afdeling Verkoop Arbeidsinspectie, K 2301
Postbus 20014
2500 EA Den Haag The Netherlands
INTERNATIONAL STANDARDS
Electrical Installations of Buildings IEC 60364
Issued by:
International Electrotechnical Commission
3 Rue de Varembé
CH 1211 Geneva 20
Switzerland
NOTE: The DEPs and most referenced external standards are available for Shell users on the SWW (Shell Wide Web) at
address http://sww.shell.com/standards.
DEP 34.17.10.30-Gen.
September 2002
Page 49
11. BIBLIOGRAPHY
Issued by:
Department of the Army, Navy, and Air Force
Washington, DC USA
Issued by:
ICBO Headquarters
5360 Workman Mill Road
Whittier, California 90601-2298
USA
DEP 34.17.10.30-Gen.
September 2002
Page 50
Notes: (1) Blast loads shall be computed at the wall nearest the blast centre.
(2) Roof shall be considered to be loaded by the peak side-on over-pressure.
(3) Depending on the load shape, some of the parameters may not be applicable.
(4) Each load case may see a different reflected wall. Indicate the wall (N,S,E or W) facing the blast for the current
load case. Figure 1 indicates the contour of the building and N,S,E or W facing to the blast source.
(5) Indicate angle of incidence in degrees, measured from the line normal to the reflected wall.
DEP 34.17.10.30-Gen.
September 2002
Page 57
Note: (1) Indicate also the distance from the building to the explosion source or epicentre.
Piling Foundation
Pile description
Item Value Unit
Maximum Horizontal Pile Capacity
Vertical Pile Spring Constant
Horizontal Pile Spring Constant
Other Requirements
! Blast Valves ! Blast Attenuators ! Blast Dampers
! Gas Detection ! Automatic Door Closer ! Other
Special Requirements:
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
Remarks:
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________