Weekly Construction Progress Report Template

This weekly construction report provides updates on the SH16 Causeway Upgrade Project. It notes that while all work is being performed safely, some elements are slightly behind schedule. Recent progress includes completing geotechnical investigations and bridge inspections. Upcoming work includes establishing site compounds, developing traffic management plans, and finalizing 50% design packages. Key risks include procuring site buildings and IT equipment on time, obtaining approvals for traffic closures, and agreeing on property handover dates with NZTA.

Uploaded by

Oumeyma Hamlaui
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
1K views2 pages

Weekly Construction Progress Report Template

This weekly construction report provides updates on the SH16 Causeway Upgrade Project. It notes that while all work is being performed safely, some elements are slightly behind schedule. Recent progress includes completing geotechnical investigations and bridge inspections. Upcoming work includes establishing site compounds, developing traffic management plans, and finalizing 50% design packages. Key risks include procuring site buildings and IT equipment on time, obtaining approvals for traffic closures, and agreeing on property handover dates with NZTA.

Uploaded by

Oumeyma Hamlaui
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

SH16 CAUSEWAY UPGRADE PROJECT

Weekly Construction Report

SH16 CAUSEWAY UPGRADE PROJECT


WEEKLY CONSTRUCTION REPORT No.10
22 February 2013
Prepared by: Glenn Houpapa (Construction Manager)

Construction Health Chart


All works performed safely Minor safety issues present Major safety issues on project
Safety
X
All actions on target Minor elements behind Major items behind
Work Ready Status
X
All resources available Some role issues evident Delays from resourcing issues
Resources
X

Recent Progress / Achievements


SAFETY
 Key issues . . .
 The ICAM for the Prodrill incident released to DOL
 Draft Safety Plan to be reviewed and implemented
 Training . . .
 XX people inducted for the week
GENERAL
 NGA asset procurement - agreement expected by 25/2/13.
 Iwi Blessing date set for 7/3/13
 Staff mobilisation – refer attached histogram
 GEOTECH INVESTIGATIONS
 Nightshift works for 2012 scheduled to finish end of Feb
 Marine based geotech investigations to be completed late Feb
 UNDER BRIDGE INSPECTIONS
 All works completed
 Test results confirm design assumptions
AREA EAST [Zone 1 Causeway] – Mike Elliot
 ZONE 1
 Preliminary planning commenced for Zone 1 Traherne Island area
 Interfacing with Geotech designers continues
 Construction programme continues to be developed
 Procurement strategies for wick drains required
AREA WEST - Zones 2 and 3
 SITE COMPOUND / TAPC
 Scope determined with TAPC – works commence next week
 Design plans developed for access, site works and compound offices to be confirmed
 Issue with SW drainage to be resolved
 Procurement of buildings and IT critical
 TTM planning to relocate cycleway to shoulder of SH16 WB
 Planning to establish site compound at Yard 2
 Preliminary discussions held with Raceway Stakeholders wrt to RW’s in this area
 Critical - Property handover dates required by NZTA
GNRI – Andrew Strong
 Scope definition continues to develop with NZTA and WCA
 Weekly meetings with WCA coordinated

1
SH16 CAUSEWAY UPGRADE PROJECT
Weekly Construction Report

 TTM MX-design 75% complete


 WCA for basalt revetment rock declined due to compliance and coordination issues
Structures – Travis Skaines
 Northern VE option at WRB declined
 WRB western access option needs to be revisited internally and with NZTA
 Staging design, temp works designer required
 Work method / construction staging plans developed
 Programme to be developed – 80% Complete
 Decision required in terms of construction staging wrt to building north or southern widening sequence –
North option preferred pending outcome of SW Access discussion with NZTA above
TRAFFIC MANAGEMENT – Dave Philip, Pauline Nobbs
 Daily TTM operations being managed without issue
 MX modelling and detailed TTM staging 75$ complete
 Draft CTMP needs review for approval / acceptance
 Draft departure for 3.1m lanes prepared for review
 Coordination meetings with WCA being held weekly
 TTM applications required for the following approvals:
 Pedestrian relocations
 Bus lane closures
 Closing of T2 lanes at GNRI and Pakiti
CONSENTS & PLANNING, COMM’S
 Non-notified alteration to consent approved
 Team coordination continues regarding early work activities
 Matters relating to stability bund and recovery of materials to be confirmed
DESIGN COORDINATION
 50% design packages forthcoming
 Twice weekly design review sessions coordinated
Risk items to be aware of: Actions:
 Site office building procurement GH / RC
 IT provisions
 TTM closure applications
 Property handover dates with NZTA
 WRB western access agreement with NZTA

Other Issues Arising: Actions:


 Draft Procurement Schedule in progress TS
 Team working with Patrick for development of Incite systems (Lots/RFI/NCR) TS / ME / HM