Wastewater Stabilization Pond-NZ
Wastewater Stabilization Pond-NZ
WASTE STABILISATION
PONDS:
DESIGN AND OPERATION
Sunlight
Reaeration by
wind action
Free board
High water level
Algae CO2H2O
Low water level Organic acids
O2 Aerobic Cycle CO2
Anaerobic
1.5m 1m Bacteria decomposition
AUTHORS
The NZWWA 2007 draft Guidelines content was authored by:
Steve Cameron, NZET Ltd
Stu Clark, NZET Ltd
The content of this manual has been provided and improved by the text, review and comments of
internal and external technical advisors:
Humphrey Archer, CH2M Beca Ltd
Gilles Altner, Global Environmental Engineering Ltd
Rupert Craggs, NIWA
John Wong, Parklink
Regan Senior, Parklink
Hugh Ratsey, The Wastewater Specialists
Nick Walmsley, Water New Zealand
REVIEWERS
Assistance was greatly appreciated from the following representatives of the Water Service
Managers Group, who provided valuable review comments.
Paul Gaydon, Horowhenua D.C.
Terry Dodd, Dunedin C.C.
Peter Cowdell, Water Northland
Mike Bourke, Christchurch C.C.
Barry Somers, Northland D.C.
Copyright:
The information contained in this Good Practice Guide is given in good faith and has been derived from sources believed
to be reliable and accurate, however, neither the organisation of Water New Zealand nor any person involved in the
preparation of this publication accept any form of liability whatsoever for its contents. No part of this document may
be reproduced, stored in any retrieval system, or copied in any way, without the prior written permission of Water New
Zealand.
Published by:
Water New Zealand | PO Box 1316, Wellington 6140 | P: +64 4 472 8925 | E: enquiries@waternz.org.nz | W:
www.waternz.org.nz
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | i
CONTENTS
ACKNOWLEDGEMENTS ............................................................................................................................................... i
1 GENERAL .......................................................................................................................................................... 1
1.1 OVERVIEW ....................................................................................................................................................... 1
1.2 WHAT’S IN A NAME? ..................................................................................................................................... 2
1.3 POND CLASSIFICATION – BASED ON ORGANIC LOADING ............................................................ 3
1.4 FACULTATIVE PONDS.................................................................................................................................. 5
1.5 MATURATION PONDS .................................................................................................................................. 6
1.6 POND CLASSIFICATION – RELATIONSHIP TO OTHER TREATMENT ............................................ 6
1.6.1. WSP EFFLUENT QUALITY ................................................................................................................ 8
2 DESIGN AND CONSTRUCTION ................................................................................................................. 9
2.1 HISTORICAL OXIDATION POND SIZING ................................................................................................. 9
2.2 CURRENT DESIGN CRITERIA ...................................................................................................................... 9
2.3 ANAEROBIC PONDS ..................................................................................................................................... 9
2.3.1. SIZING .................................................................................................................................................... 10
2.3.2. SHAPE .................................................................................................................................................... 10
2.3.3. DEPTH .................................................................................................................................................... 10
2.3.4. INLET STRUCTURE ............................................................................................................................. 10
2.3.5. OUTLET STRUCTURE ........................................................................................................................ 10
2.3.6. PERFORMANCE ................................................................................................................................... 10
2.3.7. BIOGAS USE ......................................................................................................................................... 11
2.4 FACULTATIVE PONDS.................................................................................................................................. 11
2.4.1. SIZING, MIXING AND ODOUR CONTROL .................................................................................... 11
2.4.2. SHAPE .................................................................................................................................................... 13
2.4.3. DEPTH .................................................................................................................................................... 13
2.4.4. INLET STRUCTURES .......................................................................................................................... 13
2.4.5. OUTLET STRUCTURES ...................................................................................................................... 14
2.5 MATURATION PONDS .................................................................................................................................. 16
2.6 HYDRAULIC DESIGN ..................................................................................................................................... 17
2.6.1. ESTIMATING POND HRT PROFILE ................................................................................................. 17
2.7 POND CONSTRUCTION ............................................................................................................................... 18
2.7.1. LOCATION AND GROUND CONDITIONS .................................................................................... 18
2.8 EMBANKMENTS, WAVEBANDS AND FREEBOARD ............................................................................. 19
2.8.1. EMBANKMENTS .................................................................................................................................. 19
2.8.2. PIPES....................................................................................................................................................... 19
2.8.3. WAVEBANDS ....................................................................................................................................... 19
2.8.4. FREEBOARD ......................................................................................................................................... 20
2.9 CONSTRUCTION ............................................................................................................................................ 20
2.10 MAINTENANCE ACCESS.............................................................................................................................. 20
2.11 FENCING ........................................................................................................................................................... 20
2.12 ROAD ACCESS ................................................................................................................................................ 21
2.13 WARNING NOTICES ...................................................................................................................................... 21
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | ii
2.14 OPERATION BUILDING ................................................................................................................................. 21
2.15 FILLING .............................................................................................................................................................. 22
2.16 MONITORING FACILITIES ............................................................................................................................ 22
2.16.1. FLOWS ................................................................................................................................................... 22
2.16.2. RECORDING ......................................................................................................................................... 23
2.17 SEASONAL VARIATION ................................................................................................................................ 23
2.18 ALLOWANCE FOR POPULATION GROWTH .......................................................................................... 24
2.19 CONSULTATION AND CONSENTING ...................................................................................................... 24
3 POND MODIFICATIONS AND UPGRADES.............................................................................................. 26
3.1 MAINTAINING OR UPGRADING ................................................................................................................. 26
3.1.1. DRIVERS ................................................................................................................................................ 26
3.1.2. OPERATION AND MAINTENANCE ................................................................................................. 26
3.1.3. POND UPGRADES .............................................................................................................................. 27
3.2 TREATMENT IMPROVEMENTS ................................................................................................................... 27
3.2.1. ALGAL SOLIDS..................................................................................................................................... 27
3.2.2. BIOMASS SOLIDS ............................................................................................................................... 28
3.2.3. INERT SOLIDS ...................................................................................................................................... 29
3.2.4. SURFACE SLUDGE ............................................................................................................................. 30
3.2.5. BOD ......................................................................................................................................................... 31
3.2.6. AMMONIACAL-N ................................................................................................................................. 31
3.2.7. TOTAL NITROGEN .............................................................................................................................. 32
3.2.8. TOTAL PHOSPHORUS ...................................................................................................................... 33
3.2.9. FAECAL BACTERIA AND VIRUSES ................................................................................................ 34
3.2.10. ODOUR .................................................................................................................................................. 35
3.2.11. OTHER .................................................................................................................................................... 36
3.3 PRE-POND UPGRADES................................................................................................................................. 36
3.3.1. SCREENING .......................................................................................................................................... 36
3.3.2. SEPTAGE RECEIVING STATIONS ................................................................................................... 39
3.3.3. GRIT REMOVAL SYSTEMS ............................................................................................................... 40
3.3.4. SEPTAGE PONDS, IMHOFF TANKS AND GEOBAGS ............................................................... 41
3.3.5. ANAEROBIC PONDS .......................................................................................................................... 42
3.3.6. OTHER .................................................................................................................................................... 43
3.4 IN-POND UPGRADES .................................................................................................................................... 43
3.4.1. INLET MODIFICATIONS..................................................................................................................... 43
3.4.2. OUTLET MODIFICATIONS ................................................................................................................ 44
3.4.3. FLOW DIRECTION DEVICES ............................................................................................................ 47
3.4.4. AERATION AND MIXING; TYPE AND PLACEMENT ................................................................... 50
3.4.5. PASSIVE AERATION EQUIPMENT .................................................................................................. 53
3.4.6. SUBDIVIDING PONDS ....................................................................................................................... 54
3.4.7. ATTACHED GROWTH MEDIA .......................................................................................................... 54
3.4.8. FLOATING WETLANDS ..................................................................................................................... 56
3.4.9. POND COVERS AND IN-POND ROCK FILTERS ......................................................................... 57
3.4.10. CHEMICAL DOSING ........................................................................................................................... 59
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | iii
3.4.11. ULTRASONIC ALGAE CONTROL.................................................................................................... 61
3.4.12. ENHANCED MICROBIAL DIGESTION ............................................................................................ 61
3.4.13. POND CONVERSIONS ....................................................................................................................... 63
3.4.14. OTHER .................................................................................................................................................... 64
3.5 POST-POND UPGRADES ............................................................................................................................. 64
3.5.1. POST FILTRATION .............................................................................................................................. 64
3.5.2. MEMBRANE FILTRATION .................................................................................................................. 66
3.5.3. DAF OR IAF TREATMENT ................................................................................................................. 66
3.5.4. LAMELLAR CLARIFIERS AND MICRO-SAND INJECTED RAPID GRAVITY SETTLERS ..... 67
3.5.5. UV DISINFECTION .............................................................................................................................. 69
3.5.6. EXTERNAL ROCK FILTERS ............................................................................................................... 70
3.5.7. OTHER EXTERNAL FILTERS ............................................................................................................ 70
3.5.8. WETLANDS ........................................................................................................................................... 71
3.5.9. ELECTROCOAGULATION PROCESS............................................................................................. 73
3.6 HIGH RATE ALGAL PONDS AND ALGAL HARVEST PONDS ............................................................ 74
3.6.1. HIGH RATE ALGAL PONDS (HRAPS)............................................................................................. 74
3.6.2. ALGAL HARVEST PONDS (AHPS) .................................................................................................. 76
3.7 PETRO® SYSTEMS .......................................................................................................................................... 77
3.7.1. DESCRIPTION OF THE PETRO® SYSTEM ..................................................................................... 77
3.8 PARTIALLY AND FULLY MIXED AERATED LAGOONS ........................................................................ 78
4 OPERATION AND MAINTENANCE ............................................................................................................ 79
4.1 GENERAL .......................................................................................................................................................... 79
4.2 MONITORING AND SAMPLING .................................................................................................................. 79
4.2.1. RESOURCE CONSENT MONITORING........................................................................................... 79
4.2.2. INFLUENT MONITORING .................................................................................................................. 79
4.2.3. SEPTAGE AND INDUSTRIAL DISCHARGE MONITORING ....................................................... 79
4.2.4. PROCESS MONITORING ................................................................................................................... 80
4.2.5. BETWEEN PONDS MONITORING................................................................................................... 81
4.2.6. MONITORING OF EXTERNAL PARAMETERS .............................................................................. 82
4.2.7. SAMPLE METHOD – EFFLUENT ..................................................................................................... 82
4.2.8. SLUDGE LEVEL MONITORING ........................................................................................................ 82
4.2.9. WSP SLUDGE MEASUREMENT TECHNIQUES ........................................................................... 82
4.2.10. SAMPLE METHOD – SLUDGE ......................................................................................................... 85
4.2.11. RECOMMENDED SAMPLING SCHEDULE .................................................................................... 85
4.3 TROUBLESHOOTING .................................................................................................................................... 86
4.3.1. SMELLS AND ODOURS ..................................................................................................................... 86
4.3.2. LOW DO ................................................................................................................................................. 86
4.3.3. STRATIFICATION AND POND TURN-OVER ................................................................................ 87
4.3.4. UNEXPECTED POND CRASHES ..................................................................................................... 87
4.3.5. INSUFFICIENT ALGAL GROWTH .................................................................................................... 87
4.3.6. EXCESSIVE ALGAL GROWTH ......................................................................................................... 88
4.3.7. BLUE-GREEN ALGAE (CYANOBACTERIA) BLOOMS ................................................................ 88
4.3.8. COLOUR OBSERVATIONS ............................................................................................................... 89
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | iv
4.3.9. INVASIVE PLANT GROWTH ............................................................................................................. 89
4.3.10. FLIES, MOSQUITOS AND MIDGES ................................................................................................. 90
4.3.11. FISH ......................................................................................................................................................... 90
4.3.12. BIRDS ...................................................................................................................................................... 91
4.3.13. EFFLUENT DETERIORATION ........................................................................................................... 91
4.3.14. OVERLOADING .................................................................................................................................... 92
4.3.15. SLUDGE ACCUMULATION ............................................................................................................... 93
4.3.16. EXCESSIVE FLOATING MATTER .................................................................................................... 93
4.4 MAINTENANCE ............................................................................................................................................... 93
4.4.1. GENERAL HOUSEKEEPING .............................................................................................................. 93
4.4.2. EQUIPMENT MAINTENANCE........................................................................................................... 94
4.4.3. INSTRUMENTATION MAINTENANCE ........................................................................................... 94
4.4.4. INLET AND OUTLET STRUCTURES ............................................................................................... 94
4.4.5. WAVEBAND MAINTENANCE AND REPAIR ................................................................................. 94
4.4.6. POND LINER MAINTENANCE AND REPAIR ................................................................................ 94
4.4.7. DESLUDGING METHODS ................................................................................................................. 94
4.4.8. OTHER .................................................................................................................................................... 95
5 RESOURCE CONSENT AND POND MONITORING............................................................................... 95
5.1 RESOURCE CONSENT CONDITIONS ....................................................................................................... 95
5.1.1. SUPPORTING DOCUMENTATION ................................................................................................. 96
5.1.2. MITIGATION .......................................................................................................................................... 96
5.1.3. RISK COMMUNICATION STRATEGY ............................................................................................. 96
5.1.4. MONITORING ....................................................................................................................................... 96
5.1.5. RECORDS .............................................................................................................................................. 96
5.1.6. MINIMISING ADVERSE EFFECTS .................................................................................................... 96
5.1.7. REVIEW OF CONDITIONS ................................................................................................................ 97
6 FREQUENTLY ASKED QUESTIONS .......................................................................................................... 98
APPENDIX A: INDICATIVE EFFLUENT QUALITY FROM IMPROVED POND SYSTEMS ............................... 99
APPENDIX B: POND RECORD SHEET ....................................................................................................................... 100
7 REFERENCES ................................................................................................................................................... 101
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | v
TABLES
Table 1-1 Typical effluent results for one and two cell facultative WSP systems: (Hickey et al 1989) ..... 8
Table 3-1 Upgrade Options for Algal Solids .......................................................................................................... 28
Table 3-2 Upgrade Options for Biomass Solids .................................................................................................... 29
Table 3-3 Upgrade Options for Large Inert Solids ............................................................................................... 30
Table 3-4 Upgrade Options against Surface Sludge on Facultative Ponds ................................................... 31
Table 3-5 Upgrade Options for Dissolved BOD ..................................................................................................... 31
Table 3-6 Upgrade Options for Ammoniacal-N at the Inlet ............................................................................... 32
Table 3-7 Upgrade Options for Ammoniacal-N within the Pond / at Outlet .................................................. 32
Table 3-8 Upgrade Options for Total N ................................................................................................................... 33
Table 3-9 Upgrade Options for Particulate P reduction...................................................................................... 33
Table 3-10 Upgrade Options for DRP reduction ................................................................................................. 34
Table 3-11 Upgrade Options for Bacteria and Viruses ......................................................................................... 35
Table 3-12 Upgrade Options for Odour Issues ................................................................................................... 35
Table 3-13 Upgrade Options for Other Issues .................................................................................................... 36
Table 3-14 Screen Types for Pond System Upgrades ...................................................................................... 37
Table 3-15 Mixing and Aeration Devices for Facultative and Maturation Ponds ....................................... 50
Table 3-16 Passive Aeration Devices for Facultative and Maturation Ponds ............................................. 53
Table 3-17 Selective Chemicals Used for Alkalinity Adjustment .................................................................... 59
Table 3-18 Post Filtration Devices for Facultative & Maturation Ponds........................................................ 65
Table 3-19 Actiflo Treatment Standards in Different Applications ................................................................. 67
Table 3-19 Actiflo Treatment Standards in Different Applications ................................................................. 68
Table 3-20 External Rock Filters .............................................................................................................................. 70
Table 4-1 Recommended Monitoring Schedule .................................................................................................... 81
Table 4-2 Recommended Sampling Schedule ...................................................................................................... 85
Table 4-3 Connection between colour of the pond and operational characteristics ................................. 89
Table 4-4 Principal causes of effluent quality deterioration .............................................................................. 92
FIGURES
Figure 1-1 The Processes at work in WSP ........................................................................................................... 2
Figure 1-2 Anaerobic Pond .......................................................................................................................................3
Figure 1-3 Facultative Pond ......................................................................................................................................4
Figure 1-4 Facultative Pond Augmented with Aeration ................................................................................4
Figure 1-5 The processes at work in a Primary oxidation pond or Facultative WSP................................ 5
Figure 1-6 Facultative Pond Provides Solids Settlement, Biological Treatment and Sludge
Digestion .................................................................................................................................................................. 7
Figure 1-7 Facultative Pond follows “Conventional” Primary Treatment, providing Biological
Treatment and Sludge Digestion .............................................................................................................................. 7
Figure 1-8 Maturation Pond; follows either a Facultative pond or "Conventional" Primary and
Secondary Treatment .................................................................................................................................................. 8
Figure 2-1 Covered Anaerobic Pond with Biogas Flare ................................................................................... 11
Figure 2-2 Modifications to Pond inlet – to provide jet attachment to the embankment wall ......... 14
Figure 2-3 Outlet structure - allowing fixed outlet flows until pond is full .............................................. 15
Figure 2-4 Outlet baffling using gabion baskets - outlet is between two stub baffles ....................... 16
Figure 2-5 Typical pond construction for cut and fill earthworks construction .................................... 19
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | vi
Figure 2-6 Typical outfall signage ..................................................................................................................... 21
Figure 2-7 V-notch weir with ultrasonic depth measurement on pond effluent.................................. 23
Figure 3-1 Auto Bar Screen .................................................................................................................................... 38
Figure 3-2 Step Screen ....................................................................................................................................... 38
Figure 3-3 Basket screen.................................................................................................................................... 39
Figure 3-4 Drum Screen ...................................................................................................................................... 39
Figure 3-5 Jetting Inlet Upgrade....................................................................................................................... 44
Figure 3-6 Distribution Inlet................................................................................................................................ 44
Figure 3-7 Flow Control Weir............................................................................................................................. 45
Figure 3-8 Level Control Weir ........................................................................................................................... 45
Figure 3-9 Old Fibre Cement Wall .................................................................................................................. 48
Figure 3-10 Concrete Wall .................................................................................................................................... 48
Figure 3-11 Concrete segments ......................................................................................................................... 48
Figure 3-12 Rock Groynes .................................................................................................................................... 49
Figure 3-13 Floating PE Curtain .......................................................................................................................... 49
Figure 3-14 Poor Quality Curtain ........................................................................................................................ 49
Figure 3-15 Brush Aerator .................................................................................................................................... 52
Figure 3-16 Air induced Mixer Type A............................................................................................................... 52
Figure 3-17 Inclined Shaft Aerator ..................................................................................................................... 52
Figure 3-18 Air Induced Mixer Type B............................................................................................................... 52
Figure 3-19 Curtain Growth Media ..................................................................................................................... 55
Figure 3-20 Cellular Growth Media .................................................................................................................... 55
Figure 3-21 Inadequate Media Type A ............................................................................................................. 56
Figure 3-22 Inadequate Media Type B.............................................................................................................. 56
Figure 3-23 Floating Wetland (new) ................................................................................................................... 57
Figure 3-24 Anaerobic Pond Cover ................................................................................................................... 57
Figure 3-25 Anaerobic Pond Conversion ......................................................................................................... 64
Figure 3-26 … to an Activated Sludge Process ............................................................................................... 64
Figure 3-27 Actiflo Micro-sand Assisted Rapid Gravity Settler process diagram .................................. 68
Figure 3-28 Actiflo Reactors ................................................................................................................................. 69
Figure 3-29 Examples of High Rate Algal Ponds in California (a & b), New Mexico (c, d & e) and
New Zealand (f & g) ................................................................................................................................................... 74
Figure 3-30 Christchurch Demonstration HRAP CO2 addition sump ........................................................ 76
Figure 3-31 Cambridge Algal harvest Ponds (AHP).......................................................................................... 76
Figure 3-32 PETRO® Basic Flow Diagram ......................................................................................................... 77
Figure 4-1 Example Sludge Column Layers .................................................................................................. 84
Figure 4-2 Covering of Screenings .................................................................................................................. 86
Figure 4-3 Cyanobacteria ................................................................................................................................... 88
Figure 4-4 Weed Growth (Photo courtesy of Sam Murphy, Buller District Council) ........................... 90
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | vii
1 GENERAL
1.1 OVERVIEW
This document is an update of the Ministry of Works Guidelines for Oxidation Ponds 1974. It follows
the NZ Water and Wastes Association (NZWWA) 2007 draft Waste Stabilisation Pond Guidelines
which were published as a 2nd draft but never finalised and it draws on recent research and
practices. It is primarily written for those involved in wastewater treatment pond management and
operations: local authorities, regional councils, and wastewater systems operations personnel. As
well as management and operations, these guidelines include basic aspects of pond design,
planning, cultural acceptance, and regulations. It is assumed that the reader has an understanding
of basic wastewater terminology.
These guidelines cover:
How Waste Stabilisation Ponds (WSP) work
How they differ from other types of ponds
How to operate WSP
What to do when things go wrong
By their nature, these guidelines cannot cover every aspect of pond design and operation, nor
should they be used like a ‘cooking recipe book’. It is recommended that the advice of experienced
design and operation practitioners should be obtained when pond performance is abnormal or
when significant upgrading work is planned.
Section 1 provides general introductions to the types of ponds and the terminology. Later sections
describe the design and operational aspects of ponds in more detail.
Appended to this Guide are a table giving performance improvement levels possible with pond
upgrades and an example pond operation log sheet. The log sheet is also separately provided as
an Excel spreadsheet.
WSP are amongst the most commonly used methods for treating domestic sewage in New Zealand,
as they are elsewhere in the world, both in developed and developing countries. The New Zealand
Ministry of Health’s Cosinz data base reported that as of the year 2000, there were some 176
community wastewater treatment systems incorporating WSP; this hasn’t changed much since. This
is over half the total number of community treatment plants in New Zealand. These community WSP
systems range in number of ponds (from 1 to 8 ponds) and in population serviced (from under 100 to
over 400,000 people). For small to medium sized communities, (50 to 30,000 population
equivalents (PE’s)), ponds are often the sole form of wastewater treatment. For larger communities,
(30,000 PE +), there is often a multiple pond system, increasingly with enhancements, to produce a
tertiary standard of final effluent quality.
WSP are also used extensively in New Zealand for treatment of dairy farms and piggery effluents as
well as agricultural processing (e.g. meatworks) wastewater. However, this Guide is limited to
information for ponds treating municipal wastewater.
The direct discharge of pond effluents to waterways is now becoming less acceptable, for both
cultural and water quality impact reasons. But ponds are experiencing resurgence in both New
Zealand and overseas. This is due to the development of advanced pond systems and retrofit
technologies. These improvements are able to achieve treatment qualities comparable to
mechanised treatment plants such as activated sludge. Where land is available, ponds also offer
significant capital and operating cost advantages when compared with alternative wastewater
treatment technologies.
Modern ponds, with enhancements, have an important role to play in wastewater treatment in New
Zealand. Ponds are robust, require low energy, are able to cope with hydraulic and organic loading
peaks, and can provide buffer storage for downstream processes such as land treatment systems.
Greenhouse gas emissions, especially methane, are an important aspect of the “environmental
footprint” of a wastewater treatment process. The 2014 National Greenhouse Gas Inventory using
the IPCC 2006 methodology notes that there is considerable uncertainty in the amount of
greenhouse gas emitted from wastewater treatment. However, the conversion factors proposed by
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 1
IPCC indicate that WSP which are primarily aerobic or facultative are likely to emit less greenhouse
gases from the whole treatment plant than mechanical systems e.g. activated sludge, unless there is
substantial energy recovery by sludge digestion.
In spite of their apparent simplicity, WSP require skilled operation and regular attention. A good
understanding of how they work and attention to maintenance requirements will make sure that
ponds operate reliably.
Dissolved nutrients in the sewage, such as nitrogen and phosphorus, are converted by bacteria and
assimilated along with carbon dioxide (CO2) by algae which are microscopic plants that live
suspended in the water.
Like land plants, algae produce oxygen by photosynthesis during the day. Pond oxygen
concentrations and some other characteristics, like pH, will therefore change throughout the day
and from day to night. The oxygen sustains the aerobic bacteria which feed on and break down the
incoming organic waste. At night the algae generate CO2 which raises the ponds alkalinity.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 2
1.3 POND CLASSIFICATION – BASED ON ORGANIC
LOADING
Previous guidelines used terminology of primary, secondary and tertiary ponds. However as further
knowledge has been gained it has become clear that this terminology can be confusing and does
not illustrate what characteristics or functions the ponds perform. New terminology that is more
accurate and descriptive, as it is based on organic loading, is now used in preference. There are
three different types of passive WSP that are classified based on organic loading: Anaerobic,
Facultative and Maturation.
Anaerobic ponds (Figure 1-2) have such a high organic loading that all the oxygen is used by
bacteria, leaving conditions that only anaerobic bacteria can survive in and break down the
wastewater. They are usually deep (greater than 3m) and in New Zealand are often used to treat
high strength wastewaters (i.e. high BOD) such as those from dairy farms, piggeries, meatworks,
stock trucks and landfills. Anaerobic ponds are suitable to treat raw municipal sewage with high
organic concentrations. There has been a perception in New Zealand that anaerobic ponds treating
municipal sewage will smell, but this needn’t occur if operated properly and particularly if a surface
crust is allowed to develop.
Facultative ponds (Figure 1-3 ) have an organic load which allows an aerobic surface with algae and
aerobic bacteria, an anoxic middle zone without dissolved oxygen, but where oxidized compounds
(e.g. NO3 and SO4) are still present, and an anaerobic bottom layer, where sludge settles and
digests.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 3
Layers: is aerobic liquid; is anoxic liquid; is anaerobic liquid; is anaerobic sludge
Figure 1-3 Facultative Pond
Some facultative ponds have been augmented with addition of mechanical aerators to help treat
high organic load by providing both mixing and aeration. However adding more than about 1w/m3 of
mechanical aeration is disruptive to the algal cycles and creates a completely different type of
aerated pond which is not covered in this guide.
Partially and fully aerated lagoons (refer 3.8) are designed for aerobic treatment to be completely
provided by mechanical aeration, in the same way as an activated sludge plant, but usually without
the return of settled sludge. They can be designed with either in-pond sludge settling or be followed
by a sludge settling pond or clarifier.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 4
Maturation ponds typically follow facultative ponds, aerated lagoons or mechanical treatment plants
and have the lowest organic load and are completely aerobic.
Figure 1-5 The processes at work in a Primary oxidation pond or Facultative WSP
The depth of the aerobic zone (the top zone) in a WSP depends on organic loading, hydraulic
retention time, climate and season (both temperature and sunlight), mixing/stratification and the
concentration of algae (dependent on all of the above, as well as algal grazers and pathogens).
Aeration is predominantly from algal photosynthesis with minor (but helpful) contributions from
agitation of the water surface due to wind and rain. The depth of the aerobic zone also varies
diurnally as, although algal photosynthesis only occurs during the day, both algal and bacterial
respirations occur throughout the day and night.
Given sufficient light and temperature, algal concentration is generally dependent on the
concentration of nitrogen in the wastewater. However, high organic loading and/or ammonia
concentrations can limit algal growth, and some cyanobacteria can grow even at low pond water
nitrogen concentrations by fixing nitrogen from the air.
The depth of the algae layer typically depends on the average water clarity (depth of light
penetration) and level of mixing, although some motile algae swim up and down within the pond
during the day to adjust their light environment. Other algae (usually cyanobacteria) tend to
accumulate in a layer at the pond surface, unless dispersed by mechanical mixing or continually
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 5
removed by a surface outflow weir. Surface accumulations of algae can cause problems with
elevated BOD levels, particularly if they die-off within the pond.
The dissolved oxygen concentration in the water gradually rises after sunrise, in response to
photosynthetic activity, to a maximum level in the mid-afternoon, after which it falls to a minimum
during the night, when photosynthesis ceases and algal and bacterial respiration continues to
consume oxygen. At high daytime photosynthetic rates, the algae consume all the available carbon
dioxide and carbonate and bicarbonate ions react to provide more carbon dioxide for the algae,
leaving an excess of hydroxyl ions. As a result, the pH of the water rises to levels as high as 9 - 10.
In the pond’s aerobic zone, bacteria use oxygen to break down dissolved organic matter releasing
nutrients and carbon dioxide, which are used by algae and sometimes nitrifying bacteria for growth.
Good mixing within the upper water layer maintains a uniform distribution of algae, dissolved
oxygen, pH, bacteria, BOD and nutrients, thereby leading to more efficient wastewater treatment.
The long hydraulic retention time and low velocities of wastewater in the pond means that some of
the bacterial and algal biomass settles within the pond, together with any heavier solids in the
influent.
The aerobic zone also scrubs the odours from gases produced in the lower layers.
Below the aerobic zone, the anoxic zone provides habitat for bacteria that survive by reducing
oxidized compounds (e.g. denitrification: NO3 to N2 gas).
The interface between the sludge and the liquid anaerobic zone is where most anaerobic activity
occurs. Settled solids are washed around the pond floor but tend to accumulate to greater
thicknesses near the inlet where the heavier influent solids have settled. Over the rest of the pond
there is a more uniform depth of liquid between the pond surface and the top of the sludge layer,
regardless of pond floor contours (i.e. sludge tends to fill up any deep areas).
Anaerobic bacteria decompose the organic matter, converting it to carbon dioxide (CO2), methane
(CH4), and residual matter. The bacteria derive their energy from the organic matter they consume.
The carbon dioxide and methane released can be observed as bubbles and sludge eruptions on
the pond surface.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 6
Guidelines are now superseded by the standard international nomenclature of calling primary ponds
facultative, with secondary and tertiary ponds called maturation ponds.
Figure 1-6 Facultative Pond Provides Solids Settlement, Biological Treatment and Sludge Digestion
A facultative pond can either receive raw wastewater, or primary effluent, such as that from a
clarifier or Imhoff tank (this latter arrangement is now less common).
Figure 1-7 Facultative Pond follows “Conventional” Primary Treatment, providing Biological
Treatment and Sludge Digestion
Maturation ponds can follow one or more facultative ponds, or follow a secondary treatment plant.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 7
Figure 1-8 Maturation Pond; follows either a Facultative pond or "Conventional" Primary and
Secondary Treatment
Table 1-1 Typical effluent results for one and two cell facultative WSP systems: (Hickey et al 1989)
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 8
2 DESIGN AND CONSTRUCTION
2.1 HISTORICAL OXIDATION POND SIZING
In New Zealand, facultative pond area sizing historically has been based on a population equivalent
organic loading rate. This historical design value for facultative (primary) ponds has been 84 kg
BOD5/ha/day or 1,200 people/ha (assuming 70g of BOD5 produced per person per day), (refer to
Ministry of Works Guidelines for Oxidation Ponds 1974 -- MoW). It should be noted that the
population loading guide applied to only the first pond in a series of ponds and the area of
downstream ponds required further calculation. This loading level has proven to be conservative for
many circumstances as long as the influent is from a mainly domestic source and the ponds are not
located in inland locations with cold temperatures and little wind mixing during winter.
Secondary facultative ponds (i.e. ponds which follow a primary sedimentation process e.g. a primary
sedimentation tank, or Imhoff Tank) were also sized on the basis of 84 kg BOD5/ha day. However,
allowing for a 33% reduction of BOD5 in the primary treatment unit, this equates to 1,800 persons/ha.
The design of a secondary or maturation pond following a facultative (primary) pond was based on a
detention period of 20 days at average flow, and was typically only one pond. The relatively large
maturation pond did not need to be sized on BOD loading because the facultative (primary) pond
reduced BOD by about 70%.
A suggested limitation of primary pond area was 8 to 12 hectares. The MoW considered that, in
larger ponds, wind action generated waves large enough to resuspend bottom sediments which
were then discharged in the pond effluent. Also, as pond size increased it was more difficult to
distribute the inlet BOD loading over the whole area, which led to overloading in the inlet part of the
pond. This was the case if mechanical aerator/mixers were not installed, which was typical prior to
1974 and continued until about 1995.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 9
capture biogas for energy recovery (Craggs et al. 2015). Standard CAP designs are not suitable for
all industrial effluents.
There are some specific designs e.g. high rate anaerobic lagoons (HRAL) which can be used to treat
sludge or specific high strength industrial wastes. These ponds require more complicated internal
mixing and gas recovery to work properly (Walmsley & van Oorschot, 2004) and are not considered
in this Guide.
2.3.1. SIZING
Covered (and uncovered) anaerobic ponds are designed based on a volumetric organic loading rate
(typically between 0.1-0.3 kg BOD5 m-3 d-1 (Mara, 2005) for ponds operating in climates with average
air temperatures for the coldest month between 10-30oC respectively. An organic loading rate (0.1-
0.2 kg BOD5 m-3 d-1) is appropriate for most parts of New Zealand although climatic conditions must
be taken into account. This is particularly important to minimize the risk of odour nuisance.
Anaerobic ponds with no cover (i.e. relying on a layer of alkaline water to prevent the release of
odours) can only be lightly loaded compared with anaerobic ponds with a stable crust that reduces
the water surface area for odour release and acts as a filter of the biogas. Covered anaerobic
ponds with a geomembrane cover are able to receive a higher organic loading as the odorous
gases are captured.
Anaerobic ponds typically have hydraulic retention times (HRT) of 1.5-3 days, however, the solids
retention time (SRT) is much longer, usually 1-3 years, depending on when the settled digested
sludge is removed.
2.3.2. SHAPE
Anaerobic ponds should have a uniform rectangular shape with a surface width that enables sludge
to be removed right across the pond bottom (this will depend on pond depth, embankment slope
and method of sludge removal).
2.3.3. DEPTH
To reduce the pond surface and cover area, it is best that a CAP is constructed as deep as practical
(often 4-6 m) depending on groundwater depth at the site.
2.3.6. PERFORMANCE
Wastewater solids settle to the pond bottom of anaerobic ponds where they digest and
concentrate, leaving a liquid digestate above. The digestate typically contains ~30% of the total
solids (TS) and ~20% of the volatile solids (VS) of the influent wastewater (Craggs et al. 2015).
Annual average biogas methane production from CAPs in New Zealand is 0.40 m3CH4 kg-1
BOD5Removed (or 0.22 m3 CH4 kg-1 VSAdded) which is quite similar to that reported for more costly and
complex mesophilic (~35oC) digesters. CAP biogas production varies seasonally with higher
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 10
production occurring at warmer temperatures. The much longer solids retention time of CAP than
mesophilic digesters, appears to compensate for the lower operating temperature and lack of
mechanical mixing.
It is important not to construct CAP with their base below the ground water table to avoid either
floatation during commissioning or maintenance, and to avoid continuous cooling of the contents by
the surrounding groundwater which will reduce the rates of biological activity.
The sludge accumulation over time is similar for conventional anaerobic ponds and CAPs. However
CAPs will be more difficult to desludge unless they are permanently fitted with desludging facilities.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 11
Zealand because the increased growth of bacterial biomass, that is needed to reduce the soluble
and suspended BOD fractions, restricts the penetration of sunlight for photosynthesis by algae. It is
noted that higher BOD5 loading rates can be used in warmer tropical areas with higher and more
constant light conditions and temperatures (Mara 1992, and Shilton 2006).
Facultative ponds used in inland or sheltered locations where there are cooler temperatures in
winter and/or lack of wind for pond mixing , should have a loading rate of about 60 kg BOD5/ha/day
(USEPA 2011).
It is noted that facultative ponds located in New Zealand coastal areas have generally performed
well without causing odours, because of the normally frequent on-shore winds which mix them. The
exception is the Nelson coastal area which typically has calmer conditions about 50% of the time –
similar to inland areas of New Zealand. In other coastal areas of New Zealand calm conditions are
experienced less than 30% of the time.
Pond odour nuisance results when there is a breakdown of the temperature and organic
stratification in the pond. It typically occurs during spring and autumn, when odorous anaerobic
pond water can reach the pond surface. In spring this is often due to sporadic pond mixing bringing
anaerobic bottom water to the pond surface during stormy weather. In autumn warm anaerobic
bottom water can be displaced (“turnover”) with cold aerobic surface waters during cold nights.
Changes in pond bacteria and algal populations and the resulting oxygen concentration also
exacerbate the potential for odour release. The following comments by recognised pond experts
provide useful guidance.
Gloyna (1971) noted that “during periods of high water temperatures in shallow ponds, sludge mats
may rise from the bottom. Usually the bacterial activity is intense and the odours are
overpowering.” Gloyna recommended using a jet of water to break up the mats and resettle them.
Marais (1970) reported on South African pond experience and noted: “Of the physical factors
influencing the behaviour of a pond, mixing is probably the most important. Mixing is induced
principally by wind action. Lack of wind, coupled with solar radiation normally leads to a state of
stratification or non-mixing in the pond”. He strongly recommended: “The favourable influence of
mixing is so pronounced that the writer is convinced that there is a place in oxidation pond design
for inducing artificial mixing.” This observation was based on ponds in sunny, warm, inland
locations which did not receive adequate wind mixing.
Brockett (1975) studied the Mangere, Auckland oxidation ponds in the early 1970’s and
recommended as follows: “In autumn, as the liquid temperature reduces, the methane formers
cease activity before the volatile acid formers, which can result in accumulation of odorous volatile
acids. The autumn instability is compounded by a change in the algal populations”
“The importance of the presence of dissolved oxygen in lagoon liquor cannot be overstated, for
these aerobic conditions oxidise any odours produced by the anaerobic decomposition of organic
matter in the bottom regions of the lagoons.
Because of this, mixing is very important. Non-motile algae tend to sink to the pond floor and it is
important that they are brought to the surface to be in the effective zone of light penetration. In
most cases, wind action is sufficient to do this, although on occasions it may be necessary to
supplement with ‘aerators’ whose function is as much to mix, as to aerate”.
Mara (2004) made these observations: “Gently mixing (stirring, circulating) the contents of an
overloaded facultative pond can greatly aid its performance – often to the point where it no longer
acts as if it were overloaded. The use of wind-powered mixers can be a cost-effective means to mix
these ponds; alternatively, electric-powered mixers can be used with a power input of <1W/m3,
rather than the 3 to 6 W/m3 used in aerated lagoons.”
It is clear from the recommendations made by eminent researchers of ponds from overseas and
New Zealand, that some mechanical mixer/aerators should be installed on facultative ponds, to
extend the depth of the aerobic zone and provide a larger buffer for potential odour release from
anaerobic bottom water reaching the pond surface. It may not be necessary to operate the
mixer/aerators at night as long as the pond surface remains aerobic.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 12
2.4.2. SHAPE
Primary facultative ponds should be uniform in shape, from square to rectangular with length not
more than twice the width and rounded corners for efficient mixing. Ponds should not have
irregularly shaped or enclosed bays in which scum can lodge and weed growth can develop.
2.4.3. DEPTH
Some facultative pond depths in 1960/70 designs were about 1.0m but current designs should be
within the range 1.3m to 1.5m and can be deeper. This can be influenced by an allowance for sludge
accumulation and storage before desludging. There should be at least 0.9m of aerobic water depth
above any sludge layer for algae to thrive and control odours as described in section 2.4.1. The
design of larger ponds should check that the sludge storage depth will not be disturbed by bottom
currents induced by wind and wave action.
Some designs have depths between 1.5 and 2.0m to allow for greater sludge storage and flow
buffering capacity. Little advantage is gained by making the pond any deeper. Greater depths can
exacerbate temperature and organic stratification in ponds without mechanical mixing, and the
potential for the pond to “turn over” and odour nuisance.
Ponds with adequate mechanical aeration (often used for mixing as much as for aeration), generally
avoid thermal stratification and turnover events as described in section 2.4.1.
Slight variations in pond depth due to natural land contours prior to construction do not affect pond
operation. The natural movement of solids tends to fill deeper areas to give a uniform depth of liquid
layers.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 13
Figure 2-2 Modifications to Pond inlet – to provide jet attachment to the embankment wall
Inlet flows should be screened to remove floatable material. Where mechanical screening is not
used the inlet should have a baffle chamber which traps floatable material for manual removal and
disposal.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 14
Figure 2-3 Outlet structure - allowing fixed outlet flows until pond is full
Here, the small slot in the outlet chamber allows a nearly constant flow to pass with any excess
creating an increase in pond depth. If storm flows occur, then the flow passes through the top of the
chamber as it did prior to modification. Pond levels at this plant have been dropped to 0.8m depth
leading into summer (no discharge) period, to allow for extra buffer storage. This depth reduction
has not created any problems.
Outlet and transfer structures should generally be sited on the upwind side of the ponds, under
prevailing wind conditions, to keep them clear of floating debris and to reduce the likelihood of
short-circuiting.
Figure 2-4 shows a baffled outlet structure to prevent short circuiting currents passing along the
embankments from flowing straight into the outlet. In this case, gabion baskets and a pipe boom
with a suspended geotextile curtain were used to create the baffles.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 15
Figure 2-4 Outlet baffling using gabion baskets - outlet is between two stub baffles
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 16
2.6 HYDRAULIC DESIGN
Shilton (2001) presented an extensive study on the hydraulics of stabilization ponds. Twenty
experimental configurations were tested in the laboratory. Ten of these experimental cases were
mathematically modelled and were consistent with the experimental work. Shilton and Harrison
(2003) then introduced guidelines for hydraulic design of WSP to "help fill the knowledge gap in the
pond hydraulics area". They recommended:
Short-circuiting should be avoided as it decreases the discharge quality.
Influent flows can be mixed into the main body of the pond to avoid localised overloading
near the inlet, while not creating short-circuiting.
A pond should maintain a similar and reasonably well-defined flow pattern through the range
of possible flow rates.
Baffles to shield both the inlet and the outlet, should be considered.
Examples of these recommendations are given in sections 2.8 and 3.4 of thIs Guide.
An important aspect of hydraulic design in ponds is the hydraulic retention time (HRT). This is the
average time that the incoming wastewater stays in the pond. The HRT will affect the level of
treatment the pond performs. Ideally if there are no short circuits, the pond can be considered a
completely mixed system. The flow comes in at one end, travels round the pond and having been
everywhere passes through the outlet. The HRT can then be calculated by dividing the water
volume (excluding sludge zone) of the pond by the flow.
If a primary pond serves 5000 people and is loaded at 1200 people per hectare, then using the
1974 MoW sizing guideline, as noted in section 2.1, the pond will be 5000/1200 = 4.16 ha in area. If
the pond is 1.5m deep, of which an average of 0.3m of the depth is for sludge accumulation, then
the pond wastewater volume is 4.16 x 10,000 (m2/ha) x (1.5-0.3) = 49,920m3. If the average incoming
flow is 300 litres per person per day, or 0.3 x 5000 = 1,500m3/d, then the nominal HRT will be
49,920/1,500 = 33.3 days.
At best the average pond HRT will be 33.3 days, so it will often be longer or shorter than this. This is
because of dead zones where flow does not go, and temporary wind mixed currents, which can
cause short circuiting. Estimating the HRT profile is important so that pond performance can be
improved using baffles and other methods. There are several methods of estimating the HRT profile
as outlined below.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 17
2.7 POND CONSTRUCTION
2.7.1. LOCATION AND GROUND CONDITIONS
Ponds can be constructed in virtually any location, however it helps to reduce the cost if the site has
suitable conditions and is located at a lower elevation from the area serviced, so the wastewater
can flow to the pond by gravity. Ideally an area should be selected where the water table is deep
and the soil is heavy and impermeable. Silt or clay soils are ideal for pond foundations and
construction. Building ponds over coarse sands, gravels, fractured rock or other materials that will
allow effluent to seep out of the pond or allow groundwater to enter, will require care and specialist
geotechnical engineering.
WSP will ideally be located at some distance from residential areas (due to potential odours and
aerosols).
The emission of undesirable odours from WSP has occurred from pond systems, especially those
relying on natural aeration. In many cases these were due to overloading, poor design or poor
operation. Reference should be made to the NZWWA ‘Manual for Wastewater Odour Management,
2000’. The manual covers the regulatory and legislative issues, methods of quantifying odour,
dispersion modelling and guidelines, and techniques for assessing the potential for odour problems
to occur. Also see section 2.4.1 and 3.2.10 for more discussion of reduced odours from ponds.
For proximity of ponds to residential dwellings and areas, the 1974 MWD Guidelines recommended:
“300m from built-up areas or 150m from isolated dwellings. For populations of less than 1,000
persons these restrictions may be reduced provided that there is adequate natural screening (by
trees or landscaping) and that the prevailing wind blows away from any housing area”.
Odour dispersion modelling studies since 1994, have confirmed the general validity of these buffer
distances but each site should be evaluated on its own merits. Having mechanised aeration, for
example, will reduce the risk of odour problems.
Some designers prefer sheltered sites to reduce undesirable wind-driven flow patterns. However,
on balance, it is preferable to have open area to take advantage of the sun and wind which will
assist the efficient operation of the WSP and improve the quality of the discharge.
It is also recommended to avoid sites that are likely to flood, have steep slopes that run towards a
waterway, springs or water supply bores. The pond should be orientated with the longest diagonal
dimension of the pond parallel to the direction of the prevailing wind, the inlet should be at the
downwind end, and outlet at the upwind end. Ponds should not be located too close to airports, or
landing/take off flight paths, as any birds attracted to the ponds may constitute a bird strike risk to
aircraft. If near an airport, both the Civil Aviation Authority and the airport operating authority should
be consulted.
The site should preferably be flat. Surface drainage should be away from the site or should be
diverted away from the pond formation. Some WSP have previously been located in pre-existing
shallow gullies, with little modification to the original floor levels. Whilst this can make for
economical pond construction, the variable and excessive water depths which usually occur with
such sites, often cause pond performance problems.
Where a pond is built on top of a site where considerable plant material, wood or branches are
buried in the ground, such material should be fully cleaned out and NOT pushed into the pond base
prior to construction to avoid the risk of such material coming to the surface over time.
Ground conditions will normally dictate what type of pond sealing material can be used, e.g. clay or
an artificial liner. Both types have their advantages and disadvantages, which should be carefully
considered for both life expectancy and desludging impacts prior to selection.
Ponds built without the use of a liner can initially leak slightly. This leakage will often reduce as
sludge layers build up. However predicting the leakage rate is often not certain and resource
consent conditions may enforce either a liner or monitoring wells to ensure the groundwater is not
adversely affected. Ponds which leak due to incomplete sealing, may also have the impacts of
seepage controlled by pumping the seepage back into the pond.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 18
2.8 EMBANKMENTS, WAVEBANDS AND FREEBOARD
2.8.1. EMBANKMENTS
Embankments form the sides of the pond. They must be well constructed to prevent seepage,
settlement or erosion over time. Embankment slopes are commonly 1 (vertical) to 3 (horizontal)
internally and 1 to 2.5 to 4.0 externally (the flatter grade if they are to be mowed). External
embankments should be protected from storm water erosion by providing adequate drainage.
Internal embankments should be protected from wave action erosion by using concrete wavebands
or rock rip-rap. Where a synthetic liner is used, rough textured liner must be provided in places to
allow safe entry and exit for maintenance.
Embankment tops should be wide enough to permit vehicle access for maintenance purposes; a
minimum width of 4m is recommended. Tracks should be metalled to provide a good base for
vehicle traction. Fill embankments should be constructed on good foundations and be compacted
according to earthworks construction standards for the soils involved. A well-constructed
embankment, as shown in Figure 2-5, will not be at risk from moving due to the weight of the pond
water. However, good compaction will also minimise settlement, form a good base for wavebands,
and reduce the risk of erosion damage from floodwaters, or seepage flows from within the pond.
Special care must be taken to locate any soft spots or filled areas on the pond site. These should be
excavated and refilled with well compacted, good quality fill material.
Figure 2-5 Typical pond construction for cut and fill earthworks construction
2.8.2. PIPES
Where pipes are laid through embankments care must be taken with back-filling around the pipe. If
pipelines are laid through the base of the pond embankment it may be preferable to use
Polyethylene (PE) or Glass-Reinforced Plastic (GRP) flexible pipes without joints. The pipes should be
laid at the same time that the embankment is built up. This will reduce the problems associated with
differential settlement and avoid the need to dig up the embankment to repair damaged pipework.
Special precautions such as puddle flanges or bentonite supplements should be used to prevent
water tracking along the pipe wall. Similarly special detailing is required for penetrations through
artificial liners.
2.8.3. WAVEBANDS
A wave band forms a clean edge to a pond, preventing erosion and making the pond easier to
maintain. Various materials have been used for wave band construction but to date, only concrete
and rock have been found completely satisfactory. Geomembrane liner, while a good option for
small ponds, does not allow access onto the waveband for cleaning, as it is slippery when wet, but
sections of textured non-slip liner can be used where access is needed.
Concrete wave slabs must be keyed into the embankment. The use of small precast slabs is not
recommended because of the difficulty of providing an adequate key; unkeyed slabs have been
known to slip. Joints between pre-cast slabs are also prone to weed growth.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 19
Rock can provide bank protection at lower cost than concrete. Suitable rock sizes need to be
readily available (based on wave size) and the pond inlet must be screened to prevent debris
collecting in the rock. The rock rip rap should be placed over the full slope length, on medium to
heavy grade geotextile or graded rock rip rap protection. Rock and geotextile has the advantage of
not being affected by bank settlement, and wave run-up is reduced.
2.8.4. FREEBOARD
Freeboard (the amount of waveband above the water surface) and waveband width must be related
to the size of waves which may form and the roughness of the waveband material; the rougher the
material the shorter the run-up of the wave. Freeboard sizing in texts which do not specify
waveband roughness is often based on a concrete surface and should be adjusted for other
materials. Wave size depends on the size and wind exposure (fetch) of the pond. Typical wave band
sizing for smaller ponds (up to 2 ha), is shown in Figure 2-5. For larger ponds specific design should
be undertaken.
2.9 CONSTRUCTION
Certain site-related factors, such as the location of the water table and the composition of the soil,
should always be considered when designing pond systems. Ideally, ponds should be constructed
in areas with clay or other soils that won't allow the wastewater to quickly percolate down through
the pond bottom to the groundwater. Ponds in sensitive areas must be artificially lined with clay,
bentonite, plastic, rubber, concrete, or other impervious materials to prevent groundwater pollution.
Imported linings will increase construction costs significantly.
When preparing a site for WSP, all organic material should first be stripped from the pond area. The
subgrade is then compacted and any soft spots filled, embankments are formed along with inlet and
outlet pipework and the base and sides sealed if the soil used for construction is not fine enough to
keep the rate of seepage suitably low. Finally, the wavebands and tracks are constructed.
In cases where the ground water table can rise above pond floor level, the pond must be filled as
quickly as is practicable and must be kept full to prevent the sealing layer from being lifted. In such
cases, site dewatering may be required if the pond is ultimately emptied for desludging. This should
be clearly noted in written operational procedures. Subsoil drains or permanent site groundwater
bores, which can be used for groundwater monitoring and dewatering, can be beneficial.
2.11 FENCING
Fences are essential to keep livestock out of pond areas and to deter public access. The large
areas of land usually involved tend to make climb-proof fencing expensive, although from a health
and safety perspective its use is desirable. In many cases the “front entrance” to ponds is security
fenced in this manner, with the “back door” being left at stock proof fencing. Normal 7 or 8 wire
stock-proof fences are usually all that is provided. Deer fencing can provide additional security with
limited additional expense.
Fencing can be erected on top of the pond embankment immediately above the wave slab. This
approach lessens the amount of land to be kept tidy but makes maintenance work such as the
removal of floating debris and repairing erosion more difficult. Maintenance access must be
considered before erecting a fence.
A second approach is to erect the fence and leave an access-way around the top of the pond
embankment. Pasture growth between the edge of the pond and the fence must be controlled by
mowing or by periodic grazing. If grazing is used, drinking water must be supplied for the stock and
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 20
temporary fencing used to prevent stock access to the pond. Allowance for surface damage
through impact of the animals’ feet should also be considered.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 21
suitable water supply is often a problem but this can be overcome by collection, tank storage and
treatment of rain water from the roof of the building. Provision of a toilet should also be considered.
2.15 FILLING
Ponds should be completely filled and maintained at operating level as soon after construction as is
possible. Rapid filling prevents the establishment of weeds. This filling can use a natural water
supply and, after testing for water tightness, raw sewage can be introduced to start process
commissioning.
Ponds that are allowed to fill slowly, generally suffer bank erosion until the liquid level rises to the
wave band. Some slow-filling ponds have become anaerobic, accumulating large areas of floating or
settled sludge with limited volumes of liquid due to loss by seepage and evaporation.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 22
Figure 2-7 V-notch weir with ultrasonic depth measurement on pond effluent
Terminal pumping stations should be fitted with a flow measuring device and an “hours run” meter.
For pumped flows a “full bore” magnetic type flow meter usually provides accurate measurements.
2.16.2. RECORDING
Most pond monitoring equipment comes with outputs for recording and data logging of critical
information (like pond inflow rates and dissolved oxygen measurements). One option is for the data
to be manually entered during a site visit or, alternatively, it can be automatically logged onto a data
logger or sent electronically through a telemetry system to be logged at a base station.
Many discharge consents for pond systems now require automatic measurement and logging of key
parameters such as flow, temperature, and dissolved oxygen. Telemetry systems are also becoming
more common for ponds. Both automatic measurement and telemetry are desirable if there is the
possibility of the ponds requiring rapid intervention, for example in response to low oxygen levels.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 23
the pond surface and agitation of the pond surface e.g. using brush aerators, can greatly reduce the
accumulation of blue-green algae scum on ponds.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 24
imperative. However, views on the detail of how wastes should be managed vary across regions
and open dialogue on wastewater management and appropriate local solutions is important.
Other affected and interested parties for a new or upgraded WSP include Ministry of Health,
Department of Conservation, Fish and Game, other water users, downstream consent holders,
environmental groups, local landowners and occupiers and the public.
It is important, therefore, to start consulting early on the options for treatment and discharge.
Consultation must be undertaken in good faith and solutions considered that genuinely address
people’s concerns. Local people will understand the physical and technical conditions of their area
that can constrain the feasible options if they are clearly presented.
Careful planning for consultation and consent application will generally save time and expense and
avoid a project becoming contentious.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 25
3 POND MODIFICATIONS AND UPGRADES
3.1 MAINTAINING OR UPGRADING
3.1.1. DRIVERS
Reasons for implementing modifications or upgrades of a pond system are generally due to one or
more of three reasons:
Significant operational problems such as odour, non-compliance with Resource Consent
conditions, complaints from neighbours or equipment failure. These are generally the
consequence of a prolonged and systematic lack of maintenance and operational care of
the pond. Often this is due to a lack of knowledge of the fundamental O&M requirements of
a pond-based treatment system. Signs of such a situation include overgrown or crumbling
embankments, unacceptable sludge accumulation, frequent or prolonged odour or non-
compliant discharge events. In such a case it is important to initially review and update the
O&M protocols applied at the plant and to consider upgrade options only as a second step.
Political reasons, e.g. “ponds are old technology, which cannot achieve the required
treatment standards”, and therefore “it is better to treat wastewater using a mechanical
treatment plant”. This reason will always be the most difficult to satisfy. It is often based on
a lack of in-depth knowledge of the pond-based treatment process itself. Often it is not
founded on either process or technical reasons. It can therefore be difficult to change the
stakeholders’ views without a good process and operational knowledge of the existing
plant together with a list of successfully operating pond-based reference plants.
Experience shows that all reasons put forward for the need for a pond upgrade have generally an
O&M issue at their root. Recognition of the importance of effective O&M practices is therefore
paramount. It is therefore here that the needs and requirements of the pond should first be
considered and changes be implemented. A pond’s O&M requirements as well as
recommendations for sampling process and procedures are provided in section 4.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 26
Resource Consent conditions developed for mechanical treatment plants were directly applied to
pond systems.
It is recommended that the operator be proactive in sampling and analysis of parameters that are
not required by the Resource Consent conditions if, after reading this Guide, she/he considers that
there is insufficient data to fully understand the operation of the pond system or the plant’s
condition.
Section 5 discusses issues related to Resource Consent conditions for ponds. It encourages
operators and Councils to work with the Regional Authorities in developing pond-specific Resource
Consent conditions, which do provide adequate and comprehensive information on the plant’s
condition and give a correct picture of the quality of effluent being discharged.
The reader is therefore encouraged to read sections 4 and 5 before starting with an investigation
into possible plant upgrade options.
Gradual upgrades can be related to the application of more stringent Resource Consent conditions
over time which can significantly reduce overall upgrade costs.
Traditional ponds are heavily impacted by environmental and seasonal changes on which the
operator has minimal influence. In contrast, modern ponds and the upgrade options discussed in
this Guide, provide more treatment consistency and the operator with more control over the plant’s
treatment process and quality.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 27
within the water column, little disturbance (avoidance of intense mixing), correct pH, and the
absence of predators (e.g. invertebrates), algaecides or high concentrations of chemicals preventing
their development.
Because of the wide range of algae developing in WSP depending on the type of pond, climate and
weather conditions the removal of algae can be difficult and inconsistent. Simple, low-cost options
can often be as effective as high-cost systems. This is to be kept in mind when considering more
advanced, technical treatment or removal options e.g. the storage and final disposal of algae or
algae and chemical sludge generated by some advanced removal processes can be difficult,
expensive and can create their own environmental issues, which should be investigated thoroughly
prior to implementation.
Table 3-1 Upgrade Options for Algal Solids
Use
Mechanism Upgrade Options Refer Sections
Pond Term
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 28
Table 3-2 Upgrade Options for Biomass Solids
Use
Mechanism Upgrade Options Refer Sections
Pond Term
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 29
Table 3-3 Upgrade Options for Large Inert Solids
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 30
Table 3-4 Upgrade Options against Surface Sludge on Facultative Ponds
Use
Mechanism Upgrade Options Refer Sections
Pond Term
3.2.5. BOD
Excessive BOD within a pond or at its discharge can relate to algae biomass, biological floc
(biomass solids) or dissolved BOD. This section addresses specifically the removal of dissolved
BOD. Algae and biomass related BOD can be addressed as described in the relevant sections 3.2.1
and 3.2.2.
Dissolved BOD issues can either be related to an excessive loading of the pond or inadequate
treatment capacity because of incorrect pond sizing, a gradual filling up of the pond with sludge or
severe short-circuiting. Generally the occurrence of excess dissolved BOD will be preceded or
happen at the same time as a range of other issues at the plant (e.g. odour, floating sludge). It
should initially be addressed through good O&M prior to investigating upgrade options.
Table 3-5 Upgrade Options for Dissolved BOD
Pond Term
3.2.6. AMMONIACAL-N
Excessive NH4-N concentrations at the inlet or within a pond can often be traced back to high inflow
NH4-N concentrations and therefore unusual discharges into the plant (e.g. industrial, portaloo, or
septic tank discharges). Such loads can have a severe impact on the pond’s health as high NH4-N
concentrations are toxic to algae, nitrifying bacteria and pond invertebrates, particularly at warmer
temperatures and high pond pH.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 31
High NH4-N concentrations at the pond outlet can either be the result of insufficient treatment or the
release of NH4-N during degradation of organic compounds within the pond. NH4-N is also released
within a few days of the pond algae population being grazed by invertebrates or treatment against
excessive algae growth causes the algae to settle and degrade on the pond bottom.
Traditional WSP have limited NH4-N treatment capacity with NH4-N reduction rates mainly
depending on assimilation into algae biomass which depends on sunlight, temperature and pond
HRT. These algae then settle to the pond bottom. NH4-N can sometimes be partly removed by
volatilization of NH3 (at high pond water pH and temperature with pond surface agitation) or by
nitrification to NO3. However, nitrifying bacteria are slow growing and prefer to be attached to
aerobic surfaces. Nitrification in facultative and maturation ponds can be augmented by the addition
of growth media and purpose-designed aeration which can reduce NH4-N levels down to 1mg/l.
Such systems do nevertheless represent a significant upgrade and have to be properly designed
and operated.
Table 3-6 Upgrade Options for Ammoniacal-N at the Inlet
Table 3-7 Upgrade Options for Ammoniacal-N within the Pond / at Outlet
Pond Term
Prevention Desludging F/(M) S/L 3.4.12, 4.4.7
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 32
nitrification has to be followed by denitrification of nitrate to nitrogen gas, which requires anoxic
conditions and available organic carbon.
Consistent total N removal down to low levels can only be achieved using traditional WSP at water
temperatures > 5 oC and HRT of > 20 days when they are augmented to promote both nitrification
and denitrification. This requires the addition of biofilm attachment surfaces to support a population
of nitrifying bacteria in aerobic surface water and denitrifying bacteria in anoxic deeper water.
Mechanical aeration is also required to maintain adequate dissolved oxygen levels for nitrification.
While denitrification can occur to some degree within facultative ponds it is most efficiently
achieved using a subsurface flow wetland or denitrification filter following the pond. These provide
more stable anoxic conditions compared with ponds, and provide both attachment surfaces for the
denitrifying bacteria as well as an organic carbon source.
Table 3-8 Upgrade Options for Total N
Treatment Refer to sections 3.2.1, 3.2.2 and 3.2.3 for treatment options
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 33
Mechanism Upgrade Options Use Refer Sections
Pond Term
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 34
Table 3-11 Upgrade Options for Bacteria and Viruses
3.2.10. ODOUR
Odour can be a serious nuisance issue for WSP and is one of the main reasons why ponds have
been discredited. Odour is nevertheless only the result of a malfunction of the plant. A correctly
designed and operated WSP rarely generates nuisance odour.
Odour generation tends to be limited to anaerobic and facultative ponds and is either related to
over- loading or to an upset within the treatment pond. The former includes excessive or
uncharacteristic influent loads (e.g. too hot, too low/high pH, too high conductivity). It also includes
an excessive loading of the inlet area, which may have filled up with solids (reducing HRT) or has
insufficient aeration. It can also be related to the under loading of an anaerobic pond, which is
unable to build up a stable crust.
Pond related issues include incorrect pond designs as well as seasonal issues such as pond turn-
over, seasonal DO deficiency or excessive sludge accumulation. Many of these issues can be linked
to poor operation and maintenance.
It is therefore important to first establish the exact location and true reason(s) for the odour
production and use this to initiate the best counter measures.
Odour nuisance can also be generated within maturation ponds when a cyanobacteria bloom
accumulates and dies.
Table 3-12 Upgrade Options for Odour Issues
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 35
Mechanism Upgrade Options Use Refer Sections
Pond Term
3.2.11. OTHER
Other parameters related to the raw influent as well as to the condition of the pond and its operation
and maintenance can also have an effect on the treatment quality.
Table 3-13 Upgrade Options for Other Issues
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 36
It reduces maintenance through the removal of larger solids, which would otherwise float on
the pond surface, settle on the embankments or obstruct overflow weirs.
It protects equipment installed within the pond such as aerators and mixers from jamming
and growth media and rock filters from clogging.
It improves the pond’s sludge quality so that it can be put to beneficial re-use in the future.
It can reduce the raw influent BOD5 loading by up to 5%.
Such improvements to the plant operation will come at some costs:
Screening incurs relatively high capital costs for the civil work, the screen and power and
wash water connections.
It increases operating costs; power, maintenance, screening collection and disposal.
The type, aperture and sizing of a screen depend on the level of protection and load removal to be
achieved. A screen for a pond system can range from the most basic manual 20mm bar screen to
an automated, fine 6mm diameter hole or 3mm wedgewire drum screen. A good screenings
washing and compaction system is always recommended to avoid odours and flies and to reduce
the volume of screenings to be disposed of. The screenings quantity (washed) can be estimated
using the general guideline of about 2–5 l/PE/yr for rough screens and 5–15 l/PE/yr for fine screens.
The quality of workmanship and material selection for a screen are both important for the longevity
of the screen; for larger, heavy, manual bar screens HDG steel or aluminum bars are acceptable.
Finer manual and all automatic screens should be made from at least SS304. Plastic screens should
only be used as secondary screens after a rough pre-screening. SS316 material is essential for all
installations near the sea or in case of a high industrial input (e.g. brine or similar) or after long rising
main discharges. Automated screens should always be fitted with an overflow and by-pass channel
integrating a correctly sized manual bar screen. These should be made from the same quality
material as the main screen.
Whatever screen type is being selected, it should not be undersized. In today’s competitive
environment some suppliers tend to size their screens for only the current flow to secure the
project. It is in fact recommended to oversize the screen, the by-pass screen and channel to be able
to cater for future flow increases. Screen selection shuld also consider the type and length of the
sewer network: small bore pressure systems with grinder pumps will generate different screenings
from long or very short gavity systems.
Screen types, costs and capacities should therefore always be compared using the screen’s clean
water throughput as well as the screen’s throughput using the same blinding factor and the
resulting amount of capacity reduction. The final selection should also take into account ease of
maintenance and the availability and costs of spare parts.
If the plant’s peak flow and infiltration are not fully known, or if high industrial loads or a short sewer
network can be expected, significant oversizing or provision for two parallel screens should be
envisaged to handle unexpected flows and potential blinding.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 37
Type Suggested Aperture Advantage Disadvantage
and Application
possible; screenings and flows. solids to pass (e.g.
Relatively immune against cotton wool buds,
medium to larger
grit and sand. some sanitary pads).
plants
Can pass 50% of
screenings.
Rotary inclined 6mm wedgewire For medium to deep Careful selection of
basket screen screen generally channels. Good capture screen brushing
sufficient; 3mm rate due to flow diversion. mechanism
wedgewire and 5mm Increased screening (and recommended due to
holes possible; BOD reduction). Smaller possible blinding
aperture screens only and/or need for
Small, medium and
recommended for special frequent replacement.
larger plants
applications due to Limited capacity to
significant increase in the deal with peak loads if
volume of screenings. Can not correctly sized.
remove 90% of
screenings.
Horizontal, 2mm, 3mm, 6mm, For shallow to medium Possible abrasion due
“Contrashear-type” 10mm wedgewire depth channels. Reliable to grit and sand. High
drum screen screen; concept with high oil and fat
screenings capture rate at concentration in raw
medium to larger
already larger apertures. influent can require
plants
hot water cleaning.
Vertical band screen 6mm, center-fed For medium to deep Sensitive to screenings
channels. Excellent type as only water
medium to large
screening performance cleaned.
plants with high peak
and for high flow variability
flows
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 38
Figure 3-3 Basket screen Figure 3-4 Drum Screen
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 39
Septage storage and slow injection within the pond’s treatment capacity.
Septage receiving stations should preferably provide:
An enclosed, odour-proof acceptance container, which allows a direct connection of the
septic tanker for gravity or in some cases, pressure discharges.
Sufficient treatment capacity to allow for the emptying of a tanker within minutes.
A rock trap for rocks and large stones.
A flow meter.
Anti-blockage, anti-overloading and auto-cleaning mechanisms.
A heavy-duty screen with a cutter-type cleaning mechanism and a screenings washing and
collection system.
A septage storage, dilution and dosing system for an extended, slow injection of the
septage into the pond over several hours or days.
An electronic recording system for the septic tanker identification, time of discharge and
volume discharged, which is linked to Council’s trade waste records and charging system.
An extensive number of septage systems are currently on the New Zealand market, and their
specific design, purpose and limitations should be understood so that the system is selected in line
with the plant’s requirements:
European and US “compact” septage systems provide good screening and a certain
amount of septage load dilution. They do not provide septage storage. Such systems can
rapidly be limited in their throughput capacity when confronted with old, thick sludge such
as typically found in New Zealand (ie septic tanks emptied every 20 years instead of every
5 years). The result can be lengthy discharge times (>20min per load) which lead to illegal
discharges elsewhere in the sewerage system to shorten truck journey times.
These systems were designed for mechanical treatment plants and do not reduce the
instantaneous high loading of the pond. So, for high loads or small plants they should be
fitted with a septage storage and dosing system after the initial screening.
Step screens, rotary drum screens and inclined basket screens with large apertures are
used in New Zealand as part of locally designed septage receiving stations in order to
avoid expensive compact units.
Experience has shown that such screens are acceptable, but that they have to be
oversized to deal with the compact and heavy New Zealand loads. They will be more
expensive to run because of their higher O&M requirements and they tend to have a
reduced life expectancy when compared with their application in raw effluent screening.
Septage storage and dosing is recommended for high loads and/or smaller ponds.
Alternative, site-specific low-cost septage receiving systems using manual or semi-manual
bar screens and a storage and dosing system can be developed locally as long as the
septic loads are well known and understood. Simple systems are prone to odour
production, clogging and cleaning issues if not correctly designed or maintained. Tanker
drivers should therefore be involved in the system’s design from the start and should
accept responsibility for its operation and maintenance.
Apart from screening and storage or direct discharge into a stabilisation pond there are also a
number of alternative options available, which are mainly used overseas and are slowly coming into
New Zealand. They include the use of Geobags or septage specific (anaerobic) ponds. These are
discussed in more detail in the section 3.3.4.
Grit and sand quantities in wastewater can vary widely between 20 and 200l per 1,000 m3 of
wastewater with an average of about 60l per 1000 m3. High quantities of such solids settling out in
the pond’s inlet area can lead to a reduction in treatment capacity in this crucial treatment area and
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 40
therefore an increased risk of odour. In such instances, a grit removal system can be justified to
avoid the need for a costly desludging of the pond.
Two parallel channels operating as duty/stand-by or a single channel / circular grit chamber
fitted with an automatic cleaning system, isolating gates and by-pass channel.
A grit classifier, a grit washing system and a storage bin for the clean grit.
Discussions about the positioning of a grit removal system in relation to the inlet screening system
are ongoing:
Its installation upstream of an inlet screen will protect the latter from abrasion and wear. Its
installation downstream of an inlet screen will prevent rags and heavy inorganics to settle
out in the grit chamber and contaminate the grit. Both issues can be avoided through
correct design. System positioning should preferentially be decided based on the
operator’s past experience with the quality and characteristics of the raw influent.
A grit system should not be used instead of or as a replacement for a septage receiving
system as it is not designed for such an application. Grit systems are also not
recommended if the plant receives regular septage discharges. In this case the
construction of a dedicated septage pond would be the preferred option because of the
systems’ overall lower O&M costs and added treatment benefits.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 41
They are most cost-effective if the final product can be re-used. Many re-use options
require pre- or post-screening, which increases the overall costs.
Design requirements for Imhoff Tank, Septage Pond and Geobag treatment:
Determine the final disposal path of the treated sludge (ie reuse or disposal).
Find a long-term partner for disposal or reuse.
Depending on the final usage, decide on the required pre-treatment (e.g. septage
screening) and if the origin of the septage may have to be restricted (e.g. heavy metals,
industrial loads).
Design the system for long-term operation and get the buy-in from the septic tanker drivers
and preferably also from the local community.
Set the septage charges in accordance with the long-term operation and maintenance of the
system.
3.3.4.3 GEOBAGS
Geobags can be used for direct septage sludge storage and treatment. They are more commonly
known for their use in pond desludging, but internationally they are also used for direct septage
treatment. In such applications Geobags are used in pairs with a one to two year rotation. Chemical
dosing (Alum) can be applied, but is generally avoided as it does not have the same benefits as for
pond desludging and can generate issues for the beneficial re-use of the sludge. During the resting
time the Geobag achieves good sludge decomposition and high disinfection rates resulting in a
readily reusable sludge.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 42
Addition of an Anaerobic pond as part of a WSP upgrade needs to take into account other aspects
of the upgrade, particularly with respect to the availability of organic carbon in the wastewater for
denitrification if nitrification is going to be promoted.
More details about their sizing, pond design as well as the design of inlet and outlet structures are
provided in Section 2.3
3.3.6. OTHER
WSP can be used for a wide range of effluent treatment as long as components of the raw influent
do not negatively affect the biological treatment process within the ponds. WSP will even adapt to
difficult raw influent characteristics (e.g. high salt content) if they are kept small and have minimum
variation. It is therefore possible to adapt WSP to a large variety of wastewaters by selecting specific
pre-treatment systems.
Pre-treatment options, which are considered too wastewater specific to be included in the previous
chapters include:
Pre-aeration
DAF treatment
Physical or chemical precipitation
pH adjustment and neutralization
Alkalinity adjustment
Heavy metals and/or chemicals adsorption
Hydrocarbon pre-treatment
Other, industrial influent-specific pre-treatments
Such pre-treatment options need to be selected and integrated into the overall WSP design on a
case-by-case basis to operate either on the main- or a side stream. Some of these are better
considered as pre-treatment at source prior to an individual discharge into the sewerage system.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 43
The Distribution Inlet
If the inflow to the plant is of a highly variable nature (e.g. gravity flow, VSD pump operation) the
opposite approach to the jetting inlet is often preferred. The distributing inlet first breaks the inflow
velocity by directing it towards a T section before the flow is divided into two streams, which are
then distributed over multiple outlets (generally two to four) over a wider area at the front of the
pond. This design tries to inhibit any sort of jetting effect and instead distributes the load over a
large surface area from the moment it enters the pond.
Care has to be taken with the design of a distribution inlet if the raw influent contains a high level of
heavy solid material, which could settle out within the distribution pipe due to the reduced flow
velocity. In this case the designer will either select a lesser number of discharge ports or will select a
jetting inlet design instead.
The choice of inlet design depends on the pond design, type of inflow (gravity, pumped), size of
pond, loading as well as the type and number of other flow directing devices to be installed. “Jetting
Inlets” are often combined with surface mixers and aerators (e.g. brush aerators) to further direct the
flow through the pond. “Distribution Inlets” are more frequently combined with sub-surface aeration,
which provides a high level of pre-aeration and mixing in the area over which the raw influent is
distributed.
Transfer works between ponds are preferably upgraded using the “distribution inlet”. This is
because the flow between ponds can vary widely and a “jetting inlet” would therefore not be able to
maintain a consistent flow pattern.
Whatever inlet design is adopted the raw influent should always be injected into the pond
sufficiently below the water surface to avoid any splashing. The inlet pipe should always remain
submerged even if the pond is operating with variable water level.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 44
It defines and controls the amount of designer-specified water level variations within the
pond.
It controls the discharge velocity from the pond and therefore it’s buffering capacity.
It provides a hydraulic separation between the pond and downstream process units.
An outlet structure should therefore present at least four control elements:
An outside baffle to retain floatables and to ensure that the effluent is only withdrawn at a
specific depth below the water surface (except Maturation Ponds).
An overflow weir, which can be flat, V-crested or be fitted with a purpose-designed narrow
gap control section for level and flow control.
Weirs should include a replaceable discharge section to allow adjustment for possible flow
changes in the future
Weirs should be fitted with a device which allows the outflow to be completely stopped.
A collection chamber, which hydraulically separates the pond from the discharge pipe (see
below).
An adequately sized discharge pipe.
Outlet structures can further be fitted with a manual fine screen if downstream treatment units need
to be protected from potential discharges of debris or wildlife such as eels or ducks. Such screens
can either be integrated into the discharge structure itself or they can be installed into a dedicated
discharge manhole located outside of the pond.
Generally a pond is fitted with a single outlet structure, representing a single point of discharge. For
shallow, wide ponds where a single point of discharge could have a significant and negative impact
on the flow pattern and treatment capacity of the pond, an outlet manifold structure fitted with
multiple baffles and overflow weirs is preferred as it will provide a significantly improved flow within
the pond and reduce the potential for short-circuiting.
The weir itself should always remain the sole element of level and flow control and should not be
obstructed or influenced through the installation of any upstream pipe, screen or similar elements.
To enable the weir to remain the controlling element it is important that it hydraulically separates the
pond from the discharge pipe itself. The discharge pipe should therefore be located at the bottom
of an effluent collection chamber which has sufficient volume and internal height to cater for any
water level variations due to head loss in the discharge pipe.
The weir and its baffle design must take into account the location within and size of the pond in
which it will be installed as well as prevailing wind/wave action, uplift forces, and extreme flow
conditions. They are generally made from stainless steel (SS304 or SS316 depending on the
location of the plant) and some elements may be made from concrete, aluminum, GRP or plastic
materials. The choice of material and design for any removable section (i.e. control weir element or
gate) must ensure that they can be easily removed or adjusted in all temperature conditions, even if
solids clog the guide rails. Outlet structures also have to be easily and safely accessible by the
operator for verification and maintenance purposes.
Figure 3-7 Flow Control Weir Figure 3-8 Level Control Weir
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 45
Outlet structures must be designed in accordance with the specific requirements of the type of WSP
they are installed in:
Anaerobic pond weir designs depend on whether they have a crust or impermeable cover.
Anaerobic ponds with a crust require a weir which will only allow a limited amount of water
level variation in order to prevent breaking-up the pond’s crust. The outlet structure should
have a baffle, which reaches sufficiently above the water surface to retain the crust. It
should also reach sufficiently below the water surface to ensure that the bottom of the
crust is not entrained: The baffle should therefore extend between 200 to 400 mm above
and about 400mm or more below the water level.
Covered anaerobic ponds should not have an outlet structure at the pond surface as it will
interfere with the pond cover. An outlet manifold with several horizontal openings should
be place at ~500 mm below the pond surface to avoid entrainment of floating solids.
Facultative pond weir designs require a baffle so that the algae in the surface layer of the
pond are not removed with the treated effluent. The baffle is also required to protect the
weir from wave action, and therefore should extend about 600+mm below the minimum
operating water level and 200mm or more above the maximum water level. Larger ponds
with potential for higher waves require higher baffles.
The space between the baffle and the weir is used for flow velocity control to ensure minimum
discharge of any settleable and minimum preferential flow of suspended solids and is therefore
an important design factor of the outlet design.
The weir design will pre-determine the operating conditions of the facultative pond during low,
normal and peak flow conditions. It can be designed to control the discharge flow velocity and
can create buffer storage or maintain a constant water level. It will also determine the maximum
allowed water level in the pond in case of an emergency.
As a result, a weir for a facultative pond can combine a flat crested weir, a narrow gap weir, a
certain type of V-notch weir or more sophisticated weir slots depending on the specific pond
operating conditions the designer wants to achieve.
Maturation pond weir designs should not have a baffle to ensure that the most highly
disinfected surface water is discharged from the pond and floating blue/green algae do
not accumulate in the pond and cause blooms. Any large floatables can be prevented from
being discharged by using a screen. Maturation pond weirs are therefore generally flat
crested or shallow V-notch weirs
The weir design for a maturation pond will not generally be used to control the discharge
flow such as on facultative ponds. That is, unless the system’s Resource Consent limits the
maximum daily discharge. In this case the need for a maximum flow buffer capacity may
require the use of a narrow gap weir or similar.
A separate category is represented by floating weir structures. These can be used on facultative as
well as maturation ponds. Their baffles are designed for effluent withdrawal at optimal depth at or
below the water surface and the weir is generally a flat crested or shallow V-Notch weir. Flow
discharge will be constant or can be controlled by varying the buoyancy control or using a control
valve located in a manhole outside the pond.
Floating weir structures have the advantage of optimal effluent withdrawal with high accuracy of
flow and level control over a wide range of flow conditions. Their disadvantages are their high costs,
relative high level of sophistication and the reliance on power and control equipment for more
sophisticated options.
For any of these outlet structures it is important that the weir length is sufficiently long that the
approach velocity within the pond (i.e. around the outer baffle) and close to the weir (i.e. between
baffle and weir) remains sufficiently low to avoid solids capture. Simple, straight outlet pipes, even if
followed by a weir arrangement outside the pond, should therefore be avoided.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 46
3.4.3. FLOW DIRECTION DEVICES
Traditional ponds present an uninterrupted water surface with an inlet at one end and the outlet at
the other. Flow conditions and treatment quality in such ponds are highly variable due to multiple
factors listed previously.
In modern ponds the flow is directed through a defined flow path in order to reduce this variation.
Flow directing devices are one way of ensuring that the flow of the wastewater through the pond is
optimised.
Flow directing devices can be divided into two main categories:
Active flow directing devices include aerators and mixers. They use electricity to create
directional flow or mixing, which impacts on the flow direction and velocity of the
wastewater through the pond. These devices are discussed in more detail in section 3.4.4.
Passive flow directing devices include baffles, rock groynes and floating curtains. They are
used to divide ponds, redirect the flow or to create a defined flow path through a pond.
Such devices are generally permanent installations and their design, strength and material
selection has to take into account their long-term maintenance and resistance to seasonal
weather conditions. These devices are discussed in this section.
A number of passive flow directing devices are available for the use in pond upgrades. The
selection of the type of device, its placement and its design depend on the type of pond in
which it is to be used, the site ground conditions, what is to be achieved and the available
budget.
The use of passive flow directing devices is normally limited to their use in facultative or
maturation ponds. Their use in anaerobic ponds is rare and not recommended unless they are
used to subdivide an over-sized anaerobic pond into two parallel ponds. Because of the
different goals behind subdividing ponds this upgrade technology is discussed in its own
section 3.4.6.
Flow directing devices can achieve a number of benefits for pond treatment:
Stub-baffles (Figure 2-4) can be used to detach jetted flows (refer 3.4.1) from the
embankment and direct them into the pond.
Stub- baffles can be used to protect a pond outlet from short-circuiting around the outside
of the pond.
Longer walls or floating baffle curtains can be used to create a defined flow path through a
pond along which different treatment stages can be achieved.
Longer baffles help reduce wave height by breaking up long ponds into smaller narrow
sections.
Baffles can reduce short-circuiting as well as dead zones and increase actual HRT.
Baffles reduce the impact of changing wind direction on treatment.
However, passive flow directing devices can also have some negative impacts on pond
performance:
They can retain or accumulate floating matter.
They can reduce the pond’s capacity (i.e. wide rock walls).
They can make desludging more difficult.
They could potentially lead to localised overloading due to smaller more defined treatment
areas, especially around the inlet.
There is an optimal amount of baffling within a pond, beyond which there is no additional
benefit, because of the increase in dead zones.
A number of parameters should be taken into account when selecting and designing passive flow
directing devices:
The design, type of device and material to be used need to be selected based on pond
size, depth, site conditions and treatment goal to be achieved.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 47
Site conditions (weather, wind, earthquake prone), site access for installation and the
device’s required life expectancy.
The pond depth, sludge depth, sub-base condition and strength in the proposed location(s)
of installation have to be known together with the expected variation in water level.
Desludging of the entire pond or at least along the line of installation is recommended if
the sludge layer exceeds 200mm. Installation into ponds with a deeper sludge layer is
possible but not recommended. It carries the risks of incorrect design, difficulties for
installation and alignment and an ultimately poor overall performance.
Materials used, including any liners, anchoring posts, gabion material, cables, shackles and
weights, should be corrosion and UV resistant and able to resist the strong forces from
wind and waves.
Figure 3-9 Old Fibre Cement Figure 3-10 Concrete Wall Figure 3-11 Concrete
Wall segments
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 48
3.4.3.3 FLOATING CURTAINS
Floating curtains can be used in smaller ponds (approximately 2ha) to create barriers to provide a
defined flow path and reduce short-circuiting even at times of high wind and wave action. In larger
ponds, especially in coastal locations, the wind and wave forces can damage curtain type and other
barriers, such as rigid sheeting on posts.
Floating curtains have to be designed to a high standard with respect to the material used, their
anchoring system and their connection to the embankment. Sealing at the base can be difficult if the
base is uneven (see later).
Research has shown that curtains of about 70% the width of a pond are most effective for creating a
flow path through a pond. The effectiveness of curtain addition on pond improved treatment
performance increases with typically up to three curtains.
Floating curtains should be made from a strong impermeable material such as HDPE or FPP of
about 0.75 to 1.5mm thickness. PVC is generally to be avoided as its life expectancy can be reduced
in New Zealand’s high UV environment. The type of material selected depends partly on the
application; for a pond operating with a constant water level a more rigid HDPE curtain is possible,
for a pond with a changing water level a more flexible FPP material is preferred.
Figure 3-12 Rock Groynes Figure 3-13 Floating PE Curtain Figure 3-14 Poor Quality
Curtain
Composite materials (i.e. fibre reinforced liners or tarpaulin material) should be avoided as the thin
cover membrane is prone to abrasion and the underlying reinforcing material is generally not UV
resistant. A combination of materials for above and below the UV impacted area is possible (i.e.
generally above water to 600mm below water), but rarely financially advantageous.
The curtain floats should be both strong and light. They can consist of marine grade polystyrene
blocks enclosed and sealed into individual liner capsules. Other floats may be made from PE pipe or
PVC tubing. The latter should be limited to heavy duty PVC (i.e. pressure pipe PVC, not electric
ducting). The pipe ends should be permanently sealed with glue-on caps. To extend their life
expectancy floats are preferably filled with marine grade polystyrene or a similar light, hydrophobic
material to keep them afloat, even if their glued-on end seals fails.
The use of larger diameter floats (i.e. 200mm or even 250mm diameter versus 100mm) has
advantages as they present a stronger barrier against wave action and will therefore be more
effective against short circuiting over the baffle even in windy conditions. Since larger floats present
a greater obstacle to wind and waves they require a stronger anchoring system for the baffle.
Floating curtains should be fitted with a heavy chain at their base to hold them in position and to
form a seal with the pond base. The chain should be hot dip galvanized and preferably enclosed
and sealed within the curtain material. In order to achieve a good barrier, the curtain has to reach
and seal with the pond base along its whole length. It is therefore imperative that a survey of the
pond depth is undertaken along the potential position of a new curtain. Depth measurements
should be made at about 1.0m intervals so that any changes in depth can be incorporated during
manufacture of the curtain.
Floating curtains can be used in ponds operating at a constant water level or with a variable water
level. The sophistication of curtain design varies significantly between the two. Curtains operating
with a constant water level can be sized according to the pond base variation and the specified
water level. They can be made from more rigid material (i.e. HDPE), can have minimum slack and
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 49
can sit relatively straight in the water column. During strong winds or storms such curtains remain in
position as long as the anchoring chain and anchors remain in place.
Curtains operating with a variable water level have to be designed to prevent excess curtain
material from floating loosely or being captured by the wind when the pond operates at low level. In
storm conditions such spare material is at risk from wind damage. Variable level curtains therefore
need to be made from more flexible material (e.g. FPP) and are preferably fitted with an intermediate
ballast chain, which holds down and straightens the spare material at times of low water level.
If the curtain has ever to be shifted within the pond, dedicated lifting ropes should be attached to
the chain and floats at regular short distances during construction. Otherwise the weight of the
chain and the effect of the chain sinking into the pond base or sludge will make lifting the chain off
the bottom too difficult. The position of a curtain is therefore permanent, unless the curtain is
inadequately designed and shifts during strong wind conditions (e.g. too much material, inadequate
anchoring).
In the past, long curtains had to be joined at regular distances with mechanical joining pieces, which
created sealing issues. Today pre-fabricated sections of a long curtain can be welded together on
site, which allows for strong continuous barriers. The whole curtain can then be floated into
position, anchored and then deployed.
Curtains have been installed in ponds with sludge levels up to 600mm. This is done by “jetting” the
curtain into the sludge layer. This practice is not recommended and considered shortsighted.
Installing curtains into a pond with significant sludge accumulation carries the risk of the curtain
moving due to the weight of sludge and makes desludging after installation much more difficult. As
a general rule, regular pond desludging remains best O&M practice and should be considered as a
first step towards improving pond performance.
One of the more difficult aspects of a curtain design is effective sealing with the pond embankment
and most incidences of short-circuiting with curtains occur here. If the embankment consists of rock
riprap a reinforced section of the curtain can be permanently embedded into the riprap. If the
embankment has a concrete or liner waveband the sealing between the embankment and the
curtain needs careful consideration and design. The curtain should continue as far as possible up to
the top of the embankment or at least 300mm above the maximum water level. The attachment of
the curtain should be sufficiently low above the top of the embankment to avoid lifting the curtain
out of the water and creating a ‘sail’ area for the wind to catch on. It should also be sufficiently high
so that the stainless cable or rope does not damage the embankment material or wear out over
time.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 50
Type Application Comments
Not recommended for facultative & maturation ponds
Inclined shaft Limited application in Good aeration and mixing efficiency and flow directing
aerator facultative ponds, properties. But originally designed for deep ponds (>
with depths > 1.5m. 2m). Can be adjusted for shallow ponds but with a
significant drop in efficiency.
Anti-erosion plates
Prone to high O&M needs in ponds with no current or
recommended in
past screening due to frequent clogging of impeller.
clay-lined ponds.
Relatively high power requirement vs. aeration efficiency
in shallow ponds.
Recommended for deeper areas of facultative ponds
Brush aerator Traditional aerator Good mixing and aeration in shallow ponds (<1.2m). For
for facultative and deeper ponds (< 2m) limited aeration capacity, but still
maturation ponds good flow-directing properties and mixing of pond strata
in area of influence.
Relatively high capital costs compared with aeration
efficiency and O&M requirements vary significantly
depending on manufacturer.
Recommended for shallow ponds and where flow-
directing properties are the main focus.
Air induced Facultative ponds, Device with good aeration & mixing properties and good
mixer for high mixing and long-distance flow directing properties.
Type A aeration applications Needs to be installed close to the embankment because
(NZ made) blowers are installed outside of the pond.
Aerator design and blower capacity need to be
specifically adapted by manufacturer to each particular
application.
Relatively low capital costs and O&M requirements, but
with higher running (power) costs.
Recommended for facultative ponds (< 2m) in areas
where high mixing and turbulent aeration is of benefit.
Air induced Facultative and Excellent aeration, slow mixing and good flow-directing
mixer maturation ponds, properties with low power consumption.
Type B for slow mixing and Can be installed in all locations within a pond due to its
(US made) gentle aeration on-board blowers.
Exists in two versions, aluminum and SS. Latter is to be
used for any application anywhere close to the sea.
Medium level capital costs, low O&M and low running
(power) costs.
Recommended for facultative and maturation ponds for
all applications, which do not specifically require
turbulent mixing.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 51
Figure 3-15 Brush Aerator Figure 3-16 Air induced Mixer Type A
Figure 3-17 Inclined Shaft Aerator Figure 3-18 Air Induced Mixer Type B
Typical situations in which aerators can be successfully used to achieve improvements in pond
performance include:
In the pond inlet area for odour control, in case of an increase in loading and/or to disperse
the load (and sludge) rapidly over a wider pond area.
For oxygen supplementation during day, or during night-time to prevent a possible pond
crash due to low oxygen concentration.
During a change of seasons to prevent pond stratification and pond turnover.
In specific locations within the pond to prevent dead zones or to create back mixing and
circular mixing zones.
A few aerator types can positively contribute to the aerobic digestion of organic bottom
sludge through a combination of aeration and mixing. This arrangement must recognise the
increased oxygen demand from the re-suspended solids and the influence they may have
on algal health.
Aeration can help improve the pond’s discharge quality. But a lack of artificial aeration may
not be the reason for a non-compliance of a pond system. The operator should understand
the underlying causes for non-compliance first.
The positioning of an aerator and the amount of turbulence it generates should be carefully
considered at the time of selection. If an aerator/mixer with high turbulence is suited for installation
towards the inlet of a pond and in areas with high sludge accumulation, an aerator with
predominantly flow-directing properties will be better suited to prevent dead zones and for flow-
directing. Less turbulence should be preferred towards a pond outlet or where surface mixing or
flow direction is the dominant requirement.
Aerators are mostly installed in facultative ponds to address overloading, odours or sludge
accumulation, but aerators can equally achieve effluent improvements when installed in maturation
ponds. The disinfection properties of higher oxygen concentrations in ponds, as well as the
difficulties for algae to develop significantly in continuously mixed environments, are both factors for
which certain aerators can be used successfully. Aerators for maturation ponds would therefore be
those with slow mixing rates, but good oxygen input.
Both the capital and operational costs of an aerator should be considered prior to purchase. While
there may be a capital budget constraint, the total cost may be less for a more expensive aerator
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 52
with greater efficiency running long hours. The combined capital, maintenance and power costs of
one type of aerator can often render an initially more expensive aerator more attractive within a few
years of operation than a cheaper one.
The addition of any aerator to a pond will have an impact on the O&M requirements of the plant,
through the need for motor, bearing and general maintenance, but especially for its need for regular
cleaning. The latter will be required more often if the pond is not or was never fitted with a raw
influent screening device, or has never been desludged even though a screen has been installed.
The aspects of accessibility for servicing and ease of cleaning and/or ease of removal should all be
considered carefully at the time of aerator selection.
Damage to a pond as a consequence of the installation of an aerator can be easily avoided if
adequate steps have been taken at the time of selection. Ponds with artificial liners require forward
thinking and great care during aerator installation, placement and anchorage. Anchoring posts
should be strong, correctly placed and anchor cables adequately sized and correctly fitted.
Continuous movement by the aerator as well as wind and wave action can, over time, dislodge and
pull simple steel stakes from the ground resulting in significant liner damage and/or a sinking
aerator.
Table 3-16 Passive Aeration Devices for Facultative and Maturation Ponds
Draught Used overseas for mixing Can be implemented in small and wider areas.
Tube and aeration in facultative Increases in efficiency with increase in depth.
Aeration ponds High air output and high power use.
Only use for spot aeration/mixing in ponds with well-
screened effluent to avoid clogging.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 53
3.4.6. SUBDIVIDING PONDS
Mara et al have found that the use of multiple ponds of the same combined surface area of a single
large pond can improve the overall treatment quality of a pond system. Subdividing an oversized
single pond to achieve higher quality treatment is therefore a realistic upgrade strategy.
A real improvement in effluent quality relies on the rigorous division of one large reactor basin into
multiple, fully separated smaller basins in which the inflow and outflow as well as the overall pond
hydraulics can be much better controlled. Significant improvements will therefore only be possible
through full separation with embankments, new inlet and outlet structures and possibly
mixers/aerators to create defined flow patterns in each new pond.
Such an upgrade has significant investment costs, as well as the loss of some reactor volume
through the construction of new embankments within the existing pond. Successful examples are in
larger ponds at Blenheim, Nelson North, Queenstown, Greytown, Geraldine and Temuka. The
installation of permanent dividing walls (e.g. sheet piling, concrete posts with pre-cast concrete
panels) is an alternative for smaller ponds, but may not be less expensive.
A more economical option for smaller ponds is the division by floating curtains. The separation by
curtains will never be as effective as a division by solid earth banks or walls, as curtains will always
allow a certain amount of bypass and return flows. Also, curtains may not be suitable for larger
ponds because of the excessive forces generated by wind and waves (refer also section 3.4.3.3). A
well-designed curtain may not achieve the full treatment quality improvements of a solid wall
division. Floating curtains in smaller ponds can nevertheless be applied successfully to achieve
improvement:
A continuous curtain wall can retain floating solids and protect downstream treatment
equipment (e.g. aerators, growth media etc.).
Multiple curtain walls can be used to create individual treatment zones with different
process characteristics (e.g. high aeration zone, algae settling zone, facultative/maturation
zones).
By increasing the number of curtains their overall effectiveness can be increased.
To achieve maximum effectiveness, floating curtain walls have to be carefully designed and have to
be of a high quality in respect to material used, their fitting within the pond and their sealing on the
embankments. Material selection (fully impermeable or partially impermeable) should be adapted to
the goal to be achieved. Transfer openings should be adapted in size and position to the
characteristics of the effluent to be transferred to the next zone (e.g. opening located below the
algae level for facultative ponds).
With floating separation walls the designer should keep in mind that pond division will only be
partially achieve, even by using multiple curtains. The inlet and outlet of a pond should remain as far
from each other as possible and be separated with as many curtains as possible to achieve best
overall results.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 54
Systems specifically targeting Nitrification therefore need to accurately determine the surface area
required for their amount of nitrification, the need for this to be replenished by turbulent mixing and
to provide the necessary aeration requirements.
By shifting the WSP from an algae and suspended biomass based process to an artificially aerated
and attached biomass process the dependence on sunlight and wind mixing is significantly
reduced. The amount of growth media and aeration is determined according to loading,
temperature range, HRT and the treatment standard to be achieved. The operator is then able to
take control of the process by adjusting and optimizing the amount and location of aeration and
mixing according to treatment requirements and seasonal changes.
Figure 3-19 Curtain Growth Media Figure 3-20 Cellular Growth Media
Growth media exists for installations into shallow (1.2m) as well as into deeper ponds (i.e. 3.0m).
Although it can – theoretically – increase a pond capacity up to 10 times, a growth media system
design requires the involvement of a specialist. Its sizing has to take into account the pond
hydraulics, pond depth, pond base horizontality, HRT as well as multiple wastewater and
environmental parameters. Also, the resulting system will only be able to achieve its design
discharge quality if it is based on a comprehensive set of data. It is therefore important that the
operator knows his plant well and has collected representative data over a sufficiently long time.
Growth media upgrades can allow a pond system to achieve treatment standards equal to those
achieved by an activated sludge or SBR plant. The sludge production of a pond system retrofitted
with growth media will not noticeably increase compared to its pre-upgrade due to the slow growth
of attached biomass as well as the sludge digestion effect of the permanent aeration.
A growth media plant upgrade as an advanced stage pond upgrade should only be implemented
once inlet, outlet, screening and hydraulic optimization has taken place. Overall costs for an
upgrade of a pond using growth media can vary between 30% and 100% of those of an activated
sludge plant depending on the available infrastructure. The significant cost savings will therefore
often only show during operation with about 20% to 50% of those of a mechanical plant. Growth
media upgrades also have the added advantage of maintaining simplicity of operation and
operators need not be trained to the same level of process knowledge as for an activated sludge or
similar mechanical plant.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 55
Figure 3-21 Inadequate Media Type A Figure 3-22 Inadequate Media Type B
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 56
Floating wetlands have a lot in common with artificial growth media (refer 3.4.7); they significantly
increase the amount of biomass and general bioactivity, which directly impacts on the pond area
beneath and close to them. Floating wetlands can therefore, in certain circumstances, achieve
significant nutrient and solids removal rates. Their efficiency depends on a good hydraulic flow
pattern, an adequate loading rate per square meter and sufficient oxygen in the pond water.
As with artificial growth media, the installation of floating wetlands should only be considered once
all basic upgrade steps, including pond desludging have been implemented. Floating wetlands can
be used for a wide range of applications and it is important to establish what their true purpose will
be and their compatibility with the pond in question before even considering design and sizing
options e.g.:
Are the floating wetlands installed to replace an existing, traditional, failed wetland?
Is this new floating wetland installed to satisfy cultural requirements?
Will the floating wetland be used as a solids retainer only (e.g. at the outlet of a facultative or
a maturation pond)?
Will they also have to achieve nutrient removal? What kind? How much?
What loading rate can a wetland raft accept with and without dedicated aeration?
How can the maximum loading rate per raft be maintained?
Could existing pond conditions impact on their treatment (i.e. sludge accumulation) and have
these to be addressed first?
How easily are the rafts accessible and stable for plant cutting and general maintenance?
Who will maintain them?
Is there a plan for pond desludging in future?
Figure 3-23 Floating Wetland (new) Figure 3-24 Anaerobic Pond Cover
Floating wetlands are not a treatment solution for all ponds and will not solve all pond problems.
While a number of floating wetland installations in New Zealand have shown good nutrient removal
results, an equal number of plants have shown that overly optimistic design or treatment quality
assumptions can lead to substandard results and non-compliance. Failure to adequately prepare the
plant (e.g. not desludging prior to installation) has also led to failures to perform and even to a
deterioration of effluent quality.
The potential range of applications of floating wetlands is much wider than for traditional wetlands.
They are more compact and allow access for maintenance and plant replacement independently of
the water level. However, their capital investment costs are high and maintenance costs are
relatively high.
Floating wetlands should be considered as one upgrade option out of many. A close collaboration
between experienced designers, operators and suppliers will establish the number of rafts required
and their positioning. When considering floating wetlands one should keep in mind the possibility of
a phased upgrade approach, which allows confirmed treatment improvements in increments and to
optimize the cost-benefit balance of an installation.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 57
anaerobic ponds, where the main focus is odour prevention and for facultative and maturation
ponds where the main focus is suspended solids and algae reduction.
Floating covers for anaerobic ponds can be divided into two categories:
Fully impermeable floating covers which seal the whole pond and are used for odour and
greenhouse gas emission prevention and for biogas collection.
Floating, permeable, natural or artificial covers which are only used to prevent odours.
Fully impermeable covers for anaerobic ponds are not considered an upgrade option and are
therefore not discussed here.
Floating, permeable, natural covers (crusts) on anaerobic ponds form by themselves if the pond is
fed with sufficiently concentrated loads of floatable material. Such natural covers/crusts provide an
effective means of preventing odour nuisance from anaerobic ponds. They also reduce wave action
and therefore also protect the pond embankments and provide some thermal insulation to the
pond. While all anaerobic ponds should be fenced off for health and safety purposes, this is
particularly important for those with natural covers as they can easily be mistaken for a meadow.
Floating, permeable artificial covers are not recommended for anaerobic ponds unless the water
surface under the cover remains clear at all times, i.e. without floating sludge, solids or oil and
grease. This is generally only achieved on some selective industrial plants and even in such special
conditions the risks remain that the cover clogs over time or does not resist New Zealand’s high UV
exposure. The use of permeable artificial covers on anaerobic ponds on municipal plants is also not
recommended because of the extremely high failure rate of such installations in the past and the
resulting high costs, environmental and health and safety issues related to their removal. If a new
type of cover were to be developed an in-depth due diligence should be undertaken before
selection.
Floating wetlands on anaerobic ponds could potentially present an alternative to purely natural
covers for those applications where the load and oil and grease content of the wastewater is
insufficient or wind or climate conditions are such that a natural cover does not develop. To date
there are very limited examples for such installations and some have failed, and therefore
insufficient data is available on their long-term operation and maintenance. There is also no
information available on the long-term effect of the anaerobic pond water on the root growth of
wetland plants and the impact of the plant roots on treatment. Considering the lack of information
available on the benefits and drawbacks of floating wetland covers for anaerobic ponds, particularly
long-term operation experience, and the high installation costs (higher than impermeable covers),
their use is considered high risk.
Pond covers for facultative and maturation ponds provide an option to reduce algal biomass, the
associated BOD5 and TSS in a pond discharge through algal settling by eliminating light and
reducing wind mixing. Use is consequently focused on the discharge end of a pond. For maximum
algae elimination the covered volume has to have a hydraulic residence time of at least 4 days.
Care has to be taken in respect to the selection of material used as a pond cover. Materials used
range from individual small floats (e.g. hand-size hexagon shaped floats, black, hollow PE balls) to
specially designed and manufactured continuous floating covers. This equipment is mostly
manufactured overseas and has to be imported at significant capital cost.
In-pond rock filters for facultative and maturation ponds present an alternative to artificial pond
covers as they also eliminate light within the filter. Rock filters have the added advantage in that
they will grow biomass on the rocks, which will bind algae and floating biomass. They act as artificial
growth media and can assist with nitrification and especially denitrification.
The type of material used has an influence on the effluent treatment (e.g. Lime rock will provide
extra alkalinity). It is important that rock filters are constructed using sufficiently large rocks (100 to
250mm diameter) with minimum undersized material. Otherwise the openings can clog up over time
and/or the rock filter will rapidly develop anaerobic conditions.
Neither floating covers nor rock filters should be installed in areas of a pond that are treating high
organic loads or that are not desludged. The result can have multiple detrimental consequences
such as cover or filter clogging as well as the establishment of anaerobic conditions, effluent
deterioration and the generation of odour.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 58
3.4.10. CHEMICAL DOSING
Chemical dosing can be used in waste stabilization ponds for a number of short-term emergency
situations and for longer term treatment. Short-term applications include:
Short-term chemical oxygen supplementation.
Short-term action after a pond crash.
Short-term treatment to tackle excessive algae growth.
These situations are considered to fall under O&M rather than representing a treatment upgrade.
They are therefore discussed in Section 4 of the guidelines.
The chemical dosing implemented to achieve longer-term treatment improvements and which fall
therefore under WSP upgrades include:
Chemical dosing for alkalinity adjustment
Chemical dosing for total phosphorus reduction.
Chemical Comments
Advantage Disadvantage
Hydrated Lime / Calcium Hydroxide Relatively cheap, available. Not easy to handle (Read
[ Ca(OH)2 ]/ Slaked Lime product H&S sheet).
Limited solubility. Used as a
slurry, which needs to be
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 59
Chemical Comments
Advantage Disadvantage
kept constantly in motion
otherwise it will settle and
will clog pipework rapidly.
Can raise the pH above
pH7 if overdosed.
Caustic Soda / Sodium Hydroxide [NaOH] Fast-acting. Easier dosing Easy to overdose and end
than with solid agents. up with pH 9+. More
hazardous than other
agents.
Quicklime/Calcium Oxide [ CaO ] Cheaper than hydrated lime. Not easy to handle (Read
product H&S sheet). Highly
irritating dust. More
impurity than hydrated lime.
Can raise pH above pH7 if
overdosed.
Limestone [CaCO3 ] Cheapest. Will not raise pH Highly insoluble so slow to
above pH7 when react. Will sink to the
overdosing. bottom, where it will not
Can be used for long-term, contact the main body of
slow release. water.
Soda Ash / Sodium Carbonate [Na2CO3] Cheap and fast-acting. Can raise pH over pH7 if
seriously overdosed.
Sodium Bicarbonate [NaHCO3] Relatively easy to handle. More expensive: needs
Will not raise pH above pH7 60% by mass more than
when overdosing. Readily soda ash for equivalent
available. Fast acting. chemical effect.
Table
provided by Julian Glen of Prolyze Ltd, Auckland
For longer-term alkalinity adjustment the raw influent composition as well as the reason for a pH
drop should be investigated in detail. The selection of the chemical to be used should be based on
process considerations and health and safety issues as well as chemical and implementation costs
and any extra O&M procedures and costs, which could be generated by the product and/or its
implementation.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 60
increase back up slowly over time. A treatment plant with 80 days HRT will only need one such
treatment every 3 to 5 months.
In New Zealand, ferric dosing is generally implemented on an on-going basis, i.e. a small contact
tank is installed upstream or between two ponds and the resulting ferric phosphate settles out in the
pond with the sludge. Ferric phosphate is a stable compound and will not dissolve unless the pH of
the pond drops below pH5, which is unlikely in a normally operating pond system. Long-term the
ferric phosphate can be removed when the pond is desludged.
TP reduction for Resource Consent purposes can be optimized by ferric injection at the end of the
treatment process. In this instance chemical dosing can be implemented post-pond discharge in a
separate small reactor if the operator feels uncomfortable with dosing directly into the pond. Dosing
at the end of the process will allow a more accurate dosing to target the exact amount of residual
TP required. It will allow a reduction in dosing rate, as some TP will already have been taken up by
the biological process upstream. The amount of ferric phosphate generated will therefore be less.
Post-pond treatment is also useful if only seasonal TP reduction is required.
3.4.12.1 THEORY
Many naturally occurring bacteria have the capability to excrete enzymes outside of the cell into the
wastewater (exoenzymes). These enzymes hydrolyse colloidal and particulate organic material into
simple, soluble material that can be taken up by the bacteria and broken down to inorganic
compounds. In this process, a fraction of the organic material (10% to 40%) is converted into new
biomass, and the remainder is converted to CO2 NH4-N, DRP and water, thus causing a net
reduction in total sludge.
The rate of hydrolysis of colloidal and particulate organic substrate significantly influences the rate
of sludge accumulation or digestion. The rate of hydrolysis can be increased through
physical/chemical methods or by Enhanced Microbial Digestion.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 61
3.4.12.2 ENHANCED SLUDGE DIGESTION THROUGH PHYSICAL –
CHEMICAL MEANS
Sludge digestion is increased by reducing the average size of sludge particles by methods
including:
• Maceration. Maceration physically chops, grinds, or blends sludge into smaller particles.
• Chemical addition. Chemical addition uses acids or bases such as sodium hydroxide
(NaOH), ammonia hydroxide (NH4OH), and sulphuric acid (H2SO4) to promote hydrolysis of the
wastewater
• Thermal Hydrolysis. Thermal hydrolysis is achieved by heating the wastewater to 100-200
o
C for 30-120 minutes.
• Sonication. Sonication is the application of ultrasound waves to sludge for a period of time.
Research has shown that each of these methods converts colloids and particulate substrate into
soluble substrate at varying efficiencies, and that this conversion improves overall sludge digestion.
However, while these methods are helpful in operations such as anaerobic digesters, their use is
not generally practical in WSP.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 62
3.4.12.6 PRACTICAL CONSIDERATIONS FOR ENHANCED MICROBIAL
DIGESTION
All of the following are important when evaluating the possible use of Enhanced Microbial Digestion
to reduce accumulated sludge in the WSP
Sludge solids concentration and volume. Any use of Enhanced Microbial Digestion will
require knowing the wet sludge volume and dry solids concentrations in the WSP prior to
application. Accurately measuring the sludge volume and solids concentration during the
course of application is essential to ensuring measurable treatment success (see section
4.2.10). As Enhanced Microbial Digestion progresses and organic solids are consumed in
the upper more biologically active sludges, the lower compacted solids will begin to
hydrate and increase in volume until equilibrium in solids concentration is reached
throughout the sludge column. This can be monitored as a progress indicator during the
first phases of treatment. The initial reduction in solids concentrations can equate to the
removal of significant quantities of material while the overall sludge volume may not have
reduced by much.
Safety. Whether using an enzyme product or mixed bacterial cultures or a combination of
both, the safety of applicators and compliance with New Zealand and local laws with
respect to biosecurity are essential. All users of Enhanced Microbial Digestion should
ensure that the supplier provides the proper Safety Data Sheets, and where applicable,
proof of legal importation of the products into New Zealand.
Effluent Quality. In WSP with heavy sludge accumulation or where effluent compliance is
borderline, caution must be exercised to ensure good effluent quality. In such situations, a
gradual stepwise initiation of the treatment program with ongoing monitoring is essential.
Cost Effectiveness. The cost / benefit of standard sludge removal vs Enhanced Microbial
Digestion should be compared. Enhanced Microbial Digestion, when properly
implemented and measured, has the potential to significantly reduce the cost of sludge
removal in WSP.
The rate of reduction of accumulated sludge will depend on many factors including the age of the
sludge, history of chemical addition to the sludge, presence or absence of aeration and mixing,
climate, and influent loading. For example, Enhanced Microbial Digestion will theoretically digest
organic sludge, but will not digest inorganic sludge (grit). Therefore, the amount of sludge reduction
that can be achieved with an old, digested pond sludge which has a high inert solids fraction is less
than a younger sludge with a lower inert fraction.
The most important considerations for the WSP manager are to know the general rate of sludge
build up over time, the starting sludge volume and solids concentrations, intermediate and final
sludge inventory, maintaining or improving the quality of the final effluent discharge, and a cost
comparison (e.g. Enhanced Microbial Digestion compared with sludge removal, dewatering and
disposal).
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 63
has to be taken when converting such ponds to adequately protect embankments and the pond
base against erosion as well as for the selection of the aeration system. A detailed hydraulic
analysis is also required to ensure that the anoxic – aerobic zone separation will be achieved in an
aerated lagoon and that the sludge will be maintained in suspension in an activated sludge plant.
The conversion of facultative ponds (e.g. 1.5m water depth) can be challenging and might require
raising the embankments. The investment in design, engineering and earthworks can nevertheless
be worthwhile with potential savings compared with the construction of a new concrete structure.
Figure 3-25 Anaerobic Pond Conversion Figure 3-26 … to an Activated Sludge Process
3.4.14. OTHER
A number of further in-pond upgrade options are currently being developed or have recently been
installed into plants overseas and are therefore not yet ready for inclusion into this Guide. The
general trend is towards increasing the overall pond depth from the traditional 1.2 -1.5m water depth
to 2.0 and even 2.5m water depth. This gives better advantage of the pond’s flow buffering capacity
as well as effectively merging the new technologies into existing ponds.
Increasing pond and operating water depth is therefore becoming an option consistent with a
general upgrade of WSP. This can be done by deepening an existing pond; although it will affect the
existing liner and can potentially interfere with the ground water. Another option is to instead lift the
pond’s embankments. This has the advantage to not only gain operating depth, but also surface
area. Existing pumping stations can often accommodate one extra metre of lift and therefore only
require minimum adjustments. Modifications to inlet and outlet structures in accordance with
sections 3.4.1 and 3.4.2 are also easier after the lifting of a pond’s embankments.
Increasing a pond’s treatment volume through raising its existing embankments has the added
advantage that it allows pond operation at varying water levels, e.g. loads can be stored and treated
at extended HRT and storm flows can be more effectively stored and released at a slow rate.
Looking into the future such deeper ponds will be ready to accept growth media or other, newer,
technologies to achieve higher treatment standards without the need for new extensive civil works.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 64
significantly increase pond outflows, and hence the size of the required filtration system. Another
potential downside resides in the disposal of the concentrated solids. Disposing of this waste in an
upstream pond is not recommended as it will contribute to sludge accumulation and over time
release nutrients (e.g. NH4-N) leading to overall effluent deterioration. Instead it should be disposed
into a dedicated solids storage pond for concentration and ultimately off-site permanent disposal or
re-use. Table 3-18 lists some of the filtration systems and their recommended applications.
Table 3-18 Post Filtration Devices for Facultative & Maturation Ponds
Rapid Sand For algae and TSS Standard deep-bed sand filter, similar to those used in
Filtration removal. Can be used in water treatment. Removes solids through depth filtration
conjunction with chemical (i.e. over the first 500 to 800mm of the filtration media).
dosing for TP reduction. Needs to be backwashed regularly, therefore requires
Should not be used for at least two filters. Correct and precise sand grading,
TP reduction using Alum adequate backwash air and flow capacity and careful
without pH and alkalinity design of the effluent distribution are all essential
control to avoid severe elements of such a filter. Often requires pumping
clogging. between pond and filter.
Can be effective if correctly designed but are
expensive.
Continuous For algae and TSS Deep-bed filters remove solids by depth filtration.
Backwash removal. Can be used in Constant removal and washing of the sand allows
Sand filters conjunction with chemical continuous operation. Exists in vertical and horizontal
dosing for TP reduction. versions. Effective for solids removal. Not
Should not be used for recommended for TP reduction using Alum as these
TP reduction using Alum filters are difficult to clean once clogged. Material
without pH and alkalinity compatibility should be checked before using Ferric
control! salts.
Typically requires pumping between pond and filter.
Expensive, but generally reliable and long-lasting when
operated correctly.
Slow Sand For algae and TSS Shallow-bed filters remove solids by a combination of
Filters / removal, BOD5 and FC surface and partially depth-filtration. Requires large
Intermittent and E. coli reduction. Not filtration beds, which are either fed continuously at a
Sand Filters recommended for TP slow rate or which are fed intermittently. Expensive but
reduction. simple and reliable to operate. Requires regular
operator input for cleaning. Can often be operated by
gravity.
Micro- For TSS reduction, Micro-screening is effective for solids removal such as
screening excluding most algae biological floc and inorganic matter. But it is only of
limited effectiveness for algae removal even at aperture
sizes down to 5 micron.
Most failures involving the use of filters after stabilization ponds observed in New Zealand are either
due to an incorrect sizing of the filters or, more often, due to the use of Alum as the flocculent
without adequate control systems to measure and adjust alkalinity and pH prior to dosing. This
rapidly results in an infiltration of excess Alum into the depth of the sand bed with the effect of
severe bed clogging, incomplete backwashing or a complete failure of some automatic
backwashing filters. In such cases it is not the filters, which are to blame, but the lack of
understanding by the operator of the intricacies of Alum dosing and the necessity for the required
comprehensive pH control system when using the cheaper Alum instead of Ferric salts.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 65
3.5.2. MEMBRANE FILTRATION
The use of membrane filtration (micro or ultrafiltration) as post-treatment has become more common
in New Zealand e.g. at Dannevirke, Helensville, Matamata and Motueka. It provides the advantage
of complete solids removal combined with a disinfection stage. It can therefore achieve high
discharge standards on both accounts.
Membrane plants are normally supplied on a design-build basis and these factors need to be
considered by the designers who now have experience in NZ:
Type of process: A membrane reactor, even if only used as a filtration and disinfection device is a
sophisticated treatment plant, which can be fully automated. It requires well trained operators and
regular servicing and maintenance. It relies on power to operate and in a pond situation it requires
pumps to lift the effluent into the plant and produce the necessary pressure against the membranes.
Membrane plants are compact and can have a significant foundation loading which may require
ground improvements.
Type of membrane: Only a few membrane suppliers offer membranes which are specifically
designed to operate on pond effluent, i.e. at a TSS concentration, including algae, of between 100
and 200mg/l in the pond, which translates to 500mg/l to 1,000mg/l in the reactor. Most membranes
on the market are designed for either MBBR plants (MLSS of 10,000 to 15,000 mg/l) or potable
water applications (TSS of 50 to 300 mg/l). Using inadequate membranes generally involves a
reduced flow capacity, higher backwash rate and frequency and a shorter membrane life
expectancy.
Flow limitations: The costs and size of a membrane plant are directly proportional to the flow it has
to treat. Peak inflows combined with rainfall on ponds can result in significant and sudden flow
increases. Unless the ponds have an effective in-built buffer capacity (e.g. additional freeboard for
storage) the membrane plant should be sized for peak discharge flows. Membrane plants do allow
for short bursts of peak flows, but their effectiveness, life and run lengths are often overrated by the
suppliers. Peak flow treatment has therefore to be considered with caution in a plant combining
membranes and ponds and a substantial safety factor is recommended.
Return rate: Membranes have to be backwashed frequently. In addition, they have to be chemically
cleaned at regular intervals. These flows are generally returned to the front end of the stabilization
ponds. Here they will add to the overall flow and will therefore reduce the HRT of the ponds.
Membrane plant return rates currently range between 10% and 30% of the flow treated. The use of
incorrect membranes, operating membranes in peak flow conditions as well as aging membranes
will all result in higher return rates. These factors have to be taken into account in respect of the
plant’s overall HRT as well as to the organic and nutrient load returned to the front end of the ponds.
A reduction in the overall plant’s HRT will further reduce its capacity for nutrient removal (e.g. NH4-N,
TN).
An optimal post-pond membrane plant will focus on limiting peak flows to the membranes by using
the freeboard flow buffering capacity of the ponds. It will incorporate a membrane plant with ample
spare capacity, reliable and high-quality membranes and the possibility for modular capacity
expansion over time. It will have an overall return rate of less than 20% (preferably less than 15%) as
a “not-to-exceed” performance criterion and ensure that this extra flow does not affect the ponds’
HRT (e.g. through increasing the operating level and volume). An increase in nutrient load at the
pond system’s inlet due to backwash return will also have to be taken into account in respect to
current and future treatment and effluent discharge requirements.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 66
easy to handle and it should not be returned to the front end of the plant. It is recommended to
dispose of it at a dedicated pond for drying and later removal for disposal.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 67
Figure 3-27 Actiflo Micro-sand Assisted Rapid Gravity Settler process diagram
Faecal Coliforms 1-1.5 log removal 1-1.5 log removal 1-1.5 log removal 1-1.5 log removal
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 68
Figure 3-28 Actiflo Reactors
Although such micro-sand ballasted gravity settlers can achieve good results, a number of issues
have to be considered when selecting and operating such systems:
Type of process: While the process itself is relatively simple, the reactor is highly technical and
maintaining optimal operating conditions through the full range of varying flows is not easy.
Maintaining treatment performance during rapid flow variations is also difficult. Start-up, dosing
adjustment and optimisation do take time and operators have found that such units cannot be
started by the turn of a key. Operators have to be well trained and supplier support should be
available for several years to get the best out of the system.
Capital and operating costs: The unit is tall and compact and therefore requires stable foundations.
Capital costs can depend on the place of fabrication, and so can the quality of workmanship. Such
expensive systems should be provided with adequate warranties for a few years covering materials
and fabrication as well as process performance guarantees.
Operating costs depend significantly on how well the unit is optimized, automated and if it is fitted
with adequate process controls. Pumping costs are one aspect. If Alum is being used as coagulant
for TSS and TP reduction the installation of a pH and alkalinity control system is highly
recommended although often not part of the standard supply. Dosing Alum within the wrong pH
range results in the build-up of a poor floc and the resolubilisation of Alum. This has to be countered
by the operator through constant overdosing, which in turn results in a continuous loss of Alum
through the discharge as well as a loss of micro-sand, which is an expensive and essential process
additive. As a result, operating costs of more than $1,000 per day in additives can easily be reached
for a poorly controlled system.
3.5.5. UV DISINFECTION
UV disinfection is an effective way of reducing pathogen levels in the final effluent. It should only be
applied in situations where adequate transmissivity can be guaranteed. Its application is therefore
recommended after a well operating maturation pond or after post-pond-treatment to remove most
algae and TSS.
UV systems should be fitted with flow pacing and preferably also allow intensity adjustment to
compensate for a drop in transmissivity. System capacity should be sized for peak flow conditions,
although storm flows at pond outlets often have a reduced pathogen count and a higher
transmissivity and therefore do not necessarily require a larger UV unit than for average daytime
flow.
The location of the UV disinfection within the treatment train should be discussed in detail with the
consenting authority as well as Iwi, especially if wetlands are to be part of the treatment system. A
wetland will increase the pathogen count through the presence of natural bird life. For best final
discharge results UV disinfection should therefore take place after any wetlands, although the
higher faecal indicator and possibly solids and algae TSS levels at this point can make such
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 69
installation more challenging. The alternative is to agree compliance measurement after UV and
before the wetland which may then have a diffuse number of discharge points to the general
environment.
Rock Filter Solids and algae (TSS Generally natural rock in large, shallow beds or in dam-
and BOD) reduction, like structures (external or at the edge of the pond)
Nitrification, spray irrigated with the effluent. Can have some
denitrification treatment effect, but not as effective and consistent as a
well-defined structure such as a trickling filter.
Lime Stone Solids and algae (TSS Built within or on the edge of a pond or between ponds
Filter and BOD) reduction, to regain alkalinity prior to further treatment. Expensive
some TN reduction, but to build, but with practically no maintenance costs.
mostly used to gain Mainly used for nitrification and denitrification. Consider
alkalinity rock hardness re life and solubility effects.
