0% found this document useful (0 votes)
989 views1 page

Inspection Checklist - M&E (2.03.2018) - 7

The document is an inspection report for cable/wire installation at an unspecified project location. It details the inspection criteria under three categories: 1) preparatory works to ensure approved materials are used and cables show no damage, 2) proper installation including cable tray alignment and protection of cables, and 3) completion including fire stops and protection from paint. The report records the inspection results and any non-conformances needing re-inspection.

Uploaded by

Encik Muhammad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
989 views1 page

Inspection Checklist - M&E (2.03.2018) - 7

The document is an inspection report for cable/wire installation at an unspecified project location. It details the inspection criteria under three categories: 1) preparatory works to ensure approved materials are used and cables show no damage, 2) proper installation including cable tray alignment and protection of cables, and 3) completion including fire stops and protection from paint. The report records the inspection results and any non-conformances needing re-inspection.

Uploaded by

Encik Muhammad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

MC/MEP/Cable

RFWI No. :

Cable/ Wire Installation


Reference Drawing Attached : YES / NO

Project Name : 1st 2nd (Re-Inspection)

Location/ Gridline/ Area : dd/mm/yy dd/mm/yy

1) Preparatory Works SC MC CR SC MC CR

a) Approved materials (type, brand, size, etc.)


b) No visible damage to cable/ wire

2) Installation of Cable/ Wire SC MC CR SC MC CR

a) Cable tray/ ladder/ trunking alignment properly installed


b) Adequate space for cable/ wire
c) Cable/ wire is marked/ numbered
d) Cable/ wire is concealed (where applicable)
e) Connection of conductors checked and accepted
f) Routing of cables/ wires in safe zones
g) Properly earthed
h) Connector provided for other trade/ fixtures (i.e. lighting)

3) Others SC MC CR SC MC CR

a) Fire stop at wall penetration area completely done according to specification


b) Completed works protected from any paint drops/ stains
c) Sufficient headroom clearance according to drawing

Remark for Failure / Re-inspection :

Non-Conformance Report (NCR) Raised During Inspection / Re-inspection

NCR No.: _______________________________________________ Closed Outstanding

Inspected & Confirmed by : Sub-Contractor Main Contractor Consultant Representatives

Signature

Name
Designation
Date
Inspection Status :  = Acceptable, X = Not Acceptable, - = Not Applicable