Project: Bldg (G+1+PH) on Plot # 477 @ Maysalon , Sharjah .
Client: : SHEIK SULTAN SAEED MAJID AL QASSIMI.
Consultant : International Engineering Consultant .
Contractor : ................................. Building Cont.
Bill Of Quantities ( BOQ )
Rate Amount
SN Description Unit Qty Remarks
( AED ) ( AED )
B1 Preliminary Works :
B1.1 Mobilization L.S. 1 150,000 150,000
B1.2 Site Expenses during Construction ( Running Cost ) L.S. 1 30,000 30,000
B1.3 De-Mobilization & Handing Over L.S. 1 15,000 15,000
B1.4 Tender Fees for Consultant L.S. 1 0 0
Total of Bill # 1 195,000
B2 Earth Works:
B2.1 Excavation ( up to LVL = -4.15 m ) M³ 6,500 15 97,500
B2.2 Removal of the Result of excavation from the site M³ 1,120 25 28,000
B2.3 Refilling with the Result of excavation M³ 5,380 20 107,600
B2.4 Refilling with Imported Materials M³ 0 0
B2.5 Road base M³ 300 90 27,000
Total of Bill # 2 260,100
B3 Shoring Works:
B3.1 Shoring Works LS 0 Excluded
B3.2 Dewatering Works LS 0 Excluded
Total of Bill # 3 0
B4 RCC Substructure Works:
B4.1 PCC for Raft, ... etc. M³ 130 500 65,000
B4.2 RCC for Raft, . M³ 500 1,200 600,000
B4.3 RCC for Strap Beam . M³ 20 1,300 26,000
B4.4 RCC for Tie Beam. M³ 50 1,300 65,000
B4.5 RCC for Neck Columns & wall. M³ 65 1,300 84,500
B4.6 Floor concrete with BRC mesh M³ 160 750 120,000
B4.7 R.C.C. for U.G.W. Tanks M³ 55 1,250 68,750
B4.8 Solid block works M³ 600 85 51,000
B4.9 Septic Tank LS 1 25,000 25,000
Total of Bill # 4 1,105,250
B5 Water Proof for Substructure :
B5.1 Polythene sheets LS 1 10,000 10,000
B5.2 Water Proofing for Substructure Works LS 1 40,000 40,000
Water Proofing for U.G.W.Tank ( Single layer 2mm Membrane + Protection
B5.4 M² 170 80 13,600
Board )
B5.5 GRP Linning for UGW Tank M² 142 80 11,360
B5.6 Water Stopper agent for UGW Tank R.M. 38 70 2,660
B5.7 Anti-termite treatment. L.S. 1 10,000 10,000
Total of Bill # 5 87,620
B6 RCC Super Structure Works :
B6.1 RCC Columns M³ 105 1,350 141,750
B6.2 RCC Walls M³ 97 1,350 130,950
B6.3 RCC Beams M³ 60 1,250 75,000
B6.4 RCC Slabs M³ 770 1,250 962,500
B6.5 RCC Parapets M³ 60 1,200 72,000
B6.6 RCC Staircase M³ 40 1,250 50,000
B6.7 R.C.C.Lintels /Arches L.S. 1 15,000 15,000
Total of Bill # 6 1,432,200
B7 Block Works :
B7.1 100 mm thick hollow block work M² 860 85 73,100
B7.2 200 mm thick hollow block work M² 1,708 95 162,260
B7.3 200 mm thick thermal insulation block work M² 1,300 110 143,000
Total of Bill # 7 378,360
Rate Amount
SN Description Unit Qty Remarks
( AED ) ( AED )
B8 Floors Finishes :
Marble Floors. ( Supply P. C. = 160 Dhs. / m² )
B8.1 M² 0
Main Enterance , Lift Lobby @ Gr Floor.
Ceramic Floors ( Supply P. C. = 30 Dhs. / m² ) Lift Lobby @ Typ
B8.2 M² 0
Floors .
Ceramic Floors For Shops,Watchman room @ Gr Flr,Living,Bed room &
B8.3 balacony @ Typ Flrs ( Supply P. C. = 30 Dhs. / m² ) M² 0
Ceramic Floors Pump , Garbage @ Gr and Typ Floor .