Trickling Solids and algae (TSS Most well-known for its application as part of the Petro®
Filter and BOD) reduction and process, which uses a combination of ponds and a
assistance in TN trickling filter for nutrient removal (refer Figure 3-32).
reduction Trickling filters are expensive to build, but are simple to
operate. Operating costs involve mainly pumping costs.
Slag Filter Mainly for TP reduction Shallow-bed rock filter constructed solely from slag.
but will also reduce TSS. Slag adsorbs DRP onto its surface and therefore
reduces TP in the effluent. Slag filters have proven
effective for TP reduction, but expensive in the long-
term because of their limited life expectancy i.e. limited
adsorption capacity.
Aerated For advanced BOD and A large, gravel-type rock filter built above or below
External TN reduction in cold ground and fitted with a well-designed effluent
Rock Filters climates distribution and aeration system. Used overseas for
advanced TN reduction. Expensive to build, but requires
minimum operator input.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 70
Bark filters have been tested in New Zealand for TN reduction in a number of places. Bark acts as a
type of trickling filter media, but in addition provides a carbon source for denitrification. Bark filters
have been used in bark beds, which can be fed by gravity from pond outlets. At this stage there is
limited information available on sizing and the treatment standards which can be achieved
consistently. Further studies and treatment installations could in the future provide design criteria for
the use of such filters after WSP.
Biofiltro nitrifying filters have been introduced into New Zealand from South America. They consist
of a sand filter type structure filled with wood chips and seeded with Tiger worms. The effluent is
spray irrigated over the surface of the bark and trickles through the filter for treatment. Construction
and operating costs for such a filter are low. The filters operated in New Zealand on pond effluent
show good BOD5 reduction and nitrification, but little denitrification. Biofiltro filters have proven
successful in combination with ponds as the pond protects the filter from large solids and an
overloading in BOD5. The treatment ponds can also provide flow buffering to ensure a consistent
irrigation rate over the filter. Biofiltro plants are generally equipped with a simple but effective UV
disinfection system at their discharge end.
Bio-domes and bio-shells were developed by Wastewater Compliance Systems Utah, USA and are
marketed in New Zealand. They are submerged, aerated, fixed film, concentrically nested domes
giving a high surface area to volume media that provide substrate for bacteria. They are placed on
the bottom of a pond, creating a dark environment with robust air and wastewater mixing which
removes contaminants from the water. They do not rely solely on pond retention time but calculate
the number of bio-domes or bio-shells required based on mass loads of N to be removed. Bio-
domes also remove BOD and operate well in colder climates. Bio-Shells utilize the same underlying
principles as the Bio-Domes, only they have 2.7 times the surface area.
3.5.8. WETLANDS
Wetlands not only provide effective treatment of pond effluent but in New Zealand they can also
play an important part in the cultural acceptance of a wastewater treatment plant. Wetlands are
used overseas for small to large treatment plants including providing full wastewater and sludge
treatment for towns up to 200,000 inhabitants. Wetlands can achieve up to 80% BOD5 reduction,
70% TN reduction as well as significant pathogen and some TP reduction. They are becoming
increasingly important as a tertiary process in wastewater treatment in Europe because of their
capacity to absorb and treat micro-pollutants, which are currently not effectively treated in
conventional mechanical treatment plants. However, wetlands require up to 10 times the land area
of WSP for similar treatment capacity, so they are best used as a post treatment for ponds. Wetlands
can be broadly divided into surface and sub-surface flow wetlands, although combinations and
alterations of both types exist.
Surface flow wetlands have open water visible and meandering between wetland plants set in a
shallow pond. Such wetlands are often separated into multiple cells to achieve better flow
conditions and to allow for easier servicing of smaller wetland portions. Surface flow wetlands are
the most common wetlands in New Zealand and many of them either do not achieve the predicted
treatment standard or have become overgrown and out of control through lack of regular
maintenance.
The design of a surface flow wetland is complicated as it must take into account the wetland’s
hydraulics, treatment quality and ease of maintenance at the time of planting, as well as its natural
growth and changes over time. Wetland designs fall therefore into an area between landscape and
plant specialists and wastewater engineers. Both should closely work together for best long-term
results. The construction of an artificial wetland is expensive and the quality of its design cannot
easily be evaluated at the time of commissioning. It will only become apparent after at least 3 years
of operation when plants have fully established and quality of treatment, maintaining good hydraulic
conditions and ease of servicing become increasingly important.
Wetlands can experience significant flow variations, which should not substantially change their flow
pattern. Over time plants will grow, others will die off and weeds will develop. Sludge will
accumulate and preferential channels can develop. Regular maintenance and easy access by the
operator and maintenance specialists have therefore to form an essential part of any wetland
design.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 71
Sub-surface flow wetlands consist of a large gravel bed into which the wetland plants are planted
and through which the effluent travels from one end to the other. With such wetlands the effluent
should only be visible at the wetland inlet and its outlet. Subsurface wetlands have to comply with
strict design criteria in respect to hydraulic and biological loading as well as in respect to the gravel
sizing, size distribution and bed depth.
The hydraulic flow through a sub-surface wetland and its consistency over many years is even more
important than for the surface flow wetland. Clogging of sections of the wetland can rapidly lead to
an overloading of other parts, resulting in further clogging and ultimately a failure of the whole
system. A division of a large wetland into smaller cells presents therefore a real advantage for
maintaining a healthy wetland treatment long-term.
A sub-surface wetland is much more accessible for servicing and maintenance as the operator or
specialized personnel can walk on the gravel bed for weeding and plant maintenance. Plant
selection and the manner of planting are important in that their root system will directly affect the
hydraulic flow conditions in the gravel bed. Plants with root systems which could take over major
parts of the wetland are to be avoided to prevent localized hydraulic overloading or channeling.
Sub-surface wetlands do not allow desludging. They rely on the natural deterioration of any solids
and biomass accumulating in the gravel bed over time. It is because of this that subsurface wetlands
are limited in respect to their hydraulic, BOD5, TSS and nutrient loading.
Hybrid flow wetlands allow mixing of wetland types to the available terrain and treatment
requirements. Some have been developed in New Zealand as a consequence of failed sub-surface
wetlands. Such a wetland consists of rows of wetland plants set in a gravel bed. Shallow channels
are dug into the gravel to carry the wastewater through the rows of wetland plants. The shallow
nature of the channels provide for full exposure of the effluent to the sunlight and therefore for
maximum UV disinfection. The gravel allows the effluent to percolate easily to the root system of the
wetland plants and maximizes nutrient uptake without the risk of gravel bed overloading. Efficient
influent distribution at the wetland inlet, as well as treated effluent collection at the outlet, are
essential for optimum treatment.
The hybrid flow wetland offers some of the advantages of the surface flow wetland (e.g. a wider
acceptable range of flow and load variation) with some of the advantages of the sub-surface
wetland (e.g. ease of maintenance). In addition it can provide high natural disinfection efficiency.
Wetlands of any kind should be designed based on sound and proven design criteria. They should
not be regarded solely as landscape features but as complex engineering and natural treatment
systems, which have to remain operational long-term.
As a general guide design features of a modern wetland should include:
A division of a large wetland into multiple smaller cells to ensure better defined hydraulic
conditions, treatment standards and easier maintenance e.g. can take one off line.
An inlet structure, which distributes the effluent equally between wetlands.
An inlet distribution and spreader system that can cater for a wide range of flows.
Distribution systems, which spread the effluent over the whole width of the cells.
Wetland plants should be selected for the required nutrient uptake as well as for their
resilience, longevity and ease of maintenance requirements.
Wetland plants should neither have tendency to take over the wetland over time nor should
they become too large to maintain or handle.
A sequencing of wetland plants according to treatment and hydraulic requirements can at
times provide better treatment and easier servicing and maintenance.
The wetland should allow for easy access for the operator and maintenance personnel to
the plants and for desludging or weeding purposes (if appropriate).
For surface flow wetlands the introduction of a sludge settling zone, free of plants is a good
option to allow for regular, easier desludging.
Surface flow wetlands should be fitted with a water level control device, which allows
operation over an extended period of time within a range of pre-set water levels. This is to
ensure better access as well as for the planting of new plants, which cannot initially be
submerged and require shallow water for quite some time.
A final effluent collection system, which ensures low velocity discharge flows over the whole
width of the wetland cell.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 72
A hydraulic separation between the wetland and the discharge pipe to ensure downstream
headloss does not affect the wetland operation.
A strict maintenance schedule. Hand weeding and removal of dead plants should take place
once every 1 to 2 months. More intensive maintenance should be undertaken once per year.
If the operator cannot undertake this task on a regular basis Council should engage an
outside contractor
When a wetland is installed for a future capacity, costs can be saved by planting for the short
term needs and allowing natural plant growth (numbers and size) to increase in line with
treatment capacity. This may require division and repositioning of plants across the wetland.
Wetland capital costs are high and regular hands-on maintenance is essential to maintain long-term
performance thus seasonal operating costs can be significant. Councils should therefore consider
their use carefully as the conversion or dismantling of a failed and inoperative wetland can be more
expensive than its construction. Before committing to a wetland Councils should visit reference
plants of the same design, which have successfully operated for a number of years and interview
the operators of these plants.
Designers should therefore refer to recent wetland development and design manuals such as in
New Zealand, France and the USA (e.g. NIWA NZ Constructed Wetland Planting Guidelines, 2006
and USEPA Constructed Wetlands Treatment of Municipal Wastewaters, 2000).
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 73
3.6 HIGH RATE ALGAL PONDS AND ALGAL HARVEST
PONDS
3.6.1. HIGH RATE ALGAL PONDS (HRAPS)
3.6.1.1 TREATMENT ROLE
High Rate Algal Ponds, as their name suggests, promote the aerobic treatment process that occurs
in the surface layer of facultative ponds by optimising algal photosynthesis and growth. As such
HRAP do not treat raw wastewater but typically follow a covered anaerobic pond or a primary
clarifier. The algae produce oxygen in the daytime with pond DO concentrations of 2-3 times
saturation (over 20 g m-3). This highly aerobic environment drives efficient bacterial decomposition
of organic matter. The algae assimilate nutrients (NH4-N and DRP) into harvestable algal biomass for
beneficial use as fertilizer and biogas production. These large surface area and shallow ponds allow
for a high level of natural disinfection, particularly sunlight-UV inactivation of faecal microbes, in
combination with photo-oxidation of dissolved organic contaminants.
Figure 3-29 Examples of High Rate Algal Ponds in California (a & b), New Mexico (c, d & e) and New
Zealand (f & g)
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 74
3.6.1.3 PERFORMANCE
A consequence of the higher algal growth rate in HRAP is that their average annual biomass
productivity (8-12 g m-2d-1 VSS) is typically 2-4 times that of facultative ponds (2-3 g m-2d-1). In addition,
HRAP biomass has a higher proportion of algae (up to 90%) than facultative pond biomass. The
constant pond mixing, natural diurnal variation of HRAP conditions (sunlight, temperature, pH and
dissolved oxygen) and lack of an anaerobic pond bottom, lead to far more efficient and consistent
wastewater treatment. HRAP also tend to select for algal strains that are less susceptible to
invertebrate grazing (a common cause of conventional pond crash). Importantly, HRAP only tend to
grow green algae and diatoms as opposed to blue/green algae which commonly occur in late
summer/autumn in New Zealand facultative ponds and can be toxic.
High levels of treatment can be achieved by HRAP systems with average annual effluent
concentrations (g m-3) of <15 BOD5; <15 TSS; <10 TN; <5 NH4-N; <6 TP; <4 DRP <100 E.coli), but
removal declines during winter months due to lower algal growth, oxygenation and nutrient
requirement.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 75
Figure 3-30 Christchurch Demonstration HRAP CO2 addition sump
3.6.2.3 PERFORMANCE
Provided the algae bioflocculate and settle out of the water column, AHPs typically achieve >60%
and periodically 70-90% removal of TSS. Large flocs of bioflocculated algal cells will settle at rates
of 30-50 cm/h and will concentrate to about 1-3% solids.
Addition of small amounts of cationic flocculent to the HRAP effluent can improve average algal
settleability and consistency of BOD5, TSS, TN and TP removal performance over that given in
section 3.6.1.3, and is necessary if the HRAP effluent is pumped to the AHP as pumping will disrupt
the flocs.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 76
3.7 PETRO® SYSTEMS
Pond Enhanced Treatment and Operation (PETRO®) is a proprietary system that was developed in
South Africa during the 1980s. The system effectively combines facultative pond pre-treatment with
mechanical secondary treatment processes (either biological trickling filter (BTF) or activated sludge
(AS) and is designed to overcome the shortcomings and promote the advantages of the individual
components (Shipin et al 1998).
The name PETRO® is a proprietary name which is an acronym of the concept title Pond Enhanced
TReatment and Operation. The system sets out to make maximum use of anaerobic biodegradation
followed by aerobic degradation in oxidation ponds prior to the polishing stage in a secondary unit.
It was developed at a time when less knowledge existed of the exact biological processes occurring
in each treatment unit and simpler variants are now possible as indicated in the preceding chapters.
All stages of the system are interlinked by multiple effluent recirculation pathways in which the
required flow rates can be selected, these pathways include recirculation of:
Oxygen-rich effluent from the secondary facultative ponds to minimize odour release from
the primary facultative pond surface by sulphide oxidation.
Humus tank solids to the primary facultative pond anaerobic zone for digestion.
Bicarbonate alkalinity from the primary facultative pond to promote nitrification in the TF
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 77
The PETRO® system can be developed in a staged manner and is suited to upgrade an existing TF
plant where land is available or to upgrade an overloaded WSP system.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 78
4 OPERATION AND MAINTENANCE
4.1 GENERAL
One of the major advantages of WSP is that they require relatively little operation and maintenance
(O&M) in comparison to mechanical wastewater treatment processes. However, some O&M is still
required to:
Monitor the health of the WSP process.
Undertake general housekeeping around the site.
Maintain the structural integrity of the WSP.
Collect samples for resource consent compliance.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 79
domestic premises should be monitored and managed in accordance with the advice within NZS
9201.23.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 80
A depth integrated sample is important for algae sampling as the algae often migrate within the
pond aerobic layer.
Chlorophyll; Chlorophyll a is a pigment found in algae, blue-green algae and plants and is critical to
the process of photosynthesis. Chlorophyll concentrations therefore give an approximation of the
amount of living algae present in WSP. As with algae monitoring, chlorophyll monitoring is most
valuable if the WSP comprises more than one pond, where the operation of individual ponds can be
adjusted based on the results of chlorophyll monitoring. A depth integrated sample is also important
for chlorophyll a sampling. Handheld meters are available to measure chlorophyll based on
absorbance of selective optical wavelengths.
Sludge Level; Sludge accumulates in the bottom of WSP over time. Increasing sludge depths result
in:
Reduced effective pond volume available for treatment.
Reduced hydraulic retention time (HRT).
Increased risk of odour nuisance and sludge rising to the surface
Increased risk of botulism outbreaks.
The quantity of sludge should be monitored periodically to understand the rate of accumulation. At
the same time, the sludge should be characterised in terms of total and volatile solids content. This
will allow effective planning and budgeting for sludge removal.
Table 4-1 Recommended Monitoring Schedule
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 81
4.2.6. MONITORING OF EXTERNAL PARAMETERS
In addition to the process monitoring detailed above it is often useful (but not mandatory) to
measure and record the following external parameters, particularly if a pond is experiencing loss of
performance.
• Septage and Industrial discharges; see sections 4.2.2 and 4.2.3 above.
Air temperature; large differences in pond and air temperature together with low wind
speed can explain overturning of a pond. Refer 4.4.3.
Wind speed and direction; this can indicate trends in wave action, contribute to pond
overturning and sources of odour complaint. Refer 4.4.1 and 4.4.3.
Solar radiation; this can explain trends in effluent disinfection when the final ponds have
low algal levels.
Sewerage catchment and pond rainfall and evaporation records.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 82
should be referenced to a clear fixed datum nearby. Ideally this survey datum should be identifiable
against the WSP as-built drawings.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 83
Figure 4-1 Example Sludge Column Layers
Any stratification in solids concentration will show up in the sample analysis at which point it can be
determined whether there is a significant difference in total dry solids calculated by either applying
an overall average dry solids percentage to the wet volume of sludge or splitting that volume into
two or three layers and applying the corresponding average dry solids percentages to each layer. If
there is a significant difference, it would be more accurate to separate out the layers and apply the
appropriate average dry solids percentage to each layer. It is also important when comparing the
solids concentrations to the depths at which the samples were taken to note that the thickness of
each layer could vary throughout the pond especially where the base profile is inconsistent.
In summary, to provide a more accurate approximation of the dry mass present, it is important to
consider variation in sludge solids concentration relative to depth. However, it is recognised that
specialist sampling equipment is required to be able to effectively collect discrete samples from
different sludge depths.
If such specialist sampling is not possible, an alternative is to homogenise a sludge core collected
through the depth of the pond. The resulting TSS concentration, multiplied by the depth of sludge,
provides a reasonable estimation of the mass of dry solids present. Examples of sludge core
collection include use of a ‘sludge judge’ and use of an open tube with a valve on top.
When using a sludge judge to collect a core sample, care should be taken as the sludge may not
enter the tube at the same rate as the tube is lowered like water does. This means that the tube will
collect sludge at the sludge surface but may begin to push sludge out of the way instead of letting it
enter the tube as it proceeds through the sludge column. This may mean that you do not capture
the whole sludge column.
When using an open tube that has a valve on top, the valve is open when lowering the tube and
closed when the tube has reached the base. The tube is then raised up with the entire sludge
column inside, including any layer of grit or soft clay from the base. Depending on the weight of the
water on top and the depth of the sludge, the grit and clay can often drop out before you have a
chance to close off the bottom of the tube when it is just below the pond water surface.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 84
4.2.10. SAMPLE METHOD – SLUDGE
When sludge depth profiling is undertaken, sludge samples should be collected and sent to a
laboratory for analysis. It is recommended that all sludge samples collected from WSP should be
analysed for TSS. In addition, a selection of the samples (e.g. 10 – 20%) should also be analysed for
volatile suspended solids (VSS).
When collecting samples of the sludge, the location and depth should be recorded for repeatability
and the sample should be undisturbed when taken. When taking samples at more than one depth
in the same location, take the upper sample first and work downwards so that each sample is
undisturbed. Some sludge survey contractors have proprietary equipment which allows discrete
sludge sampling at different depths, typically using vacuum pumps.
Sludge surveys should preferably be undertaken at the same time of year to avoid seasonal effects
on comparative volumes.
Sludge cores through the depth of the pond can be collected using a sludge judge or open tube as
noted above. To collect a homogenised sludge sample in this way, slowly pour the pond water from
the top of the sample, taking care to minimise mixing of the pond water and sludge layers. After the
pond water has been removed, pour the sludge into a bucket. It will be necessary to send only a
relatively small portion of the sludge sample to the laboratory for analysis. Therefore, it is critical that
the sludge in the bucket is mixed well to ensure homogenisation before removing the sub-sample to
send for laboratory analysis.
If beneficial reuse of the biosolids is being considered, a selection of sludge samples should also be
analysed for heavy metals, organics and pathogens. The Guidelines for the Safe Application of
Biosolids to Land in New Zealand (NZWWA, 2003) detail the contaminants which should be tested
for, and the contaminant levels to meet the various biosolids grades.
Note: These biosolids guidelines are currently being reviewed and updated as “Guidelines for
Beneficial Use of Organic Materials on Productive Land”. The revised version is expected mid 2018.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 85
4.3 TROUBLESHOOTING
Common operational problems encountered and their solutions are listed below.
4.3.2. LOW DO
The DO concentration in a WSP will fluctuate considerably over a diurnal (24-hour) period due to the
combined effects of algal photosynthetic oxygen production and oxygen consumption by the
respiration of all pond organisms. DO concentrations will be at their lowest at, or shortly after,
sunrise rising to their peak towards the early afternoon. Low DO concentrations early in the day are
not necessarily cause for concern, however if low DO (<2 mg/L) is measured in the early afternoon
this may be of concern. Nitrification is much less likely to occur under low DO conditions.
Low DO in WSP can be caused by the following factors:
Excessive BOD loading, for example due to a seasonal or permanent increase in
wastewater flow and load.
Loss of algae, either due to seasonal fluctuations in algal concentrations, or due to other
factors such as grazing by invertebrates.
Failure of or inadequate use of mechanical aeration, if mechanical aeration is used to
supplement the oxygen produced naturally by photosynthesis.
Pond turnover, resulting in the release of organic matter (BOD) from the sludge layer into
the surface layers and increasing oxygen demand.
If low DO concentrations occur, it may be possible to provide supplementary aeration by:
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 86
Mechanical aeration. Note: it is important that the anaerobic sludge layer is not disturbed
by aeration as organic matter will be released from the sludge, increasing the oxygen
demand.
Sodium nitrate. This could be introduced at a fixed point in the pond, for example with the
influent, or released from a boat moving around the pond surface.
Where the WSP comprises more than one pond, through recirculation of effluent from a
pond with relatively high DO to the surface of a pond with lower DO. This can be
particularly effective if the low DO in one pond is caused by loss of algae, and other
pond(s) still have a healthy algae population.
Note: Previous Guidelines and industry perception is that jet boats or outboard motors can be used
to provide supplementary aeration and mixing in WSP. While this is possible, care must be taken
because they have the potential to stir up the sludge layer, potentially compounding the situation.
The health and safety requirements for boats also need careful consideration. This option should
therefore only be used in emergencies and not as a regular operation.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 87
4.3.6. EXCESSIVE ALGAL GROWTH
Excessive algal growth does not adversely affect the function of a WSP, however it can cause
elevated concentrations of TSS in the treated effluent. During summer, high algal growth rates can
result in TSS concentrations in WSP of 150 mg/L or more. At such times, higher daytime DO
concentrations will increase the treatment capacity of the WSP.
The concerns around excessive algal growth are usually due to the visual impact (green plume) of
treated effluent with a high algal concentration when it is discharged into a stream or river.
Rather than control algal growth in the main WSP, reductions in TSS concentration in the discharged
effluent could be achieved by either providing shade around the outlet, or through modification of
the discharge structure. Refer to section 3.4.2 for further details of these potential solutions.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 88
4.3.8. COLOUR OBSERVATIONS
Table 4-3 Connection between colour of the pond and operational characteristics
Yellow green or The result of a rotifers, protozoa or cladoceran bloom which graze on
excessively clear the algae and can decimate their population in days
If the conditions persist, there will be a decrease in DO and the
potential for odour nuisance.
Greyish Overload of organic matter and/or short detention time
Incomplete anaerobic digestion in the sludge layer
The pond should be put out of operation
Milky green The pond is in a self-flocculation process as a result of high pH and
temperature causing flocculation of algae with magnesium and calcium
hydroxides.
Blue greenish Excessive proliferation of cyanobacteria
The bloom of a certain species forms a scum that decomposes easily,
leading to bad smells, reduction of light penetration and green algae,
as a consequence, reduction in oxygen production
Brownish red Overload of organic matter
Presence of photosynthetic sulphide-oxidising bacteria (they require
light and sulphides, use CO2 as an electron acceptor, do not produce
oxygen and do not help in BOD removal).
Source: Arceivala (1981) and CETESB (1989)
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 89
Figure 4-4 Weed Growth (Photo courtesy of Sam Murphy, Buller District Council)
Weed growth should be eradicated promptly as excessive weed growth can be difficult to control.
The bulk of the weed can be removed by dredging, however some roots will remain which is likely
to result in regrowth.
4.3.11. FISH
Eels often naturally colonise WSP in New Zealand, and in some cases are present in high numbers.
The presence of eels is generally not of concern, however they can cause blockages in outlet
chambers and pumps, and could impact on downstream treatment processes such as membrane
filtration.
If eels do cause problems, their impact can be reduced through appropriate design of outlet
structures and screening. This is discussed further in sections 3.3.1, 3.4.2.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 90
4.3.12. BIRDS
WSP are often inhabited by large transient populations of birds such as ducks, geese, and swans.
This is generally not of concern, although they can create public nuisance, equipment damage and
Operator Health and Safety issues. Public nuisance caused by birds can occur if houses are located
in close proximity to the WSP. Operator Health and Safety issues can result from trespassers
deploying firearms around WSP.
The main concern regarding birdlife on WSP is the potential for outbreaks of avian botulism which
can result in the death of birds, in particular ducks, on a large scale in and around WSP. Avian
botulism is caused by a toxin produced by the bacterium Clostridium botulinum, producing paralysis
in affected birds. C. botulinum is most prevalent in anaerobic environments, such as the sludge layer
on the bottom of WSP. The risk of outbreaks of avian botulism appears to be increased by:
Modification of WSP from a traditional WSP to a buffer pond, storage pond or sludge pond.
This reduces flow through the ponds, increasing the potential for the toxin to accumulate in
the pond.
Increased sludge depth, and/or reduced clear water depth between the anaerobic sludge
and the surface of the pond, for example by operating ponds at low levels to provide buffer
capacity. This allows the birds easier access to the sludge.
An outbreak at a plant nearby or in the natural environment with local introduction by
infected birds.
If an outbreak of avian botulism occurs on a WSP, it is important to remove and dispose of affected
birds as quickly as possible. Transmission of avian botulism occurs through concentration of the
toxin in maggots which feed on dead birds, with the maggots then being consumed by other birds. If
an outbreak of avian botulism occurs on a WSP, Fish & Game may assist with control. It is
increasingly common for Regional Councils to require avian botulism management plans for WSP.
WSP provide an attractive environment for birdlife, so it can be difficult to minimise the numbers of
birds on WSP. Ducks seem to’ know’ when their hunting season starts and their numbers often
increase at many WSP at that time since duck shooting is illegal there. The following control
methods may assist:
Culling of birds around WSP, although this will likely require approval by Fish & Game, who
are often reluctant to give such approval.
Deployment of LPG “scarecrow guns” around the perimeter of WSP. The effectiveness of
such guns is limited, particularly on larger ponds and when used over an extended period
of time.
Use of explosive cartridges fired from shotguns, for example “Birdfrite”. The effectiveness
of such cartridges is also limited, particularly on larger ponds.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 91
Table 4-4 Principal causes of effluent quality deterioration
Depending on the potential causes of the deterioration in effluent quality, refer to the relevant
section.
Algal growth – refer to section 4.3.5, 4.3.6.
Sludge build-up – refer to section 4.3.15.
Low DO – refer to section 4.3.2.
Overloading – refer to section 4.3.14.
Short-circuiting – refer to section 3.4.3.
4.3.14. OVERLOADING
Overloading occurs when the wastewater load, in kg BOD/day, exceeds the capacity of the WSP at
the current temperature and operational regime. As a result, DO concentrations fall, and the
treatment process fails. The detailed reasons for overloading should be thoroughly investigated
prior to committing to remedial action. However overloading can potentially be mitigated by:
Increasing oxygen availability in the WSP – refer to section 4.3.2.
Reducing the BOD load onto the WSP – refer to section 4.3.14.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 92
4.3.15. SLUDGE ACCUMULATION
While WSP do provide some ongoing breakdown of organic solids in the anaerobic sludge layer at
the bottom, the depth of the sludge layer will build up over time. This is due to the presence of
some inorganic (inert) solids in raw wastewater, and because it is not possible to break down all of
the organic solids deposited on the base of the WSP.
As the sludge level in a WSP rises, the following problems can potentially occur:
The increase in sludge depth reduces the depth available for wastewater treatment,
reducing the HRT and WSP performance.
Sludge can form pockets in certain areas of WSP, increasing the potential for short-
circuiting to occur.
The reduced clear water above the sludge layer can provide the environment for problems
such as weed growth and avian botulism to occur.
Anaerobic digestion of the organic material can result in the release of nutrients, in
particular NH4-N and DRP. The rate of anaerobic digestion occurs more quickly during
warmer summer temperatures.
For desludging options, refer to 3.4.12, 4.4.7.
4.4 MAINTENANCE
4.4.1. GENERAL HOUSEKEEPING
As with all WWTP sites, WSP should be kept clean and tidy. To achieve this, grass will need to be
mown, weeds controlled, and any floating debris should be removed from the surface of the WSP.
Rodent traps may also need to be installed. Any operator facilities, such as laboratory, office,
shower and toilet, should also be kept clean and tidy.
Data collection, transmission and recording should also regularly be checked.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 93
4.4.2. EQUIPMENT MAINTENANCE
While a traditional WSP has minimal mechanical equipment on site, equipment such as pumps and
aerators do require maintenance. A greater range of mechanical equipment is likely to be present
on modified WSP.
A maintenance schedule for all mechanical equipment should be developed and followed. The
manufacturers or suppliers O&M manuals will provide details of the specific maintenance that
should be undertaken on any piece of equipment. All maintenance, both planned and unplanned,
should be recorded. Access points e.g. jetties, cranage, should also be maintained available.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 94
costs than the expensive desludging methods, plus the extra pond will provide future
flexibility.
Dredge the sludge from the base of the pond, dewater the sludge externally, then transport
the dewatered sludge for reuse or disposal. Dredging does not usually require removing the
pond from service, which is a main advantage. However, care must be taken with returned
liquors from dewatering and allowing for some variations in pond effluent quality.
Sludge dewatering methods include trailer-mounted centrifuges, dewatering containers
(similar to shipping containers), or geotextile bags located in a lined basin (for collection of
filtrate and return to the pond). All the dewatering methods rely on polymer or other
chemical dosing, to allow liquid to be separated from the sludge floc. Centrifuges generally
can achieve a cake Dry Solids (DS) between 15% and 19%. Geotextile bags can achieve
between 17% and 40% DS, with the dewatering performance varying significantly depending
on the geotextile fabric selected and the chemical dosing rate. Desludging contracts may
need to have an incentive mechanism whereby the contractor receives more payment for
DS contents greater than the target value. Alternatively, a special retention could be held
and released if the target DS is achieved (within a nominated time in the case of geobag
dewatering). This would reimburse the contractor for the use of greater amounts of
chemicals, and minimise ‘skimping’ on the amount of chemical used.
Pond desludging may appear to be a simple operation, but significant documentation and
quality assurance is required for :
the sludge surveys before and after desludging, and
cake DS achieved (in the case of geobags, monitored over a 6 to 12 month period) .
Pond sludge survey data needs to be collected on a 20m x 20m grid for moderate size
ponds, and down to a 10m x 10m grid for small ponds. Samples need to be collected from
various positions in geobags because a drier crust can form near the outer surface which
‘hides’ a lower DS content in the centre of the geobag. The data gathering requires
adequate contract monitoring resources to check on the validity of the data provided by the
contractor. Independent sampling and testing may also be required.
Dewatered sludge cartage from the pond to remote sites can be a substantial portion of the
overall cost. Consequently, dewatered sludge can be used on larger WWTP sites as
landscaping mounds to minimise the cartage cost. Often geobags have been buried on the
WWTP site if space allows. Alternatively, dewatered sludge can be taken to a landfill and
used for surface restoration which may avoid the ‘tipping charge’. Because pond sludge is
normally very well stabilised with a lower organic content compared to other sludges, it may
be less attractive for commercial beneficial reuse options such as composting. However,
local uses in high volumes such as -- landfill, mine, or quarry restoration, could be an
economical solution.
Undertake a form of enhanced microbial digestion. Refer section 3.4.12.
All methods have a significant cost and each has a different timeframe, payment and resources
profile. Therefore selection should be based on a specific comparative assessment.
4.4.8. OTHER
Attention should be given to observing whether rodents, other animals or birds are causing issues.
Ducks generally prefer cleaner water such as maturation ponds and numbers can markedly increase
during duck shooting season as they seem to know they are safe within the plant confines. This can
cause a surge in effluent faecal indicator bacteria and virus concentrations.
In cold weather some animals e.g. rabbits, can dig burrows against plastic liners for warmth.
Unfortunately sometimes they gnaw through the liner causing leaks.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 95
summarise a compendium of criteria being usefully applied in the different regions of New Zealand,
for WSP discharge consents.
5.1.2. MITIGATION
Require steps to be taken in the event of a failure of the WSP that could result in any deterioration in
quality of effluent discharging to the receiving water, including: remedy and mitigate adverse
effects, notify the Medical Officer of Health, notify the Regional Council, provide follow up reporting.
Useful tools include troubleshooting flow charts, e.g. for odour control. Acknowledge a timetable
necessary for each type of remediation.
5.1.4. MONITORING
Specify:
locations of sampling points; typically discharge and receiving water impact sites (upstream
and downstream). Dissolved oxygen (DO) should preferably be measured at the same time
each day and between 0900 and 1400 hours which is typically an average of diurnal
variation. It is possible for DO to reduce to zero overnight. DO should be greater than 2
g/m³ in 90 percent of samples (i.e. 10th percentile of data set >2 g/m³. Continuous
recording will demonstrate the diurnal curve and can demonstrate healthy biology even
when periodic daily spot measurements are different (refer 4.3.2).
frequency and method of sampling,
methods and procedures for analyses, (typically the current version of “Standard Methods
for the Examination of Water and Wastewater”),
frequency of advising results and format of reporting,
requirements for flow monitoring, (typically continuous inflow and outflow monitoring),
testing for pond sealing, if a likely risk.
5.1.5. RECORDS
Keep operational records of system changes, operating procedures, troubleshooting etc. and report
annually, or as required by the consent authority. Agree the format of reporting, especially of data
minimum accuracy, presentation, trending and percentiles.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 96
5.1.7. REVIEW OF CONDITIONS
Consent authorities may at scheduled intervals initiate a RMA section 128 review and may also
review conditions to deal with any adverse effects on the receiving environment, review the
adequacy of the monitoring requirements or reduce the monitoring requirements when the effects
of the effluent discharge are adequately established.
The term of consent is to be specified, including any scheduled dates or milestones for upgrading,
or system replacement.
It is useful to schedule a periodic review meeting with the consent officer and local community
representatives to ensure everyone understands the performance achieved and especially any
deviations and their cause. Often deviations are caused either by unusual weather patterns or
community events.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 97
6 FREQUENTLY ASKED QUESTIONS
If you are using an electronic copy of these guidelines, holding down the control key plus a left
mouse button click on any of the questions below will take you to the relevant section.
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 98
Waste Stabilisation Ponds: Design and Operation 99
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 99
Waste Stabilisation Ponds: Design and Operation 100
(mg/L) (oC)
Pump Hours
Time of Test
KwH) No. 2
No. 2
No. 2
No. 2
No. 2
No. 2
No. 1
No. 1
No. 1
No. 1
No. 1
No. 1
Weather Comments
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Total
Ave
Note: A template for this record sheet is available as an excel download at http://www.waternz.org.nz/WSP
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 100
Waste Stabilisation Ponds: Design and Operation 101
7 REFERENCES
Altner, G. (2005). New Technologies for Upgrading Aging Wastewater Treatment Ponds, New
Zealand Water & Wastes Association Annual Conference 2005
Altner, G. (2006). Upgrading Waste Stabilisation Ponds Using Suspended Growth Media,
International Water Association Specialist Conference, Thailand 2006
Altner, G. (2007). Waste Stabilisation Ponds: Replace or Upgrade? A Practical Guide on how the
Performance of Existing Oxidation Ponds can be Improved, Ingenium Conference 2007
Altner, G. (2007). The Use of High-Rate Growth Media in Waste Stabilisation Ponds, New Zealand
Water & Wastes Association Annual Conference 2007
Arceivala, S.J. (1981) Wastewater Treatment and Disposal. Marcel Dekker, New York.
Archer, H. and Donaldson, S. (1998). Low Cost Upgrading of Waste stabilisation Ponds for Public
Health Protection with Nutrient Removal Benefits, New Zealand Water & Wastes Association Annual
Conference 1998.
Archer, H., Can Performance of Waste Stabilisation Ponds be Improved? Water New Zealand Annual
Conference 2015.
Archer, H., O’Brien, B. and Bourke, M. (2006). Christchurch Wastewater Treatment Plant Pond
Upgrading, The Water Conference – New Zealand Water & Wastes Association Annual Conference
2006.
Brockett O.D. (1975). Phenomenon of Biological Instability in Sewage lagoons at Mangere.
Biotechnology Conference Prac. May 1975, Massey University.
Craggs R.J., Davies-Colley R.J., Tanner C.C. and Sukias J.P.S. (2003). Advanced ponds systems:
performance with high rate ponds of different depths and areas. Water Science and Technology
48(2): 259-267.
Craggs, R., Park, J., Sutherland, D., Heubeck, S. (2015). Economic construction and operation of
hectare-scale wastewater treatment enhanced pond systems. Journal of Applied Phycology 27 (5):
1913-1922.
Crites, RW; Middlebrooks, EJ; Bastian, RK; Reed, SC (2014); Natural wastewater treatment systems
(2nd Edition); CRC Press
Finkelstein, J. Survey of new Zealand Tank Evaporation, Journal of Hydrology (NZ) Vol12 No.2, 1973.
Fitzmaurice, J.R. (1987). Municipal wastewater disposal in New Zealand. In Transaction of the
Institution of Professional Engineers of New Zealand. 14(1/CE) March.
Fitzmaurice, JR (2009); History of Auckland Wastewater and Mangere Wastewater Treatment Plant;
Proceedings of the 3rd Australasian Engineering Heritage Conference, Dunedin, NZ
GIZ (Deutsche Gesellschaft für Internationale Zusammenarbeit GmbH) / Ecosan (2011). Technology
Review of Constructed Wetlands – Subsurface Flow Constructed Wetlands for Greywater and
Domestic Wastewater Treatment
Gloyna EF., Wastewater Stabilisation Ponds, WHO 1971.
Hickey, C.W., Quinn, J.M., and Davis-Colley, R.J., (1989). Effluent characteristics of domestic sewage
oxidation ponds and their potential impacts on rivers. New Zealand Journal of Marine and
Freshwater Research, 23: 585-600.
Mara, D. D. and Pearson, H. (1998). Design Manual for Waste Stabilization Ponds in Mediterranean
Countries, Leeds: Lagoon Technology International Ltd.
Marias, G. (1970). Dynamic Behaviour of Waste stabilisation Ponds, Second Int Symp for Waste
Treatment Lagoons, Kansas City, USA..
Middlebrooks E.J. (1995). Upgrading Pond Effluents: An Overview. Watt Sic Tech. 31(12).
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 101
Waste Stabilisation Ponds: Design and Operation 102
Ministry of Works and Development. (1974). Guidelines for the Design, Construction and Operation
of Waste stabilisation Ponds.
NZWERF. NZ Municipal Wastewater Monitoring Guidelines 2002.
NZWWA (2000). Manual for wastewater Odour Management.
NZWWA (2003). Guidelines for the Safe Application of Biosolids to land in New Zealand.
New Zealand Land Treatment Collective. (2000). New Zealand Guidelines for Utilisation of Sewage
Effluent on Land. ISBN 0 478 11005 7.
Pearson, H. W. (1996). Expanding the horizons of pond technology and application in an
environmentally conscious world. Water Science and Technology 33(7): 1-9.
Shilton, A. (ed). (2006). IWA Inte.g.rated Environmental Technology Series, “Pond Treatment
Technology”, ISBN 9781843390206.
Shilton, A. (2001). Studies into the Hydraulics of Waste Stabilization ponds. Ph.D. Thesis. Massey
University, Palmerston North, New Zealand.
Shilton, A. and Harrison J. (2003). Guidelines for the Hydraulic Design of the Waste Stabilization
ponds. Institute of Technology and Engineering, Massey University, Palmerston North, New Zealand.
Shipin, O, Meiring, P and Rose, P (1998). PETRO® system: A low-tech approach to the removal of
waste-water organics (incorporating effective removal of micro-algae by the trickling filter).
Tanner, C.C. and Sukias, J.P.S. (2003). Linking pond and wetland treatment: performance of
domestic and farm systems in New Zealand. Water Science and Technology 48(2): 331–339.
Tanner, C.C., Sukias, J.P.S. and Dall, C. (2000). Constructed wetlands in New Zealand –Evaluation of
an emerging “natural” wastewater treatment technology. Proceedings of Water 2000: Guarding the
Global Resource Conference, Auckland, March 19-23. CD ROM ISBN 1-877134-30-9, NZWWA.
USEPA. (1983). Design Manual for Municipal Wastewater Stabilisation Ponds.
USEPA. (2000). Constructed Wetlands Treatment of Municipal Wastewater.
USEPA. (2011). Principles of Design and Operations of Wastewater Treatment Pond Systems for
Plant Operators, Engineers, and Managers.
Walmsley. NA, van Oorschott, R. High Rate Anaerobic Lagoons (HRALs) in Industrial/Domestic
Wastewater Treatment, New Zealand Water & Wastes Association Annual Conference 2004.
http://www.epa.gov
http://www.lagoonsonline.com
http://www.usace.army.mil
Water New Zealand Good Practice Guide: Waste Stabilisation Ponds: Design and Operation November 2017 Page | 102
A consistent approach across the 3 waters sector









