1. Students will develop bidding documents for a civil works construction project based on standard templates. This will include a detailed scope of work, bid forms, and evaluation criteria for selecting the winning bidder. 2. Procedures for contract administration such as claims management, dispute resolution, and arbitration will be proposed based on typical contract conditions. 3. An excel sheet will evaluate the bids and demonstrate how the winning bidder was selected based on the evaluation criteria.

Uploaded by

hassan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views2 pages

CE-476 Complex Engineering Problem

1. Students will develop bidding documents for a civil works construction project based on standard templates. This will include a detailed scope of work, bid forms, and evaluation criteria for selecting the winning bidder. 2. Procedures for contract administration such as claims management, dispute resolution, and arbitration will be proposed based on typical contract conditions. 3. An excel sheet will evaluate the bids and demonstrate how the winning bidder was selected based on the evaluation criteria.

Uploaded by

hassan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Complex Engineering Problem – CE-476 Construction

Contract Management
Learning Objectives of Complex Engineering Problem:
Taxonomy
Term project on complex engineering problem Domain PLO
Level
Develop bidding documents for civil works based
on PEC standard bidding document harmonized
1 with FIDIC. The documents are to include detailed Cognitive 5 11
scope of works, bid forms, evaluation criteria and
contract award.
Propose suitable Contract Administration
procedure including claims management,
2 settlement of disputes, and preparations for Cognitive 5 2
arbitration proceedings based upon FIDIC contract
conditions.
Analyze the complex engineering problem by
preparing an excel sheet that demonstrates the
3 Cognitive 4 11
detailed evaluation criteria and final contract
award to the most responsive bidder.

Notes:
1. Group project – 4x members
2. Each group to select a unique construction project (real or hypothetical)
3. Detail scope of work to be a part of bidding document that demonstrates the
bidder the work to be performed during construction
4. Contract Forms to be included but not limited to
a. Form of Bid Security
b. Form of Performance Security
c. Form of Contract Agreement
d. Form of Mobilization Advance Guarantee
5. Following Appendices to be included but not limited to:
a. Proposed Construction Schedule
b. Method of performing the work
c. List of major equipment
d. List of Subcontractor
e. Construction Camps and housing facilities
f. Integrity Pact
6. Contract Conditions including:
a. General Conditions of Contract including but not limited to:
i. Definitions
ii. THE ENGINEER’S duties and authority
iii. Contractor’s General Obligations
iv. Performance Security
v. Progress Report
vi. Security of the Site
vii. Commencement, Delays and Suspension
viii. Tests on Completion
ix. Employer’s Taking Over
x. Defects Liability
xi. Measurement and Evaluation
xii. Variations and Adjustments
xiii. Contract Price and Payment
xiv. Insurance
xv. Claims. Disputes and Arbitration
b. Particular Conditions of Contract
i. Contract Data
ii. Specific Provisions

Deliverables:
1. General Scope of Work
2. Bid Forms
3. Conditions of Contract
4. Final Report
5. Presentation

Deadline: 6th May 2019