Schedule M&E Above Ceiling Building 1 - 2FL - RV14 - Rev02

The document outlines a schedule for renovating the ceiling and mechanical and electrical (M&E) systems above the ceiling on the second floor of a factory in Vietnam from October 2021 to April 2022. Key areas that will undergo work include cleaning room 1, corridor 1A, corridor 2, and cleaning room 3. The schedule details the sequence of inspection, removal of existing partitions and equipment, reinstallation of new M&E systems, and completion of ceiling work for each area over the specified dates while noting that some work will occur on weekends and at night.

Uploaded by

Thuỳ Dung
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
65 views8 pages

Schedule M&E Above Ceiling Building 1 - 2FL - RV14 - Rev02

The document outlines a schedule for renovating the ceiling and mechanical and electrical (M&E) systems above the ceiling on the second floor of a factory in Vietnam from October 2021 to April 2022. Key areas that will undergo work include cleaning room 1, corridor 1A, corridor 2, and cleaning room 3. The schedule details the sequence of inspection, removal of existing partitions and equipment, reinstallation of new M&E systems, and completion of ceiling work for each area over the specified dates while noting that some work will occur on weekends and at night.

Uploaded by

Thuỳ Dung
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

OM DIGITAL SOLUTION VIET NAM FACTORY RENOVATION PROJECT - DETAIL SCHEDULE M&E ABOVE CEILING WORK 2FL

Date 30th July 2021 Vaccinate


2nd time
2021 2021 2021 2022 2022 2022 2022
Duration October November December January February March April
Location 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat

CEILING RENOVATION -2FL


Work saturday, sunday and Night time
Cleaning room 1 2021/11/14
Inspection and hanover Inspection and hanover
Remove PVC partition & Close opening
Re-install M&E equipment Re-install M&E equipment
M&E work under ceiling S h installation S h installation S h installation S h installation Smoke exhaust duct installation
M&E above celing
Remove existing ceiling M-bar
Remove M&E equipment
PVC partition
Install scaffolding

Corridor 1A
Inspection and hanover
Remove PVC partition
Re-install M&E equipment
Painting M-bar ceiling
M&E work under ceiling
Re-install ceiling M-bar
M&E above celing
Remove existing ceiling M-bar
Remove M&E equipment
PVC partition
Install scaffolding

Corridor 2
Inspection and hanover
Remove PVC partition
Re-install M&E equipment
Painting M-bar ceiling
M&E work under ceiling
Re-install ceiling M-bar
M&E above celing
Remove existing ceiling M-bar
Remove M&E equipment
PVC partition
Install scaffolding
Work saturday, sunday and Night time
Cleaning room 3 2021/11/28
Inspection and hanover Inspection and hanover
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
M&E work under ceiling
M&E above celing
M&E work under ceiling
Smoke exhaust duct installation
TET HORIDAY
Remove existing ceiling M-bar
Remove M&E equipment
PVC partition
Install scaffolding

Corridor 1B 2021/10/13
Inspection and hanover Inspection and hanover
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding

Corridor 3 2Corridor 3
0
2
1
Painting M-bar ceiling / Painting M-bar ceiling
Re-install ceiling M-bar 0 Re-install ceiling M-bar
8
Install sprinkler head / Install sprinkler head
Make opening 2 Make opening
0

Work saturday, sunday and Night time


Cleaning room 4
Inspection and hanover Inspection and hanover
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
M&E work under ceiling M&E work under ceiling Smoke exhaust duct installation
M&E above celing
Work saturday, sunday and Night time
Cleaning room 2 2021/12/05
Inspection and hanover Inspection and hanover
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
M&E work under ceiling M&E work under ceiling S h installation S h installation Smoke exhaust duct installation
M&E above celing

Corridor 4A
Touch up painting Touch up painting
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Make opening Make opening
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding

Corridor 4B Corridor 4B 2021/10/15


Inspection and hanover
Remove PVC partition
Re-install M&E equipment
Painting M-bar ceiling
M&E work under ceiling
Re-install ceiling M-bar
M&E above celing
Remove existing ceiling M-bar
Remove M&E equipment
PVC partition
Install scaffolding

Corridor 4C
Inspection and hanover
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding

Page 1 of 8
OM DIGITAL SOLUTION VIET NAM FACTORY RENOVATION PROJECT - DETAIL SCHEDULE M&E ABOVE CEILING WORK 2FL
Date 30th July 2021 Vaccinate
2nd time
2021 2021 2021 2022 2022 2022 2022
Duration October November December January February March April
Location 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Corridor 5
Inspection and hanover Inspection and hanover
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding

Corridor 6A Corridor 6A 2021/12/13 2022/01/03


Inspection and hanover Inspection and hanover
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding 2022/01/26
Corridor 6B Corridor 6B 2022/01/04
Inspection and hanover Inspection and hanover
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding 2022/02/14
Corridor 6C 2021/10/31 2021/03/14
Inspection and hanover Corridor 6C Inspection and hanover
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding

Corridor 7 2 Corridor 7 2021/12/07 2022/01/04


0
Inspection and hanover 2 Inspection and hanover
1
Remove PVC partition / Remove PVC partition
Re-install M&E equipment 0 Re-install M&E equipment
9
Painting M-bar ceiling / Painting M-bar ceiling
M&E work under ceiling 2 M&E work under ceiling
3
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding

Technical Room A
Inspection and hanover Inspection and hanover
Work saturday, sunday , nightime friday
Remove PVC protect Remove PVC protect
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect Remove PVC protect
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect Remove PVC protect
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect Remove PVC protect
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine

2022/01/16

Page 2 of 8
OM DIGITAL SOLUTION VIET NAM FACTORY RENOVATION PROJECT - DETAIL SCHEDULE M&E ABOVE CEILING WORK 2FL
Date 30th July 2021 Vaccinate
2nd time
2021 2021 2021 2022 2022 2022 2022
Duration October November December January February March April
Location 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Technical Room B Technical Room B 2021/12/03 2022/01/16
Inspection and hanover 2021/12/10 2022/01/09 Inspection2022/01/16
and hanover
Work saturday, sunday , nightime friday
Remove PVC protect Remove PVC protect
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect Remove PVC protect
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect Remove PVC protect
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect Remove PVC protect
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect Remove PVC protect
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine

Material warehouse 1 Material warehouse 1 2022/03/20


Inspection and hanover 2022/02/24 Inspection and hanover
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
2022/02/23 2022/04/17
2022/03/25 2022/04/24

Page 3 of 8
OM DIGITAL SOLUTION VIET NAM FACTORY RENOVATION PROJECT - DETAIL SCHEDULE M&E ABOVE CEILING WORK 2FL
Date 30th July 2021 Vaccinate
2nd time
2021 2021 2021 2022 2022 2022 2022
Duration October November December January February March April
Location 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Material warehouse 2 2022/03/25 2022/04/24
Material warehouse 2
Inspection and hanover Inspection and hanover
Wall painting Wall painting
Board installation Board installation
Wall LGS installation Wall install work Wall LGS installation
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
2022/02/25 2022/04/03
Material warehouse 3 Material warehouse 3
Inspection and hanover Inspection and hanover
Work saturday, sunday , nightime friday
Door installation Door installation
Installation of floor flushing Installation of floor flushing
Wall painting Door install work Wall painting
Wall repair Wall repair
Installation of door frame Installation of door frame
Remove PVC protect Remove PVC protect
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect Remove PVC protect
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove PVC protect machine Remove PVC protect machine
Remove scaffolding Remove scaffolding
M&E Work M&E Work
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
2022/02/25 2022/04/17
Air conditioning Room Air conditioning Room
Inspection and hanover Work saturday, sunday , nightime friday Inspection and hanover
Remove PVC protect machine Remove PVC protect machine
Remove scaffolding Remove scaffolding
M&E Work M&E Work
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect machine Remove PVC protect machine
Remove scaffolding Remove scaffolding
M&E Work M&E Work
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove scaffolding Remove scaffolding
M&E Work Remove scaffolding
Install scaffolding M&E Work
PVC protect machine Install scaffolding
Remove PVC protect machine Remove PVC protect machine
Remove scaffolding Remove scaffolding
M&E Work M&E Work
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect machine Remove PVC protect machine
Remove scaffolding Remove scaffolding
M&E Work M&E Work
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect machine Remove PVC protect machine
Remove scaffolding Remove scaffolding
M&E Work M&E Work
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine

Zone S Zone S 2022/02/25 2022/03/20


Inspection and hanover Work saturday, sunday , nightime friday Inspection and hanover
Re-install T-bar and Remove PVC protect Re-install T-bar and Remove PVC protect
M&E Work head sprinkler M&E Work head sprinkler
Remove T-bar ceiling Remove T-bar ceiling
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Re-install T-bar and Remove PVC protect Re-install T-bar and Remove PVC protect
M&E Work above ceiling M&E Work above ceiling
Remove T-bar ceiling Remove T-bar ceiling
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Re-install T-bar and Remove PVC protect Re-install T-bar and Remove PVC protect
M&E Above ceiling M&E Above ceiling
Remove T-bar ceiling Remove T-bar ceiling
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine

Staff Room A Staff Room A 2022/02/25 2022/03/20


Inspection and hanover Inspection and hanover
Work saturday, sunday , nightime friday
Remove scaffolding Remove scaffolding
Re-install existing ceiling T-bar Re-install existing ceiling T-bar
M&E under ceiling M&E under ceiling
Remove existing ceiling T-bar Remove existing ceiling T-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove scaffolding Remove scaffolding
Re-install existing ceiling T-bar 2021/11/02 Re-install existing ceiling T-bar
M&E above celing M&E above celing
Remove existing ceiling T-bar Remove existing ceiling T-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove scaffolding Remove scaffolding
Re-install existing ceiling T-bar Re-install existing ceiling T-bar
2021/1102
M&E above celing M&E above celing
Remove existing ceiling T-bar Remove existing ceiling T-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine

2022/03/25 2022/04/17

Page 4 of 8
OM DIGITAL SOLUTION VIET NAM FACTORY RENOVATION PROJECT - DETAIL SCHEDULE M&E ABOVE CEILING WORK 2FL
Date 30th July 2021 Vaccinate
2nd time
2021 2021 2021 2022 2022 2022 2022
Duration October November December January February March April
Location 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Staff Room B Staff Room B 2022/03/25 2022/04/17
Inspection and hanover Inspection and hanover
Work saturday, sunday , nightime friday
Remove scaffolding Remove scaffolding
Re-install existing ceiling T-bar Re-install existing ceiling T-bar
M&E under ceiling M&E under ceiling
Remove existing ceiling T-bar Remove existing ceiling T-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove scaffolding Remove scaffolding
Re-install existing ceiling T-bar Re-install existing ceiling T-bar
M&E above celing M&E above celing
Remove existing ceiling T-bar Remove existing ceiling T-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove scaffolding Remove scaffolding
Re-install existing ceiling T-bar Re-install existing ceiling T-bar
M&E above celing M&E above celing
Remove existing ceiling T-bar Remove existing ceiling T-bar
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine

2022/03/25 2022/04/10

Page 5 of 8
OM DIGITAL SOLUTION VIET NAM FACTORY RENOVATION PROJECT - DETAIL SCHEDULE M&E ABOVE CEILING WORK 2FL
Date 30th July 2021 Vaccinate
2nd time
2021 2021 2021 2022 2022 2022 2022
Duration October November December January February March April
Location 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Zone L Zone L 2022/03/25 2022/04/10
Inspection and hanover Work saturday, sunday , nightime friday Inspection and hanover
Remove PVC protect machine Remove PVC protect machine
Remove scaffolding Remove scaffolding
M&E Work M&E Work
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect machine Remove PVC protect machine
Remove scaffolding Remove scaffolding
M&E Work M&E Work
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine

Elevator Area Elevator Area 2021/12/29 2022/01/22


Inspection and hanover Inspection and hanover
Work time : nightime
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding
2022/01/28
Corridor 8 Corridor 8 2022/01/05
Inspection and hanover Inspection and hanover
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding
2022/02/16 2022/03/13
Storage
Inspection and hanover Storage Inspection and hanover
Work time : nightime
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding
2022/03/15 2022/04/11
Corridor 9
Inspection and hanover Corridor 9 Inspection and hanover
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling ###
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding
2022/04/13
Meeting Room 2022/03/16
Inspection and hanover Meeting Room Inspection and hanover
Work time : nightime
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
Install scaffolding Install scaffolding

Zone M Zone M 2021/12/13 2022/01/16


Inspection and hanover Inspection and hanover
Work time : nightime
Remove PVC partition Remove PVC partition
Re-install M&E equipment Re-install M&E equipment
Painting M-bar ceiling Painting M-bar ceiling
M&E work under ceiling M&E work under ceiling
Re-install ceiling M-bar Re-install ceiling M-bar
M&E above celing M&E above celing
Remove existing ceiling M-bar Remove existing ceiling M-bar
Remove M&E equipment Remove M&E equipment
PVC partition PVC partition
PVC partition
Washing room Washing room 2021/12/31 2022/01/17
Inspection and hanover Work time : nightime Inspection and hanover
Remove PVC protect machine Remove PVC protect machine
Remove scaffolding Remove scaffolding
M&E Work M&E Work
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
Remove PVC protect machine Remove PVC protect machine
Remove scaffolding Remove scaffolding
M&E Work M&E Work
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
PVC protect machine PVC protect machine
2021/10/25

Toilet room Toilet room 2021/12/24 2022/01/09


Inspection and hanover Work time : Saturday, Sunday Inspection and hanover
Remove PVC protect Remove PVC protect
Remove scaffolding Remove scaffolding
M&E Work M&E Work
Make opening for outside wall Make opening for outside wall
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
Cover PVC protect Cover PVC protect
Remove PVC protect Remove PVC protect
Remove scaffolding Remove scaffolding
M&E Work M&E Work
Remove M&E equipment Remove M&E equipment
Install scaffolding Install scaffolding
Cover PVC protect
2021/10/25

October November December January February March April


Duration
Location 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 16 17 17 18 20 21 22 23 24 24 25 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Page 6 of 8
Yakult Vietnam Factory Extension Construction Project - Detailed Schedule (Until Handover)
Date 14th Dec 2020 Site Oversea FF Owner

2021
Duration December January
Zone Location 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
All Inspection Inspection
DBiZA Inspection DBiZA Inspection
Defect work Defect work
Owner Inspection Owner Inspection
Toda Oversea inspection Toda Oversea inspection
FF inspection FF inspection
Toda Site Inspection Toda Site Inspection
Aplication for FF department Aplication for FF department
Dock Leveler

2021
Duration December January
Zone Location 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 11 12 13 14 15 16 17
Yakult Vietnam Factory Extension Construction Project - Detailed Schedule (Until Handover)
Date 25th Nov 2020 revise

2021
A 工区・ B 工区・外構 日割工程表 Duration January February
Zone Location 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 27
All Handover
Yakult start Preparation Work. Yakult start Preparation Work.
Touch-up paint for wall & floor Touch-up paint for wall & floor
Remove Scaffolding Remove Scaffolding
Repair and cleaning exsiting ceiling Repair and cleaning exsiting ceiling
A3 工区引渡し前工程 Remove Temp. panel wall Remove Temp. panel wall
Scaffolding Scaffolding
Setting Temporary Ante Room (Sheet) Setting Temporary Ante Room (Sheet)
All Inspection
DBiZA Inspection DBiZA Inspection

All

2021
Duration January February
Zone Location 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 11 12 13 14 15 16 24 25 26 27 28 29 30 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 11 12 13 14 15 16 24 25 26 27 27

Page 8 of 8