B8.4 M² 0
( Supply PC = 20 Dhs. / m² ),
Ceramic Floors ( Supply PC = 30 Dhs. / m² ), Bathrooms & Kitchens @ Typ
B8.5 M² 0
Floor
Ceramic Floors Tele ,Store,O.T.S @ Gr & Typ Flrs Machine Rooms @
B8.6 M² 0
Roof .( Supply PC = 20 Dhs. / m² ),
B8.7 Screed + Raised Floors Elec. @ Typ Flrs . M² 0
B8.8 Mosaic Tiles Roof M² 0
B8.8 Screed concrete for service room and shops @ Gr. Flr. M² 0
B8.8 Skid Epoxy Resin Floors For Drive way & Car Parking M² 0
Skirtings : 0
B8. 10 Marble Skirting @ " Gr & Typ . R.M. 0
B8.11 Ceramic Skirting R.M. 0
Landing & Steps : 0
B8.15 Marble landing @ Gr Floor ( Supply P. C = 40 Dhs. / m' ). M² 0
B8.15 Mosaic landing @ Typ Floor M² 0
Thresholds : 0
B8.17 Thresholds, 20 cm R.M. 0
B8.18 Thresholds, 10 cm R.M. 0
Total of Bill # 8 0
B9 Internal Walls Finishes :
B9.1 Plaster for internal walls M² 8,000 40 320,000
B9.2 Marble ( Supp. PC= 160 Dhs. / m² ), Main Entrance & Lift lobby @ Gr. M² 0
B9.2 Ceramic Tiles ( Supp. PC= 30 Dhs. / m² ), Lift lobby @ TYP. M² 0
B9.3 Ceramic Tiles Bathrooms & Kitchens . ( Supply PC = 30 Dhs. / m² ) M² 0
B9.4 Ceramic Tiles ( P. C. = 20 Dhs./m² ), Garbage M² 0
B9.5 Emulsion National Paint ( internall walls ). M² 0
B9.6 Semi Epoxy ( O.T.S ) & Car Parking M² 0
Total of Bill # 9 320,000
B10 Ceillings Finishes :
B10.1 c/s Plaster for Ceilings M² 1,900 35 66,500
B10.2 Gypsum Board with Decoration For Entrance @ Gr Flr . M² 0
B10.3 Gypsum Board For Corridor & Flat Entrance @ Typ . M² 0
B10.5 60 x 60 cm Gypsum vinyleTiles, ( Baths & Kitchens ) ( P.C =30 DHS /m2 ) M² 0
B10.6 Emulsion National Paint . M² 0
B10.7 Epoxy Paint for Car Praking . M² 0
Total of Bill # 10 66,500
B11 External Finishes :
B11.1 Plaster For Elevations M² 800 50 40,000
B11.2 Epoxy Paint M² 0
B11.3 Elegan Stone Paint . M² 0
Total of Bill # 11 40,000
B12 Joinery Works :
B12.1 D1: 100 x 220, Solid Flush Door , Floor & Flat Entrance( P. C. = 1,200 Dhs ). Nos 0
B12.2 D1*: 100 x 220, Solid Flush Door , Stair case .( P. C. = 1,200 Dhs ) Nos 0
B12.3 D1** :80 x 220 Semi Solid flush, Roof Stair Case .( P. C. = 1,200 Dhs ) Nos 0
B12.4 D2: 90 x 220 Semi Solid Flush, Bed room / living .( P. C. = 800 Dhs ) Nos 0
B12.5 D2a: 80 x 220 Semi Solid Flush, Kitchen .( P. C. = 800 Dhs ) Nos 0
B12.6 D3: 70 x 220 Semi Solid Flush, Bath / WC .( P. C. = 800 Dhs ) Nos 0
B12.7 D3a: 85 x 220 Semi Solid Flush, Store .( P. C. = 800 Dhs ) Nos 0
B12.8 Locks & Handles ( Ext. Doors ) ( P. C. = 125 Dhs ) Nos 0
B12.9 Locks & Handles ( Int. Doors ) ( P. C. = 55 Dhs ) Nos 0
B12.10 Wardrobes 0
Total of Bill # 12 0
Rate Amount
SN Description Unit Qty Remarks
( AED ) ( AED )
B13 Aluminum & Metal Works :
B13.1 Aluminum & Glazing ( Doors, Windows, Curtain Walls & H / Rails ) L.S. 1 0
Total of Bill # 13 0
B14 Plumbing & Drainage Works :
B14.1 Plumbing ( Water Supply & Drainage System ) L.S. 1 300,000 300,000
Total of Bill # 14 300,000
B15 Sanitary Fitting & Mixers : :
B15.1 Set Type 1 ( W/B) Nos 0
B15.2 Set Type 2 ( W/C+W/B+Shower) ( P. C. = 1,500 Dhs /Set ). Nos 0
B15.3 Set Type 3 ( W/C+W/B+Bath tup) ( P. C. = 1,500 Dhs /Set ). Nos 0
B15.4 Set Type 4 ( W/C ) Nos 0
B15.5 Set Type 5 ( W/C+W/B) Nos 0
Total of Bill # 15 0
B16 Electrical Works :
Electrical System Works ( Conduits. Wiring, Cables,
B16.1 L.S. 1 500,000 500,000
Switches, Sockets,DBs,…etc )
B16.2 Standbye Generator & ATS P.S. 0
B16.3 Attendence, Builder Works & Profit for Light Fittings LS 1 10% 50,000
B16.4 Exhaust Fans L.S. 1 0 Included
B16.5 Ceiling Fans N/I 0 Excluded
B16.6 Light Fittings L.S. 1 0 Excluded
B16.7 Attendence, Builder Works & Profit for Light Fittings LS 1 15% 0 Excluded
B16.8 Transformers N/A 0 Excluded
Total of Bill # 16 550,000
B17 Fire Alarm & Fighting System :
B17.1 Fire Alarm System L.S. 1
B17.2 Fire Fighting System ( including : Extinguishers, FHR, Sprinkler System, …etc ) L.S. 1 700,000 700,000
B17.3 Emergency Lights L.S. 1
Total of Bill # 17 L.S. 700,000
B18 A/C Works:
B18.1 A/C Works L.S. 1 0 Excluded
B18.2 Attendence, Builder Works & Profit % 10%
Total of Bill # 18 L.S. 0
B19 Conveying Systems :
B19.1 Elevators ( P. Sum = 300,000 DHS ) L.S. 1 125,000 125,000 Excluded
B19.2 Attendence, Builder Works & Profit % 10% 12,500
Total of Bill # 19 137,500
B19 Gas Works :
B19.1 Gas Works ( P. Sum = 300,000 DHS ) L.S. 1 100,000 100,000
B19.2 Attendence, Builder Works & Profit % 10% 10,000
B20 Gas Works L.S. 110,000
B21 Kitchen Cabinets Works :
Kitchen Cabinets . " HPL , including : Caracasses, Shelves,
B21.1 Back Panels, drawers, work top marble, all accessories ..etc"
B21.2 Wall Unit ( P. C. = 750 Dhs. / m). R.M. 0
B21.3 Base Unit ( P. C. = Dhs. / m ). . R.M. 0
B21.4 S/s Steel Sink Nos 0 Included
B21.5 Sink Mixers Nos 0 Included
B21.6 Cooker Hoods Nos 0
Total of Bill # 21 0
Rate Amount
SN Description Unit Qty Remarks
( AED ) ( AED )
B22 Roofing & Waterproofing Works :
B22.1 Insulation System for Roof ( W/P, Heat Insulation & Tiles ) M² 1,100 110 121,000
B22.2 Water proofing for Wet Areas. M² 300 70 21,000
Total of Bill # 22 142,000
B23 Special Works :
B23.1 Garbage Refusal System ( P.Sum = 35,000 ) P.S. 0
B23.2 Attendence, Builder Works & Profit % 5% 0
Total of Bill # 23 0
B24 Low Current Systems Works :
B24.1 TV Systems P.S. 0
B24.2 Attendence, Builder Works & Profit % 20% 0
B24.4 Traffic Barrier L.S. 0
Total of Bill # 24 0
B25 Miscell. Works :
B25.1 Internal signage L.S. 1 0
B25.2 External signage L.S. 1 0
B25.3 Mirrors L.S. 1 0 included in Sanitary Sets
B25.6 Rubber Protection for Columns L.S. 1 0
B25.7 Car Park Marking L.S. 1 0
B25.8 Kerbstone for Car Parking L.S. 1 0
Total of Bill # 25 0
B26 External Works :
B26.1 Manholes L.S. 1 0
B26.2 8 cm interlock for setback & carparking M² 600 80 48,000
B26.3 6 cm interlock for foot path M² 200 80 16,000
B26.4 Kerbstone R.M. 220 90 19,800
Total of Bill # 26 83,800
Project: Bldg (G+….P+…..) on Plot # …….. @ ……….. , Sharjah .
Client: : …………………………………
Consultant :INTERNATIONAL Engineering Consultant .
Contractor : ……………………….
Summary of BOQ
Total Amount
SN Description % Remarks
( AED )
B1 Preliminary Works 195,000 3.30%
B2 Earth works 260,100 4.40%
B3 Shoring Works 0 0.00%
B4 RCC for Sub Structure Works 1,105,250 18.71%
B5 Water Proofing for Sub-Structure 87,620 1.48%
B6 RCC for Super Structure Works 1,432,200 24.24%
B7 Block Works 378,360 6.40%
B8 Floors Finishes 0 0.00%
B9 Walls Finishes 320,000 5.42%
B10 Ceiling Finishes 66,500 1.13%
B11 External Finishes 40,000 0.68%
B12 Joinery Works 0 0.00%
B13 Aluminum & Metal works 0 0.00%
B14 Plumbing and Drainage Works 300,000 5.08%
B15 Sanitary Wares 0 0.00%
B16 Electrical Works 550,000 9.31%
B17 Fire Alarm & Fire Fighting System 700,000 11.85%
B18 A/C Works 0 0.00%
B19 Conveying Systems 137,500 2.33%
B20 Gas Works 110,000 1.86%
B21 Kitchen Cabinets Works 0 0.00%
B22 Roofing & Waterproofing Works 142,000 2.40%
B23 Special Works ( Garbage Works ) 0 0.00%
B24 Low Current Systems 0 0.00%
B25 Miscell Works 0 0.00%
B26 External Works 83,800 1.42%
GRAND TOTAL 5,908,330 100.00%
Built Up Area ( Sq. Ft ) = 31,725
Rate ( AED / Sq. Ft. ) = 186.24