1.
Individual earth pit resistance check to be done.
2. Total grid earthing resistance check required.
3. Damage earthing pit repairing required.
4. Supportive earth pit (Temporary pit) required to check the individual grid.
5. Supportive earth pit earth resistance must be same to the grid to be disconnected.
6. After the supportive earth grid is ready and tested it must be connected to the supporting grid before disconnected the main grid.
7. As per the earth value for Area 30 ,may required to improve the earth connectivity using soil treatment.
8. Each earthing pit must be colour, and paint the following details as file attached.
9. Contractor should sent competent electrical personal to do the job with valid calibrated earth tester.
10. All the required tools and equipment to do the job will be on contractor scope.
11. Certificate with earth pit identification number to be mentioned clearly.
EARTH PIT NO-
EARTH VALUE:
DATE OF CHECK:
NEXT DUE DATE: