0% found this document useful (0 votes)
1K views1 page

Earth Pit No-Earth Value: Date of Check: Next Due Date

The document outlines the steps required to check individual and total grid earthing resistance at an area, including performing resistance checks on individual pits and the total grid, repairing any damaged pits, installing a temporary supportive pit to check grids individually, ensuring the supportive pit has the same resistance as the grid being disconnected, connecting the supportive grid before disconnecting the main grid, potentially improving earth connectivity through soil treatment, labeling each pit with details like an identification number and earth value, using calibrated testing equipment and providing certification of the checks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views1 page

Earth Pit No-Earth Value: Date of Check: Next Due Date

The document outlines the steps required to check individual and total grid earthing resistance at an area, including performing resistance checks on individual pits and the total grid, repairing any damaged pits, installing a temporary supportive pit to check grids individually, ensuring the supportive pit has the same resistance as the grid being disconnected, connecting the supportive grid before disconnecting the main grid, potentially improving earth connectivity through soil treatment, labeling each pit with details like an identification number and earth value, using calibrated testing equipment and providing certification of the checks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

1.

 Individual earth pit resistance check to be done.

2.       Total grid earthing resistance check required.

3.       Damage earthing pit repairing required.

4.       Supportive earth pit (Temporary pit) required to check the individual grid.

5.       Supportive earth pit earth resistance must be same to the grid to be disconnected.

6.       After the supportive earth grid is ready and tested it must be connected to the supporting grid before disconnected the main grid.

7.       As per the earth value for Area 30 ,may required to improve the earth connectivity using soil treatment.

8.       Each earthing pit must be colour, and paint the following details as file attached.

9.       Contractor should sent competent electrical personal to do the job with valid calibrated earth tester.

10.   All the required tools and equipment to do the job will be on contractor scope.

11.   Certificate with earth pit identification number to be mentioned clearly.

EARTH PIT NO-

EARTH VALUE:

DATE OF CHECK:

NEXT DUE DATE:

You might also like