Checklist For Installation of Chemical Fire Suppression System

This document is a checklist for installing, testing, and commissioning a wet chemical fire suppression system for kitchen hoods. The checklist outlines 10 items to inspect, including verifying that materials and equipment are installed properly according to approved submittals and drawings, pipes and ducts are the correct size and slope, joints are sealed correctly, cylinders are installed as specified, control heads and valves are positioned properly, pull stations are installed correctly, fusible links have the right rating and clearance, and nozzles are the proper type and positioned correctly. Upon completion of inspections, the subcontractor, contractor, and consultant must sign off to confirm quality assurance and quality control.

Uploaded by

beho2000
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
3K views1 page

Checklist For Installation of Chemical Fire Suppression System

This document is a checklist for installing, testing, and commissioning a wet chemical fire suppression system for kitchen hoods. The checklist outlines 10 items to inspect, including verifying that materials and equipment are installed properly according to approved submittals and drawings, pipes and ducts are the correct size and slope, joints are sealed correctly, cylinders are installed as specified, control heads and valves are positioned properly, pull stations are installed correctly, fusible links have the right rating and clearance, and nozzles are the proper type and positioned correctly. Upon completion of inspections, the subcontractor, contractor, and consultant must sign off to confirm quality assurance and quality control.

Uploaded by

beho2000
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

Project Name

CHECK LIST FOR:


Ref. No:
Installation, Testing & Commissioning of Wet Chemical Fire Rev. No: 0
Suppression System for Kitchen Hoods (Installation) Page : 1 of 1
SUBCONTRACTOR X CONTRACTOR

SECTION OF WORK: MECHANICAL LOCATION:


LEVEL: WIR No.:

STAGE ITEM Checked by Checked Date


by
S/C CONT CONSU
LTANT

SETTING OUT Check Layout


Check Level, elevations & distances.
MEP/CIVIL Check for Services Clearances

INSTALLATION 1. Check materials are as per


approved material submittal.
2. Check that all equipment &
components has been installed,
levelled, piped & anchored.
3. Check that size of pipe/ ducts is as
per approved drawing.
4. Check that the levels and slope of
installed pipes are as per approved
shop drawing.
5. Check that all joints are made
properly and are clean.
6. Check the type, pressure &
installation of Cylinder as per the
approved installation details or as
recommended by the manufacturer.
7. Check the installation of Control
Head & Control Valve Assembly.
8. Check all installation of Remote
Release Pull Station.
9. Check Fusible Links Rating & are
properly fitted with enough
clearances.
10. Check type of all nozzles and are
positioned properly.
For S/C QA/QC: Date: FOR CONT. Date: For CONSULTANT Date:
QA/QC: Rep.:

Name: Sign: Name: Sign: Name: Sign: