Earned Value Analysis Tutorial
Earned Value Analysis Tutorial
Dennis J. Frailey
1.0 Overview
1.1 Background
In the midst of a typical project, it is often desirable to estimate such
quantities as “how much time is left?” or “how much of the work is complete?”
or “how much money will the project spend before it is complete?” If these
remind you of trips in the family car where the children are wondering “are we
there yet?”, it is not surprising. Just as the passengers on a trip wonder how
long it will take to get to the destination, so managers have a responsibility to
understand how long a project will take to get to its destination - and what it
will cost. Those working on the project usually want to know this too.
Earned Value Analysis (EVA) is a way to measure the amount of work actually
performed on a project (i.e., to measure its progress) and to forecast a
project’s cost and date of completion. The method relies on a key measure
known as the earned value (also known as the “budgeted cost of worked
performed” or BCWP). This measure enables one to compute performance
indices for cost and schedule, which tell how well the project is doing relative
to its original plans. These indices also enable one to forecast how the project
will do in the future.
Earned value actually uses three data values, which are computed each week,
month, or whatever other period you wish to use. We use the term “analysis
date” to refer to the date when the three values are analyzed. Thus if we
measure these values monthly, an analysis date of October 31 would include all
values from project inception until the end of October.
____________________________________________________________________________________________________
Tutorial on Earned Value Management Page 1
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved
Software Project Management EVA_Tutorial
This is the cost originally budgeted to accomplish the work that has been
completed as of the analysis date. It answers the question “how much work has
actually been completed?”.
This is the total budgeted cost up to the analysis date. It answers the question
“how much did we plan to spend as of this date?” A variant of this question is
“how much work should have been completed by this date?” BCWS can be
computed from the project’s plans, as illustrated in the sequel, or it can be
approximated by multiplying the total budget by the fraction of total project
duration at the analysis date. Thus, for example, if the project budget is $100
and 20% of the project’s time has elapsed, the approximate BCWS is $20.
This is what it actually cost to accomplish all the work completed as of the
analysis date. It answers the question “how much have we actually spent?”. This
is usually determined from the organization’s accounting system, or can often
be approximated by multiplying the number of people by the number of hours
or days or weeks worked.
Four measures can be computed from the basic values described above:
2.1 Units
There are many ways to measure “cost”. For example, we could measure actual
money spent. However it is common in a work environment to measure cost in
terms of labor - that is in work hours or work days spent. Thus the budget for
a project could be $30,000 or it could be 300 labor hours, and the amount
spent so far could be $4,500 or it might be 45 labor hours. EVA can be used
with any measure of cost, but it is important to decide which one to use. We
will use an example in dollars in this section and an example in work days in the
sequel.
Plans:
40 cookies per batch
5 batches per hour (200 cookies)
Schedule: 5 hours to make a total of 1000 cookies
Budgeted cost per cookie is $0.05
Total budget is $50.00 for cookie ingredients, or $10 per hour
____________________________________________________________________________________________________
Tutorial on Earned Value Management Page 3
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved
Software Project Management EVA_Tutorial
Analysis:
BCWS = $10.00
BCWP = $7.50 (Earned Value) [150 cookies x .05 per cookie]
ACWP = $9.00 [from above]
Therefore:
SV = BCWP - BCWS = -$2.50 (you are behind schedule)
SPI = BCWP / BCWS = 0.75 (you are running at 75% of the planned
schedule)
CV = BCWP - ACWP = $7.50 - $9.00 = -$1.50 (you are $1.50 over budget)
CPI = BCWP / ACWP = 0.833 (you are running over budget by about 17%)
____________________________________________________________________________________________________
Tutorial on Earned Value Management Page 4
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved
Software Project Management EVA_Tutorial
In other words, you forecast that it will take 6 2/3 hours and $60 to make the
cookies, if your success at making them does not improve. Stripped of all the
verbiage, imagine someone telling you “at the rate you are going, it is going to
take you all day and it will cost more than you bargained for.” EVA enables you
to say that in more precise terms.
Perhaps for making cookies, such precision is not essential (although if the
prediction was 44 hours, you would have something to worry about!). But for
running an expensive project, EVA can be very helpful, even essential.
where EAC is the amount we estimate we will spend. Looking closely we see
that the numerator is how much work is left to do and the denominator is how
much we have left to spend. Note too that if EAC is simply IEAC, then the
TCPI is the same as the CPI - i.e., it indicates that if we do not change our
performance, IEAC is the correct estimate of our final cost. (Exercise for the
reader: prove mathematically that if EAC = IEAC then CPI = TCPI.)
____________________________________________________________________________________________________
Tutorial on Earned Value Management Page 5
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved
Software Project Management EVA_Tutorial
reasonable because we were able to get the first 200 cookies in the oven for
only $9 instead of the budgeted $10. But if TCPI had been 1.5, we would know
that we were in budget trouble unless we can somehow get our supplies at a
substantial discount over the plan!
____________________________________________________________________________________________________
Tutorial on Earned Value Management Page 6
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved
Software Project Management EVA_Tutorial
(The approach illustrated above relies on the judgment of the participants but
if the organization is at SEI CMM level 1 or 2, it may not utilize any
information from past projects other than the experience of the participants.
In an organization at CMM level 3, the micro schedule might be defined by
using the organization's (tailored) process. At level 4 or higher, it might be
defined by using the process, the judgment of the participants, and past
performance data.)
____________________________________________________________________________________________________
Tutorial on Earned Value Management Page 7
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved
Software Project Management EVA_Tutorial
Table 3 - Earned Value Data, Week ending Oct 29, 1999, Project XXX
Task Effort (value) (work days) % Complete Earned
Set Up 3 100 3
Get Specs 2 50 1
Design Output 10 25 2.5
Plan Tests 3 0 0
Write Code 5 0 0
Unit Test 3 0 0
Integrate 2 0 0
Beta Test 3 0 0
TOTAL 31 6.5 (BCWP)
BCWP or earned value is the total of the “earned” column on the right hand
side. Table 3 is recomputed each week, whereas tables 1 and 2 need only be
done once. BCWP will increase each week as the project progresses. At any
given week, you have the BCWS from table 2 and the BCWP from table 3.
ACWP is whatever number of person-days of work have actually been paid for.
____________________________________________________________________________________________________
Tutorial on Earned Value Management Page 8
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved
Software Project Management EVA_Tutorial
This is simply the week number multiplied by 5 (total days worked) multiplied
by the number of people, if everyone works full time on just this project. If
people share their time between projects or work on non-project activities,
their “actual” work hours spent on the project must be determined
proportionally.
Then:
SV = BCWP - BCWS = -.50 (you are behind schedule)
SPI = BCWP / BCWS = 0.928 (you are running at about 93% of the planned
schedule)
CV = BCWP - ACWP = 6.5 - 10 = -3.50 (you are 3.5 staff days over budget)
CPI = BCWP / ACWP = 0.65 (you are running over budget by about 35%)
Forecasts:
IEAC = BAC / CPI = 31/0.65 = 47.7 work days
VAC = BAC - IEAC = 31 - 48 = -17 (17 work days over budget)
ISAC = 10 / SPI = 10 / 0.928 = 10.7 work weeks
In short, your project looks like it will come in about a week late and 35% over
budget. What should you do now?
At this point, things look pretty dismal for meeting the cost budget. You need
to ask yourself these questions:
Why is it taking more effort than planned?
Did they underestimate the job?
Are they losing too much productivity because they are being shared
between this project and something else?
Were there unforseen obstacles and, if so, have they been
corrected?
Is there some other reason?
____________________________________________________________________________________________________
Tutorial on Earned Value Management Page 9
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved
Software Project Management EVA_Tutorial
Was work performed on other tasks, but not enough to claim partial
credit yet on table 3? Maybe things aren’t quite as bad as they look
The key point here is that EVA enables you to spot a potential problem early in
the project and do something to correct the situation. You can also re-
estimate the total project duration and cost at this point, or negotiate changes
in the project with your management.
Another option is to re-estimate the schedule and base all future calculations
on this new schedule. (In effect, this is what automatically happens with EVA
-- in the end, the new schedule is whatever the actual schedule happens to be.)
Of course with this approach you never have a very good method of predicting
how much the schedule overrun will be.
A third option is to develop a new index, DPI or Delivery Performance Index, as
an alternative to SPI. DPI is based on the original completion schedules of the
individual work tasks. The specific terms and formulas are as follows:
____________________________________________________________________________________________________
Tutorial on Earned Value Management Page 10
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved
Software Project Management EVA_Tutorial
This is harder to do and many accounting systems do not have a mechanism for
keeping track of the necessary information. Further definition can be found in
(Hudec, 1996) in the references. Working out how to use DPI instead of SPI is
a good exercise for the reader.
7.0 References
Bent, James A (1982). Applied Cost and Schedule Control. New York, NY:
Marcel Dekker, Inc.
Horan, Ron and Don McNichols (1990, September). "Project Management for
Large Scale Systems." Business Communications Review 20:1924.
Mahler, Fred and Mark Mazina (1982, February). "Earned Value Reporting
Earns Its Keep." Cost Engineering 24:13-17.
Niemann, William J (1982, May-June). "If the Pharaoh had Only Used an
Earned Value System in Building the Pyramids." Program Manager 11:15.
____________________________________________________________________________________________________
Tutorial on Earned Value Management Page 11
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved
Software Project Management EVA_Tutorial
Objective: The objective of this exercise is to compute earned value metrics and
use them to evaluate a project.
Background: Read the Tutorial on Earned Value Management Systems that
accompanies this exercise. Consider the project described in section 5 of the
tutorial. Suppose the table on the next page is an updated version of table 3:
(note that ACWP is shown at the bottom)
Task 1: Fill in the values for BCWP, SV, SPI, CV, CPI, IEAC, VAC, SAC and TCPI
for each of weeks 1-6 (use the space provided in the shaded portion of the table).
Task 2: On the last page of this exercise, draw a line graph of BCWS, BCWP, and
ACWP for each week. I.e., the horizontal axis is week, starting at 0 and going to
12, and the vertical values are in units of work days. There will be three lines;
BCWS, BCWP, and ACWP. Extend BCWS to week 10 to show the original plan for
completing the 31 units of work.
Task 3: Considering these metrics and graphs, indicate whether the project is
ahead of or behind schedule and over or under budget, as of week 6, and indicate
what you believe the final cost and schedule will be. Put those answers here:
The project is: __________________ schedule and _________________ budget
Final Cost is projected to be __________________________________ because
(explain why here)
Deliverable: A copy of this exercise in which you have filled in the answers to the
various questions that are posed in the tasks above and the table and space below.
Put the answers exactly where indicated above.
_________________________________________________________________________________________________________
Tutorial on Earned Value Management Page 12
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved
Software Project Management EVA_Tutorial
Design 10 0 0 25 50 75 100
Output
Plan Tests 3 0 0 0 25 25 50
Write Code 5 0 0 0 0 25 50
Unit Test 3 0 0 0 0 0 0
Integrate 2 0 0 0 0 0 0
Beta Test 3 0 0 0 0 0 0
TOTAL 31
BCWS 3 5 7 11 15 18
BCWP
ACWP 3 7 10 15 18 22
SV
SPI
CV
CPI
BAC 31 31 31 31 31 31
IEAC
VAC
SAC
TCPI
_________________________________________________________________________________________________________
Tutorial on Earned Value Management Page 13
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved
Software Project Management EVA_Tutorial
_________________________________________________________________________________________________________
Tutorial on Earned Value Management Page 14
Copyright © 1999-2001, Dennis J. Frailey, All Rights Reserved