2019 Grid Code
2019 Grid Code
ISSUE 5
REVISION 38
4 September 2019
© 2013 Copyright owned by National Grid Electricity System Operator Limited, all rights reserved.
No part of this publication may be reproduced in any material form (including photocopying and restoring in any
medium or electronic means and whether or not transiently or incidentally) without the written permission of
National Grid Electricity System Operator Limited, except:
1. to the extent that any party who is required to comply (or is exempt from complying) with the provisions
under the Electricity Act 1989 reasonably needs to reproduce this publication to undertake its licence or
statutory duties within Great Britain (or any agent appointed so to act on that party’s behalf); and
2. in accordance with the provisions of the Copyright, Designs and Patents Act 1988.
THE GRID CODE
CONTENTS
CONTENTS* (C)
PREFACE* (P)
REVISIONS* (R)
*does not constitute part of the Grid Code
P.1. The Grid Code sets out the operating procedures and principles governing the relationship
between The Company and all Users of the National Electricity Transmission System, be
they Generators, DC Converter owners, Suppliers or Non-Embedded Customers. The
Grid Code specifies day-to-day procedures for both planning and operational purposes and
covers both normal and exceptional circumstances.
GD.1 In the Grid Code the following words and expressions shall, unless the subject matter or
context otherwise requires or is inconsistent therewith, bear the following meanings:
Access Group A group of Connection Points within which a User declares under the
Planning Code
(a) An interconnection and/or
(b) A need to redistribute Demand between those Connection Points
either pre-fault or post-fault
Where a single Connection Point does not form part of an Access Group
in accordance with the above, that single Connection Point shall be
considered to be an Access Group in its own right.
Access Period A period of time in respect of which each Transmission Interface Circuit
is to be assessed as whether or not it is capable of being maintained as
derived in accordance with PC.A.4.1.4. The period shall commence and
end on specified calendar weeks.
Act The Electricity Act 1989 (as amended by the Utilities Act 2000 and the
Energy Act 2004).
Active Energy The electrical energy produced, flowing or supplied by an electric circuit
during a time interval, being the integral with respect to time of the
instantaneous power, measured in units of watt-hours or standard
multiples thereof, ie:
1000 Wh = 1 kWh
1000 kWh = 1 MWh
1000 MWh = 1 GWh
1000 GWh = 1 TWh
Active Power The product of voltage and the in-phase component of alternating current
measured in units of watts and standard multiples thereof, ie:
1000 Watts = 1 kW
1000 kW = 1 MW
1000 MW = 1 GW
1000 GW = 1 TW
AF Rules Has the meaning given to “allocation framework” in section 13(2) of the
Energy Act 2013.
Alternate Member Shall mean an alternate member for the Panel Members elected or
appointed in accordance with this GR.7.2(a) or (b).
Ancillary Services An agreement between a User and The Company for the payment by The
Agreement Company to that User in respect of the provision by such User of
Ancillary Services.
Annual Average Cold A particular combination of weather elements which gives rise to a level of
Spell Conditions or ACS peak Demand within a Financial Year which has a 50% chance of being
Conditions exceeded as a result of weather variation alone.
Apparent Power The product of voltage and of alternating current measured in units of
voltamperes and standard multiples thereof, ie:
1000 VA = 1 kVA
1000 kVA = 1 MVA
Apparatus Other than in OC8, means all equipment in which electrical conductors are
used, supported or of which they may form a part. In OC8 it means High
Voltage electrical circuits forming part of a System on which Safety
Precautions may be applied to allow work and/or testing to be carried out
on a System.
Approved Fast Track Has the meaning given in GR.26.7, provided that no objection is received
Proposal pursuant to GR.26.12.
Authorised Certifier An entity that issues Equipment Certificates and Power Generating
Module Documents and whose accreditation is given by the national
affiliate of the European cooperation for Accreditation (‘EA’), established
in accordance with Regulation (EC) No 765/2008 of the European
Parliament and of the Council ( 1 ).
Authorised Electricity Any person (other than The Company) who is authorised under the Act
Operator to generate, participate in the transmission of, distribute or supply
electricity which shall include any Interconnector Owner or
Interconnector User
Automatic Voltage The continuously acting automatic equipment controlling the terminal
Regulator or AVR voltage of a Synchronous Generating Unit or Synchronous Power
Generating Module by comparing the actual terminal voltage with a
reference value and controlling by appropriate means the output of an
Exciter, depending on the deviations.
Authority for Access An authority which grants the holder the right to unaccompanied access to
sites containing exposed HV conductors.
Authority, The The Authority established by section 1 (1) of the Utilities Act 2000.
Auxiliaries Any item of Plant and/or Apparatus not directly a part of the boiler plant
or Power Generating Module or Generating Unit or DC Converter or
HVDC Equipment or Power Park Module, but required for the boiler
plant's or Power Generating Module’s or Generating Unit's or DC
Converter’s or HVDC Equipment’s or Power Park Module’s functional
operation.
Auxiliary Diesel Engine A diesel engine driving a Power Generating Module or Generating Unit
which can supply a Unit Board or Station Board, which can start without
an electrical power supply from outside the Power Station within which it
is situated.
Auxiliary Gas Turbine A Gas Turbine Unit, which can supply a Unit Board or Station Board,
which can start without an electrical power supply from outside the Power
Station within which it is situated.
Average Conditions That combination of weather elements within a period of time which is the
average of the observed values of those weather elements during
equivalent periods over many years (sometimes referred to as normal
weather).
Back-Up Protection A Protection system which will operate when a system fault is not cleared
by other Protection.
Balancing Code or BC That portion of the Grid Code which specifies the Balancing Mechanism
process.
Balancing Mechanism Has the meaning set out in The Company’s Transmission Licence
Balancing Principles A statement prepared by The Company in accordance with Condition C16
Statement of The Company’s Transmission Licence.
Baseline Forecast Has the meaning given to the term ‘baseline forecase’ in Section G of the
BSC.
Black Start The procedure necessary for a recovery from a Total Shutdown or Partial
Shutdown.
Black Start Capability An ability in respect of a Black Start Station, for at least one of its
Gensets to Start-Up from Shutdown and to energise a part of the System
and be Synchronised to the System upon instruction from The
Company, within two hours, without an external electrical power supply.
Black Start Contract An agreement between a Generator and The Company under which the
Generator provides Black Start Capability and other associated
services.
Black Start Stations Power Stations which are registered, pursuant to the Bilateral
Agreement with a User, as having a Black Start Capability.
Black Start Test A Black Start Test carried out by a Generator with a Black Start Station,
on the instructions of The Company, in order to demonstrate that a Black
Start Station has a Black Start Capability.
Block Load Capability The incremental Active Power steps, from no load to Rated MW, which a
generator can instantaneously supply without causing it to trip or go
outside the Frequency range of 47.5 – 52Hz (or an otherwise agreed
Frequency range). The time between each incremental step shall also be
provided.
BM Unit Has the meaning set out in the BSC, except that for the purposes of the
Grid Code the reference to “Party” in the BSC shall be a reference to User.
BM Unit Data The collection of parameters associated with each BM Unit, as described
in Appendix 1 of BC1.
British Standards or BS Those standards and specifications approved by the British Standards
Institution.
BSC Panel Has meaning set out for “Panel” in the BSC.
BS Station Test A Black Start Test carried out by a Generator with a Black Start Station
while the Black Start Station is disconnected from all external alternating
current electrical supplies.
BS Unit Test A Black Start Test carried out on a Generating Unit or a CCGT Unit or
a Power Generating Module, as the case may be, at a Black Start
Station while the Black Start Station remains connected to an external
alternating current electrical supply.
Business Day Any week day (other than a Saturday) on which banks are open for
domestic business in the City of London.
Capacity Market The Capacity Market Rules, The Electricity Capacity Regulations 2014
Documents and any other Regulations made under Chapter 3 of Part 2 of the Energy
Act 2013 which are in force from time to time.
Capacity Market Rules The rules made under section 34 of the Energy Act 2013 as modified from
time to time in accordance with that section and The Electricity Capacity
Regulations 2014.
Cascade Hydro Scheme The matrix described in Appendix 1 to BC1 under the heading Cascade
Matrix Hydro Scheme Matrix.
CfD Counterparty A person designated as a “CfD counterparty” under section 7(1) of the
Energy Act 2013.
CfD Documents The AF Rules, The Contracts for Difference (Allocation) Regulations 2014,
The Contracts for Difference (Definition of Eligible Generator) Regulations
2014 and The Contracts for Difference (Electricity Supplier Obligations)
Regulations 2014 and any other regulations made under Chapter 2 of Part
2 of the Energy Act 2013 which are in force from time to time.
in either case to carry out any of the CFD settlement activities (or any
successor entity performing CFD settlement activities).
CCGT Module Matrix The matrix described in Appendix 1 to BC1 under the heading CCGT
Module Matrix.
CCGT Module Planning A matrix in the form set out in Appendix 3 of OC2 showing the combination
Matrix of CCGT Units within a CCGT Module which would be running in relation
to any given MW output.
Closed Distribution A distribution system classified pursuant to Article 28 of Directive
System or CDSO 2009/72/EC as a Closed Distribution System by the Authority which
distributes electricity within a geographically confined industrial,
commercial or shared services site and does not supply household
Customers, without prejudice to incidental use by a small number of
households located within the area served by the System and with
employment or similar associations with the owner of the System.
CM Settlement Body the Electricity Settlements Company Ltd or such other person as may from
time to time be appointed as Settlement Body under regulation 80 of the
Electricity Capacity Regulations 2014.
CM Settlement Services any person with whom the CM Settlement Body has entered into a
Provider contract to provide services to it in relation to the performance of its
functions under the Capacity Market Documents.
Combined Cycle Gas A collection of Generating Units (registered as a CCGT Module (which
Turbine Module or could be within a Power Generating Module) under the PC) comprising
CCGT Module one or more Gas Turbine Units (or other gas based engine units) and one
or more Steam Units where, in normal operation, the waste heat from the
Gas Turbines is passed to the water/steam system of the associated
Steam Unit or Steam Units and where the component units within the
CCGT Module are directly connected by steam or hot gas lines which
enable those units to contribute to the efficiency of the combined cycle
operation of the CCGT Module.
Commercial Ancillary Ancillary Services, other than System Ancillary Services, utilised by
Services The Company in operating the Total System if a User (or other person
such as a Demand Response Provider) has agreed to provide them
under an Ancillary Services Agreement or under a Bilateral Agreement
with payment being dealt with under an Ancillary Services Agreement or
in the case of Externally Interconnected System Operators or
Interconnector Users, under any other agreement (and in the case of
Externally Interconnected System Operators and Interconnector
Users includes ancillary services equivalent to or similar to System
Ancillary Services).
Committed Level The expected Active Power output from a BM Unit after accepting a Bid-
Offer Acceptance or RR Instruction or a combination of Bid-Offer
Acceptances and RR Instructions
Committed Project Data relating to a User Development once the offer for a CUSC Contract
Planning Data is accepted.
Common Collection A busbar within a Power Park Module to which the higher voltage side of
Busbar two or more Power Park Unit generator transformers are connected.
Completion Date Has the meaning set out in the Bilateral Agreement with each User to
that term or in the absence of that term to such other term reflecting the
date when a User is expected to connect to or start using the National
Electricity Transmission System. In the case of an Embedded Medium
Power Station or Embedded DC Converter Station or Embedded
HVDC System having a similar meaning in relation to the Network
Operator’s System as set out in the Embedded Development
Agreement.
Compliance Processes That portion of the Grid Code which is identified as the Compliance
or CP Processes.
Compliance Statement A statement completed by the relevant User confirming compliance with
each of the relevant Grid Code provisions, and the supporting evidence in
respect of such compliance, of its:
Generating Unit(s); or,
Power Generating Modules (including DC Connected Power Park
Modules); or,
CCGT Module(s); or,
Power Park Module(s); or,
DC Converter(s); or
HVDC Systems; or
Plant and Apparatus at an EU Grid Supply Point owned or operated by a
Network Operator; or
Network Operator’s entire distribution System where such Network
Operator’s distribution System comprises solely of Plant and Apparatus
procured on or after 7 September 2018 and was connected to the
National Electricity Transmission System on or after 18 August 2019. In
this case, all connections to the National Electricity Transmission System
would comprise only of EU Grid Supply Points; or
Plant and Apparatus at an EU Grid Supply Point owned or operated by a
Non-Embedded Customer where such Non-Embedded Customer is
defined as an EU Code User;
in the form provided by The Company to the relevant User or another
format as agreed between the User and The Company.
Configuration 1 AC One or more Offshore Power Park Modules that are connected to an
Connected Offshore AC Offshore Transmission System and that AC Offshore
Power Park Module Transmission System is connected to only one Onshore substation
and which has one or more Interface Points.
Configuration 2 AC One or more Offshore Power Park Modules that are connected to a
Connected Offshore meshed AC Offshore Transmission System and that AC Offshore
Power Park Module Transmission System is connected to two or more Onshore
substations at its Transmission Interface Points.
Configuration 1 DC One or more DC Connected Power Park Modules that are connected to
Connected Power Park an HVDC System or Transmission DC Converter and that HVDC
Module System or Transmission DC Converter is connected to only one
Onshore substation and which has one or more Interface Points.
Configuration 2 DC One or more DC Connected Power Park Modules that are connected to
Connected Power Park an HVDC System or Transmission DC Converter and that HVDC
Module System or Transmission DC Converter is connected to only more than
one Onshore substation at its Transmission Interface Points.
Connected Planning Data which replaces data containing estimated values assumed for
Data planning purposes by validated actual values and updated estimates for
the future and by updated forecasts for Forecast Data items such as
Demand.
Connection Point A Grid Supply Point or Grid Entry Point, as the case may be.
Connection Site A Transmission Site or User Site, as the case may be.
Consumer Means the person appointed by the Citizens Advice or the Citizens
Representative Advice Scotland (or any successor body) representing all categories of
customers, appointed in accordance with GR.4.2(b)
Contingency Reserve The margin of generation over forecast Demand which is required in the
period from 24 hours ahead down to real time to cover against
uncertainties in Large Power Station availability and against both weather
forecast and Demand forecast errors.
Control Calls A telephone call whose destination and/or origin is a key on the control
desk telephone keyboard at a Transmission Control Centre and which,
for the purpose of Control Telephony, has the right to exercise priority
over (ie. disconnect) a call of a lower status.
Control Centre A location used for the purpose of control and operation of the National
Electricity Transmission System or DC Converter Station owner's
System or HVDC System Owner’s System or a User System other than
a Generator's System or an External System.
Control Engineer A person nominated by the relevant party for the control of its Plant and
Apparatus.
Control Person The term used as an alternative to "Safety Co-ordinator" on the Site
Responsibility Schedule only.
Core Industry Document In relation to a Core Industry Document, the body(ies) or entity(ies)
Owner responsible for the management and operation of procedures for making
changes to such document
CUSC Framework Has the meaning set out in The Company’s Transmission Licence
Agreement
CUSC Party As defined in the The Company’s Transmission Licence and “CUSC
Parties” shall be construed accordingly.
Customer Demand The level above which a Supplier has to notify The Company of its
Management proposed or achieved use of Customer Demand Management which is
Notification Level 12 MW in England and Wales and 5 MW in Scotland.
Data Registration Code That portion of the Grid Code which is identified as the Data Registration
or DRC Code.
Data Validation, The rules relating to validity and consistency of data, and default data to
Consistency and be applied, in relation to data submitted under the Balancing Codes, to
Defaulting Rules be applied by The Company under the Grid Code as set out in the
document “Data Validation, Consistency and Defaulting Rules” - Issue 8,
dated 25th January 2012. The document is available on the National Grid
website or upon request from The Company.
DC Connected Power A Power Park Module that is connected to one or more HVDC Interface
Park Module Points.
De-Load The condition in which a Genset has reduced or is not delivering electrical
power to the System to which it is Synchronised.
𝛥𝑓 Deviation from Target Frequency
Demand The demand of MW and Mvar of electricity (i.e. both Active and Reactive
Power), unless otherwise stated.
Demand Aggregation A process where one or more Demand Facilities or Closed Distribution
Systems can be controlled by a Demand Response Provider either as a
single facility or Closed Distribution System for the purposes of offering
one or more Demand Response Services.
Demand Control Any or all of the following methods of achieving a Demand reduction:
(a) Customer voltage reduction initiated by Network Operators (other
than following an instruction from The Company);
(b) Customer Demand reduction by Disconnection initiated by
Network Operators (other than following an instruction from The
Company);
(c) Demand reduction instructed by The Company;
(d) automatic low Frequency Demand Disconnection;
(e) emergency manual Demand Disconnection.
Demand Control The level above which a Network Operator has to notify The Company
Notification Level of its proposed or achieved use of Demand Control which is 12 MW in
England and Wales and 5 MW in Scotland.
Demand Facility A facility which consumes electrical energy and is connected at one or
more Grid Supply Points to the National Electricity Transmission System
or connection points to a Network Operator’s System. A Network
Operator’s System and/or auxiliary supplies of a Power Generating
Module do no constitute a Demand Facility.
Demand Facility Owner A person who owns or operates one or more Demand Units within a
Demand Facility. A Demand Facility Owner who owns or operates a
Demand Facility which is directed connected to the Transmission System
shall be treated as a Non Embedded Customer.
Demand Response Demand within a Demand Facility or Closed Distribution System that is
Active Power Control available for modulation by The Company or Network Operator or
Relevant Transmission Licensee, which results in an Active Power
modification.
The above Demand Response Services are not exclusive and do not
preclude Demand Response Providers from negotiating other services
for demand response capability with The Company. Where such
services are negotiated they would still be treated as a Demand
Response Service.
Demand Response That portion of the Grid Code which is identified as the Demand
Services Code (DRSC) Response Services Code being applicable to Demand Response
Providers.
Demand Response A Demand Response Service derived from a Demand within one or more
System Frequency Demand Facilities or Closed Distribution Systems that is available for the
Control reduction or increase in response to Frequency fluctuations, made by an
autonomous response from those Demand Facilities or Closed
Distribution Systems to diminish these fluctuations.
Demand Response Unit A document, issued either by the Non Embedded Customer, Demand
Document (DRUD) Facility Owner or the CDSO to The Company or the Network Operator
(as the case may be) for Demand Units with demand response and
providing a Demand Response Service which confirms the compliance of
the Demand Unit with the technical requirements set out in the Grid
Code and provides the necessary data and statements, including a
statement of compliance.
Demand Response Very A Demand Response Service derived from a Demand within a Demand
Fast Active Power Facility or Closed Distribution System that can be modulated very fast
Control in response to a Frequency deviation, which results in a very fast Active
Power modification.
Detailed Planning Data Detailed additional data which The Company requires under the PC in
support of Standard Planning Data, comprising DPD I and DPD II
Detailed Planning Data The Detailed Planning Data categorised as such in the DRC and EDRC,
Category I or DPD I and submitted in accordance with PC.4.4.2 or PC.4.4.4 as applicable.
Detailed Planning Data The Detailed Planning Data categorised as such in the DRC and EDRC,
Category II or DPD II and submitted in accordance with PC.4.4.2 or PC.4.4.4 as applicable.
Discrimination The quality where a relay or protective system is enabled to pick out and
cause to be disconnected only the faulty Apparatus.
Disconnection The physical separation of Users (or Customers) from the National
Electricity Transmission System or a User System as the case may be.
Disputes Resolution The procedure described in the CUSC relating to disputes resolution.
Procedure
Droop The ratio of the per unit steady state change in speed, or in Frequency to
the per unit steady state change in power output. Whilst not mandatory, it
is often common practice to express Droop in percentage terms.
Dynamic Parameters Those parameters listed in Appendix 1 to BC1 under the heading BM Unit
Data – Dynamic Parameters.
E&W Offshore A person who owns or operates an E&W Offshore Transmission System
Transmission Licensee pursuant to a Transmission Licence.
E&W User A User in England and Wales or any Offshore User who owns or
operates Plant and/or Apparatus connected (or which will at the OTSUA
Transfer Time be connected) to an E&W Offshore Transmission
System.
Earth Fault Factor At a selected location of a three-phase System (generally the point of
installation of equipment) and for a given System configuration, the ratio
of the highest root mean square phase-to-earth power Frequency voltage
on a sound phase during a fault to earth (affecting one or more phases at
any point) to the root mean square phase-to-earth power Frequency
voltage which would be obtained at the selected location without the fault.
Earthing Device A means of providing a connection between a conductor and earth being
of adequate strength and capability.
Elected Panel Members Shall mean the following Panel Members elected in accordance with
GR4.2(a):
(a) the representative of the Suppliers;
(b) the representative of the Onshore Transmission Licensees;
(c) the representative of the Offshore Transmission Licensees; and
(d) the representatives of the Generators
Electricity Council That body set up under the Electricity Act, 1957.
Electricity Distribution The licence granted pursuant to Section 6(1) (c) of the Act.
Licence
Electricity Supply The unincorporated members' club of that name formed inter alia to
Industry Arbitration promote the efficient and economic operation of the procedure for the
Association resolution of disputes within the electricity supply industry by means of
arbitration or otherwise in accordance with its arbitration rules.
Embedded Having a direct connection to a User System or the System of any other
User to which Customers and/or Power Stations are connected, such
connection being either a direct connection or a connection via a busbar
of another User or of a Relevant Transmission Licensee (but with no
other connection to the National Electricity Transmission System).
Embedded Person The party responsible for a Medium Power Station not subject to a
Bilateral Agreement or DC Converter Station not subject to a Bilateral
Agreement or HVDC System not subject to a Bilateral Agreement
connected to or proposed to be connected to a Network Operator’s
System.
EMR Administrative Has the meaning given to “administrative parties” in The Electricity
Parties Capacity Regulations 2014 and each CfD Counterparty and CfD
Settlement Services Provider.
EMR Documents The Energy Act 2013, The Electricity Capacity Regulations 2014, the
Capacity Market Rules, The Contracts for Difference (Allocation)
Regulations 2014, The Contracts for Difference (Definition of Eligible
Generator) Regulations 2014, The Contracts for Difference (Electricity
Supplier Obligations) Regulations 2014, The Electricity Market Reform
(General) Regulations 2014, the AF Rules and any other regulations or
instruments made under Chapter 2 (contracts for difference), Chapter 3
(capacity market) or Chapter 4 (investment contracts) of Part 2 of the
Energy Act 2013 which are in force from time to time.
EMR Functions Has the meaning given to “EMR functions” in Chapter 5 of Part 2 of the
Energy Act 2013.
Engineering The documents referred to as such and issued by the Energy Networks
Recommendations Association or the former Electricity Council.
Estimated Registered Those items of Standard Planning Data and Detailed Planning Data
Data which either upon connection will become Registered Data, or which for
the purposes of the Plant and/or Apparatus concerned as at the date of
submission are Registered Data, but in each case which for the seven
succeeding Financial Years will be an estimate of what is expected.
EU Transparency Such data as Customers and Generators are required to provide under
Availability Data Articles 7.1(a) and 7.1(b) and Articles 15.1(a), 15.1(b), 15.1(c), 15.1(d) of
European Commission Regulation (EU) No. 543/2013 respectively (known
as the Transparency Regulation), and which also forms part of DRC
Schedule 6 (Users’ Outage Data).
European Compliance That portion of the Grid Code which is identified as the European
Processes or ECP Compliance Processes.
European Connection That portion of the Grid Code which is identified as the European
Conditions or ECC Connection Conditions being applicable to EU Code Users.
Excitation System The equipment providing the field current of a machine, including all
regulating and control elements, as well as field discharge or suppression
equipment and protective devices.
Excitation System No- The minimum value of direct voltage that the Excitation System is able to
Load Negative Ceiling provide from its terminals when it is not loaded, which may be zero or a
Voltage negative value.
Excitation System Shall have the meaning ascribed to that term in IEC 34-16-1:1991
Nominal Response [equivalent to British Standard BS4999 Section 116.1 : 1992]. The time
interval applicable is the first half-second of excitation system voltage
response.
Excitation System On- Shall have the meaning ascribed to the term 'Excitation system on load
Load Positive Ceiling ceiling voltage' in IEC 34-16-1:1991[equivalent to British Standard
Voltage BS4999 Section 116.1 : 1992].
Excitation System No- Shall have the meaning ascribed to the term 'Excitation system no load
Load Positive Ceiling ceiling voltage' in IEC 34-16-1:1991[equivalent to British Standard
Voltage BS4999 Section 116.1 : 1992].
Existing AGR Plant The following nuclear advanced gas cooled reactor plant (which was
commissioned and connected to the Total System at the Transfer Date):-
(a) Dungeness B
(b) Hinkley Point B
(c) Heysham 1
(d) Heysham 2
(e) Hartlepool
(f) Hunterston B
(g) Torness
Existing AGR Plant In respect of each Genset within each Existing AGR Plant which has a
Flexibility Limit safety case enabling it to so operate, 8 (or such lower number which when
added to the number of instances of reduction of output as instructed by
The Company in relation to operation in Frequency Sensitive Mode
totals 8) instances of flexibility in any calendar year (or such lower or
greater number as may be agreed by the Nuclear Installations Inspectorate
and notified to The Company) for the purpose of assisting in the period of
low System NRAPM and/or low Localised NRAPM provided that in
relation to each Generating Unit each change in output shall not be
required to be to a level where the output of the reactor is less than 80%
of the reactor thermal power limit (as notified to The Company and which
corresponds to the limit of reactor thermal power as contained in the
"Operating Rules" or "Identified Operating Instructions" forming part of the
safety case agreed with the Nuclear Installations Inspectorate).
Existing Gas Cooled Both Existing Magnox Reactor Plant and Existing AGR Plant.
Reactor Plant
Export and Import Those parameters listed in Appendix 1 to BC1 under the heading BM Unit
Limits Data – Export and Import Limits.
Fault Current The time interval from fault inception until the end of the break time of the
Interruption Time circuit breaker (as declared by the manufacturers).
Fault Ride Through The capability of Power Generating Modules (including DC Connected
Power Park Modules) and HVDC Systems to be able to be able to
remain connected to the System and operate through periods of low
voltage at the Grid Entry Point or User System Entry Point caused by
secured faults
Fast Start A start by a Genset with a Fast Start Capability.
Fast Start Capability The ability of a Genset to be Synchronised and Loaded up to full Load
within 5 minutes.
Final Generation Outage An outage programme as agreed by The Company with each Generator
Programme and each Interconnector Owner at various stages through the
Operational Planning Phase and Programming Phase which does not
commit the parties to abide by it, but which at various stages will be used
as the basis on which National Electricity Transmission System
outages will be planned.
Final Report A report prepared by the Test Proposer at the conclusion of a System
Test for submission to The Company (if it did not propose the System
Test) and other members of the Test Panel.
Financial Year Bears the meaning given in Condition A1 (Definitions and Interpretation)
of The Company’s Transmission Licence.
Fixed Proposed The proposed date(s) for the implementation of a Grid Code Modification
Implementation Date Proposal or Workgroup Alternative Grid Code Modification such date
to be a specific date by reference to an assumed date by which a direction
from the Authority approving the Grid Code Modification Proposal or
Workgroup Alternative Grid Code Modification is required in order for
the Grid Code Modification Proposal or any Workgroup Alternative
Grid Code Modification, if it were approved, to be implemented by the
proposed date.
Flicker Severity A measure of the visual severity of flicker derived from the time series
(Short Term) output of a flickermeter over a 10 minute period and as such provides an
indication of the risk of Customer complaints.
Forecast Data Those items of Standard Planning Data and Detailed Planning Data
which will always be forecast.
Frequency The number of alternating current cycles per second (expressed in Hertz)
at which a System is running.
Frequency Containment means, in the context of Balancing Services, the active power reserves
Reserves (FCR) available to contain system frequency after the occurrence of an
imbalance.
Frequency Restoration means, in the context of Balancing Services, the active power reserves
Reserves (FRR) available to restore system frequency to the nominal frequency.
Governor Deadband An interval used intentionally to make the frequency control unresponsive
In the case of mechanical governor systems the Governor Deadband is
the same as Frequency Response Insensitivity
Governor Insensitivity The inherent feature of the control system specified as the minimum
magnitude of change in the frequency or input signal that results in a
change of output power or output signal
GSP Group Has the meaning as set out in the BSC
Frequency Sensitive Each Generating Unit in an Existing AGR Plant for which the Generator
AGR Unit has notified The Company that it has a safety case agreed with the
Nuclear Installations Inspectorate enabling it to operate in Frequency
Sensitive Mode, to the extent that such unit is within its Frequency
Sensitive AGR Unit Limit. Each such Generating Unit shall be treated
as if it were operating in accordance with BC3.5.1 provided that it is
complying with its Frequency Sensitive AGR Unit Limit.
Frequency Sensitive In respect of each Frequency Sensitive AGR Unit, 8 (or such lower
AGR Unit Limit number which when added to the number of instances of flexibility for the
purposes of assisting in a period of low System or Localised NRAPM
totals 8) instances of reduction of output in any calendar year as instructed
by The Company in relation to operation in Frequency Sensitive Mode
(or such greater number as may be agreed between The Company and
the Generator), for the purpose of assisting with Frequency control,
provided the level of operation of each Frequency Sensitive AGR Unit in
Frequency Sensitive Mode shall not be outside that agreed by the
Nuclear Installations Inspectorate in the relevant safety case.
Gas Turbine Unit A Generating Unit driven by a gas turbine (for instance by an aero-
engine).
Gas Zone Diagram A single line diagram showing boundaries of, and interfaces between, gas-
insulated HV Apparatus modules which comprise part, or the whole, of a
substation at a Connection Site (or in the case of OTSDUW Plant and
Apparatus, Transmission Interface Site), together with the associated
stop valves and gas monitors required for the safe operation of the
National Electricity Transmission System or the User System, as the
case may be.
GB Grid Supply Point A Grid Supply Point which is not an EU Grid Supply Point.
GB Synchronous Area The AC power System in Great Britain which connects User’s, Relevant
Transmission Licensee’s whose AC Plant and Apparatus is
considered to operate in synchronism with each other at each Connection
Point or User System Entry Point and at the same System Frequency.
General Conditions or That portion of the Grid Code which is identified as the General
GC Conditions.
Generating Plant The difference between Output Usable and forecast Demand.
Demand Margin
Generating Unit An Onshore Generating Unit and/or an Offshore Generating Unit which
could also be part of a Power Generating Module.
Generating Unit Data The Physical Notification, Export and Import Limits and Other
Relevant Data only in respect of each Generating Unit (which could be
part of a Power Generating Module):
(a) which forms part of the BM Unit which represents that Cascade
Hydro Scheme;
(b) at an Embedded Exemptable Large Power Station, where the
relevant Bilateral Agreement specifies that compliance with BC1
and/or BC2 is required:
(i) to each Generating Unit, or
(ii) to each Power Park Module where the Power Station
comprises Power Park Modules
Generator A person who generates electricity under licence or exemption under the
Act acting in its capacity as a generator in Great Britain or Offshore. The
term Generator includes a EU Generator and a GB Generator.
Generator Performance A diagram which shows the MW and Mvar capability limits within which a
Chart Generating Unit will be expected to operate under steady state
conditions.
Governance Rules or That portion of the Grid Code which is identified as the Governance
GR Rules.
Great Britain or GB The landmass of England and Wales and Scotland, including internal
waters.
Grid Code Fast Track A proposal to modify the Grid Code which is raised pursuant to GR.26 and
Proposals has not yet been approved or rejected by the Grid Code Review Panel.
Grid Code Modification The procedures for the modification of the Grid Code (including the
Procedures implementation of Approved Modifications) as set out in the
Governance Rules.
Grid Code Modification A proposal to modify the Grid Code which is not yet rejected pursuant to
Proposal GR.15.5 or GR.15.6 and has not yet been implemented.
Grid Code Objectives Means the objectives referred to in Paragraph 1b of Standard Condition
C14 of The Company’s Transmission Licence.
Grid Code Review Panel The panel with the functions set out in GR.1.2.
or Panel
Grid Code Review Panel The vote of Panel Members undertaken by the Panel Chairman in
Recommendation Vote accordance with Paragraph GR.22.4 as to whether in their view they
believe each proposed Grid Code Modification Proposal, or Workgroup
Alternative Grid Code Modification would better facilitate achievement
of the Grid Code Objective(s) and so should be made.
Grid Code Review Panel The vote of Panel Members undertaken by the Panel Chairman in
Self-Governance Vote accordance with GR.24.9 as to whether they believe each proposed Grid
Code Modification Proposal, as compared with the then existing provisions
of the Grid Code and any Workgroup Alternative Grid Code
Modification set out in the Grid Code Modification Self- Governance
Report, would better facilitate achievement of the Grid Code
Objective(s).
Grid Code Self- Grid Code Modification Proposals which satisfy the Self Governance
Governance Proposals Criteria.
Grid Entry Point An Onshore Grid Entry Point or an Offshore Grid Entry Point.
Issue 5 Revision 38 GD 04 September 2019
27 of 70
Grid Supply Point A point of supply from the National Electricity Transmission System to
Network Operators or Non-Embedded Customers which could be a GB
Grid Supply Point or an EU Grid Supply Point.
Headroom The Power Available (in MW) less the actual Active Power exported from
the Power Park Module (in MW).
High Voltage or HV For E&W Transmission Systems, a voltage exceeding 650 volts. For
Scottish Transmission Systems, a voltage exceeding 1000 volts.
Houseload Operation Operation which ensures that a Power Station is able to continue to
supply its in-house load in the event of System faults resulting in Power-
Generating Modules being disconnected from the System and tripped
onto their auxiliary supplies
HP Turbine Power Ratio of steady state mechanical power delivered by the HP turbine to the
Fraction total steady state mechanical power delivered by the total steam turbine at
Registered Capacity or Maximum Capacity.
Implementation Date Is the date and time for implementation of an Approved Modification as
specified in accordance with Paragraph GR.25.3.
Incident Centre A centre established by The Company or a User as the focal point in The
Company or in that User, as the case may be, for the communication and
dissemination of information between the senior management
representatives of The Company, or of that User, as the case may be,
and the relevant other parties during a Joint System Incident in order to
avoid overloading The Company's, or that User's, as the case may be,
existing operational/control arrangements.
Independent Back-Up A Back-Up Protection system which utilises a discrete relay, different
Protection current transformers and an alternate operating principle to the Main
Protection systems(s) such that it can operate autonomously in the event
of a failure of the Main Protection.
Independent Main A Main Protection system which utilises a physically discrete relay and
Protection different current transformers to any other Main Protection.
Indicated Constraint The difference between a constraint boundary transfer limit and the
Boundary Margin difference between the sum of BM Unit Maximum Export Limits and the
forecast of local Demand within the constraint boundary.
Indicated Imbalance The difference between the sum of Physical Notifications for BM Units
comprising Generating Units or CCGT Modules or Power Generating
Modules and the forecast of Demand for the whole or any part of the
System.
Indicated Margin The difference between the sum of BM Unit Maximum Export Limits
submitted and the forecast of Demand for the whole or any part of the
System
Instructor Facilities A device or system which gives certain Transmission Control Centre
instructions with an audible or visible alarm, and incorporates the means
to return message acknowledgements to the Transmission Control
Centre
Integral Equipment Test A test on equipment, associated with Plant and/or Apparatus, which takes
or IET place when that Plant and/or Apparatus forms part of a Synchronised
System and which, in the reasonable judgement of the person wishing to
perform the test, may cause an Operational Effect.
Intellectual Property" or Patents, trade marks, service marks, rights in designs, trade names,
"IPRs copyrights and topography rights (whether or not any of the same are
registered and including applications for registration of any of the same)
and rights under licences and consents in relation to any of the same and
all rights or forms of protection of a similar nature or having equivalent or
similar effect to any of the same which may subsist anywhere in the world.
Interconnector Owner Has the meaning given to the term in the Connection and Use of System
Code.
Interface Point Capacity The maximum amount of Active Power transferable at the Interface Point
as declared by a User under the OTSDUW Arrangements expressed in
whole MW.
Intermittent Power The primary source of power for a Generating Unit or Power Generating
Source Module that can not be considered as controllable, e.g. wind, wave or
solar.
IP Turbine Power Ratio of steady state mechanical power delivered by the IP turbine to the
Fraction total steady state mechanical power delivered by the total steam turbine at
Registered Capacity or Maximum Capacity.
Joint BM Unit Data Has the meaning set out in the BSC.
Joint System Incident An Event wherever occurring (other than on an Embedded Medium
Power Station or an Embedded Small Power Station) which, in the
opinion of The Company or a User, has or may have a serious and/or
widespread effect, in the case of an Event on a User(s) System(s) (other
than on an Embedded Medium Power Station or Embedded Small
Power Station), on the National Electricity Transmission System, and
in the case of an Event on the National Electricity Transmission
System, on a User(s) System(s) (other than on an Embedded Medium
Power Station or Embedded Small Power Station).
Key Safe Key A key unique at a Location capable of operating a lock, other than a
control lock, on a Key Safe.
Legal Challenge Where permitted by law a judicial review in respect of the Authority’s
decision to approve or not to approve a Grid Code Modification
Proposal.
Licence Standards Those standards set out or referred to in Condition C17 of The Company’s
Transmission Licence and/or Condition D3 and/or Condition E16 of a
Relevant Transmission Licensee’s Transmission Licence.
Load Factor The ratio of the actual output of a Generating Unit or Power Generating
Module to the possible maximum output of that Generating Unit or Power
Generating Module.
Load Management A block of Demand controlled by a Supplier or other party through the
Block means of radio teleswitching or by some other means.
Local Joint Restoration A plan produced under OC9.4.7.12 detailing the agreed method and
Plan procedure by which a Genset at a Black Start Station (possibly with other
Gensets at that Black Start Station) will energise part of the Total
System and meet complementary blocks of local Demand so as to form a
Power Island.
In Scotland, the plan may also: cover more than one Black Start Station;
include Gensets other than those at a Black Start Station and cover the
creation of one or more Power Islands.
Local Switching A procedure produced under OC7.6 detailing the agreed arrangements in
Procedure respect of carrying out of Operational Switching at Connection Sites
and parts of the National Electricity Transmission System adjacent to
those Connection Sites.
Localised Negative That margin of Active Power sufficient to allow transfers to and from a
Reserve Active Power System Constraint Group (as the case may be) to be contained within
Margin or Localised such reasonable limit as The Company may determine.
NRAPM
Low Frequency Relay Has the same meaning as Under Frequency Relay.
Low Voltage or LV For E&W Transmission Systems a voltage not exceeding 250 volts. For
Scottish Transmission Systems, a voltage exceeding 50 volts but not
exceeding 1000 volts.
LV Side of the Offshore Unless otherwise specified in the Bilateral Agreement, the busbar on the
Platform Offshore Platform (typically 33kV) at which the relevant Offshore Grid
Entry Point is located.
Main Plant and In respect of a Power Station (including Power Stations comprising of
Apparatus DC Connected Power Park Modules) is one or more of the principal
items of Plant or Apparatus required to convert the primary source of
energy into electricity.
In respect of HVDC Systems or DC Converters or Transmission DC
Converters is one of the principal items of Plant or Apparatus used to
convert high voltage direct current to high voltage alternating current or
vice versa.
In respect of a Network Operator’s equipment or a Non-Embedded
Customer’s equipment, is one of the principal items of Plant or Apparatus
required to facilitate the import or export of Active Power or Reactive
Power to or from a Network Operator’s or Non Embedded Customer’s
System.
Market Operation Data A computer system operated by The Company and made available for
Interface System use by Customers connected to or using the National Electricity
(MODIS) Transmission System for the purpose of submitting EU Transparency
Availability Data to The Company.
Market Suspension Has the meaning given to the term ‘Market Suspension Threshold’ in
Threshold Section G of the BSC.
Materially Affected Party Any person or class of persons designated by the Authority as such.
Maximum Export The maximum continuous Active Power that a Network Operator or Non
Capability Embedded Customer can export to the Transmission System at the Grid
Supply Point, as specified in the Bilateral Agreement.
Maximum Export The maximum continuous Apparent Power expressed in MVA and
Capacity maximum continuous Active Power expressed in MW which can flow from
an Offshore Transmission System connected to a Network Operator's
User System, to that User System.
Maximum Capacity or The maximum continuous Active Power which a Power Generating
Pmax Module can produce, less any demand associated solely with facilitating
the operation of that Power Generating Module and not fed into the
System.
Maximum Generation A service utilised by The Company in accordance with the CUSC and the
Service or MGS Balancing Principles Statement in operating the Total System.
Maximum Generation An agreement between a User and The Company for the payment by The
Service Agreement Company to that User in respect of the provision by such User of a
Maximum Generation Service.
Maximum Import The maximum continuous Active Power that a Network Operator or Non
Capability Embedded Customer can import from the Transmission System at the
Grid Supply Point, as specified in the Bilateral Agreement.
Maximum Import The maximum continuous Apparent Power expressed in MVA and
Capacity maximum continuous Active Power expressed in MW which can flow to
an Offshore Transmission System connected to a Network Operator's
User System, from that User System.
Medium Voltage or MV For E&W Transmission Systems a voltage exceeding 250 volts but not
exceeding 650 volts.
Mills Milling plant which supplies pulverised fuel to the boiler of a coal fired
Power Station.
Minimum Generation The minimum output (in whole MW) which a Genset can generate or DC
Converter at a DC Converter Station can import or export to the Total
System under stable operating conditions, as registered with The
Company under the PC (and amended pursuant to the PC). For the
avoidance of doubt, the output may go below this level as a result of
operation in accordance with BC3.7.
Minimum Active Power The minimum continuous Active Power which an HVDC System can
Transmission Capacity exchange with the System at each Grid Entry Point or User System
(PHmin) Entry Point as specified in the Bilateral Agreement or as agreed
between The Company and the HVDC System Owner
Minimum Regulating The minimum Active Power, as specified in the Bilateral Agreement or
Level as agreed between The Company and the Generator, down to which the
Power Generating Module can control Active Power;
Minimum Stable The minimum Active Power, as specified in the Bilateral Agreement or
Operating Level as agreed between The Company and the Generator, at which the Power
Generating Module can be operated stably for an unlimited time.
Mothballed HVDC An HVDC System that has previously imported or exported power which
System the HVDC System Owner plans not to use to import or export power for
the remainder of the current Financial Year but which could be returned
to service.
Mothballed HVDC An HVDC Converter which is part of an HVDC System that has previously
Converter imported or exported power which the HVDC System Owner plans not to
use to import or export power for the remainder of the current Financial
Year but which could be returned to service.
Mothballed Generating A Generating Unit that has previously generated which the Generator
Unit plans not to use to generate for the remainder of the current Financial
Year but which could be returned to service. For the avoidance of doubt
a Mothballed Generating Unit could be part of a Power Generating
Module.
Mothballed Power A Power Generating Module that has previously generated which the
Generating Module Generator plans not to use to generate for the remainder of the current
Financial Year but which could be returned to service.
Mothballed Power Park A Power Park Module that has previously generated which the Generator
Module plans not to use to generate for the remainder of the current Financial
Year but which could be returned to service.
MSID Has the meaning a set out in the BSC, covers Metering System Identifier
National Demand The amount of electricity supplied from the Grid Supply Points plus:-
• that supplied by Embedded Large Power Stations, and
• National Electricity Transmission System Losses,
minus:-
• the Demand taken by Station Transformers and Pumped Storage
Units’
and, for the purposes of this definition, does not include:-
• any exports from the National Electricity Transmission System
across External Interconnections.
National Electricity The Onshore Transmission System and, where owned by Offshore
Transmission System Transmission Licensees, Offshore Transmission Systems.
National Electricity The amount of electricity supplied from the Grid Supply Points plus:-
Transmission System
Demand • that supplied by Embedded Large Power Stations, and
• exports from the National Electricity Transmission System
across External Interconnections, and
• National Electricity Transmission System Losses,
and, for the purposes of this definition, includes:-
• the Demand taken by Station Transformers and Pumped Storage
Units.
National Electricity Has the meaning set out in Schedule 1 of The Company's Transmission
Transmission System Licence.
Operator Area
National Electricity A computer file produced by The Company which in The Company’s view
Transmission System provides an appropriate representation of the National Electricity
Study Network Data File Transmission System for a specific point in time. The computer file will
contain information and data on Demand on the National Electricity
Transmission System and on Large Power Stations including Genset
power output consistent with Output Usable and The Company’s view of
prevailing system conditions.
National Electricity A warning issued by The Company, in accordance with OC7.4.8.7, which
Transmission System is intended to provide short term notice, where possible, to those Users
Warning - Demand who are likely to receive Demand reduction instructions from The
Control Imminent Company within 30 minutes.
National Electricity A warning issued by The Company, in accordance with OC7.4.8.6, which
Transmission System is intended to alert recipients that there is a high risk of Demand reduction
Warning - High Risk of being implemented and which may normally result from an Electricity
Demand Reduction Margin Notice.
National Electricity A warning issued by The Company, in accordance with OC7.4.8.5, which
Transmission System is intended to invite a response from and to alert recipients to a decreased
Warning - Electricity System Margin.
Margin Notice
National Electricity A warning issued by The Company, in accordance with OC7.4.8.8, which
Transmission System is intended to alert Users of the risk of widespread and serious System
Warning - Risk of disturbance which may affect Users.
System Disturbance
Network Data The data to be provided by The Company to Users in accordance with
the PC, as listed in Part 3 of the Appendix to the PC.
Network Operator A person with a User System directly connected to the National
Electricity Transmission System to which Customers and/or Power
Stations (not forming part of the User System) are connected, acting in
its capacity as an operator of the User System, but shall not include a
person acting in the capacity of an Externally Interconnected System
Operator or a Generator in respect of OTSUA.
NGET National Grid Electricity Transmission plc (NO: 2366977) whose registered
office is at 1-3 Strand, London, WC2N 5EH
No-Load Field Voltage Shall have the meaning ascribed to that term in IEC 34-16-1:1991
[equivalent to British Standard BS4999 Section 116.1 : 1992].
Non-Embedded A Customer in Great Britain, except for a Network Operator acting in its
Customer capacity as such, receiving electricity direct from the Onshore
Transmission System irrespective of from whom it is supplied.
Normal CCGT Module A CCGT Module other than a Range CCGT Module.
Novel Unit A tidal, wave, wind, geothermal, or any similar, Generating Unit.
Offshore Means wholly or partly in Offshore Waters, and when used in conjunction
with another term and not defined means that the associated term is to be
read accordingly.
Offshore DC Converter Any User Apparatus located Offshore used to convert alternating current
electricity to direct current electricity, or vice versa. An Offshore DC
Converter is a standalone operative configuration at a single site
comprising one or more converter bridges, together with one or more
converter transformers, converter control equipment, essential protective
and switching devices and auxiliaries, if any, used for conversion.
Offshore HVDC Any User Apparatus located Offshore used to convert alternating current
Converter electricity to direct current electricity, or vice versa. An Offshore HVDC
Converter is a standalone operative configuration at a single site
comprising one or more converter bridges, together with one or more
converter transformers, converter control equipment, essential protective
and switching devices and auxiliaries, if any, used for conversion.
Offshore Generating Unless otherwise provided in the Grid Code, any Apparatus located
Unit Offshore which produces electricity, including, an Offshore
Synchronous Generating Unit and Offshore Non-Synchronous
Generating Unit which could also be part of a Power Generating
Module..
Offshore Platform A single structure comprising of Plant and Apparatus located Offshore
which includes one or more Offshore Grid Entry Points.
Offshore Power Park A collection of one or more Offshore Power Park Strings (registered as
Module a Power Park Module under the PC). There is no limit to the number of
Power Park Strings within the Power Park Module, so long as they
either:
(a) connect to the same busbar which cannot be electrically split; or
(b) connect to a collection of directly electrically connected busbars of
the same nominal voltage and are configured in accordance with the
operating arrangements set out in the relevant Bilateral
Agreement.
Offshore Power Park A collection of Offshore Generating Units or Power Park Units that are
String powered by an Intermittent Power Source, joined together by cables
forming part of a User System with a single point of connection to an
Offshore Transmission System. The connection to an Offshore
Transmission System may include a DC Converter or HVDC Converter.
Offshore Tender The process followed by the Authority to make, in prescribed cases, a
Process determination on a competitive basis of the person to whom an offshore
transmission licence is to be granted.
Offshore Transmission Such person in relation to whose Transmission Licence the standard
Licensee conditions in Section E (offshore transmission owner standard conditions)
of such Transmission Licence have been given effect, or any person in
that prospective role who has acceded to the STC.
Offshore Transmission A system consisting (wholly or mainly) of high voltage electric lines and
System used for the transmission of electricity from one Power Station to a sub-
station or to another Power Station or between sub-stations, and includes
any Plant and Apparatus (including OTSUA) and meters in connection
with the transmission of electricity but does not include any Remote
Transmission Assets. An Offshore Transmission System extends from
the Interface Point, or the Offshore Grid Entry Point(s) and may include
Plant and Apparatus located Onshore and Offshore and, where the
context permits, references to the Offshore Transmission System
includes OTSUA.
Offshore Transmission In relation to a particular User where the OTSDUW Arrangements apply,
System Development means those activities and/or works for the design, planning, consenting
User Works or OTSDUW and/or construction and installation of the Offshore Transmission
System to be undertaken by the User as identified in Part 2 of Appendix I
of the relevant Construction Agreement.
Offshore Transmission OTSDUW Plant and Apparatus constructed and/or installed by a User
System User Assets or under the OTSDUW Arrangements which form an Offshore
OTSUA Transmission System that once transferred to a Relevant Transmission
Licensee under an Offshore Tender Process will become part of the
National Electricity Transmission System.
Offshore Waters Has the meaning given to “offshore waters” in Section 90(9) of the Energy
Act 2004.
Offshore Works In relation to a particular User means those assumptions set out in
Assumptions Appendix P of the relevant Construction Agreement as amended from
time to time.
Onshore Means within Great Britain, and when used in conjunction with another
term and not defined means that the associated term is to be read
accordingly.
Onshore DC Converter Any User Apparatus located Onshore with a Completion Date after 1st
April 2005 used to convert alternating current electricity to direct current
electricity, or vice versa. An Onshore DC Converter is a standalone
operative configuration at a single site comprising one or more converter
bridges, together with one or more converter transformers, converter
control equipment, essential protective and switching devices and
auxiliaries, if any, used for conversion. In a bipolar arrangement, an
Onshore DC Converter represents the bipolar configuration.
Onshore Grid Entry A point at which a Onshore Generating Unit or a CCGT Module or a
Point CCGT Unit or an Onshore Power Generating Module or a Onshore DC
Converter or an Onshore HVDC Converter or a Onshore Power Park
Module or an External Interconnection, as the case may be, which is
directly connected to the Onshore Transmission System connects to the
Onshore Transmission System.
Onshore HVDC Any User Apparatus located Onshore used to convert alternating current
Converter electricity to direct current electricity, or vice versa. An Onshore HVDC
Converter is a standalone operative configuration at a single site
comprising one or more converter bridges, together with one or more
converter transformers, converter control equipment, essential protective
and switching devices and auxiliaries, if any, used for conversion. In a
bipolar arrangement, an Onshore HVDC Converter represents the bipolar
configuration.
Onshore Synchronous An Onshore Generating Unit (which could also be part of an Onshore
Generating Unit Power Generating Module) including, for the avoidance of doubt, a
CCGT Unit in which, under all steady state conditions, the rotor rotates at
a mechanical speed equal to the electrical frequency of the National
Electricity Transmission System divided by the number of pole pairs of
the Generating Unit.
Onshore Synchronous A Synnchronous Power Generating Module located Onshore.
Power Generating
Module
Onshore Transmission NGET, SPT, or SHETL.
Licensee
On-Site Generator Site A site which is determined by the BSC Panel to be a Trading Unit under
the BSC by reason of having fulfilled the Class 1 or Class 2 requirements
as such terms are used in the BSC.
Operating Code or OC That portion of the Grid Code which is identified as the Operating Code.
Operating Reserve The additional output from Large Power Stations or the reduction in
Demand, which must be realisable in real-time operation to respond in
order to contribute to containing and correcting any System Frequency
fall to an acceptable level in the event of a loss of generation or a loss of
import from an External Interconnection or mismatch between
generation and Demand.
Operational Data Data required under the Operating Codes and/or Balancing Codes.
Operational Day The period from 0500 hours on one day to 0500 on the following day.
Operation Diagrams Diagrams which are a schematic representation of the HV Apparatus and
the connections to all external circuits at a Connection Site (and in the
case of OTSDUW, Transmission Interface Site), incorporating its
numbering, nomenclature and labelling.
Operational Effect Any effect on the operation of the relevant other System which causes the
National Electricity Transmission System or the System of the other
User or Users, as the case may be, to operate (or be at a materially
increased risk of operating) differently to the way in which they would or
may have operated in the absence of that effect.
Operational Planning The period from 8 weeks to the end of the 5th year ahead of real time
Phase operation.
Operational Procedures Management instructions and procedures, both in support of the Safety
Rules and for the local and remote operation of Plant and Apparatus,
issued in connection with the actual operation of Plant and/or Apparatus
at or from a Connection Site.
Operational Switching Operation of Plant and/or Apparatus to the instruction of the relevant
Control Engineer. For the avoidance of doubt, the operation of
Transmission Plant and/or Apparatus forming part of the National
Electricity Transmission System will be to the instruction of the
Relevant Transmission Licensee.
Other Relevant Data The data listed in BC1.4.2(f) under the heading Other Relevant Data.
OTSDUW Arrangements The arrangements whereby certain aspects of the design, consenting,
construction, installation and/or commissioning of transmission assets are
capable of being undertaken by a User prior to the transfer of those assets
to a Relevant Transmission Licensee under an Offshore Tender
Process.
OTSDUW Data and The data and information to be provided by Users undertaking OTSDUW,
Information to The Company in accordance with Appendix F of the Planning Code.
OTSDUW Development The timetable for both the delivery of OTSDUW Data and Information and
and Data Timetable OTSDUW Network Data and Information as referred to in Appendix F of
the Planning Code and the development of the scope of the OTSDUW.
OTSDUW Network Data The data and information to be provided by The Company to Users
and Information undertaking OTSDUW in accordance with Appendix F of the Planning
Code.
OTSDUW Plant and Plant and Apparatus, including any OTSDUW DC Converter, designed
Apparatus by the User under the OTSDUW Arrangements.
OTSUA Transfer Time The time and date at which the OTSUA are transferred to a Relevant
Transmission Licensee.
Output Usable or OU The (daily or weekly) forecast value (in MW), at the time of the (daily or
weekly) peak demand, of the maximum level at which the Genset can
export to the Grid Entry Point, or in the case of Embedded Power
Stations, to the User System Entry Point. In addition, for a Genset
powered by an Intermittent Power Source the forecast value is based
upon the Intermittent Power Source being at a level which would enable
the Genset to generate at Registered Capacity.
For the purpose of OC2 only, the term Output Usable shall include the
terms Interconnector Export Capacity and Interconnector Import
Capacity where the term Output Usable is being applied to an External
Interconnection.
Over-excitation Limiter Shall have the meaning ascribed to that term in IEC 34-16-1:1991
[equivalent to British Standard BS4999 Section 116.1 : 1992].
Panel Members’ The recommendation in accordance with the "Grid Code Review Panel
Recommendation Recommendation Vote"
Part 1 System Ancillary Ancillary Services which are required for System reasons and which
Services must be provided by Users in accordance with the Connection
Conditions. An exhaustive list of Part 1 System Ancillary Services is
included in that part of CC.8.1 headed Part 1.
Part 2 System Ancillary Ancillary Services which are required for System reasons and which
Services must be provided by a User if the User has agreed to provide them under
a Bilateral Agreement. A non-exhaustive list of Part 2 System Ancillary
Services is included in that part of CC.8.1 headed Part 2.
Part Load The condition of a Genset, or Cascade Hydro Scheme which is Loaded
but is not running at its Maximum Export Limit.
Permit for Work for In respect of E&W Transmission Systems, a document issued by the
proximity work Relevant E&W Transmission Licensee or an E&W User in accordance
with its respective Safety Rules to enable work to be carried out in
accordance with OC8A.8 and which provides for Safety Precautions to
be applied and maintained. An example format of a Relevant E&W
Transmission Licensee’s permit for work is attached as Appendix E to
OC8A.
In respect of Scottish Transmission Systems, a document issued by a
Relevant Scottish Transmission Licensee or a Scottish User in
accordance with its respective Safety Rules to enable work to be carried
out in accordance with OC8B.8 and which provides for Safety
Precautions to be applied and maintained. Example formats of Relevant
Scottish Transmission Licensees’ permits for work are attached as
Appendix E to OC8B.
Pending Grid Code A Grid Code Modification Proposal in respect of which, at the relevant
Modification Proposal time, the Authority has not yet made a decision as to whether to direct
such Grid Code Modification Proposal to be made pursuant to the
Transmission Licence (whether or not a Grid Code Modification Report
has been submitted in respect of such Grid Code Modification Proposal)
or, in the case of a Grid Code Self Governance Proposals, in respect of
which the Grid Code Review Panel has not yet voted whether or not to
approve.
Phase (Voltage) The ratio (in percent) between the rms values of the negative sequence
Unbalance component and the positive sequence component of the voltage.
Physical Notification Data that describes the BM Participant’s best estimate of the expected
input or output of Active Power of a BM Unit and/or (where relevant)
Generating Unit, the accuracy of the Physical Notification being
commensurate with Good Industry Practice.
Planning Code or PC That portion of the Grid Code which is identified as the Planning Code.
Planned Outage An outage of a Large Power Station or of part of the National Electricity
Transmission System, or of part of a User System, co-ordinated by The
Company under OC2.
Plant Fixed and movable items used in the generation and/or supply and/or
transmission of electricity, other than Apparatus.
Point of Common That point on the National Electricity Transmission System electrically
Coupling nearest to the User installation at which either Demands or Loads are, or
may be, connected.
Point of Isolation The point on Apparatus (as defined in OC8A.1.6.2 and OC8B.1.7.2) at
which Isolation is achieved.
Power Island Gensets at an isolated Power Station, together with complementary local
Demand. In Scotland a Power Island may include more than one Power
Station.
Power Park Module Any Onshore Power Park Module or Offshore Power Park Module.
Power Park Module The matrix described in Appendix 1 to BC1 under the heading Power Park
Availability Matrix Module Availability Matrix.
Power Park Module A matrix in the form set out in Appendix 4 of OC2 showing the combination
Planning Matrix of Power Park Units within a Power Park Module which would be
expected to be running under normal conditions.
Power Station An installation comprising one or more Generating Units or Power Park
Modules or Power Generating Modules (even where sited separately)
owned and/or controlled by the same Generator, which may reasonably
be considered as being managed as one Power Station.
Preface The preface to the Grid Code (which does not form part of the Grid Code
and therefore is not binding).
Preliminary Notice A notice in writing, sent by The Company both to all Users identified by it
under OC12.4.2.1 and to the Test Proposer, notifying them of a proposed
System Test.
Preliminary Project Data relating to a proposed User Development at the time the User
Planning Data applies for a CUSC Contract but before an offer is made and accepted.
Primary Response The automatic increase in Active Power output of a Genset or, as the
case may be, the decrease in Active Power Demand in response to a
System Frequency fall. This increase in Active Power output or, as the
case may be, the decrease in Active Power Demand must be in
accordance with the provisions of the relevant Ancillary Services
Agreement which will provide that it will be released increasingly with time
over the period 0 to 10 seconds from the time of the start of the Frequency
fall on the basis set out in the Ancillary Services Agreement and fully
available by the latter, and sustainable for at least a further 20 seconds.
The interpretation of the Primary Response to a – 0.5 Hz frequency
change is shown diagrammatically in Figure CC.A.3.2 and Figure
ECC.A.3.2
Private Network A network which connects to a Network Operator’s System and that
network belongs to a User who is not classified as a Generator, Network
Operator or Non Embedded Customer.
Programming Phase The period between the Operational Planning Phase and the Control
Phase. It starts at the 8 weeks ahead stage and finishes at 17:00 on the
day ahead of real time.
Proposal Notice A notice submitted to The Company by a User which would like to
undertake a System Test.
Proposed The proposed date(s) for the implementation of a Grid Code Modification
Implementation Date Proposal or Workgroup Alternative Grid Code Modification such
date(s) to be either (i) described by reference to a specified period after a
direction from the Authority approving the Grid Code Modification
Proposal or Workgroup Alternative Grid Code Modification or (ii) a
Fixed Proposed Implementation Date.
Protection Apparatus A group of one or more Protection relays and/or logic elements
designated to perform a specified Protection function.
Pump Storage A a hydro unit in which water can be raised by means of pumps and stored
to be used for the generation of electrical energy;
Pumped Storage A Generator which owns and/or operates any Pumped Storage Plant.
Generator
Pumped Storage Plant The Dinorwig, Ffestiniog, Cruachan and Foyers Power Stations.
Purchase Contracts A final and binding contract for the purchase of the Main Plant and
Apparatus.
Q/Pmax The ratio of Reactive Power to the Maximum Capacity. The relationship
between Power Factor and Q/Pmax is given by the formula:-
𝑸
Power Factor = Cos [arctan[ ]]
𝑷𝒎𝒂𝒙
For example, a Power Park Module with a Q/P value of +0.33 would
equate to a Power Factor of Cos(arctan0.33) = 0.95 Power Factor lag.
Quiescent Physical Data that describes the MW levels to be deducted from the Physical
Notification or QPN Notification of a BM Unit to determine a resultant operating level to which
the Dynamic Parameters associated with that BM Unit apply, and the
associated times for such MW levels. The MW level of the QPN must
always be set to zero.
Range CCGT Module A CCGT Module where there is a physical connection by way of a steam
or hot gas main between that CCGT Module and another CCGT Module
or other CCGT Modules, which connection contributes (if open) to efficient
modular operation, and which physical connection can be varied by the
operator.
Rated Field Voltage Shall have the meaning ascribed to that term in IEC 34-16-1:1991
[equivalent to British Standard BS4999 Section 116.1 : 1992].
Reactive Energy The integral with respect to time of the Reactive Power.
Reactive Power The product of voltage and current and the sine of the phase angle
between them measured in units of voltamperes reactive and standard
multiples thereof, ie:
1000 VAr = 1 kVAr
1000 kVAr = 1 Mvar
Registered Data Those items of Standard Planning Data and Detailed Planning Data
which upon connection become fixed (subject to any subsequent
changes).
Regulations The Utilities Contracts Regulations 1996, as amended from time to time.
Reheater Time Constant Determined at Registered Capacity, the reheater time constant will be
construed in accordance with the principles of the IEEE Committee Report
"Dynamic Models for Steam and Hydro Turbines in Power System Studies"
published in 1973 which apply to such phrase.
Rejected Grid Code A Grid Code Modification Proposal in respect of which the Authority
Modification Proposal has decided not to direct The Company to modify the Grid Code pursuant
to The Company’s Transmission Licence in the manner set out herein
or, in the case of a Grid Code Self Governance Proposals, in respect of
which the Grid Code Review Panel has voted not to approve.
Related Person means, in relation to an individual, any member of his immediate family,
his employer (and any former employer of his within the previous 12
months), any partner with whom he is in partnership, and any company or
Affiliate of a company in which he or any member of his immediate family
controls more than 20% of the voting rights in respect of the shares of the
company;
Relevant E&W As the context requires NGET and/or an E&W Offshore Transmission
Transmission Licensee Licensee.
Relevant Scottish As the context requires SPT and/or SHETL and/or a Scottish Offshore
Transmission Licensee Transmission Licensee.
Relevant Transmission Means National Grid Electricity Transmission plc (NGET) in its
Licensee Transmission Area or SP Transmission Ltd (SPT) in its Transmission
Area or Scottish Hydro-Electric Transmission Ltd (SHETL) in its
Transmission Area or any Offshore Transmission Licensee in its
Transmission Area.
Replacement Reserves means, in the context of Balancing Services, the active power reserves
(RR) available to restore or support the required level of FRR to be prepared for
additional system imbalances, including generation reserves;
Responsible Manager A manager who has been duly authorised by a User or a Relevant
Transmission Licensee to sign Site Responsibility Schedules on
behalf of that User or Relevant Transmission Licensee as the case may
be.
Re-synchronisation The bringing of parts of the System which have become Out of
Synchronism with any other System back into Synchronism, and like
terms shall be construed accordingly.
Restricted Applies to a TERRE Bid which has been marked so that it will be passed
to the TERRE Central Platform but will not be used in the auction
Safety From The System That condition which safeguards persons when work is to be carried out
on or near a System from the dangers which are inherent in the System.
Safety Key A key unique at the Location capable of operating a lock which will cause
an Isolating Device and/or Earthing Device to be Locked.
Safety Rules The rules of the Relevant Transmission Licensee or a User that seek to
ensure that persons working on Plant and/or Apparatus to which the rules
apply are safeguarded from hazards arising from the System.
Scottish User A User in Scotland or any Offshore User who owns or operates Plant
and/or Apparatus connected (or which will at the OTSUA Transfer Time
be connected) to a Scottish Offshore Transmission System
Secondary BM Unit Has the same meaning set out in the BSC
Secondary Response The automatic increase in Active Power output of a Genset or, as the
case may be, the decrease in Active Power Demand in response to a
System Frequency fall. This increase in Active Power output or, as the
case may be, the decrease in Active Power Demand must be in
accordance with the provisions of the relevant Ancillary Services
Agreement which will provide that it will be fully available by 30 seconds
from the time of the start of the Frequency fall and be sustainable for at
least a further 30 minutes. The interpretation of the Secondary Response
to a -0.5 Hz frequency change is shown diagrammatically in Figure
CC.A.3.2 or Figure ECC.A.3.2.
Secured Event Has the meaning set out in the Security and Quality of Supply Standard.
Security and Quality of The version of the document entitled ‘Security and Quality of Supply
Supply Standard (SQSS) Standard’ established pursuant to the Transmission Licence in force at
the time of entering into the relevant Bilateral Agreement.
Self-Governance A Grid Code Modification Proposal that does not fall within the scope of
Modifications a Significant Code Review and that meets the Self-Governance Criteria
or which the Authority directs is to be treated as such any direction under
GR.24.4.
Self-Governance The statement made by the Grid Code Review Panel and submitted to
Statement the Authority:
(a) confirming that, in its opinion, the Self-Governance Criteria are met
and the proposed Grid Code Modification Proposal is suitable for the
Self-Governance route; and
(b) providing a detailed explanation of the Grid Code Review Panel’s
reasons for that opinion
Setpoint Voltage The value of voltage at the Grid Entry Point, or User System Entry Point
if Embedded, on the automatic control system steady state operating
characteristic, as a percentage of the nominal voltage, at which the transfer
of Reactive Power between a Power Park Module, DC Converter,
HVDC Converter or Non-Synchronous Generating Unit and the
Transmission System, or Network Operator’s system if Embedded, is
zero.
Settlement Period A period of 30 minutes ending on the hour and half-hour in each hour
during a day.
Seven Year Statement A statement, prepared by The Company in accordance with the terms of
The Company’s Transmission Licence, showing for each of the seven
succeeding Financial Years, the opportunities available for connecting to
and using the National Electricity Transmission System and indicating
those parts of the National Electricity Transmission System most suited
to new connections and transport of further quantities of electricity.
SF6 Gas Zone A segregated zone surrounding electrical conductors within a casing
containing SF6 gas.
Significant Code Review Means the period commencing on the start date of a Significant Code
Review as stated in the notice issued by the Authority, and ending in the
circumstances described in GR.16.6 or GR.16.7, as appropriate.
Significant Code Review Means the period commencing on the start date of a Significant Code
Phase Review as stated in the notice issued by the Authority, and ending in the
circumstances described in GR.16.6 or GR.16.7, as appropriate.
Single Line Diagram A schematic representation of a three-phase network in which the three
phases are represented by single lines. The diagram shall include (but not
necessarily be limited to) busbars, overhead lines, underground cables,
power transformers and reactive compensation equipment. It shall also
show where Large Power Stations are connected, and the points at which
Demand is supplied.
Single Point of A single Point of Connection, with no interconnection through the User’s
Connection System to another Point of Connection.
Site Common Drawings Drawings prepared for each Connection Site (and in the case of
OTSDUW, Transmission Interface Site) which incorporate Connection
Site (and in the case of OTSDUW, Transmission Interface Site) layout
drawings, electrical layout drawings, common protection/ control drawings
and common services drawings.
Site Responsibility A schedule containing the information and prepared on the basis of the
Schedule provisions set out in Appendix 1 of the CC and Appendix E1 of the ECC.
Slope The ratio of the steady state change in voltage, as a percentage of the
nominal voltage, to the steady state change in Reactive Power output, in
per unit of Reactive Power capability. For the avoidance of doubt, the
value indicates the percentage voltage reduction that will result in a 1 per
unit increase in Reactive Power generation.
Speeder Motor Setting The minimum and maximum no-load speeds (expressed as a percentage
Range of rated speed) to which the turbine is capable of being controlled, by the
speeder motor or equivalent, when the Generating Unit terminals are on
open circuit.
Standard Modifications A Grid Code Modification Proposal that does not fall within the scope of
a Significant Code Review subject to any direction by the Authority
pursuant to GR.16.3 and GR.16.4, nor meets the Self-Governance
Criteria subject to any direction by the Authority pursuant to GR.24.4 and
in accordance with any direction under GR.24.2.
Standard Planning Data The general data required by The Company under the PC. It is generally
also the data which The Company requires from a new User in an
application for a CUSC Contract, as reflected in the PC.
Standard Product means a harmonised balancing product defined by all EU TSOs for the
exchange of balance services.
Specific Product Means in the context of Balancing Services a product that is not a standard
product;
Start Time The time named as such in an instruction issued by The Company
pursuant to the BC.
Statement of Readiness Has the meaning set out in the Bilateral Agreement and/or Construction
Agreement.
Station Board A switchboard through which electrical power is supplied to the Auxiliaries
of a Power Station, and which is supplied by a Station Transformer. It
may be interconnected with a Unit Board.
Steam Unit A Generating Unit whose prime mover converts the heat-energy in steam
to mechanical energy.
Surplus A MW figure relating to a System Zone equal to the total Output Usable
in the System Zone:
(a) minus the forecast of Active Power Demand in the System Zone,
and
(b) minus the export limit in the case of an export limited System Zone,
or
plus the import limit in the case of an import limited System Zone,
and
(c) (only in the case of a System Zone comprising the National
Electricity Transmission System) minus the Operational
Planning Margin.
For the avoidance of doubt, a Surplus of more than zero in an export
limited System Zone indicates an excess of generation in that System
Zone; and a Surplus of less than zero in an import limited System Zone
indicates insufficient generation in that System Zone.
Synchronising Group A group of two or more Gensets) which require a minimum time interval
between their Synchronising or De-Synchronising times.
Synchronous Area An area covered by synchronously interconnected Transmission
Licensees, such as the Synchronous Areas of Continental Europe,
Great Britain, Ireland-Northern Ireland and Nordic and the power systems
of Lithuania, Latvia and Estonia, together referred to as ‘Baltic’ which are
part of a wider Synchronous Area;
Synchronous The operation of rotating synchronous Apparatus for the specific purpose
Compensation of either the generation or absorption of Reactive Power.
Synchronous A diagram showing the Real Power (MW) and Reactive Power (MVAr)
Generating Unit capability limits within which a Synchronous Generating Unit at its stator
Performance Chart terminals (which is part of a Synchronous Power Generating Module)
will be expected to operate under steady state conditions.
Synchronous Power- An indivisible set of installations which can generate electrical energy such
Generating Module that the frequency of the generated voltage, the generator speed and the
frequency of network voltage are in a constant ratio and thus in
synchronism. For the avoidance of doubt a Synchronous Power
Generating Module could comprise of one or more Synchronous
Generating Units
Synchronous Power The matrix described in Appendix 1 to BC1 under the heading
Generating Module Synchronous Power Generating Module Matrix.
Matrix
Synchronous Power A matrix in the form set out in Appendix 5 of OC2 showing the combination
Generating Module of Synchronous Generating Units within a Synchronous Power
Planning Matrix Generating Module which would be running in relation to any given MW
output.
Synchronous Power Has the same meaning as a Synchronous Generating Unit and would
Generating Unit be considered to be part of a Power Generating Module.
System Any User System and/or the National Electricity Transmission System,
as the case may be.
System Ancillary Collectively Part 1 System Ancillary Services and Part 2 System
Services Ancillary Services.
System Constraint A limitation on the use of a System due to lack of transmission capacity or
other System conditions.
System Constrained That portion of Registered Capacity or Registered Import Capacity not
Capacity available due to a System Constraint.
System Constraint A part of the National Electricity Transmission System which, because
Group of System Constraints, is subject to limits of Active Power which can
flow into or out of (as the case may be) that part.
System Negative That margin of Active Power sufficient to allow the largest loss of Load at
Reserve Active Power any time.
Margin or System
NRAPM
System Operator - Has the meaning set out in The Company’s Transmission Licence
Transmission Owner
Code or STC
System Tests Tests which involve simulating conditions, or the controlled application of
irregular, unusual or extreme conditions, on the Total System, or any part
of the Total System, but which do not include commissioning or
recommissioning tests or any other tests of a minor nature.
System to Demand An intertrip scheme which disconnects Demand when a System fault has
Intertrip Scheme arisen to prevent abnormal conditions occurring on the System.
Target Frequency That Frequency determined by The Company, in its reasonable opinion,
as the desired operating Frequency of the Total System. This will
normally be 50.00Hz plus or minus 0.05Hz, except in exceptional
circumstances as determined by The Company, in its reasonable opinion
when this may be 49.90 or 50.10Hz. An example of exceptional
circumstances may be difficulties caused in operating the System during
disputes affecting fuel supplies.
TERRE Activation A period of time lasting 15 minutes and starting at either 0, 15, 30 or 45
Period minutes past the hour (e.g. 10:00 to 10:15). There are 4 TERRE
Activation Periods in one TERRE Auction Period
TERRE Auction Period A period of time lasting one hour and starting and ending on the hour (e.g.
from 10:00 to 11:00). Hence there are 24 TERRE Auction Periods in a
day
TERRE Gate Closure 60 minutes before the start of the TERRE Auction period (note still ongoing
discussions if this may become 55 minutes)
TERRE Data Validation A document produced by the central TERRE project detailing the correct
and Consistency Rules format of submissions for TERRE
Test Panel A panel, whose composition is detailed in OC12, which is responsible, inter
alia, for considering a proposed System Test, and submitting a Proposal
Report and a Test Programme.
The Company National Grid Electricity System Operator Limited (NO: 11014226) whose
registered office is at 1-3 Strand, London, WC2N 5EH as the person whose
Transmission Licence Section C of such Transmission Licence has
been given effect.
The Company Control The nominated person employed by The Company to direct the operation
Engineer of the National Electricity Transmission System or such person as
nominated by The Company.
The Company The Company's operational procedures which form the guidelines for
Operational Strategy operation of the National Electricity Transmission System.
Total Shutdown The situation existing when all generation has ceased and there is no
electricity supply from External Interconnections and, therefore, the
Total System has shutdown with the result that it is not possible for the
Total System to begin to function again without The Company’s
directions relating to a Black Start.
Total System The National Electricity Transmission System and all User Systems in
the National Electricity Transmission System Operator Area.
Trading Point A commercial and, where so specified in the Grid Code, an operational
interface between a User and The Company, which a User has notified
to The Company.
Transfer Date Such date as may be appointed by the Secretary of State by order under
section 65 of the Act.
Transmission Means, when used in conjunction with another term relating to equipment
or a site, whether defined or not, that the associated term is to be read as
being part of or directly associated with the National Electricity
Transmission System, and not of or with the User System.
Transmission Area Has the meaning set out in the Transmission Licence of a Transmission
Licensee.
Transmission A Demand Facility which has a Grid Supply Point to the National
Connected Demand Electricity Transmission System
Facilities
Transmission Interface means the electrical point of connection between the Offshore
Point Transmission System and an Onshore Transmission System.
Transmission Interface the site at which the Transmission Interface Point is located.
Site
Transmission Licensee The Company and any Onshore Transmission Licensee or Offshore
Transmission Licensee
Transmission Site Means a site owned (or occupied pursuant to a lease, licence or other
agreement) by a Relevant Transmission Licensee in which there is a
Connection Point. For the avoidance of doubt, a site owned by a User
but occupied by the Relevant Transmission Licensee as aforesaid, is a
Transmission Site.
Transmission System Has the same meaning as the term "licensee's transmission system" in the
Transmission Licence of a Transmission Licensee.
Turbine Time Constant Determined at Registered Capacity, the turbine time constant will be
construed in accordance with the principles of the IEEE Committee Report
"Dynamic Models for Steam and Hydro Turbines in Power System Studies"
published in 1973 which apply to such phrase.
Type A Power A Power-Generating Module with a Grid Entry Point or User System
Generating Module
Entry Point below 110 kV and a Maximum Capacity of 0.8 kW or
greater but less than 1MW;
Type B Power A Power-Generating Module with a Grid Entry Point or User System
Generating Module Entry Point below 110 kV and a Maximum Capacity of 1MW or greater
but less than 10MW;
Type C Power A Power-Generating Module with a Grid Entry Point or User System
Generating Module Entry Point below 110 kV and a Maximum Capacity of 10MW or
greater but less than 50MW;
Under-excitation Limiter Shall have the meaning ascribed to that term in IEC 34-16-1:1991
[equivalent to British Standard BS4999 Section 116.1 : 1992].
Under Frequency Relay An electrical measuring relay intended to operate when its characteristic
quantity (Frequency) reaches the relay settings by decrease in
Frequency.
Unit Board A switchboard through which electrical power is supplied to the Auxiliaries
of a Generating Unit and which is supplied by a Unit Transformer. It may
be interconnected with a Station Board.
Unit Load Controller The time constant, expressed in units of seconds, of the power output
Response Time increase which occurs in the Secondary Response timescale in response
Constant to a step change in System Frequency.
Unresolved Issues Any relevant Grid Code provisions or Bilateral Agreement requirements
identified by The Company with which the relevant User has not
demonstrated compliance to The Company’s reasonable satisfaction at
the date of issue of the Preliminary Operational Notification and/or
Interim Operational Notification and/or Limited Operational
Notification and which are detailed in such Preliminary Operational
Notification and/or Interim Operational Notification and/or Limited
Operational Notification.
User A term utilised in various sections of the Grid Code to refer to the persons
using the National Electricity Transmission System, as more
particularly identified in each section of the Grid Code concerned. In the
Preface and the General Conditions the term means any person to whom
the Grid Code applies. The term User includes an EU Code User and a
GB Code User.
User Data File Structure The file structure given at DRC 18 which will be specified by The Company
which a Generator or DC Converter Station owner or HVDC System
Onwer must use for the purposes of CP to submit DRC data Schedules
and information demonstrating compliance with the Grid Code and, where
applicable, with the CUSC Contract(s), unless otherwise agreed by The
Company.
User Self Certification of A certificate, in the form attached at CP.A.2.(1) or ECP.A.2.(1) completed
Compliance by a Generator or DC Converter Station owner or HVDC System Owner
to which the Compliance Statement is attached which confirms that such
Plant and Apparatus complies with the relevant Grid Code provisions and
where appropriate, with the CUSC Contract(s), as identified in the
Compliance Statement and, if appropriate, identifies any Unresolved
Issues and/or any exceptions to such compliance and details the
derogation(s) granted in respect of such exceptions.
User Site A site owned (or occupied pursuant to a lease, licence or other agreement)
by a User in which there is a Connection Point. For the avoidance of
doubt, a site owned by a Relevant Transmission Licensee but occupied
by a User as aforesaid, is a User Site.
User System Entry Point A point at which a Power Generating Module, Generating Unit, a CCGT
Module or a CCGT Unit or a Power Park Module or a DC Converter or
an HVDC Converter, as the case may be, which is Embedded connects
to the User System.
Water Time Constant Bears the meaning ascribed to the term "Water inertia time" in IEC308.
Website The site established by The Company on the World-Wide Web for the
exchange of information among Users and other interested persons in
accordance with such restrictions on access as may be determined from
time to time by The Company.
A number of the terms listed above are defined in other documents, such as the Balancing and Settlement
Code and the Transmission Licence. Appendix 1 sets out the current definitions from the other documents
of those terms so used in the Grid Code and defined in other documents for ease of reference, but does not
form part of the Grid Code.
GD.2 Construction of References
GD.2.1 In the Grid Code:
(i) a table of contents, a Preface, a Revision section, headings, and the Appendix to this
Glossary and Definitions are inserted for convenience only and shall be ignored in
construing the Grid Code;
(ii) unless the context otherwise requires, all references to a particular paragraph, sub-
paragraph, Appendix or Schedule shall be a reference to that paragraph, sub-paragraph
Appendix or Schedule in or to that part of the Grid Code in which the reference is made;
(iii) unless the context otherwise requires, the singular shall include the plural and vice versa,
references to any gender shall include all other genders and references to persons shall
include any individual, body corporate, corporation, joint venture, trust, unincorporated
association, organisation, firm or partnership and any other entity, in each case whether
or not having a separate legal personality;
CONTENTS
(This contents page does not form part of the Grid Code)
PC.3 SCOPE
PC.3.1 The PC applies to The Company and to Users, which in the PC means:
(a) Generators;
(b) Generators undertaking OTSDUW;
(c) Network Operators;
(d) Non-Embedded Customers;
Issue 5 Revision 34 PC 23 May 2019
3 of 79
(e) DC Converter Station owners; and
(f) HVDC System Owners
The above categories of User will become bound by the PC prior to them generating,
operating, or consuming or importing/exporting, as the case may be, and references to the
various categories (or to the general category) of User should, therefore, be taken as
referring to them in that prospective role as well as to Users actually connected.
PC.3.2 In the case of Embedded Power Stations, Embedded DC Converter Stations and
Embedded HVDC Systems, unless provided otherwise, the following provisions apply with
regard to the provision of data under this PC:
(a) each Generator shall provide the data direct to The Company in respect of (i)
Embedded Large Power Stations, (ii) Embedded Medium Power Stations subject to
a Bilateral Agreement and (iii) Embedded Small Power Stations which form part of a
Cascade Hydro Scheme;
(b) each DC Converter owner or HVDC System Owner shall provide the data direct to
The Company in respect of Embedded DC Converter Stations and Embedded
HVDC Systems subject to a Bilateral Agreement;
(c) each Network Operator shall provide the data to The Company in respect of each
Embedded Medium Power Station not subject to a Bilateral Agreement or
Embedded DC Converter Station not subject to a Bilateral Agreement or Embedded
HVDC System not subject to a Bilateral Agreement connected, or proposed to be
connected within such Network Operator’s System;
(d) although data is not normally required specifically on Embedded Small Power
Stations or on Embedded installations of direct current converters which do not form a
DC Converter Station or HVDC System under this PC, each Network Operator in
whose System they are Embedded should provide the data (contained in the
Appendix) to The Company in respect of Embedded Small Power Stations or
Embedded installations of direct current converters which do not form a DC Converter
Station or Embedded installations of HVDC Systems if:
(i) it falls to be supplied pursuant to the application for a CUSC Contract or in the
Statement of Readiness to be supplied in connection with a Bilateral Agreement
and/or Construction Agreement, by the Network Operator; or
(ii) it is specifically requested by The Company in the circumstances provided for
under this PC.
PC.3.3 Certain data does not normally need to be provided in respect of certain Embedded Power
Stations, Embedded DC Converter Stations or Embedded HVDC Systems, as provided
in PC.A.1.12.
In summary, Network Operators are required to supply the following data in respect of
Embedded Medium Power Stations not subject to a Bilateral Agreement or Embedded
DC Converter Stations not subject to a Bilateral Agreement or Embedded HVDC
Systems not subject to a Bilateral Agreement connected, or is proposed to be connected,
within such Network Operator’s System:
PC.A.2.1.1
PC.A.2.2.2
PC.A.2.5.5.2
PC.A.2.5.5.7
PC.A.2.5.6
PC.A.3.1.5
PC.A.3.2.2
PC.A.3.3.1
To reflect different types of data, Preliminary Project Planning Data and Committed
Project Planning Data are themselves divided into:
(a) those items of Standard Planning Data and Detailed Planning Data which will always
be forecast, known as Forecast Data; and
(b) those items of Standard Planning Data and Detailed Planning Data which relate to
Plant and/or Apparatus which upon connection will become Registered Data, but
which prior to connection, for the seven succeeding Financial Years, will be an
estimate of what is expected, known as Estimated Registered Data.
Connected Planning Data
PC.5.5 The PC requires that, at the time that a Statement of Readiness is submitted under the
Bilateral Agreement and/or Construction Agreement, any estimated values assumed for
planning purposes are confirmed or, where practical, replaced by validated actual values and
by updated estimates for the future and by updated forecasts for forecast data items such as
Demand. In the case of an Embedded Development the relevant Network Operator will
update any estimated values assumed for planning purposes with validated actual values as
soon as reasonably practicable after energisation. This data is then termed Connected
Planning Data.
To reflect the three types of data referred to above, Connected Planning Data is itself
divided into:
(a) those items of Standard Planning Data and Detailed Planning Data which will always
be forecast data, known as Forecast Data; and
(b) those items of Standard Planning Data and Detailed Planning Data which upon
connection become fixed (subject to any subsequent changes), known as Registered
Data; and
(c) those items of Standard Planning Data and Detailed Planning Data which for the
purposes of the Plant and/or Apparatus concerned as at the date of submission are
Registered Data but which for the seven succeeding Financial Years will be an
estimate of what is expected, known as Estimated Registered Data,
as more particularly provided in the Appendix.
PC.5.6 Connected Planning Data, together with Connection Entry Capacity and Transmission
Entry Capacity data from the CUSC Contract, and other data held by The Company
relating to the National Electricity Transmission System, will form the background against
which new applications by any User will be considered and against which planning of the
National Electricity Transmission System will be undertaken. Accordingly, Connected
Planning Data, Connection Entry Capacity and Transmission Entry Capacity data will
not be treated as confidential to the extent that The Company:
PC.5.7 Committed Project Planning Data and Connected Planning Data will each contain both
Standard Planning Data and Detailed Planning Data.
PC.7.9 A User may at any time, in writing, request further specified National Electricity
Transmission System network data in order to provide The Company with viable User
network data (as required under this PC). Upon receipt of such request The Company shall
consider, and where appropriate provide such National Electricity Transmission System
network data to the User as soon as reasonably practicable following the request.
PC.A.1 INTRODUCTION
PC.A.1.1 The Appendix specifies data requirements to be submitted to The Company by Users, and
in certain circumstances to Users by The Company.
PC.A.1.2 Submissions by Users
(a) Planning data submissions by Users shall be:
(i) with respect to each of the seven succeeding Financial Years (other than in the
case of Registered Data which will reflect the current position and data relating to
Demand forecasts which relates also to the current year);
(ii) provided by Users in connection with a CUSC Contract (PC.4.1, PC.4.4 and
PC.4.5 refer);
(iii) provided by Users on a routine annual basis in calendar week 24 of each year to
maintain an up-to-date data bank (although Network Operators may delay the
submission of data (other than that to be submitted pursuant to PC.3.2(c) and
PC.3.2(d)) until calendar week 28). In addition the structural data in DRC
Schedule 5 Tables 5(a), 5(b), 5(d), 5(e) , 5(f) and DRC Schedule 13 (Lumped
system susceptance (PC.A.2.3) only) provided by Network Operators by calendar
week 28 shall be updated by calendar week 50 of each year (again which may be
delayed as above until week 2 of the following calendar year). Where from the date
of one annual (or in the case of Schedule 5 or Schedule 13 the calendar week 50)
submission to another there is no change in the data (or in some of the data) to be
submitted, instead of re-submitting the data, a User may submit a written
statement that there has been no change from the data (or some of the data)
submitted the previous time; and
(iv) provided by Network Operators in connection with Embedded Development
(PC.4.4 refers).
(b) Where there is any change (or anticipated change) in Committed Project Planning
Data or a significant change in Connected Planning Data in the category of Forecast
Data or any change (or anticipated change) in Connected Planning Data in the
categories of Registered Data or Estimated Registered Data supplied to The
Company under the PC, notwithstanding that the change may subsequently be notified
to The Company under the PC as part of the routine annual update of data (or that the
change may be a Modification under the CUSC), the User shall, subject to PC.A.3.2.3
and PC.A.3.2.4, notify The Company in writing without delay.
(c) The notification of the change will be in the form required under this PC in relation to the
supply of that data and will also contain the following information:
(i) the time and date at which the change became, or is expected to become,
effective;
(ii) if the change is only temporary, an estimate of the time and date at which the data
will revert to the previous registered form.
(d) The routine annual update of data, referred to in (a)(iii) above, need not be submitted in
respect of Small Power Stations or Embedded installations of direct current
converters which do not form a DC Converter Station or HVDC System (except as
provided in PC.3.2.(c)), or unless specifically requested by The Company, or unless
otherwise specifically provided.
PC.A.1.3 Submissions by The Company
Network Data release by The Company shall be:
(a) with respect to the current Financial Year;
PC.A.2.2.5 For each transformer shown on the Single Line Diagram provided under PC.A.2.2.1, each
User (including those undertaking OTSDUW) shall provide the following details:
Rated MVA
Voltage Ratio
Winding arrangement
Positive sequence reactance (max, min and nominal tap)
Positive sequence resistance (max, min and nominal tap)
Zero sequence reactance
PC.A.2.2.5.1. In addition, for all interconnecting transformers between the User's Supergrid Voltage
System and the User's Subtransmission System throughout Great Britain and, in
Scotland and Offshore, also for all interconnecting transformers between the User’s 132kV
System and the User’s Subtransmission System (and any OTSUA) the User shall supply
the following information:-
Tap changer range
Tap change step size
Tap changer type: on load or off circuit
Earthing method: Direct, resistance or reactance
Impedance (if not directly earthed )
PC.A.2.2.6 Each User shall supply the following information about the User’s equipment installed at a
Transmission Site (or in the case of OTSUA, all OTSDUW Plant and Apparatus):-
(a) Switchgear. For all circuit breakers:-
Rated voltage (kV)
Operating voltage (kV)
Rated 3-phase rms short-circuit breaking current, (kA)
Rated 1-phase rms short-circuit breaking current, (kA)
Rated 3-phase peak short-circuit making current, (kA)
Rated 1-phase peak short-circuit making current, (kA)
Rated rms continuous current (A)
DC time constant applied at testing of asymmetrical breaking abilities (secs)
In the case of OTSDUW Plant and Apparatus operating times for circuit breaker,
Protection, trip relay and total operating time should be provided.
(b) Substation Infrastructure. For the substation infrastructure (including, but not limited to,
switch disconnectors, disconnectors, current transformers, line traps, busbars, through
bushings, etc):-
Rated 3-phase rms short-circuit withstand current (kA)
Rated 1-phase rms short-circuit withstand current (kA).
Rated 3-phase short-circuit peak withstand current (kA)
In addition, if an equivalent Single Line Diagram has been provided the data items listed
under the following parts of PC.A.2.5.6(a) shall be provided:-
(xi), (xii), (xiii);
In addition, for a Power Park Module (including DC Connected Power Park Modules) in
which one or more of the Power Park Units utilise a protective control such as a crowbar
circuit:-
the data items listed under the following parts of PC.A.2.5.6(a) shall be provided:-
(xiv), (xv);
All of the above data items shall be provided in accordance with the detailed provisions of
PC.A.2.5.6(c), (d), (f).
Should actual data in respect of fault infeeds be unavailable at the time of the application for
a CUSC Contract or Embedded Development Agreement, a limited subset of the data,
representing the maximum fault infeed that may result from all of the plant types being
considered, shall be submitted. This data will, as a minimum, represent the root mean
square of the positive, negative and zero sequence components of the fault current for both
single phase and three phase solid faults at the Grid Entry Point (or User System Entry
Point if Embedded) at the time of fault application and 50ms following fault application.
Actual data in respect of fault infeeds shall be submitted to The Company as soon as it is
available, in line with PC.A.1.2
PC.A.2.5.6 Data Items
(a) The following is the list of data utilised in this part of the PC. It also contains rules on
the data which generally apply:-
(i) Root mean square of the symmetrical three-phase short circuit current infeed at the
instant of fault, (I1");
(ii) Root mean square of the symmetrical three-phase short circuit current after the
subtransient fault current contribution has substantially decayed, (I 1');
(iii) the zero sequence source resistance and reactance values of the User's System
as seen from the node on the Single Line Diagram provided under PC.A.2.2.1 (or
Power Generating Module or Station Transformer high voltage terminals or
Generating Unit terminals or DC Converter terminals or HVDC System terminals,
as appropriate) consistent with the infeed described in PC.A.2.5.1.(b);
(iv) root mean square of the pre-fault voltage at which the maximum fault currents were
calculated;
(v) the positive sequence X/R ratio at the instant of fault;
(vi) the negative sequence resistance and reactance values of the User's System
seen from the node on the Single Line Diagram provided under PC.A.2.2.1 (or
Power Generating Module or Station Transformer high voltage terminals, or
Generating Unit terminals or DC Converter terminals or HVDC System terminals
as appropriate) if substantially different from the values of positive sequence
resistance and reactance which would be derived from the data provided above;
(vii) A continuous trace and a table showing the root mean square of the positive,
negative and zero sequence components of the short circuit current between zero
and 140ms at 10ms intervals;
PC.A.3.2.3 Notwithstanding any other provision of this PC, the CCGT Units within a CCGT Module,
details of which are required under paragraph (g) of PC.A.3.2.2, can only be amended in
accordance with the following provisions:-
(a) if the CCGT Module is a Normal CCGT Module, the CCGT Units within that CCGT
Module can only be amended such that the CCGT Module comprises different CCGT
Units if The Company gives its prior consent in writing. Notice of the wish to amend
the CCGT Units within such a CCGT Module must be given at least 6 months before it
is wished for the amendment to take effect;
(b) if the CCGT Module is a Range CCGT Module, the CCGT Units within that CCGT
Module and the Grid Entry Point at which the power is provided can only be amended
as described in BC1.A1.6.4.
PC.A.3.2.4 Notwithstanding any other provision of this PC, the Power Park Units within a Power Park
Module (including DC Connected Power Park Modules), and the Power Park Modules
(including DC Connected Power Park Modules) within a BM Unit, details of which are
required under paragraph (k) of PC.A.3.2.2, can only be amended in accordance with the
following provisions:-
(a) if the Power Park Units within that Power Park Module can only be amended such
that the Power Park Module comprises different Power Park Units due to
repair/replacement of individual Power Park Units if The Company gives its prior
consent in writing. Notice of the wish to amend a Power Park Unit within such a
Power Park Module (including DC Connected Power Park Modules) must be given at
least 4 weeks before it is wished for the amendment to take effect;
(b) if the Power Park Units within that Power Park Module (including DC Connected
Power Park Modules) and/or the Power Park Modules (including DC Connected
Power Park Modules) within that BM Unit can be selected to run in different Power
Park Modules and/or BM Units as an alternative operational running arrangement the
Power Park Units within the Power Park Module, the BM Unit of which each Power
Park Module forms part, and the Grid Entry Point at which the power is provided can
only be amended as described in BC1.A.1.8.4.
PC.A.3.2.5 Notwithstanding any other provision of this PC, the Synchronous Generating Units within a
Synchronous Power Generating Module, and the Synchronous Power Generating
Modules within a BM Unit, details of which are required under paragraph (l) of PC.A.3.2.2,
can only be amended in accordance with the following provisions:-
Issue 5 Revision 34 PC 23 May 2019
34 of 79
(a) if the Synchronous Generating Units within that Synchronous Power Generating
Module can only be amended such that the Synchronous Power Generating Module
comprises different Synchronous Generating Units due to repair/replacement of
individual Synchronous Generating Units if The Company gives its prior consent in
writing. Notice of the wish to amend a Synchronous Generating Unit within such a
Synchronous Power Generating Module must be given at least 4 weeks before it is
wished for the amendment to take effect;
(b) if the Synchronous Generating Units within that Synchronous Power Generating
Module and/or the Synchronous Power Generating Modules within that BM Unit
can be selected to run in different Synchronous Power Generating Modules and/or
BM Units as an alternative operational running arrangement the Synchronous
Generating Units within the Synchronous Power Generating Module, the BM Unit
of which each Synchronous Power Generating Module forms part, and the Grid
Entry Point at which the power is provided can only be amended as described in
BC1.A.1.9.4(c).The requirements of PC.A.3.2.5 need not be satisfied if Generators
have already submitted data in respect of PC.A.3.2.3, PC.A.3.2.4 and PC.A.3.2.5 for the
same Power Generating Module.
PC.A.3.3. Rated Parameters Data
PC.A.3.3.1 The following information is required to facilitate an early assessment, by The Company, of
the need for more detailed studies;
(a) for all Generating Units (excluding Power Park Units) and Power Park Modules
(including DC Connected Power Park Modules):
Rated MVA
Rated MW;
(b) for each Synchronous Generating Unit (including Synchronous Generating Units
within a Synchronous Power Generating Module):
Short circuit ratio
Direct axis transient reactance;
Inertia constant (for whole machine), MWsecs/MVA;
(c) for each Synchronous Generating Unit step-up transformer (including the step up
transformer of a Synchronous Generating Unit within a Synchronous Power
Generating Module):
Rated MVA
Positive sequence reactance (at max, min and nominal tap);
(d) for each DC Converter at a DC Converter Station, HVDC System, DC Converter
connecting an exisiting Power Park Module (including DC Connected Power Park
Modules) and Transmission DC Converter (forming part of an OTSUA).
DC Converter or HVDC Converter type (e.g. current/voltage sourced)
Rated MW per pole for import and export
Number of poles and pole arrangement
Rated DC voltage/pole (kV)
Return path arrangement
Remote AC connection arrangement (excluding OTSDUW DC Converters)
Maximum HVDC Active Power Transmission Capacity
(e) for each type of Power Park Unit in a Power Park Module not connected to the Total
System by a DC Converter or HVDC System:
Issue 5 Revision 34 PC 23 May 2019
35 of 79
Rated MVA
Rated MW
Rated terminal voltage
Inertia constant, (MWsec/MVA)
Additionally, for Power Park Units that are squirrel-cage or doubly-fed induction
generators driven by wind turbines:
Stator reactance.
Magnetising reactance.
Rotor resistance (at rated running)
Rotor reactance (at rated running)
The generator rotor speed range (minimum and maximum speeds in RPM)
(for doubly-fed induction generators only)
Converter MVA rating (for doubly-fed induction generators only)
For a Power Park Unit consisting of a synchronous machine in combination with a
back-to-back DC Converter or HVDC Converter, or for a Power Park Unit not driven
by a wind turbine, the data to be supplied shall be agreed with The Company in
accordance with PC.A.7.
This information should only be given in the data supplied in accordance with PC.4.4 and
PC.4.5.
PC.A.3.4 General Generating Unit, Power Park Module (including DC Connected Power Park
Modules), Power Generating Module, HVDC System and DC Converter Data
PC.A.3.4.1 The point of connection to the National Electricity Transmission System or the Total
System, if other than to the National Electricity Transmission System, in terms of
geographical and electrical location and system voltage is also required.
PC.A.3.4.2 (a) Type of Generating Unit (ie Synchronous Power Generating Unit within a Power
Generating Module, Synchronous Generating Unit, Non-Synchronous Generating
Unit, DC Converter, Power Park Module (including DC Connected Power Park
Modules) or HVDC System).
(b) In the case of a Synchronous Generating Unit (including Synchronous Generating
Units within a Synchronous Power Generating Module) details of the Exciter
category, for example whether it is a rotating Exciter or a static Exciter or in the case of
a Non-Synchronous Generating Unit the voltage control system.
(c) Whether a Power System Stabiliser is fitted.
PC.A.3.4.3 Each Generator shall supply The Company with the production type(s) used as the primary
source of power in respect of each Generating Unit (including Synchronous Generating
Units within a Synchronous Power Generating Module), selected from the list set out
below:
- Biomass
- Fossil brown coal/lignite
- Fossil coal-derived gas
- Fossil gas
- Fossil hard coal
- Fossil oil
- Fossil oil shale
- Fossil peat
- Geothermal
Issue 5 Revision 34 PC 23 May 2019
36 of 79
- Hydro pumped storage
- Hydro run-of-river and poundage
- Hydro water reservoir
- Marine
- Nuclear
- Other renewable
- Solar
- Waste
- Wind offshore
- Wind onshore
- Other
Embedded
PC.A.5.1.2 Each Generator, in respect of its existing, or proposed, Embedded Large Power Stations
and its Embedded Medium Power Stations subject to a Bilateral Agreement and each
Network Operator in respect of Embedded Medium Power Stations not subject to a
Bilateral Agreement within its System shall provide The Company with data relating to
each of those Large Power Stations and Medium Power Stations, both current and
forecast, as specified in PC.A.5.2, PC.A.5.3, PC.A.5.4 and PC.A.5.7 as applicable.
Each DC Converter Station owner or HVDC System Owner, or Network Operator in the
case of an Embedded DC Converter Station or Embedded HVDC System not subject to a
Bilateral Agreement within its System with existing or proposed HVDC Systems or DC
Converter Stations shall provide The Company with data relating to each of those HVDC
Systems or DC Converter Stations, both current and forecast, as specified in PC.A.5.2 and
PC.A.5.4.
However, no data need be supplied in relation to those Embedded Medium Power
Stations or Embedded DC Converter Stations or Embedded HVDC Systems if they are
connected at a voltage level below the voltage level of the Subtransmission System except
in connection with an application for, or under a, CUSC Contract or unless specifically
requested by The Company under PC.A.5.1.4.
GB Generators, DC Converter Station owners, EU Generators and HVDC System
Owners shall ensure that the models supplied in respect of their Plant and Apparatus
provide a true and accurate behaviour of the plant as built as required under PC.A.5.3.2(c),
PC.A.5.4.2(a) and PC.A.5.4.3 and verified through the Compliance Processes (CP) or
European Compliance Processes (ECP) as applicable
PC.A.5.1.3 Each Network Operator need not submit Planning Data in respect of Embedded Small
Power Stations unless required to do so under PC.A.1.2(b), PC.A.3.1.4 or unless
specifically requested under PC.A.5.1.4 below, in which case they will supply such data.
For the avoidance of doubt, Demand data associated with Generators undertaking
OTSDUW which utilise an OTSDUW DC Converter should supply data under PC.A.4.
PC.A.5.3 Synchronous Power Generating Modules, Synchronous Generating Unit and Associated
Control System Data
PC.A.5.3.1 The data submitted below are not intended to constrain any Ancillary Services Agreement
PC.A.5.3.2 The following Synchronous Generating Unit (including Synchronous Generating Units
within a Synchronous Power Generating Module) and Power Station data should be
supplied:
(a) Synchronous Generating Unit Parameters
Rated terminal volts (kV)
Maximum terminal voltage set point (kV)
Option 1
DC gain of Excitation Loop
Rated field voltage
Maximum field voltage
Minimum field voltage
Maximum rate of change of field voltage (rising)
Maximum rate of change of field voltage (falling)
Details of Excitation Loop described in block diagram form showing transfer
functions of individual elements.
Dynamic characteristics of Over-excitation Limiter.
Issue 5 Revision 34 PC 23 May 2019
46 of 79
Dynamic characteristics of Under-excitation Limiter
Option 2
Excitation System Nominal Response
Rated Field Voltage
No-Load Field Voltage
Excitation System On-Load Positive Ceiling Voltage
Excitation System No-Load Positive Ceiling Voltage
Excitation System No-Load Negative Ceiling Voltage
Stator Current Limiter (applicable only to Synchronous Power Generating
Modules)
Details of Excitation System (including PSS if fitted) described in block diagram
form showing transfer functions of individual elements.
Details of Over-excitation Limiter described in block diagram form showing
transfer functions of individual elements.
Details of Under-excitation Limiter described in block diagram form showing
transfer functions of individual elements.
The block diagrams submitted after 1 January 2009 in respect of the Excitation
System (including the Over-excitation Limiter and the Under-excitation Limiter)
for Generating Units with a Completion date after 1 January 2009 or subject to a
Modification to the Excitation System after 1 January 2009, should have been
verified as far as reasonably practicable by simulation studies as representing the
expected behaviour of the system.
(d) Governor Parameters
Incremental Droop values (in %) are required for each Generating Unit at six MW
loading points (MLP1 to MLP6) as detailed in PC.A.5.5.1 (this data item needs only be
provided for Large Power Stations)
Note: The data items requested under Option 1 below may continue to be provided by
Generators in relation to Generating Units on the System at 09 January 1995 (in this
paragraph, the "relevant date") or they may provide the new data items set out under
Option 2. Generators must supply the data as set out under Option 2 (and not those
under Option 1) for Generating Unit governor control systems commissioned after the
relevant date, those Generating Unit governor control systems recommissioned for any
reason such as refurbishment after the relevant date and Generating Unit governor
control systems where, as a result of testing or other process, the Generator is aware
of the data items listed under Option 2 in relation to that Generating Unit. EU
Generators are also required to submit the data as set out in option 2. Additional data
required from EU Generators which own or operate Type C or Type D Power
Generating Modules are marked in brackets with an asterisk (eg (*)). For the
avoidance of doubt, items marked as (*) need not be supplied by GB Generators.
Option 1
(i) Governor Parameters (for Reheat Steam Units)
HP governor average gain MW/Hz
Speeder motor setting range
HP governor valve time constant
HP governor valve opening limits
HP governor valve rate limits
Reheater time constant (Active Energy stored in reheater)
Issue 5 Revision 34 PC 23 May 2019
47 of 79
IP governor average gain MW/Hz
IP governor setting range
IP governor valve time constant
IP governor valve opening limits
IP governor valve rate limits
(ii) Governor Parameters (for Non-Reheat Steam Units and Gas Turbine Units)
Governor average gain
Speeder motor setting range
Time constant of steam or fuel governor valve
Governor valve opening limits
Governor valve rate limits
Time constant of turbine
Governor block diagram
The following data items need only be supplied for Large Power Stations:
(iii) Boiler & Steam Turbine Data
Boiler Time Constant (Stored Active Energy) s
HP turbine response ratio:
proportion of Primary Response arising from HP turbine %
HP turbine response ratio:
proportion of High Frequency Response arising from HP turbine %
[End of Option 1]
Option 2
(i) Governor and associated prime mover Parameters - All Generating Units
(including Synchronous Generating Units within a Synchronous Power
Generating Module)
Governor Block Diagram showing transfer function of individual elements
including acceleration sensitive elements.
Governor Time Constant (in seconds)
Speeder Motor Setting Range (%)
Average Gain (MW/Hz)
Governor Deadband (and Governor Insensitivity Governor Deadband*)
need only be provided for Large Power Stations (and both Governor
Deadband and Governor Insensitivity should be supplied in respect of Type
C and D Power Generating Modules within Large Power Station and
Medium Power Stations excluding Embedded Medium Power Stations not
subject to a Bilateral Agreement*)
(iii) Governor and associated prime mover Parameters - Gas Turbine Units
Inlet Guide Vane Time Constant (in seconds)
Inlet Guide Vane Opening Limits (%)
Inlet Guide Vane Opening Rate Limits (%/second)
Inlet Guide Vane Closing Rate Limits (%/second)
Fuel Valve Constant (in seconds)
Fuel Valve Opening Limits (%)
(iv) Governor and associated prime mover Parameters - Hydro Generating Units
Guide Vane Actuator Time Constant (in seconds)
Guide Vane Opening Limits (%)
Guide Vane Opening Rate Limits (%/second)
Guide Vane Closing Rate Limits (%/second)
Water Time Constant (in seconds)
[End of Option 2]
Data items marked with a hash (#) should be applicable to a Genset which has been
Shutdown for 48 hours.
* Data items marked with an asterisk are already requested under partx1, PC.A.3.3.1, to
facilitate an early assessment by The Company as to whether detailed stability studies
will be required before an offer of terms for a CUSC Contract can be made. Such data
items have been repeated here merely for completeness and need not, of course, be
resubmitted unless their values, known or estimated, have changed.
PC.A.5.4 Power Park Module, Non-Synchronous Generating Unit and Associated Control System
Data
PC.A.5.4.1 The data submitted below are not intended to constrain any Ancillary Services Agreement
PC.A.5.4.2 The following Power Park Unit, Power Park Module and Power Station data should be
supplied in the case of a Power Park Module not connected to the Total System by a DC
Converter or HVDC System (and in the case of PC.A.5.4.2(f) any OTSUA):
Where a Manufacturer’s Data & Performance Report exists in respect of the model of the
Power Park Unit, the User may subject to The Company’s agreement, opt to reference the
Manufacturer’s Data & Performance Report as an alternative to the provision of data in
accordance with PC.A.5.4.2 except for:
(1) the section marked thus # at sub paragraph (b); and
(2) all of the harmonic and flicker parameters required under sub paragraph (h); and
(3) all of the site specific model parameters relating to the voltage or frequency control
systems required under sub paragraphs (d) and (e),
which must be provided by the User in addition to the Manufacturer’s Data & Performance
Report reference.
(a) Power Park Unit model
The rotor power coefficient (Cp) versus tip speed ratio () curves for a range of
blade angles (where applicable) together with the corresponding values submitted
in tabular format. The tip speed ratio () is defined as R/U where is the angular
velocity of the rotor, R is the radius of the wind turbine rotor and U is the wind
speed.
The electrical power output versus generator rotor speed for a range of wind
speeds over the entire operating range of the Power Park Unit, together with the
corresponding values submitted in tabular format.
The blade angle versus wind speed curve together with the corresponding values
submitted in tabular format.
The electrical power output versus wind speed over the entire operating range of
the Power Park Unit, together with the corresponding values submitted in tabular
format.
Transfer function block diagram, including parameters and description of the
operation of the power electronic converter and fault ride through capability (where
applicable).
For a Power Park Unit consisting of a synchronous machine in combination with a back
to back DC Converter or HVDC System, or for a Power Park Unit not driven by a
wind turbine, the data to be supplied shall be agreed with The Company in accordance
with PC.A.7.
(c) Torque / speed and blade angle control systems and parameters
For the Power Park Unit, details of the torque / speed controller and blade angle
controller in the case of a wind turbine and power limitation functions (where applicable)
described in block diagram form showing transfer functions and parameters of individual
elements.
(d) Voltage/Reactive Power/Power Factor control system parameters
Issue 5 Revision 34 PC 23 May 2019
53 of 79
For the Power Park Unit and Power Park Module details of voltage/Reactive
Power/Power Factor controller (and PSS if fitted) described in block diagram form
showing transfer functions and parameters of individual elements.
(e) Frequency control system parameters
For the Power Park Unit and Power Park Module details of the Frequency controller
described in block diagram form showing transfer functions and parameters of individual
elements.
(f) Protection
Details of settings for the following Protection relays (to include): Under Frequency,
over Frequency, under voltage, over voltage, rotor over current, stator over current,
high wind speed shut down level.
* Data items marked with an asterisk are already requested under part 1, PC.A.3.3.1, to
facilitate an early assessment by The Company as to whether detailed stability studies
will be required before an offer of terms for a CUSC Contract can be made. Such data
items have been repeated here merely for completeness and need not, of course, be
resubmitted unless their values, known or estimated, have changed.
Note: Details in PC.A.5.4.3.1 are required for each DC Converter connected to the DC
Network and HVDC System, unless each is identical or where the data has already been
submitted for an identical DC Converter or HVDC System at another Connection Point.
Note: For a Power Park Module and DC Connected Power Park Module connected to the
Grid Entry Point or (User System Entry Point if Embedded) by a DC Converter or HVDC
System the equivalent inertia and fault infeed at the Power Park Unit should be given.
DC Converter and HVDC System Control System Models
PC.A.5.4.3.2 The following data is required by The Company to represent DC Converters and
associated DC Networks and HVDC Systems (and including OTSUA which includes an
OTSDUW DC Converter) in dynamic power system simulations, in which the AC power
system is typically represented by a positive sequence equivalent. DC Converters and
HVDC Systems are represented by simplified equations and are not modelled to switching
device level.
Issue 5 Revision 34 PC 23 May 2019
55 of 79
(i) Static VDC-IDC (DC voltage - DC current) characteristics, for both the rectifier and inverter
modes for a current source converter. Static VDC-PDC (DC voltage - DC power)
characteristics, for both the rectifier and inverter modes for a voltage source converter.
Transfer function block diagram including parameters representation of the control
systems of each DC Converter and of the DC Converter Station and the HVDC
System, for both the rectifier and inverter modes. A suitable model would feature the
DC Converter or HVDC Converter firing angle as the output variable.
(ii) Transfer function block diagram representation including parameters of the DC
Converter or HVDC Converter transformer tap changer control systems, including time
delays
(iii) Transfer function block diagram representation including parameters of AC filter and
reactive compensation equipment control systems, including any time delays.
(iv) Transfer function block diagram representation including parameters of any Frequency
and/or load control systems.
(v) Transfer function block diagram representation including parameters of any small signal
modulation controls such as power oscillation damping controls or sub-synchronous
oscillation damping controls, that have not been submitted as part of the above control
system data.
(vi) Transfer block diagram representation of the Reactive Power control at converter ends
for a voltage source converter.
In addition and where not provided for above, HVDC System Owners shall also provide the
following dynamic simulation sub-models
(i) HVDC Converter unit models
(ii) AC component models
(iii) DC Grid models
(iv) Voltage and power controller
(v) Special control features if applicable (eg power oscillation damping (POD) function,
subsynchronous torsional interaction (SSTI) control;
(vi) Multi terminal control, if applicable
(vii) HVDC System protection models as agreed between The Company and the HVDC
System Owner
HVDC System Owners are also required to supply an equivalent model of the control
system when adverse control interactions may result with HVDC Converter Stations and
other connections in close proximity if requested by The Company. The equivalent model
shall contain all necessary data for the realistic simulation of the adverse control interactions.
Plant Flexibility Performance
PC.A.5.4.3.3 The following information on plant flexibility and performance should be supplied (and also in
respect of OTSUA which includes an OTSDUW DC Converter):
(i) Nominal and maximum (emergency) loading rate with the DC Converter or HVDC
Converter in rectifier mode.
(ii) Nominal and maximum (emergency) loading rate with the DC Converter or HVDC
Converter in inverter mode.
(iii) Maximum recovery time, to 90% of pre-fault loading, following an AC system fault or
severe voltage depression.
(iv) Maximum recovery time, to 90% of pre-fault loading, following a transient DC Network
fault.
Harmonic Assessment Information
* Data items marked with an asterisk are already requested under part 1, PC.A.3.3.1, to
facilitate an early assessment by The Company as to whether detailed stability studies will
be required before an offer of terms for a CUSC Contract can be made. Such data items
have been repeated here merely for completeness and need not, of course, be resubmitted
unless their values, known or estimated, have changed.
PC.A.5.5 Response Data For Frequency Changes
The information detailed below is required to describe the actual frequency response
capability profile as illustrated in Figure CC.A.3.1 of the Connection Conditions, and need
only be provided for each:
(i) Genset at Large Power Stations; and
(ii) Generating Unit (including Synchronous Generating Units within a Synchronous
Power Generating Module), Power Park Module (including a DC Connected Power
Park Module) or CCGT Module at a Medium Power Station or DC Converter Station
or HVDC System that has agreed to provide Frequency response in accordance with a
CUSC Contract.
In the case of (ii) above for the rest of this PC.A.5.5 where reference is made to
Gensets, it shall include such Generating Units (including Synchronous Generating
Units within a Synchronous Power Generating Module), CCGT Modules, Power
Park Modules (including DC Connected Power Park Modules), HVDC Systems and
DC Converters as appropriate, but excludes OTSDUW Plant and Apparatus utilising
OTSDUW DC Converters.
In this PC.A.5.5, for a CCGT Module with more than one Generating Unit, the phrase
Minimum Generation or Minimum Regulating Level applies to the entire CCGT Module
operating with all Generating Units (including Synchronous Generating Units within a
Synchronous Power Generating Module) Synchronised to the System. Similarly for a
Power Park Module (including a DC Connected Power Park Module) with more than one
Power Park Unit, the phrase Minimum Generation or Minimum Regulating Level applies
to the entire Power Park Module operating with all Power Park Units Synchronised to the
System.
PC.A.5.5.1 MW Loading Points At Which Data Is Required
Response values are required at six MW loading points (MLP1 to MLP6) for each Genset.
Primary and Secondary Response values need not be provided for MW loading points
which are below Minimum Generation or Minimum Stable Operating Level. MLP1 to
MLP6 must be provided to the nearest MW.
Prior to the Genset being first Synchronised, the MW loading points must take the following
values :
MLP1 Designed Minimum Operating Level or Minimum Regulating Level
MLP2 Minimum Generation or Minimum Stable Operating Level
MLP3 70% of Registered Capacity or Maximum Capacity
MLP4 80% of Registered Capacity or Maximum Capacity
MLP5 95% of Registered Capacity or Maximum Capacity
MLP6 Registered Capacity or Maximum Capacity
When data is provided after the Genset is first Synchronised, the MW loading points may
take any value between the Designed Minimum Operating Level or Minimum Regulating
Level and Registered Capacity or Minimum Regulating Level and Maximum Capacity
but the value of the Designed Minimum Operating Level or Minimum Regulating Level
must still be provided if it does not form one of the MW loading points.
Issue 5 Revision 34 PC 23 May 2019
57 of 79
PC.A.5.5.2 Primary And Secondary Response To Frequency Fall
Primary and Secondary Response values for a -0.5Hz ramp are required at six MW
loading points (MLP1 to MLP6) as detailed above
PC.A.5.5.3 High Frequency Response To Frequency Rise
High Frequency Response values for a +0.5Hz ramp are required at six MW loading points
(MLP1 to MLP6) as detailed above.
PC.A.5.6 Mothballed Power Generating Module, Mothballed Generating Unit, Mothballed Power Park
Module (including DC Connected Power Park Modules), Mothballed HVDC Systems or
Mothballed DC Converter At A DC Converter Station And Alternative Fuel Information
Data identified under this section PC.A.5.6 must be submitted as required under PC.A.1.2
and at The Company’s reasonable request.
In the case of Embedded Medium Power Stations not subject to a Bilateral Agreement,
Embedded HVDC Systems not subject to a Bilateral Agreement and Embedded DC
Converter Stations not subject to a Bilateral Agreement, upon request from The
Company each Network Operator shall provide the information required in PC.A.5.6.1,
PC.A.5.6.2, PC.A.5.6.3 and PC.A.5.6.4 on respect of such Embedded Medium Power
Stations and Embedded DC Converters Stations and Embedded HVDC Systems with
their System.
PC.A.5.6.1 Mothballed Generating Unit Information
Generators, HVDC System Owners and DC Converter Station owners must supply with
respect to each Mothballed Power Generating Module, Mothballed Generating Unit,
Mothballed Power Park Module (including a DC Connected Power Park Module),
Mothballed HVDC System or Mothballed DC Converter at a DC Converter Station the
estimated MW output which could be returned to service within the following time periods
from the time that a decision to return was made:
< 1 month;
1-2 months;
2-3 months;
3-6 months;
6-12 months; and
>12 months.
The return to service time should be determined in accordance with Good Industry Practice
assuming normal working arrangements and normal plant procurement lead times. The MW
output values should be the incremental values made available in each time period as further
described in the DRC.
PC.A.5.6.2 Generators, HVDC System Owners and DC Converter Station owners must also notify
The Company of any significant factors which may prevent the Mothballed Power
Generating Module, Mothballed Generating Unit, Mothballed Power Park Module
(including DC Connected Power Park Modules), Mothballed HVDC Systems or
Mothballed DC Converter at a DC Converter Station achieving the estimated values
provided under PC.A.5.6.1 above, excluding factors relating to Transmission Entry
Capacity.
PC.A.5.6.3 Alternative Fuel Information
The following data items must be supplied with respect to each Generating Unit (including
Synchronous Generating Units within a Synchronous Power Generating Module)
whose main fuel is gas.
For each alternative fuel type (if facility installed):
PC.A.8 To allow a User to model the National Electricity Transmission System, The Company
will provide, upon request, the following Network Data to Users, calculated in accordance
with Good Industry Practice:
To allow a User to assess undertaking OTSDUW and except where provided for in Appendix
F, The Company will provide upon request the following Network Data to Users, calculated
in accordance with Good Industry Practice:
PC.A.8.1 Single Point of Connection
For a Single Point of Connection to a User's System (and OTSUA), as an equivalent
400kV or 275kV source and also in Scotland and Offshore as an equivalent 132kV source,
the data (as at the HV side of the Point of Connection (and in the case of OTSUA, each
Interface Point and Connection Point) reflecting data given to The Company by Users)
will be given to a User as follows:
The data items listed under the following parts of PC.A.8.3:
(a) (i), (ii), (iii), (iv), (v) and (vi)
and the data items shall be provided in accordance with the detailed provisions of PC.A.8.3
(b) - (e).
PC.A.8.2 Multiple Point of Connection
For a Multiple Point of Connection to a User's System equivalents suitable for use in
loadflow and fault level analysis shall be provided. These equivalents will normally be in the
form of a π model or extension with a source (or demand for a loadflow equivalent) at each
node and a linking impedance. The boundary nodes for the equivalent shall be either at the
Connection Point (and in the case of OTSDUW, each Interface Point and Connection
Point) or (where The Company agrees) at suitable nodes (the nodes to be agreed with the
User) within the National Electricity Transmission System. The data at the Connection
Point (and in the case of OTSDUW, each Interface Point and Connection Point) will be
given to a User as follows:
The data items listed under the following parts of PC.A.8.3:-
(a) (i), (ii), (iv), (v), (vi), (vii), (viii), (ix), (x) and (xi)
and the data items shall be provided in accordance with the detailed provisions of PC.A.8.3
(b) - (e).
When an equivalent of this form is not required The Company will not provide the data items
listed under the following parts of PC.A.8.3:-
(a) (vii), (viii), (ix), (x) and (xi)
PC.A.8.3 Data Items
(a) The following is a list of data utilised in this part of the PC. It also contains rules on the
data which generally apply.
(i) symmetrical three-phase short circuit current infeed at the instant of fault from the
National Electricity Transmission System, (I1");
(ii) symmetrical three-phase short circuit current from the National Electricity
Transmission System after the subtransient fault current contribution has
substantially decayed, (I1');
(iii) the zero sequence source resistance and reactance values at the Point of
Connection (and in case of OTSUA, each Interface Point and Connection
Point), consistent with the maximum infeed below;
(iv) the pre-fault voltage magnitude at which the maximum fault currents were
calculated;
(v) the positive sequence X/R ratio at the instant of fault;
PC.B.1 The diagrams below show three examples of single line diagrams, showing the detail that
should be incorporated in the diagram. The first example is for an Network Operator
connection, the second for a Generator connection, the third for a Power Park Module
electrically equivalent system.
Notes:
(1) The electrically equivalent Power Park Unit consists of a number of actual Power Park
Units of the same type ie. any equipment external to the Power Park Unit terminals is
considered as part of the Equivalent Network. Power Park Units of different types shall
be included in separate electrically equivalent Power Park Units. The total number of
equivalent Power Park Units shall represent all of the actual Power Park Units in the
Power Park Module (which could be a DC Connected Power Park Module).
(2) Separate electrically equivalent networks are required for each different type of
electrically equivalent Power Park Unit. The electrically equivalent network shall
include all equipment between the Power Park Unit terminals and the Common
Collection Busbar.
(3) All Plant and Apparatus including the circuit breakers, transformers, lines, cables and
reactive compensation plant between the Common Collection Busbar and Substation
A shall be shown.
PC.C.1 Planning and design of the SPT and SHETL Transmission Systems is based generally, but
not totally, on criteria which evolved from joint consultation among various Transmission
Licensees responsible for design of the National Electricity Transmission System.
PC.C.2 The above criteria are set down within the standards, memoranda, recommendations and
reports and are provided as a guide to system planning. It should be noted that each
scheme for reinforcement or modification of the Transmission System is individually
designed in the light of economic and technical factors associated with the particular system
limitations under consideration.
PC.C.3 The tables below identify the literature referred to above, together with the main topics
considered within each document.
PART 1 – SHETL's TECHNICAL AND DESIGN CRITERIA
PC.D.1 Pursuant to PC.3.4, The Company will not disclose to a Relevant Transmission Licensee
data items specified in the below extract:
PC DATA
DATA DESCRIPTION UNITS
REFERENCE CATEGORY
Option 1
Part of Option 2
PC.A.5.3.2 (d)
Option 2 (i) All Generating Units (including Synchronous
Generating Units forming part of a Synchronous
Power Generating Module)
Maximum Hz DPD II
Normal Hz DPD II
Minimum Hz DPD II
MW Export
MW Import
PC.E.1 In the absence of any relevant Electrical Standards, Offshore Transmission Licensees
and Generators undertaking OTSDUW are required to ensure that all equipment used in the
construction of their network is:
(i) Fully compliant and suitably designed to any relevant Technical Specification;
(ii) Suitable for use and operation in an Offshore environment, where such parts of the
Offshore Transmission System and OTSDUW Plant and Apparatus are located in
Offshore Waters and are not installed in an area that is protected from that Offshore
environment, and
(iii) Compatible with any relevant Electrical Standards or Technical Specifications at the
Offshore Grid Entry Point and Interface Point.
PC.E.2 The table below identifies the technical and design criteria that will be used in the design and
development of an Offshore Transmission System and OTSDUW Plant and Apparatus.
* Note:- Items 2, 3 and 4 above shall only apply at the Interface Point.
PC.F.1 Introduction
PC.F.1.1 Appendix F specifies data requirements to be submitted to The Company by Users and
Users by The Company in respect of OTSDUW.
PC.F.1.2 Such User submissions shall be in accordance with the OTSDUW Development and Data
Timetable in a Construction Agreement.
PC.F.1.3 Such The Company submissions shall be issued with the offer of a CUSC Contract in the
case of the data in Part 1 and otherwise in accordance with the OTSDUW Development
and Data Timetable in a Construction Agreement.
PC.F.2. OTSDUW Network Data and Information
PC.F.2.1 With the offer of a CUSC Contract under the OTSDUW Arrangements The Company shall
provide:
(a) the site specific technical design and operational criteria for the Connection Site;
(b) the site specific technical design and operational criteria for the Interface Point, and
(c) details of The Company’s preliminary identification and consideration of the options
available for the Interface Point in the context of the User’s application for connection
or modification, the preliminary costs used by The Company in assessing such options
and the Offshore Works Assumptions including the assumed Interface Point
identified during these preliminary considerations.
PC.F.2.2 In accordance with the OTSDUW Development and Data Timetable in a Construction
Agreement The Company shall provide the following information and data to a User:
(a) equivalent of the fault infeed or fault level ratings at the Interface Point (as identified in
the Offshore Works Assumptions)
(b) notification of numbering and nomenclature of the HV Apparatus comprised in the
OTSDUW;
(i) past or present physical properties, including both actual and designed physical
properties, of Plant and Apparatus forming part of the National Electricity
Transmission System at the Interface Point at which the OTSUA will be
connected to the extent it is required for the design and construction of the
OTSDUW, including but not limited to:
(ii) the voltage of any part of such Plant and Apparatus;
(iii) the electrical current flowing in or over such Plant and Apparatus;
(iv) the configuration of any part of such Plant and Apparatus
(v) the temperature of any part of such Plant and Apparatus;
(vi) the pressure of any fluid forming part of such Plant and Apparatus
(vii) the electromagnetic properties of such Plant and Apparatus; and
(viii) the technical specifications, settings or operation of any Protection Systems
forming part of such Plant and Apparatus.
(c) information necessary to enable the User to harmonise the OTSDUW with construction
works elsewhere on the National Electricity Transmission System that could affect
the OTSDUW
(d) information related to the current or future configuration of any circuits of the Onshore
Transmission System with which the OTSUA are to connect;
(e) any changes which are planned on the National Electricity Transmission System in
the current or following six Financial Years and which will materially affect the planning
or development of the OTSDUW.
Issue 5 Revision 34 PC 23 May 2019
77 of 79
PC.F.2.3 At the User's reasonable request additional information and data in respect of the National
Electricity Transmission System shall be provided.
PC.F.2.4 OTSDUW Data And Information
PC.F.2.4.1 In accordance with the OTSDUW Development and Data Timetable in a Construction
Agreement the User shall provide to The Company the following information and data
relating to the OTSDUW Plant and Apparatus in accordance with Appendix A of the
Planning Code.
CONTENTS
(This contents page does not form part of the Grid Code)
CC.2 OBJECTIVE
CC.2.1 The objective of the CC is to ensure that by specifying minimum technical, design and
operational criteria the basic rules for connection to the National Electricity Transmission
System and (for certain GB Code Users) to a User's System are similar for all GB Code
Users of an equivalent category and will enable The Company to comply with its statutory
and Transmission Licence obligations.
CC.2.2 In the case of any OTSDUW the objective of the CC is to ensure that by specifying the
minimum technical, design and operational criteria the basic rules relating to an Offshore
Transmission System designed and constructed by an Offshore Transmission Licensee
and designed and/or constructed by an GB Code User under the OTSDUW Arrangements
are equivalent.
CC.2.3 Provisions of the CC which apply in relation to OTSDUW and OTSUA, and/or a
Transmission Interface Site, shall (in any particular case) apply up to the OTSUA Transfer
Time, whereupon such provisions shall (without prejudice to any prior non-compliance)
cease to apply, without prejudice to the continuing application of provisions of the CC
applying in relation to the relevant Offshore Transmission System and/or Connection
Site. It is the case therefore that in cases where the OTSUA become operational prior to the
OTSUA Transfer Time that a GB Generator is required to comply with this CC both as it
applies to its Plant and Apparatus at a Connection Site\Connection Point and the
OTSUA at the Transmission Interface Site/Transmission Interface Point until the
OTSUA Transfer Time and this CC shall be construed accordingly.
CC.2.4 In relation to OTSDUW, provisions otherwise to be contained in a Bilateral Agreement may
be contained in the Construction Agreement, and accordingly a reference in the CC to a
relevant Bilateral Agreement includes the relevant Construction Agreement.
CC.3 SCOPE
CC.3.1 The CC applies to The Company and to GB Code Users, which in the CC means:
(a) GB Generators (other than those which only have Embedded Small Power Stations),
including those undertaking OTSDUW;
(b) Network Operators;
(c) Non-Embedded Customers;
CC.3.3 Embedded Medium Power Stations not subject to a Bilateral Agreement and Embedded
DC Converter Stations not subject to a Bilateral Agreement Provisions.
The following provisions apply in respect of Embedded Medium Power Stations not
subject to a Bilateral Agreement and Embedded DC Converter Stations not subject to a
Bilateral Agreement.
CC.3.3.1 The obligations within the CC that are expressed to be applicable to GB Generators in
respect of Embedded Medium Power Stations not subject to a Bilateral Agreement and
DC Converter Station Owners in respect of Embedded DC Converter Stations not subject
to a Bilateral Agreement (where the obligations are in each case listed in CC.3.3.2) shall be
read and construed as obligations that the Network Operator within whose System any
such Medium Power Station or DC Converter Station is Embedded must ensure are
performed and discharged by the GB Generator or the DC Converter Station owner.
Embedded Medium Power Stations not subject to a Bilateral Agreement and Embedded
DC Converter Stations not subject to a Bilateral Agreement which are located Offshore
and which are connected to an Onshore GB Code Users System will be required to meet
the applicable requirements of the Grid Code as though they are an Onshore GB Generator
or Onshore DC Converter Station Owner connected to an Onshore User System Entry
Point.
CC.3.3.2 The Network Operator within whose System a Medium Power Station not subject to a
Bilateral Agreement is Embedded or a DC Converter Station not subject to a Bilateral
Agreement is Embedded must ensure that the following obligations in the CC are
performed and discharged by the GB Generator in respect of each such Embedded
Medium Power Station or the DC Converter Station owner in the case of an Embedded
DC Converter Station:
CC.5.1
CC.5.2.2
CC.5.3
CC.6.1.3
CC.6.1.5 (b)
CC.6.3.2, CC.6.3.3, CC.6.3.4, CC.6.3.6, CC.6.3.7, CC.6.3.8, CC.6.3.9, CC.6.3.10,
CC.6.3.12, CC.6.3.13, CC.6.3.15, CC.6.3.16
CC.6.4.4
CC.6.5.6 (where required by CC.6.4.4)
that would otherwise have been specified in a Bilateral Agreement will be notified to the
relevant Network Operator in writing in accordance with the provisions of the CUSC and the
Network Operator must ensure such requirements are performed and discharged by the
GB Generator or the DC Converter Station owner.
CC.3.4 In the case of Offshore Embedded Power Stations connected to an Offshore GB Code
User’s System which directly connects to an Offshore Transmission System, any
additional requirements in respect of such Offshore Embedded Power Stations may be
specified in the relevant Bilateral Agreement with the Network Operator or in any Bilateral
Agreement between The Company and such Offshore Embedded Power Station.
CC.3.5 In the case of a GB Generator undertaking OTSDUW connecting to an Onshore Network
Operator’s System, any additional requirements in respect of such OTSDUW Plant and
Apparatus will be specified in the relevant Bilateral Agreement with the GB Generator.
For the avoidance of doubt, requirements applicable to GB Generators undertaking
OTSDUW and connecting to a Network Operator’s User System, shall be consistent with
those applicable requirements of GB Generators undertaking OTSDUW and connecting to a
Transmission Interface Point.
CC.4 PROCEDURE
CC.4.1 The CUSC contains certain provisions relating to the procedure for connection to the
National Electricity Transmission System or, in the case of Embedded Power Stations
or Embedded DC Converter Stations, becoming operational and includes provisions
relating to certain conditions to be complied with by GB Code Users prior to and during the
course of The Company notifying the GB Code User that it has the right to become
operational. The procedure for a GB Code User to become connected is set out in the
Compliance Processes.
CC.5 CONNECTION
CC.5.1 The provisions relating to connecting to the National Electricity Transmission System (or
to a User's System in the case of a connection of an Embedded Large Power Station or
Embedded Medium Power Station or Embedded DC Converter Station) are contained in:
(a) the CUSC and/or CUSC Contract (or in the relevant application form or offer for a
CUSC Contract);
(b) or, in the case of an Embedded Development, the relevant Distribution Code and/or
the Embedded Development Agreement for the connection (or in the relevant
application form or offer for an Embedded Development Agreement),
and include provisions relating to both the submission of information and reports relating to
compliance with the relevant Connection Conditions for that GB Code User, Safety
Rules, commissioning programmes, Operation Diagrams and approval to connect (and
their equivalents in the case of Embedded Medium Power Stations not subject to a
Bilateral Agreement or Embedded DC Converter Stations not subject to a Bilateral
Agreement). References in the CC to the "Bilateral Agreement” and/or “Construction
Agreement" and/or “Embedded Development Agreement” shall be deemed to include
references to the application form or offer therefor.
CC.5.2 Items For Submission
For the avoidance of doubt, disconnection, by frequency or speed based relays is not
permitted within the frequency range 47.5Hz to 51.5Hz, unless agreed with The Company in
accordance with CC.6.3.12.
Grid Voltage Variations
CC.6.1.4 Subject as provided below, the voltage on the 400kV part of the National Electricity
Transmission System at each Connection Site with a GB Code User (and in the case of
OTSDUW Plant and Apparatus, a Transmission Interface Point) will normally remain
within 5% of the nominal value unless abnormal conditions prevail. The minimum voltage is
-10% and the maximum voltage is +10% unless abnormal conditions prevail, but voltages
between +5% and +10% will not last longer than 15 minutes unless abnormal conditions
prevail. Voltages on the 275kV and 132kV parts of the National Electricity Transmission
System at each Connection Site with a User (and in the case of OTSDUW Plant and
Apparatus, a Transmission Interface Point) will normally remain within the limits 10% of
the nominal value unless abnormal conditions prevail. At nominal System voltages below
132kV the voltage of the National Electricity Transmission System at each Connection
Site with a User (and in the case of OTSDUW Plant and Apparatus, a Transmission
Interface Point) will normally remain within the limits 6% of the nominal value unless
abnormal conditions prevail. Under fault conditions, voltage may collapse transiently to zero
at the point of fault until the fault is cleared. The normal operating ranges of the National
Electricity Transmission System are summarised below:
The Company and a GB Code User may agree greater or lesser variations in voltage to
those set out above in relation to a particular Connection Site, and insofar as a greater or
lesser variation is agreed, the relevant figure set out above shall, in relation to that GB Code
User at the particular Connection Site, be replaced by the figure agreed.
Vsteadystate
%Vsteadystate = │100 x │
Vn
and
(iii) Vsteadystate is the voltage at the end of a period of 1 s during which the rate of
change of system voltage over time is ≤ 0.5%;
(iv) Vsteadystate is the difference in voltage between the initial steady state voltage
prior to the RVC (V0) and the final steady state voltage after the RVC (V 0’);
(v) Vmax is the absolute change in the system voltage relative to the initial steady
state system voltage (V0);
(vi) All voltages are the r.m.s. of the voltage measured over one cycle refreshed
every half a cycle as per BS EN 61000-4-30; and
(vii) The applications in the ‘Example Applicability’ column are examples only and are
not definitive.
NOTE 1: 6% is permissible for 100 ms reduced to 3% thereafter as per Figure CC.6.1.7 (1) .
If the profile of repetitive voltage change(s) falls within the envelope given in Figure CC.6.1.7 (1) , the
assessment of such voltage change(s) shall be undertaken according to the recommendations for
assessment of flicker and shall conform to the planning levels provided for flicker.
If any part of the voltage change(s) falls outside the envelope given in Figure CC.6.1.7(1), the assessment
of such voltage changes, repetitive or not, shall be done according to the guidance and limits for RVCs.
NOTE 2: No more than 1 event is permitted per day, consisting of up to 4 RVCs, each separated by at least 10
(b) The voltage change limit is the absolute maximum allowed of either the phase-to-earth
voltage change or the phase-to-phase voltage change, whichever is the highest. The
limits do not apply to single phasor equivalent voltages, e.g. positive phase sequence
(PPS) voltages. For high impedance earthed systems, the maximum phase-to-phase,
i.e. line voltage, should be used for assessment.
(c) The RVCs in Category 2 and 3 should not exceed the limits depicted in the time
dependent characteristic shown in Figure CC.6.1.7 (2) and Figure CC.6.1.7 (3)
respectively. These limits do not apply to: 1) fault clearance operations; or 2) immediate
operations in response to fault conditions; or 3) operations relating to post fault system
restoration (for the avoidance of doubt this third exception pertains to a fault that is
external to the Users plant and apparatus).
(d) Any RVCs permitted in Category 2 and Category 3 should be at least 10 minutes apart.
(e) The value of Vsteadystate should be established immediately prior to the start of a RVC.
Following a RVC, the voltage should remain within the relevant envelope, as shown in
Figures CC.6.1.7 (1), CC.6.1.7 (2), CC.6.1.7 (3), until a Vsteadystate condition has been
satisfied.
V0+3%
V0
V0−3%
V0−6%
V0−10%
V0+6%
V0+3%
V0
V0−3%
V0−10%
V0−12%
(f) The voltage change between two steady state voltage conditions should not exceed 3%. (The limit
is based on 3% of the nominal voltage of the system (Vn) as measured at the Point of Common
Coupling. The step voltage change as measured at the customer’s supply terminals or equipment
terminals could be greater. For example: The step voltage change limit stated in BS EN 61000-3-3
and BS EN 61000-3-11 is 3.3% when measured at the equipment terminals.)
(g) The limits apply to voltage changes measured at the Point of Common Coupling.
(h) Category 3 events that are planned should be notified to The Company in advance.
NOTE 1: The magnitude of Pst is linear with respect to the magnitude of the voltage changes giving rise to it.
NOTE 2: Extreme caution is advised in allowing any excursions of P st and Plt above the planning level.
The values and figures referred to in this paragraph CC.6.1.7 are derived from Engineering
Recommendation P28 Issue 2.
CC.6.1.8 Voltage fluctuations at a Point of Common Coupling with a fluctuating Load directly
connected to an Offshore Transmission System (or in the case of OTSDUW, OTSDUW
Plant and Apparatus) shall not exceed the limits set out in the Bilateral Agreement.
Sub-Synchronous Resonance and Sub-Synchronous Torsional Interaction
CC.6.1.9 The Company shall ensure that GB Code Users' Plant and Apparatus will not be subject
to unacceptable Sub-Synchronous Oscillation conditions as specified in the relevant Licence
Standards.
CC.6.1.10 The Company shall ensure where necessary, and in consultation with Relevant
Transmission Licensees where required, that any relevant site specific conditions
applicable at a GB Code User's Connection Site, including a description of the Sub-
Synchronous Oscillation conditions considered in the application of the relevant License
Standards, are set out in the GB Code User's Bilateral Agreement.
Figure 1
Point A is equivalent 0.95 leading Power Factor at Rated MW output or Interface Point
(in MVAr) to Capacity in the case of OTSDUW Plant and Apparatus
Point B is equivalent 0.95 lagging Power Factor at Rated MW output or Interface Point
(in MVAr) to: Capacity in the case of OTSDUW Plant and Apparatus
Point C is equivalent -5% of Rated MW output or Interface Point Capacity in the case
(in MVAr) to: of OTSDUW Plant and Apparatus
Point E is equivalent -12% of Rated MW output or Interface Point Capacity in the case
(in MVAr) to: of OTSDUW Plant and Apparatus
(d) All Onshore Non-Synchronous Generating Units and Onshore Power Park
Modules in Scotland with a Completion Date after 1 April 2005 and before 1 January
2006 must be capable of supplying Rated MW at the range of power factors either:
(i) from 0.95 lead to 0.95 lag as illustrated in Figure 1 at the User System Entry
Point for Embedded GB Generators or at the HV side of the 33/132kV or
33/275kV or 33/400kV transformer for GB Generators directly connected to the
Onshore Transmission System. With all Plant in service, the Reactive Power
limits defined at Rated MW will apply at all Active Power output levels above 20%
of the Rated MW output as defined in Figure 1. These Reactive Power limits will
be reduced pro rata to the amount of Plant in service, or
(ii) from 0.95 lead to 0.90 lag at the Onshore Non-Synchronous Generating Unit
(including Power Park Unit) terminals. For the avoidance of doubt GB Generators
complying with this option (ii) are not required to comply with CC.6.3.2(b).
(e) The short circuit ratio of Offshore Synchronous Generating Units at a Large Power
Station shall be not less than 0.5. At a Large Power Station all Offshore
Synchronous Generating Units, Offshore Non-Synchronous Generating Units,
Offshore DC Converters and Offshore Power Park Modules must be capable of
maintaining:
(i) zero transfer of Reactive Power at the Offshore Grid Entry Point for all GB
Generators with an Offshore Grid Entry Point at the LV Side of the Offshore
Platform at all Active Power output levels under steady state voltage conditions.
The steady state tolerance on Reactive Power transfer to and from an Offshore
Transmission System expressed in MVAr shall be no greater than 5% of the
Rated MW, or
(ii) a transfer of Reactive Power at the Offshore Grid Entry Point at a value
specified in the Bilateral Agreement that will be equivalent to zero at the LV Side
of the Offshore Platform. In addition, the steady state tolerance on Reactive
Power transfer to and from an Offshore Transmission System expressed in
MVAr at the LV Side of the Offshore Platform shall be no greater than 5% of the
Rated MW, or
(iii) the Reactive Power capability (within associated steady state tolerance) specified
in the Bilateral Agreement if any alternative has been agreed with the GB
Generator, Offshore Transmission Licensee and The Company.
(f) In addition, a Genset shall meet the operational requirements as specified in BC2.A.2.6.
CC.6.3.3 Each Generating Unit, DC Converter (including an OTSDUW DC Converter), Power Park
Module and/or CCGT Module must be capable of:
(a) continuously maintaining constant Active Power output for System Frequency
changes within the range 50.5 to 49.5 Hz; and
Figure 2
(c) For the avoidance of doubt in the case of a Generating Unit or Power Park Module (or
OTSDUW DC Converters at the Interface Point) using an Intermittent Power Source
where the mechanical power input will not be constant over time, the requirement is that
the Active Power output shall be independent of System Frequency under (a) above
and should not drop with System Frequency by greater than the amount specified in
(b) above.
(d) A DC Converter Station must be capable of maintaining its Active Power input (i.e.
when operating in a mode analogous to Demand) from the National Electricity
Transmission System (or User System in the case of an Embedded DC Converter
Station) at a level not greater than the figure determined by the linear relationship
shown in Figure 3 for System Frequency changes within the range 49.5 to 47 Hz, such
that if the System Frequency drops to 47.8 Hz the Active Power input decreases by
more than 60%.
100% of Active
Power Input
40% of Active
Power Input
Figure 3
(e) At a Large Power Station, in the case of an Offshore Generating Unit, Offshore
Power Park Module, Offshore DC Converter and OTSDUW DC Converter, the GB
Generator shall comply with the requirements of CC.6.3.3. GB Generators should be
aware that Section K of the STC places requirements on Offshore Transmission
Licensees which utilise a Transmission DC Converter as part of their Offshore
Transmission System to make appropriate provisions to enable GB Generators to
fulfil their obligations.
(f) In the case of an OTSDUW DC Converter the OTSDUW Plant and Apparatus shall
provide a continuous signal indicating the real time frequency measured at the
Interface Point to the Offshore Grid Entry Point.
CC.6.3.4 At the Grid Entry Point, the Active Power output under steady state conditions of any
Generating Unit, DC Converter or Power Park Module directly connected to the National
Electricity Transmission System or in the case of OTSDUW, the Active Power transfer at
the Interface Point, under steady state conditions of any OTSDUW Plant and Apparatus
should not be affected by voltage changes in the normal operating range specified in
paragraph CC.6.1.4 by more than the change in Active Power losses at reduced or
increased voltage. In addition:
(a) For any Onshore Generating Unit, Onshore DC Converter and Onshore Power
Park Module or OTSDUW the Reactive Power output under steady state conditions
should be fully available within the voltage range 5% at 400kV, 275kV and 132kV and
lower voltages, except for an Onshore Power Park Module or Onshore Non-
Synchronous Generating Unit if Embedded at 33kV and below (or directly connected
to the Onshore Transmission System at 33kV and below) where the requirement
shown in Figure 4 applies.
(b) At a Large Power Station, in the case of an Offshore Generating Unit, Offshore DC
Converter and Offshore Power Park Module where an alternative reactive capability
has been agreed with the GB Generator, as specified in CC.6.3.2(e) (iii), the voltage /
Reactive Power requirement shall be specified in the Bilateral Agreement. The
Reactive Power output under steady state conditions shall be fully available within the
voltage range 5% at 400kV, 275kV and 132kV and lower voltages.
105%
100%
95%
Power Factor 0.95 Lead at Rated 1.0 Power Factor 0.95 lag at Rated MW
MW output or Onshore Grid output or Onshore Grid Entry Point
Entry Point equivalent Power equivalent Power Factor if connected
Factor if connected to the to the Onshore Transmission
Onshore Transmission System System in Scotland or optionally in
in Scotland Scotland for Plant with a Completion
Date before 1 January 2006 Power
Factor 0.9 lag at an Onshore Non-
synchronous Generating Unit or
Onshore Power Park Unit Terminals
Figure 4
CC.6.3.5 It is an essential requirement that the National Electricity Transmission System must
incorporate a Black Start Capability. This will be achieved by agreeing a Black Start
Capability at a number of strategically located Power Stations. For each Power Station
The Company will state in the Bilateral Agreement whether or not a Black Start
Capability is required.
Control Arrangements
CC.6.3.6 (a) Each:
(i) Offshore Generating Unit in a Large Power Station or Onshore Generating
Unit; or,
(ii) Onshore DC Converter with a Completion Date on or after 1 April 2005 or
Offshore DC Converter at a Large Power Station; or,
(iii) Onshore Power Park Module in England and Wales with a Completion Date on
or after 1 January 2006; or,
(iv) Onshore Power Park Module in operation in Scotland on or after 1 January 2006
(with a Completion Date after 1 July 2004 and in a Power Station with a
Registered Capacity of 50MW or more); or,
(v) Offshore Power Park Module in a Large Power Station with a Registered
Capacity of 50MW or more;
must be capable of contributing to Frequency control by continuous modulation of
Active Power supplied to the National Electricity Transmission System or the User
System in which it is Embedded. For the avoidance of doubt each OTSDUW DC
Converter shall provide each GB Code User in respect of its Offshore Power
Stations connected to and/or using an Offshore Transmission System a continuous
signal indicating the real time Frequency measured at the Transmission Interface
Point.
(b) Each:
(i) Onshore Generating Unit; or,
(ii) Onshore DC Converter (with a Completion Date on or after 1 April 2005
excluding current source technologies); or
Issue 5 Revision 38 CC 04 September 2019
26 of 97
(iii) Onshore Power Park Module in England and Wales with a Completion Date on
or after 1 January 2006; or,
(iv) Onshore Power Park Module in Scotland irrespective of Completion Date; or,
(v) Offshore Generating Unit at a Large Power Station, Offshore DC Converter at
a Large Power Station or Offshore Power Park Module at a Large Power
Station which provides a reactive range beyond the minimum requirements
specified in CC.6.3.2(e) (iii); or,
(vi) OTSDUW Plant and Apparatus at a Transmission Interface Point
must be capable of contributing to voltage control by continuous changes to the
Reactive Power supplied to the National Electricity Transmission System or the
User System in which it is Embedded.
CC.6.3.7 (a) Each Generating Unit, DC Converter or Power Park Module (excluding Onshore
Power Park Modules in Scotland with a Completion Date before 1 July 2004 or
Onshore Power Park Modules in a Power Station in Scotland with a Registered
Capacity less than 50MW or Offshore Power Park Modules in a Large Power
Station located Offshore with a Registered Capacity less than 50MW) must be fitted
with a fast acting proportional Frequency control device (or turbine speed governor)
and unit load controller or equivalent control device to provide Frequency response
under normal operational conditions in accordance with Balancing Code 3 (BC3). In
the case of a Power Park Module the Frequency or speed control device(s) may be on
the Power Park Module or on each individual Power Park Unit or be a combination of
both. The Frequency control device(s) (or speed governor(s)) must be designed and
operated to the appropriate:
(i) European Specification; or
(ii) in the absence of a relevant European Specification, such other standard which
is in common use within the European Community (which may include a
manufacturer specification);
as at the time when the installation of which it forms part was designed or (in the case of
modification or alteration to the Frequency control device (or turbine speed governor))
when the modification or alteration was designed.
The European Specification or other standard utilised in accordance with sub-
paragraph CC.6.3.7 (a) (ii) will be notified to The Company by the GB Generator or DC
Converter Station owner or, in the case of an Embedded Medium Power Station not
subject to a Bilateral Agreement or Embedded DC Converter Station not subject to a
Bilateral Agreement, the relevant Network Operator:
(i) as part of the application for a Bilateral Agreement; or
(ii) as part of the application for a varied Bilateral Agreement; or
(iii) in the case of an Embedded Development, within 28 days of entry into the
Embedded Development Agreement (or such later time as agreed with The
Company); or
(iv) as soon as possible prior to any modification or alteration to the Frequency control
device (or governor); and
(b) The Frequency control device (or speed governor) in co-ordination with other control
devices must control the Generating Unit, DC Converter or Power Park Module
Active Power Output with stability over the entire operating range of the Generating
Unit, DC Converter or Power Park Module; and
(c) The Frequency control device (or speed governor) must meet the following minimum
requirements:
(i) Where a Generating Unit, DC Converter or Power Park Module becomes
(vi) In particular, other control facilities, including constant Reactive Power output
control modes and constant Power Factor control modes (but excluding VAR
limiters) are not required. However, if present in the excitation or voltage control
system they will be disabled unless the Bilateral Agreement records otherwise.
Operation of such control facilities will be in accordance with the provisions
contained in BC2.
(b) Excitation and voltage control performance requirements applicable to Offshore
Generating Units at a Large Power Station, Offshore Power Park Modules at a
Large Power Station and Offshore DC Converters at a Large Power Station.
A continuously acting automatic control system is required to provide either:
(i) control of Reactive Power (as specified in CC.6.3.2(e) (i) (ii)) at the Offshore Grid
Entry Point without instability over the entire operating range of the Offshore
Generating Unit, Offshore DC Converter or Offshore Power Park Module. The
performance requirements for this automatic control system will be specified in the
15
Figure 5b
(ii) provide Active Power output at the Grid Entry Point or in the case of an
OTSDUW, Active Power transfer capability at the Transmission Interface Point,
during Supergrid Voltage dips on the Onshore Transmission System as
described in Figure 5b, at least in proportion to the retained balanced voltage at the
Onshore Grid Entry Point (for Onshore Power Park Modules) or Interface
Point (for OTSDUW Plant and Apparatus and Offshore Power Park Modules)
(or the retained balanced voltage at the User System Entry Point if Embedded)
except in the case of a Non-Synchronous Generating Unit or OTSDUW Plant
and Apparatus or Power Park Module where there has been a reduction in the
Intermittent Power Source or in the case of OTSDUW Active Power transfer
capability in the time range in Figure 5b that restricts the Active Power output or in
the case of an OTSDUW Active Power transfer capability below this level and
shall generate maximum reactive current (where the voltage at the Grid Entry
Point, or in the case of an OTSDUW Plant and Apparatus, the Interface Point
voltage, is outside the limits specified in CC.6.1.4) without exceeding the transient
rating limits of the OTSDUW Plant and Apparatus or Power Park Module and
any constituent Power Park Unit; and,
(iii) restore Active Power output (or, in the case of OTSDUW, Active Power transfer
capability), following Supergrid Voltage dips on the Onshore Transmission
System as described in Figure 5b, within 1 second of restoration of the voltage at
the:
Onshore Grid Entry Point for directly connected Onshore Power Park
Modules or,
100%
94%
60%
15%
Figure 6
V/VN is the ratio of the actual voltage on one or more phases at the LV Side of the
Offshore Platform to the nominal voltage of the LV Side of the Offshore
Platform.
(ii) Each Offshore Generating Unit, or Offshore Power Park Module and any
constituent Power Park Unit thereof shall provide Active Power output, during
voltage dips on the LV Side of the Offshore Platform as described in Figure 6, at
least in proportion to the retained voltage at the LV Side of the Offshore Platform
except in the case of an Offshore Non-Synchronous Generating Unit or
Offshore Power Park Module where there has been a reduction in the
Intermittent Power Source in the time range in Figure 6 that restricts the Active
Power output below this level and shall generate maximum reactive current
without exceeding the transient rating limits of the Offshore Generating Unit or
Offshore Power Park Module and any constituent Power Park Unit or, in the
case of Plant and Apparatus installed on or after 1 December 2017, reactive
compensation equipment. Once the Active Power output has been restored to the
required level, Active Power oscillations shall be acceptable provided that:
- the total Active Energy delivered during the period of the oscillations is at
least that which would have been delivered if the Active Power was constant
- the oscillations are adequately damped
and;
(iii) Each Offshore DC Converter shall be designed to meet the Active Power
recovery characteristics as specified in the Bilateral Agreement upon restoration
of the voltage at the LV Side of the Offshore Platform.
(ii) provide Active Power output, during voltage dips on the LV Side of the Offshore
Platform as described in Figure 7a, at least in proportion to the retained balanced
or unbalanced voltage at the LV Side of the Offshore Platform and shall
generate maximum reactive current (where the voltage at the Offshore Grid Entry
Point is outside the limits specified in CC.6.1.4) without exceeding the transient
rating limits of the Offshore Synchronous Generating Unit and,
(iii) within 1 second of restoration of the voltage to 1.0p.u of the nominal voltage at the
LV Side of the Offshore Platform, restore Active Power to at least 90% of the
Offshore Synchronous Generating Unit's immediate pre-disturbed value, unless
there has been a reduction in the Intermittent Power Source in the time range in
Figure 7a that restricts the Active Power output below this level. Once the Active
Power output has been restored to the required level, Active Power oscillations
shall be acceptable provided that:
- the total Active Energy delivered during the period of the oscillations is at
least that which would have been delivered if the Active Power was constant
- the oscillations are adequately damped
(2b) Requirements applicable to Offshore Power Park Modules to withstand voltage dips
on the LV Side of the Offshore Platform greater than 140ms in duration.
15
Figure 7b
(ii) provide Active Power output, during voltage dips on the LV Side of the Offshore
Platform as described in Figure 7b, at least in proportion to the retained balanced
or unbalanced voltage at the LV Side of the Offshore Platform except in the case
of an Offshore Non-Synchronous Generating Unit or Offshore Power Park
Module where there has been a reduction in the Intermittent Power Source in
the time range in Figure 7b that restricts the Active Power output below this level
and shall generate maximum reactive current (where the voltage at the Offshore
Grid Entry Point is outside the limits specified in CC.6.1.4) without exceeding the
transient rating limits of the Offshore Power Park Module and any constituent
Power Park Unit or reactive compensation equipment. For Plant and Apparatus
installed on or after 1 December 2017, switched reactive compensation equipment
(such as mechanically switched capacitors and reactors) shall be controlled such
that it is not switched in or out of service during the fault but may act to assist in
post fault voltage recovery; and,
(iii) within 1 second of the restoration of the voltage at the LV Side of the Offshore
Platform (to the minimum levels specified in CC.6.1.4) restore Active Power to at
least 90% of the Offshore Power Park Module's immediate pre-disturbed value,
unless there has been a reduction in the Intermittent Power Source in the time
range in Figure 7b that restricts the Active Power output below this level. Once the
Active Power output has been restored to the required level, Active Power
oscillations shall be acceptable provided that:
Issue 5 Revision 38 CC 04 September 2019
39 of 97
- the total Active Energy delivered during the period of the oscillations is at
least that which would have been delivered if the Active Power was constant
- the oscillations are adequately damped
CC.6.3.15.3 Other Requirements
(i) In the case of a Power Park Module (comprising of wind-turbine generator units), the
requirements in CC.6.3.15.1 and CC.6.3.15.2 do not apply when the Power Park
Module is operating at less than 5% of its Rated MW or during very high wind speed
conditions when more than 50% of the wind turbine generator units in a Power Park
Module have been shut down or disconnected under an emergency shutdown
sequence to protect GB Code User’s Plant and Apparatus.
(ii) In addition to meeting the conditions specified in CC.6.1.5(b) and CC.6.1.6, each Non-
Synchronous Generating Unit, OTSDUW Plant and Apparatus or Power Park
Module with a Completion Date after 1 April 2005 and any constituent Power Park
Unit thereof will be required to withstand, without tripping, the negative phase sequence
loading incurred by clearance of a close-up phase-to-phase fault, by System Back-Up
Protection on the Onshore Transmission System operating at Supergrid Voltage.
(iii) In the case of an Onshore Power Park Module in Scotland with a Completion Date
before 1 January 2004 and a Registered Capacity less than 30MW the requirements in
CC.6.3.15.1 (a) do not apply. In the case of an Onshore Power Park Module in
Scotland with a Completion Date on or after 1 January 2004 and before 1 July 2005
and a Registered Capacity less than 30MW the requirements in CC.6.3.15.1 (a) are
relaxed from the minimum Onshore Transmission System Supergrid Voltage of zero
to a minimum Onshore Transmission System Supergrid Voltage of 15% of nominal.
In the case of an Onshore Power Park Module in Scotland with a Completion Date
before 1 January 2004 and a Registered Capacity of 30MW and above the
requirements in CC.6.3.15.1 (a) are relaxed from the minimum Onshore Transmission
System Supergrid Voltage of zero to a minimum Onshore Transmission System
Supergrid Voltage of 15% of nominal.
(iv) To avoid unwanted island operation, Non-Synchronous Generating Units in Scotland
(and those directly connected to a Scottish Offshore Transmission System), Power
Park Modules in Scotland (and those directly connected to a Scottish Offshore
Transmission System) , or OTSDUW Plant and Apparatus with an Interface Point in
Scotland shall be tripped for the following conditions:
(1) Frequency above 52Hz for more than 2 seconds
(2) Frequency below 47Hz for more than 2 seconds
(3) Voltage as measured at the Onshore Connection Point or Onshore User
System Entry Point or Offshore Grid Entry Point or Interface Point in the case
of OTSDUW Plant and Apparatus is below 80% for more than 2.5 seconds
(4) Voltage as measured at the Onshore Connection Point or Onshore User
System Entry Point or Offshore Grid Entry Point or Interface Point in the case
of OTSDUW Plant and Apparatus is above 120% (115% for 275kV) for more than
1 second.
The times in sections (1) and (2) are maximum trip times. Shorter times may be used to
protect the Non-Synchronous Generating Units, or OTSDUW Plant and Apparatus
or Power Park Modules.
(c) Detailed specifications of these required electronic facilities will be provided by The
Company on request and they are listed as Electrical Standards in the Annex to the
General Conditions.
Facsimile Machines
CC.6.5.9 Each GB Code User and The Company shall provide a facsimile machine or machines:
(a) in the case of GB Generators, at the Control Point of each Power Station and at its
Trading Point;
(b) in the case of The Company and Network Operators, at the Control Centre(s); and
(c) in the case of Non-Embedded Customers and DC Converter Station owners at the
Control Point.
Each GB Code User shall notify, prior to connection to the System of the GB Code User's
Plant and Apparatus, The Company of its or their telephone number or numbers, and will
notify The Company of any changes. Prior to connection to the System of the GB Code
User's Plant and Apparatus The Company shall notify each GB Code User of the
telephone number or numbers of its facsimile machine or machines and will notify any
changes.
CC.6.5.10 Busbar Voltage
The Relevant Transmission Licensee shall, subject as provided below, provide each GB
Generator or DC Converter Station owner at each Grid Entry Point where one of its
Power Stations or DC Converter Stations is connected with appropriate voltage signals to
enable the GB Generator or DC Converter Station owner to obtain the necessary
information to permit its Gensets or DC Converters to be Synchronised to the National
Electricity Transmission System. The term "voltage signal" shall mean in this context, a
point of connection on (or wire or wires from) a relevant part of Transmission Plant and/or
Apparatus at the Grid Entry Point, to which the GB Generator or DC Converter Station
owner, with The Company's agreement (not to be unreasonably withheld) in relation to the
Plant and/or Apparatus to be attached, will be able to attach its Plant and/or Apparatus
(normally a wire or wires) in order to obtain measurement outputs in relation to the busbar.
CC.6.5.11 Bilingual Message Facilities
CC.A.1.1 Principles
Types of Schedules
CC.A.1.1.1 At all Complexes (which in the context of this CC shall include, Interface Sites until the
OTSUA Transfer Time) the following Site Responsibility Schedules shall be drawn up
using the relevant proforma attached or with such variations as may be agreed between The
Company and Users, but in the absence of agreement the relevant proforma attached will
be used. In addition, in the case of OTSDUW Plant and Apparatus, and in readiness for the
OTSUA Transfer Time, the User shall provide The Company with the necessary
information such that Site Responsibility Schedules in this form can be prepared by the
Relevant Transmission Licensees for the Transmission Interface Site:
(a) Schedule of HV Apparatus
(b) Schedule of Plant, LV/MV Apparatus, services and supplies;
(c) Schedule of telecommunications and measurements Apparatus.
Other than at Generating Unit, DC Converter, Power Park Module and Power Station
locations, the schedules referred to in (b) and (c) may be combined.
New Connection Sites
CC.A.1.1.2 In the case of a new Connection Site each Site Responsibility Schedule for a
Connection Site shall be prepared by The Company in consultation with relevant GB Code
Users at least 2 weeks prior to the Completion Date (or, where the OTSUA is to become
Operational prior to the OTSUA Transfer Time, an alternative date) under the Bilateral
Agreement and/or Construction Agreement for that Connection Site (which may form
part of a Complex). In the case of a new Interface Site where the OTSUA is to become
Operational prior to the OTSUA Transfer Time each Site Responsibility Schedule for an
Interface Site shall be prepared by The Company in consultation with relevant GB Code
Users at least 2 weeks prior to the Completion Date under the Bilateral Agreement and/or
Construction Agreement for that Interface Site (which may form part of a Complex) (and
references to and requirements placed on “Connection Site” in this CC shall also be read
as “Interface Site” where the context requires and until the OTSUA Transfer Time). Each
GB Code User shall, in accordance with the timing requirements of the Bilateral
Agreement and/or Construction Agreement , provide information to The Company to
enable it to prepare the Site Responsibility Schedule.
Sub-division
CC.A.1.1.3 Each Site Responsibility Schedule will be subdivided to take account of any separate
Connection Sites on that Complex.
Scope
CC.A.1.1.4 Each Site Responsibility Schedule shall detail for each item of Plant and Apparatus:
(a) Plant/Apparatus ownership;
(b) Site Manager (Controller) (except in the case of Plant/Apparatus located in SPT’s
Transmission Area);
(c) Safety issues comprising applicable Safety Rules and Control Person or other
responsible person (Safety Co-ordinator), or such other person who is responsible for
safety;
(d) Operations issues comprising applicable Operational Procedures and control
engineer;
1 Details of circuits traversing the Connection Site are only needed from the date which is the earlier of the date when the Site
Responsibility Schedule is first updated and 15th October 2004. In Scotland or Offshore, from a date to be agreed between The
Company and the Relevant Transmission Licensee.
AREA
COMPLEX: SCHEDULE:
CONNECTION SITE:
AREA
COMPLEX: SCHEDULE:
CONNECTION SITE:
NOTES:
Basic Principles
(1) Where practicable, all the HV Apparatus on any Connection Site shall be shown on one
Operation Diagram. Provided the clarity of the diagram is not impaired, the layout shall
represent as closely as possible the geographical arrangement on the Connection Site.
(2) Where more than one Operation Diagram is unavoidable, duplication of identical
information on more than one Operation Diagram must be avoided.
(3) The Operation Diagram must show accurately the current status of the Apparatus e.g.
whether commissioned or decommissioned. Where decommissioned, the associated
switchbay will be labelled "spare bay".
(4) Provision will be made on the Operation Diagram for signifying approvals, together with
provision for details of revisions and dates.
(5) Operation Diagrams will be prepared in A4 format or such other format as may be agreed
with The Company.
(6) The Operation Diagram should normally be drawn single line. However, where appropriate,
detail which applies to individual phases shall be shown. For example, some HV Apparatus
is numbered individually per phase.
CC.A.4A.1 Scope
The fault ride through requirement is defined in CC.6.3.15.1 (a), (b) and CC.6.3.15.3. This
Appendix provides illustrations by way of examples only of CC.6.3.15.1 (a) (i) and further
background and illustrations to CC.6.3.15.1 (1b) (i) and CC.6.3.15.1 (2b) (i) and is not
intended to show all possible permutations.
CC.A.4A.2 Short Circuit Faults At Supergrid Voltage On The Onshore Transmission System Up To
140ms In Duration
For short circuit faults at Supergrid Voltage on the Onshore Transmission System (which
could be at an Interface Point) up to 140ms in duration, the fault ride through requirement is
defined in CC.6.3.15.1 (a) (i). Figures CC.A.4A.1 (a) and (b) illustrate two typical examples of
voltage recovery for short-circuit faults cleared within 140ms by two circuit breakers (a) and
three circuit breakers (b) respectively.
CC.A.4A.3 Supergrid Voltage Dips On The Onshore Transmission System Greater Than 140ms In
Duration
CC.A.4A3.1 Requirements applicable to Synchronous Generating Units subject to Supergrid Voltage
dips on the Onshore Transmission System greater than 140ms in duration.
For balanced Supergrid Voltage dips on the Onshore Transmission System having
durations greater than 140ms and up to 3 minutes, the fault ride through requirement is
defined in CC.6.3.15.1 (1b) and Figure 5a which is reproduced in this Appendix as Figure
CC.A.4A3.1 and termed the voltage–duration profile.
This profile is not a voltage-time response curve that would be obtained by plotting the
transient voltage response at a point on the Onshore Transmission System (or User
System if located Onshore) to a disturbance. Rather, each point on the profile (i.e. the
heavy black line) represents a voltage level and an associated time duration which
connected Synchronous Generating Units must withstand or ride through.
Figures CC.A.4A3.2 (a), (b) and (c) illustrate the meaning of the voltage-duration profile for
voltage dips having durations greater than 140ms.
CC.A.4A3.2 Requirements applicable to Power Park Modules or OTSDUW Plant and Apparatus
subject to Supergrid Voltage dips on the Onshore Transmission System greater than
140ms in duration
For balanced Supergrid Voltage dips on the Onshore Transmission System (which could
be at an Interface Point) having durations greater than 140ms and up to 3 minutes the fault
ride through requirement is defined in CC.6.3.15.1 (2b) and Figure 5b which is reproduced in
this Appendix as Figure CC.A.4A3.3 and termed the voltage–duration profile.
Figure CC.A.4A3.3
CC.A.4B.1 Scope
The fault ride through requirement is defined in CC.6.3.15.2 (a), (b) and CC.6.3.15.3. This
Appendix provides illustrations by way of examples only of CC.6.3.15.2 (a) (i) and further
background and illustrations to CC.6.3.15.2 (1b) and CC.6.3.15.2 (2b) and is not intended to
show all possible permutations.
CC.A.4B.2 Voltage Dips On The LV Side Of The Offshore Platform Up To 140ms In Duration
For voltage dips on the LV Side of the Offshore Platform which last up to 140ms in
duration, the fault ride through requirement is defined in CC.6.3.15.2 (a) (i). This includes
Figure 6 which is reproduced here in Figure CC.A.4B.1. The purpose of this requirement is
to translate the conditions caused by a balanced or unbalanced fault which occurs on the
Onshore Transmission System (which may include the Interface Point) at the LV Side of
the Offshore Platform.
V/VN is the ratio of the voltage at the LV side of the Offshore Platform to the nominal
voltage of the LV side of the Offshore Platform.
Figure CC.A.4B.1
Figures CC.A.4B.2 (a) and CC.A.4B.2 (b) illustrate two typical examples of the voltage
recovery seen at the LV Side of the Offshore Platform for a short circuit fault cleared within
140ms by (a) two circuit breakers and (b) three circuit breakers on the Onshore
Transmission System.
CCA.4B.3 Voltage Dips Which Occur On The LV Side Of The Offshore Platform Greater Than 140ms
In Duration
CC.A.4B.3.1 Requirements applicable to Offshore Synchronous Generating Units subject to voltage
dips which occur on the LV Side of the Offshore Platform greater than 140ms in duration.
In addition to CC.A.4B.2 the fault ride through requirements applicable to Offshore
Synchronous Generating Units during balanced voltage dips which occur at the LV Side
of the Offshore Platform and having durations greater than 140ms and up to 3 minutes are
defined in CC.6.3.15.2 (1b) and Figure 7a which is reproduced in this Appendix as Figure
CC.A.4B3.1 and termed the voltage–duration profile.
This profile is not a voltage-time response curve that would be obtained by plotting the
transient voltage response at the LV Side of the Offshore Platform to a disturbance.
Rather, each point on the profile (i.e. the heavy black line) represents a voltage level and an
associated time duration which connected Offshore Synchronous Generating Units must
withstand or ride through.
Figure CC.A.4B3.1
CC.A.4B.3.2 Requirements applicable to Offshore Power Park Modules subject to Voltage Dips Which
Occur On The LV Side Of The Offshore Platform Greater Than 140ms in Duration.
In addition to CCA.4B.2 the fault ride through requirements applicable for Offshore Power
Park Modules during balanced voltage dips which occur at the LV Side of the Offshore
Platform and have durations greater than 140ms and up to 3 minutes are defined in
CC.6.3.15.2 (2b) (i) and Figure 7b which is reproduced in this Appendix as Figure CC.A.4B.4
and termed the voltage–duration profile.
Figure CC.A.4B.4
Figure CC.A.4B.5(c)
(b) Operating time: Relay operating time shall not be more than 150 ms;
(e) Output contacts: Two output contacts per stage to be capable of repetitively
making and breaking for 1000 operations:
48.8 5
48.75 5
48.7 10
48.6 7.5 10
48.5 7.5 10
48.4 7.5 10 10
48.2 7.5 10 10
48.0 5 10 10
47.8 5
Total % Demand 60 40 40
Table CC.A.5.5.1a
Note – the percentages in table CC.A.5.5.1a are cumulative such that, for example, should
the frequency fall to 48.6 Hz in the NGET Transmission Area, 27.5% of the total Demand
connected to the National Electricity Transmission System in the NGET Transmission
Area shall be disconnected by the action of Low Frequency Relays.
The percentage Demand at each stage shall be allocated as far as reasonably practicable.
The cumulative total percentage Demand is a minimum.
CC.A.6.2.5.5 The Power System Stabiliser shall include elements that limit the bandwidth of the output
signal. The bandwidth limiting must ensure that the highest frequency of response cannot
excite torsional oscillations on other plant connected to the network. A bandwidth of 0-5Hz
would be judged to be acceptable for this application.
CC.A.6.2.5.6 The GB Generator will agree Power System Stabiliser settings with The Company, in
coordination with the Relevant Transmission Licensee prior to the on-load commissioning
detailed in BC2.11.2(d). To allow assessment of the performance before on-load
commissioning the GB Generator will provide to The Company a report covering the areas
specified in CP.A.3.2.1.
CC.A.6.2.5.7 The Power System Stabiliser must be active within the Excitation System at all times
when Synchronised including when the Under Excitation Limiter or Over Excitation
Limiter are active. When operating at low load when Synchronising or De-Synchronising
an Onshore Generating Unit, the Power System Stabiliser may be out of service.
CC.A.6.2.5.8 Where a Power System Stabiliser is fitted to a Pumped Storage Unit it must function
when the Pumped Storage Unit is in both generating and pumping modes.
CC.A.6.2.6 Overall Excitation System Control Characteristics
CC.A.6.2.6.1 The overall Excitation System shall include elements that limit the bandwidth of the output
signal. The bandwidth limiting must be consistent with the speed of response requirements
and ensure that the highest frequency of response cannot excite torsional oscillations on
other plant connected to the network. A bandwidth of 0-5 Hz will be judged to be acceptable
for this application.
CC.A.6.2.6.2 The response of the Automatic Voltage Regulator combined with the Power System
Stabiliser shall be demonstrated by injecting similar step signal disturbances into the
Automatic Voltage Regulator reference as detailed in OC5A.2.2 and OC5.A.2.4. The
Automatic Voltage Regulator shall include a facility to allow step injections into the
Automatic Voltage Regulator voltage reference, with the Onshore Generating Unit
operating at points specified by The Company (up to rated MVA output). The
damping shall be judged to be adequate if the corresponding Active Power response to the
disturbances decays within two cycles of oscillation.
CC.A.6.2.6.3 A facility to inject a band limited random noise signal into the Automatic Voltage Regulator
voltage reference shall be provided for demonstrating the frequency domain response of the
Power System Stabiliser. The tuning of the Power System Stabiliser shall be judged to be
adequate if the corresponding Active Power response shows improved damping with the
Power System Stabiliser in combination with the Automatic Voltage Regulator compared
with the Automatic Voltage Regulator alone over the frequency range 0.3Hz – 2Hz.
CC.A.6.2.7 Under-Excitation Limiters
CC.A.6.2.7.1 The security of the power system shall also be safeguarded by means of MVAr Under
Excitation Limiters fitted to the generator Excitation System. The Under Excitation
Limiter shall prevent the Automatic Voltage Regulator reducing the generator excitation to
a level which would endanger synchronous stability. The Under Excitation Limiter shall
operate when the excitation system is providing automatic control. The Under Excitation
Limiter shall respond to changes in the Active Power (MW) and the Reactive Power
(MVAr), and to the square of the generator voltage in such a direction that an increase in
voltage will permit an increase in leading MVAr. The characteristic of the Under Excitation
Limiter shall be substantially linear from no-load to the maximum Active Power output of
the Onshore Generating Unit at any setting and shall be readily adjustable.
CC.A.6.2.8.3 The GB Generator shall also make provision to prevent any over-excitation restriction of the
generator when the Excitation System is under manual control, other than that necessary
to ensure the Onshore Generating Unit is operating within its design limits.
CC.A.7.1 Scope
CC.A.7.1.1 This Appendix sets out the performance requirements of continuously acting automatic
voltage control systems for Onshore Non-Synchronous Generating Units, Onshore DC
Converters, Onshore Power Park Modules and OTSDUW Plant and Apparatus at the
Interface Point that must be complied with by the GB Code User. This Appendix does not
limit any site specific requirements that may be included in a Bilateral Agreement where in
The Company's reasonable opinion these facilities are necessary for system reasons.
CC.A.7.1.2 Proposals by GB Generators to make a change to the voltage control systems are required
to be notified to The Company under the Planning Code (PC.A.1.2(b) and (c)) as soon as
the GB Generator anticipates making the change. The change may require a revision to the
Bilateral Agreement.
CC.A.7.2 Requirements
CC.A.7.2.1 The Company requires that the continuously acting automatic voltage control system for the
Onshore Non-Synchronous Generating Unit, Onshore DC Converter or Onshore Power
Park Module or OTSDUW Plant and Apparatus shall meet the following functional
performance specification. If a Network Operator has confirmed to The Company that its
network to which an Embedded Onshore Non-Synchronous Generating Unit, Onshore
DC Converter, Onshore Power Park Module or OTSDUW Plant and Apparatus is
connected is restricted such that the full reactive range under the steady state voltage
control requirements (CC.A.7.2.2) cannot be utilised, The Company may specify in the
Bilateral Agreement alternative limits to the steady state voltage control range that reflect
these restrictions. Where the Network Operator subsequently notifies The Company that
such restriction has been removed, The Company may propose a Modification to the
Bilateral Agreement (in accordance with the CUSC contract) to remove the alternative
limits such that the continuously acting automatic voltage control system meets the following
functional performance specification. All other requirements of the voltage control system will
remain as in this Appendix.
CC.A.7.2.2 Steady State Voltage Control
CC.A.7.2.2.1 The Onshore Non-Synchronous Generating Unit, Onshore DC Converter, Onshore
Power Park Module or OTSDUW Plant and Apparatus shall provide continuous steady
state control of the voltage at the Onshore Grid Entry Point (or Onshore User System
Entry Point if Embedded) (or the Interface Point in the case of OTSDUW Plant and
Apparatus) with a Setpoint Voltage and Slope characteristic as illustrated in Figure
CC.A.7.2.2a. It should be noted that where the Reactive Power capability requirement of a
directly connected Onshore Non-Synchronous Generating Unit, Onshore DC Converter,
Onshore Power Park Module in Scotland, or OTSDUW Plant and Apparatus in Scotland
as specified in CC.6.3.2 (c), is not at the Onshore Grid Entry Point or Interface Point, the
values of Qmin and Qmax shown in this figure will be as modified by the 33/132kV or
33/275kV or 33/400kV transformer.
CC.A.7.2.2.2 The continuously acting automatic control system shall be capable of operating to a
Setpoint Voltage between 95% and 105% with a resolution of 0.25% of the nominal voltage.
For the avoidance of doubt values of 95%, 95.25%, 95.5% … may be specified, but not
intermediate values. The initial Setpoint Voltage will be 100%. The tolerance within which
this Setpoint Voltage shall be achieved is specified in BC2.A.2.6. For the avoidance of
doubt, with a tolerance of 0.25% and a Setpoint Voltage of 100%, the achieved value shall
be between 99.75% and 100.25%. The Company may request the GB Generator to
implement an alternative Setpoint Voltage within the range of 95% to 105%. For
Embedded GB Generators the Setpoint Voltage will be discussed between The Company
and the relevant Network Operator and will be specified to ensure consistency with
CC.6.3.4.
CC.A.7.2.2.3 The Slope characteristic of the continuously acting automatic control system shall be
adjustable over the range 2% to 7% (with a resolution of 0.5%). For the avoidance of doubt
values of 2%, 2.5%, 3% may be specified, but not intermediate values. The initial Slope
setting will be 4%. The tolerance within which this Slope shall be achieved is specified in
BC2.A.2.6. For the avoidance of doubt, with a tolerance of 0.5% and a Slope setting of 4%,
the achieved value shall be between 3.5% and 4.5%. The Company may request the GB
Generator to implement an alternative slope setting within the range of 2% to 7%. For
Embedded GB Generators the Slope setting will be discussed between The Company and
the relevant Network Operator and will be specified to ensure consistency with CC.6.3.4.
Figure CC.A.7.2.2c
(iii) the magnitude of the Reactive Power output response produced within 1 second shall
vary linearly in proportion to the magnitude of the step change.
(iv) within 2 seconds from achieving 90% of the response as defined in CC.A.7.2.3.1 (ii), the
peak to peak magnitude of any oscillations shall be less than 5% of the change in
steady state Reactive Power.
(v) following the transient response, the conditions of CC.A.7.2.2 apply.
MVArs
Required response at 1
second
0.2 1 Seconds
Figure CC.A.7.2.3.1a
(a) changing its Reactive Power output from its maximum lagging value to its maximum
leading value, or vice versa, then reverting back to the initial level of Reactive Power
output once every 15 seconds for at least 5 times within any 5 minute period; and
(b) changing its Reactive Power output from zero to its maximum leading value then
reverting back to zero Reactive Power output at least 25 times within any 24 hour
period and from zero to its maximum lagging value then reverting back to zero
Reactive Power output at least 25 times within any 24 hour period. Any subsequent
restriction on reactive capability shall be notified to The Company in accordance with
BC2.5.3.2, and BC2.6.1.
In all cases, the response shall be in accordance to CC.A.7.2.3.1 where the change in
Reactive Power output is in response to an on-load step change in Onshore Grid Entry
Point or Onshore User System Entry Point voltage, or in the case of OTSDUW Plant and
Apparatus an on-load step change in Transmission Interface Point voltage.
CONTENTS
(This contents page does not form part of the Grid Code)
(b) the minimum technical, design and operational criteria with which The Company will
comply in relation to the part of the National Electricity Transmission System at the
Connection Site with Users. In the case of any OTSDUW Plant and Apparatus, the
ECC also specify the minimum technical, design and operational criteria which must be
complied with by the User when undertaking OTSDUW.
(c ) The requirements of European Regulation (EU) 2016/631 shall not apply to
(i) Power Generating Modules that are installed to provide backup power and
operate in parallel with the Total System for less than 5 minutes per calendar
month while the System is in normal state. Parallel operation during
maintenance or commissioning of tests of that Power Generating Module shall
not count towards that five minute limit.
(ii) Power Generating Modules connected to the Transmission System or
Network Operators System which are not operated in synchronism with a
Synchronous Area.
(iii) Power Generating Modules that do not have a permanent Connection Point
or User System Entry Point and used by The Company to temporarily provide
power when normal System capacity is partly or completely unavailable.
ECC.2 OBJECTIVE
ECC.2.1 The objective of the ECC is to ensure that by specifying minimum technical, design and
operational criteria the basic rules for connection to the National Electricity Transmission
System and (for certain Users) to a User's System are similar for all Users of an equivalent
category and will enable The Company to comply with its statutory and Transmission
Licence obligations and European Regulations.
ECC.2.2 In the case of any OTSDUW the objective of the ECC is to ensure that by specifying the
minimum technical, design and operational criteria the basic rules relating to an Offshore
Transmission System designed and constructed by an Offshore Transmission Licensee
and designed and/or constructed by a User under the OTSDUW Arrangements are
equivalent.
ECC.3 SCOPE
ECC.3.1 The ECC applies to The Company and to Users, which in the ECC means:
(a) EU Generators (other than those which only have Embedded Small Power Stations),
including those undertaking OTSDUW including Power Generating Modules, and DC
Connected Power Park Modules.
(b) Network Operators but only in respect of:-
(i) Network Operators who are EU Code Users
(ii) Network Operators who only have EU Grid Supply Points
(iii) Embedded Medium Power Stations not subject to a Bilateral Agreement as
provided for in ECC.3.2, ECC.3.3, EC3.4, EC3.5, ECC5.1, ECC.6.4.4 and
ECA.3.4;
(iv) Notwithstanding the requirements of ECC3.1(b)(i)(ii) and (iii) , Network
Operators who own and/or operate EU Grid Supply Points, are only required
to satisfy the requirements of this ECC in relation to each EU Grid Supply Point.
Network Operators in respect of all other Grid Supply Points should continue
to satisfy the requirements as specified in the CCs.
(c) Non-Embedded Customers who are also EU Code Users ;
(d) HVDC System Owners who are also EU Code Users; and
(e) BM Participants and Externally Interconnected System Operators who are also EU
Code Users in respect of ECC.6.5 only.
ECC.3.2 The above categories of User will become bound by the applicable sections of the ECC prior
to them generating, distributing, supplying or consuming, as the case may be, and references
to the various categories should, therefore, be taken as referring to them in that prospective
role.
ECC.3.3 Embedded Medium Power Stations not subject to a Bilateral Agreement and Embedded
HVDC Systems not subject to a Bilateral Agreement Provisions.
The following provisions apply in respect of Embedded Medium Power Stations not subject
to a Bilateral Agreement and Embedded HVDC Systems not subject to a Bilateral
Agreement.
that would otherwise have been specified in a Bilateral Agreement will be notified to the
relevant Network Operator in writing in accordance with the provisions of the CUSC and the
Network Operator must ensure such requirements are performed and discharged by the
Generator or the HVDC System owner.
ECC.4 PROCEDURE
ECC.4.1 The CUSC contains certain provisions relating to the procedure for connection to the National
Electricity Transmission System or, in the case of Embedded Power Stations or
Embedded HVDC Systems, becoming operational and includes provisions relating to certain
conditions to be complied with by EU Code Users prior to and during the course of The
Company notifying the User that it has the right to become operational. The procedure for an
EU Code User to become connected is set out in the Compliance Processes.
ECC.5 CONNECTION
ECC.5.1 The provisions relating to connecting to the National Electricity Transmission System (or
to a User's System in the case of a connection of an Embedded Large Power Station or
Embedded Medium Power Stations or Embedded HVDC System) are contained in:
(a) the CUSC and/or CUSC Contract (or in the relevant application form or offer for a CUSC
Contract);
(b) or, in the case of an Embedded Development, the relevant Distribution Code and/or
the Embedded Development Agreement for the connection (or in the relevant
application form or offer for an Embedded Development Agreement),
and include provisions relating to both the submission of information and reports relating to
compliance with the relevant European Connection Conditions for that EU Code User,
Safety Rules, commissioning programmes, Operation Diagrams and approval to connect
(and their equivalents in the case of Embedded Medium Power Stations not subject to a
Bilateral Agreement or Embedded HVDC Systems not subject to a Bilateral Agreement).
References in the ECC to the "Bilateral Agreement” and/or “Construction Agreement"
and/or “Embedded Development Agreement” shall be deemed to include references to the
application form or offer therefor.
ECC.5.2 Items For Submission
ECC.5.2.1 Prior to the Completion Date (or, where the EU Generator is undertaking OTSDUW, any
later date specified) under the Bilateral Agreement and/or Construction Agreement, the
following is submitted pursuant to the terms of the Bilateral Agreement and/or Construction
Agreement:
(a) updated Planning Code data (both Standard Planning Data and Detailed Planning
Data), with any estimated values assumed for planning purposes confirmed or, where
practical, replaced by validated actual values and by updated estimates for the future and
by updated forecasts for Forecast Data items such as Demand, pursuant to the
requirements of the Planning Code;
ECC.6.1.2.1.3 For the avoidance of doubt, disconnection, by frequency or speed based relays is not
permitted within the frequency range 47.5Hz to 51.5Hz. EU Generators should however be
aware of the combined voltage and frequency operating ranges as defined in ECC.6.3.12 and
ECC.6.3.13.
ECC.6.1.2.1.4 The Company in co-ordination with the Relevant Transmission Licensee and/or Network
Operator and a User may agree on wider variations in frequency or longer minimum operating
times to those set out in ECC.6.1.2.1.2 or specific requirements for combined frequency and
voltage deviations. Any such requirements in relation to Power Generating Modules shall
be in accordance with ECC.6.3.12 and ECC.6.3.13. A User shall not unreasonably withhold
consent to apply wider frequency ranges or longer minimum times for operation taking account
of their economic and technical feasibility.
ECC.6.1.2.2 Grid Frequency variations for HVDC Systems and Remote End HVDC Converter Stations
ECC.6.1.2.2.1 HVDC Systems and Remote End HVDC Converter Stations shall be capable of staying
connected to the System and remaining operable within the frequency ranges and time
periods specified in Table ECC.6.1.2.2 below. This requirement shall continue to apply during
the Fault Ride Through conditions defined in ECC.6.3.15
Table ECC.6.1.2.2 – Minimum time periods HVDC Systems and Remote End HVDC Converter Stations
shall be able to operate for different frequencies deviating from a nominal value without
disconnecting from the National Electricity Transmission System
ECC.6.1.2.2.2 The Company in coordination with the Relevant Transmission Licensee and a HVDC
System Owner may agree wider frequency ranges or longer minimum operating times if
required to preserve or restore system security. If wider frequency ranges or longer minimum
times for operation are economically and technically feasible, the HVDC System Owner shall
not unreasonably withhold consent.
ECC.6.1.2.2.3 Not withstanding the requirements of ECC.6.1.2.2.1, an HVDC System or Remote End HVDC
Converter Station shall be capable of automatic disconnection at frequencies specified by
The Company and/or Relevant Network Operator.
ECC.6.1.2.2.4 In the case of Remote End HVDC Converter Stations where the Remote End HVDC
Converter Station is operating at either nominal frequency other than 50Hz or a variable
frequency, the requirements defined in ECC6.1.2.2.1 to ECC.6.1.2.2.3 shall apply to the
Remote End HVDC Converter Station other than in respect of the frequency ranges and
time periods.
ECC.6.1.2.3 Grid Frequency Variations for DC Connected Power Park Modules
Table ECC.6.1.2.3 – Minimum time periods a DC Connected Power Park Module shall be able to operate
for different frequencies deviating from a nominal value without disconnecting from the
System
ECC.6.1.2.3.2 The Company in coordination with the Relevant Transmission Licensee and a Generator
may agree wider frequency ranges or longer minimum operating times if required to preserve
or restore system security and to ensure the optimum capability of the DC Connected Power
Park Module. If wider frequency ranges or longer minimum times for operation are
economically and technically feasible, the EU Generator shall not unreasonably withhold
consent.
ECC.6.1.3 Not used
ECC.6.1.4 Grid Voltage Variations
ECC.6.1.4.1 Grid Voltage Variations for Users excluding DC Connected Power Park Modules and
Remote End HVDC Converters
Subject as provided below, the voltage on the 400kV part of the National Electricity
Transmission System at each Connection Site with a User (and in the case of OTSDUW
Plant and Apparatus, a Transmission Interface Point, excluding DC Connected Power
Park Modules and Remote End HVDC Converters) will normally remain within 5% of the
nominal value unless abnormal conditions prevail. The minimum voltage is -10% and the
maximum voltage is +10% unless abnormal conditions prevail, but voltages between +5% and
+10% will not last longer than 15 minutes unless abnormal conditions prevail. Voltages on the
275kV and 132kV parts of the National Electricity Transmission System at each
Connection Point (and in the case of OTSDUW Plant and Apparatus, a Transmission
Interface Point) will normally remain within the limits 10% of the nominal value unless
abnormal conditions prevail. At nominal System voltages below 110kV the voltage of the
National Electricity Transmission System at each Connection Site with a User (and in the
case of OTSDUW Plant and Apparatus, a Transmission Interface Point), excluding
Connection Sites for DC Connected Power Park Modules and Remote End HVDC
Converters) will normally remain within the limits 6% of the nominal value unless abnormal
conditions prevail. Under fault conditions, the voltage may collapse transiently to zero at the
point of fault until the fault is cleared. The normal operating ranges of the National Electricity
Transmission System are summarised below:
National Electricity Normal Operating Range Time period for Operation
Transmission System
Nominal Voltage
The Company and a User may agree greater variations or longer minimum time periods of
operation in voltage to those set out above in relation to a particular Connection Site, and
insofar as a greater variation is agreed, the relevant figure set out above shall, in relation to
that User at the particular Connection Site, be replaced by the figure agreed.
ECC.6.1.4.2 Grid Voltage Variations for all DC Connected Power Park Modules
ECC.6.1.4.2.1 All DC Connected Power Park Modules shall be capable of staying connected to the Remote
End HVDC Converter Station at the HVDC Interface Point and operating within the voltage
ranges and time periods specified in Tables ECC.6.1.4.2(a) and ECC.6.1.4.2(b) below. The
applicable voltage range and time periods specified are selected based on the reference 1pu
voltage.
Table ECC.6.1.4.2(a) – Minimum time periods for which DC Connected Power Park Modules shall be
capable of operating for different voltages deviating from reference 1pu without
disconnecting from the network where the nominal voltage base is 110kV or above and less
than 300kV.
Voltage Range (pu) Time Period for Operation (s)
0.85pu – 0.9pu 60 minutes
0.9pu – 1.05pu Unlimited
1.05pu – 1.15pu 15 minutes
Table ECC.6.1.4.2(b) – Minimum time periods for which DC Connected Power Park Modules shall be
capable of operating for different voltages deviating from reference 1pu without
disconnecting from the network where the nominal voltage base is from 300kV up to and
including 400kV.
ECC.6.1.4.2.2 The Company and a EU Generator in respect of a DC Connected Power Park Module may
agree greater voltage ranges or longer minimum operating times. If greater voltage ranges
or longer minimum times for operation are economically and technically feasible, the EU
Generator shall not unreasonably withhold any agreement .
ECC.6.1.4.2.3 For DC Connected Power Park Modules which have an HVDC Interface Point to the
Remote End HVDC Converter Station, The Company in coordination with the Relevant
Transmission Licensee may specify voltage limits at the HVDC Interface Point at which the
DC Connected Power Park Module is capable of automatic disconnection.
Table ECC.6.1.4.3(a) – Minimum time periods for which a Remote End HVDC Converter shall be capable
of operating for different voltages deviating from reference 1pu without disconnecting from
the network where the nominal voltage base is 110kV or above and less than 300kV.
Voltage Range (pu) Time Period for Operation (s)
0.85pu – 0.9pu 60 minutes
0.9pu – 1.05pu Unlimited
1.05pu – 1.15pu 15 minutes
Table ECC.6.1.4.3(b) – Minimum time periods for which a Remote End HVDC Converter shall be capable
of operating for different voltages deviating from reference 1pu without disconnecting from
the network where the nominal voltage base is from 300kV up to and including 400kV.
ECC.6.1.4.3.2 The Company and a HVDC System Owner may agree greater voltage ranges or longer
minimum operating times which shall be in accordance with the requirements of ECC.6.1.4.2.
ECC.6.1.4.3.4 For HVDC Interface Points which fall outside the scope of ECC.6.1.4.3.1 The Company in
coordination with the Relevant Transmission Licensee shall specify any applicable
requirements at the Grid Entry Point or User System Entry Point.
ECC.6.1.4.3.5 Where the nominal frequency of the AC collector System which is connected to an HVDC
Interface Point is at a value other than 50Hz, the voltage ranges and time periods specified
by The Company in coordination with the Relevant Transmission Licensee shall be
proportional to the values specified in Table ECC.6.1.4.3(a) and Table ECC.6.1.4.3(b)
Voltage Waveform Quality
ECC.6.1.5 All Plant and Apparatus connected to the National Electricity Transmission System, and
that part of the National Electricity Transmission System at each Connection Site or, in
the case of OTSDUW Plant and Apparatus, at each Interface Point, should be capable of
withstanding the following distortions of the voltage waveform in respect of harmonic content
and phase unbalance:
(a) Harmonic Content
Voltage Fluctuations
ECC.6.1.7 Voltage changes at a Point of Common Coupling on the Onshore Transmission System
shall not exceed:
(a) The limits specified in Table ECC.6.1.7(a) with the stated frequency of occurrence, where:
(i)
Vsteadystate
%Vsteadystate = │100 x │ and
Vn
Vmax
%Vmax =100 x ;
Vn
(ii) Vn is the nominal system voltage;
(iii) Vsteadystate is the voltage at the end of a period of 1 s during which the rate of change
of system voltage over time is ≤ 0.5%;
(iv) Vsteadystate is the difference in voltage between the initial steady state voltage prior
to the RVC (V0) and the final steady state voltage after the RVC (V0’);
NOTE 1: 6% is permissible for 100 ms reduced to 3% thereafter as per Figure ECC.6.1.7 (1) .
If the profile of repetitive voltage change(s) falls within the envelope given in Figure ECC.6.1.7 (1) , the
assessment of such voltage change(s) shall be undertaken according to the recommendations for
assessment of flicker and shall conform to the planning levels provided for flicker.
If any part of the voltage change(s) falls outside the envelope given in Figure ECC.6.1.7(1), the
assessment of such voltage changes, repetitive or not, shall be done according to the guidance and limits
for RVCs.
NOTE 2: No more than 1 event is permitted per day, consisting of up to 4 RVCs, each separated by at least 10
minutes with all switching completed within a two-hour window.
NOTE 3: −10% is permissible for 100 ms reduced to -6% until 2 s then reduced to -3% thereafter as per Figure
ECC.6.1.7 (2).
NOTE 4: +6% is permissible for 0.8 s from the instant the event begins then reduced to +3% thereafter as per Figure
ECC.6.1.7 (2).
NOTE 5: −12% is permissible for 100 ms reduced to −10% until 2 s then reduced to -3% thereafter as per Figure
ECC.6.1.7 (3).
(b) The voltage change limit is the absolute maximum allowed of either the phase-to-earth
voltage change or the phase-to-phase voltage change, whichever is the highest. The limits
do not apply to single phasor equivalent voltages, e.g. positive phase sequence (PPS)
voltages. For high impedance earthed systems, the maximum phase-to-phase, i.e. line
voltage, should be used for assessment.
(c) The RVCs in Category 2 and 3 should not exceed the limits depicted in the time dependent
characteristic shown in Figure ECC.6.1.7 (2) and Figure ECC.6.1.7 (3) respectively.
These limits do not apply to: 1) fault clearance operations; or 2) immediate operations in
response to fault conditions; or 3) operations relating to post fault system restoration (for
the avoidance of doubt this third exception pertains to a fault that is external to the Users
plant and apparatus).
(d) Any RVCs permitted in Category 2 and Category 3 should be at least 10 minutes apart.
(e) The value of Vsteadystate should be established immediately prior to the start of a RVC.
Following a RVC, the voltage should remain within the relevant envelope, as shown in
Figures ECC.6.1.7 (1), ECC.6.1.7 (2), ECC.6.1.7 (3), until a Vsteadystate condition has been
satisfied.
V0+6%
V0+3%
V0
V0−3%
V0−6%
V0−10%
V0+6%
V0+3%
V0
V0−3%
V0−10%
V0−12%
NOTE 1: The magnitude of Pst is linear with respect to the magnitude of the voltage changes giving rise to it.
NOTE 2: Extreme caution is advised in allowing any excursions of P st and Plt above the planning level.
The values and figures referred to in this paragraph ECC.6.1.7 are derived from Engineering
Recommendation P28 Issue 2.
ECC.6.1.8 Voltage fluctuations at a Point of Common Coupling with a fluctuating Load directly
connected to an Offshore Transmission System (or in the case of OTSDUW, OTSDUW
Plant and Apparatus) shall not exceed the limits set out in the Bilateral Agreement.
A Power Generating Module (other than a Power Park Unit), HVDC Equipment or
OTSDUW Plant and Apparatus) with Back-Up Protection or Independent Back-Up
Protection will also be required to withstand, without tripping, the loading incurred during
the clearance of a fault on the National Electricity Transmission System by breaker
fail Protection at 400kV or 275kV or of a fault cleared by Back-Up Protection where the
EU Generator (including in the case of OTSDUW Plant and Apparatus or DC
Connected Power Park Module) or HVDC System is connected at 132kV and below.
This will permit Discrimination between the Generator in respect of OTSDUW Plant
and Apparatus or DC Connected Power Park Modules or HVDC System Owners’
Back-Up Protection or Independent Back-Up Protection and the Back-Up Protection
provided on the National Electricity Transmission System and other Users' Systems.
(c) When the Power Generating Module (other than Power Park Units), or the HVDC
Equipment or OTSDUW Plant and Apparatus is connected to the National Electricity
Transmission System at 400kV or 275kV, and in Scotland and Offshore also at 132kV,
and a circuit breaker is provided by the Generator (including in respect of OTSDUW
Plant and Apparatus or DC Connected Power Park Modules) or the HVDC System
owner, or the Relevant Transmission Licensee, as the case may be, to interrupt fault
current interchange with the National Electricity Transmission System, or Generator's
System, or HVDC System Owner’s System, as the case may be, circuit breaker fail
Protection shall be provided by the Generator (including in respect of OTSDUW Plant
and Apparatus or DC Connected Power Park Modules) or HVDC System Owner, or
the Relevant Transmission Licensee, as the case may be, on this circuit breaker. In
the event, following operation of a Protection system, of a failure to interrupt fault current
by these circuit-breakers within the Fault Current Interruption Time, the circuit breaker
fail Protection is required to initiate tripping of all the necessary electrically adjacent
circuit-breakers so as to interrupt the fault current within the next 200ms.
(d) The target performance for the System Fault Dependability Index shall be not less than
99%. This is a measure of the ability of Protection to initiate successful tripping of circuit
breakers which are associated with the faulty item of Apparatus.
ECC.6.2.2.3 Equipment including Protection equipment to be provided
The Relevant Transmission Licensee shall specify the Protection schemes and settings
necessary to protect the National Electricity Transmission System, taking into account the
characteristics of the Power Generating Module or HVDC Equipment.
ECC.6.2.2.6.2 The parameters of different control modes of the HVDC System shall be able to be changed
in the HVDC Converter Station, if required by The Company in coordination with the
Relevant Transmission Licensee and in accordance with ECC.6.2.2.6.4.
ECC.6.2.2.6.3 Any change to the schemes or settings of parameters of the different control modes and
protection of the HVDC System including the procedure shall be agreed with The Company
in coordination with the Relevant Transmission Licensee and the HVDC System Owner.
ECC.6.2.2.6.4 The control modes and associated set points shall be capable of being changed remotely, as
specified by The Company in coordination with the Relevant Transmission Licensee.
ECC.6.2.2.7 Control Schemes and Settings
ECC.6.2.2.7.1 The schemes and settings of the different control devices on the Power Generating Module
and HVDC Equipment that are necessary for Transmission System stability and for taking
emergency action shall be agreed with The Company in coordination with the Relevant
Transmission Licensee and the EU Generator or HVDC System Owner.
ECC.6.2.2.7.2 Subject to the requirements of ECC.6.2.2.7.1 any changes to the schemes and settings,
defined in ECC.6.2.2.7.1, of the different control devices of the Power Generating Module or
HVDC Equipment shall be coordinated and agreed between , the Relevant Transmission
Licensee, the EU Generator and HVDC System Owner.
ECC.6.2.2.8 Ranking of Protection and Control
ECC.6.2.2.8.1 The Company in coordination with Relevant Transmission Licensees, shall agree and
coordinate the protection and control devices of EU Generators Plant and Apparatus in
accordance with the following general priority ranking (from highest to lowest):
(i) The interface between the National Electricity Transmission System and
the Power Generating Module or HVDC Equipment Protection equipment;
(ii) frequency control (active power adjustment);
(iii) power restriction; and
(iv) power gradient constraint;
ECC.6.2.2.9 Synchronising
ECC.6.2.2.9.1 For any Power Generating Module directly connected to the National Electricity
Transmission System or Type D Power Generating Module, synchronisation shall be
performed by the EU Generator only after instruction by The Company in accordance with
the requirements of BC.2.5.2.
ECC.6.2.2.9.2 Each Power Generating Module directly connected to the National Electricity
Transmission System or Type D Power Generating Module shall be equipped with the
necessary synchronisation facilities. Synchronisation shall be possible within the range of
frequencies specified in ECC.6.1.2.
ECC.6.2.2.9.3 The requirements for synchronising equipment shall be specified in accordance with the
requirements in the Electrical Standards listed in the annex to the General Conditions. The
synchronisation settings shall include the following elements below. Any variation to these
requirements shall be pursuant to the terms of the Bilateral Agreement.
(a) voltage
(b) Frequency
(c) phase angle range
(d) phase sequence
(e) deviation of voltage and Frequency
ECC.6.2.2.9.4 HVDC Equipment shall be required to satisfy the requirements of ECC.6.2.2.9.1 –
ECC.6.2.2.9.3. In addition, unless otherwise specified by The Company, during the
synchronisation of a DC Connected Power Park Module to the National Electricity
Transmission System, any HVDC Equipment shall have the capability to limit any steady
state voltage changes to the limits specified within ECC.6.1.7 or ECC.6.1.8 (as applicable)
which shall not exceed 5% of the pre-synchronisation voltage. The Company in coordination
with the Relevant Transmission Licensee shall specify any additional requirements for the
maximum magnitude, duration and measurement of the voltage transients over and above
those defined in ECC.6.1.7 and ECC.6.1.8 in the Bilateral Agreement.
ECC.6.2.2.9.5 EU Generators in respect of DC Connected Power Park Modules shall also provide output
synchronisation signals specified by The Company in co-ordination with the Relevant
Transmission Licensee.
No Network Operator or Non Embedded Customer equipment shall be energised until the
Protection settings have been agreed prior to commissioning. The Network Operator or Non
Embedded Customer shall agree with The Company (in coordination with the Relevant
Transmission Licensee) and carry out a combined commissioning programme for the
Protection systems, and generally, to a minimum standard as specified in the Bilateral
Agreement.
ECC.6.2.3.8 Control Requirements
ECC.6.2.3.8.1 The Company in coordination with the Relevant Transmission Licensee and the Network
Operator or Non Embedded Customer shall agree on the control schemes and settings at
each EU Grid Supply Point of the different control devices of the Network Operator’s or Non
Embedded Customer’s System relevant for security of the National Electricity
Transmission System. Such requirements would be pursuant to the terms of the Bilateral
Agreement which shall also cover at least the following elements:
(a) Isolated (National Electricity Transmission System) operation;
(b) Damping of oscillations;
(c) Disturbances to the National Electricity Transmission System;
(d) Automatic switching to emergency supply and restoration to normal topology;
(e) Automatic circuit breaker re-closure (on 1-phase faults).
ECC.6.2.3.8.2 Subject to the requirements of ECC.6.2.3.8.1 any changes to the schemes and settings,
defined in ECC.6.2.3.8.1 of the different control devices of the Network Operator’s or Non-
Embedded Customer’s System at the EU Grid Supply Point shall be coordinated and
agreed between The Company, the Relevant Transmission Licensee, the Network
Operator or Non Embedded Customer.
ECC.6.2.3.9 Ranking of Protection and Control
ECC.6.2.3.9.1 The Network Operator or the Non Embedded Customer who owns or operates an EU Grid
Supply Point shall set the Protection and control devices of its System, in compliance with
the following priority ranking, organised in decreasing order of importance:
(a) National Electricity Transmission System Protection;
(b) Protection equipment at each EU Grid Supply Point;
(c) Frequency control (Active Power adjustment);
(d) Power restriction.
ECC.6.2.3.10 Synchronising
ECC.6.2.3.10.1 Each Network Operator or Non Embedded Customer at each EU Grid Supply Point shall
be capable of synchronisation within the range of frequencies specified in ECC.6.1.2 unless
otherwise agreed with The Company.
ECC.6.2.3.10.2 The Company and the Network Operator or Non Embedded Customer shall agree on the
settings of the synchronisation equipment at each EU Grid Supply Point prior to the
Completion Date. The Company and the relevant Network Operator or Non-Embedded
Customer shall agree the synchronisation settings which shall include the following elements.
(a) Voltage;
(b) Frequency;
(c) phase angle range;
(d) deviation of voltage and Frequency.
Issue 5 Revision 38 ECC 04 September 2019
28 of 137
ECC.6.3 GENERAL POWER GENERATING MODULE, OTSDUW AND HVDC EQUIPMENT
REQUIREMENTS
ECC.6.3.1 This section sets out the technical and design criteria and performance requirements for
Power Generating Modules and HVDC Equipment (whether directly connected to the
National Electricity Transmission System or Embedded) and (where provided in this
section) OTSDUW Plant and Apparatus which each Generator or HVDC System Owner
must ensure are complied with in relation to its Power Generating Modules, HVDC
Equipment and OTSDUW Plant and Apparatus . References to Power Generating
Modules, HVDC Equipment in this ECC.6.3 should be read accordingly.
Plant Performance Requirements
ECC.6.3.2 REACTIVE CAPABILITY
ECC.6.3.2.1 Reactive Capability for Type B Synchronous Power Generating Modules
ECC.6.3.2.1.1 When operating at Maximum Capacity, all Type B Synchronous Power Generating
Modules must be capable of continuous operation at any points between the limits of 0.95
Power Factor lagging and 0.95 Power Factor leading at the Grid Entry Point or User
System Entry Point unless otherwise agreed with The Company or relevant Network
Operator. At Active Power output levels other than Maximum Capacity, all Generating
Units within a Type B Synchronous Power Generating Module must be capable of
continuous operation at any point between the Reactive Power capability limits identified
on the HV Generator Performance Chart unless otherwise agreed with The Company or
relevant Network Operator.
ECC.6.3.2.2 Reactive Capability for Type B Power Park Modules
ECC.6.3.2.2.1 When operating at Maximum Capacity all Type B Power Park Modules must be capable
of continuous operation at any points between the limits of 0.95 Power Factor lagging and
0.95 Power Factor leading at the Grid Entry Point or User System Entry Point unless
otherwise agreed with The Company or relevant Network Operator. At Active Power
output levels other than Maximum Capacity, each Power Park Module must be capable
of continuous operation at any point between the Reactive Power capability limits
identified on the HV Generator Performance Chart unless otherwise agreed with The
Company or Network Operator.
ECC.6.3.2.3 Reactive Capability for Type C and D Synchronous Power Generating Modules
ECC.6.3.2.3.1 In addition to meeting the requirements of ECC.6.3.2.3.2 – ECC.6.3.2.3.5, EU Generators
which connect a Type C or Type D Synchronous Power Generating Module(s) to a Non
Embedded Customers System or private network, may be required to meet additional
reactive compensation requirements at the point of connection between the System and
the Non Embedded Customer or private network where this is required for System
reasons.
ECC.6.3.2.3.2 All Type C and Type D Synchronous Power Generating Modules shall be capable of
satisfying the Reactive Power capability requirements at the Grid Entry Point or User
System Entry Point as defined in Figure ECC.6.3.2.3 when operating at Maximum
Capacity.
ECC.6.3.2.3.3 At Active Power output levels other than Maximum Capacity, all Generating Units within
a Synchronous Power Generating Module must be capable of continuous operation at
any point between the Reactive Power capability limit identified on the HV Generator
Performance Chart at least down to the Minimum Stable Operating Level. At reduced
Active Power output, Reactive Power supplied at the Grid Entry Point (or User System
Entry Point if Embedded) shall correspond to the HV Generator Performance Chart of
the Synchronous Power Generating Module, taking the auxiliary supplies and the Active
Power and Reactive Power losses of the Generating Unit transformer or Station
Transformer into account.
Figure ECC.6.3.2.4(a)
Figure ECC.6.3.2.4(c)
ECC.6.3.2.5 Reactive Capability for Offshore Synchronous Power Generating Modules,
Configuration 1 AC connected Offshore Power Park Modules and Configuration 1 DC
Connected Power Park Modules.
ECC.6.3.2.5.1 The short circuit ratio of any Offshore Synchronous Generating Units within a
Synchronous Power Generating Module shall not be less than 0.5. All Offshore
Synchronous Generating Units, Configuration 1 AC connected Offshore Power Park
Modules or Configuration 1 DC Connected Power Park Modules must be capable of
maintaining zero transfer of Reactive Power at the Offshore Grid Entry Point. The steady
state tolerance on Reactive Power transfer to and from an Offshore Transmission
System expressed in MVAr shall be no greater than 5% of the Maximum Capacity.
ECC.6.3.2.5.2 For the avoidance of doubt if an EU Generator (including those in respect of DC
Connected Power Park Modules) wishes to provide a Reactive Power capability in
excess of the minimum requirements defined in ECC.6.3.2.5.1 then such capability
(including steady state tolerance) shall be agreed between the Generator, Offshore
Transmission Licensee and The Company and/or the relevant Network Operator.
Figure ECC.6.3.2.6(a)
ECC.6.3.2.6.2 All AC Connected Configuration 2 Offshore Power Park Modules and Configuration
2 DC Connected Power Park Modules shall be capable of satisfying the Reactive Power
capability requirements at the Offshore Grid Entry Point as defined in Figure
ECC.6.3.2.6(b) when operating below Maximum Capacity. With all Plant in service, the
Reactive Power limits will reduce linearly below 50% Active Power output as shown in
Figure ECC.6.3.2.6(b) unless the requirement to maintain the Reactive Power limits
defined at Maximum Capacity (or Interface Point Capacity in the case of OTSDUW Plant
and Apparatus) under absorbing Reactive Power conditions down to 20% Active Power
output has been specified with The Company. These Reactive Power limits will be
reduced pro rata to the amount of Plant in service. The Company in co-ordination with the
Relevant Transmission Licensee may agree to alternative reactive capability
requirements to those specified in Figure ECC.6.3.2.6(b), where it is demonstrated that it
is uneconomic and inefficient to do so, for example in the case of new technologies or
advanced control strategies.
(c) For the avoidance of doubt, in the case of a Power Generating Module including a DC
Connected Power Park Module using an Intermittent Power Source where the
mechanical power input will not be constant over time, the requirement is that the Active
Power output shall be independent of System Frequency under (a) above and should
not drop with System Frequency by greater than the amount specified in (b) above.
100% of Active
Power Input
40% of Active
Power Input
Figure ECC.6.3.3(b)
(e) In the case of an Offshore Generating Unit or Offshore Power Park Module or DC
Connected Power Park Module or Remote End HVDC Converter or Transmission
DC Converter, the EU Generator shall comply with the requirements of ECC.6.3.3. EU
Generators should be aware that Section K of the STC places requirements on Offshore
Transmission Licensees which utilise a Transmission DC Converter as part of their
Offshore Transmission System to make appropriate provisions to enable EU
Generators to fulfil their obligations.
(f) Transmission DC Converters and Remote End HVDC Converters shall provide a
continuous signal indicating the real time frequency measured at the Interface Point to
the Offshore Grid Entry Point or HVDC Interface Point for the purpose of Offshore
Generators or DC Connected Power Park Modules to respond to changes in System
Frequency on the Main Interconnected Transmission System. A DC Connected
Power Park Module or Offshore Power Generating Module shall be capable of
receiving and processing this signal within 100ms.
ECC.6.3.4 ACTIVE POWER OUTPUT UNDER SYSTEM VOLTAGE VARIATIONS
ECC.6.3.4.1 At the Grid Entry Point or User System Entry Point , the Active Power output under steady
state conditions of any Power Generating Module or HVDC Equipment directly connected
to the National Electricity Transmission System or in the case of OTSDUW, the Active
Power transfer at the Interface Point, under steady state conditions of any OTSDUW Plant
and Apparatus should not be affected by voltage changes in the normal operating range
specified in paragraph ECC.6.1.4 by more than the change in Active Power losses at reduced
or increased voltage.
ECC.6.3.5 BLACK START
ECC.6.3.5.1 Black Start is not a mandatory requirement, however EU Code Users may wish to notify The
Company of their ability to provide a Black Start facility and the cost of the service. The
Company will then consider whether it wishes to contract with the EU Code User for the
provision of a Black Start service which would be specified via a Black Start Contract. Where
an EU Code User does not offer to provide a cost for the provision of a Black Start Capability,
The Company may make such a request if it considers System security to be at risk due to a
lack of Black Start capability.
Issue 5 Revision 38 ECC 04 September 2019
36 of 137
ECC.6.3.5.2 It is an essential requirement that the National Electricity Transmission System must
incorporate a Black Start Capability. This will be achieved by agreeing a Black Start
Capability at a number of strategically located Power Stations and HVDC Systems. For
each Power Station or HVDC System, The Company will state in the Bilateral Agreement
whether or not a Black Start Capability is required.
ECC.6.3.5.3 Where an EU Code User has entered into a Black Start Contract to provide a Black Start
Capability in respect of a Type C Power Generating Module or Type D Power Generating
Module (including DC Connected Power Park Modules) the following requirements shall
apply.
(i) The Power-Generating Module or DC Connected Power Park Module shall be
capable of starting from shutdown without any external electrical energy supply within
a time frame specified by The Company in the Black Start Contract.
(ii) Each Power Generating Module or DC Connected Power Park Module shall be
able to synchronise within the frequency limits defined in ECC.6.1. and, where
applicable, voltage limits specified in ECC.6.1.4;
(iii) The Power Generating Module or DC Connected Power Park Module shall be
capable of connecting on to an unenergised System.
(iv) The Power-Generating Module or DC Connected Power Park Module shall be
capable of automatically regulating dips in voltage caused by connection of demand;
(v) The Power Generating Module or DC Connected Power Park Module shall:
be capable of Block Load Capability,
be capable of operating in LFSM-O and LFSM-U, as specified in ECC.6.3.7.1 and
ECC.6.3.7.2
control Frequency in case of overfrequency and underfrequency within the whole
Active Power output range between the Minimum Regulating Level and
Maximum Capacity as well as at houseload operation levels
be capable of parallel operation of a few Power Generating Modules including
DC Connected Power Park Modules within an isolated part of the Total System
that is still supplying Customers, and control voltage automatically during the
system restoration phase;
ECC.6.3.5.4 Each HVDC System or Remote End HVDC Converter Station which has a Black Start
Capability shall be capable of energising the busbar of an AC substation to which another
HVDC Converter Station is connected. The timeframe after shutdown of the HVDC System
prior to energisation of the AC substation shall be pursuant to the terms of the Black Start
Contract. The HVDC System shall be able to synchronise within the Frequency limits defined
in ECC.6.1.2.1.2 and voltage limits defined in ECC.6.1.4.1 unless otherwise specified in the
Black Start Contract. Wider Frequency and voltage ranges can be specified in the Black
Start Contract in order to restore System security.
ECC.6.3.5.5 With regard to the capability to take part in operation of an isolated part of the Total System
that is still supplying Customers:
(i) Power Generating Modules including DC Connected Power Park Modules shall
be capable of taking part in island operation if specified in the Black Start Contract
required by The Company and:
the Frequency limits for island operation shall be those specified in ECC.6.1.2,
the voltage limits for island operation shall be those defined in ECC.6.1.4;
(iii) As much as possible of the proportional reduction in Active Power output must result
from the frequency control device (or speed governor) action and must be achieved
within 10 seconds of the time of the Frequency increase above 50.4 Hz. The Power
Generating Module (including DC Connected Power Park Modules) or HVDC
Systems shall be capable of initiating a power Frequency response with an initial delay
that is as short as possible. If the delay exceeds 2 seconds the EU Generator or HVDC
System Owner shall justify the variation, providing technical evidence to The
Company.
(iv) The residue of the proportional reduction in Active Power output which results from
automatic action of the Power Generating Module (including DC Connected Power
Park Modules) or HVDC System output control devices other than the frequency
control devices (or speed governors) must be achieved within 3 minutes for the time of
the Frequency increase above 50.4Hz.
(v) For the avoidance of doubt, the LFSM-O response must be reduced when the
Frequency falls again and, when to a value less than 50.4Hz, as much as possible of
the increase in Active Power must be achieved within 10 seconds.
(vi) For Type A and Type B Power Generating Modules which are not required to
have Frequency Sensitive Mode (FSM) as described in ECC.6.3.7.3 for
deviations in Frequency up to 50.9Hz at least half of the proportional reduction
in Active Power output must be achieved in 10 seconds of the time of the
Frequency increase above 50.4Hz. For deviations in Frequency beyond 50.9Hz
the measured rate of change of Active Power reduction must exceed 0.5%/sec
of the initial output. The LFSM-O response must be reduced when the
Frequency subsequently falls again and when to a value less than 50.4Hz, at
least half the increase in Active Power must be achieved in 10 seconds. For a
Frequency excursion returning from beyond 50.9Hz the measured rate of
change of Active Power increase must exceed 0.5%/second.
ECC.6.3.7.1.3 Each Power Generating Module (including DC Connected Power Park Modules) or HVDC
Systems which is providing Limited High Frequency Response (LFSM-O) must continue to
provide it until the Frequency has returned to or below 50.4Hz or until otherwise instructed by
The Company. EU Generators in respect of Gensets and HVDC Converter Station
Owners in respect of an HVDC System should also be aware of the requirements in
BC.3.7.2.2.
ECC.6.3.7.1.4 Steady state operation below the Minimum Stable Operating Level in the case of Power
Generating Modules including DC Connected Power Park Modules or Minimum Active
Power Transmission Capacity in the case of HVDC Systems is not expected but if System
operating conditions cause operation below the Minimum Stable Operating Level or
Minimum Active Power Transmission Capacity which could give rise to operational
difficulties for the Power Generating Module including a DC Connected Power Park Module
or HVDC Systems then the EU Generator or HVDC System Owner shall be able to return
the output of the Power Generating Module including a DC Connected Power Park Module
to an output of not less than the Minimum Stable Operating Level or HVDC System to an
output of not less than the Minimum Active Power Transmission Capacity.
ECC.6.3.7.1.5 All reasonable efforts should in the event be made by the EU Generator or HVDC System
Owner to avoid such tripping provided that the System Frequency is below 52Hz in
accordance with the requirements of ECC.6.1.2. If the System Frequency is at or above
52Hz, the requirement to make all reasonable efforts to avoid tripping does not apply and the
EU Generator or HVDC System Owner is required to take action to protect its Power
Generating Modules including DC Connected Power Park Modules or HVDC Converter
Stations.
(iii) The actual delivery of Active Power Frequency Response in LFSM-U mode shall take
into account
(iv) In LFSM_U Mode, the Power Generating Module (including DC Connected Power
Park Modules) and HVDC Systems, shall be capable of providing a power increase
up to its Maximum Capacity or Maximum HVDC Active Power Transmission
Capacity (as applicable).
ECC.6.3.7.3.4 HVDC Systems shall also meet the following minimum requirements:
(i) HVDC Systems shall be capable of responding to Frequency deviations in each
connected AC System by adjusting their Active Power import or export as shown in
Figure 6.3.7.3.4(a) with the corresponding parameters in Table 6.3.7.3.4(a).
Parameter Setting
Active Power as a percentage of 10%
Maximum Capacity (frequency
ǀ𝜟𝑷𝟏 ǀ
response range) ( )
𝑷𝒎𝒂𝒙
ECC.6.3.13.3 Each HVDC System and Remote End HVDC Converter Station when connected and
synchronised to the System, shall be capable of withstanding without tripping a rate of change
of Frequency up to and including ±2.5Hz per second as measured over the previous 1 second
period. Voltage dips may cause localised rate of change of Frequency values in excess of
±2.5 Hz per second for short periods, and in these cases, the requirements under ECC.6.3.15
(fault ride through) supersedes this clause. For the avoidance of doubt, this requirement
relates to the capabilities of HVDC Systems and Remote End HVDC Converter Stations
only and does not impose the need for rate of change of Frequency protection nor does it
impose a specific setting for anti-islanding or loss-of-mains protection relays.
ECC.6.3.13.4 Each DC Connected Power Park Module when connected to the System, shall be capable
of withstanding without tripping a rate of change of Frequency up to and including ±2.0Hz per
second as measured over the previous 1 second period. Voltage dips may cause localised
rate of change of Frequency values in excess of ±2.0 Hz per second for short periods, and in
these cases, the requirements under ECC.6.3.15 (fault ride through) supersedes this clause.
For the avoidance of doubt, this requirement relates to the capabilities of DC Connected
Power Park Modules only and does not impose the need for rate of change of Frequency
protection nor does it impose a specific setting for anti-islanding or loss-of-mains protection
relays.
ECC.6.3.14.1 It may be agreed in the Bilateral Agreement that a Genset shall have a Fast-Start
Capability. Such Gensets may be used for Operating Reserve and their Start-Up may be
initiated by Frequency-level relays with settings in the range 49Hz to 50Hz as specified
pursuant to OC2.
ECC.6.3.15.1 General Fault Ride Through requirements, principles and concepts applicable to Type B,
Type C and Type D Power Generating Modules and OTSDUW Plant and Apparatus
subject to faults up to 140ms in duration
ECC.6.3.15.1.1 ECC.6.3.15.1 – ECC.6.3.15.8 section sets out the Fault Ride Through requirements on
Type B, Type C and Type D Power Generating Modules, OTSDUW Plant and
Apparatus and HVDC Equipment that shall apply in the event of a fault lasting up to
140ms in duration.
ECC.6.3.15.1.2 Each Power Generating Module, Power Park Module, HVDC Equipment and OTSDUW
Plant and Apparatus is required to remain connected and stable for any balanced and
unbalanced fault where the voltage at the Grid Entry Point or User System Entry Point
or (HVDC Interface Point in the case of Remote End DC Converter Stations or
Interface Point in the case of OTSDUW Plant and Apparatus) remains on or above the
heavy black line defined in sections ECC.6.3.15.2 – ECC.6.3.15.7 below.
ECC.6.3.15.1.3 The voltage against time curves defined in ECC.6.3.15.2 – ECC.6.3.15.7 expresses the
lower limit (expressed as the ratio of its actual value and its reference 1pu) of the actual
course of the phase to phase voltage (or phase to earth voltage in the case of
asymmetrical/unbalanced faults) on the System voltage level at the Grid Entry Point or
User System Entry Point (or HVDC Interface Point in the case of Remote End HVDC
Converter Stations or Interface Point in the case of OTSDUW Plant and Apparatus)
during a symmetrical or asymmetrical/unbalanced fault, as a function of time before, during
and after the fault.
ECC.6.3.15.2 Voltage against time curve and parameters applicable to Type B Synchronous Power
Generating Modules
ECC.6.3.15.3 Voltage against time curve and parameters applicable to Type C and D Synchronous
Power Generating Modules connected below 110kV
Figure ECC.6.3.15.3 - Voltage against time curve applicable to Type C and D Synchronous
Power Generating Modules connected below 110kV
ECC.6.3.15.4 Voltage against time curve and parameters applicable to Type D Synchronous Power
Generating Modules connected at or above 110kV
ECC.6.3.15.5 Voltage against time curve and parameters applicable to Type B, C and D Power Park
Modules connected below 110kV
Figure ECC.6.3.15.5 - Voltage against time curve applicable to Type B, C and D Power
Park Modules connected below 110kV
ECC.6.3.15.6 Voltage against time curve and parameters applicable to Type D Power Park Modules with
a Grid Entry Point or User System Entry Point at or above 110kV, DC Connected Power
Park Modules at the HVDC Interface Point or OTSDUW Plant and Apparatus at the
Interface Point.
Figure ECC.6.3.15.6 - Voltage against time curve applicable to Type D Power Park Modules with a Grid
Entry Point or User System Entry Point at or above 110kV, DC Connected Power Park
Modules at the HVDC Interface Point or OTSDUW Plant and Apparatus at the Interface
Point.
Table ECC.6.3.15.6 Voltage against time parameters applicable to a Type D Power Park Modules with a
Grid Entry Point or User System Entry Point at or above 110kV, DC Connected Power
Park Modules at the HVDC Interface Point or OTSDUW Plant and Apparatus at the
Interface Point.
ECC.6.3.15.7 Voltage against time curve and parameters applicable to HVDC Systems and Remote End
HVDC Converter Stations
Table ECC.6.3.15.7 Voltage against time parameters applicable to HVDC Systems and Remote End HVDC
Converter Stations
(vii) Each Type B, Type C and Type D Power Generating Module, HVDC System and
OTSDUW Plant and Apparatus at the Interface Point shall be designed such that
upon clearance of the fault on the Onshore Transmission System and within 0.5
seconds of restoration of the voltage at the Grid Entry Point or User System Entry
Point or HVDC Interface Point in the case of a Remote End HVDC Converter
Stations or Interface Point in the case of OTSDUW Plant and Apparatus to 90% of
nominal voltage or greater, Active Power output (or Active Power transfer capability
in the case of OTSDW Plant and Apparatus or Remote End HVDC Converter
Stations) shall be restored to at least 90% of the level immediately before the fault.
Once Active Power output (or Active Power transfer capability in the case of
OTSDUW Plant and Apparatus or Remote End HVDC Converter Stations) has
been restored to the required level, Active Power oscillations shall be acceptable
provided that:
- The total Active Energy delivered during the period of the oscillations is at least
that which would have been delivered if the Active Power was constant
- The oscillations are adequately damped.
- In the event of power oscillations, Power Generating Modules shall retain
steady state stability when operating at any point on the Power Generating
Module Performance Chart.
For AC Connected Onshore and Offshore Power Park Modules comprising
switched reactive compensation equipment (such as mechanically switched capacitors
and reactors), such switched reactive compensation equipment shall be controlled
such that it is not switched in or out of service during the fault but may act to assist in
post fault voltage recovery.
ECC.6.3.15.9 General Fault Ride Through requirements for faults in excess of 140ms in duration.
ECC.6.3.15.9.1 General Fault Ride Through requirements applicable to HVDC Equipment and OTSDUW
DC Converters subject to faults and voltage dips in excess of 140ms.
ECC.6.3.15.9.2 Fault Ride Through requirements for Type C and Type D Synchronous Power Generating
Modules and Type C and Type D Power Park Modules and OTSDUW Plant and Apparatus
subject to faults and voltage disturbances on the Onshore Transmission System in excess
of 140ms
(i) remain transiently stable and connected to the System without tripping of any
Synchronous Power Generating Module for balanced Supergrid Voltage dips
and associated durations on the Onshore Transmission System (which could be
at the Interface Point) anywhere on or above the heavy black line shown in Figure
ECC.6.3.15.9(a) Appendix 4 and Figures EA.4.3.2(a), (b) and (c) provide an
explanation and illustrations of Figure ECC.6.3.15.9(a); and,
Figure ECC.6.3.15.9(a)
(ii) provide Active Power output at the Grid Entry Point, during Supergrid Voltage
dips on the Onshore Transmission System as described in Figure
ECC.6.3.15.9(a), at least in proportion to the retained balanced voltage at the
Onshore Grid Entry Point (for Onshore Synchronous Power Generating
Modules) or Interface Point (for Offshore Synchronous Power Generating
Modules) (or the retained balanced voltage at the User System Entry Point if
Embedded) and shall generate maximum reactive current (where the voltage at the
Grid Entry Point is outside the limits specified in ECC.6.1.4) without exceeding the
transient rating limits of the Synchronous Power Generating Module and,
(iii) restore Active Power output following Supergrid Voltage dips on the Onshore
Transmission System as described in Figure ECC.6.3.15.9(a), within 1 second of
restoration of the voltage to 1.0pu of the nominal voltage at the:
to at least 90% of the level available immediately before the occurrence of the dip.
Once the Active Power output has been restored to the required level, Active
Power oscillations shall be acceptable provided that:
- the total Active Energy delivered during the period of the oscillations is at
least that which would have been delivered if the Active Power was constant
- the oscillations are adequately damped.
(b) Requirements applicable to Type C and Type D Power Park Modules and OTSDUW
Plant and Apparatus (excluding OTSDUW DC Converters) subject to Supergrid
Voltage dips on the Onshore Transmission System greater than 140ms in duration.
(i) remain transiently stable and connected to the System without tripping of any
OTSDUW Plant and Apparatus, or Power Park Module and / or any constituent
Power Park Unit, for balanced Supergrid Voltage dips and associated durations
on the Onshore Transmission System (which could be at the Interface Point)
anywhere on or above the heavy black line shown in Figure ECC.6.3.15.9(b).
Appendix 4 and Figures EA.4.3.4 (a), (b) and (c) provide an explanation and
illustrations of Figure ECC.6.3.15.9(b) ; and,
15
Figure ECC.6.3.15.9(b)
(iii) restore Active Power output (or, in the case of OTSDUW, Active Power transfer
capability), following Supergrid Voltage dips on the Onshore Transmission
Issue 5 Revision 38 ECC 04 September 2019
60 of 137
System as described in Figure ECC.6.3.15.9(b), within 1 second of restoration of
the voltage to 0.9 pu of the nominal voltage at the:
Onshore Grid Entry Point for directly connected Onshore Power Park
Modules or,
Interface Point for OTSDUW Plant and Apparatus and Offshore Power
Park Modules or,
User System Entry Point for Embedded Onshore Power Park Modules or ,
User System Entry Point for Embedded Medium Power Stations which
comprise Power Park Modules not subject to a Bilateral Agreement and with
an Onshore User System Entry Point (irrespective of whether they are
located Onshore or Offshore)
to at least 90% of the level available immediately before the occurrence of the dip
except in the case of a Non-Synchronous Generating Unit, OTSDUW Plant and
Apparatus or Power Park Module where there has been a reduction in the
Intermittent Power Source in the time range in Figure ECC.6.3.15.9(b) that
restricts the Active Power output or, in the case of OTSDUW, Active Power transfer
capability below this level. Once the Active Power output or, in the case of
OTSDUW, Active Power transfer capability has been restored to the required level,
Active Power oscillations shall be acceptable provided that:
- the total Active Energy delivered during the period of the oscillations is at
least that which would have been delivered if the Active Power was constant
- the oscillations are adequately damped.
(i) In the case of a Power Park Module, the requirements in ECC.6.3.15.9 do not apply
when the Power Park Module is operating at less than 5% of its Rated MW or during
very high primary energy source conditions when more than 50% of the Power Park
Units in a Power Park Module have been shut down or disconnected under an
emergency shutdown sequence to protect User’s Plant and Apparatus.
(ii) In addition to meeting the conditions specified in ECC.6.1.5(b) and ECC.6.1.6, each Non-
Synchronous Generating Unit, OTSDUW Plant and Apparatus or Power Park
Module and any constituent Power Park Unit thereof will be required to withstand,
without tripping, the negative phase sequence loading incurred by clearance of a close-
up phase-to-phase fault, by System Back-Up Protection on the Onshore
Transmission System operating at Supergrid Voltage.
(iii) Generators in respect of Type B, Type C and Type D Power Park Modules and HVDC
System Owners are required to confirm to The Company, their repeated ability to
operate through balanced and unbalanced faults and System disturbances each time the
voltage at the Grid Entry Point or User System Entry Point falls outside the limits
specified in ECC.6.1.4. Demonstration of this capability would be satisfied by EU
Generators and HVDC System Owners supplying the protection settings of their plant,
informing The Company of the maximum number of repeated operations that can be
performed under such conditions and any limiting factors to repeated operation such as
protection or thermal rating; and
(iv) Notwithstanding the requirements of ECC.6.3.15(v), Power Generating Modules shall
be capable of remaining connected during single phase or three phase auto-reclosures
to the National Electricity Transmission System and operating without power reduction
as long as the voltage and frequency remain within the limits defined in ECC.6.1.4 and
ECC.6.1.2; and
(v) For the avoidance of doubt the requirements specified in ECC.6.3.15 do not apply to
Power Generating Modules connected to either an unhealthy circuit and/or islanded
from the Transmission System even for delayed auto reclosure times.
ECC.6.3.15.11.1 The HVDC System shall be capable of finding stable operation points with a minimum
change in Active Power flow and voltage level, during and after any planned or
unplanned change in the HVDC System or AC System to which it is connected. The
Company shall specify the changes in the System conditions for which the HVDC
Systems shall remain in stable operation.
ECC.6.3.15.11.2 The HVDC System owner shall ensure that the tripping or disconnection of an HVDC
Converter Station, as part of any multi-terminal or embedded HVDC System, does not
result in transients at the Grid Entry Point or User System Entry Point beyond the limit
specified by The Company in co-ordination with the Relevant Transmission Licensee.
ECC.6.3.15.11.3 The HVDC System shall withstand transient faults on HVAC lines in the network adjacent
or close to the HVDC System, and shall not cause any of the equipment in the HVDC
System to disconnect from the network due to autoreclosure of lines in the System.
ECC.6.3.15.11.4 The HVDC System Owner shall provide information to The Company on the resilience
of the HVDC System to AC System disturbances.
ECC.6.3.16.1 General Fast Fault Current injection, principles and concepts applicable to Type B, Type
C and Type D Power Park Modules and HVDC Equipment
ECC.6.3.16.1.1 In addition to the requirements of ECC.6.1.4, ECC.6.3.2, ECC.6.3.8 and ECC.A.7, each
Type B, Type C and Type D Power Park Module or each Power Park Unit within a Type
B, Type C and Type D Power Park Module or HVDC Equipment shall be required to
satisfy the following requirements. For the purposes of this requirement, current and
voltage are assumed to be positive phase sequence values.
ECC.6.3.16.1.2 For any balanced fault which results in the positive phase sequence voltage falling below
the voltage levels specified in ECC.6.1.4 at the Grid Entry Point or User System Entry
Point (if Embedded), each Type B, Type C and Type D Power Park Module or each
Power Park Unit within a Type B, Type C and Type D Power Park Module or HVDC
Equipment shall, as a minimum (unless an alternative type registered solution has
otherwise been agreed with The Company), be required to inject a reactive current above
the heavy black line shown in Figure ECC.16.3.16(a)
ECC.6.3.16.1.3 Figure ECC.6.3.16(a) defines the reactive current (IR) to be supplied under a faulted condition
which shall be dependent upon the pre-fault operating condition and the retained voltage at
the Grid Entry Point or User System Entry Point voltage. For the avoidance of doubt, each
Power Park Module (and any constituent element thereof) or HVDC Equipment, shall be
required to inject a reactive current (IR) which shall be not less than its pre-fault reactive current
and which shall as a minimum increase with the fall in the retained voltage each time the
voltage at the Grid Entry Point or User System Entry Point (if Embedded) falls below 0.9pu
whilst ensuring the overall rating of the Power Park Module (or constituent element thereof)
or HVDC Equipment shall not be exceeded.
ECC.6.3.16.1.4 In addition to the requirements of ECC.6.3.16.1.2 and ECC.6.3.16.1.3, each Type B, Type C
and Type D Power Park Module or each Power Park Unit within a Type B, Type C and
Type D Power Park Module or HVDC Equipment shall be required to inject reactive current
above the shaded area shown in Figure ECC.6.3.16(b) and Figure ECC.6.3.16(c) which
illustrates how the reactive current shall be injected over time from fault inception in which the
value of IR is determined from Figure ECC.6.3.16(a). In figures ECC.6.3.16(b) and
ECC.6.3.16(c) IR is the value of the reactive current (IR) less the prefault current. In this
context fault inception is taken to be when the voltage at the Grid Entry Point or User System
Entry Point falls below 0.9pu.
Figure ECC.16.3.16(c)
ECC.6.3.16.1.5 The injected reactive current (IR)shall be above the shaded area shown in Figure
ECC.6.3.16(b) and Figure ECC.6.3.16(c) with priority being given to reactive current injection
with any residual capability being supplied as active current. Under any faulted condition,
where the voltage falls outside the limits specified in ECC.6.1.4, there would be no requirement
for each Power Park Module or constituent Power Park Unit or HVDC Equipment to exceed
its transient or steady state rating of 1.0pu as defined in ECC.6.3.16.1.7.
ECC.6.3.16.1.6 For any planned or switching events (as outlined in ECC.6.1.7 of the Grid Code) or unplanned
events which results in temporary power frequency over voltages (TOV’s), each Type B, Type
C and Type D Power Generating Module or each Power Park Unit within a Type B, Type
C or Type D Power Park Module or HVDC Equipment will be required to satisfy the transient
overvoltage limits specified in the Bilateral Agreement.
Figure ECC.16.3.16(d)
ECC.6.3.16.1.14 In the case of a unbalanced fault, the Generator or HVDC System Owner shall confirm
to The Company their ability to prevent transient overvoltages arising on the remaining
healthy phases and the control strategy employed.
ECC.6.5.6.4 (a) The Company or The Relevant Transmission Licensee, as applicable, shall provide
system control and data acquisition (SCADA) outstation interface equipment., each EU
Code User shall provide such voltage, current, Frequency, Active Power and Reactive
Power measurement outputs and plant status indications and alarms to the
Transmission SCADA outstation interface equipment as required by The Company in
accordance with the terms of the Bilateral Agreement. In the case of OTSDUW, the
User shall provide such SCADA outstation interface equipment and voltage, current,
Frequency, Active Power and Reactive Power measurement outputs and plant status
indications and alarms to the SCADA outstation interface equipment as required by The
Company in accordance with the terms of the Bilateral Agreement.
(b) For the avoidance of doubt, for Active Power and Reactive Power measurements,
circuit breaker and disconnector status indications from:
(i) CCGT Modules from Type B, Type C and Type D Power Generating Modules,
the outputs and status indications must each be provided to The Company on an
individual CCGT Unit basis. In addition, where identified in the Bilateral
Agreement, Active Power and Reactive Power measurements from Unit
Transformers and/or Station Transformers must be provided.
(ii) For Type B, Type C and Type D Power Park Modules the outputs and status
indications must each be provided to The Company on an individual Power Park
Module basis. In addition, where identified in the Bilateral Agreement, Active
Power and Reactive Power measurements from station transformers must be
provided.
(iii) In respect of OTSDUW Plant and Apparatus, the outputs and status indications
must be provided to The Company for each piece of electrical equipment. In
addition, where identified in the Bilateral Agreement, Active Power and Reactive
Issue 5 Revision 38 ECC 04 September 2019
73 of 137
Power measurements at the Interface Point must be provided.
(c) For the avoidance of doubt, the requirements of ECC.6.5.6.4(a) in the case of a Cascade
Hydro Scheme will be provided for each Generating Unit forming part of that Cascade
Hydro Scheme. In the case of Embedded Generating Units forming part of a Cascade
Hydro Scheme the data may be provided by means other than the SCADA outstation
located at the Power Station, such as, with the agreement of the Network Operator in
whose system such Embedded Generating Unit is located, from the Network
Operator’s SCADA system to The Company. Details of such arrangements will be
contained in the relevant Bilateral Agreements between The Company and the
Generator and the Network Operator.
(d) In the case of a Power Park Module, additional energy input signals (e.g. wind speed,
and wind direction) may be specified in the Bilateral Agreement. A Power Available
signal will also be specified in the Bilateral Agreement. The signals would be used to
establish the potential level of energy input from the Intermittent Power Source for
monitoring pursuant to ECC.6.6.1 and Ancillary Services and will, in the case of a wind
farm, be used to provide The Company with advanced warning of excess wind speed
shutdown and to determine the level of Headroom available from Power Park Modules
for the purposes of calculating response and reserve. For the avoidance of doubt, the
Power Available signal would be automatically provided to The Company and represent
the sum of the potential output of all available and operational Power Park Units within
the Power Park Module. The refresh rate of the Power Available signal shall be
specified in the Bilateral Agreement.
ECC.6.5.6.5 In addition to the requirements of the Balancing Codes, each HVDC Converter unit of an
HVDC system shall be equipped with an automatic controller capable of receiving instructions
from The Company. This automatic controller shall be capable of operating the HVDC
Converter units of the HVDC System in a coordinated way. The Company shall specify the
automatic controller hierarchy per HVDC Converter unit.
ECC.6.5.6.6 The automatic controller of the HVDC System referred to in paragraph ECC.6.5.6.5 shall be
capable of sending the following signal types to The Company (where applicable) :
(a) operational metering signals, providing at least the following:
(i) start-up signals;
(ii) AC and DC voltage measurements;
(iii) AC and DC current measurements;
(iv) Active and Reactive Power measurements on the AC side;
(v) DC power measurements;
(vi) HVDC Converter unit level operation in a multi-pole type HVDC Converter;
(vii) elements and topology status; and
(viii) Frequency Sensitive Mode, Limited Frequency Sensitive Mode Overfrequency and
Limited Frequency Sensitive Mode Underfrequency Active Power ranges (where
applicable).
(b) alarm signals, providing at least the following:
(i) emergency blocking;
(ii) ramp blocking;
(iii) fast Active Power reversal (where applicable)
ECC.6.5.6.7 The automatic controller referred to in ECC.6.5.6.5 shall be capable of receiving the following signal
types from The Company (where applicable) :
(a) operational metering signals, receiving at least the following:
(i) start-up command;
Issue 5 Revision 38 ECC 04 September 2019
74 of 137
(ii) Active Power setpoints;
(iii) Frequency Sensitive Mode settings;
(iv) Reactive Power, voltage or similar setpoints;
(v) Reactive Power control modes;
(vi) power oscillation damping control; and
(c) Detailed specifications of these required electronic facilities will be provided by The
Company on request and they are listed as Electrical Standards in the Annex to the
General Conditions.
Facsimile Machines
ECC.6.5.9 Each User and The Company shall provide a facsimile machine or machines:
(a) in the case of Generators, at the Control Point of each Power Station and at its Trading
Point;
(b) in the case of The Company and Network Operators, at the Control Centre(s); and
(c) in the case of Non-Embedded Customers and HVDC Equipment owners at the Control
Point.
ECC.A.1.1 Principles
Types of Schedules
ECC.A.1.1.1 At all Complexes (which in the context of this ECC shall include, Interface Sites until the
OTSUA Transfer Time) the following Site Responsibility Schedules shall be drawn up using
the relevant proforma attached or with such variations as may be agreed between The
Company and Users, but in the absence of agreement the relevant proforma attached will be
used. In addition, in the case of OTSDUW Plant and Apparatus, and in readiness for the
OTSUA Transfer Time, the User shall provide The Company with the necessary information
such that Site Responsibility Schedules in this form can be prepared by the Relevant
Transmission Licensees for the Transmission Interface Site:
(a) Schedule of HV Apparatus
(b) Schedule of Plant, LV/MV Apparatus, services and supplies;
(c) Schedule of telecommunications and measurements Apparatus.
Other than at Power Generating Module (including DC Connected Power Park Modules)
and Power Station locations, the schedules referred to in (b) and (c) may be combined.
New Connection Sites
ECC.A.1.1.2 In the case of a new Connection Site each Site Responsibility Schedule for a Connection
Site shall be prepared by The Company in consultation with relevant Users at least 2 weeks
prior to the Completion Date (or, where the OTSUA is to become Operational prior to the
OTSUA Transfer Time, an alternative date) under the Bilateral Agreement and/or
Construction Agreement for that Connection Site (which may form part of a Complex). In
the case of a new Interface Site where the OTSUA is to become Operational prior to the
OTSUA Transfer Time each Site Responsibility Schedule for an Interface Site shall be
prepared by The Company in consultation with relevant Users at least 2 weeks prior to the
Completion Date under the Bilateral Agreement and/or Construction Agreement for that
Interface Site (which may form part of a Complex) (and references to and requirements
placed on “Connection Site” in this ECC shall also be read as “Interface Site” where the
context requires and until the OTSUA Transfer Time). Each User shall, in accordance with
the timing requirements of the Bilateral Agreement and/or Construction Agreement ,
provide information to The Company to enable it to prepare the Site Responsibility
Schedule.
Sub-division
ECC.A.1.1.3 Each Site Responsibility Schedule will be subdivided to take account of any separate
Connection Sites on that Complex.
Scope
ECC.A.1.1.4 Each Site Responsibility Schedule shall detail for each item of Plant and Apparatus:
(a) Plant/Apparatus ownership;
(b) Site Manager (Controller) (except in the case of Plant/Apparatus located in SPT’s
Transmission Area);
(c) Safety issues comprising applicable Safety Rules and Control Person or other
responsible person (Safety Co-ordinator), or such other person who is responsible for
safety;
(d) Operations issues comprising applicable Operational Procedures and control engineer;
(e) Responsibility to undertake statutory inspections, fault investigation and maintenance.
Issue 5 Revision 38 ECC 04 September 2019
85 of 137
Each Connection Point shall be precisely shown.
Detail
ECC.A.1.1.5 (a) In the case of Site Responsibility Schedules referred to in ECC.A.1.1.1(b) and (c), with
the exception of Protection Apparatus and Intertrip Apparatus operation, it will be
sufficient to indicate the responsible User or Transmission Licensee, as the case may
be.
(b) In the case of the Site Responsibility Schedule referred to in ECC.A.1.1.1(a) and for
Protection Apparatus and Intertrip Apparatus, the responsible management unit must
be shown in addition to the User or Transmission Licensee, as the case may be.
ECC.A.1.1.6 The HV Apparatus Site Responsibility Schedule for each Connection Site must include
lines and cables emanating from or traversing1 the Connection Site.
Issue Details
ECC.A.1.1.7 Every page of each Site Responsibility Schedule shall bear the date of issue and the issue
number.
Accuracy Confirmation
ECC.A.1.1.8 When a Site Responsibility Schedule is prepared it shall be sent by The Company to the
Users involved for confirmation of its accuracy.
ECC.A.1.1.9 The Site Responsibility Schedule shall then be signed on behalf of The Company by its
Responsible Manager (see ECC.A.1.1.16) and on behalf of each User involved by its
Responsible Manager (see ECC.A.1.1.16), by way of written confirmation of its accuracy.
The Site Responsibility Schedule will also be signed on behalf of the Relevant
Transmission Licensee by its Responsible Manager.
Distribution and Availability
ECC.A.1.1.10 Once signed, two copies will be distributed by The Company, not less than two weeks prior
to its implementation date, to each User which is a party on the Site Responsibility
Schedule, accompanied by a note indicating the issue number and the date of
implementation.
ECC.A.1.1.11 The Company and Users must make the Site Responsibility Schedules readily available
to operational staff at the Complex and at the other relevant control points.
Alterations to Existing Site Responsibility Schedules
ECC.A 1.1.12 Without prejudice to the provisions of ECC.A.1.1.15 which deals with urgent changes, when a
User identified on a Site Responsibility Schedule becomes aware that an alteration is
necessary, it must inform The Company immediately and in any event 8 weeks prior to any
change taking effect (or as soon as possible after becoming aware of it, if less than 8 weeks
remain when the User becomes aware of the change). This will cover the commissioning of
new Plant and/or Apparatus at the Connection Site, whether requiring a revised Bilateral
Agreement or not, de-commissioning of Plant and/or Apparatus, and other changes which
affect the accuracy of the Site Responsibility Schedule.
ECC.A 1.1.13 Where The Company has been informed of a change by a User, or itself proposes a change,
it will prepare a revised Site Responsibility Schedule by not less than six weeks prior to the
change taking effect (subject to it having been informed or knowing of the change eight weeks
prior to that time) and the procedure set out in ECC.A.1.1.8 shall be followed with regard to
the revised Site Responsibility Schedule.
1 Details of circuits traversing the Connection Site are only needed from the date which is the earlier of the date when the Site
Responsibility Schedule is first updated and 15th October 2004. In Scotland or Offshore, from a date to be agreed between The
Company and the Relevant Transmission Licensee.
Issue 5 Revision 38 ECC 04 September 2019
86 of 137
ECC.A 1.1.14 The revised Site Responsibility Schedule shall then be signed in accordance with the
procedure set out in ECC.A.1.1.9 and distributed in accordance with the procedure set out in
ECC.A.1.1.10, accompanied by a note indicating where the alteration(s) has/have been made,
the new issue number and the date of implementation.
Urgent Changes
ECC.A.1.1.15 When a User identified on a Site Responsibility Schedule, or The Company, as the case
may be, becomes aware that an alteration to the Site Responsibility Schedule is necessary
urgently to reflect, for example, an emergency situation which has arisen outside its control,
the User shall notify The Company, or The Company shall notify the User, as the case may
be, immediately and will discuss:
(a) what change is necessary to the Site Responsibility Schedule;
(b) whether the Site Responsibility Schedule is to be modified temporarily or permanently;
(c) the distribution of the revised Site Responsibility Schedule.
The Company will prepare a revised Site Responsibility Schedule as soon as possible, and
in any event within seven days of it being informed of or knowing the necessary alteration.
The Site Responsibility Schedule will be confirmed by Users and signed on behalf of The
Company and Users and the Relevant Transmission Licensee (by the persons referred to
in ECC.A.1.1.9) as soon as possible after it has been prepared and sent to Users for
confirmation.
Responsible Managers
ECC.A.1.1.16 Each User shall, prior to the Completion Date under each Bilateral Agreement and/or
Construction Agreement, supply to The Company a list of Managers who have been duly
authorised to sign Site Responsibility Schedules on behalf of the User and The Company
shall, prior to the Completion Date under each Bilateral Agreement and/or Construction
Agreement, supply to that User the name of its Responsible Manager and the name of the
Relevant Transmission Licensee’s Responsible Manager and each shall supply to the
other any changes to such list six weeks before the change takes effect where the change is
anticipated, and as soon as possible after the change, where the change was not anticipated.
De-commissioning of Connection Sites
ECC.A.1.1.17 Where a Connection Site is to be de-commissioned, whichever of The Company or the User
who is initiating the de-commissioning must contact the other to arrange for the Site
Responsibility Schedule to be amended at the relevant time.
AREA
COMPLEX: SCHEDULE:
CONNECTION SITE:
AREA
COMPLEX: SCHEDULE:
CONNECTION SITE:
NOTES:
Basic Principles
(1) Where practicable, all the HV Apparatus on any Connection Site shall be shown on one
Operation Diagram. Provided the clarity of the diagram is not impaired, the layout shall
represent as closely as possible the geographical arrangement on the Connection Site.
(2) Where more than one Operation Diagram is unavoidable, duplication of identical information
on more than one Operation Diagram must be avoided.
(3) The Operation Diagram must show accurately the current status of the Apparatus e.g.
whether commissioned or decommissioned. Where decommissioned, the associated
switchbay will be labelled "spare bay".
(4) Provision will be made on the Operation Diagram for signifying approvals, together with
provision for details of revisions and dates.
(5) Operation Diagrams will be prepared in A4 format or such other format as may be agreed
with The Company.
(6) The Operation Diagram should normally be drawn single line. However, where appropriate,
detail which applies to individual phases shall be shown. For example, some HV Apparatus
is numbered individually per phase.
ECC.A.3.1 Scope
The frequency response capability is defined in terms of Primary Response, Secondary
Response and High Frequency Response. In addition to the requirements defined in
ECC.6.3.7 this appendix defines the minimum frequency response requirements for:-
(a) each Type C and Type D Power Generating Module
(b) each DC Connected Power Park Module
(c) each HVDC System
For the avoidance of doubt, this appendix does not apply to Type A and Type B Power
Generating Modules.
OTSDUW Plant and Apparatus should facilitate the delivery of frequency response services
provided by Offshore Generating Units and Offshore Power Park Units.
The functional definition provides appropriate performance criteria relating to the provision of
Frequency control by means of Frequency sensitive generation in addition to the other
requirements identified in ECC.6.3.7.
In this Appendix 3 to the ECC, for a Power Generating Module including a CCGT Module or
a Power Park Module or DC Connected Power Park Module, the phrase Minimum
Regulating Level applies to the entire CCGT Module or Power Park Module or DC
Connected Power Park Module operating with all Generating Units Synchronised to the
System.
The minimum Frequency response requirement profile is shown diagrammatically in Figure
ECC.A.3.1. The capability profile specifies the minimum required level of Frequency
Response Capability throughout the normal plant operating range.
ECC.A.3.2 Plant Operating Range
The upper limit of the operating range is the Maximum Capacity of the Power Generating
Module or Generating Unit or CCGT Module or HVDC Equipment.
The Minimum Stable Operating Level may be less than, but must not be more than, 65%
of the Maximum Capacity. Each Power Generating Module and/or Generating Unit and/or
CCGT Module and/or Power Park Module or HVDC Equipment must be capable of
operating satisfactorily down to the Minimum Regulating Level as dictated by System
operating conditions, although it will not be instructed to below its Minimum Stable Operating
Level . If a Power Generating Module or Generating Unit or CCGT Module or Power Park
Module, or HVDC Equipment is operating below Minimum Stable Operating Level because
of high System Frequency, it should recover adequately to its Minimum Stable Operating
Level as the System Frequency returns to Target Frequency so that it can provide Primary
and Secondary Response from its Minimum Stable Operating Level if the System
Frequency continues to fall. For the avoidance of doubt, under normal operating conditions
steady state operation below the Minimum Stable Operating Level is not expected. The
Minimum Regulating Level must not be more than 55% of Maximum Capacity.
In the event of a Power Generating Module or Generating Unit or CCGT Module or Power
Park Module or HVDC Equipment load rejecting down to no less than its Minimum
Regulating Level it should not trip as a result of automatic action as detailed in BC3.7. If the
load rejection is to a level less than the Minimum Regulating Level then it is accepted that
the condition might be so severe as to cause it to be disconnected from the System.
ECC.A.3.3 Minimum Frequency Response Requirement Profile
FAULT RIDE THROUGH REQUIREMENTS FOR TYPE B, TYPE C AND TYPE D POWER GENERATING
MODULES (INCLUDING OFFSHORE POWER PARK MODULES WHICH ARE EITHER AC CONNECTED
POWER PARK MODULES OR DC CONNECTED POWER PARK MODULES), HVDC SYSTEMS AND
OTSDUW PLANT AND APPARATUS
ECC.A.4A.1 Scope
The Fault Ride Through requirements are defined in ECC.6.3.15. This Appendix provides
illustrations by way of examples only of ECC.6.3.15.1 to ECC.6.3.15.10 and further
background and illustrations and is not intended to show all possible permutations.
ECC.A.4A.2 Short Circuit Faults At Supergrid Voltage On The Onshore Transmission System Up To
140ms In Duration
For short circuit faults at Supergrid Voltage on the Onshore Transmission System (which
could be at an Interface Point) up to 140ms in duration, the Fault Ride Through requirement
is defined in ECC.6.3.15. In summary any Power Generating Module (including a DC
Connected Power Park Module) or HVDC System is required to remain connected and
stable whilst connected to a healthy circuit. Figure ECC.A.4.A.2 illustrates this principle.
Figure ECC.A.4.A.2
In Figure ECC.A.4.A.2 a solid three phase short circuit fault is applied adjacent to substation
A resulting in zero voltage at the point of fault. All circuit breakers on the faulty circuit (Lines
ABC) will open within 140ms resulting in Gen X tripping. The effect of this fault, due to the low
impedance of the network, will be the observation of a low voltage at each substation node
across the Total System until the fault has been cleared. In this example, Gen Y and Gen Z
(an Embedded Generator) would need to remain connected and stable as both are still
connected to the Total System and remain connected to healthy circuits .
The criteria for assessment is based on a voltage against time curve at each Grid Entry Point
or User System Entry Point. The voltage against time curve at the Grid Entry Point or User
System Entry Point varies for each different type and size of Power Generating Module as
detailed in ECC.6.3.15.2. – ECC.6.3.15.7.
The post fault voltage at a Grid Entry Point or User System Entry Point is largely influenced
by the topology of the network rather than the behaviour of the Power Generating Module
itself. The EU Generator therefore needs to ensure each Power Generating Module remains
connected and stable for a close up solid three phase short circuit fault for 140ms at the Grid
Entry Point or User System Entry Point.
Two examples are shown in Figure EA.4.2(a) and Figure EA4.2(b). In Figure EA.4.2(a) the
post fault profile is above the heavy black line. In this case the Power Generating Module
must remain connected and stable. In Figure EA4.2(b) the post fault voltage dips below the
heavy black line in which case the Power Generating Module is permitted to trip.
Figure EA.4.2(a)
Figure EA.4.2(b)
The process for demonstrating Fault Ride Through compliance against the requirements of
ECC.6.3.15 is detailed in ECP.A.3.5 and ECP.A.6.7 (as applicable).
ECC.A.4A.3 Supergrid Voltage Dips On The Onshore Transmission System Greater Than 140ms In
Duration
This profile is not a voltage-time response curve that would be obtained by plotting the
transient voltage response at a point on the Onshore Transmission System (or User
System if located Onshore) to a disturbance. Rather, each point on the profile (ie the heavy
black line) represents a voltage level and an associated time duration which connected
Synchronous Power Generating Modules must withstand or ride through.
Figures EA.4.3.2 (a), (b) and (c) illustrate the meaning of the voltage-duration profile for
voltage dips having durations greater than 140ms.
Figure EA.4.3.1
ECC.A.4A3.2 Requirements applicable to Power Park Modules or OTSDUW Plant and Apparatus subject
to Supergrid Voltage dips on the Onshore Transmission System greater than 140ms in
duration
For balanced Supergrid Voltage dips on the Onshore Transmission System (which could
be at an Interface Point) having durations greater than 140ms and up to 3 minutes the Fault
Ride Through requirement is defined in ECC.6.3.15.9.2.1(b) and Figure ECC.6.3.15.9(b)
which is reproduced in this Appendix as Figure EA.4.3.3 and termed the voltage–duration
profile.
This profile is not a voltage-time response curve that would be obtained by plotting the
transient voltage response at a point on the Onshore Transmission System (or User
System if located Onshore) to a disturbance. Rather, each point on the profile (ie the heavy
black line) represents a voltage level and an associated time duration which connected Power
Park Modules or OTSDUW Plant and Apparatus must withstand or ride through.
Figure EA.4.3.3
Figure EA.4.3.4(a)
Figure ECC4.3(a)
ECC.4EC1.2.1 In this example, the voltage dips to 0.5pu for 710ms. Under ECC.6.3.16 each Type B, Type
C and Type D Power Park Module is required to inject reactive current into the System and
shall respond in proportion to the change in System voltage at the Grid Entry Point or User
System Entry Point up to a maximum value of 1.0pu of rated current. An example of the
expected injected reactive current at the Connection Point is shown in Figure ECC4.5
Figure ECC4.5 Reactive Current Injected for a 50% voltage dip for a period of 710ms
(b) Operating time: Relay operating time shall not be more than 150 ms;
(d) Direction Tripping interlock for forward or reverse power flow capable of
being set in either position or off
(f) Output contacts: Two output contacts per stage to be capable of repetitively
making and breaking for 1000 operations:
48.8 5
48.75 5
48.7 10
48.6 7.5 10
48.5 7.5 10
48.4 7.5 10 10
48.2 7.5 10 10
48.0 5 10 10
47.8 5
Total % Demand 60 40 40
Table ECC.A.5.5.1a
Note – the percentages in table ECC.A.5.5.1a are cumulative such that, for example, should
the frequency fall to 48.6 Hz in NGET’s Transmission Area, 27.5% of the total Demand
connected to the National Electricity Transmission System in NGET’s Transmission Area
shall be disconnected by the action of Low Frequency Relays.
The percentage Demand at each stage shall be allocated as far as reasonably practicable.
The cumulative total percentage Demand is a minimum.
ECC.A.5.5.2 In the case of a Non-Embedded Customer (who is also an EU Code User) the percentage
of Demand (based on Annual ACS Conditions) at the time of forecast National Electricity
Transmission System peak Demand that each Non-Embedded Customer whose System
is connected to the Onshore Transmission System which shall be disconnected by Low
Frequency Relays shall be in accordance with OC6.6 and the Bilateral Agreement.
ECC.A.5.6 Connection and Reconnection
ECC.A.5.6.1 As defined under OC.6.6 once automatic low Frequency Demand Disconnection has taken
place, the Network Operator on whose User System it has occurred, will not reconnect until
The Company instructs that Network Operator to do so in accordance with OC6. The same
requirement equally applies to Non-Embedded Customers.
ECC.A.5.6.2 Once The Company instructs the Network Operator or Non Embedded Customer to
reconnect to the National Electricity Transmission System following operation of the Low
Frequency Demand Disconnection scheme it shall do so in accordance with the
requirements of ECC.6.2.3.10 and OC6.6.
ECC.A.6.1 Scope
ECC.A.6.1.1 This Appendix sets out the performance requirements of continuously acting automatic
excitation control systems for Type C and Type D Onshore Synchronous Power
Generating Modules that must be complied with by the User. This Appendix does not limit
any site specific requirements where in The Company's reasonable opinion these facilities
are necessary for system reasons.
ECC.A.6.1.2 Where the requirements may vary the likely range of variation is given in this Appendix. It may
be necessary to specify values outside this range where The Company identifies a system
need, and notwithstanding anything to the contrary The Company may specify values outside
of the ranges provided in this Appendix 6. The most common variations are in the on-load
excitation ceiling voltage requirements and the response time required of the Exciter. Actual
values will be included in the Bilateral Agreement.
ECC.A.6.1.3 Should an EU Generator anticipate making a change to the excitation control system it shall
notify The Company under the Planning Code (PC.A.1.2(b) and (c)) as soon as the EU
Generator anticipates making the change. The change may require a revision to the Bilateral
Agreement.
ECC.A.6.2 Requirements
ECC.A.6.2.1 The Excitation System of a Type C or Type D Onshore Synchronous Power Generating
Module shall include an excitation source (Exciter), and a continuously acting Automatic
Voltage Regulator (AVR) and shall meet the following functional specification. Type D
Synchronous Power Generating Modules are also required to be fitted with a Power
System Stabiliser in accordance with the requirements of ECC.A.6.2.5.
ECC.A.6.2.3 Steady State Voltage Control
ECC.A.6.2.3.1 An accurate steady state control of the Onshore Synchronous Power Generating Module
pre-set Synchronous Generating Unit terminal voltage is required. As a measure of the
accuracy of the steady-state voltage control, the Automatic Voltage Regulator shall have
static zero frequency gain, sufficient to limit the change in terminal voltage to a drop not
exceeding 0.5% of rated terminal voltage, when the output of a Synchronous Generating
Unit within an Onshore Synchronous Power Generating Module is gradually changed from
zero to rated MVA output at rated voltage, Active Power and Frequency.
ECC.A.6.2.4 Transient Voltage Control
ECC.A.6.2.4.1 For a step change from 90% to 100% of the nominal Onshore Synchronous Generating
Unit terminal voltage, with the Onshore Synchronous Generating Unit on open circuit, the
Excitation System response shall have a damped oscillatory characteristic. For this
characteristic, the time for the Onshore Synchronous Generating Unit terminal voltage to
first reach 100% shall be less than 0.6 seconds. Also, the time to settle within 5% of the voltage
change shall be less than 3 seconds.
ECC.A.6.2.4.2 To ensure that adequate synchronising power is maintained, when the Onshore Power
Generating Module is subjected to a large voltage disturbance, the Exciter whose output is
varied by the Automatic Voltage Regulator shall be capable of providing its achievable upper
and lower limit ceiling voltages to the Onshore Synchronous Generating Unit field in a time
not exceeding that specified in the Bilateral Agreement. This will normally be not less than
50 ms and not greater than 300 ms. The achievable upper and lower limit ceiling voltages may
be dependent on the voltage disturbance.
ECC.A.6.2.4.3 The Exciter shall be capable of attaining an Excitation System On Load Positive Ceiling
Voltage of not less than a value specified in the Bilateral Agreement that will be:
ECC.A.6.2.8.3 The EU Generator shall also make provision to prevent any over-excitation restriction of the
Onshore Synchronous Generating Unit when the Excitation System is under manual
control, other than that necessary to ensure the Onshore Power Generating Module is
operating within its design limits.
ECC.A.7.1 Scope
ECC.A.7.1.1 This Appendix sets out the performance requirements of continuously acting automatic voltage
control systems for Onshore Power Park Modules, Onshore HVDC Converters Remote
End HVDC Converter Stations and OTSDUW Plant and Apparatus at the Interface Point
that must be complied with by the User. This Appendix does not limit any site specific
requirements where in The Company's reasonable opinion these facilities are necessary for
system reasons. The control performance requirements applicable to Configuration 2 AC
Connected Offshore Power Park Modules and Configuration 2 DC Connected Power
Park Modules are defined in Appendix E8.
ECC.A.7.1.2 Proposals by EU Generators or HVDC System Owners to make a change to the voltage
control systems are required to be notified to The Company under the Planning Code
(PC.A.1.2(b) and (c)) as soon as the Generator or HVDC System Owner anticipates making
the change. The change may require a revision to the Bilateral Agreement.
ECC.A.7.1.3 In the case of a Remote End HVDC Converter at a HVDC Converter Station, the control
performance requirements shall be specified in the Bilateral Agreement. These requirements
shall be consistent with those specified in ECC.6.3.2.4. In the case where the Remote End
HVDC Converter is required to ensure the zero transfer of Reactive Power at the HVDC
Interface Point then the requirements shall be specified in the Bilateral Agreement which
shall be consistent with those requirements specified in ECC.A.8 . In the case where a wider
reactive capability has been specified in ECC.6.3.2.4, then the requirements consistent with
those specified in ECC.A.7.2 shall apply with any variations being agreed between the User
and The Company.
ECC.A.7.2 Requirements
Figure ECC.A.7.2.2a
ECC.A.7.2.2.2 The continuously acting automatic control system shall be capable of operating to a Setpoint
Voltage between 95% and 105% with a resolution of 0.25% of the nominal voltage. For the
avoidance of doubt values of 95%, 95.25%, 95.5% … may be specified, but not intermediate
values. The initial Setpoint Voltage will be 100%. The tolerance within which this Setpoint
Voltage shall be achieved is specified in BC2.A.2.6. For the avoidance of doubt, with a
tolerance of 0.25% and a Setpoint Voltage of 100%, the achieved value shall be between
99.75% and 100.25%. The Company may request the EU Generator or HVDC System
Owner to implement an alternative Setpoint Voltage within the range of 95% to 105%. For
Embedded Generators and Embedded HVDC System Owners the Setpoint Voltage will
be discussed between The Company and the relevant Network Operator and will be
specified to ensure consistency with ECC.6.3.4.
Figure ECC.A.7.2.2b
Figure ECC.A.7.2.2c
− 1 second where the step is sufficiently large to require a change in the steady
state Reactive Power output from zero to its maximum leading value or
maximum lagging value as required by ECC.6.3.2 (or, if appropriate
ECC.A.7.2.2.6 or ECC.A.7.2.2.7);
(iii) the magnitude of the Reactive Power output response produced within 1 second shall
vary linearly in proportion to the magnitude of the step change.
(iv) within 5 seconds from achieving 90% of the response as defined in ECC.A.7.2.3.1 (ii),
the peak to peak magnitude of any oscillations shall be less than 5% of the change in
steady state maximum Reactive Power.
(v) following the transient response, the conditions of ECC.A.7.2.2 apply.
Required response at 1
second
0.2 1 Seconds
Figure ECC.A.7.2.3.1a
ECC.A.7.2.3.2 OTSDUW Plant and Apparatus or Onshore Power Park Modules or Onshore HVDC
Converters shall be capable of
(a) changing its Reactive Power output from its maximum lagging value to its maximum
leading value, or vice versa, then reverting back to the initial level of Reactive Power
output once every 15 seconds for at least 5 times within any 5 minute period; and
(b) changing its Reactive Power output from zero to its maximum leading value then
reverting back to zero Reactive Power output at least 25 times within any 24 hour
period and from zero to its maximum lagging value then reverting back to zero Reactive
Power output at least 25 times within any 24 hour period. Any subsequent restriction
on reactive capability shall be notified to The Company in accordance with BC2.5.3.2,
and BC2.6.1.
In all cases, the response shall be in accordance to ECC.A.7.2.3.1 where the change in
Reactive Power output is in response to an on-load step change in Onshore Grid Entry
Point or Onshore User System Entry Point voltage, or in the case of OTSDUW Plant and
Apparatus an on-load step change in Transmission Interface Point voltage.
ECC.A.7.3.2 The Onshore Power Park Module or OTSDUW Plant and Apparatus or Onshore HVDC
Converter shall be capable of setting the Reactive Power setpoint anywhere in the Reactive
Power range as specified in ECC.6.3.2.4 with setting steps no greater than 5 MVAr or 5%
(whichever is smaller) of full Reactive Power, controlling the reactive power at the Grid Entry
Point or User System Entry Point if Embedded to an accuracy within plus or minus 5MVAr
or plus or minus 5% (whichever is smaller) of the full Reactive Power.
ECC.A.7.3.3 Any additional requirements for Reactive Power control mode of operation shall be specified
by The Company in coordination with the relevant Network Operator..
ECC.A.7.4.1 As defined in ECC.6.3.8.4.3, Power Factor control mode of operation is not required in
respect of Onshore Power Park Modules or OTSDUW Plant and Apparatus or Onshore
HVDC Converters unless otherwise specified by The Company in coordination with the
relevant Network Operator. However where there is a requirement for Power Factor control
mode of operation, the following requirements shall apply.
ECC.A.7.4.2 The Onshore Power Park Module or OTSDUW Plant and Apparatus or Onshore HVDC
Converter shall be capable of controlling the Power Factor at the Grid Entry Point or User
System Entry Point (if Embedded) within the required Reactive Power range as specified
in ECC.6.3.2.2.1 and ECC.6.3.2.4 to a specified target Power Factor. The Company shall
specify the target Power Factor value (which shall be achieved within 0.01 of the set Power
Factor), its tolerance and the period of time to achieve the target Power Factor following a
sudden change of Active Power output. The tolerance of the target Power Factor shall be
expressed through the tolerance of its corresponding Reactive Power. This Reactive Power
tolerance shall be expressed by either an absolute value or by a percentage of the maximum
Reactive Power of the Onshore Power Park Module or OTSDUW Plant and Apparatus or
Onshore HVDC Converter. The details of these requirements being pursuant to the terms of
the Bilateral Agreement.
ECC.A.7.4.3 Any additional requirements for Power Factor control mode of operation shall be specified by
The Company in coordination with the relevant Network Operator.
ECC.A.8.1 Scope
ECC.A.8.1.1 This Appendix sets out the performance requirements of continuously acting automatic voltage
control systems for Configuration 2 AC Connected Offshore Power Park Modules and
Configuration 2 DC Connected Power Park Modules that must be complied with by the EU
Code User. This Appendix does not limit any site specific requirements that may be specified
where in The Company's reasonable opinion these facilities are necessary for system
reasons.
ECC.A.8.1.2 These requirements also apply to Configuration 2 DC Connected Power Park Modules. In
the case of a Configuration 1 DC Connected Power Park Module the technical performance
requirements shall be specified by The Company. Where the EU Generator in respect of a
DC Connected Power Park Module has agreed to a wider reactive capability range as
defined under ECC.6.3.2.5 and ECC.6.2.3.6 then the requirements that apply will be specified
by The Company and which shall reflect the performance requirements detailed in ECC.A.8.2
below but with different parameters such as droop and Setpoint Voltage.
ECC.A.8.1.3 Proposals by EU Generators to make a change to the voltage control systems are required
to be notified to The Company under the Planning Code (PC.A.1.2(b) and (c)) as soon as
the Generator anticipates making the change. The change may require a revision to the
Bilateral Agreement.
ECC.A.8.2 Requirements
ECC.A.8.2.1 The Company requires that the continuously acting automatic voltage control system for the
Configuration 2 AC connected Offshore Power Park Module and Configuration 2 DC
Connected Power Park Module shall meet the following functional performance
specification.
ECC.A.8.2.2 Steady State Voltage Control
ECC.A.8.2.2.1 The Configuration 2 AC connected Offshore Power Park Module and Configuration 2 DC
Connected Power Park Module shall provide continuous steady state control of the voltage
at the Offshore Connection Point with a Setpoint Voltage and Slope characteristic as
illustrated in Figure ECC.A.8.2.2a.
Figure ECC.A.8.2.2a
Figure ECC.A.8.2.2b
ECC.A.8.2.2.4 Figure ECC.A.8.2.2b shows the required envelope of operation for Configuration 2 AC
connected Offshore Power Park Module and Configuration 2 DC Connected Power Park
Module. The enclosed area within points ABCDEFGH is the required capability range within
which the Slope and Setpoint Voltage can be changed.
ECC.A.8.2.2.5 Should the operating point of the Configuration 2 AC connected Offshore Power Park or
Configuration 2 DC Connected Power Park Module deviate so that it is no longer a point
on the operating characteristic (Figure ECC.A.8.2.2a) defined by the target Setpoint Voltage
and Slope, the continuously acting automatic voltage control system shall act progressively to
return the value to a point on the required characteristic within 5 seconds.
(iii) the magnitude of the Reactive Power output response produced within 1 second shall
vary linearly in proportion to the magnitude of the step change.
(iv) within 5 seconds from achieving 90% of the response as defined in ECC.A.8.2.3.1 (ii),
the peak to peak magnitude of any oscillations shall be less than 5% of the change in
steady state maximum Reactive Power.
(v) following the transient response, the conditions of ECC.A.8.2.2 apply.
MVArs
Required response at 1
second
0.2 1 Seconds
Figure ECC.A.8.2.3.1a
(a) changing their Reactive Power output from maximum lagging value to maximum
leading value, or vice versa, then reverting back to the initial level of Reactive Power
output once every 15 seconds for at least 5 times within any 5 minute period; and
(b) changing Reactive Power output from zero to maximum leading value then reverting
back to zero Reactive Power output at least 25 times within any 24 hour period and
from zero to its maximum lagging value then reverting back to zero Reactive Power
output at least 25 times within any 24 hour period. Any subsequent restriction on
reactive capability shall be notified to The Company in accordance with BC2.5.3.2,
and BC2.6.1.
In all cases, the response shall be in accordance to ECC.A.8.2.3.1 where the change in
Reactive Power output is in response to an on-load step change in Offshore Grid Entry
Point or Offshore User System Entry Point voltage or HVDC Interface Point voltage.
ECC.A.8.3.3 Any additional requirements for Reactive Power control mode of operation shall be specified
by The Company.
ECC.A.8.4.1 Power Factor control mode of operation is not required in respect of Configuration 2 AC
connected Offshore Power Park Modules or Configuration 2 DC Connected Power Park
Modules unless otherwise specified by The Company. However where there is a
requirement for Power Factor control mode of operation, the following requirements shall
apply.
ECC.A.8.4.3 Any additional requirements for Power Factor control mode of operation shall be specified by
The Company.
CONTENTS
(This contents page does not form part of the Grid Code)
DRSC.1 INTRODUCTION 2
DRSC.2 OBJECTIVE 2
DRSC.3 SCOPE 2
DRSC.4 GENERAL PROVISIONS 3
DRSC.11.3 COMPLIANCE 6
DRSC.1 INTRODUCTION
DRSC.1.1 The Demand Response Services Code is concerned with Demand Response Providers
who contract with The Company for the provision of Ancillary Services.
DRSC.1.2 Ancillary Services are non-mandatory services used by The Company in operating the
System. They are provided by Demand Response Providers with payment being dealt
with under the terms of the relevant agreement for the Ancillary Service.
DRSC.1.3 Where a Demand Response Provider is interested in offering an Ancillary Service to The
Company, then further details and additional information of the Ancillary Services are
available from the Balancing Services section of the Website.
DRSC.1.4 Where The Company and a Demand Response Provider enter into an Ancillary Services
agreement, it shall be in accordance with Transmission Licence condition C16 and the
Standard Contract Terms.
DRSC 1.5 The Demand Response Services Code which would form part of an Ancillary Services
agreement between a Demand Response Provider and The Company nd to discharge
the obligations under European Regulation (EU) 2016/1388. The Ancillary Services
agreement will include an obligation on the Demand Response Provider to satisfy the
applicable requirements of this Demand Response Services Code.
DRSC.1.6 The Demand Response Code applies only to Demand Response Providers who have
entered into an agreement with The Company to provide an Ancillary Service. This
Demand Response Services Code does not apply to Users who are not Demand
Response Providers.
DRSC.1.7 For the avoidance of doubt, Network Operators and Non Embedded Customers in
respect of EU Grid Supply Points are required to satisfy the compliance requirements in
section DRSC.11 of this code in addition to the European Compliance Processes only if
they are also a Demand Response Provider unless they are also a Demand Response
Provider.
DRSC.2 OBJECTIVE
The objectives of the DRSC are to
DRSC.2.1 Ensure the obligations of European Regulation (EU) 2016/1388 have been discharged; and
DRSC.2.2 Complement the requirements of the Ancillary Services agreement between The
Company and a Demand Response Provider; and
DRSC.2.3 Define the minimum technical and compliance requirements Demand Response Providers
are required to satisfy if they provide a Demand Response Service to The Company under
an Ancillary Services agreement.
DRSC.3 SCOPE
DRSC.3.1 The DRSC applies to any Demand Response Provider who has entered into an agreement
to provide Ancillary Services with The Company.
DRSC.3.2 The DRSC does not apply to Users or parties who are not Demand Response Providers.
DRSC.4.2 Demand Response Providers who own, operate, control or manage Plant and Apparatus
or Demand Unit(s) within a Demand Facility and/or Closed Distribution System(s) or on
an aggregated basis may provide Demand Response Services to The Company.
Demand Response Providers can offer Demand Response Services on an individual or
collective basis and increase or decrease their Demand in accordance with the terms of their
Ancillary Services agreement.
DRSC.4.3 The Demand Response Services specified in DRSC.4.1 are not exclusive and do not
preclude Demand Response Providers from negotiating other services with The Company.
These services would be pursuant to the terms of the Ancillary Services agreement.
DRSC.5 SPECIFIC PROVISIONS FOR DEMAND UNITS WITH DEMAND RESPONSE ACTIVE
POWER CONTROL AND TRANSMISSION CONSTRAINT MANAGEMENT
DRSC.5.1 Where a Demand Response Provider provides Demand Response Active Power
Control, Demand Response Reactive Power Control or Demand Response
Transmission Constraint Management to The Company, then the following requirements
as detailed below shall apply. For the avoidance of doubt these requirements shall apply
either individually or where it is not part of a Demand Facility, collectively as part of a
Demand Aggregation scheme through a Demand Response Provider. Demand
Response Providers shall ensure that any Demand Unit which they own, operate, control
or manage and which is used to provide Demand Response Services shall:-
(a) Be capable of satisfying the Frequency range requirements as specified in ECC.6.1.2.1.
(b) Be capable of satisfying the voltage range requirements as specified in ECC.6.1.4.1.
(c) Be capable of controlling the power consumption from the Total System in accordance
with the terms of the Ancillary Services agreement.
(d) Be capable of receiving instructions from The Company either directly or through a third
party to modify their demand in accordance with the Demand Response Service they
have agreed to provide..
(e) Be capable of adjusting its Real Power or Reactive Power flow within a time period
pursuant to the terms of the Ancillary Services agreement.
(f) Be capable of full execution of an instruction issued by The Company to modify its
power flow.
(g) Be capable of further demand changes as instructed by The Company, following the
execution of a previous instruction issued by The Company in accordance with the
Ancillary Services agreement. Any such instruction shall not exceed the normal safe
operating conditions of the Demand Response Provider’s Plant and Apparatus or
Demand Unit(s) which could cause such equipment to trip. Instructions to modify
Active Power or Reactive Power flow may have immediate or delayed effects but in
any event would need to comply with the requirements of the Ancillary Services
agreement.
(h) Notify The Company of any change in the available capacity in accordance with the
relevant Ancillary Services agreement.
(i) Be capable of withstanding a rate of change of System Frequency of up to a maximum
of 1Hz/s measured over a 500ms time frame.
DRSC.9.1 The operational metering data required to be submitted to The Company will vary depending
upon the type of Demand Response Service provided. Demand Response Providers may
be required to install such operational metering equipment in accordance with the Ancillary
Services agreement.
DRSC.10.1 Demand Response Providers may be required to be fitted with communication and
instruction facilities to enable The Company to instruct them in the operational timeframe.
These requirements will vary depending upon the type of Demand Response Service
provided and will be set out in the Ancillary Services agreement.
PART II
DRSC.11.1.1 Demand Response Providers who enter into an agreement with The Company to provide
Ancillary Services are required to undertake a compliance process to ensure the Plant and
Apparatus or Demand Unit(s) which they own, operate, control or manage, satisfies the
requirements of the Ancillary Services agreement and the Demand Response Services
Code. For the avoidance of doubt, Demand Response Providers who are also EU Code
Users, will also be required to satisfy the requirements of the applicable requirements of the
European Compliance Processes (ECP’s).
DRSC.11.1.2 Each Demand Response Provider, shall confirm to The Company its ability to comply
with the requirements of the Ancillary Services agreement.
DRSC.11.1.3 Each Demand Response Provider shall notify The Company of any change to the
Plant or Apparatus which they own, operate, control or manage such they are no
longer able to satisfy the conditions specified in the Ancillary Services agreement
and/or the relevant provisions of the DRSC. Such changes shall be notified to The
Company in accordance with the terms of the Ancillary Services agreement.
DRSC.11.2.3 When the Demand Response Provider has submitted a final DRUD to the satisfaction
of The Company which clearly demonstrates full compliance with the Ancillary
Services agreement, The Company shall issue a Final Operational Notification to
the Demand Response Provider.
DRSC.11.3 COMPLIANCE
DRSC.11.3.1.1 Demand Response Providers are required to satisfy the requirements of the Ancillary
Services agreement which shall include satisfying the applicable requirements of this
Demand Response Services Code.
DRSC.11.3.1.2 Should the Demand Response Provider wish to modify the technical capability of the
Plant and Apparatus or Demand Unit(s) which it owns, operates, controls or manages
and which affects its compliance with the Ancillary Services agreement, it should notify
and agree any timescales for the change with The Company prior to making any
change.
DRSC.11.3.1.3 Any operational incidents or failure of the Plant and Apparatus or Demand Unit(s)
owned, operated, controlled or managed by the Demand Response Provider which
impacts its ability to satisfy the compliance requirements detailed in this Demand
Response Services Code shall be notified to The Company as soon as possible after
occurrence of the incident.
DRSC.11.3.1.4 Any planned test schedules and procedures to verify compliance of the Plant and
Apparatus or Demand Unit(s) owned, operated, controlled or managed by the
Demand Response Provider shall be submitted to The Company in advance of the
tests. The Company shall assess the test schedules and procedures in a timely
manner prior to agreeing that the Demand Response Provider can carry out the tests.
DRSC.11.3.1.5 The Company may witness such tests and record the performance of the Plant and
Apparatus owned, operated, controlled or managed by the Demand Response
Provider to verify compliance with the Ancillary Services agreement and the Demand
Response Services Code.
DRSC.11.3.2.1 The Company shall assess the compliance of the Demand Response Provider and
shall undertake monitoring throughout the life time of the Plant and Apparatus or
Demand Unit(s) owned, operated, controlled or managed by the Demand Response
Provider to ensure compliance with the requirements of the Ancillary Services
agreement. The Company shall inform the Demand Response Provider of the
outcome of such assessment
DRSC.11.3.2.2 The Company may require Demand Response Providers to carry out compliance
tests and simulations according to a repeat plan or general scheme or replacement of
equipment which may have an impact on the compliance of the Plant and Apparatus
Issue 5 Revision 33 DRS 5 April 2019
6 of 12
or Demand Units owned, operated, controlled or managed by the Demand
Response Provider as detailed in DRSC.11.3.1.3 and DRSC.11.3.1.4. The
Company shall inform the Demand Response Provider of the results of these tests.
DRSC.11.3.2.3 As part of this compliance process, the Demand Response Provider shall provide the
following items:-
(a) Relevant documentation and certificates associated with the compliance process.
(b) Details of the technical data required to ensure compliance with the Ancillary
Services agreement.
(c) Steady state and dynamic models (as applicable) of their Demand Units or Plant and
Apparatus (or equivalent) as required and agreed with The Company.
(d) Timelines for the submission of system data required to perform System studies
(e) Study results showing the expected steady state and dynamic performance of the
Plant and Apparatus or Demand Unit(s) or the performance of their Demand
Response Service on an aggregated basis as required and agreed with The
Company.
(g) Conditions and procedures for the use of relevant Equipment Certificates issued by
an Authorised Certifier to a Demand Response Provider or equivalent to the
satisfaction of The Company.
DRSC.11.3.2.4 If compliance tests or simulations cannot be carried out as agreed between the Demand
Response Provider and The Company due to reasons attributable to The Company,
then The Company shall not unreasonably withhold the Operational Notification
referred to in DRSC.11.2.3.
DRSC.11.4.1.1 The purpose of compliance testing is to ensure that the Plant and Apparatus or Demand
Unit(s) owned, operated, controlled or managed by a Demand Response Provider is
capable of satisfying the requirements of the Ancillary Services agreement and applicable
sections of this Demand Response Services Code in addition to verifying that the models
and data submitted provide a true and accurate representation of the Plant as built.
DRSC.11.4.1.2 Notwithstanding the minimum requirements for compliance testing detailed in DRSC.11.4
of this Demand Response Services Code, The Company shall:-
(a) Allow the Demand Response Provider to carry out an alternative set of tests
provided that they are efficient and sufficient to demonstrate that the Plant and
Apparatus or Demand Unit(s) owned, operated, controlled or managed by a
Demand Response Provider is capable of satisfying the requirements of the
Ancillary Services agreement and the applicable sections of the Demand Response
Services Code.
(c) Require the Demand Response Provider to be responsible for carrying out the tests
in accordance with the requirements specified in DRSC.11.4 and DRSC.11.5 of the
Demand Response Services Code. The Company shall cooperate with the
Demand Response Provider and will not unduly delay the scheduling of the tests.
DRSC.11.4.1.3 The Company may witness such tests (either on site or remotely from The
Company’s control room) to record the performance of the Demand Response
Providers capability to verify compliance with the Ancillary Services agreement and
the Demand Response Services Code. Where The Company witnesses the tests
remotely, the Demand Response Provider shall provide the monitoring equipment
necessary to record all relevant test signals and measurements in addition to ensuring
that necessary representatives from the Demand Response Provider are available
on site for the entire testing period. Signals specified by The Company shall be
provided if for selected tests, The Company wishes to use its own equipment to
record performance. The Company will inform the Demand Response Provider if it
wishes to witness the tests.
DRSC.11.5 Compliance Testing for Demand Response Providers with Demand Response Active
Power Control, Reactive Power Control and Transmission Constraint Management.
DRSC.11.5.1.1 Demand Response Providers who have signed an Ancillary Services agreement
with The Company to provide Demand Response Active Power Control, Demand
Response Reactive Power Control or Demand Response Transmission
Constraint Management, are required to demonstrate (through site tests) the
capability of the Plant and Apparatus or Demand Unit(s) they own, operate, control
or manage to satisfy the requirements of the Ancillary Services agreement and the
applicable requirements of DRSC.5. The site tests should demonstrate the capability
of the Demand Response Providers ability to operate with instruction over the
agreed timeframes, Demand range and duration pursuant to the terms of the
Ancillary Services agreement. The tests can be completed individually or as part of
a Demand aggregation scheme.
DRSC.11.5.1.2 The tests shall be carried out either by instruction from The Company’s Control
Centre or by site tests through injections applied to the Plant and Apparatus or
Demand Unit(s) owned, operated, controlled or managed by the Demand Response
Provider.
DRSC.11.5.1.3 The test shall be deemed as passed if the requirements of the Ancillary Services
agreement have been satisfied and the applicable requirements of DRSC.5
demonstrated to the satisfaction of The Company.
DRSC.11.5.2.1 Demand Response Providers who have signed an Ancillary Services agreement
with The Company to provide Demand Response Active Power Control, Demand
Response Reactive Power Control or Demand Response Transmission
Constraint Management and have also agreed to disconnect or reconnect (or both)
static compensation facilities when receiving an instruction from The Company in
Issue 5 Revision 33 DRS 5 April 2019
8 of 12
accordance with the requirements of the Ancillary Services agreement and
DRSC.5.3, shall be required to demonstrate the performance of the Plant and
Apparatus or Demand Unit(s) they own, operate, control or manage to satisfy these
requirements. These requirements can be demonstrated individually or collectively as
part of a demand aggregation scheme.
DRSC.11.5.2.2 The tests shall be carried out either by instruction from The Company’s Control
Centre or by site tests resulting in the disconnection and subsequent re-connection of
the static compensation facilities.
DRSC.11.5.2.3 The test shall be deemed as passed if the requirements of the Ancillary Services
agreement have been satisfied and the applicable requirements of DRSC.5.3 demonstrated
to the satisfaction of The Company.
DRSC.11.6.1.1 Demand Response Providers who agree to provide Demand Response Very Fast Active
Power Control are required to demonstrate their ability to satisfy the requirements of the
Ancillary Services agreement and DRSC.7 through necessary simulation studies to the
satisfaction of The Company.
DRSC.11.6.1.2 Demand Response Providers who have contracted to provide a Demand Response Very
Fast Active Power Control service, are required to submit further simulation studies where
there has been a development, replacement or modernisation of the Plant and Apparatus
or Demand Unit(s)_ owned, operated, controlled or managed by the Demand Response
Provider, or The Company has identified a non–compliance with the Demand Response
Provider’s ability to satisfy the requirements of the Ancillary Services agreement or
DRSC.7.
(a) Allow the Demand Response Provider to carry out an alternative set of simulations
provided that they are efficient and sufficient to demonstrate that the Plant and
Apparatus or Demand Unit(s) owned, operated, controlled or managed by the
Demand Response Provider is capable of satisfying the requirements of the Ancillary
Services agreement and the applicable sections of the Demand Response Services
Code.
(b) Require the Demand Response Provider to carry out additional or alternative
simulations to those specified in DRSC11.6.1.1 and DRSC.11.6.1.28 where they would
otherwise be insufficient to demonstrate compliance with the Ancillary Services
agreement.
DRSC.11.6.1.4 The Company may check that the Demand Response Provider complies with the
requirements of the Ancillary Services agreement and the applicable sections of the
Demand Response Services Code by carrying out its own compliance simulations based
on the simulation reports, models and test measurements.
DRSC.11.6.1.5 The Company will supply upon request from the Demand Response Provider, data to
enable the Demand Response Provider to carry out the required simulations in accordance
with the requirements of the Ancillary Services agreement and DRSC.11.6.
Compliance Requirements
DRSC Requirement Compliance Demand Response Provider
Y/N Statement
Declaration
I declare that for all the Demand Response Provider’s information associated with this contract:
1. Compliance with the requirements of the Demand Response Services Code is achieved.
Name:
Signature:
Company Name:
Position:
I confirm that I have witnessed the commissioning checks in this document on behalf of
Name:
Signature:
Company Name:
CONTENTS
(This contents page does not form part of the Grid Code)
CP.2 OBJECTIVE
CP.2.1 The objective of the CP is to ensure that there is a clear and consistent process for
demonstration of compliance by GB Code Users with the Connection Conditions and
Bilateral Agreement which are similar for all GB Code Users of an equivalent category and
will enable The Company to comply with its statutory and Transmission Licence
obligations.
CP.2.2 Provisions of the CP which apply in relation to OTSDUW and OTSUA shall (in any particular
case) apply up to the OTSUA Transfer Time, whereupon such provisions shall (without
prejudice to any prior non-compliance) cease to apply.
CP.2.3 In relation to OTSDUW, provisions otherwise to be contained in a Bilateral Agreement may
be contained in the Construction Agreement, and accordingly a reference in the CP to a
relevant Bilateral Agreement includes the relevant Construction Agreement.
CP.3 SCOPE
CP.3.1 The CP applies to The Company and to GB Code Users, which in the CP means:
(a) GB Generators (other than in relation to Embedded Small Power Stations or
Embedded Medium Power Stations not subject to a Bilateral Agreement) including
those undertaking OTSDUW.
(b) Network Operators;
(c) Non-Embedded Customers;
(d) DC Converter Station owners (other than those which only have Embedded DC
Converter Stations not subject to a Bilateral Agreement).
The process illustrated in CP.A.1.1 applies to all GB Code Users energising passive network Plant and
Apparatus including Distribution Network Operators, Non-embedded Customers, Generators and DC
Converter Station owners. This process is a subset of the full process for Generators and DC Converter
Station owners shown in CP.A.1.2. This diagram illustrates the process in the CP and includes references in
brackets to specific Grid Code clauses.
This diagram illustrates the process in the CP and includes references in brackets to specific Grid Code
clauses. For the avoidance of doubt this process does not apply to Embedded Medium Power Stations not
subject to a Bilateral Agreement and Embedded DC Converter Stations not subject to a Bilateral
Agreement.
This diagram illustrates the process in the CP and includes references in brackets to specific Grid Code
clauses.
This diagram illustrates the process in the CP and includes references in brackets to specific Grid Code
clauses. For the avoidance of doubt this process does not apply to Embedded Medium Power Stations not
subject to a Bilateral Agreement and Embedded DC Converter Stations not subject to a Bilateral
Agreement.
This diagram illustrates the process in the CP and includes references in brackets to specific Grid Code
clauses. For the avoidance of doubt this process does not apply to Embedded Medium Power Stations not
subject to a Bilateral Agreement and Embedded DC Converter Stations not subject to a Bilateral
Agreement.
Power Station/ DC
[Name of Connection Site/site of connection]
Converter Station:
OTSUA [Name of Interface Site]
This User Self Certification of Compliance records the compliance by the GB Code User in respect of
[NAME] Power Station/DC Converter Station [and, in the case of OTSDUW Arrangements, OTSUA] with
the Grid Code and the requirements of the Bilateral Agreement and Construction Agreement dated [ ]
with reference number [ ]. It is completed by the Power Station/DC Converter Station owner in the case of
Plant and/or Apparatus (including OTSUA) connected to the National Electricity Transmission System
and for Embedded Plant.
We have recorded our compliance against each requirement of the Grid Code which applies to the Power
Station/DC Converter Station/OTSUA, together with references to supporting evidence and a commentary
where this is appropriate, and have provided this to The Company. A copy of the Compliance Statement is
attached.
Supporting evidence, in the form of simulation results, test results, manufacturer’s data and other
documentation, is attached in the User Data File Structure.
The GB Code User hereby certifies that, to the best of its knowledge and acting in accordance with Good
Industry Practice, [the Power Station is compliant with the Grid Code and the Bilateral Agreement] [the
OTSUA is compliant with the Grid Code and the Construction Agreement] in all aspects [with the following
Unresolved Issues*] [with the following derogation(s)**]:
Connection
Requirement Ref: Issue
Condition
* Include for Interim User Self Certification of Compliance ahead of Interim Operational Notification.
** Include for final User Self Certification of Compliance ahead of Final Operational Notification where derogation(s) have been granted.
If no derogation(s) required delete wording and Table.
CP.A.3.6.5 Simulation study shall be performed for both control modes, Frequency Sensitive Mode
(FSM) and Limited Frequency Sensitive Mode (LFSM). The simulation study results
should indicate Active Power and Frequency in the island system that includes the
Generating Unit, DC Converter or Power Park Module.
Figure CP.A.3.7.2
The simulation study shall show Active Power output (MW) and the equivalent of
Frequency injected.
CP.A.3.7.3 To demonstrate the Excitation System model the Generator shall submit simulation studies
representing the response of the Synchronous Generating Unit as follows:
(i) operating open circuit at rated terminal voltage and subjected to a 2% step increase in
terminal voltage reference.
CONTENTS
(This contents page does not form part of the Grid Code)
ECP.1 INTRODUCTION
ECP.1.3 Where a Generator or HVDC System Owner and/or The Company are
required to apply for a derogation to the Authority, this is not in respect of
OTSUA.
ECP.2 OBJECTIVE
ECP.2.1 The objective of the ECP is to ensure that there is a clear and consistent
process for demonstration of compliance by Users with the European
Connection Conditions and Bilateral Agreement and will enable The
Company to comply with its statutory and Transmission Licence
obligations. For the avoidance of doubt, the requirements of the European
Compliance Processes do not apply to Demand Response Providers
unless they are also an EU Code User and have entered into a CUSC
Contract with The Company.
ECP.2.2 Provisions of the ECP which apply in relation to OTSDUW and OTSUA shall
(in any particular case) apply up to the OTSUA Transfer Time, whereupon
such provisions shall (without prejudice to any prior non-compliance) cease
to apply.
ECP.3 SCOPE
ECP.3.1 The ECP applies to The Company and to Users, which in the ECP means:
(d) HVDC System Owners (other than those which only have
Embedded HVDC Systems not subject to a Bilateral
Agreement).
ECP.3.2 The above categories of User will become bound by the ECP prior to them
generating, distributing, supplying or consuming, or in the case of OTSUA,
transmitting, as the case may be, and references to the various categories
should, therefore, be taken as referring to them in that prospective role.
ECP.3.3 For the avoidance of doubt, Demand Response Providers do not need to
satisfy the requirements of this ECP unless they are also defined as an EU
Code User and have a CUSC Contract with The Company. Where a
Demand Response Provider is not an EU Code User and does not have a
CUSC Contract with The Company, the requirements of the Demand
Response Services Code shall only apply.
ECP.3.4 For the avoidance of doubt, this ECP does not apply to GB Code Users
other than in respect of Network Operator’s EU Grid Supply Points.
ECP.4.1 The CUSC Contract(s) contain certain provisions relating to the procedure
for connection to the National Electricity Transmission System or, in the
case of Embedded Power Stations or Embedded HVDC Systems,
becoming operational and include provisions to be complied with by Users
prior to and during the course of The Company notifying the User that it
has the right to become operational. In addition to such provisions this ECP
sets out in further detail the processes to be followed to demonstrate
compliance. While this ECP does not expressly address the processes to
be followed in the case OTSUA connecting to a Network Operator’s User
System prior to OTSUA Transfer Time, the processes to be followed by
The Company and the Generator in respect of the OTSUA in such
circumstances shall be consistent with those set out below by reference
OTSUA directly connected to the National Electricity Transmission
System.
(iv) for operating by using the Grid Supply Point an ION for;
ECP.4.2.1 The provisions contained in ECP.5 relate to the connection and energisation
of User’s Plant and Apparatus (including OTSUA) to the National
Electricity Transmission System or where Embedded, to a User’s
System.
ECP.4.2.2 The provisions contained in ECP.6 and ECP.7 provide the process for
Generators, HVDC System Owners, Network Operators and non-
Embedded Customers to demonstrate compliance with the Grid Code and
with, where applicable, the CUSC Contract(s) prior to and during the
course of such Generator’s, HVDC System Owner’s (including OTSUA up
to the OTSUA Transfer Time), Network Operator’s and Noon-Embedded
Customer’s Plant and Apparatus) becoming operational.
ECP.4.2.3 The provisions contained in ECP.8 detail the process to be followed when:
(a) a Generator’s or HVDC System Owner’s, or Network Operator’s
or Non-Embedded Customer’s Plant and/or Apparatus (including
the OTSUA) is unable to comply with any provisions of the Grid
Code and Bilateral Agreement; or,
(b) following any notification by a Generator or a HVDC System
Owner or a Network Operator or a Non-Embedded Customer
under the PC of any change to its Plant and Apparatus (including
any OTSUA); or,
(c) a Modification to a Generator’s or a HVDC System Owner’s or a
Network Operator’s or a Non-Embedded Customer’s Plant
and/or Apparatus.
ECP.5.1.1 Certain provisions relating to the connection and energisation of the User’s
Plant and Apparatus at the Connection Site and OTSUA at the
Transmission Interface Point and in certain cases of Embedded Plant
and Apparatus are specified in the CUSC and/or CUSC Contract(s). For
other Embedded Plant and Apparatus the Distribution Code, the DCUSA
and the Embedded Development Agreement for the connection specify
equivalent provisions. Further detail on this is set out in ECP.5 below.
ECP.5.2 The items for submission prior to the issue of an Energisation Operational
Notification are set out in ECC.5.2
ECP.5.3 In the case of a Generator or HVDC System Owner the items referred to in
ECC.5.2 shall be submitted using the Power Generating Module
Document or User Data File Structure as applicable.
ECP.5.4 Not less than 28 days, or such shorter period as may be acceptable in The
Company’s reasonable opinion, prior to the User wishing to energise its
Plant and Apparatus (including passive OTSUA) for the first time, the User
will submit to The Company a Certificate of Readiness to Energise High
Voltage Equipment which specifies the items of Plant and Apparatus
(including OTSUA) ready to be energised in a form acceptable to The
Company.
ECP.5.5 If the relevant obligations under the provisions of the CUSC and/or CUSC
Contract(s) and the conditions of ECP.5 have been completed to The
Company’s reasonable satisfaction then The Company shall issue an
Energisation Operational Notification. Any dynamically controlled
reactive compensation OTSUA (including Statcoms or Static Var
Compensators) shall not be Energised until the appropriate Interim
Operational Notification has been issued in accordance with ECP.6.
ECP.6.1.2 Not less than 7 days, or such shorter period as may be acceptable in The
Company’s reasonable opinion, prior to the Generator wishing to
Synchronise its Plant and Apparatus for the first time the Generator will:
(viii) The contact details of the Generator and the installer and their
signatures.
ECP.6.1.5 When the requirements of ECP.6.1.2 to ECP.6.1.4 have been met, The
Company will notify the Generator that the Power Generating Module
may (subject to the Generator having fulfilled the requirements of
ECP.6.1.3 where that applies) be Synchronised to the Total System.
ECP.6.1.6 Not less than 7 days, or such shorter period as may be acceptable in The
Company’s reasonable opinion, prior to the Generator wishing to
decommission its Plant and Apparatus the Generator will submit to The
Company a Notification of User’s Intention to Disconnect.
ECP.6.2.2 Not less than 28 days, or such shorter period as may be acceptable in The
Company’s reasonable opinion, prior to the Generator wishing to
Synchronise its Plant and Apparatus or dynamically controlled OTSUA for
the first time the Generator or HVDC Equipment owner will:
ECP.6.2.3 Items for submission prior to issue of the Interim Operational Notification.
(i) updated Planning Code data (both Standard Planning Data and
Detailed Planning Data), with any estimated values assumed for
planning purposes confirmed or, where practical, replaced by
validated actual values and by updated estimates for the future
and by updated forecasts for Forecast Data items such as
Demand;
PC.A.5.4.2
PC.A.5.4.3.2,
ECC.6.3.4,
ECC.6.3.7.3.1 to ECC.6.3.7.3.6,
ECC.6.3.15, ECC.6.3.16
ECC.A.6.2.5.6
ECC.A.7.2.3.1
(v) a detailed schedule of the tests and the procedures for the tests
required to be carried out by the Generator under ECP.7.2 to
demonstrate compliance with relevant Grid Code requirements.
Such schedule to be consistent with Appendix ECP.A.5 (in the
case of a Synchronous Power Generating Module) or Appendix
ECP.A.6 (in the case of a Power Park Modules) and OTSUA as
applicable);
(i) those tests required to establish the open and short circuit
saturation characteristics of the Synchronous Power
Generating Module (as detailed in Appendix ECP.A.4.3) to
enable assessment of the short circuit ratio in accordance
with ECC.6.3.2. Such tests may be carried out at a
location other than the Power Station site and supplied in
the form of an Equipment Certificate or as otherwise
agreed by The Company; and
ECP.6.2.5 The Company shall assess the schedule of tests submitted by the
Generator with the Notification of User’s Intention to Synchronise under
ECP.6.2.3 and shall determine whether such schedule has been completed
to The Company’s satisfaction.
ECP.6.2.6 When the requirements of ECP.6.2.2 to ECP.6.2.5 have been met, The
Company will notify the Generator that the:
Synchronous Power Generating Module,
CCGT Module,
Power Park Module or
Dynamically controlled OTSUA
ECP.6.2.6.2 The Generator must operate the Power Generating Module or OTSUA in
accordance with the terms, arising from the Unresolved Issues, of the
Interim Operational Notification. Where practicable, The Company will
discuss such terms with the Generator prior to including them in the
Interim Operational Notification.
ECP.6.2.6.3 The Interim Operational Notification will include the following limitations:
(i) 20% of the Maximum Capacity of the Power Park Module (or
the output of a single Power Park Unit where this exceeds 20%
of the Power Station’s Maximum Capacity)
until the Generator has completed the voltage control tests (detailed
in ECP.A.6.2) (including in respect of any dynamically controlled
OTSUA) to The Company’s reasonable satisfaction. Following
successful completion of this test each additional Power Park Unit
should be included in the voltage control scheme as soon as is
technically possible (unless The Company agrees otherwise).
ECP.6.2.7 Other than Unresolved Issues that are subject to tests required under
ECP.7.2 to be witnessed by The Company, the Generator must resolve
any Unresolved Issues prior to the commencement of the tests, unless
The Company agrees to a later resolution. The Generator must liaise with
The Company in respect of such resolution. The tests that may be
witnessed by The Company are specified in ECP.7.2.
ECP.6.2.8 Not less than 28 days, or such shorter period as may be acceptable in The
Company’s reasonable opinion, prior to the Generator wishing to
commence tests required under ECP.7 to be witnessed by The Company,
ECP.6.2.9 The items referred to at ECP.7.3 shall be submitted by the Generator after
successful completion of the tests required under ECP.7.2.
ECP.6.3.2 Not less than 28 days, or such shorter period as may be acceptable in The
Company’s reasonable opinion, prior to the Generator or HVDC System
Owner wishing to Synchronise its Plant and Apparatus or dynamically
controlled OTSUA for the first time the Generator or HVDC System
Owner will:
ECP.6.3.3 Items for submission prior to issue of the Interim Operational Notification.
(a) updated Planning Code data (both Standard Planning Data and
Detailed Planning Data), with any estimated values assumed for
planning purposes confirmed or, where practical, replaced by
validated actual values and by updated estimates for the future and
by updated forecasts for Forecast Data items such as Demand;
PC.A.5.4.2
PC.A.5.4.3.2,
ECC.6.3.4,
ECC.6.3.7.3.1 to ECC.6.3.7.3.6,
ECC.6.3.15, ECC.6.3.16
ECC.A.6.2.5.6
ECC.A.7.2.3.1
(i) those tests required to establish the open and short circuit
saturation characteristics of the Synchronous Power
Generating Module (as detailed in Appendix ECP.A.5.3) to
enable assessment of the short circuit ratio in accordance
with ECC.6.3.2. Such tests may be carried out at a
location other than the Power Station site; and
ECP.6.3.5 The Company shall assess the schedule of tests submitted by the
Generator or HVDC System Owner with the Notification of User’s
Intention to Synchronise under ECP.6.3.1 and shall determine whether
such schedule has been completed to The Company’s satisfaction.
ECP.6.3.6 When the requirements of ECP.6.3.2 to ECP.6.3.5 have been met, The
Company will notify the Generator or HVDC System Owner that the:
Synchronous Power Generating Module,
CCGT Module,
Power Park Module
Dynamically controlled OTSUA or
ECP.6.3.6.1 The Interim Operational Notification will be time limited, the expiration
date being specified at the time of issue. The Interim Operational
Notification may be renewed by The Company for up to a maximum of 24
months from the date of the first issue of the Interim Operational
Notification. The Company may only issue an extension to an Interim
Operational Notification beyond 24 months provided the Generator or
HVDC System Owner has applied for a derogation for any remaining
Unresolved Issues to the Authority as detailed in ECP.9.
ECP.6.3.6.2 The Generator or HVDC System Owner must operate the Power
Generating Module or HVDC Equipment in accordance with the terms,
arising from the Unresolved Issues, of the Interim Operational
Notification. Where practicable, The Company will discuss such terms
with the Generator or HVDC System Owner prior to including them in the
Interim Operational Notification.
ECP.6.3.6.3 The Interim Operational Notification will include the following limitations:
(ii) 50MW
until the Generator has completed the voltage control tests (detailed
in ECP.A.6.3.2) to The Company’s reasonable satisfaction.
Following successful completion of this test each additional Power
Park Unit should be included in the voltage control scheme as soon
as is technically possible (unless The Company agrees otherwise).
ECP.6.3.7 Other than Unresolved Issues that are subject to tests required under
ECP.7.2 to be witnessed by The Company, the Generator or HVDC
System Owner must resolve any Unresolved Issues prior to the
commencement of the tests, unless The Company agrees to a later
resolution. The Generator or HVDC System Owner must liaise with The
Company in respect of such resolution. The tests that may be witnessed by
The Company are specified in ECP.7.2.
ECP.6.3.8 Not less than 28 days, or such shorter period as may be acceptable in The
Company’s reasonable opinion, prior to the Generator or HVDC System
Owner wishing to commence tests required under ECP.7 to be witnessed
by The Company, the Generator or HVDC System Owner will notify The
Company that the Power Generating Module(s) or HVDC Equipment(s)
as applicable is ready to commence such tests.
ECP.6.3.9 The items referred to at ECP.7.3 shall be submitted by the Generator or the
HVDC System Owner after successful completion of the tests required
under ECP.7.2.
ECP.6.4.2 Not less than 28 days, or such shorter period as may be acceptable in The
Company’s reasonable opinion, prior to the Network Operator or Non-
Embedded Customer wishing to operate its Plant and Apparatus by using
the EU Grid Supply Point for the first time, the Network Operator or Non-
Embedded Customer will:
ECP.6.4.3 Items for submission prior to issue of the Interim Operational Notification.
(a) updated Planning Code data (both Standard Planning Data and
Detailed Planning Data), with any estimated values assumed for
planning purposes confirmed or, where practical, replaced by
validated actual values and by updated estimates for the future and
by updated forecasts for Forecast Data items such as Demand;
PC.A.2.2
PC.A.2.3
PC.A.2.4
PC.A.2.5.2
PC.A.2.5.3
PC.A.2.5.4
PC.A.2.5.6
PC.A.4
PC.A.6.1.3
PC.A.6.3
PC.A.6.7.1
(e) a detailed schedule of the tests and the procedures for the tests
required to be carried out by the Network Operator or Non-
Embedded Customer under ECP.7.8 (or Equipment Certificates
as relevant) to demonstrate compliance with relevant Grid Code
requirements. Such schedule is to be consistent with Appendix
ECP.A.8.
ECP.6.4.5 The Company shall assess the schedule of tests submitted by the Network
Operator or Non-Embedded Customer with the Notification of User’s
ECP.6.4.6 When the requirements of ECP.6.4.2 to ECP.6.4.5 have been met, The
Company will notify the Network Operator or Non-Embedded Customer
that the Plant and Apparatus may (subject to the Network Operator or
Non-Embedded Customer having fulfilled the requirements of ECP.6.4.3
where that applies) be operated by using the EU Grid Supply Point
through the issue of an Interim Operational Notification.
ECP.6.4.6.1 The Interim Operational Notification will be time limited, the expiration
date being specified at the time of issue. The Interim Operational
Notification may be renewed by The Company for up to a maximum of 24
months from the date of the first issue of the Interim Operational
Notification. The Company may only issue an extension to an Interim
Operational Notification beyond 24 months provided the Network
Operator or Non-Embedded Customer has applied for a derogation for
any remaining Unresolved Issues to the Authority as detailed in ECP.9.
ECP.6.4.8 Not less than 28 days, or such shorter period as may be acceptable in The
Company’s reasonable opinion, prior to the Network Operator or Non-
Embedded Customer wishing to commence tests required under
ECP.7.8(e) and ECP.A.8 to be witnessed by The Company the Network
Operator or Non-Embedded Customer will notify The Company that the
Network Operator or Non-Embedded Customer as applicable is ready to
commence such tests.
ECP.7.1 The following provisions apply in relation to the issue of a Final Operational
Notification in respect of a Power Station consisting of Type B, Type C
and Type D Power Generating Modules or an HVDC System.
ECP.7.2 Tests to be carried out prior to issue of the Final Operational Notification.
(e) any further tests reasonably required by The Company and agreed
with the EU Code User to demonstrate any aspects of compliance
with the Grid Code and the CUSC Contracts.
ECP.7.2.4 In the case of Offshore Power Park Modules which do not contribute to
Offshore Transmission Licensee Reactive Power capability as described
in ECC.6.3.2.5 or ECC.6.3.2.6 or Voltage Control as described in
ECC.6.3.8.5 the tests outlined in ECP.7.2.2 (a) and ECP.7.2.2 (b) are not
ECP.7.2.5 Following completion of each of the tests specified in this ECP.7.2, The
Company will notify the Generator or HVDC System Owner whether, in
the opinion of The Company, the results demonstrate compliance with the
relevant Grid Code conditions.
ECP.7.2.6 The Generator or HVDC System Owner is responsible for carrying out the
tests and retains the responsibility for safety and personnel during the test.
ECP.7.3 Items for submission prior to issue of the Final Operational Notification
(a) updated Planning Code data (both Standard Planning Data and
Detailed Planning Data), with validated actual values and updated
estimates for the future including Forecast Data items such as
Demand;
(e) results from the tests required in accordance with ECP.7.2 carried
out by the Generator to demonstrate compliance with relevant
Grid Code requirements including the tests witnessed by The
Company; and
ECP.7.4 If the requirements of ECP.7.2 and ECP.7.3 have been successfully met,
The Company will notify the Generator or HVDC System Owner that
compliance with the relevant Grid Code provisions has been demonstrated
for the Power Generating Module(s), OTSUA if applicable or HVDC
Equipment as applicable through the issue of a Final Operational
Notification. In respect of a Embedded Power Station or Embedded
HVDC Equipment other than a Embedded Medium Power Stations not
subject to a Bilateral Agreement and Embedded HVDC Equipment not
ECP.7.6 The following provisions apply in relation to the issue of a Final Operational
Notification in respect of Network Operators and Non-Embedded
Customers Plant and Apparatus.
(a) updated Planning Code data (both Standard Planning Data and
Detailed Planning Data), with validated actual values and updated
estimates for the future including Forecast Data items such as
Demand;
(b) any items required by ECP.5.2 and ECP.6.4 updated by the User
as necessary;
(e) results from the tests and simulations required in accordance with
ECP.A.8 carried out by the Network Operator or Non-Embedded
Customer to demonstrate compliance with relevant Grid Code
requirements including any tests witnessed by The Company; and
ECP.8.4 Except where the provisions of ECP.8.3 apply, where the restriction notified in
ECP.8.2 is not resolved in 28 days, then
(i) the Generator or HVDC System Owner with input from and
discussion of conclusions with The Company, and the Network
Operator where the Synchronous Power Generating Module,
CCGT Module, Power Park Module or Power Station as applicable
is Embedded, shall undertake an investigation to attempt to
determine the causes of and determine a solution to the non-
compliance. Such investigation shall continue for no longer than 56
days. During such an investigation, the Generator or HVDC System
Owner shall provide to The Company the relevant data which has
changed due to the restriction in respect of ECP.7.3.1 as notified to
the Generator or HVDC System Owner by The Company as being
required to be provided; or
ECP.8.5.1 Following the issue of a Final Operational Notification, The Company will
issue to the Generator, HVDC System Owner, Network Operator or Non-
Embedded Customer a Limited Operational Notification if:
ECP.8.5.2 The Limited Operational Notification will be time limited (in the case of
Type D, HVDC Systems, Network Operator’s or Non-Embedded
Customer’s Plant and Apparatus to expire no later than 12 months from the
start of the non-compliance or restriction or from reconnection following a
change). The Company may agree a longer duration in the case of a Limited
Operational Notification following a Modification or whilst the Authority is
considering the application for a derogation in accordance with ECP.9.1.
ECP.8.5.3 The Limited Operational Notification will notify the Generator, HVDC
System Owner, Network Operator or Non-Embedded Customer of any
restrictions on the operation of the Synchronous Power Generating
Module(s), CCGT Module(s), Power Park Module(s) , OTSUA if applicable,
HVDC Equipment or Plant and Apparatus and will specify the Unresolved
Issues. The Generator, HVDC System Owner, Network Operator or Non-
Embedded Customer must operate in accordance with any notified
restrictions and must resolve the Unresolved Issues.
ECP.8.5.4 The User and The Company will be deemed compliant with all the relevant
provisions of the Grid Code provided operation is in accordance with the
Limited Operational Notification, whilst it is in force, and that the provisions
of and referred to in ECP.8 are complied with.
(a) updated Planning Code data (both Standard Planning Data and
Detailed Planning Data);
(d) a detailed schedule of the tests and the procedures for the tests
required to be carried out by the Generator, HVDC Equipment
Station, Network Operator or Non-Embedded Customer to
demonstrate compliance with relevant Grid Code requirements as
agreed by The Company. The schedule of tests shall be consistent
with Appendix ECP.A.5, Appendix ECP.A.6 or Appendix ECP.A.8
as appropriate; and
(a) those tests required to establish the open and short circuit
saturation characteristics of the Synchronous Power Generating
Module (as detailed in Appendix ECP.A.5.3) to enable assessment
of the short circuit ratio in accordance with ECC.6.3.2.3.4 or
ECC.6.3.2.5. Such tests may be carried out at a location other
than the Power Station site; and
ECP.8.6 In the case of a change or Modification, not less than 28 days, or such
shorter period as may be acceptable in The Company’s reasonable
opinion:
ECP.8.7 Other than Unresolved Issues that are subject to tests to be witnessed by
The Company, the Generator, HVDC System Owner, Network Operator
or Non-Embedded Customer must resolve any Unresolved Issues prior
to the commencement of the tests, unless The Company agrees to a later
resolution. The Generator, HVDC System Owner, Network Operator or
Non-Embedded Customer must liaise with The Company in respect of
such resolution. The tests that may be witnessed by The Company are
specified in ECP.7.2.2.
ECP.8.8 Not less than 28 days, or such shorter period as may be acceptable in The
Company’s reasonable opinion, prior to the Generator or HVDC System
Owner wishing to commence tests listed as Unresolved Issues to be
witnessed by The Company, the Generator or HVDC System Owner will
notify The Company that the Synchronous Power Generating Module(s),
CCGT Module(s), Power Park Module(s), OTSUA if applicable or HVDC
Equipment as applicable is ready to commence such tests.
ECP.8.10 Where the Unresolved Issues have been resolved a Final Operational
Notification will be issued to the User.
ECP.8.11 If a Final Operational Notification has not been issued by The Company as
referred to at ECP.8.5.2 (or where agreed following a Modification by the
expiry time of the LON) then the Generator, HVDC System Owner, Network
Operator or Non-Embedded Customer (where licensed in respect of its
activities) and The Company shall apply to the Authority for a derogation.
ECP.9.1 Whilst the Authority is considering the application for a derogation, the
Interim Operational Notification or Limited Operational Notification will
be extended to remain in force until the Authority has notified The
Company and the Generator, HVDC System Owner, Network Operator
or Non-Embedded Customer of its decision. Where the Generator or
HVDC System Owner is not licensed The Company may propose any
necessary changes to the Bilateral Agreement with such unlicensed
Generator or HVDC System Owner.
Issue 5 Revision 33 ECP 5 April 2019
25 of 67
ECP.9.2 If the Authority:
(a) grants a derogation in respect of the Plant and/or Apparatus, then
The Company shall issue Final Operational Notification once all
other Unresolved Issues are resolved; or
(b) decides a derogation is not required in respect of the Plant and/or
Apparatus then The Company will reconsider the relevant
Unresolved Issues and may issue a Final Operational Notification
once all other Unresolved Issues are resolved; or
(c) decides not to grant any derogation in respect of the Plant and/or
Apparatus, then there will be no Operational Notification in place
and The Company and the User shall consider its rights pursuant to
the CUSC.
ECP.10.1.4 The Company will maintain and publish a register of those Manufacturer’s
Data & Performance Reports which The Company has received and
accepted as being an accurate representation of the performance of the
relevant Plant and / or Apparatus. Such register will identify the
manufacturer, the model(s) of Power Park Unit(s) to which the report applies
and the provisions of the Grid Code in respect of which the report contributes
towards the demonstration of compliance. The inclusion of any report in the
register does not in any way confirm that any Power Park Modules which
The Company will not require Fault Ride Through simulation studies
to be conducted as per ECP.A.3.5.1 and qualified in ECP.A.3.5.2
provided that;
ECP.10.5 It is the responsibility of the EU Code User to ensure that the correct
reference for the Manufacturer’s Data & Performance Report is used and
the EU Code User by using that reference accepts responsibility for the
accuracy of the information. The EU Code User shall ensure that the
manufacturer has kept The Company informed of any relevant variations in
ECP.10.6 The Company may contact the Power Park Unit manufacturer directly to
verify the relevance of the use of such Manufacturer’s Data & Performance
Report. If The Company believe the use some or all of such
Manufacturer’s Data & Performance Report information is incorrect or the
referenced data is inappropriate then the reference to the Manufacturer’s
Data & Performance Report may be declared invalid by The Company.
Where, and to the extent possible, the data included in the Manufacturer’s
Data & Performance Report is appropriate, the compliance assessment
process will be continued using the data included in the Manufacturer’s Data
& Performance Report.
APPENDIX 1
NOT USED
This User Self Certification of Compliance records the compliance by the EU Code User in
respect of [NAME] Power Station/HVDC Equipment Station with the Grid Code and the
requirements of the Bilateral Agreement and Construction Agreement dated [ ] with
reference number [ ]. It is completed by the Power Station/HVDC System Owner in the
case of Plant and/or Apparatus connected to the National Electricity Transmission
System and for Embedded Plant.
We have recorded our compliance against each requirement of the Grid Code which applies
to the Power Station/HVDC Equipment Station, together with references to supporting
evidence and a commentary where this is appropriate, and have provided this to The
Company. A copy of the Compliance Statement is attached.
Supporting evidence, in the form of simulation results, test results, manufacturer’s data and
other documentation, is attached in the User Data File Structure.
The EU Code User hereby certifies that, to the best of its knowledge and acting in
accordance with Good Industry Practice, the Power Station is compliant with the Grid
Code and the Bilateral Agreement in all aspects [with the following Unresolved Issues*]
[with the following derogation(s)**]:
Connection
Requirement Ref: Issue
Condition
* Include for Interim User Self Certification of Compliance ahead of Interim Operational
Notification.
** Include for final User Self Certification of Compliance ahead of Final Operational
Notification where derogation(s) have been granted. If no derogation(s) required delete
wording and Table.
SIMULATION STUDIES
ECP.A.3.1 SCOPE
ECP.A.3.1.1 This Appendix sets out the simulation studies required to be submitted to The
Company to demonstrate compliance with the Connection Conditions unless
otherwise agreed with The Company. This Appendix should be read in
conjunction with ECP.6 with regard to the submission of the reports to The
Company. Where there is any inconsistency in the technical requirements in
respect of which compliance is being demonstrated by simulation in this
Appendix and ECC.6.3 and the Bilateral Agreement, the provisions of the
Bilateral Agreement and ECC.6.3 prevail. The studies specified in this
Appendix will normally be sufficient to demonstrate compliance. However The
Company may agree an alternative set of studies proposed by the
Generator or HVDC System Owner provided The Company deem the
alternative set of studies sufficient to demonstrate compliance with the Grid
Code and the Bilateral Agreement.
ECP.A.3.1.2 The Generator or HVDC System Owner shall submit simulation studies in
the form of a report to demonstrate compliance. In all cases the simulation
studies must utilise models applicable to the Synchronous Power
Generating Module, HVDC Equipment or Power Park Module with
proposed or actual parameter settings. Reports should be submitted in
English with all diagrams and graphs plotted clearly with legible axes and
scaling provided to ensure any variations in plotted values is clear. In all
cases the simulation studies must be presented over a sufficient time period
to demonstrate compliance with all applicable requirements.
ECP.A.3.1.4 The Company will permit relaxation from the requirement ECP.A.3.2 to
ECP.A.3.8 where an Equipment Certificate for the Power Generating
Module or HVDC Equipment has been provided which details the
characteristics from appropriate simulations on a representative installation
with the same equipment and settings and the performance of the Power
Generating Module or HVDC Equipment can, in The Company’s opinion,
reasonably represent that of the installed Power Generating Module or
HVDC Equipment.
ECP.A.3.1.5 For Type B, Type C and Type D Power Generating Modules the relevant
Equipment Certificate must be supplied in the Power Generating Module
Document or Users Data File structure as applicable. For HVDC
Equipment the relevant Equipment Certificates must be supplied in the
Users Data File structure.
(iv) gain and phase Bode diagrams for the open loop frequency domain
response of the Synchronous Power Generating Module
Excitation System with and without the Power System
Stabiliser. These should be in a suitable format to allow
assessment of the phase contribution of the Power System
Stabiliser and the gain and phase margin of the Excitation
System with and without the Power System Stabiliser in service.
(vi) gain Bode diagram for the closed loop on load frequency domain
response of the Synchronous Power Generating Module
Excitation System with and without the Power System
Stabiliser. The Synchronous Power Generating Module
operating at full load and at unity power factor. These diagrams
should be in a suitable format to allow comparison of the Active
Power damping across the frequency range specified in
ECC.A.6.2.6.3 with and without the Power System Stabiliser in
service.
(i) the Voltage Control System model including the Power System
Stabiliser with settings as required under the Planning Code
(PC.A.5.4) and Bilateral Agreement.
(ii) on load time series dynamic simulation studies of the response of the
Voltage Control System with and without the Power System
Stabiliser to 2% and 10% steps in the reference voltage and a three
phase short circuit fault applied to the Grid Entry Point or the
Interface Point in the case of OTSDUW Plant and Apparatus for
100ms. The simulation studies should be carried out operating at full
Active Power and maximum leading Reactive Power import
condition with the fault level at the Supergrid HV connection point at
ECP.A.3.3.1 (a) The Generator shall supply simulation studies to demonstrate the
capability to meet ECC.6.3.4.1 by submission of a report containing:
(ii) a load flow simulation study result to demonstrate the maximum leading
Reactive Power capability of the Synchronous Power Generating
Module, OTSUA or Power Park Module at Maximum Capacity
when the Grid Entry Point or User System Entry Point if
Embedded or Interface Point (in the case of OTSUA) voltage is at
95% of nominal.
ECP.A.3.3.1 (b) The HVDC System Owner shall supply simulation studies to
demonstrate the capability to meet ECC.6.3.4.1 by submission of a
report containing:
(ii) a load flow simulation study result to demonstrate the maximum leading
Reactive Power capability of the Synchronous Power Generating
Module, HVDC Equipment, OTSUA or Power Park Module at
Maximum HVDC Active Power Transmission Capacity when the
Grid Entry Point or User System Entry Point if Embedded or
Interface Point (in case of OTSUA) voltage is at 95% of nominal.
ECP.A.3.3.3 In the case of a Power Park Module where the load flow simulation studies
show that the individual Power Park Units deviate from nominal voltage to
meet the Reactive Power requirements then evidence must be provided from
factory (e.g. in a Manufacturer’s Data & Performance Report) or site
testing that the Power Park Unit is capable of operating continuously at the
operating points determined in the load flow simulation studies.
ECP.A.3.4.1 This section applies to HVDC Equipment; and Type C & Type D Power
Park Modules to demonstrate the voltage control capability and Type B
Power Park Modules to demonstrate the voltage control capability if
specified by The Company.
(i) a dynamic time series simulation study result of a sufficiently large negative
step in System voltage to cause a change in Reactive Power from zero to
the maximum lagging value at Rated MW.
(ii) a dynamic time series simulation study result of a sufficiently large positive
step in System voltage to cause a change in Reactive Power from zero to
the maximum leading value at Rated MW.
(iii) a dynamic time series simulation study result to demonstrate control stability
at the lagging Reactive Power limit by application of a -2% voltage step while
operating within 5% of the lagging Reactive Power limit.
(iv) a dynamic time series simulation study result to demonstrate control stability
at the leading Reactive Power limit by application of a +2% voltage step
while operating within 5% of the leading Reactive Power limit.
ECP.A.3.4.2 All the above studies should be completed with a network operating at the
voltage applicable for zero Reactive Power transfer at the Grid Entry Point
or User System Entry Point if Embedded or, in the case of OTSUA,
Interface Point unless stated otherwise. The fault level at the HV connection
point should be set at the minimum level as agreed with The Company.
ECP.A.3.5.1 This section applies to Type B, Type C and Type D Power Generating
Modules and HVDC Equipment to demonstrate the modules fault ride
through and Fast Fault Current injection capability.
The Generator or HVDC System Owner shall supply time series simulation
study results to demonstrate the capability of Synchronous Power
Generating Module, HVDC Equipment, and Power Park Modules and
OTSUA to meet ECC.6.3.15 and ECC.6.3.16 by submission of a report
containing:
(i) a time series simulation study of a 140ms three phase short circuit
fault with a retained voltage as detailed in table A.3.5.1 below applied
at the Grid Entry Point or (User System Entry Point if Embedded)
of the Power Generating Module or HVDC Equipment or OTSUA.
For HVDC Equipment or Power Park Modules the simulation study should
be completed with the HVDC Equipment or Power Park Module operating
at full Active Power and zero Reactive Power output and the fault level at
the Supergrid HV connection point at minimum or as otherwise agreed with
The Company. Where the HVDC Equipment or Power Park Module is
Embedded the minimum Network Operator’s System impedance to the
Supergrid HV connection point shall be used which may be calculated from
the maximum fault level at the User System Entry Point.
For HVDC Equipment the simulations should include the duration of each
voltage dip 1 to 4 above for which the HVDC Equipment will remain
connected.
ECP.A.3.5.2 In the case of Power Park Modules comprised of Power Park Units in
respect of which the User’s reference to a Manufacturer’s Data &
Performance Report has been accepted by The Company for Fault Ride
Through, ECP.A.3.5.1 will not apply provided:
ECP.A.3.6.1 This section applies to Type B, Type C and Type D Power Generating
Modules, HVDC Equipment to demonstrate the capability to modulate Active
Power at high frequency as required by ECC6.3.7.3.5(ii).
ECP.A.3.6.3 For HVDC Equipment and Power Park Modules consisting of units
connected wholly by power electronic devices the simulation methodology
may be modified by the addition of a Synchronous Power Generating
Module (G2) connected as indicated in Figure ECP.A.3.6.2. This additional
Synchronous Power Generating Module should have an inertia constant of
3.5MWs/MVA, be initially operating at rated power output and unity power
factor. The mechanical power of the Synchronous Power Generating
Module (G2) should remain constant throughout the simulation.
ECP.A.3.6.4 At the start of the simulation study the Power Generating Module or HVDC
Equipment will be operating maximum Active Power output. The Power
Generating Module or HVDC Equipment will then be islanded from the
Total System but still supplying load “X” by the opening of a breaker, which is
not the Power Generating Module or HVDC Equipment connection circuit
breaker (the governor should therefore, not receive any signals that the
breaker has opened other than the reduction in load and subsequent increase
in speed). A schematic arrangement of the simulation study is illustrated by
Figure ECP.A.3.6.1.
DEMAND FORECASTS
CONTENTS
(This contents page does not form part of the Grid Code)
OC1.2 OBJECTIVE
The objectives of OC1 are to:
OC1.2.1 enable the provision of data to The Company by Users in the Programming Phase,
Control Phase and Post-Control Phase; and
OC1.2.2 provide for the factors to be taken into account by The Company when Demand forecasting
in the Programming Phase and Control Phase.
OC1.3 SCOPE
OC1 applies to The Company and to Users which in this OC1 means:
(a) Network Operators, and
(b) Suppliers.
CONTENTS
(This contents page does not form part of the Grid Code)
(c) The Company and each in respect of outages of all Embedded Large Power
Network Operator Stations and in respect of outages of other Plant
and/or Apparatus relating to such Embedded
Large Power Stations;
(e) Each Network Operator and in respect of User System outages relevant to The
each Non-Embedded Company; and
Customer and The in respect of Network Operators only, outages of
Company the Network Operator’s User System that may
impact upon an Offshore Transmission System
connected to that Network Operator’s User
System.
OC2.4.1.2 Planning of Power Generating Modules, Synchronous Generating Unit And External
Interconnection and Power Park Module Outages
OC2.4.1.2.1 Operational Planning Phase - Planning for Calendar Years 3 to 5 inclusive – Weekly
Resolution
In each calendar year:
(a) By the end of week 2
Each Generator and each Interconnector Owner will provide The Company in writing with:
MW
Rated MW F G
Output
100%
50%
20%
MVAr
A E C D B
LEADING LAGGING
Point A is equivalent (in MVAr) to: 0.95 leading Power Factor at Rated MW output
Point B is equivalent (in MVAr) to: 0.95 lagging Power Factor at Rated MW output
Line F is equivalent (in MVAr) to: Leading Power Factor Reactive Despatch Network Restriction
Line G is equivalent (in MVAr) to: Lagging Power Factor Reactive Despatch Network Restriction
0MW to 150MW
/
151MW to 250MW
/ /
251MW to 300MW
/ /
301MW to 400MW
/ / /
401MW to 450MW
/ / /
451MW to 550MW
/ / / /
Number of units
Power Park Module [unique identifier]
POWER PARK POWER PARK UNITS
UNIT AVAILABILITY
Type A Type B Type C Type D
Description
(Make/Model)
Number of units
The Power Park Module Planning Matrix may have as many columns as are required to provide
information on the different make and model for each type of Power Park Unit in a Power Park Module and
as many rows as are required to provide information on the Power Park Modules within each BM Unit. The
description is required to assist identification of the Power Park Units within the Power Park Module and
correlation with data provided under the Planning Code.
POWER 1st 2nd 3rd 4th 5th 6th 1st 2nd 3rd
GENERATING GT GT GT GT GT GT ST ST ST
MODULE
OUTPUT USABLE
MW
0MW to 150MW
/
151MW to 250MW
/ /
251MW to 300MW
/ /
301MW to 400MW
/ / /
401MW to 450MW
/ / /
451MW to 550MW
/ / / /
NOT USED
NOT USED
CONTENTS
(This contents page does not form part of the Grid Code)
OC5.3 SCOPE
OC5 applies to The Company and to Users, which in OC5 means:
(a) Generators (including those undertaking OTSDUW);
(b) Network Operators;
(c) Non-Embedded Customers;
(d) Suppliers; and
(e) DC Converter Station owners or HVDC Equipment Owners.
OC5.4 MONITORING
OC5.4.1 Parameters To Be monitored
The Company will monitor the performance of:
(a) BM Units against their expected input or output derived from their Final Physical
Notification Data and agreed Bid-Offer Acceptances issued under BC2;
(b) compliance by Users with the CC or ECC as applicable; and
(c) the provision by Users of Ancillary Services which they are required or have agreed to
provide.
OC5.4.2 Procedure For Monitoring
OC5.4.2.1 In the event that a BM Unit fails persistently, in The Company's reasonable view, to follow,
in any material respect, its expected input or output or a User fails persistently to comply with
the CC or ECC as applicable and in the case of response to Frequency, BC3 or to provide
the Ancillary Services it is required, or has agreed, to provide, The Company shall notify the
relevant User giving details of the failure and of the monitoring that The Company has carried
out.
OC5.4.2.2 The relevant User will, as soon as possible, provide The Company with an explanation of the
reasons for the failure and details of the action that it proposes to take to:
(a) enable the BM Unit to meet its expected input or output or to provide the Ancillary
Services it is required or has agreed to provide, within a reasonable period, or
(b) in the case of a Power Generating Module, Generating Unit (excluding a Power Park
Unit), CCGT Module, Power Park Module, OTSUA (prior to the OTSUA Transfer
Time), HVDC Equipment or DC Converter to comply with the CC or ECC as applicable
and in the case of response to Frequency, BC3 or to provide the Ancillary Services it
is required or has agreed to provide, within a reasonable period.
Issue 5 Revision 34 OC5 23 May 2019
4 of 43
OC5.4.2.3 The Company and the User will then discuss the action the User proposes to take and will
endeavour to reach agreement as to:
(a) any short term operational measures necessary to protect other Users; and
(b) the parameters which are to be submitted for the BM Unit and the effective date(s) for
the application of the agreed parameters.
OC5.4.2.4 In the event that agreement cannot be reached within 10 days of notification of the failure by
The Company to the User, The Company or the User shall be entitled to require a test, as
set out in OC5.5 and OC5.6, to be carried out.
OC5.5 PROCEDURE FOR TESTING
OC5.5.1 The Company’s Instruction For Testing
OC5.5.1.1 The Company may at any time (although not normally more than twice in any calendar year
in respect of any particular BM Unit) issue an instruction requiring a User to carry out a test,
provided The Company has reasonable grounds of justification based upon:
(a) a failure to agree arising from the process in CP.8.1 or ECP.8.1; or
(b) monitoring carried out in accordance with OC5.4.2.
OC5.5.1.2 The test, referred to in OC5.5.1.1 and carried out at a time no sooner than 48 hours from the
time that the instruction was issued, on any one or more of the User’s BM Units should only
be to demonstrate that the relevant BM Unit:
(a) if active in the Balancing Mechanism, meets the ability to operate in accordance with its
submitted Export and Import Limits, QPN, Joint BM Unit Data and Dynamic
Parameters and achieve its expected input or output which has been monitored under
OC5.4; and
(b) meets the requirements of the paragraphs in the CC which are applicable to such BM
Units; and
in the case of a BM Unit comprising a Generating Unit, a CCGT Module, a Power Park
Module, a Power Generating Module, HVDC System or a DC Converter meets,
(c) the requirements for operation in Frequency Sensitive Mode and compliance with the
requirements for operation in Limited Frequency Sensitive Mode in accordance with
CC.6.3.3, ECC.6.3.3, CC.6.3.7, ECC.6.3.7, BC3.5.2 and BC3.7.2; or
(d) the terms of the applicable Bilateral Agreement agreed with the Generator to have a
Fast Start Capability; or
(e) the Reactive Power capability registered with The Company under OC2 which shall
meet the requirements set out in CC.6.3.2 or ECC.6.3.2 as applicable. In the case of a
test on a Generating Unit within a CCGT Module the instruction need not identify the
particular CCGT Unit within the CCGT Module which is to be tested, but instead may
specify that a test is to be carried out on one of the CCGT Units within the CCGT Module.
OC5.5.1.3 (a) The instruction referred to in OC5.5.1.1 may only be issued if the relevant User has
submitted Export and Import Limits which notify that the relevant BM Unit is available
in respect of the Operational Day current at the time at which the instruction is issued.
The relevant User shall then be obliged to submit Export and Import Limits with a
magnitude greater than zero for that BM Unit in respect of the time and the duration that
the test is instructed to be carried out, unless that BM Unit would not then be available
by reason of forced outage or Planned Outage expected prior to this instruction.
(b) In the case of a CCGT Module the Export and Import Limits data must relate to the
same CCGT Units which were included in respect of the Operational Day current at the
time at which the instruction referred to in OC5.5.1.1 is issued and must include, in relation
to each of the CCGT Units within the CCGT Module, details of the various data set out
in BC1.A.1.3 and BC1.A.1.5, which parameters The Company will utilise in instructing in
accordance with this OC5 in issuing Bid-Offer Acceptances. The parameters shall
reasonably reflect the true operating characteristics of each CCGT Unit.
Genset.
OC5.5.4.1 The duration of the Dynamic Parameter tests in the above table will be consistent with and
sufficient to measure the relevant expected input or output derived from the Final Physical
Notification Data and Bid-Offer Acceptances issued under BC2 which are still in dispute
following the procedure in OC5.4.2.
OC5.A.1.3.1 The Company accept that the signals specified in OC5.A.1.3(c) may have lower effective
sample rates than those required in CC.6.6.2 although any signals supplied for connection to
The Company’s recording equipment which do not meet at least the sample rates detailed in
CC.6.6.2 should have the actual sample rates indicated to The Company before testing
commences.
OC5.A.1.3.2 For all The Company witnessed testing either;
(i) the Generator or DC Converter Station owner shall provide to The Company all signals
outlined in OC5.A.1.3 direct from the Power Park Module control system without any
attenuation, delay or filtering which would result in the inability to fully demonstrate the
objectives of the test, or identify any potential safety or plant instability issues, and with a
signal update rate corresponding to CC.6.6.2.1; or
Issue 5 Revision 34 OC5 23 May 2019
16 of 43
(ii) in the case of Onshore Power Park Modules the Generator or DC Converter Station
owner shall provide signals OC5.A.1.3(a) direct from one or more transducer(s)
connected to current and voltage transformers for monitoring in real time on site; or,
(iii) In the case of Offshore Power Park Modules and OTSUA signals OC5.A.1.3(a) will be
provided at the Interface Point by the Offshore Transmission Licensee pursuant to the
STC or by the Generator when OTSDUW Arrangements apply.
OC5.A.1.3.3 Options OC5.A.1.3.2 (ii) and (iii) will only be available on condition that;
(a) all signals outlined in OC5.A.1.3 are recorded and made available to The Company by
the Generator or DC Converter Station owner from the Power Park Module or OTSUA
or DC Converter control systems as a download once the testing has been completed;
and
(b) the full test results are provided by the Generator or DC Converter Station owner within
2 working days of the test date to The Company unless The Company agrees otherwise;
and
(c) all data is provided with a sample rate in accordance with CC.6.6.2.2 unless The
Company agrees otherwise; and
(d) in The Company’s reasonable opinion the solution does not unreasonably add a
significant delay between tests or impede the volume of testing which can take place on
the day.
OC5.A.1.3.4 In the case of where transducers connected to current and voltage transformers are installed
(OC5.A.1.3.3 (ii) and (iii)), the transducers shall meet the following specification
(a) The transducer(s) shall be permanently installed to easily allow safe testing at any point
in the future, and to avoid a requirement for recalibration of the current transformers and
voltage transformers.
(b) The transducer(s) should be directly connected to the metering quality current
transformers and voltage transformers or similar.
(c) The transducers shall either have a response time no greater than 50ms to reach 90% of
output, or no greater than 300ms to reach 99.5%.
OC5.A.2.8.5 The recorded results (e.g. Finj, MW and control signals) should be sampled at a minimum rate
of 1 Hz to allow The Company to assess the plant performance from the initial transients
(seconds) to the final steady state conditions (5-15 minutes depending on the plant design).
This is not witnessed by The Company. The Generator shall supply the recordings including
data to The Company in an electronic spreadsheet format. Results shall be legible, identifiable
by labelling, and shall have appropriate scaling.
OC5.A.2.8.7 The tests are divided into the following two types;
(i) Frequency response volume tests as per OC5.A.2.8. Figure 1. These tests consist of
Frequency profile and ramp tests.
(ii) System islanding and step response tests as shown by OC5.A.2.8. Figure 2.
OC5.A.2.8.8 There should be sufficient time allowed between tests for control systems to reach steady
state. Where the diagram states ‘HOLD’ the current injection should be maintained until the
Active Power (MW) output of the Generating Unit or CCGT Module has stabilised. The
frequency response capability test (see Figure 1) injection signal shall be returned to zero at
the same rate at which it was applied. The Company may require repeat tests should the tests
give unexpected results.
0.4
Frequency (Hz)
HOLD
0.2
HOLD
0 10s 30s 60s 10s 10s 10s 0 10s 30s 60s
0
10s 10s 10s
HOLD
-0.2
HOLD
HOLD
-0.4
HOLD
HOLD
-0.6
-0.8
Response (MW)
+
Typical
HF Ramp
HF Ramp
HF Ramp
LF Ramp
LF Ramp
LF Ramp
LF Event
LF Event
Profile 1
Profile 2
+0.5Hz
+0.1Hz
+0.2Hz
-0.2Hz
-0.1Hz
-0.5Hz
Load
Point
MLP6 * * 1 2 3 * 4 *
MLP5 5 * * 6 * * 7 *
MLP4 8 9 10 11 12 13 14 *
MLP3 15 * * * * * 16 17
MLP2 18 * * 19 20 21 * 22
MLP1 23 * * 24 25 * * 26
0.4
Frequency (Hz)
HOLD
HOLD
0.2
0 1s (G) 31s
0 2s (A,J) 32s
0
0 1s 0 30s
HOLD
-0.2 HOLD
-0.4
HOLD HOLD
-0.6
-0.5Hz (K)
-2Hz (A,J)
-0.8
Response (MW)
+
Typical
Load Point +2.0* +0.02 -0.2 +0.2 -0.5 +0.5 +0.6 -0.5 -2.0 + 0**
MLP6 BC1 BC2 L
MLP6 LFSM BC3 BC4
MLP5 A
MLP4 D/E F G H I J M
*
MLP4 LFSM N
MLP3
MLP2
MLP1 K
* This will generally be +2.0Hz unless an injection of this size causes a reduction in plant output
that takes the operating point below Designed Minimum Operating Level in which case an
appropriate injection should be calculated in accordance with the following:
For example 0.9Hz is needed to take an initial output 65% to a final output of 20%. If the initial
output was not 65% and the Designed Minimum Operating Level is not 20% then the
injected step should be adjusted accordingly as shown in the example given below
** Tests L and M in Figure 2 shall be conducted if in this range of tests the system frequency
feedback signal is replaced by the injection signal rather than the injection signal being added
to the system frequency signal. The tests will consist of monitoring the Generating Unit and
CCGT Module in Frequency Sensitive Mode during normal system frequency variations
without applying any injection. Test N in figure 2 shall be conducted in all cases. All three tests
should be conducted for a period of at least 10 minutes.
OC5.A.3.1 Scope
OC5.A.3.1.1 This Appendix outlines the general testing requirements for Power Park Modules and OTSUA
to demonstrate compliance with the relevant aspects of the Grid Code, Ancillary Services
Agreement and Bilateral Agreement and apply only to GB Generators. The testing
requirements applicable to EU Generators are specified in ECP.A.6. The tests specified in
this Appendix will normally be sufficient to demonstrate compliance however The Company
may:
(i) agree an alternative set of tests provided The Company deem the alternative set of tests
sufficient to demonstrate compliance with the Grid Code, Ancillary Services
Agreement and Bilateral Agreement; and/or
(ii) require additional or alternative tests if information supplied to The Company during the
compliance process suggests that the tests in this Appendix will not fully demonstrate
compliance with the relevant section of the Grid Code, Ancillary Services Agreement
or Bilateral Agreement; and/or
(ii) require additional tests if a Power System Stabiliser is fitted; and/or
(iv) agree a reduced set of tests if a relevant Manufacturer's Data & Performance Report
has been submitted to and deemed to be appropriate by The Company; and/or
(v) agree a reduced set of tests for subsequent Power Park Modules or OTSUA following
successful completion of the first Power Park Module or OTSUA tests in the case of a
Power Station comprised of two or more Power Park Modules or OTSUA which The
Company reasonably considers to be identical.
If:
(a) the tests performed pursuant to OC5.A.3.1.1(iv) do not replicate the results contained in
the Manufacturer’s Data & Performance Report or
(b) the tests performed pursuant to OC5.A.3.1.1(v) in respect of subsequent Power Park
Modules or OTSUA do not replicate the full tests for the first Power Park Module or
OTSUA, or
(c) any of the tests performed pursuant to OC5.A.3.1.1(iv) or OC5.A.3.1.1(v) do not fully
demonstrate compliance with the relevant aspects of the Grid Code, Ancillary Services
Agreement and / or Bilateral Agreement,
then notwithstanding the provisions above, the full testing requirements set out in this
Appendix will be applied.
OC5.A.3.1.2 The Generator is responsible for carrying out the tests set out in and in accordance with this
Appendix and the Generator retains the responsibility for the safety of personnel and plant
during the test. The Company will witness all of the tests outlined or agreed in relation to this
Appendix unless The Company decides and notifies the Generator owner otherwise.
Reactive Capability tests may be witnessed by The Company remotely from the The
Company control centre. For all on site The Company witnessed tests the Generator must
ensure suitable representatives from the Generator and / or Power Park Module
manufacturer (if appropriate) and/or OTSUA manufacturer (if appropriate) are available on site
for the entire testing period. In all cases and in addition to any recording of signals conducted
by The Company the Generator shall record all relevant test signals as outlined in OC5.A.1.
OC5.A.3.1.3 In addition to the dynamic signals supplied in OC5.A.1 the Generator shall inform The
Company of the following information prior to the commencement of the tests and any
changes to the following, if any values change during the tests:
(i) All relevant transformer tap numbers; and
(ii) Number of Power Park Units in operation
Voltage
Time
1 tap
10s
minimum
(ii)
Applied
Voltage
2%
Step
1% Time
10s
OC5.A.3.5 Figure 2 – Step injection sequence for voltage control tests
OC.A.3.5.7 In the case of OTSUA where the Bilateral Agreement specifies additional damping
facilities, additional testing to demonstrate these damping facilities may be required.
OC5.A.3.6.5 The recorded results (e.g. Finj, MW and control signals) should be sampled at a minimum rate
of 1 Hz to allow The Company to assess the plant performance from the initial transients
(seconds) to the final steady state conditions (5-15 minutes depending on the plant design).
This is not witnessed by The Company. The Generator shall supply the recordings including
data to The Company in an electronic spreadsheet format. Results shall be legible, identifiable
by labelling, and shall have appropriate scaling.
Full Frequency Response Testing Schedule Witnessed by The Company
OC5.A.3.6.6 The tests are to be conducted at a number of different Module Load Points (MLP). In the case
of a Power Park Module the module load points are conducted as shown below unless agreed
otherwise by The Company.
OC5.A.3.6.7 The tests are divided into the following two types;
Issue 5 Revision 34 OC5 23 May 2019
33 of 43
(i) Frequency response volume tests as per OC5.A.3.6. Figure 1. These tests consist of
frequency profile and ramp tests.
(ii) System islanding and step response tests as shown by OC5.A.3.6 Figure 2
OC5.A.3.6.8 There should be sufficient time allowed between tests for control systems to reach steady state
(depending on available power resource). Where the diagram states ‘HOLD’ the current
injection should be maintained until the Active Power (MW) output of the Power Park Module
has stabilised. All frequency response tests should be removed over the same timescale for
which they were applied. The Company may require repeat tests should the response volume
be affected by the available power, or if tests give unexpected results.
0.6
HOLD
0.4
Frequency (Hz)
HOLD
0.2
HOLD
0 10s 30s 60s 10s 10s 10s 0 10s 30s 60s
0
10s 10s 10s
HOLD
-0.2
HOLD
HOLD
-0.4
HOLD
HOLD
-0.6
-0.8
Response (MW)
+
Typical
HF Ramp
HF Ramp
HF Ramp
LF Ramp
LF Ramp
LF Ramp
LF Event
LF Event
Profile 1
Profile 2
+0.5Hz
+0.1Hz
+0.2Hz
-0.2Hz
-0.1Hz
-0.5Hz
Load
Point
MLP6 * * 1 2 3 * 4 *
MLP5 5 * * 6 * * 7 *
MLP4 8 9 10 11 12 13 14 *
MLP3 15 * * * * * 16 17
MLP2 18 * * 19 20 21 * 22
MLP1 23 * * 24 25 * * 26
HOLD
HOLD
0.2
0 1s (G) 31s
0 2s (A,J) 32s
0
0 1s 0 30s
HOLD
-0.2 HOLD
-0.4
HOLD HOLD
-0.6
-0.5Hz (K)
-2Hz (A,J)
-0.8
Response (MW)
+
Typical
Load Point +2.0* +0.02 -0.2 +0.2 -0.5 +0.5 +0.6 -0.5 -2.0 + 0**
MLP6 BC1 BC2 L
MLP6 LFSM BC3 BC4
MLP5 A
MLP4 D/E F G H I J M
*
MLP4 LFSM N
MLP3
MLP2
MLP1 K
* This will generally be +2.0Hz unless an injection of this size causes a reduction in plant output
that takes the operating point below Designed Minimum Operating Level in which case an
appropriate injection should be calculated in accordance with the following:
For example 0.9Hz is needed to take an initial output 65% to a final output of 20%. If the initial
output was not 65% and the Designed Minimum Operating Level is not 20% then the
injected step should be adjusted accordingly as shown in the example given below
** Tests L and M in Figure 2 shall be conducted if in this range of tests the system frequency
feedback signal is replaced by the injection signal rather than the injection signal being added
to the system frequency signal. The tests will consist of monitoring the Power Park Module
in Frequency Sensitive Mode during normal system frequency variations without applying
any injection. Test N in Figure 2 shall be conducted in all cases. All three tests should be
conducted for a period of at least 10 minutes.
OC5.A.3.7 Fault Ride Through Testing
OC5.A.3.7.1 This section describes the procedure for conducting fault ride through tests on a single Power
Park Unit.
Issue 5 Revision 34 OC5 23 May 2019
35 of 43
OC5.A.3.7.2 The test circuit will utilise the full Power Park Unit with no exclusions (e.g. in the case of a
wind turbine it would include the full wind turbine structure) and shall be conducted with
sufficient resource available to produce at least 95% of the Registered Capacity of the Power
Park Unit. The test will comprise of a number of controlled short circuits applied to a test
network to which the Power Park Unit is connected, typically comprising of the Power Park
Unit transformer and a test impedance to shield the connected network from voltage dips at
the Power Park Unit terminals.
OC5.A.3.7.3 In each case the tests should demonstrate the minimum voltage at the Power Park Unit
terminals or High Voltage side of the Power Park Unit transformer which the Power Park
Unit can withstand for the length of time specified in OC5.A.3.7.5. Any test results provided to
The Company should contain sufficient data pre and post fault in order to determine steady
state values of all signals, and the power recovery timescales.
OC5.A.3.7.4 In addition to the signals outlined in OC5.A.1.2. the following signals from either the Power
Park Unit terminals or High Voltage side of the Power Park Unit transformer should be
provided for this test only:
(i) Phase voltages
(ii) Positive phase sequence and negative phase sequence voltages
(iii) Phase currents
(iv) Positive phase sequence and negative phase sequence currents
(v) Estimate of Power Park Unit negative phase sequence impedance
(vi) MW – Active Power at the generating unit.
(vii) MVAr – Reactive Power at the generating unit.
(viii) Mechanical Rotor Speed
(ix) Real / reactive, current / power reference as appropriate
(x) Fault ride through protection operation (e.g. a crowbar in the case of a doubly fed
induction generator)
(xi) Any other signals relevant to the control action of the fault ride through control deemed
applicable for model validation.
At a suitable frequency rate for fault ride through tests as agreed with The Company.
OC5.A.3.7.5 The tests should be conducted for the times and fault types indicated in OC5.A.3.7 Table 1.
3 Phase Phase to Phase 2 Phase to 1 Phase to Grid Code Ref
Earth Earth
0.14s 0.14s 0.14s 0.14s CC.6.3.15a
0.384s CC.6.3.15b
0.710s
2.5s
180.0s
Voltage
Time
1 tap
>10s
OC5.A.3.8 Figure 1 – Transformer tap sequence for reactive transfer tests
<=10s
Time
Active
Power
10% of
Change
Registered Capacity
OC5.A.4.1.1 This Appendix outlines the general testing requirements for DC Converter Station owners to
demonstrate compliance with the relevant aspects of the Grid Code, Ancillary Services
Agreement and Bilateral Agreement and apply only to DC Converter Station owners. The
testing requirements applicable to HVDC System Owners are specified in ECP.A.7. The tests
specified in this Appendix will normally be sufficient to demonstrate compliance however The
Company may:
(i) agree an alternative set of tests provided The Company deem the alternative set of tests
sufficient to demonstrate compliance with the Grid Code, Ancillary Services
Agreement and Bilateral Agreement; and/or
(ii) require additional or alternative tests if information supplied to The Company during the
compliance process suggests that the tests in this Appendix will not fully demonstrate
compliance with the relevant section of the Grid Code, Ancillary Services Agreement
or Bilateral Agreement; and/or
(iii) require additional tests if control functions to improve damping of power system
oscillations and/or subsynchronous resonance torsional oscillations required by the
Bilateral Agreement or included in the control scheme and active; and/or
(iv) agree a reduced set of tests for subsequent DC Converters following successful
completion of the first DC Converter tests in the case of a Power Station comprised of
two or more DC Converters which The Company reasonably considers to be identical.
If:
(a) the tests performed pursuant to OC5.A.4.1.1(iv) in respect of subsequent DC Converters
do not replicate the full tests for the first DC Converter, or
(b) any of the tests performed pursuant to OC5.A.4.1.1(iv) do not fully demonstrate
compliance with the relevant aspects of the Grid Code, Ancillary Services Agreement
and / or Bilateral Agreement,
then notwithstanding the provisions above, the full testing requirements set out in this
Appendix will be applied.
OC5.A.4.1.2 The DC Converter Station owner is responsible for carrying out the tests set out in and in
accordance with this Appendix and the DC Converter Station owner retains the responsibility
for the safety of personnel and plant during the test. The DC Converter Station owner is
responsible for ensuring that suitable arrangements are in place with the Externally
Interconnected System Operator to facilitate testing. The Company will witness all of the
tests outlined or agreed in relation to this Appendix unless The Company decides and notifies
the DC Converter Station owner otherwise. Reactive Capability tests if required, may be
witnessed by The Company remotely from the The Company control centre. For all on site
The Company witnessed tests the DC Converter Station owner must ensure suitable
representatives from the DC Converter Station owner and / or DC Converter manufacturer
(if appropriate) are available on site for the entire testing period. In all cases and in addition
to any recording of signals conducted by The Company the DC Converter Station owner
shall record all relevant test signals as outlined in OC5.A.1.
OC5.A.4.1.3 In addition to the dynamic signals supplied in OC5.A.1 the DC Converter Station owner shall
inform The Company of the following information prior to the commencement of the tests and
any changes to the following, if any values change during the tests:
(i) All relevant transformer tap numbers.
OC5.A.4.1.4 The DC Converter Station owner shall submit a detailed schedule of tests to The Company
in accordance with CP.6.3.1, and this Appendix.
Voltage
Time
1 tap
>10s
OC5.A.4.3 Figure 1 – Transformer tap sequence for reactive transfer tests
<=10s
Time
Active
Power
10% of
Change
Registered Capacity
Voltage
Time
1 tap
10s
minimum
(ii)
Applied
Voltage
2%
Step
1% Time
10s
OC5.A.4.4 Figure 2 – Step injection sequence for voltage control tests
OC5.A.4.5.5 The recorded results (e.g. Finj, MW and control signals) should be sampled at a minimum rate
of 1 Hz to allow The Company to assess the plant performance from the initial transients
(seconds) to the final steady state conditions (5-15 minutes depending on the plant design).
This is not witnessed by The Company. The DC Converter Station owner shall supply the
recordings including data to The Company in an electronic spreadsheet format. Results shall
be legible, identifiable by labelling, and shall have appropriate scaling.
Full Frequency Response Testing Schedule Witnessed by The Company
OC5.A.4.5.6 The tests are to be conducted at a number of different Module Load Points (MLP). In the case
of a DC Converter the module load points are conducted as shown below unless agreed
otherwise by The Company.
0.6
HOLD
0.4
Frequency (Hz)
HOLD
0.2
HOLD
0 10s 30s 60s 10s 10s 10s 0 10s 30s 60s
0
10s 10s 10s
HOLD
-0.2
HOLD
HOLD
-0.4
HOLD
HOLD
-0.6
-0.8
Response (MW)
+
Typical
HF Ramp
HF Ramp
HF Ramp
LF Ramp
LF Ramp
LF Ramp
LF Event
LF Event
Profile 1
Profile 2
+0.5Hz
+0.1Hz
+0.2Hz
-0.2Hz
-0.1Hz
-0.5Hz
Load
Point
MLP6 * * 1 2 3 * 4 *
MLP5 5 * * 6 * * 7 *
MLP4 8 9 10 11 12 13 14 *
MLP3 15 * * * * * 16 17
MLP2 18 * * 19 20 21 * 22
MLP1 23 * * 24 25 * * 26
0.4
Frequency (Hz)
HOLD
HOLD
0.2
0 1s (G) 31s
0 2s (A,J) 32s
0
0 1s 0 30s
HOLD
-0.2 HOLD
-0.4
HOLD HOLD
-0.6
-0.5Hz (K)
-2Hz (A,J)
-0.8
Response (MW)
+
Typical
Load Point +2.0* +0.02 -0.2 +0.2 -0.5 +0.5 +0.6 -0.5 -2.0 + 0**
MLP6 BC1 BC2 L
MLP6 LFSM BC3 BC4
MLP5 A
MLP4 D/E F G H I J M
*
MLP4 LFSM N
MLP3
MLP2
MLP1 K
* This will generally be +2.0Hz unless an injection of this size causes a reduction in plant output
that takes the operating point below Designed Minimum Operating Level in which case an
appropriate injection should be calculated in accordance with the following:
For example 0.9Hz is needed to take an initial output 65% to a final output of 20%. If the initial
output was not 65% and the Designed Minimum Operating Level is not 20% then the
injected step should be adjusted accordingly as shown in the example given below
** Tests L and M in Figure 2 shall be conducted if in this range of tests the system frequency
feedback signal is replaced by the injection signal rather than the injection signal being added
to the system frequency signal. The tests will consist of monitoring the DC Converter in
Frequency Sensitive Mode during normal system frequency variations without applying any
injection. Test N in Figure 2 shall be conducted in all cases. All three tests should be conducted
for a period of at least 10 minutes.
DEMAND CONTROL
CONTENTS
(This contents page does not form part of the Grid Code)
OC6.1.6 Connections between Large Power Stations and the National Electricity Transmission
System and between such Power Stations and a User System will not, as far as possible, be
disconnected by The Company pursuant to the provisions of OC6 insofar as that would interrupt
supplies
(a) for the purposes of operation of the Power Station (including Start-Up and shutting down);
(b) for the purposes of keeping the Power Station in a state such that it could be Started-up
when it is off-Load for ordinary operational reasons; or
(c) for the purposes of compliance with the requirements of a Nuclear Site Licence.
Demand Control pursuant to this OC6 therefore applies subject to this exception.
OC6.3 SCOPE
OC6.3.1 OC6 applies to The Company and to Users which in OC6 means:
(a) Generators; and
(b) Network Operators.
It also applies to The Company in relation to Non-Embedded Customers.
OC6.3.2 Explanation
OC6.3.2.1 (a) Although OC6 does not apply to Suppliers, the implementation of Demand Control may
affect their Customers.
(b) In all situations envisaged in OC6, Demand Control is exercisable:
(i) by reference to a Network Operator's System; or
(ii) by The Company in relation to Non-Embedded Customers.
(c) Demand Control in all situations relates to the physical organisation of the Total System,
and not to any contractual arrangements that may exist.
OC6.3.2.2 (a) Accordingly, Demand Control will be exercisable with reference to, for example, five per
cent (or such other figure as may be utilised under OC6.5) tranches of Demand by a
Network Operator.
(b) For a Supplier, whose Customers may be spread throughout a number of User Systems
(and the National Electricity Transmission System), to split its Customers into five per
cent (or such other figure as may be utilised under OC6.5) tranches of Demand would not
result in Demand Control being implemented effectively on the Total System.
(c) Where Demand Control is needed in a particular area, The Company would not know
which Supplier to contact and (even if it were to) the resulting Demand Control
implemented, because of the diversity of contracts, may well not produce the required
result.
OC6.3.2.3 (a) Suppliers should note, however, that, although implementation of Demand Control in
respect of their Customers is not exercisable by them, their Customers may be affected by
Demand Control.
each Network Operator will abide by the instructions of The Company, which
should specify whether a voltage reduction or Demand Disconnection stage is
required; or
(iii) if the instruction relates to less than 20 per cent of its total Demand, is in four
Demand Disconnection stages each of which can reasonably be expected to
deliver between four and six per cent Demand reduction,
each Network Operator will abide by the instructions of The Company with regard to
Demand reduction under OC6.5 without delay.
(b) The Demand reduction must be achieved within the Network Operator's System as far as
possible uniformly across all Grid Supply Points (unless otherwise specified in the
National Electricity Transmission System Warning - High Risk of Demand Reduction)
either by Customer voltage reduction or by Demand Disconnection.
(c) Demand Control initiated by voltage reduction shall be initiated as soon as possible but in
any event no longer than two minutes from the instruction being received from The
Company, and completed within 10 minutes of the instruction being received from The
Company.
(d) Demand Control initiated by Demand Disconnection shall be initiated as soon as possible
but in any event no longer than two minutes from the instruction being received from The
Company, and completed within five minutes of the instruction being received from The
Company.
(e) Each Network Operator must notify The Company in writing by calendar week 24 each
year, for the succeeding Financial Year onwards, whether Demand Control is to be
implemented either:
together with the magnitude of the voltage reduction stages (where applicable) and for
Demand Disconnection stages, the demand reduction anticipated. Thereafter, any
Issue 5 Revision 32 0C6 1 April 2019
6 of 12
changes must be notified in writing to The Company at least 10 Business Days prior to the
change coming into effect.
OC6.5.4 (a) Where The Company wishes to instruct a Demand reduction of more than 20 per cent of a
Network Operator's Demand (measured at the time the Demand reduction is required), it
shall, if it is able, issue a National Electricity Transmission System Warning - High Risk
of Demand Reduction to the Network Operator by 1600 hours on the previous day. The
warning will state the percentage level of Demand reduction that The Company may want
to instruct (measured at the time the Demand reduction is required).
(b) The National Electricity Transmission System Warning - High Risk of Demand
Reduction will specify the percentage of Demand reduction that The Company may
require in integral multiples of the percentage levels notified by Users under OC6.5.3(c) up
to (and including) 20 per cent and of five per cent above 20 per cent and will not relate to
more than 40 per cent of Demand (measured at the time the Demand reduction is
required) of the Demand on the User System of a Network Operator.
(c) If The Company has issued the National Electricity Transmission System Warning -
High Risk of Demand Reduction by 1600 hours on the previous day, on receipt of it the
relevant Network Operator shall make available the percentage reduction in Demand
specified for use within the period of the National Electricity Transmission System
Warning.
(d) If The Company has not issued the National Electricity Transmission System Warning -
High Risk of Demand Reduction by 1600 hours the previous day, but after that time, the
Network Operator shall make available as much of the required Demand reduction as it is
able, for use within the period of the National Electricity Transmission System Warning.
OC6.5.5 (a) If The Company has given a National Electricity Transmission System Warning - High
Risk of Demand Reduction to a Network Operator, and has issued it by 1600 hours on
the previous day, it can instruct the Network Operator to reduce its Demand by the
percentage specified in the National Electricity Transmission System Warning.
(b) The Company accepts that if it has not issued the National Electricity Transmission
System Warning - High Risk of Demand Reduction by 1600 hours on the previous day
or if it has issued it by 1600 hours on the previous day, but it requires a further percentage
of Demand reduction (which may be in excess of 40 per cent of the total Demand on the
User System of the Network Operator (measured at the time the Demand reduction is
required) from that set out in the National Electricity Transmission System Warning, it
can only receive an amount that can be made available at that time by the Network
Operator.
(c) Other than with regard to the proviso, the provisions of OC6.5.3 shall apply to those
instructions.
OC6.5.6 Once a Demand reduction has been applied by a Network Operator at the instruction of The
Company, the Network Operator may interchange the Customers to whom the Demand
reduction has been applied provided that,
(i) the percentage of Demand reduction at all times within the Network Operator's System
does not change; and
(ii) at all times it is achieved within the Network Operator's System as far as possible
uniformly across all Grid Supply Points (unless otherwise specified in the National
Electricity Transmission System Warning - High Risk of Demand Reduction if one has
been issued),
until The Company instructs that Network Operator in accordance with OC6.
Notes:
1. Data to be provided annually by week 24 to cover the following year.
OPERATIONAL LIAISON
CONTENTS
(This contents page does not form part of the Grid Code)
OC7.2 OBJECTIVE
The objectives of OC7 are:
OC7.2.1 To provide for the exchange of information so that the implications of an Operation and/or
Event can be considered, possible risks arising from it can be assessed and appropriate action
taken by the relevant party in order to maintain the integrity of the Total System. OC7 does not
seek to deal with any actions arising from the exchange of information, but merely with that
exchange.
OC7.2.2 To provide for types of National Electricity Transmission System Warnings which may be
issued by The Company.
OC7.2.3 To provide the framework for the information flow and discussion between The Company and
certain Users in relation to Integral Equipment Tests.
OC7.2.4 To provide the procedure to be followed in respect of Operational Switching
OC7.3.1 OC7 applies to The Company and to Users, which in OC7 means:
(a) Generators (other than those which only have Embedded Small Power Stations or
Embedded Medium Power Stations) and including Generators undertaking OTSDUW;
(b) Network Operators;
(c) Non-Embedded Customers;
(d) Suppliers (for the purposes of National Electricity Transmission System Warnings);
(e) Externally Interconnected System Operators (for the purposes of National Electricity
Transmission System Warnings); and
(f) DC Converter Station owners and HVDC System Owners.
The procedure for operational liaison by The Company with Externally Interconnected
System Operators is set out in the Interconnection Agreement with each Externally
Interconnected System Operator.
OC7.6 also applies to Relevant Transmission Licensees.
OC7.4 PROCEDURE
OC7.4.1 The term "Operation" means a scheduled or planned action relating to the operation of a
System (including an Embedded Power Station).
OC7.4.2 The term "Event" means an unscheduled or unplanned (although it may be anticipated)
occurrence on, or relating to, a System (including an Embedded Power Station) including,
without limiting that general description, faults, incidents and breakdowns and adverse weather
conditions being experienced.
OC7.4.3 The term "Operational Effect" means any effect on the operation of the relevant other System
which causes the National Electricity Transmission System or the Systems of the other User
or Users, as the case may be, to operate (or be at a materially increased risk of operating)
differently to the way in which they would or may have normally operated in the absence of that
effect.
OC7.4.4 References in this OC7 to a System of a User or User's System shall not include Embedded
Small Power Stations or Embedded Medium Power Stations, unless otherwise stated.
OC7.4.5 Requirement To Notify Operations
OC7.4.5.1 Operation On The National Electricity Transmission System
In the case of an Operation on the National Electricity Transmission System, which will have
(or may have) an Operational Effect on the System(s) of a User or Users, The Company will
notify the User or Users whose System(s) will, or may, in the reasonable opinion of The
Company, be affected, in accordance with OC7.
OC7.4.5.2 Operation On a User's System
In the case of an Operation on the System of a User which will have (or may have) an
Operational Effect on the National Electricity Transmission System (including an equivalent
to an Operation on the equivalent of a System of a User or other person connected to that
User's System which, via that User System, will or may have an Operational Effect on the
National Electricity Transmission System), the User will notify The Company in accordance
with OC7. Following notification by the User, The Company will notify any other User or Users
on whose System(s) the Operation will have, or may have, in the reasonable opinion of The
Company, an Operational Effect, in accordance with OC7 and will notify any Externally
Interconnected System Operator on whose System the Operation will have, or may have, in
the reasonable opinion of The Company, an Operational Effect, if it is required to do so by the
relevant Interconnection Agreement.
Issue 5 Revision 32 OC7 1 April 2019
4 of 200
OC7.4.5.3 Examples Of Situations Where Notification By The Company Or a User may be Required
Whilst in no way limiting the general requirement to notify in advance set out in OC7.4.5.1 and
OC7.4.5.2, the following are examples of situations where notification in accordance with
OC7.4.5 will be required if they will, or may, have an Operational Effect:
(a) the implementation of a planned outage of Plant and/or Apparatus which has been
arranged pursuant to OC2;
(b) the operation (other than, in the case of a User, at the instruction of The Company) of any
circuit breaker or isolator/disconnector or any sequence or combination of the two; or
(c) voltage control.
OC7.4.5.4 Operations Caused By Another Operation Or By An Event
An Operation may be caused by another Operation or an Event on another's System
(including an Embedded Power Station) (or by the equivalent of an Event or Operation on the
System of an Externally Interconnected System Operator or Interconnector User) and in
that situation the information to be notified is different to that where the Operation arose
independently of any other Operation or Event, as more particularly provided in OC7.4.5.6.
OC7.4.5.5 Form
A notification and any response to any questions asked under OC7.4.5, of an Operation which
has arisen independently of any other Operation or of an Event, shall be of sufficient detail to
describe the Operation (although it need not state the cause) and to enable the recipient of the
notification reasonably to consider and assess the implications and risks arising (provided that, in
the case of an Operation on a User's System which The Company is notifying to other Users
under OC7.4.5.2, The Company will only pass on what it has been told by the User which has
notified it) and will include the name of the individual reporting the Operation on behalf of The
Company or the User, as the case may be. The recipient may ask questions to clarify the
notification and the giver of the notification will, insofar as it is able, answer any questions raised,
provided that, in the case of an Operation on a User's System which The Company is
notifying to other Users under OC7.4.5.2, in answering any question, The Company will not
pass on anything further than that which it has been told by the User which has notified it. The
Company may pass on the information contained in the notification as provided in OC7.4.5.6.
OC7.4.5.6 (a) A notification by The Company of an Operation under OC7.4.5.1 which has been caused
by another Operation (the "first Operation") or by an Event on a User's System, will
describe the Operation and will contain the information which The Company has been
given in relation to the first Operation or that Event by the User. The notification and any
response to any questions asked (other than in relation to the information which The
Company is merely passing on from a User) will be of sufficient detail to enable the
recipient of the notification reasonably to consider and assess the implications and risks
arising from the Operation on the National Electricity Transmission System and will
include the name of the individual reporting the Operation on behalf of The Company. The
recipient may ask questions to clarify the notification and The Company will, insofar as it is
able, answer any questions raised, provided that in relation to the information which The
Company is merely passing on from a User, in answering any question The Company will
not pass on anything further than that which it has been told by the User which has notified
it.
(b) Where a User is reporting an Operation or an Event which itself has been caused by an
incident or scheduled or planned action affecting (but not on) its System, the notification to
The Company will contain the information which the User has been given by the person
connected to its System in relation to that incident or scheduled or planned action (which
the User must require, contractually or otherwise, the person connected to its System to
give to it) and The Company may pass on the information contained in the notification as
provided in this OC7.4.5.6.
NATIONAL ELECTRICITY OC7.4.8.5 Fax or Generators, Network All timescales when Insufficient generation Offers of increased availability from
TRANSMISSION other Suppliers, Operators, Non- at the time there is available to meet forecast Generators or DC Converter Station
WARNING – electronic Externally Interconected Embedded not a high risk of Demand plus Operating owners. HVDC System Owners and
ELECTRICITY MARGIN means System Operators, DC Customers Demand reduction. Margin. Interconnector Users.
Issue 5 Revision 32
NOTICE Converter Station owners
and HVDC System Primarily 1200 hours Notification that if not Suppliers notify The Company of any
Owners onwards for a future improved Demand additional Customer Demand
period. reduction may be Management that they will initiate.
instructed.
NATIONAL ELECTRICITY OC7.4.8.6 Fax or Generators, All timescales where Insufficient generation Offers of increased availability from
TRANSMISSION other Suppliers, there is a high risk of available to meet forecast Generators or DC Converter Station
SYSTEM WARNING – electronic Network Operators, Demand Reduction. Demand plus Operating owners or HVDC Syustem Owners
High risk of Demand means Non-Embedded Margin and/or a high risk of and Interconnector Users.
Reduction Customers, Primarily 1200 hours Demand Reduction being
Externally Interconnected onwards for a future instructed. Suppliers notify The Company of any
System Operators, DC period additional Customer Demand
Converter Station Owners, (May be issued locally as Management that they will initiate.
HVDC System Owners demand reduction risk only
for circuit overloads) Specified Network Operators and
Non-Embedded Customers to
OC7
prepare their Demand Reduction
20 of 200
arrangements and take actions as
necessary to enable compliance with
The Company instructions that may
follow.
WARNINGS TABLE
NATIONAL ELECTRICITY OC7.4.8.8 Fax/Teleph Generators, DC Converter Suppliers Control room time Risk of, widespread system Recipients take steps to warn
TRANSMISSION one or Station owners, HVDC scales disturbance to whole or part operational staff and maintain plant or
SYSTEM WARNING – other System Owners, of the National Electricity apparatus such that they are best
Risk of System electronic Network Operators, Non- Transmission System able to withstand the disturbance.
Disturbance means Embedded Customers,
Externally Interconnected
APPENDIX 1 - NATIONAL ELECTRICITY TRANSMISSION SYSTEM
1 April 2019
OPERATING CODE NO. 8
(OC8)
SAFETY CO-ORDINATION
CONTENTS
(This contents page does not form part of the Grid Code)
OC8.2 OBJECTIVE
OC8.2.1 The objective of OC8 is to achieve:
(i) Safety From The System when work on or near a System necessitates the provision
of Safety Precautions on another System on HV Apparatus up to a Connection
Point; and
(ii) Safety From The System when work is to be carried out at a User’s Site or a
Transmission Site (as the case may be) on equipment of the User or a Relevant
Transmission Licensee (as the case may be) where the work or equipment is near to
HV Apparatus on the Implementing Safety Co-ordinator’s System.
OC8.3 SCOPE
OC8.3.1 OC8 applies to The Company and to Users, which in OC8 means:
(a) Generators (including where undertaking OTSDUW);
(b) Network Operators; and
(c) Non-Embedded Customers.
OC8 also applies to Relevant Transmission Licensees.
The procedures for the establishment of safety co-ordination by The Company in relation to
External Interconnections are set out in Interconnection Agreements with relevant
persons for the External Interconnections.
OC8.4 PROCEDURE
OC8.4.1 Safety Co-Ordination In Respect Of The E&W Transmission Systems Or The Systems Of
E&W Users
OC8.4.1.1 OC8 Appendix 1, OC8A, applies when work is to be carried out on or near to the E&W
Transmission System or the Systems of E&W Users or when Safety Precautions are
required to be established on the E&W Transmission System or the Systems of E&W
Users when work is to be carried out on or near to the Scottish Transmission System or
the Systems of Scottish Users.
CONTENTS
(This contents page does not form part of the Grid Code)
OC8A.2 OBJECTIVE
OC8A.2.1 The objective of OC8A is to achieve:-
(i) Safety From The System when work on or near a System necessitates the provision
of Safety Precautions on another System on HV Apparatus up to a Connection
Point (or, in the case of OTSUA, Transmission Interface Point); and
OC8A.4 PROCEDURE
OC8A.4.1 Approval Of Local Safety Instructions
OC8A.4.1.1 (a) In accordance with the timing requirements of its Bilateral Agreement, each E&W
User will supply to the Relevant E&W Transmission Licensee a copy of its Local
Safety Instructions relating to its side of the Connection Point at each Connection
Site, or in the case of OTSUA a copy of its Local Safety Instructions relating to its
side of the Transmission Interface Point at each Transmission Interface Site.
(b) In accordance with the timing requirements of each Bilateral Agreement, the Relevant
E&W Transmission Licensee will supply to each E&W User a copy of its Local Safety
Instructions relating to the Transmission side of the Connection Point at each
Connection Site, or in the case of OTSUA a copy of its Local Safety Instructions
relating to the Transmission side of the Transmission Interface Point at each
Transmission Interface Site.
(c) Prior to connection the Relevant E&W Transmission Licensee and the E&W User
must have approved each other's relevant Local Safety Instructions in relation to
Isolation and Earthing.
OC8A.4.1.2 Either party may require that the Isolation and/or Earthing provisions in the other party’s
Local Safety Instructions affecting the Connection Site (or, in the case of OTSUA,
Transmission Interface Site) should be made more stringent in order that approval of the
other party’s Local Safety Instructions can be given. Provided these requirements are not
unreasonable, the other party will make such changes as soon as reasonably practicable.
These changes may need to cover the application of Isolation and/or Earthing at a place
remote from the Connection Site (or, in the case of OTSUA, Transmission Interface Site),
depending upon the System layout. Approval may not be withheld because the party
required to approve reasonably believes the provisions relating to Isolation and/or Earthing
are too stringent.
OC8A.4.1.3 If, following approval, a party wishes to change the provisions in its Local Safety
Instructions relating to Isolation and/or Earthing, it must inform the other party. If the
change is to make the provisions more stringent, then the other party merely has to note the
changes. If the change is to make the provisions less stringent, then the other party needs to
approve the new provisions and the procedures referred to in OC8A.4.1.2 apply.
RISSP NUMBER
PART 1
Safety Precautions have been established by the Implementing Safety Co-ordinator (or by another User on that User's
System connected to the Implementing Safety Co-ordinator's System) to achieve (in so far as it is possible from that side of
the Connection Point/Transmission Interface Point) Safety From The System on the following HV Apparatus on the
Requesting Safety Co-ordinator's System: [State identity - name(s) and, where applicable, identification of the HV circuit(s)
up to the Connection Point/Transmission Interface Point]:
______________________________________________________________________________________________
______________________________________________________________________________________________
Further Safety precautions required on the Requesting Safety Co-ordinator’s System as notified by the Implementing
Safety Co-ordinator.
______________________________________________________________________________________________
(a) ISOLATION
[State the Location(s) at which Isolation has been established (whether on the Implementing Safety Co-ordinator's System
or on the System of another User connected to the Implementing Safety Co-ordinator's System). For each Location,
identify each point of Isolation. For each point of Isolation, state the means by which the Isolation has been achieved, and
whether, immobilised and Locked, Caution Notice affixed, other safety procedures applied, as appropriate.]
______________________________________________________________________________________________
______________________________________________________________________________________________
______________________________________________________________________________________________
(b) EARTHING
[State the Location(s) at which Earthing has been established (whether on the Implementing Safety Co-ordinator's System
or on the System of another User connected to the Implementing Safety Co-ordinator's System). For each Location,
identify each point of Earthing. For each point of Earthing, state the means by which Earthing has been achieved, and
whether, immobilised and Locked, other safety procedures applied, as appropriate].
______________________________________________________________________________________________
______________________________________________________________________________________________
______________________________________________________________________________________________
1.3 ISSUE
2.1 CANCELLATION
Safety Precautions have been established by the Implementing Safety Co-ordinator (or by another User on that User's
System connected to the Implementing Safety Co-ordinator's System) to achieve (in so far as it is possible from that side of
the Connection Point/Transmission Interface Point) Safety From The System on the following HV Apparatus on the
Requesting Safety Co-ordinator's System: [State identity - name(s) and, where applicable, identification of the HV circuit(s)
up to the Connection Point/Transmission Interface Point]:
______________________________________________________________________________________________
______________________________________________________________________________________________
Recording of notification given to the Requesting Safety Co-ordinator concerning further Safety Precautions required on the
Requesting Safety Co-ordinator’s System.
(a) ISOLATION
[State the Location(s) at which Isolation has been established (whether on the Implementing Safety Co-ordinator's System
or on the System of another User connected to the Implementing Safety Co-ordinator's System). For each Location,
identify each point of Isolation. For each point of Isolation, state the means by which the Isolation has been achieved, and
whether, immobilised and Locked, Caution Notice affixed, other safety procedures applied, as appropriate.]
______________________________________________________________________________________________
______________________________________________________________________________________________
______________________________________________________________________________________________
(b) EARTHING
[State the Location(s) at which Earthing has been established (whether on the Implementing Safety Co-ordinator's System
or on the System of another User connected to the Implementing Safety Co-ordinator's System). For each Location,
identify each point of Earthing. For each point of Earthing, state the means by which Earthing has been achieved, and
whether, immobilised and Locked, other safety procedures applied, as appropriate].
______________________________________________________________________________________________
______________________________________________________________________________________________
______________________________________________________________________________________________
1.3 ISSUE
2.1 CANCELLATION
l have received confirmation from _________________________________________ (name of the Requesting Safety Co-
ordinator) at ________________________________________ (location) that the Safety Precautions set out in paragraph 1.2
are no longer required and accordingly the RISSP is cancelled.
NGSC Number:
NGET Safety Circular (NGSC) ..........................
Date:
RISSP prefixes - Issue x Issued By:
Example
Pursuant to the objectives of The Grid Code, Operating Code 8A1 - Safety Co-ordination, this circular will be
used in relation to all cross boundary safety management issues with the Relevant E&W Transmission
Licensee customers. Of particular note will be the agreed prefixes for the Record of Inter System Safety
Precautions (RISSP) documents.
Equipment Identification………………………………….………………………………………………………………………
………………………………………………………………………………………………………………………………………
Work to be done
………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………
Primary Earths
………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………
Actions taken to avoid Danger by draining, venting, purging and containment or dissipation of stored energy*
………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………
Further precautions to be taken during the course of the work to avoid System derived hazards*
………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………
State whether this Permit for Work must be personally retained yes no
Issued (Signed)
Competent Person
CONTENTS
(This contents page does not form part of the Grid Code)
OC8B.2 OBJECTIVE
OC8B.2.1 The objective of OC8B is to achieve:-
(i) Safety From The System when work on or near a System necessitates the provision of
Safety Precautions on another System on HV Apparatus up to a Connection Point
(or, in the case of OTSUA, Transmission Interface Point); and
(ii) Safety From The System when work is to be carried out at a Scottish User’s Site or a
Transmission Site (as the case may be) on equipment of the Scottish User or the
Relevant Scottish Transmission Licensee (as the case may be) where the work or
equipment is near to HV Apparatus on the Implementing Safety Co-ordinator’s
System.
OC8B.2.2 A flow chart, set out in OC8B Appendix C, illustrates the process utilised in OC8B to achieve
the objective set out in OC8B.2.1. In the case of a conflict between the flow chart and the
provisions of the written text of OC8B, the written text will prevail.
OC8B.3 SCOPE
OC8B.3.1 OC8B applies to The Company, Relevant Scottish Transmission Licensees and to
Scottish Users, which in OC8 means:-
(a) Generators (including where undertaking OTSDUW);
(b) Network Operators; and
(c) Non-Embedded Customers.
The procedures for the establishment of safety co-ordination by The Company in relation to
External Interconnections are set out in Interconnection Agreements with relevant
persons for the External Interconnections.
OC8B.4 PROCEDURE
OC8B.4.1 Approval Of Safety Rules
OC8B.4.1.1 (a) In accordance with the timing requirements of its Bilateral Agreement, each Scottish
User will supply to the Relevant Scottish Transmission Licensee a copy of its Safety
Rules relating to its side of the Connection Point at each Connection Site or in the
case of OTSUA a copy of its Local Safety Instructions relating to its side of the
Transmission Interface Point at each Transmission Interface Site.
(b) In accordance with the timing requirements of each Bilateral Agreement the Relevant
Scottish Transmission Licensee will supply to each Scottish User a copy of its
Safety Rules relating to the Transmission side of the Connection Point at each
Connection Site or in the case of OTSUA a copy of its Local Safety Instructions
relating to the Transmission side of the Transmission Interface Point at each
Transmission Interface Site.
(c) Prior to connection the Relevant Scottish Transmission Licensee and the Scottish
User must have approved each other’s relevant Safety Rules in relation to Isolation
and Earthing.
Part 1
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
(a) ISOLATION
State the Locations(s) at which Isolation has been established on the Implementing
Safety Co-ordinator's System. For each Location, identify each point of Isolation. For
each point of Isolation state, the means by which the Isolation has been achieved, and
whether, immobilised and Locked, Caution Notice affixed, other Safety Precautions
applied, as appropriate.
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
State the Locations(s) at which Earthing has been established on the Implementing
Safety Co-ordinator's System. For each Location, identify each point of Earthing. For
each point of Earthing state, the means by which the Earthing has been achieved, and
whether, immobilised and Locked, other Safety Precautions applied, as appropriate.
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
1.3 ISSUE
PART 2
2.1 CANCELLATION
PART 1
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
(a) ISOLATION
State the Location(s) at which isolation has been established on the Implementing
Safety Co-ordinator's System. For each Location, identify each point of Isolation. For
each point of Isolation state, the means by which the Isolation has been achieved, and
whether, immobilised and Locked, Caution Notice affixed, other Safety Precautions
applied, as appropriate.
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
State the Location(s) at which Earthing has been established on the Implementing
Safety Co-ordinator's System. For each Location, identify each point of Earthing. For
each point of Earthing state, the means by which the Earthing has been achieved, and
whether, immobilised and Locked, other Safety Precautions applied, as appropriate.
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
1.3 ISSUE
PART 2
2.1 CANCELLATION
Not Used
1. ISSUE
To …………………………………………………………………………..………………….……………………………..
The following High Voltage Apparatus has been made safe in accordance with the Operational Safety Rules for the work detailed on
this Permit-to-Work to proceed:
……………………………………………………………………………………..……………………………………….……..….
……………………………………………………………………………………..……………………………………….……..….
……………………………………………………………………………………..……………………………………….……..….
……………………………………………………………………………………..……………………………………….……..….
……………………………………………………………………………………..……………………………………….……..….
……………………………………………………………………………………..……………………………………….……..….
Other precautions (see Operational Safety Rules 3.2.1(b), 4.6.2(c) and 5.5.3), and any special instructions:
……………………………………………………………………………………..……………………………………….……..….
……………………………………………………………………………………..……………………………………….……..….
……………………………………………………………………………………..……………………………………….……..….
……………………………………………………………………………………..……………………………………….……..….
……………………………………………………………………………………..……………………………………….……..….
……………………………………………………………………………………..……………………………………….……..….
Circuit Identification Issued: Colour …...…………. No. of wristlets …….………..… No. of step bolts ………..………
_____________________________________________________________________________________________
2. RECEIPT
I accept responsibility for carrying out the work on the Apparatus detailed on this Permit-to-Work, applying additional earths as
necessary. No attempt will be made by me, or by the persons under my charge, to work on any other Apparatus.
_____________________________________________________________________________________________
3. CLEARANCE
All persons under my control have been withdrawn and warned that it is no longer safe to work on the Apparatus detailed on this
Permit-to Work.
All gear, tools and additional earths have/have not* been removed. The works is/is not* complete.
_____________________________________________________________________________________________
4. CANCELLATION
………………………………………………………………………………………….………………………………...
………………………………………………….…………………………………………………………………………
……………………………………………………….…………………………………………………………………...
……………………………………………………….…………………………………………………………………...
……………………………………………………….…………………………………………………………………...
_____________________________________________________________________________________________
2. (i) PRECAUTIONS TAKEN TO ACHIEVE SAFETY FROM THE SYSTEM: State points at which Plant/Apparatus has been
Isolated and specify position(s) of Earthing Devices applied. State actions taken to avoid Danger by draining, venting,
purging and containment or dissipation of stored energy.
…………………………………………….………………………………………………………………….………….
…………………………………………….………………………………………………………………….………….
…………………………………………….………………………………………………………………….………….
…………………………………………….………………………………………………………………….………….
…………………………………………….………………………………………………………………….………….
…………………………………………….………………………………………………………………….………….
…………………………………………….………………………………………………………………….………….
…………………………………………….………………………………………………………………….………….
…………………………………………….………………………………………………………………….………….
(ii) FURTHER PRECAUTIONS TO BE TAKEN DURING THE COURSE OF WORK TO AVOID SYSTEM DERIVED HAZARDS
…………………………………………….………………………………………………………………….………….
…………………………………………….………………………………………………………………….………….
…………………………………………….………………………………………………………………….………….
…………………………………………….………………………………………………………………….………….
…………………………………………….………………………………………………………………….………….
This Permit for Work must only be transferred under the Personal Supervision of a Senior Authorised
Person* ………………………………………..
Signed …………………………………………. being a Senior Authorised Person. Time: ……….. Date: …………….
____________________________________________________________________________________________
3. ISSUE
(i) Key Safe Key (No.)* …..….. (ii) Earthing Schedule* …….... (iii) Portable Drain Earths (No. off)* ………………
(iv) Selected Person’s Report (No.)* ………………….. (v) Circuit Identification Flags (No. off)* ……………………
for the issue of this Permit for Work Time: ……… Date: ………………
4. RECEIPT
I understand and accept my responsibilities under the ScottishPower Safety Rules as recipient of this Permit for Work and
acknowledge receipt of the items in Section 3.
being a Competent Person in the employ of Firm/Dept …………………………………… Time ………. Date …………
_____________________________________________________________________________________________
TRANSFER RECORD
†Signature of Person receiving re-issued Document in accordance with conditions detailed in Section 4.
_____________________________________________________________________________________________
5. CLEARANCE: I certify that all persons working under this Permit for Work have been withdrawn from, and warned not to work
on, the Plant/Apparatus in Section 1. All gears, tools, Drain Earths and loose material have been removed and guards and
access doors have been replaced, except for:
…………………………………………….………………………………………………………………….…………………
…………………………………………….………………………………………………………………….…………………
…………………………………………….………………………………………………………………….…………………
_____________________________________________________________________________________________
6. CANCELLATION: I certify that all items issued under Section 3 have been accounted for and the Control
_____________________________________________________________________________________________
CONTINGENCY PLANNING
CONTENTS
(This contents page does not form part of the Grid Code)
OC9.2 OBJECTIVE
The overall objectives of OC9 are:
OC9.2.1 To achieve, as far as possible, restoration of the Total System and associated Demand in
the shortest possible time, taking into account Power Station capabilities, including
Embedded Generating Units, External Interconnections and the operational constraints
of the Total System.
OC9.2.2 To achieve the Re-Synchronisation of parts of the Total System which have become Out
of Synchronism with each other.
OC9.2.3 To ensure that communication routes and arrangements are available to enable senior
management representatives of The Company and Users, who are authorised to make
binding decisions on behalf of The Company or the relevant User, as the case may be, to
communicate with each other in the situation described in OC9.1.3.
OC9.2.4 To describe the role that in respect of Transmission Systems, Relevant Transmission
Licensees may have in the restoration processes as detailed in the relevant OC9 De-
Synchronised Island Procedures and Local Joint Restoration Plans.
OC9.3 SCOPE
OC9.3.1 OC9 applies to The Company and to Users, which in OC9 means:-
(a) Generators;
(b) Network Operators; and
(c) Non-Embedded Customers.
OC9.3.2 The procedure for the establishment of emergency support/contingency planning between
The Company and Externally Interconnected System Operators is set out in the
Interconnection Agreement with each Externally Interconnected System Operator.
OC9.3.3 In respect of Transmission Systems, OC9.4 and OC9.5 also apply to Relevant
Transmission Licensees.
Following determination by The Company pursuant to its obligations under the BSC that the
Market Suspension Threshold has been met, or deemed to have been met, The
Company shall (as soon as practicable) inform the BSCCo of that time and date at which
the Market Suspension Threshold was met, or deemed to have been met, and the BSCCo
will determine the Settlement Period in accordance with the provisions of the BSC with
effect from which the Balancing Mechanism will be suspended.
Should The Company determine that the Total System is capable of returning to normal
operation without meeting the Market Suspension Threshold, The Company will follow the
procedure given in OC9.4.7.9.
The Black Start will conclude with effect from the time and date determined in accordance
with OC9.4.7.10.
In respect of Scottish Transmission Systems, in exceptional circumstances, as specified in
the Local Joint Restoration Plan, SPT or SHETL, may invoke such Local Joint
Restoration Plan for its own Transmission System and Scottish Offshore Transmission
Systems connected to it and operate within its provisions.
OC9.4.7 Black Start
OC9.4.7.1 The procedure necessary for a recovery from a Total Shutdown or Partial Shutdown is
known as a "Black Start". The procedure for a Partial Shutdown is the same as that for a
Total Shutdown except that it applies only to a part of the Total System. It should be
remembered that a Partial Shutdown may affect parts of the Total System which are not
themselves shutdown.
(b) Black Start following a Partial Shutdown where the Balancing Mechanism has not
been suspended
During a Black Start situation where the Balancing Mechanism has not been suspended,
instructions in relation to Black Start Stations and to Network Operators which are part of
an invoked Local Joint Restoration Plan will (unless The Company specifies otherwise)
be deemed to be Emergency Instructions under BC2.9.2.2 (iv) and will recognise any
differing Black Start operational capabilities (however termed) set out in the relevant
Ancillary Services Agreement in preference to the declared operational capability as
registered pursuant to BC1 (or as amended from time to time in accordance with the BC).
For the purposes of these instructions the Black Start will be an emergency circumstance
under BC2.9.
In Scotland, Gensets that are not at Black Start Stations, but which are part of an invoked
Local Joint Restoration Plan, may be instructed in accordance with the provisions of that
Local Joint Restoration Plan.
(c) If during the Demand restoration process any Genset cannot, because of the Demand
being experienced, keep within its safe operating parameters, the Generator shall, unless a
Local Joint Restoration Plan is in operation, inform The Company. The Company will,
where possible, either instruct Demand to be altered or will re-configure the National
Electricity Transmission System or will instruct a User to re-configure its System in order
to alleviate the problem being experienced by the Generator. If a Local Joint Restoration
Plan is in operation, then the arrangements set out therein shall apply. However, The
Company accepts that any decision to keep a Genset operating, if outside its safe operating
parameters, is one for the Generator concerned alone and accepts that the Generator may
change generation on that Genset if it believes it is necessary for safety reasons (whether
relating to personnel or Plant and/or Apparatus). If such a change is made without prior
notice, then the Generator shall inform The Company as soon as reasonably practical
(unless a Local Joint Restoration Plan is in operation in which case the arrangements set
out therein shall apply).
For the avoidance of doubt, until resumption of the Balancing Mechanism, The Company
is likely to continue to issue Emergency Instructions in accordance with BC2.9.
Users shall use reasonable endeavours to submit Physical notifications ten hours prior to
the start of the Settlement Period determined by the BSC Panel in accordance with
paragraph G3.1.2(d)(i) of the BSC and as notified by The Company to Users, in preparation
for a return to normal operations.
In the event that the Balancing Mechanism has not been suspended and The Company
has determined that the Total System has returned to normal operation, The Company
shall inform Users and the BSCCo as soon as possible of the time and date at which (in The
Company’s determination) the Total System returned to normal operation.
(a) Where the Balancing Mechanism was suspended, the start of the Settlement Period
that the Balancing Mechanism resumed normal operation, as determined by the BSC
Panel and notified by the BSCCo in accordance with the provisions of the BSC; or
(b) Where the Balancing Mechanism was not suspended, the end of the Settlement
Period determined and notified by the BSCCo (in accordance with the provisions of the
BSC) and corresponding to the time and date that The Company determined that the Total
System had returned to normal operation.
CONTENTS
(This contents page does not form part of the Grid Code)
OC10.2 OBJECTIVE
The objective of OC10 is to facilitate the provision of more detailed information, in writing, of
Significant Incidents which were initially orally reported under OC7 and to enable joint
investigations to take place if The Company and the relevant Users agree.
OC10.3 SCOPE
OC10.3.1 OC10 applies to The Company and to Users, which in OC10 means:-
(a) Generators (other than those which only have Embedded Small Power Stations and/or
Embedded Medium Power Stations);
(b) Network Operators;
(c) Non-Embedded Customers;
(d) DC Converter Station owners; and
(e) HVDC System Owners.
The procedure for Event information supply between The Company and Externally
Interconnected System Operators is set out in the Interconnection Agreement with each
Externally Interconnected System Operator.
OC10.4 PROCEDURE
OC10.4.1 Reporting
OC10.4.1.1 Written Reporting Of Events By Users To The Company
In the case of an Event which was initially reported by a User to The Company orally and
subsequently determined by The Company to be a Significant Incident, and accordingly
notified by The Company to a User pursuant to OC7, the User will give a written report to The
Company, in accordance with OC10. The Company will not pass on this report to other
affected Users but may use the information contained therein in preparing a report under OC10
to another User (or in a report which The Company is required to submit under an
Interconnection Agreement) in relation to a Significant Incident (or its equivalent under an
Interconnection Agreement or STC) on the National Electricity Transmission System which
has been caused by (or exacerbated by) the Significant Incident on the User's System.
OC10.4.1.2 Written Reporting Of Events By The Company To Users
In the case of an Event which was initially reported by The Company to a User orally and
subsequently determined by the User to be a Significant Incident, and accordingly notified by
the User to The Company pursuant to OC7, The Company will give a written report to the
User, in accordance with OC10. The User will not pass on the report to other affected Users
but:
MATTERS, IF APPLICABLE TO THE SIGNIFICANT INCIDENT AND TO THE RELEVANT USER (OR THE
COMPANY, AS THE CASE MAY BE) TO BE INCLUDED IN A WRITTEN REPORT GIVEN IN
ACCORDANCE WITH OC10.4.1 AND OC10.4.2
2. Location.
3. Plant and/or Apparatus directly involved (and not merely affected by the Event).
5. Demand (in MW) and/or generation (in MW) interrupted and duration of interruption.
6. Power Generating Module, Generating Unit, Power Park Module, HVDC System or DC
Converter - Frequency response (MW correction achieved subsequent to the Significant
Incident).
7. Power Generating Module, Generating Unit, Power Park Module, HVDC System or DC
Converter - MVAr performance (change in output subsequent to the Significant Incident).
CONTENTS
(This contents page does not form part of the Grid Code)
OC11.2 OBJECTIVE
OC11.2.1 The overall objective of OC11 is to ensure, so far as possible, the safe and effective operation of
the Total System and to reduce the risk of human error faults by requiring, in certain
circumstances, that the numbering and nomenclature of Users HV Apparatus and OTSDUW
HV Apparatus shall be in accordance with the system as notified from time to time by The
Company.
OC11.3 SCOPE
OC11.3.1 OC11 applies to The Company and to Users, which in OC11 means:-
(a) Generators;
(b) Generators undertaking OTSDUW;
(c) Network Operators;
(d) Non-Embedded Customers;
(e) DC Converter Station owners; and
(f) HVDC System Owners
OC11.4 PROCEDURE
OC11.4.1.1 The term "User Site" means a site owned (or occupied pursuant to a lease, licence or other
agreement) by a User in which there is a Connection Point (and in the case of OTSDUW,
where there is a Connection Point or an Interface Point). For the avoidance of doubt, where a
site is owned by a Relevant Transmission Licensee but occupied by a User (as aforesaid), the
site is a User Site.
OC11.4.1.2 The term "Transmission Site" means a site owned (or occupied pursuant to a lease, licence or
other agreement) by a Relevant Transmission Licensee in which there is a Connection Point
(or in the case of OTSDUW, an Interface Point). For the avoidance of doubt, where a site is
owned by a User but occupied by a Relevant Transmission Licensee (as aforesaid), the site is
an Transmission Site.
SYSTEM TESTS
CONTENTS
(This contents page does not form part of the Grid Code)
OC12.2 OBJECTIVE
The overall objectives of OC12 are:
OC12.2.1 to ensure, so far as possible, that System Tests proposed to be carried out either by:
(a) a User (or certain persons in respect of Systems Embedded within a Network Operator’s
System) which may have an effect on the Total System or any part of the Total System
(in addition to that User's System) including the National Electricity Transmission
System; or
(b) by The Company which may have an effect on the Total System or any part of the Total
System (in addition to the National Electricity Transmission System)
do not threaten the safety of either their personnel or the general public, cause minimum threat
to the security of supplies and to the integrity of Plant and/or Apparatus, and cause minimum
detriment to The Company and Users;
OC12.2.2 to set out the procedures to be followed for establishing and reporting System Tests.
OC12.3 SCOPE
OC12 applies to The Company and to Users, which in OC12 means:-
(a) Generators other than in respect of Embedded Medium Power Stations and Embedded
Small Power Stations (and the term Generator in OC12 shall be constructed accordingly);
(b) Network Operators;
(c) Non-Embedded Customers; and
(d) DC Converter Station owners other than in respect of Embedded DC Converter
Stations.
(e) HVDC System Owners other than in respect of Embedded HVDC Systems.
The procedure for the establishment of System Tests on the National Electricity
Transmission System, with Externally Interconnected System Operators which do not affect
any User, is set out in the Interconnection Agreement with each Externally Interconnected
System Operator. The position of Externally Interconnected System Operators and
Interconnector Users is also referred to in OC12.4.2.
OC12.3.2 Each Network Operator will liaise within The Company as necessary in those instances where
an Embedded Person intends to perform a System Test which may have an effect on the Total
System or any part of the Total System (in addition to that Generator’s or other User’s
System) including the National Electricity Transmission System. The Company is not
required to deal with such persons.
OC12.3.3 Each Network Operator shall be responsible for co-ordinating with the Embedded Person or
such other person and assessing the effect of any System Tests upon:
Issue 5 Revision 26 OC12 26 September 2018
2 of 6
(a) any Embedded Medium Power Station, Embedded Small Power Stations, Embedded
HVDC System or Embedded DC Converter Station within the Network Operator’s
System; or
(b) any other User connected to or within the Network Operator’s System.
The Company is not required to deal with such persons.
OC12.4 PROCEDURE
OC12.4.1 Proposal Notice
OC12.4.1.1 Where a User (or in the case of a Network Operator, a person in respect of Systems
Embedded within its System, as the case may be) has decided that it would like to undertake a
System Test it shall submit a notice (a "Proposal Notice”) to The Company at least twelve
months in advance of the date it would like to undertake the proposed System Test.
OC12.4.1.2 The Proposal Notice shall be in writing and shall contain details of the nature and purpose of
the proposed System Test and shall indicate the extent and situation of the Plant and/or
Apparatus involved.
OC12.4.1.3 If The Company is of the view that the information set out in the Proposal Notice is insufficient,
it will contact the person who submitted the Proposal Notice (the "Test Proposer") as soon as
reasonably practicable, with a written request for further information. The Company will not be
required to do anything under OC12 until it is satisfied with the details supplied in the Proposal
Notice or pursuant to a request for further information.
OC12.4.1.4 If The Company wishes to undertake a System Test, The Company shall be deemed to have
received a Proposal Notice on that System Test
OC12.4.1.5 Where, under OC12, The Company is obliged to notify or contact the Test Proposer, The
Company will not be so obliged where it is The Company that has proposed the System Test.
Users and the Test Panel, where they are obliged under OC12 to notify, send reports to or
otherwise contact both The Company and the Test Proposer, need only do so once where The
Company is the proposer of the System Test.
OC12.4.2 Preliminary Notice And Establishment Of Test Panel
OC12.4.2.1 Using the information supplied to it under OC12.4.1 The Company will determine, in its
reasonable estimation, which Users, other than the Test Proposer, may be affected by the
proposed System Test. If The Company determines, in its reasonable estimation, that an
Externally Interconnected System Operator and/or Interconnector User (or Externally
Interconnected System Operators and/or Interconnector Users) may be affected by the
proposed System Test, then (provided that the Externally Interconnected System Operator
and/or Interconnector User (or each Externally Interconnected System Operator and/or
Interconnector User where there is more than one affected) undertakes to all the parties to the
Grid Code to be bound by the provisions of the Grid Code for the purposes of the System Test)
for the purposes of the remaining provisions of this OC12, that Externally Interconnected
System Operator and/or Interconnector User (or each of those Externally Interconnected
System Operators and/or Interconnector Users) will be deemed to be a User and references
to the Total System or to the Plant and/or Apparatus of a User will be deemed to include a
reference to the Transmission or distribution System and Plant and/or Apparatus of that
Externally Interconnected System Operator and/or Interconnector User or (as the case may
be) those Externally Interconnected System Operators and/or Interconnector Users. In the
event that the Externally Interconnected System Operator and/or Interconnector User (or
any of the Externally Interconnected System Operators and/or Interconnector Users where
there is more than one affected) refuses to so undertake, then the System Test will not take
place.
CONTENTS
(This contents page does not form part of the Grid Code)
BC1.2 OBJECTIVE
The procedure for the submission of BM Unit Data and/or Generating Unit Data is intended
to enable The Company to assess which BM Units and Generating Units (which could be
part of a Power Generating Module) are expected to be operating in order that The
Company can ensure (so far as possible) the integrity of the National Electricity
Transmission System, and the security and quality of supply.
Where reference is made in this BC1 to Generating Units and/or Power Generating
Modules (unless otherwise stated) it only applies:
(a) to each Generating Unit which forms part of the BM Unit of a Cascade Hydro
Scheme; and
(b) at an Embedded Exemptable Large Power Station where the relevant Bilateral
Agreement specifies that compliance with BC1 is required:
(i) to each Generating Unit which could be part of a Synchronous Power
Generating Module, or
(ii) to each Power Park Module where the Power Station comprises Power Park
Modules.
BC1.3 SCOPE
BC1 applies to The Company and to Users, which in this BC1 means:-
(a) BM Participants;
(b) Externally Interconnected System Operators; and
(c) Network Operators.
• for a change greater than 300MW and less than 1000MW 50MW per minute;
unless prior arrangements have been discussed and agreed with The Company. This
limitation is not intended to limit the Run-Up or Run-Down Rates provided as Dynamic
Parameters.
An example of the format of Physical Notification is shown below. The convention to be
applied is that where it is proposed that the BM Unit will be importing, the Physical
Notification is negative.
From To
Data Name BMU name Time From
level Time To Level
(MW) MW)
PN , TAGENT , BMUNIT01 , 2001-11-03 06:30 , 77 , 2001-11-03 07:00 , 100
PN , TAGENT , BMUNIT01 , 2001-11-03 07:00 , 100 , 2001-11-03 07:12 , 150
PN , TAGENT , BMUNIT01 , 2001-11-03 07:12 , 150 , 2001-11-03 07:30 , 175
A linear interpolation will be assumed between the Physical Notification From and To
levels specified for the BM Unit by the BM Participant.
For each BM Unit A series of MW figures and associated times, which describe the MW
(optional) levels to be deducted from the Physical Notification of a BM Unit to
determine a resultant operating level to which the Dynamic
Parameters associated with that BM Unit apply.
From To
Data Name BMU name Time From
level Time To level
(MW) (MW)
QPN , TAGENT , BMUNIT04 , 2001-11-03 06:30 , -200 , 2001-11-03 07:00 , -220
QPN , TAGENT , BMUNIT04 , 2001-11-03 07:00 , -220 , 2001-11-03 07:18 , -245
QPN , TAGENT , BMUNIT04 , 2001-11-03 07:18 , -245 , 2001-11-03 07:30 , -300
A linear interpolation will be assumed between the QPN From and To levels specified for the
BM Unit by the BM Participant.
From To
Data Name BMU name Time From
level Time To level
(MW) (MW)
MEL , TAGENT , BMUNIT01 , 2001-11-03 05:00 , 410 , 2001-11-03 09:35 , 410
MEL , TAGENT , BMUNIT01 , 2001-11-03 09:35 , 450 , 2001-11-03 12:45 , 450
For each BM Unit for each Up to 10 Bid-Offer Pairs as defined in the BSC.
Settlement Period:
0MW to 150MW /
151MW to 250MW / /
251MW to 300MW / /
301MW to 400MW / / /
401MW to 450MW / / /
451MW to 550MW / / / /
BM Unit Name
Power Park Module [unique identifier]
POWER PARK POWER PARK UNITS
UNIT AVAILABILITY Type A Type B Type C Type D
Description
(Make/Model)
Number of units
Power Park Module [unique identifier]
POWER PARK POWER PARK UNITS
UNIT AVAILABILITY Type A Type B Type C Type D
Description
(Make/Model)
Number of units
BC1.A.1.8.2 In the absence of the correct submission of a Power Park Module Availability Matrix the
last submitted (or deemed submitted) Power Park Module Availability Matrix shall be
taken to be the Power Park Module Availability Matrix submitted hereunder.
BC1.A.1.8.3 The Company will rely on the Power Park Units, Power Park Modules and BM Units
specified in such Power Park Module Availability Matrix running as indicated in the Power
Park Module Availability Matrix when it issues an instruction in respect of the BM Unit.
BC1.A.1.8.4 Subject as provided in PC.A.3.2.4 any changes to Power Park Module or BM Unit
configuration, or availability of Power Park Units which affects the information set out in the
Power Park Module Availability Matrix must be notified immediately to The Company in
accordance with the relevant provisions of BC1. Initial notification may be by telephone. In
some circumstances, such as a significant re-configuration of a Power Park Module due to
an unplanned outage, a revised Power Park Module Availability Matrix must be supplied
on The Company's request.
0MW to 150MW /
151MW to 250MW / /
251MW to 300MW / /
301MW to 400MW / / /
401MW to 450MW / / /
451MW to 550MW / / / /
BC1.A.10.1 For each Additional BM Unit and Secondary BM Unit the relevant BM Participant
will submit data relating to the effect of a Bid-Off Acceptance on each Grid Supply
Point within the GSP Group over which the Additional BM Unit or Secondary BM
Unit was defined.
BC1.A.10.2 For each Additional BM Unit and Secondary BM Unit the relevant BM Participant
will also provide the post-codes and MSIDs that make up the Additional BM Unit or
Secondary BM Unit
BMU Name
Operational Day from which values apply
Grid Supply Point % Impact Grid Supply Point % Impact
Target Data
Release Time Period Start Time Period End Time
02:00 02:00 D0 05:00 D+1
10:00 10:00 D0 05:00 D+1
16:00 05:00 D+1 05:00 D+2
16:30 16:30 D0 05:00 D+1
22:00 22:00 D0 05:00 D+2
In this table, D0 refers to the current day, D+1 refers to the next day and D+2 refers to the
day following D+1.
In all cases, data will be ½ hourly average MW values calculated by The Company.
Information to be released includes:
National Information
(i) National Indicated Margin;
(ii) National Indicated Imbalance;
(iii) Updated forecast of National Electricity Transmission System Demand.
CONTENTS
(This contents page does not form part of the Grid Code)
BC2.2 OBJECTIVE
The procedure covering the operation of the Balancing Mechanism and the issuing of
instructions to Users is intended to enable The Company as far as possible to maintain the
integrity of the National Electricity Transmission System together with the security and
quality of supply.
Where reference is made in this BC2 to Power Generating Modules or Generating Units
(unless otherwise stated) it only applies:
(a) to each Generating Unit which forms part of the BM Unit of a Cascade Hydro Scheme;
and
(b) at an Embedded Exemptable Large Power Station where the relevant Bilateral
Agreement specifies that compliance with BC2 is required:
(i) to each Generating Unit which could be part of a Synchronous Power Generating
Module, or
(ii) to each Power Park Module where the Power Station comprises Power Park
Modules.
BC2.3 SCOPE
BC2 applies to The Company and to Users, which in this BC2 means:-
(a) BM Participants;
(b) Externally Interconnected System Operators, and
(c) Network Operators.
BC2.6 COMMUNICATIONS
Electronic communications are always conducted in GMT. However, the input of data and
display of information to Users and The Company and all other communications are
conducted in London time.
BC2.6.1 Normal Communication With Control Points
(a) With the exception of BC2.6.1(c) below, Bid-Offer Acceptances and, unless otherwise
agreed with The Company, Ancillary Service instructions shall be given by automatic
logging device and will be given to the Control Point for the BM Unit. For all Planned
Maintenance Outages the provisions of BC2.6.5 will apply. For Generating Units
(including DC Connected Power Park Modules (if relevant)) communications under
BC2 shall be by telephone unless otherwise agreed by The Company and the User.
(b) Bid-Offer Acceptances and Ancillary Service instructions must be formally
acknowledged immediately by the BM Participant (or the relevant person on its behalf)
via the Control Point for the BM Unit or Generating Unit in respect of that BM Unit or
that Generating Unit. The acknowledgement and subsequent confirmation or rejection,
within two minutes of receipt, is normally given electronically by automatic logging device.
If no confirmation or rejection is received by The Company within two minutes of the
issue of the Bid-Offer Acceptance, then The Company will contact the Control Point
for the BM Unit by telephone to determine the reason for the lack of confirmation or
rejection. Any rejection must be given in accordance with BC2.7.3 or BC2.8.3.
Issue 5 Revision 32 BC2 1 April 2019
9 of 35
(c) In the event of a failure of the logging device or a The Company computer system outage,
Bid-Offer Acceptances and instructions will be given, acknowledged, and confirmed or
rejected by telephone. The provisions of BC2.9.7 are also applicable.
(d) In the event that in carrying out the Bid-Offer Acceptances or providing the Ancillary
Services, or when operating at the level of the Final Physical Notification Data as
provided in BC2.5.1, an unforeseen problem arises, caused on safety grounds (relating
to personnel or plant), The Company must be notified without delay by telephone.
(e) The provisions of BC2.5.3 are also relevant.
(f) Submissions of revised MVAr capability may be made by facsimile transmission, using
the format given in Appendix 3 to BC2.
(g) Communication will normally be by telephone for any purpose other than Bid-Offer
Acceptances, in relation to Ancillary Services or for revisions of MVAr Data.
(h) Submissions of revised availability of Frequency Sensitive Mode may be made by
facsimile transmission, using the format given in Appendix 4 to BC2. This process should
only be used for technical restrictions to the availability of Frequency Sensitive Mode.
BC2.6.2 Communication With Control Points In Emergency Circumstances
The Company will issue Emergency Instructions direct to the Control Point for each BM
Unit [or Generating Unit] in Great Britain. Emergency Instructions to a Control Point will
normally be given by telephone (and will include an exchange of operator names).
BC2.6.3 Communication With Network Operators In Emergency Circumstances
The Company will issue Emergency Instructions direct to the Network Operator at each
Control Centre in relation to special actions and Demand Control. Emergency Instructions
to a Network Operator will normally be given by telephone (and will include an exchange of
operator names). OC6 contains further provisions relating to Demand Control instructions.
BC2.6.4 Communication With Externally Interconnected System Operators In Emergency
Circumstances
The Company will issue Emergency Instructions directly to the Externally Interconnected
System Operator at each Control Centre. Emergency Instructions to an Externally
Interconnected System Operator will normally be given by telephone (and will include an
exchange of operator names).
BC2.6.5 Communications During Planned Outages Of Electronic Data Communication Facilities
Planned Maintenance Outages will normally be arranged to take place during periods of low
data transfer activity. Upon any such Planned Maintenance Outage in relation to a post Gate
Closure period:-
(a) BM Participants should operate in relation to any period of time in accordance with the
Physical Notification prevailing at Gate Closure current at the time of the start of the
Planned Maintenance Outage in relation to each such period of time. Such operation
shall be subject to the provisions of BC2.5.1, which will apply as if set out in this BC2.6.5.
No further submissions of BM Unit Data (other than data specified in BC1.4.2(c) and
BC1.4.2(e)) should be attempted or Generating Unit Data. Plant failure or similar
problems causing significant deviation from Physical Notification should be notified to
The Company by the submission of a revision to Export and Import Limits in relation
to the BM Unit or Generating Unit so affected;
(b) during the outage, revisions to the data specified in BC1.4.2(c) and BC1.4.2(e) may be
submitted. Communication between Users Control Points and The Company during
the outage will be conducted by telephone;
(c) The Company will issue Bid-Offer Acceptances by telephone; and
(d) no data will be transferred from The Company to the BMRA until the communication
facilities are re-established.
BC2.8.2 Consistency With Export And Import Limits, QPNs And Dynamic Parameters
Ancillary Service instructions will be consistent with the Export and Import Limits, QPNs,
and Joint BM Unit Data provided or modified under BC1 or BC2 and the Dynamic
Parameters provided or modified under BC2. Ancillary Service instructions may also
recognise Other Relevant Data provided or modified under BC1 or BC2.
BC2.8.3 Rejection Of Ancillary Service Instructions
(a) Ancillary Service instructions may only be rejected, by automatic logging device or by
telephone, on safety grounds (relating to personnel or plant) or because they are not
consistent with the applicable Export and Import Limits, QPNs, Dynamic Parameters,
Joint BM Unit Data, Other Relevant Data or data contained in the Ancillary Services
Agreement and a reason must be given immediately for non-acceptance.
(b) The issue of Ancillary Service instructions for Reactive Power will be made with due
regard to any resulting change in Active Power output. The instruction may be rejected
if it conflicts with any Bid-Offer Acceptance issued in accordance with BC2.7 or with the
Physical Notification.
(c) Where Ancillary Service instructions relating to Active Power and Reactive Power are
given together, and to achieve the Reactive Power output would cause the BM Unit to
operate outside Dynamic Parameters as a result of the Active Power instruction being
met at the same time, then the timescale of implementation of the Reactive Power
instruction may be extended to be no longer than the timescale for implementing the
Active Power instruction but in any case to achieve the MVAr Ancillary Service
instruction as soon as possible.
BC2.8.4 Action Required From BM Units
(a) Each BM Unit (or Generating Unit) will comply in accordance with BC2.8.1 with all
Ancillary Service instructions relating to Reactive Power properly given by The
Company within 2 minutes or such longer period as The Company may instruct, and all
other Ancillary Service instructions without delay, unless the BM Unit or Generating
Unit has given notice to The Company under the provisions of BC2.8.3 regarding non-
acceptance of Ancillary Service instructions.
(b) Each BM Unit may deviate from the profile of its Final Physical Notification Data, as
modified by any Bid-Offer Acceptances issued in accordance with BC2.7.1, only as a
result of responding to Frequency deviations when operating in Frequency Sensitive
Mode in accordance with the Ancillary Services Agreement.
Issue 5 Revision 32 BC2 1 April 2019
13 of 35
(c) Each Generating Unit that does not form part of a BM Unit may deviate from the profile
of its Final Physical Notification Data where agreed by The Company and the User,
including but not limited to, as a result of providing an Ancillary Service in accordance
with the Ancillary Service Agreement.
(d) In the event that while carrying out the Ancillary Service instructions an unforeseen
problem arises caused by safety reasons (relating to personnel or plant), The Company
must be notified immediately by telephone and this may lead to revision of BM Unit Data
or Generating Unit Data in accordance with BC2.5.3.
BC2.8.5 Reactive Despatch Network Restrictions
Where The Company has received notification pursuant to the Grid Code that a Reactive
Despatch to Zero MVAr Network Restriction is in place with respect to any Embedded
Power Generating Module and/or Embedded Generating Unit and/or Embedded Power
Park Module or HVDC Converter at an Embedded HVDC Converter Station or DC
Converter at an Embedded DC Converter Station, then The Company will not issue any
Reactive Despatch Instruction with respect to that Power Generating Module and/or
Generating Unit and/or Power Park Module or DC Converter or HVDC Converter until such
time as notification is given to The Company pursuant to the Grid Code that such Reactive
Despatch to Zero MVAr Network Restriction is no longer affecting that Power Generating
Module and/or Generating Unit and/or Power Park Module or DC Converter or HVDC
Converter.
BC2.9.2.3 In all cases under this BC2.9 except BC2.9.1.2 (e) where The Company issues an
Emergency Instruction to a BM Participant which is not rejected under BC2.9.2.1, the
Emergency Instruction shall be treated as a Bid-Offer Acceptance. For the avoidance of
doubt, any Emergency Instruction issued to a Network Operator or to an Externally
Interconnected System Operator or in respect of a Generating Unit that does not form part
of a BM Unit, will not be treated as a Bid-Offer Acceptance.
BC2.9.2.4 In the case of BC2.9.1.2 (e) (ii) where The Company issues an Emergency Instruction
pursuant to a Maximum Generation Service Agreement payment will be dealt with in
accordance with the CUSC and the Maximum Generation Service Agreement.
BC2.9.2.5 In the case of BC2.9.1.2 (e) (iii) where The Company issues an Emergency Deenergisation
Instruction payment will be dealt with in accordance with the CUSC, Section 5.
BC2.9.2.6 In the of BC2.9.1.2 (e) (i) upon receipt of an Emergency Instruction by a Generator during
a Black Start the provisions of Section G of the BSC relating to compensation shall apply.
BC2.9.3 Examples Of Emergency Instructions
BC2.9.3.1 In the case of a BM Unit or a Generating Unit, Emergency Instructions may include an
instruction for the BM Unit or the Generating Unit to operate in a way that is not consistent
with the Dynamic Parameters, QPNs and/or Export and Import Limits.
BC2.9.3.2 In the case of a Generator, Emergency Instructions may include:
(a) an instruction to trip one or more Gensets (excluding Operational Intertripping); or
BC2.9.4 Maintaining Adequate System And Localised NRAPM (Negative Reserve Active Power
Margin)
BC2.9.4.1 Where The Company is unable to satisfy the required System NRAPM or Localised NRAPM
by following the process described in BC1.5.5, The Company will issue an Emergency
Instruction to exporting BM Units for De-Synchronising on the basis of Bid-Offer Data
submitted to The Company in accordance with BC1.4.2(d).
BC2.9.4.2 In the event that The Company is unable to differentiate between exporting BM Units
according to Bid-Offer Data, The Company will instruct a BM Participant to Shutdown a
specified exporting BM Unit for such period based upon the following factors:
(a) effect on power flows (resulting in the minimisation of transmission losses);
(b) reserve capability;
(c) Reactive Power worth;
(d) Dynamic Parameters;
(e) in the case of Localised NRAPM, effectiveness of output reduction in the management
of the System Constraint.
BC2.9.4.3 Where The Company is still unable to differentiate between exporting BM Units, having
considered all the foregoing, The Company will decide which exporting BM Unit to Shutdown
by the application of a quota for each BM Participant in the ratio of each BM Participant’s
Physical Notifications.
BC2.11 LIAISON WITH GENERATORS FOR RISK OF TRIP AND AVR TESTING
BC2.11.1 A Generator at the Control Point for any of its Large Power Stations may request The
Company's agreement for one of the Gensets at that Power Station to be operated under a
risk of trip. The Company's agreement will be dependent on the risk to the National
Electricity Transmission System that a trip of the Genset would constitute.
BC2.11.2 (a) Each Generator at the Control Point for any of its Large Power Stations will operate
its Synchronised Gensets (excluding Power Park Modules) with:
(i) AVRs in constant terminal voltage mode with VAR limiters in service at all times.
AVR constant Reactive Power or Power Factor mode should, if installed, be
disabled; and
(ii) its generator step-up transformer tap changer selected to manual mode,
unless released from this obligation in respect of a particular Genset by The Company.
(b) Each Generator at the Control Point for any of its Large Power Stations will operate
its Power Park Modules with a Completion Date before 1st January 2006 at unity power
factor at the Grid Entry Point (or User System Entry Point if Embedded).
(c) Each Generator at the Control Point for any of its Large Power Stations will operate
its Power Park Modules with a Completion Date on or after 1st January 2006 in voltage
control mode at the Grid Entry Point (or User System Entry Point if Embedded).
Constant Reactive Power or Power Factor mode should, if installed, be disabled.
(b) Ancillary Service instructions for Reactive Power will normally follow the form:
(a) an exchange of operator names;
(b) BM Unit Name;
(c) Time of instruction;
(d) Type of instruction (MVAr, VOLT, SETPOINT, SLOPE or TAPP)
(e) Target Value
(f) Target Time.
The times required in the instruction are expressed as London time.
For example, for BM Unit ABCD-1 instructed at 1400 hours to provide 100MVAr by 1415
hours:
“BM Unit ABCD-1 message timed at 1400 hours. MVAr instruction. Unit to plus 100 MVAr
target time 1415 hours.”
Instruction Type of
Description
Name Instruction
MVAr Output The individual MVAr output from the Genset onto the MVAr
National Electricity Transmission System at the Grid
Entry Point (or onto the User System at the User System
Entry Point in the case of Embedded Power Stations),
namely on the higher voltage side of the generator step-up
transformer or Grid Entry Point or User System Entry
Point in the case of a Power Generating Module. In
relation to each Genset, where there is no HV indication,
The Company and the Generator will discuss and agree
equivalent MVAr levels for the corresponding LV indication.
Target Voltage Target voltage levels to be achieved by the Genset on the VOLT
Levels National Electricity Transmission System at the Grid
Entry Point (or on the User System at the User System
Entry Point in the case of Embedded Power Stations,
namely on the higher voltage side of the generator step-
up transformer or Grid Entry Point or User System Entry
Point in the case of a Power Generating Module. Where
a Genset is instructed to a specific target voltage, the
Generator must achieve that target within a tolerance of
±1 kV (or such other figure as may be agreed with The
Company) by tap changing on the generator step-up
transformer, or adjusting the Genset terminal voltage,
subject to compliance with CC.6.3.8 (a) (v) or
ECC.6.3.8.3.3 (as applicable), to a value that is equal to
or higher than 1.0p.u. of the rated terminal voltage, or a
combination of both. In relation to each Genset, where
there is no HV indication, The Company and the
Generator will discuss and agree equivalent voltage
levels for the corresponding LV indication.
Tap Changes Details of the required generator step-up transformer tap TAPP
changes in relation to a Genset. The instruction for tap
changes may be a Simultaneous Tap Change
instruction, whereby the tap change must be effected by
the Generator in response to an instruction from The
Company issued simultaneously to relevant Power
Stations. The instruction, which is normally preceded by
advance notice, must be effected as soon as possible, and
in any event within one minute of receipt from The
Company of the instruction.
For a Simultaneous Tap Change, change Genset
generator step-up transformer tap position by one [two] taps
to raise or lower (as relevant) System voltage, to be
executed at time of instruction.
BC2.A.2.7 In addition, the following provisions will apply to Reactive Power instructions:
(a) In circumstances where The Company issues new instructions in relation to more than
one BM Unit at the same Power Station at the same time, tapping will be carried out by
the Generator one tap at a time either alternately between (or in sequential order, if more
than two), or at the same time on, each BM Unit.
(b) Where the instructions require more than two taps per BM Unit and that means that the
instructions cannot be achieved within 2 minutes of the instruction time (or such longer
period at The Company may have instructed), the instructions must each be achieved
with the minimum of delay after the expiry of that period.
Full Output In the case of a Synchronous Generating Unit (as defined in the
Glossary and Definitions ((which could be part of a Synchronous
Power Generating Module) and not limited by BC2.2) is the MW
output measured at the generator stator terminals representing the
LV equivalent of the Registered Capacity at the Grid Entry Point,
and in the case of a Non-Synchronous Generating Unit (excluding
Power Park Units), HVDC Converter or DC Converter or Power
Park Module is the Registered Capacity at the Grid Entry Point
Minimum Output In the case of a Synchronous Generating Unit (as defined in the
Glossary and Definitions ((which could be part of a Synchronous
Power Generating Module) and not limited by BC2.2 ) is the MW
output measured at the generator stator terminals representing the
LV equivalent of the Minimum Generation or Minimum Stable
Operating Level at the Grid Entry Point, and in the case of a Non-
Synchronous Generating Unit (excluding Power Park Units),
HVDC Converter or DC Converter or Power Park Module is the
Minimum Generation or Minimum Stable Operating Level or
Minimum Active Power Transmission Capacity at the Grid Entry
Point
BC2.A.3.2 The following provisions apply to faxed submission of revised MVAr data:
(a) The fax must be transmitted to The Company (to the relevant location in accordance with
GC6) and must contain all the sections from the relevant part of Annexure 1 and from
either Annexure 2 or 3 (as applicable) but with only the data changes set out. The
"notification time" must be completed to refer to the time of transmission, where the time
is expressed as London time.
(b) Upon receipt of the fax, The Company will acknowledge receipt by sending a fax back to
the User. The acknowledgement will either state that the fax has been received and is
legible or will state that it (or part of it) is not legible and will request re-transmission of
the whole (or part) of the fax.
(c) Upon receipt of the acknowledging fax the User will, if requested, re-transmit the whole
or the relevant part of the fax.
(d) The provisions of paragraphs (b) and (c) then apply to that re-transmitted fax.
Optional
Logo
Sent By : ........................................................................................................
................................................................................
Legibility of FAX :
Acceptable
REVISED REACTIVE POWER CAPABILITY DATA – GENERATING UNITS EXCLUDING POWER PARK
MODULES AND DC CONVERTERS
Generating Unit*
* For a Synchronous Power Generating Module and/or CCGT Module and/or a Cascade Hydro Scheme,
the redeclaration is for a Generating Unit within a Synchronous Power Generating Module and/or CCGT
Module and/or Cascade Hydro Scheme. For BM Units quote The Company BM Unit id, for other units
quote the Generating Unit id used for OC2.4.1.2 Outage Planning submissions. Generating Unit has the
meaning given in the Glossary and Definitions and is not limited by BC2.2.
REVISION TO THE REACTIVE POWER CAPABILITY AT THE GENERATING UNIT STATOR TERMINALS
(at rated terminal volts) AS STATED IN THE RELEVANT ANCILLARY SERVICES AGREEMENT:
AT RATED MW
AT MINIMUM
OUTPUT (MW)
COMMENTS e.g. generator transformer tap restrictions, predicted end time if known
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________
REVISED REACTIVE POWER CAPABILITY DATA – POWER PARK MODULES, HVDC CONVERTERS
AND DC CONVERTERS
* For BM Units quote The Company BM Unit id, for other units quote the id used for OC2.4.1.2 Outage Planning
submissions
AT RATED MW
AT 50% OF RATED
MW
AT 20% OF RATED MW
AT 0% OF RATED
MW
COMMENTS e.g. generator transformer tap restrictions, predicted end time if known
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________
Issue 5 Revision 32 BC2 1 April 2019
33 of 35
APPENDIX 4 - SUBMISSION OF AVAILABILITY OF FREQUENCY
SENSITIVE MODE
BC2.A.4.1 For the purpose of submitting availability of Frequency Sensitive Mode, this process only
relates to the provision of response under the Frequency Sensitive Mode and does not cover
the provision of response under the Limited Frequency Sensitive Mode.
BC2.A.4.2 The following provisions apply to the faxed submission of the Frequency Sensitive Mode
availability;
(a) The fax must be transmitted to The Company (to the relevant location in accordance with
GC6) and must contain all the sections relevant to Appendix 4 - Annexure1 but with only
the data changes set out. The “notification time” must be completed to refer to the time
and date of transmission, where the time is expressed in London time.
(b) Upon receipt of the fax, The Company will acknowledge receipt by sending a fax back to
the User. This acknowledging fax should be in the format of Appendix 4 – Annexure 1.
The acknowledgement will either state that the fax has been received and is legible or
will state that it (or part of it) is not legible and will request re-transmission of the whole
(or part) of the fax.
(c) Upon receipt of the acknowledging fax the User will, if requested re-transmit the whole or
the relevant part of the fax.
(d) The provisions of paragraph (b) and (c) then apply to the re-transmitted fax.
BC2.A.4.3 The User shall ensure the availability of operating in the Frequency Sensitive Mode is
restored as soon as reasonably practicable and will notify The Company using the format of
Appendix 4 – Annexure 1. In the event of a sustained unavailability of Frequency Sensitive
Mode The Company may seek to confirm compliance with the relevant requirements in the
CC or ECC through the process in OC5 or ECP.
Genset or DC Converter
The availability of the above unit to operate in Frequency Sensitive Mode is as follows:
Contract Mode e.g. A Availability for operation in Frequency Sensitive Mode [Y/N]
_________________________________________________________________________
_________________________________________________________________________
Time:
Date:
Signature:
CONTENTS
(This contents page does not form part of the Grid Code)
BC3.2 OBJECTIVE
The procedure for The Company to direct System Frequency control is intended to enable
(as far as possible) The Company to meet the statutory requirements of System
Frequency control.
BC3.3 SCOPE
BC3 applies to The Company and to GB Code Users and EU Code Users, which in this
BC3 means:
(a) GB Generators with regard to their Large Power Stations (except those Large Power
Stations with a Registered Capacity less than 50MW comprising of Power Park
Modules),
(b) EU Generators with regard to their Large Power Stations
(c) Network Operators,
(d) DC Converter Station owners and HVDC System Owners,
(e) other providers of Ancillary Services,
(f) Externally Interconnected System Operators.
Issue 5 Revision 26 BC3 26 September 2018
3 of 9
BC3.4 MANAGING SYSTEM FREQUENCY
BC3.4.1 Statutory Requirements
When The Company determines it is necessary (by having monitored the System
Frequency), it will, as part of the procedure set out in BC2, issue instructions (including
instructions for Commercial Ancillary Services) in order to seek to regulate System
Frequency to meet the statutory requirements of Frequency control. Gensets (except
those owned and/or operated by GB Generators comprising of a Power Park Module in a
Power Station with a Registered Capacity less than 50MW and those owned and/or
operated by GB Generators comprising of a Power Park Module in Scotland with a
Completion Date before 1 July 2004) and DC Converters at DC Converter Stations or
HVDC Systems when transferring Active Power to the Total System, operating in
Frequency Sensitive Mode will be instructed by The Company to operate taking due
account of the Target Frequency notified by The Company.
BC3.4.2 Target Frequency
The Company will give 15 minutes notice of variation in Target Frequency.
BC3.4.3 Electric Time
The Company will endeavour (in so far as it is able) to control electric clock time to within
plus or minus 10 seconds by specifying changes to Target Frequency, by accepting bids
and offers in the Balancing Mechanism. Errors greater than plus or minus 10 seconds may
be temporarily accepted at The Company 's reasonable discretion.
(b) (i) The Company will specify within the range agreed with Generators and/or EISOs
and/or DC Converter Station owners or HVDC System Owners (if so agreed as
described in BC3.1.3), Low Frequency Relay settings to be applied to Gensets or
DC Converters at DC Converter Stations or HVDC Systems pursuant to
BC3.6.1 (a) and instruct the Low Frequency Relay initiated response placed in
and out of service.
(ii) Generators and/or EISOs and/or DC Converter Station owners or HVDC System
Owners (if so agreed as described in BC3.1.3) will comply with The Company
instructions for Low Frequency Relay settings and Low Frequency Relay
initiated response to be placed in or out of service. Generators or DC Converter
Station owners or HVDC System Owners or EISOs may not alter such Low
Frequency Relay settings or take Low Frequency Relay initiated response out of
service without The Company's agreement (such agreement not to be
unreasonably withheld or delayed), except for safety reasons.
BC3.6.2 Low Frequency Relay Initiated Response From Demand And Other Demand Modification
Arrangements (Which May Include A DC Converter Station or HVDC System When
Importing Active Power From The Total System)
(a) The Company may, pursuant to an Ancillary Services Agreement, utilise Demand
with the capability of Low Frequency Relay initiated Demand reduction in establishing
its requirements for Frequency Control.
(b) (i) The Company will specify within the range agreed the Low Frequency Relay
settings to be applied pursuant to BC3.6.2 (a), the amount of Demand reduction to
be available and will instruct the Low Frequency Relay initiated response to be
placed in or out of service.
(ii) Users will comply with The Company instructions for Low Frequency Relay
settings and Low Frequency Relay initiated Demand reduction to be placed in or
out of service. Users may not alter such Low Frequency Relay settings or take
Low Frequency Relay initiated response out of service without The Company's
agreement, except for safety reasons.
(iii) In the case of any such Demand which is Embedded, The Company will notify
the relevant Network Operator of the location of the Demand, the amount of
Demand reduction to be available, and the Low Frequency Relay settings.
(c) The Company may also utilise other Demand modification arrangements pursuant to
an agreement for Ancillary Services, in order to contribute towards Operating
Reserve.
(b) (i) The rate of change of Active Power output must be at a minimum rate of 2 per
cent of output per 0.1 Hz deviation of System Frequency above 50.4 Hz.
(ii) The reduction in Active Power output must be continuously and linearly
proportional, as far as is practicable, to the excess of Frequency above 50.4 Hz
and must be provided increasingly with time over the period specified in (iii) below.
(iii) As much as possible of the proportional reduction in Active Power output must
result from the frequency control device (or speed governor) action and must be
achieved within 10 seconds of the time of the Frequency increase above 50.4 Hz.
(iv) The residue of the proportional reduction in Active Power output which results
from automatic action of the Genset (or DC Converter at a DC Converter
Station) output control devices other than the frequency control devices (or speed
governors) must be achieved within 3 minutes from the time of the Frequency
increase above 50.4 Hz.
(v) Any further residue of the proportional reduction which results from non-automatic
action initiated by the Generator or DC Converter Station owner shall be initiated
within 2 minutes, and achieved within 5 minutes, of the time of the Frequency
increase above 50.4 Hz.
(c) Each GB Code User in respect of a Genset (or DC Converter at a DC Converter
Station) which is providing Limited High Frequency Response in accordance with
this BC3.7.2 must continue to provide it until the Frequency has returned to or below
50.4 Hz or until otherwise instructed by The Company.
BC.3.7.2.2 Plant in Limited Frequency Sensitive Mode applicable to EU Code Users
EU Code Users in respect of Gensets and HVDC Systems are required to operate in
Limited Frequency Sensitive Mode at all times unless instructed by The Company to
operate in Frequency Senstive Mode. Where EU Code Users Gensets and HVDC
Systems are required to operate in Limited Frequency Senstive Mode then the
requirements of ECC.6.3.7.1 and ECC.6.3.7.2 shall apply. For the avoidance of doubt, the
requirements defined in BC.3.7.2.1 do not apply to New Generators and HVDC System
Owners.
BC3.7.3 Plant Operation To Below Minimum Generation or Minimum Stable Operating Level
TERRE PROCESSES
CONTENTS
(This contents page does not form part of the Grid Code)
BC4.2 OBJECTIVE
This procedure facilitates the participation of BM Participants in the TERRE market.
Particpation in TERRE is voluntary for BM Participants.
BC4.3 SCOPE
BC4 applies to :-
(a) The Company;
(b) BM Participants;
(b) Externally Interconnected System Operators; and
(c) Network Operators.
TERRE Bids must follow the formats and rules in the TERRE Data Validation and
Consistency Rules
BC4.9 Outages of computer systems leading to the suspension of the TERRE market
The TERRE market operates in short processing times meaning that Planned Maintenance
Outages or unplanned computer system failures can result in the suspension of the TERRE
market.
Suspension of the TERRE market in GB will occur in the following circumstances:
(a) Loss of communication from The Company to the TERRE Central Platform
(b) Failure of the TERRE Central Platform to produce RR Acceptances
(c) Loss of communication from the TERRE Central Platform to The Company
(d) Loss of electronic logging devices to a large number of BM Participants
CONTENTS
(This contents page does not form part of the Grid Code)
BC5.1 PREQUALIFICATION...................................................................................................................2
BC5.1.1 Prequalification Timelines .................................................................................................3
BC5.2 FCR PREQUALIFICATION PROCESS .......................................................................................3
BC5.2.1 FCR Minimum Technical Requirements ............................................................................3
BC5.3 FRR PREEQUALIFICATION PROCESS ....................................................................................5
BC5.3.1 FRR Minimum Technical Requirements ...........................................................................5
BC5.4 RR PREQUALIFICATION PROCESS.........................................................................................5
BC5.4.1 RR Minimum Technical Requirements .............................................................................5
The Company shall list the current status and dates of potential status changes of
Balancing Services as Frequency Containment Reserves (FCR), Frequency
Restoration Reserves (FRR) or Replacement Reserves (RR) or existing GB.
Where a Balancing Service has been approved as a Standard Product or Specific
Product providing FCR, FRR or RR, The Companyshall ensure that prequalification
processes for that Balancing Service follows the processes as set out here.The
Company shall ensure that each relevant Balancing Service requires a formal
application from the FCR, FRR or RR provider to prequalify.
BC5.1.1.1 The following minimum timescales shall be apply to the FCR, FRR and RR
prequalification processes;
(a) Within 8 weeks of a formal application from the FCR, FRR or RR provider The
Company shall confirm the application is complete or incomplete (from the
perspective of information provision)
(b) If the application is incomplete the FCR, FRR, or RR provider shall submit the
additional required information within 4 weeks of the a request from The
Company or it will be presumed that the application has been withdrawn
(c) For units connected to distribution networks, The Company shall liaise with
the relevant DNO(s) to identify potential limitations imposed on the proposed
Balancing Services Provider by the distribution networks.
(d) Within 3 months of confirming that all information has been provided The
Company shall confirm if the potential FCR, FRR or RR provider meets the
requirements in BC5.2.1, BC5.3.1 or BC5.4.1 respectively.
BC5.1.1.2 The Company shall re-assess the qualification of FCR, FRR or RR
providing units or groups:
Each FCR providing unit and each FCR providing group shall;
(a) activate the agreed FCR by means of a proportional governor or load controller
reacting to frequency deviations or alternatively based on a monotonic piecewise
linear power-frequency characteristic in case of relay activated FCR.
(b) be capable of activating FCR within the frequency ranges specified in the
ECC.6.1.2.1.2.
(e) Each FCR provider shall be capable of making available to The Company, for each
of its FCR providing units and FCR providing groups, at least the following
information:
(iii) droop of the governor or load controller for Type C Power Generating Modules
and Type D Power Generating Modules acting as FCR providing units, or its
equivalent parameter for FCR providing groups consisting of Type A Power-
Generating Modules and/or Type B Power Generating Modules, and/or
Demand Units with Demand Response Active Power.
(f) An FCR provider shall guarantee the continuous availability of FCR, with the exception
of a forced outage of a FCR providing unit, during the period of time in which it is
obliged to provide FCR.
(g) Each FCR provider shall inform The Company, as soon as possible, about any
changes in the actual availability of its FCR providing unit and/or its FCR providing
group, in whole or in part, relevant for the results of this prequalification.
(a) voltage levels and connection points of the reserve providing units or groups;
(b) the DNO(s) who operate the distribution systems to which the reserve providing
untis or groups are connected;
(c) the type of active power reserves;
(d) the maximum reserve capacity provided by the reserve providing units or groups
at each connection point; and
(e) the maximum rate of change of active power for the reserve providing units or
groups.
The relevant DNOs will identify potential distribution network restrictions, based on
technical reasons, on the provision of the proposed Balancing Service
by the reserve providing groups or units.
(b) ensure that the FRR activation of the FRR providing units within a reserve
providing group can be monitored. For that purpose the FRR provider shall be
capable of supplying to The Company real-time measurements of the connection
point or another point of interaction agreed with The Company concerning:
(d) be capable of activating its complete manual reserve capacity on FRR within the
FRR full activation time;
(e) fulfil the FRR availability requirements;
(a) voltage levels and connection points of the reserve providing units or groups;
(b) the DNO(s) who operate the distribution systems to which the reserve providing
units or groups are connected;
(e) the maximum rate of change of active power for the reserve providing units or group
The relevant DNOs will identify potential distribution network restrictions, based on
technical reasons, on the provision of the proposed Balancing Service by the reserve
providing groups or units.
The Company shall ensure that each relevant Balancing Service prequalification
process shall, as a minimum, require the RR provider to submit a self-certification of
the RR Minimum Technical Requirements as defined in BC5.4.1 and BC5.4.2.
(a) activate RR in accordance with the setpoint received from The Company;
(b) ensure activation of complete reserve capacity on RR within the activation time
defined by The Company;
(d) ensure that the RR activation of the RR providing units within a reserve providing
group can be monitored. For that purpose, the RR provider shall be capable of
supplying to The Company real-time measurements of the connection point or
another point of interaction agreed with The Company:
(i) the time-stamped scheduled active power output, for each RR providing unit and
group and for each power generating module or demand unit of a RR providing
group with maximum active power output larger than or equal to 1.5 MW;
(ii) the time-stamped instantaneous active power, for each RR providing unit and
group, and for each power generating module or demand unit of aRR providing
group with a maximum active output than or ewqual to 1.5 MW;
(a) voltage levels and connection points of the reserve providing units or groups;
(b) the DNO(s) who operate the distribution systems to which the reserve providing
units or groups are connected;
CONTENTS
(This contents page does not form part of the Grid Code)
DRC.2 OBJECTIVE
The objective of the DRC is to:
DRC.2.1 List and collate all the data to be provided by each category of User to The Company under
the Grid Code.
DRC.2.2 List all the data to be provided by The Company to each category of User under the Grid
Code.
DRC.3 SCOPE
DRC.3.1 The DRC applies to The Company and to Users, which in this DRC means:-
(a) Generators (including those undertaking OTSDUW and/or those who own and/or
operate DC Connected Power Park Modules);
(b) Network Operators;
(c) DC Converter Station owners and HVDC System Owners;
(d) Suppliers;
(e) Non-Embedded Customers (including, for the avoidance of doubt, a Pumped Storage
Generator in that capacity);
(f) Externally Interconnected System Operators;
(g) Interconnector Users; and
(h) BM Participants.
DRC.3.2 For the avoidance of doubt, the DRC applies to both GC Code Users and EU Code Users
User’s.
User Schedule
All Suppliers 12
All BM Participants 8
Notes:
(1) Network Operators must provide data relating to Small Power Stations and/or
Customer Generating Plant Embedded in their Systems when such data is
requested by The Company pursuant to PC.A.3.1.4 or PC.A.5.1.4.
(2) The data in schedules 1, 14 and 15 need not be supplied in relation to Medium Power
Stations connected at a voltage level below the voltage level of the Subtransmission
System except in connection with a CUSC Contract or unless specifically requested by
The Company.
(3) Each Network Operator within whose System an Embedded Medium Power Station
not subject to a Bilateral Agreement or Embedded DC Converter Station not subject
to a Bilateral Agreement is situated shall provide the data to The Company in respect
of each such Embedded Medium Power Station or Embedded DC Converter
Station or HVDC System.
(4) In the case of Schedule 2, Generators, HVDC System Owners, DC Converter
Station owners or Network Operators in the case of Embedded Medium Power
Stations not subject to a Bilateral Agreement or Embedded DC Converter Stations
not subject to a Bilateral Agreement, would only be expected to submit data in relation
to Standard Planning Data as required by the Planning Code.
ABBREVIATIONS:
SPD = Standard Planning Data DPD = Detailed Planning Data
CUSC Contract = User data which may be CUSC App. Form = User data which may
submitted to the Relevant be submitted to the
Transmission Relevant
Licensees by The Transmission
Company, following the Licensees by The
acceptance by a User of Company, following an
a CUSC Contract. application by a User
for a CUSC Contract.
Note:
All parameters, where applicable, are to be measured at nominal System Frequency
+ these SPD items should only be given in the data supplied with the application for a CUSC
Contract.
* Asterisk items are not required for Small Power Stations and Medium Power Stations
Information is to be given on a Unit basis, unless otherwise stated. Where references to CCGT
Modules are made, the columns "G1" etc should be amended to read "M1" etc, as appropriate
□ These data items may be submitted to the Relevant Transmission Licensees from The
Company in respect of the National Electricity Transmission System. The data may be
submitted to the Relevant Transmission Licensees in a summarised form e.g. network model;
the data transferred will have been originally derived from data submitted by Users to The
Company.
■ these data items may be submitted to the Relevant Transmission Licensee from The
Company in respect to Relevant Units only. The data may be submitted to the Relevant
Transmission Licensee in a summarised form e.g. network model; the data transferred will
have been originally derived from data submitted by Users to The Company.
Note:- the above data item relating to armature winding direct-current resistance need only be provided by Generators in relation to
Generating Units or Synchronous Generating Units within Power Generating Modules commissioned after 1st March
1996 and in cases where, for whatever reason, the Generator is aware of the value of the data item.
TIME CONSTANTS
(Short-circuit and Unsaturated)
Direct axis transient time constant S □ DPD I
(PC.A.5.3.2(a))
Direct axis sub-transient time constant S □ DPD I
(PC.A.5.3.2(a))
Quadrature axis sub-transient time constant S □ DPD I
(PC.A.5.3.2(a))
Stator time constant (PC.A.5.3.2(a)) S □ DPD I
MECHANICAL PARAMETERS
(PC.A.5.3.2(a))
The number of turbine generator masses □ DPD II
Diagram showing the Inertia and parameters Kgm2 □ DPD II
for each turbine generator mass for the DPD II
complete drive train
Diagram showing Stiffness constants and Nm/rad □ DPD II
parameters between each turbine generator DPD II
mass for the complete drive train
Number of poles □ DPD II
Relative power applied to different parts of % □ DPD II
the turbine
Torsional mode frequencies Hz □ DPD II
Modal damping decrement factors for the □ DPD II
different mechanical modes
Note: The data items requested under Option 1 below may continue to be provided by Generators in relation to Generating
Units on the System at 9 January 1995 (in this paragraph, the "relevant date") or they may provide the new data items set
out under Option 2. Generators must supply the data as set out under Option 2 (and not those under Option 1) for
Generating Unit and Synchronous Power Generating Unit excitation control systems commissioned after the relevant
date, those Generating Unit or Synchronous Power Generating Unit excitation control systems recommissioned for any
reason such as refurbishment after the relevant date and Generating Unit or Synchronous Power Generating Unit
excitation control systems where, as a result of testing or other process, the Generator is aware of the data items listed
under Option 2 in relation to that Generating Unit or Synchronous Power Generating Unit.
Option 1
Option 2
Note: The data items requested under Option 1 below may continue to be provided by Generators in relation to Generating Units
on the System at 9 January 1995 (in this paragraph, the "relevant date") or they may provide the new data items set out
under Option 2. Generators must supply the data as set out under Option 2 (and not those under Option 1) for Generating
Unit and Synchronous Power Generating Unit governor control systems commissioned after the relevant date, those
Generating Unit and Synchronous Power Generating Unit governor control systems recommissioned for any reason
such as refurbishment after the relevant date and Generating Unit and Synchronous Power Generating Unit governor
control systems where, as a result of testing or other process, the Generator is aware of the data items listed under Option 2
in relation to that Generating Unit and Synchronous Power Generating Unit.
Option 1
End of Option 2
Maximum Hz DPD II
Normal Hz DPD II
Minimum Hz DPD II
*Output Usable (on a monthly basis) MW SPD (except in relation to CCGT Modules when
(PC.A.3.2.2(b)) required on a unit basis under the Grid Code,
this data item may be supplied under Schedule
3)
Number & Type of Power Park Units within □ SPD
each Power Park Module (PC.A.3.2.2(k))
Number & Type of Offshore Power Park SPD
Units within each Offshore Power Park
String and the number of Offshore Power
Park Strings and connection point within
each Offshore Power Park Module
(PC.A.3.2.2.(k))
In the case where an appropriate Reference the SPD
Manufacturer’s Data & Performance Manufacturer’s
Report is registered with The Company then Data &
subject to The Company’s agreement, the Performance
report reference may be given as an Report
alternative to completion of the following
sections of this Schedule 1 to the end of page
11 with the exception of the sections marked
thus # below.
□ ■
Total number of AC filter banks Text DPD II
□ ■
Diagram of filter connections Diagram □ ■
DPD II
Type of equipment (e.g. fixed or variable) Text □ DPD II
Capacitive rating; or MVAr □ DPD II
Inductive rating; or MVAr □ DPD II
Operating range MVAr DPD II
□
Reactive Power capability as a function of Table DPD II
various MW transfer levels
MW Export
Nominal loading rate MW/s DPD I
Maximum (emergency) loading rate MW/s DPD I
MW Import DPD I
Nominal loading rate MW/s DPD I
Maximum (emergency) loading rate MW/s
□ DPD II
Maximum recovery time, to 90% of pre-fault s
loading, following an AC system fault or
severe voltage depression.
□ DPD II
Maximum recovery time, to 90% of pre-fault
loading, following a transient DC Network s
fault.
NOTE: Users are referred to Schedules 5 & 14 which set down data required for all Users directly
connected to the National Electricity Transmission System, including Power Stations. Generators
undertaking OTSDUW Arrangements and are utilising an OTSDUW DC Converter are referred to
Schedule 18.
This schedule contains the Genset Generation Planning Parameters required by The Company to
facilitate studies in Operational Planning timescales.
For a Generating Unit including those within a Power Generating Module (other than a Power Park Unit)
at a Large Power Station the information is to be submitted on a unit basis and for a CCGT Module or
Power Park Module at a Large Power Station the information is to be submitted on a module basis, unless
otherwise stated.
Where references to CCGT Modules or Power Park Modules at a Large Power Station are made, the
columns "G1" etc should be amended to read "M1" etc, as appropriate.
OUTPUT CAPABILITY
(PC.A.3.2.2)
Registered Capacity on a station and unit basis
(on a station and module basis in the case of a MW SPD
CCGT Module or Power Park Module at a
Large Power Station)
□ ■
Maximum Capacity on a Power Generating
Module basis and Synchronous Generating
Unit basis and Registered Capacity on a
Power Station basis)
REGIME UNAVAILABILITY
SYNCHRONISING PARAMETERS
OC2.4.2.1(a)
Notice to Deviate from Zero (NDZ) after 48 hour Mins ■ OC2
Shutdown
RUN-UP PARAMETERS
PC.A.5.3.2(f) & OC2.4.2.1(a)
Run-up rates (RUR) after 48 hour (Note that for DPD only a single value of run-up rate from Synch Gen to Registered
Shutdown: Capacity is required)
(See note 2 page 3)
MW Level 1 (MWL1) MW ■ OC2 -
MW Level 2 (MWL2) MW ■ OC2 -
DPD II
&
RUR from Synch. Gen to MWL1 MW/Mins ■ OC2
RUR from MWL1 to MWL2 MW/Mins ■ OC2
RUR from MWL2 to RC MW/Mins ■ OC2
Run-Down Rates (RDR): (Note that for DPD only a single value of run-down rate from Registered Capacity to de-
synch is required)
MWL2 MW ■ OC2
RDR from RC to MWL2 MW/Min ■ DPD II
OC2
MWL1 MW ■ OC2
RDR from MWL2 to MWL1 MW/Min ■ OC2
RDR from MWL1 to de-synch MW/Min ■ OC2
DATA to DATA
DATA DESCRIPTION UNITS RTL CAT. GENSET OR STATION DATA
CUSC CUSC G1 G2 G3 G4 G5 G6 STN
Contract App.
Form
REGULATION PARAMETERS
OC2.4.2.1(a)
Regulating Range MW ■ DPD II
Load rejection capability while still MW ■ DPD II
Synchronised and able to supply Load.
NOTES:
(1) To allow for different groups of Gensets within a Power Station (eg. Gensets with the same
operator) each Genset may be allocated to one of up to four Synchronising Groups. Within
each such Synchronising Group the single synchronising interval will apply but between
Synchronising Groups a zero synchronising interval will be assumed.
(2) The run-up of a Genset from synchronising block load to Registered Capacity or Maximum
Capacity is represented as a three stage characteristic in which the run-up rate changes at two
intermediate loads, MWL1 and MWL2. The values MWL1 & MWL2 can be different for each
Genset.
INFLEXIBILITY
OUTPUT PROFILES
CUSC CUSC
Contract App.
Form
In the case of Large Power Stations whose output MW F. yrs 1 - 7 Week 24 SPD
may be expected to vary in a random manner (eg.
wind power) or to some other pattern (eg. Tidal)
sufficient information is required to enable an
understanding of the possible profile
Notes: 1. The week numbers quoted in the Update Time column refer to standard weeks in the
current year.
Issue 5 Revision 38
MLP1 Designed Minimum Operating Level or
Minimum Regulating Level (for a CCGT
Module or Power Park Module, on a
modular basis assuming all units are
Synchronised)
DRC
Capacity
41 of 107
PAGE 1 OF 1
04 September 2019
SCHEDULE 5 - USERS SYSTEM DATA
PAGE 1 OF 11
The data in this Schedule 5 is required from Users who are connected to the National Electricity
Transmission System via a Connection Point (or who are seeking such a connection). Generators
undertaking OTSDUW should use DRC Schedule 18 although they should still supply data under Schedule 5
in relation to their User’s System up to the Offshore Grid Entry Point.
Table 5 (a)
A Single Line Diagram showing all or part of the User’s System is SPD
required. This diagram shall include:-
The Single Line Diagram may also include additional details of the ■ ■
User’s Subtransmission System, and the transformers connecting
the User’s Subtransmission System to a lower voltage. With The
Company’s agreement, it may also include details of the User’s
System at a voltage below the voltage of the Subtransmission
System.
The data below is all Standard Planning Data. Details are to be given for all circuits shown on the Single Line Diagram
Table 5 (d)
Issue 5 Revision 38
Years Node 1 Node 2 Rated Operating Positive Phase Sequence Zero Phase Sequence (self) Zero Phase Sequence (mutual)
Valid Voltage Voltage % on 100 MVA % on 100 MVA % on 100 MVA
kV kV
R X B R X B R X B
DRC
45 of 107
PAGE 4 OF 11
SCHEDULE 5 – USERS SYSTEM DATA
Notes
1. Data should be supplied for the current, and each of the seven succeeding Financial Years. This should be done by showing for
which years the data is valid in the first column of the Table.
04 September 2019
USERS SYSTEM DATA
Transformer Data (PC.A.2.2.5) (■ CUSC Contract & ■ CUSC Application Form)
The data below is all Standard Planning Data, and details should be shown below of all transformers shown on the Single Line Diagram. Details of
Winding Arrangement, Tap Changer and earthing details are only required for transformers connecting the User’s higher voltage system with its
Primary Voltage System.
Table 5 (e)
Issue 5 Revision 38
Years Name Trans- Rating Voltage Ratio Positive Phase Positive Phase Zero Winding Tap Changer Earthin
valid of former MVA Sequence Reactance Sequence Resistance Sequence Arr. g
Node % on Rating % on Rating React- Details
or ance (delete
Conn- % on as
ection HV LV Max. Min. Nom. Max. Min. Nom. Rating range step size type app.) *
Point Tap Tap Tap Tap Tap Tap +% to -% % (delete
as
ON/
app.)
Direct/
OFF Res/
Rea
ON/
OFF Direct/
Res/
ON/ Rea
OFF
DRC
46 of 107
Direct
ON/ /Res/
PAGE 5 OF 11
OFF Rea
ON/ Direct/
OFF Res/
Rea
SCHEDULE 5 – USERS SYSTEM DATA
ON/
OFF
Direct/
Res/
*If Resistance or Reactance please give impedance value
ON/OF Rea
Notes F
Direct/R
1. Data should be supplied for the current, and each of the seven succeeding Financial Years. This should be done by showing for which es/Rea
years the data is valid in the first column of the Table
2. For a transformer with two secondary windings, the positive and zero phase sequence leakage impedances between the HV and LV1, HV Direct
and LV2, and LV1 and LV2 windings are required. /Res/
04 September 2019
Rea
USER’S SYSTEM DATA
Switchgear Data (PC.A.2.2.6(a)) (■ CUSC Contract & CUSC Application Form ■)
The data below is all Standard Planning Data, and should be provided for all switchgear (ie. circuit breakers, load disconnectors and
disconnectors) operating at a Supergrid Voltage, and also in Scotland and Offshore, operating at 132kV. In addition, data should be
provided for all circuit breakers irrespective of voltage located at a Connection Site which is owned by a Relevant Transmission Licensee
or operated or managed by The Company.
Table 5(f)
Issue 5 Revision 38
Years Connect-ion Switch Rated Operating Rated short-circuit Rated short-circuit peak Rated rms DC time
Valid Point No. Voltage kV Voltage breaking current making current continuous constant at
rms kV rms current testing of
(A) asymmetri
cal
3 Phase 1 Phase 3 Phase 1 Phase breaking
kA rms kA rms kA peak kA peak ability(s)
DRC
47 of 107
PAGE 6 OF 11
SCHEDULE 5 –USERS SYSTEM DATA
Notes
2. Data should be supplied for the current, and each of the seven succeeding Financial Years. This should be done by showing for which years the
data is valid in the first column of the Table
04 September 2019
SCHEDULE 5 –USERS SYSTEM DATA
PAGE 7 OF 11
Table 5(g)
(d) For Generating Units (other than Power Park Units) ■ DPD II
having a circuit breaker at the generator terminal voltage
clearance times for electrical faults within the
Generating Unit zone must be declared.
(d) an indication of which items of equipment may be out of service simultaneously during
Planned Outage conditions
(b) for all transformers connecting the User's Subtransmission System to a lower voltage:
Rated MVA
Voltage Ratio
Positive phase sequence resistance
Positive Phase sequence reactance
Tap-changer range
Number of tap steps
Tap-changer type: on-load or off-circuit
AVC/tap-changer time delay to first tap movement
AVC/tap-changer inter-tap time delay
(The Company advises Network Operators of National Years 2-5 Week 28)
Electricity Transmission System outages affecting their
Systems)
Network Operator informs The Company if unhappy with ■ " Week 30 OC2
proposed outages)
Network Operator details of relevant outages affecting the ■ Year 1 Week 32 OC2
Total System (OC2.4.1.3.3)
(The Company informs Users of aspects that may affect Year 1 Week 34)
their Systems) (OC2.4.1.3.3)
Users inform The Company if unhappy with aspects as ■ Year 1 Week 36 OC2
notified
(OC2.4.1.3.3)
The data below is to be provided to The Company as required for compliance with the European
Commission Regulation No 543/2013 (OC2.4.2.3). Data provided under Article Numbers 7.1(a), 7.1(b),
15.1(a), 15.1(b), and 15.1(c) and 15.1(d) is to be provided using MODIS.
ECR USERS
FREQUENCY OF
ARTICLE DATA DESCRIPTION PROVIDING
SUBMISSION
No. DATA
* Energy Identification Coding (EIC) is a coding scheme that is approved by ENTSO-E for standardised electronic data interchanges
and is utilised for reporting to the Central European Transparency Platform. The Company will act as the Local Issuing Office for IEC in
respect of GB.
All data in this schedule 7 is categorised as Standard Planning Data (SPD) and is required for existing and
agreed future connections. This data is only required to be updated when requested by The Company.
CODE DESCRIPTION
- No information collated under this Schedule will be transferred to the Relevant Transmission Licensees
CODE DESCRIPTION
CC Operation Diagram
OC2 Surpluses and OU requirements for each Generator over varying timescales
BC3 Location, amount, and Low Frequency Relay settings of any Low Frequency
Relay initiated Demand reduction for Demand which is Embedded.
- No information collated under this Schedule will be transferred to the Relevant Transmission
Licensees
1. The Transmission Licence requires The Company to publish annually the Seven Year
Statement which is designed to provide Users and potential Users with information to enable
them to identify opportunities for continued and further use of the National Electricity
Transmission System.
2. The Transmission Licence also requires The Company to offer terms for an agreement for
connection to and use of the National Electricity Transmission System and further
information will be given by The Company to the potential User in the course of the discussions
of the terms of such an agreement.
The following information is required from each Network Operator and from each Non-Embedded Customer. The data
should be provided in calendar week 24 each year (although Network Operators may delay the submission until
calendar week 28).
DATA DESCRIPTION F. Yr. F. Yr. F. Yr. F. Yr. F. Yr. F. Yr. F. Yr. F. Yr. UPDATE DATA CAT
0 1 2 3 4 5 6 7 TIME
LV1 ■ ■
LV2 ■ ■
LV3 ■ ■
EHV ■ ■
HV ■ ■
Traction ■ ■
Lighting ■ ■
User System Losses ■ ■
NOTES:
Demand and Active Energy data should relate to the point of connection to the National Electricity
Transmission System and should be net of the output (as reasonably considered appropriate by
the User) of all Embedded Small Power Stations, Medium Power Stations and Customer
Generating Plant. Auxiliary demand of Embedded Power Stations should be included in the
demand data submitted by the User at the Connection Point. Users should refer to the PC for a
full definition of the Demand to be included.
3. Demand profiles and Active Energy data should be for the total System of the Network Operator,
including all Connection Points, and for each Non-Embedded Customer. Demand Profiles
should give the numerical maximum demand that in the User's opinion could reasonably be imposed
on the National Electricity Transmission System.
4. In addition the demand profile is to be supplied for such days as The Company may specify, but
such a request is not to be made more than once per calendar year.
The following information is required from each Network Operator and from each Non-Embedded
Customer. The data should be provided in calendar week 24 each year (although Network Operators may
delay the submission until calendar week 28).
Connection Point:
Access Group:
Note: The following data block to be repeated for each Connection Point with the Access Group.
Name of associated Connection Point within PC.A.4.
the same Access Group: 3.1
Demand at associated Connection Point PC.A.4.
(MW) 3.1
Demand at associated Connection Point PC.A.4.
(MVAr) 3.1
Deduction made at associated Connection
Point for Small Power Stations, Medium PC.A.4.
Power Stations and Customer Generating 3.2(a)
Plant (MW)
Summated PC.A.3.1.
Capacity of all 4(a)
these Generating
Units
Where the Network Operator’s System places a constraint on the capacity of an Embedded Large
Power Station
PC.A.3.2.
Station Name
2(c)
PC.A.3.2.
Generating Unit
2(c)
System PC.A.3.2.
Constrained 2(c)(i)
Capacity
Reactive PC.A.3.2.
Despatch 2(c)(ii)
Network
Restriction
Where the Network Operator’s System places a constraint on the capacity of an Offshore
Transmission System at an Interface Point
Offshore PC.A.3.2.
Transmission 2(c)
System Name
Interface Point PC.A.3.2.
Name 2(c)
Maximum Export PC.A.3.2.
Capacity 2(c)
Maximum Import PC.A.3.2.
Capacity 2(c)
For each Embedded Small Power Station of 1MW and above, the following information is required, effective 2015 in line with the Week 24 data submissions.
DATA An Connection Generator Technology CHP Registered Lowest voltage Where it Control Control mode Loss of Loss of
Issue 5 Revision 38
DESCRIPTION Embedded Date unit Type (Y/N) capacity in node on the generates mode voltage target mains mains
Small (Financial Reference / Production MW (as most up-to-date electricity from and reactive protection protection
Power Year for type defined in the Single Line wind or PV, range or type settings
Station generator Distribution Diagram to the target pf (as
reference connecting Code) which it geographical appropriate)
unique to after week connects or location of the
each 24 2015) where it will primary or
Network export most of higher voltage
Operator its power substation to
which it
connects
DATA CAT PC.A.3.1.4 PC.A.3.1.4 PC.A.3.1.4 PC.A.3 PC.A.3.1.4 (a) PC.A.3.1.4 (a) PC.A.3.1.4 (a) PC.A.3.1.4 PC.A.3.1.4 PC.A.3.1.4 PC.A.3.1.4
(a) (a) (a) .1.4 (a) (a) (a) (a)
(a)
DRC
64 of 107
PAGE 3 OF 5
SCHEDULE 11 - CONNECTION POINT DATA
04 September 2019
SCHEDULE 11 - CONNECTION POINT DATA
PAGE 4 OF 5
NOTES:
1. 'F.Yr.' means 'Financial Year'. F.Yr. 1 refers to the current financial year.
2. All Demand data should be net of the output (as reasonably considered appropriate by the User) of all Embedded
Small Power Stations, Medium Power Stations and Customer Generating Plant. Generation and / or Auxiliary
demand of Embedded Large Power Stations should not be included in the demand data submitted by the User.
Users should refer to the PC for a full definition of the Demand to be included.
3. Peak Demand should relate to each Connection Point individually and should give the maximum demand that in
the User's opinion could reasonably be imposed on the National Electricity Transmission System. Users may
submit the Demand data at each node on the Single Line Diagram instead of at a Connection Point as long as
the User reasonably believes such data relates to the peak (or minimum) at the Connection Point.
In deriving Demand any deduction made by the User (as detailed in note 2 above) to allow for Embedded Small
Power Stations, Medium Power Stations and Customer Generating Plant is to be specifically stated as
indicated on the Schedule.
4. The Company may at its discretion require details of any Embedded Small Power Stations or Embedded
Medium Power Stations whose output can be expected to vary in a random manner (eg. wind power) or
according to some other pattern (eg. tidal power)
5. Where more than 95% of the total Demand at a Connection Point is taken by synchronous motors, values of the
Power Factor at maximum and minimum continuous excitation may be given instead. Power Factor data should
allow for series reactive losses on the User's System but exclude reactive compensation network susceptance
specified separately in Schedule 5.
6. Where a Reactive Despatch Network Restriction is in place which requires the generator to maintain a target
voltage set point this should be stated as an alternative to the size of the Reactive Despatch Network Restriction.
Table 11 (d)
Network
Operator
Aggregate
Registered
Capacity Number of
Fuel Type Total MW PGMs Comments
Biomass
Fossil brown coal/lignite
Fossil coal-derived gas
Fossil gas
Fossil hard coal
Fossil oil
Fossil oil shale
Fossil peat
Geothermal
Hydro pumped storage
Hydro run-of-river and poundage
Hydro water reservoir
Marine
Nuclear
Other renewable
Solar
Waste
Wind offshore
Wind onshore
Other
The following information is required from each Network Operator and where indicated with an
asterisk from Externally Interconnected System Operators and/or Interconnector Users
and a Pumped Storage Generator. Where indicated with a double asterisk, the information is
only required from Suppliers.
Demand Control
For each half hour MW Wks 2-8 ahead 1000 Mon OC1
For each half hour MW Days 2-12 ahead 1200 Wed OC1
Cumulative percentage of
Connection Point Demand
(Active Power) which can be
disconnected by the following times
from an instruction from The
Company
Notes:
1. Network Operators may delay the submission until calendar week 28.
2. No information collated under this Schedule will be transferred to the Relevant
Transmission Licensees (or Generators undertaking OTSDUW).
Note: All demand refers to that at the time of forecast National Electricity Transmission System
peak demand.
Network Operators may delay the submission until calendar week 28
No information collated under this schedule will be transferred to the Relevant
Transmission Licensees (or Generators undertaking OTSDUW).
The data in this Schedule 13 is all Standard Planning Data, and is required from all Users other than
Generators who are connected to the National Electricity Transmission System via a Connection Point
(or who are seeking such a connection). A data submission is to be made each year in Week 24 (although
Network Operators may delay the submission until Week 28). A separate submission is required for each
node included in the Single Line Diagram provided in Schedule 5.
DATA DESCRIPTION UNITS F.Yr F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA to
0 1 2 3 4 5 6 7 RTL
SHORT CIRCUIT INFEED TO THE CUSC CUSC
Contract App.
NATIONAL ELECTRICITY Form
TRANSMISSION SYSTEM FROM
USERS SYSTEM AT A CONNECTION
POINT
(PC.A.2.5)
□ ■
Name of node or Connection
Point
- at instant of fault kA □ ■
- Resistance % on 100 □ ■
- Reactance % on 100 □ ■
DATA DESCRIPTION UNITS F.Yr F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA to
0 1 2 3 4 5 6 7 RTL
SHORT CIRCUIT INFEED TO THE CUSC CUSC
Contract App.
NATIONAL ELECTRICITY Form
TRANSMISSION SYSTEM FROM
USERS SYSTEM AT A CONNECTION
POINT
Negative sequence
impedances
of User’s System as seen
from
the Point of Connection or
node on the Single Line
Diagram (as appropriate). If
no data is given, it will be
assumed that they are equal
to the positive sequence
values.
- Resistance % on □ ■
100
- Reactance % on □ ■
100
The data in this Schedule 14 is all Standard Planning Data, and is to be provided by Generators, with
respect to all directly connected Power Stations, all Embedded Large Power Stations and all
Embedded Medium Power Stations connected to the Subtransmission System. A data submission
is to be made each year in Week 24.
Fault infeeds via Unit Transformers
A submission should be made for each Generating Unit (including those which are part of a
Synchronous Power Generating Module) with an associated Unit Transformer. Where there is
more than one Unit Transformer associated with a Generating Unit, a value for the total infeed
through all Unit Transformers should be provided. The infeed through the Unit Transformer(s) should
include contributions from all motors normally connected to the Unit Board, together with any
generation (eg Auxiliary Gas Turbines) which would normally be connected to the Unit Board, and
should be expressed as a fault current at the Generating Unit terminals for a fault at that location.
DATA DESCRIPTION UNITS F.Yr. F.Yr. F.Yr F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA to
0 1 2 3 4 5 6 7 RTL
CUSC CUSC
(PC.A.2.5) Contract App.
Form
Name of Power Station □ ■
- at instant of fault kA □ ■
- Resistance % on 100 □ ■
- Reactance % on 100 □ ■
DATA DESCRIPTION UNITS F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA to
0 1 2 3 4 5 6 7 RTL
CUSC CUSC
(PC.A.2.5) Contract App.
Form
Number of Station □ ■
Transformer
- at instant of fault kA □ ■
- Resistance % on □ ■
100
- Reactance % on □ ■
100
Note 1. The pre-fault voltage provided above should represent the voltage within the range 0.95 to 1.05
that gives the highest fault current
Note 2. % on 100 is an abbreviation for % on 100 MVA
DATA DESCRIPTION UNITS F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA to
0 1 2 3 4 5 6 7 RTL
CUSC CUSC
(PC.A.2.5) Contract App.
Form
Name of Power Station □ ■
DATA UNITS F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA DATA
DESCRIPTION 0 1 2 3 4 5 6 7 to DESCRIPTION
RTL
CUSC CUSC App. Form
Contract
- A continuous time Graphical
trace and table and
showing the root tabular □ ■
mean square of the
positive, negative kA
and zero sequence versus s
components of the
fault current from the
time of fault inception
to 140ms after fault
inception at 10ms
intervals
DATA UNITS F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA DATA
DESCRIPTION 0 1 2 3 4 5 6 7 to DESCRIPTION
RTL
CUSC CUSC App. Form
Contract
For Power Park Units
that utilise a protective
control, such as a
crowbar circuit,
% on
- additional rotor MVA □ ■
resistance applied
to the Power Park
Unit under a fault % on
situation MVA □ ■
- additional rotor
reactance
applied to the
Power Park Unit
under a fault
situation.
Minimum zero
sequence impedance
of the equivalent at a □ ■
Common Collection
Busbar
Active Power MW
generated pre-fault □ ■
Items of reactive □ ■
compensation switched
in pre-fault
Note 1. The pre-fault voltage provided above should represent the voltage within the range 0.95 to 1.05
that gives the highest fault current
Issue 5 Revision 38
Mothballed Power Park Module (including Mothballed DC Connected Power Park Modules), Mothballed HVDC Systems,
Mothballed HVDC Converters or Mothballed DC Converters at a DC Converter station
Power Station_____________________________________ Generating Unit, Power Park Module or DC Converter Name (e.g. Unit
1) _______________________________
DATA UNITS DATA GENERATING UNIT DATA
DESCRIPTIO CAT
N <1 1-2 2-3 3-6 6-12 >12 Total MW
month months months months months months being
returned
MW output MW DPD II
that can be
returned to
DRC
service
77 of 107
Notes
PAGE 1 OF 3
1. The time periods identified in the above table represent the estimated time it would take to return the Mothballed Power Generating
Module, Mothballed Generating Unit, Mothballed Power Park Module (Mothballed DC Connected Power Park Modules),
Mothballed HVDC Systems, Mothballed HVDC Converters or Mothballed DC Converter at a DC Converter Station to service once
a decision to return has been made.
2. Where a Mothballed Power Generating Module, Mothballed Generating Unit, Mothballed Power Park Module (including a
Mothballed DC Connected Power Park Module), Mothballed HVDC System, Mothballed HVDC Converter or Mothballed DC
Converter at a DC Converter Station can be physically returned in stages covering more than one of the time periods identified in the
above table then information should be provided for each applicable time period.
3. The estimated notice to physically return MW output to service should be determined in accordance with Good Industry Practice
assuming normal working arrangements and normal plant procurement lead times.
4. The MW output values in each time period should be incremental MW values, e.g. if 150MW could be returned in 2 – 3 months and an
AT A DC CONVERTER STATION AND ALTERNATIVE FUEL DATA
additional 50MW in 3 – 6 months then the values in the columns should be Nil, Nil, 150, 50, Nil, Nil, 200 respectively.
5. Significant factors which may prevent the Mothballed Power Generating Module, Mothballed Generating Unit, Mothballed Power
GENERATING UNIT, MOTHBALLED POWER PARK MODULE (INCLUDING
Park Module (Mothballed DC Connected Power Park Modue). Mothballed HVDC System, Mothballed HVDC Converter or
Mothballed DC Converter at a DC Converter Station achieving the estimated values provided in this table, excluding factors relating
SCHEDULE 15 – MOTHBALLED POWER GENERATING MODULE, MOTHBALLED
04 September 2019
ALTERNATIVE FUEL INFORMATION
The following data items for alternative fuels need only be supplied with respect to each Generating Unit whose primary fuel is gas
including thos which form part of a Power Generating Module.
Issue 5 Revision 38
Power Station___________________________ Generating Unit Name (e.g. Unit 1) _____________________________
DATA DESCRIPTION UNITS DATA GENERATING UNIT DATA
CAT
1 2 3 4
Alternative Fuel Type Text DPD II Oil distillate Other gas* Other* Other*
(*please specify)
CHANGEOVER TO ALTERNATIVE FUEL
For off-line changeover:
Time to carry out off-line fuel changeover Minutes DPD II
Maximum output following off-line changeover MW DPD II
DRC
For on-line changeover:
78 of 107
PAGE 2 OF 3
Practice
Is changeover to alternative fuel used in normal
Text DPD II
operating arrangements?
Number of successful changeovers carried out in 0 / 1-5 / 0 / 1-5 / 0 / 1-5 / 0 / 1-5 /
CONNECTED POWER PARK MODULES), MOTHBALLED HVDC SYSTEMS,
the last Financial Year Text DPD II 6-10 / 11-20 / 6-10 / 11-20 / 6-10 / 11-20 / 6-10 / 11-20 /
GENERATING UNIT, MOTHBALLED POWER PARK MODULE (INCLUDING DC
04 September 2019
Issue 5 Revision 38
DATA DESCRIPTION UNITS DATA GENERATING UNIT DATA
CAT
1 2 3 4
CHANGEOVER BACK TO MAIN FUEL
For off-line changeover:
Time to carry out off-line fuel
Minutes
changeover
For on-line changeover:
Time to carry out on-line fuel
Minutes
changeover
Maximum output during on-line fuel
DRC
MW
79 of 107
changeover
PAGE 3 OF 3
Notes
1. Where a Generating Unit has the facilities installed to generate using more than one alternative fuel type details of each
alternative fuel should be given.
2. Significant factors and their effects which may prevent the use of alternative fuels achieving the estimated values provided
in this table (e.g. emissions limits, distilled water stocks etc.) should be appended separately.
AT A DC CONVERTER STATION AND ALTERNATIVE FUEL DATA
GENERATING UNIT, MOTHBALLED POWER PARK MODULE (INCLUDING
- No information collated under this Schedule will be transferred to the Relevant Transmission Licensees
MOTHBALLED DC CONNECTED POWER PARK MODULES), MOTHBALLED HVDC
SCHEDULE 15 – MOTHBALLED POWER GENERATING MODULES, MOTHBALLED
04 September 2019
Issue 5 Revision 38
BLACK START INFORMATION
The following data/text items are required from each Generator for each BM Unit at a Large Power Station as detailed in PC.A.5.7. Data is not
required for Generating Units that are contracted to provide Black Start Capability, Power Generating Modules Power Park Modules or Generating
Units that have an Intermittent Power Source. The data should be provided in accordance with PC.A.1.2 and also, where possible, upon request from
The Company during a Black Start.
Assuming all BM Units were running immediately prior to the Total Shutdown or Partial Shutdown and in the event of
loss of all external power supplies, provide the following information:
a) Expected time for the first and subsequent BM Units to be Synchronised, from the restoration of external power Tabular or DPD II
supplies, assuming external power supplies are not available for up to 24hrs Graphical
DRC
80 of 107
PAGE 1 OF 1
b) Describe any likely issues that would have a significant impact on a BM Unit’s time to be Synchronised arising as a Text DPD II
direct consequence of the inherent design or operational practice of the Power Station and/or BM Unit, e.g. limited
barring facilities, time from a Total Shutdown or Partial Shutdown at which batteries would be discharged.
c) Provide estimated Block Loading Capability from 0MW to Registered Capacity of each BM Unit based on the unit Tabular or DPD II
SCHEDULE 16 - BLACK START INFORMATION
being ‘hot’ (run prior to shutdown) and also ‘cold’ (not run for 48hrs or more prior to the shutdown). The Block Loading Graphical
Capability should be valid for a frequency deviation of 49.5Hz – 50.5Hz. The data should identify any required ‘hold’
points.
04 September 2019
SCHEDULE 17 - ACCESS PERIOD DATA
PAGE 1 OF 1
Submissions byUsers using this Schedule 17 shall commence in 2011 and shall then continue in
each year thereafter
Access Group
Comments
The data in this Schedule 18 is required from Generators who are undertaking OTSDUW and
connecting to a Transmission Interface Point.
OTSDUW DEMANDS
This Single Line Diagram shall depict the arrangement(s) of all of the ■ ■ SPD
existing and proposed load current carrying Apparatus relating to both
existing and proposed Interface Points and Connection Points,
showing electrical circuitry (ie. overhead lines, underground cables
(including subsea cables), power transformers and similar equipment),
operating voltages, circuit breakers and phasing arrangements
Operational Diagrams of all substations within the OTSDUW Plant and ■ ■ SPD
Apparatus
Issue 5 Revision 38
PPS PARAMETERS ZPS PARAMETERS Maximum Continuous
Ratings
DRC
84 of 107
PAGE 3 OF 24
Notes
1. For information equivalent STC Reference: STCP12-1m Part 3 – 2.1 Branch Data
2. In the case where an overhead line exists within the OTSDUW Plant and Apparatus the Mutual inductances should also be provided.
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
04 September 2019
OFFSHORE TRANSMISSION SYSTEM DATA
Issue 5 Revision 38
2 Winding Transformer Data (PC.A.2.2.5)
The data below is Standard Planning Data, and details should be shown below of all transformers shown on the Single Line Diagram
HV Node HV LV LV Rating Positive Phase Positive Phase Tap Changer Winding Earthing Earthing
Trans-former
(kV) Node (kV) (MVA) Sequence Reactance Sequence Resistance Arr. Method Imped
% on 100MVA % on 100 MVA (Direct /Res Ance
/Reac) method
Max Min Nom Max Min Nom Range Step type
Tap Tap Tap Tap Tap Tap +% to -% size
%
DRC
85 of 107
PAGE 4 OF 24
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
Notes
1 For information the corresponding STC Reference is STCP12-1: Part 3 – 2.4 Transformers
04 September 2019
USERS SYSTEM DATA (OTSUA)
The data below is all Standard Planning Data, and details should be shown below of all transformers shown on the Single Line Diagram.
Issue 5 Revision 38
HV VH LV VL PSS/E Rating Transfo Positive Phase Positive Phase Taps Earthin EQUIVALENT T ZPS PARAMETERS (FLIP) The The
NODE (kV) NODE (kV) Circuit (MVA) rmer Sequence Sequence g Compa Compa
Reactance Resistance Impeda ny nyCode
% on 100MVA % on 100 MVA nce Sheet
Method
Max Min Nom Max Min Nom Range Step Type Winding ZOH ZOL ZOT
Tap Tap Tap Tap Tap Tap +% to -% size (onload Arrange Dflt X/R =20
% Offload ment
R0H X0H R0L X0L R0T X0T
% % % % % %
100 100 100 100 100 100
MVA MVA MVA MVA MVA MVA
DRC
86 of 107
PAGE 5 OF 24
Notes
04 September 2019
OFFSHORE TRANSMISSION SYSTEM DATA
Issue 5 Revision 38
Circuit Breaker Data (PC.A.2.2.6(a))
The data below is all Standard Planning Data, and should be provided for all OTSUA switchgear (ie. circuit breakers, load disconnectors
and disconnectors)
Location Name Rated Operatin Make Model Type Year Circuit Minimum Total Continuo Fault Rating Fault Break Fault Break Fault Make Fault Rating Fault Break Fault Break Fault Make DC time
Voltage g Voltage Commission Breaker Protection & Time us (RMS Rating (RMS Rating (Peak Rating (Peak (RMS Rating (RMS Rating (Peak Rating (Peak constant at
DRC
ed (mS) Trip Relay (mS) Rating Symmetrical) Symmetrical) Asymmetrical) Asymmetrical) Symmetrical) Symmetrical) Asymmetrical) Asymmetrical) testing of
87 of 107
(mS) (A) (3 phase) (3 phase) (kA) (3 phase) (kA) (3 phase) (kA) (1 phase) (1 phase) (kA) (1 phase) (kA) (1 phase) (kA) asymmetrical
(MVA) (MVA) breaking ability
PAGE 6 OF 24
(s)
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
04 September 2019
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 7 OF 24
Notes:
1.For information STC Reference: STCP12-1: Part 3 - 2.5 Reactive Compensation Equipment
2. Data relating to continuously variable reactive compensation equipment (such as statcoms or SVCs)
should be entered on the SVC Modelling table.
3. For the avoidance of doubt this includes any AC Reactive Compensation equipment included within the
OTSDUW DC Converter other than harmonic filter data which is to be entered in the harmonic filter data
table.
PC.A.2.4.1(e) A mathematical representation in block diagram format to model the control of any
dynamic compensation plant. The model should be suitable for RMS dynamic stability
type studies in which the time constants used should not be less than 10ms.
Issue 5 Revision 38
HV LV Control Norminal Target Max Min Slope Voltage Normal R1 X1 R0 X0 Transf. Connection
Node Node Node Voltage Voltage MVAr MVAr % Dependant Running PPS_R PPS_X ZPS_R ZPS_X Winding (Direct/Tert
(kV) (kV) at HV at HV Q Limit Mode Type iary)
DRC
89 of 107
PAGE 8 OF 24
Notes:
1.For information the equivalent STC Ref,erence is: STCP12-1: Part 3 - 2.7 SVC Modelling Data
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
04 September 2019
SCHEDULE 18 - OFFSHORE TRANSMISSION SYSTEM DATA
PAGE 9 OF 24
Filter Description
Manufacturer Model Filter Type Filter connection Notes
type (Delta/Star,
Grounded/
Ungrounded)
Parameter as applicable
Filter Capacitance Inductance (milli- Resistance Notes
Component (R, (micro-Farads) Henrys) (Ohms)
C or L)
Filter frequency characteristics (graphs) detailing for frequency range up to 10kHz and higher
Notes:
1. For information STC Reference: STCP12-1: Part 3 - 2.8 Harmonic Filter Data
The information listed below may be requested by The Company from each User undertaking OTSDUW
with respect to any Interface Point or Connection Point to enable The Company to assess transient
overvoltage on the National Electricity Transmission System.
(a) Busbar layout plan(s), including dimensions and geometry showing positioning of any current and
voltage transformers, through bushings, support insulators, disconnectors, circuit breakers, surge
arresters, etc. Electrical parameters of any associated current and voltage transformers, stray
capacitances of wall bushings and support insulators, and grading capacitances of circuit breakers;
(b) Electrical parameters and physical construction details of lines and cables connected at that busbar.
Electrical parameters of all plant e.g., transformers (including neutral earthing impedance or zig-zag
transformers if any), series reactors and shunt compensation equipment connected at that busbar
(or to the tertiary of a transformer) or by lines or cables to that busbar;
(c) Basic insulation levels (BIL) of all Apparatus connected directly, by lines or by cables to the busbar;
(d) Characteristics of overvoltage Protection devices at the busbar and at the termination points of all
lines, and all cables connected to the busbar;
(e) Fault levels at the lower voltage terminals of each transformer connected to each Interface Point or
Connection Point without intermediate transformation;
(f) The following data is required on all transformers within the OTSDUW Plant and Apparatus.
(g) An indication of which items of equipment may be out of service simultaneously during Planned
Outage conditions.
The information given below, both current and forecast, where not already supplied in this Schedule 14
may be requested by The Company from each User if it is necessary for The Company to evaluate the
production/magnification of harmonic distortion on National Electricity Transmission System. The
impact of any third party Embedded within the User’s System should be reflected:-
(a) Overhead lines and underground cable circuits (including subsea cables) of the User's OTSDUW
Plant and Apparatus must be differentiated and the following data provided separately for each
type:-
(b) for all transformers connecting the OTSDUW Plant and Apparatus to a lower voltage:-
Rated MVA
Voltage Ratio
Positive phase sequence resistance
Positive phase sequence reactance
Equivalent positive phase sequence interconnection impedance with other lower voltage points
The minimum and maximum Demand (both MW and MVAr) that could occur
Harmonic current injection sources in Amps at the Connection Points and Interface Points
(d) an indication of which items of equipment may be out of service simultaneously during Planned
Outage conditions
The information listed below, where not already supplied in this Schedule 14, may be requested by The
Company from each User undertaking OTSDUW with respect to any Connection Point or Interface Point
if it is necessary for The Company to undertake detailed voltage assessment studies (eg to examine
potential voltage instability, voltage control co-ordination or to calculate voltage step changes on the
National Electricity Transmission System).
(a) For all circuits of the User’s OTSDUW Plant and Apparatus:-
(b) for all transformers connecting the User's OTSDUW Plant and Apparatus to a lower voltage:-
Rated MVA
Voltage Ratio
Positive phase sequence resistance
Positive Phase sequence reactance
Tap-changer range
Number of tap steps
Tap-changer type: on-load or off-circuit
AVC/tap-changer time delay to first tap movement
AVC/tap-changer inter-tap time delay
The information listed below, both current and forecast, and where not already supplied under this Schedule
14, may be requested by The Company from each User undertaking OTSDUW with respect to any
Connection Point or Interface Point where prospective short-circuit currents on Transmission equipment
are close to the equipment rating.
(a) For all circuits of the User’s OTSDUW Plant and Apparatus:-
Positive phase sequence resistance
Positive phase sequence reactance
Positive phase sequence susceptance
Zero phase sequence resistance (both self and mutuals)
Zero phase sequence reactance (both self and mutuals)
Zero phase sequence susceptance (both self and mutuals)
(b) for all transformers connecting the User's OTSDUW Plant and Apparatus to a lower voltage:-
Rated MVA
Voltage Ratio
Positive phase sequence resistance (at max, min and nominal tap)
Positive Phase sequence reactance (at max, min and nominal tap)
Zero phase sequence reactance (at nominal tap)
Tap changer range
Earthing method: direct, resistance or reactance
Impedance if not directly earthed
Fault infeed data to be submitted by OTSDUW Plant and Apparatus providing a fault infeed (including
OTSDUW DC Converters) (PC.A.2.5.5)
A submission is required for OTSDUW Plant and Apparatus (including OTSDUW DC Converters at each
Transmission Interface Point and Connection Point. The submission shall represent operating
conditions that result in the maximum fault infeed. The fault current from all auxiliaries of the OTSDUW Plant
and Apparatus at the Transmission Interface Point and Connection Point shall be included. The fault
infeed shall be expressed as a fault current at the Transmission Interface Point and also at each
Connection Point.
Should actual data in respect of fault infeeds be unavailable at the time of the application for a CUSC
Contract or Embedded Development Agreement, a limited subset of the data, representing the maximum
fault infeed that may result from the OTSDUW Plant and Apparatus, shall be submitted. This data will, as a
minimum, represent the root mean square of the positive, negative and zero sequence components of the
fault current for both single phase and three phase solid faults at each Connection Point and Interface
Point at the time of fault application and 50ms following fault application. Actual data in respect of fault
infeeds shall be submitted to The Company as soon as it is available, in line with PC.A.1.2.
DATA DESCRIPTION UNITS F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. F.Yr. DATA to RTL
0 1 2 3 4 5 6 7
CUSC CUSC
(PC.A.2.5) Contract App.
Form
Name of OTSDUW Plant and
Apparatus
□ ■
Note 1. The pre-fault voltage provided above should represent the voltage within the range 0.95 to 1.05
that gives the highest fault current
Prefault load 6hr 95% Line 580 132 95% Line 540 123 95% Line 465 106
exceeds line 20m Line 580 132 Line 540 123 Line 465 106
prefault 10m mva Line 580 132 mva Line 540 123 mva Line 465 106
continuous rating
5m 125 Line 580 132 116 Line 540 123 100 Line 465 106
3m Line 580 132 Line 540 123 Line 465 106
6hr 90% Line 580 132 90% Line 540 123 90% Line 465 106
20m Line 580 132 Line 540 123 Line 465 106
Short Term 10m mva Line 580 132 mva Line 540 123 mva Line 465 106
Overloads 5m 118 Line 580 132 110 Line 540 123 95 Line 465 106
3m Line 580 132 Line 540 123 Line 465 106
Limiting Item 6hr 84% Line 580 132 84% Line 540 123 84% Line 465 106
and permitted 20m Line 590 135 Line 545 125 Line 470 108
overload 10m mva Line 630 144 mva Line 580 133 mva Line 495 113
values 5m 110 Line 710 163 103 Line 655 149 89 Line 555 126
for different 3m Line 810 185 Line 740 170 Line 625 143
times and
pre-fault loads 6hr 75% Line 580 132 75% Line 540 123 75% Line 465 106
20m Line 595 136 Line 555 126 Line 475 109
10m mva Line 650 149 mva Line 600 137 mva Line 510 116
5m 99 Line 760 173 92 Line 695 159 79 Line 585 134
3m Line 885 203 Line 810 185 Line 685 156
6hr 60% Line 580 132 60% Line 540 123 60% Line 465 106
20m Line 605 138 Line 560 128 Line 480 110
10m mva Line 675 155 mva Line 620 142 mva Line 530 121
5m 79 Line 820 187 73 Line 750 172 63 Line 635 145
3m Line 985 226 Line 900 206 Line 755 173
6hr 30% Line 580 132 30% Line 540 123 30% Line 465 106
20m Line 615 141 Line 570 130 Line 490 112
10m mva Line 710 163 mva Line 655 150 mva Line 555 127
5m 39 Line 895 205 36 Line 820 187 31 Line 690 158
3m Line 1110 255 Line 1010 230 Line 845 193
6hr
20m
10m
5m
3m
6hr
20m
10m
5m
3m
Notes or
Restrictions
Detailed
Notes: 1. For information the equivalent STC Reference: STCP12-1: Part 3 - 2.6 Thermal Ratings
2. The values shown in the above table is example data.
Protection Schedules(PC.A.6.3)
Data schedules for the protection systems associated with each primary plant item including:
Protection, Intertrip Signalling & operating times
Intertripping and protection unstabilisation initiation
Synchronising facilities
Delayed Auto Reclose sequence schedules
A diagram of the scheme and an explanation of how the system will operate and what plant will be affected
by the scheme’s operation.
Substation: _______________________________
A diagram of the scheme and an explanation of how the system will operate and what plant will be effected
by the schemes operation.
Substation:________________________________
A diagram of the scheme and an explanation of how the system will operate and what plant will be effected
by the schemes operation
Substation: __________________________
Location Details:
Transmission Interface
Generator Interface
1. Substation Type:
2. Voltage Control: (short description of voltage control system. To include mention of modes ie
Voltage, manual etc. Plus control step increments ie 0.5%-0.33kV?)
3. Energisation Switching Information: (The standard energisation switching process from dead.)
4. Intertrip Systems:
5. Reactive Plant Outage: (A short explanation of any system re-configurations required to facilitate
the outage of any reactive plant which form part of the OTSDUW Plant and Apparatus equipment.
Also any generation restrictions required).
6. Harmonic Filter Outage: (An explanation as to any OTSDUW Plant and Apparatus reconfigurations
required to facilitate the outage and maintain the system within specified Harmonic limits, also any
generation restrictions required).
□ ■
If the busbars at the Interface Point or Section SPD
Connection Point are normally run in separate Number
sections identify the section to which the
OTSDUW DC Converter configuration is □ ■ SPD+
connected MW
OTSDUW DC CONVERTER
TRANSFORMER
(PC.A.5.4.3.1)
MVA □ DPD II
Rated MVA
□
Winding arrangement kV DPD II
□
Nominal primary voltage kV DPD II
Nominal secondary (converter-side) voltage(s) □
Positive sequence reactance % on □ DPD II
Maximum tap MVA □ DPD II
Nominal tap % on DPD II
Minimum tap MVA
Positive sequence resistance % on □ DPD II
□
Maximum tap MVA DPD II
□
Nominal tap □
DPD II
Minimum tap % on □ DPD II
Zero phase sequence reactance MVA □ DPD II
Tap change range % on DPD II
Number of steps MVA
% on
MVA
% on
MVA
+% / -%
□
Details of any large or small signal modulating DPD II
controls, such as power oscillation Diagram
damping controls or sub-synchronous
oscillation damping controls, that have not
been submitted as part of the above
control system data.
CONTENTS
(This contents page does not form part of the Grid Code)
GC.2 SCOPE
GC.2.1 The General Conditions apply to all Users (including, for the avoidance of doubt, The Company).
GC.6 MISCELLANEOUS
GC.6.1 Data and Notices
GC.6.1.1 Data and notices to be submitted either to The Company or to Users under the Grid Code (other than
data which is the subject of a specific requirement of the Grid Code as to the manner of its delivery) shall
be delivered in writing either by hand or sent by first-class pre-paid post, or by facsimile transfer or by
electronic mail to a specified address or addresses previously supplied by The Company or the User (as
the case may be) for the purposes of submitting that data or those notices.
GC.6.1.2 References in the Grid Code to “in writing” or “written” include typewriting, printing, lithography, and other
modes of reproducing words in a legible and non-transitory form and in relation to submission of data and
notices includes electronic communications.
GC.6.1.3 Data delivered pursuant to paragraph GC.6.1.1, in the case of data being submitted to The Company,
shall be addressed to the Transmission Control Centre at the address notified by The Company to each
User prior to connection, or to such other Department within The Company or address, as The Company
may notify each User from time to time, and in the case of notices to be submitted to Users, shall be
addressed to the chief executive of the addressee (or such other person as may be notified by the User in
writing to The Company from time to time) at its address(es) notified by each User to The Company in
writing from time to time for the submission of data and service of notices under the Grid Code (or failing
which to the registered or principal office of the addressee).
GC.6.1.4 All data items, where applicable, will be referenced to nominal voltage and Frequency unless otherwise
stated.
GC.12.3 The Company has obligations under the EMR Documents to inform EMR Administrative Parties
of certain data. The Company may pass on User data to an EMR Administrative Party where The
Company is required to do so under an EMR Document.
GC.12.4 The Company may use User data for the purpose of carrying out its EMR Functions.
EDL Instruction Interface Valid Reason Codes Issue 2 23rd Jul 2001
The data to be submitted in respect of OC2.4.1.2.3 (a) and OC2.4.1.2.4 (b) and (c) need only be in
respect of dates on or after 1 April 2005.
GC.A.3 Cut-over
GC.A.3.1 It is anticipated that it will be appropriate for arrangements to be put in place for final transition to BETTA in
the period up to and following (for a temporary period) Go-Live, for the purposes of:
(a) managing the transition from operations under the Grid Code as in force immediately prior to Go-
Active to operations under the GB Grid Code and the BSC as in force on and after Go-Active;
PART B
GC.B.1 Introduction
GCB.1.1 This Appendix Part B to the General Conditions deals with issues arising out of the transition associated
with the approval and implementation of Grid Code Modification Proposal GC0112 (Modifications
relating to the transfer of the system operator functions from NGET to NGESO).
GC.B.1.2 This Appendix Part B sets out the arrangements such that:
B.1.2.1 the Post GC0112 Grid Code reflects the Transfer of the System Operator Role;
B.1.2.2 certain amendments are made to Grid Code Related Agreements/Documents to reflect the
Transfer of the System Operator Role,
B.1.2.2 arrangements can be put in place prior to the SO Transfer Date to enable the transition of the
operations with NGET under the Pre GC0112 Grid Code to operations with NGESO under the
Post GC0112 Grid Code; and
GC.B.1.3 The provisions of the Post GC0112 Grid Code shall be suspended until the SO Transfer Date except for
this Appendix Part B (and any related definitions within it) which will take immediate effect on the
Implementation Date for GC0112.
Issue 5 Revision 33 GC 5 April 2019
15 of 15
GC.B.1.4 In this (and solely for the purposes of this) Appendix Part B the following terms have the following
meaning:
B.1.4.1 the term “Grid Code Related Agreements/Documents" shall mean each or any of those
agreements or documents entered into under or envisaged by the Pre GC0112 Grid Code prior t the
SO Transfer Date which continue on and after the SO Transfer Date;
B.1.4.2 the term “GC0112" shall mean Grid Code Modification Proposal 0112 (Amendments relating to the
transfer of the system operator functions from NGET to NGESO);
B.1.4.3 the term “NGET” shall mean National Grid Electricity Transmission plc;
B.1.4.4 the term “NGESO” shall mean National Grid Electricity System Operator Limited;
B.1.4.5 the term “Post GC0112 Grid Code" means the version of the Grid Code as amended by GC 0112;
B.1.4.6 the term “Pre GC Grid Code” means the version of the Grid Code prior to amendment by GC0112;
B.1.4.7 the term “SO Transfer Date” means the date on which NGET’s Transmission Licence is transferred
in part to NGESO to reflect the Transfer of the System Operator Role; and
B.1.4.8 the term “Transfer of the System Operator Role” means the the transfer, by means of the transfer in
part of NGET’s Transmission Licence, of the system operator role to NGESO.
GC.B.1.5 Without prejudice to any specific provision under this Appendix Part B as to the time within which or
the manner in which any party should perform its obligations under this Appendix Part B, where a
party is required to take any step or measure under this Appendix Part B, such requirement shall be
construed as including any obligation to:
B.1.5.2 do such associated or ancillary things as may be necessary to complete such step or measure
as quickly as reasonably practicable.
CONTENTS
(This contents page does not form part of the Grid Code)
PART A
GR.1 INTRODUCTION..................................................................................................................................... 2
PART B
GR.2 CODE ADMINISTRATOR ....................................................................................................................... 2
GR.3 GRID CODE REVIEW PANEL ................................................................................................................ 2
GR.4 APPOINTMENT OF PANEL MEMBERS ................................................................................................ 4
GR.5 TERM OF OFFICE .................................................................................................................................. 5
GR.6 REMOVAL FROM OFFICE .................................................................................................................... 5
GR.7 ALTERNATES........................................................................................................................................ 6
GR.8 MEETINGS ............................................................................................................................................ 7
GR.9 PROCEEDINGS AT MEETINGS ........................................................................................................... 9
GR.10 QUORUM ............................................................................................................................................... 9
GR.11 VOTING ............................................................................................................................................... 10
GR.12 PROTECTIONS FOR PANEL MEMBERS .......................................................................................... 10
PART C
GR.13 GRID CODE MODIFICATION REGISTER .......................................................................................... 11
GR.14 CHANGE CO-ORDINATION ............................................................................................................... 11
GR.15 GRID CODE MODIFICATION PROPOSALS ...................................................................................... 11
GR.16 SIGNIFICANT CODE REVIEW ............................................................................................................ 14
GR.17 AUTHORITY LET MODIFICATIONS ................................................................................................... 16
GR.18 GRID CODE MODIFICATION PROPOSAL EVALUATION................................................................. 18
GR.19 PANEL PROCEEDINGS ...................................................................................................................... 19
GR.20 WORKGROUPS .................................................................................................................................. 20
GR.21 THE CODE ADMINISTRATOR CONSULTATION .............................................................................. 23
GR.22 GRID CODE MODIFICATION REPORTS ........................................................................................... 25
GR.23 URGENT MODIFICATIONS ................................................................................................................ 28
GR.24 SELF-GOVERNANCE ......................................................................................................................... 30
GR.25 IMPLEMENTATION ............................................................................................................................. 33
GR.26 FAST TRACK ....................................................................................................................................... 34
GR.1 INTRODUCTION
GR.1.1 This section of the Grid Code sets out how the Grid Code is to be amended and the
procedures set out in this section, to the extent that they are dealt with in the Code
Administration Code of Practice, are consistent with the principles contained in the Code
Administration Code of Practice. Where inconsistencies or conflicts exist between the
Grid Code and the Code Administration Code of Practice, the Grid Code shall take
precedence.
GR.1.2 There is a need to bring proposed amendments to the attention of Users and others, to
discuss such proposals and to report on them to the Authority and in furtherance of this,
the Governance Rules set out the functions of a Grid Code Review Panel and
Workgroups and for consultation by the Code Administrator.
GR.1.3 For the purpose of these Governance Rules the term “User” shall mean any person who
is under any obligation or granted any rights under the Grid Code.
PART B
GR.2.2 The Code Administrator shall in conjunction with other code administrators, maintain,
publish, review and (where appropriate) amend from time to time the Code
Administration Code of Practice approved by the Authority provided that any
amendments to the Code Administration Code of Practice proposed by the Code
Administrator are approved by the Grid Code Review Panel prior to being raised by the
Code Administrator, and any amendments to be made to the Code Administration
Code of Practice are approved by the Authority.
GR.3.1.1 The Grid Code Review Panel shall be the standing body to carry out the functions
referred to in GR.3.2
GR.3.1.2 The Grid Code Review Panel shall comprise the following members:
(a) the person appointed as the chairman of the Grid Code Review Panel (the “Panel
Chairman”) in accordance with GR.4.1, who shall (subject to GR.11.4) be a voting
member unless they are an employee of The Company in which case they will be a
non-voting member;
(b) the following members, appointed in accordance with GR.4.2 (a), who shall be non-
voting members:
(d) a secretary (the “Panel Secretary”), who shall be a person appointed and provided
by the Code Administrator to assist the Grid Code Review Panel and who shall be
responsible for the administration of the Grid Code Review Panel and Grid Code
Modification Proposals. The Panel Secretary will be a non-voting member of the
Grid Code Review Panel.
GR.3.2 Functions of the Grid Code Review Panel and the Code Administrator’s Role
(a) The Grid Code Review Panel shall have the functions assigned to it in these
Governance Rules.
(b) Without prejudice to GR.3.2(a) and to the further provisions of these Governance
Rules, the Grid Code Review Panel shall endeavour at all times to operate:
(d) Subject to notifying Users, the Code Administrator will, with the Authority’s
approval, apply to the Authority for a revision or revisions to the Implementation
Date where the Code Administrator becomes aware of any circumstances which is
likely to mean that the Implementation Date is unachievable, which shall include as
a result of a Legal Challenge, at any point following the approval of the Grid Code
Modification Proposal.
(e) In the event that the Authority’s decision to approve or not to approve a Grid Code
Modification Proposal is subject of Legal Challenge (and the party raising such
Legal Challenge has received from the relevant authority the necessary permission
to proceed) then the Code Administrator will, with the Authority’s approval, apply
to the Authority for a revision or revisions to the Proposed Implementation Date in
the Grid Code Modification Report in respect of such Grid Code Modification
Proposal as necessary such that if such Grid Code Modification Proposal were to
be approved following such Legal Challenge the Proposed Implementation Date
Issue 5 Revision 37 1 August 2019
would be achievable.
(f) Prior to making any request to the Authority for any revision pursuant to GR.3.2(d)
(including where it is necessary as a result of a Legal Challenge) or GR.3.2(e) the
Code Administrator shall consult on the revision with Users and such other person
who may properly be considered to have an appropriate interest in it in accordance
with GR.21.2 and GR.21.8. The request to the Authority shall contain copies of (and
a summary of) all written representations or objections made by consultees during
the consultation period.
(i) shall act impartially and in accordance with the requirements of the Grid Code;
and
(ii) shall not be representative of, and shall act without undue regard to the
particular interests of the persons or body of persons by whom he was
appointed as Panel Member and any Related Person from time to time.
(b) Such a person shall not be appointed as a Panel Member or an Alternate Member
(as the case may be) unless he shall have first:
(i) confirmed in writing to the Code Administrator for the benefit of all Users that
he agrees to act as a Panel Member or Alternate Member in accordance
with the Grid Code and acknowledges the requirements of GR.3.3 (a) and
GR.3.3(c);
(ii) where that person is employed, provided to the Panel Secretary a letter from
his employer agreeing that he may act as Panel Member or Alternate
Member, and that the requirement in GR.3.3(a)(ii) shall prevail over his
duties as an employee.
(c) A Panel Member or Alternate Member shall, at the time of appointment and upon
any change in such interests, disclose (in writing) to the Panel Secretary any such
interests (in relation to the Grid Code) as are referred to in GR.3.3(a)(ii).
(a) The Panel Chairman shall be a person appointed (or re-appointed) by The
Company, having particular regard to the views of the Grid Code Review Panel,
and shall act independently of The Company.
(b) A person shall be appointed or re-appointed as the Panel Chairman where the
Authority has approved such appointment or reappointment and The Company has
given notice to the Panel Secretary of such appointment, with effect from the date of
such notice or (if later) with effect from the date specified in such notice.
(b) The Citizens Advice or the Citizens Advice Scotland may appoint one person as a
Panel Member representing customers by giving notice of such appointment to the
Panel Secretary, and may remove and re-appoint by notice.
(c) The Company shall appoint the The Company representative referred to at
GR.3.1.2(c)(i) and shall give notice of the identity of such person to the Panel
Secretary, and may remove and re-appoint by notice to the Panel Secretary.
(d) The BSC Panel shall appoint a representative to be the member of the Grid Code
Review Panel referred to at GR.3.1.2(c) (iii) and shall give notice of the identity of
such person to the Panel Secretary, and may remove and re-appoint by notice to the
Panel Secretary.
GR.4.3. The Authority shall from time to time notify the Panel Secretary of the identity of the
Authority representative referred to at GR.3.1.2(b)(ii).
(a) If in the opinion of the Authority there is a class or category of person (whether or
not a User) who have interests in respect of the Grid Code but whose interests:
(i) are not reflected in the composition of Panel Members for the time being
appointed; but
(ii) would be so reflected if a particular person was appointed as an additional
Panel Member, then the Authority may at any time appoint (or re-appoint)
that person as a Panel Member by giving notice of such appointment to the
Panel Secretary but in no event shall the Authority be able to appoint more
than one person so that there could be more than one such Panel Member.
(b) A person appointed as a Panel Member pursuant to this GR.4.4 shall remain
appointed, subject to GR.5 and GR.6, notwithstanding that the conditions by virtue of
which he was appointed (for example that the interests he reflects are otherwise
reflected) may cease to be satisfied.
No person other than an individual shall be appointed a Panel Member or his alternate.
The term of office of a Panel Member, the Panel Chairman and Alternate Members
shall be a period expiring on 31 December every second year. A Panel Member, the
Panel Chairman and Alternate Member shall be eligible for reappointment on expiry of
his term of office.
GR.6.1 A person shall cease to hold office as the Panel Chairman, a Panel Member or an
Alternate Member:
(d) if the Grid Code Review Panel resolves (and the Authority does not veto such resolution
by notice in writing to the Panel Secretary within fifteen (15) Business Days) that he
should cease to hold office on grounds of his serious misconduct;
(e) if the Grid Code Review Panel resolves (and the Authority does not veto such resolution
by notice in writing to the Panel Secretary within fifteen (15) Business Days) that he
should cease to hold office due to a change in employer notwithstanding compliance with
GR.3.3(d).
GR.6.2 A Grid Code Review Panel resolution under GR.6.1(d) or (e) shall, notwithstanding any
other paragraph, require the vote in favour of at least all Panel Members less one (other
than the Panel Member or Alternate Member who is the subject of such resolution) and
for these purposes an abstention shall count as a vote cast in favour of the resolution. A
copy of any such resolution shall forthwith be sent to the Authority by the Panel
Secretary.
GR.6.3 A person shall not qualify for appointment as a Panel Member or Alternate Member if at
the time of the proposed appointment he would be required by the above to cease to hold
that office.
GR.6.4 The Panel Secretary shall give prompt notice to The Company, all Panel Members, all
Users and the Authority of the appointment or re-appointment of any Panel Member or
Alternate Member or of any Panel Member or Alternate Member ceasing to hold office
and publication on the Website and (where relevant details are supplied to the Panel
Secretary) despatch by electronic mail shall fulfil this obligation.
GR.7 ALTERNATES
The Panel Chairman shall preside at every meeting of the Grid Code Review Panel at
which he is present. If he is unable to be present at a meeting, he may appoint an
alternate (who shall be a senior employee of The Company) to act as the Panel
Chairman, who may or may not be a Panel Member. If neither the Panel Chairman nor
his alternate is present at the meeting within half an hour of the time appointed for holding
the meeting, the Panel Members present may appoint one of their number to be the
chairman of the meeting.
(a) At the same time that the parties entitled to vote in the relevant election appoint
Elected Panel Members under GR.4.2(a), they shall appoint the following Alternate
Members:
(i) one alternate representative of the Suppliers;
(ii) one alternate representative of the Onshore Transmission Licensees;
(iii) one alternate representative of the Offshore Transmission Licensees; and
(iv) two alternate representatives of the Generators.
In the event that the election process fails to appoint an Alternate Member for
any of the Elected Panel Members, each Elected Panel Member shall be entitled (but
not obligated) to each at their own discretion nominate their own Alternate Member.
(b) Any Panel Member that is not an Elected Panel Member shall be entitled (but not
obligated) to each at their own discretion nominate their own Alternate Member.
(c) A Panel Member shall give notice to the Panel Secretary in the event it will be
Issue 5 Revision 37 1 August 2019
represented by an Alternate Member for any one Grid Code Review Panel
meeting.
(d) Where a Panel Member has nominated an Alternate Member in accordance with
GR.7.2(a) or (b), they may remove such Alternate Member, by giving notice of such
removal, and any nomination of a different Alternate Member, to the Panel
Secretary. A Panel Member may not choose as his Alternate Member: any party
who is already acting as an Alternate Member for another Panel Member; or
another Panel Member.
(e) All information to be sent by the Panel Secretary to Panel Members pursuant to
these Governance Rules shall also be sent by the Panel Secretary to each
Alternate Member by electronic mail (where relevant details shall have been
provided by each Alternate Member).
(b) The Panel Secretary shall promptly notify all Panel Members and Users of
appointment or removal by any Panel Member of any alternate and publication on
the Website and (where relevant details have been provided to the Panel Secretary)
despatch by electronic mail shall fulfil this obligation.
(a) Where the Panel Chairman or a Panel Member has appointed an alternate:
(ii) the Alternate Member shall have the same voting rights the Panel Member in
whose place he is attending;
(iii) GR.8, GR.9, GR.10, GR.11 and GR.12 shall apply to the Alternate Member as
if he were the appointing Panel Member and a reference to a Panel Member
elsewhere in the Grid Code shall,unless the context otherwise requires,
include his duly appointed Alternate Member.
(iv) for the avoidance of doubt, the appointing Panel Member shall not enjoy any of
the rights transferred to the Alternate Member at any meeting at which, or in
relation to any matter on which, the Alternate Member acts on his behalf.
GR.8 MEETINGS
GR.8.1 Meetings of the Grid Code Review Panel shall be held at regular intervals and at least
Issue 5 Revision 37 1 August 2019
every 2 months at such time and such place as the Grid Code Review Panel shall
decide.
GR.8.2 A regular meeting of the Grid Code Review Panel may be cancelled if:
(a) the Panel Chairman considers, having due regard to the lack of business in the
agenda, that there is insufficient business for the Grid Code Review Panel to
conduct and requests the Panel Secretary to cancel the meeting;
(b) the Panel Secretary notifies all Panel Members, not less than five (5) Business
Days before the date for which the meeting is to be convened, of the proposal to
cancel the meeting; and
(c) by the time three (3) Business Days before the date for which the meeting is or is to
be convened, no Panel Member has notified the Panel Secretary that he objects to
such cancellation.
GR.8.3 If any Panel Member wishes, acting reasonably, to hold a special meeting (in addition to
regular meetings under GR.8.1) of the Grid Code Review Panel:
(a) he shall request the Panel Secretary to convene such a meeting and inform the
Panel Secretary of the matters to be discussed at the meeting;
(b) the Panel Secretary shall promptly convene the special meeting for a day as soon as
practicable but not less than five (5) Business Days after such request.
GR.8.4 Any meeting of the Grid Code Review Panel shall be convened by the Panel Secretary
by notice (which will be given by electronic mail if the relevant details are supplied to the
Panel Secretary) to each Panel Member (and to the Authority):
(a) setting out the date, time and place of the meeting and (unless the Grid Code
Review Panel has otherwise decided) given at least five (5) Business Days before
the date of the meeting;
(b) accompanied by an agenda of the matters for consideration at the meeting and any
supporting papers available to the Panel Secretary at the time the notice is given
(and the Panel Secretary shall circulate to Panel Members any late papers as and
when they are received by him).
GR.8.5 The Panel Secretary shall send a copy of the notice convening a meeting of the Grid
Code Review Panel, and the agenda and papers accompanying the notice, to the Panel
Members and Alternate Members, and publication on the Website and despatch by
electronic mail (if the relevant details are supplied to the Panel Secretary) shall fulfil this
obligation.
GR.8.6 Any Panel Member (or, at the Panel Member’s request, the Panel Secretary) may
notify matters for consideration at a meeting of the Grid Code Review Panel in addition
to those notified by the Panel Secretary under GR.8.4 by notice to all Panel Members
and persons entitled to receive notice under GR.8.5, not less than three (3) Business
Days before the date of the meeting.
GR.8.7 The proceedings of a meeting of the Grid Code Review Panel shall not be invalidated by
the accidental omission to give or send notice of the meeting or a copy thereof or any of
the accompanying agenda or papers to, or failure to receive the same by, any person
entitled to receive such notice, copy, agenda or paper.
GR.8.8 A meeting of the Grid Code Review Panel may consist of a conference between Panel
Members who are not all in one place but who are able (by telephone or otherwise) to
speak to each of the others and to be heard by each of the others simultaneously.
GR.8.9 With the consent of all Panel Members (whether obtained before, at or after any such
meeting) the requirements of this GR.8 as to the manner in and notice on which a
meeting of the Grid Code Review Panel is convened may be waived or modified
provided that no meeting of the Grid Code Review Panel shall be held unless notice of
GR.8.11 Where:
(a) any matter (not contained in the agenda and not notified pursuant to GR.8.4 and
GR.8.6) is put before a meeting of the Grid Code Review Panel, and
(b) in the opinion of the Grid Code Review Panel it is necessary (in view of the urgency
of the matter) that the Grid Code Review Panel resolve upon such matter at the
meeting, the Grid Code Review Panel may so resolve upon such matter, and the
Grid Code Review Panel shall also determine at such meeting whether the decision
of the Grid Code Review Panel in relation to such matter should stand until the
following meeting of the Grid Code Review Panel, in which case (at such following
meeting) the decision shall be reviewed and confirmed or (but not with effect earlier
than that meeting, and only so far as the consequences of such revocation do not
make implementation of the Grid Code or compliance by Users with it impracticable)
revoked.
GR.9.1 Subject as provided in the Grid Code, the Grid Code Review Panel may regulate the
conduct of and adjourn and reconvene its meetings as it sees fit.
GR.9.2 Meetings of the Grid Code Review Panel shall be open to attendance by a
representative of any User (including any Authorised Electricity Operator; The
Company or a Materially Affected Party), the Citizens Advice or the Citizens Advice
Scotland and any person invited by the Panel Chairman and/or any other Panel
Member.
GR.9.3 The Panel Chairman and any other Panel Member may invite any person invited by
them under GR.9.2, and/or any attending representative of a User, to speak at the
meeting (but such person shall have no vote).
GR.9.4 As soon as practicable after each meeting of the Grid Code Review Panel, the Panel
Secretary shall prepare and send (by electronic mail or otherwise) to Panel Members
the minutes of such meeting, which shall be (subject to GR.9.5) approved (or amended
and approved) at the next meeting of the Grid Code Review Panel after they were so
sent, and when approved (excluding any matter which the Grid Code Review Panel
decided was not appropriate for such publication) shall be placed on the Website.
GR.9.5 If, following the circulation of minutes (as referred to in GR.9.4), the meeting of the Grid
Code Review Panel at which they were to be approved is cancelled pursuant to GR.8.2,
such minutes (including any proposed changes thereto which have already been
received) shall be recirculated with the notification of the cancellation of the meeting of
the Grid Code Review Panel. Panel Members shall confirm their approval of such
minutes to the Panel Secretary (by electronic mail) no later than five (5) Business Days
following such minutes being re-circulated. If no suggested amendments are received
within such five (5) Business Days period, the minutes will be deemed to have been
approved. If the minutes are approved, or deemed to have been approved, (excluding
any matter which the Grid Code Review Panel decided was not appropriate for such
publication) they shall be placed on the Website. If suggested amendments are received
within such five (5) Business Days period, the minutes shall remain unapproved and the
process for approval (or amendment and approval) of such minutes at the next meeting of
the Grid Code Review Panel, as described in GR.9.4, shall be followed.
GR.10 QUORUM
GR.10.1 No business shall be transacted at any meeting of the Grid Code Review Panel unless a
quorum is present throughout the meeting.
GR.10.2 Subject to GR.10.4, a quorum shall be 6 Panel Members who have a vote
GR.10.3 If within half an hour after the time for which the meeting of the Grid Code Review Panel
has been convened a quorum is not present (and provided the Panel Secretary has not
been notified by Panel Members that they have been delayed and are expected to arrive
within a reasonable time):
(a) the meeting shall be adjourned to the same day in the following week (or, if that day
is not a Business Day the next Business Day following such day) at the same time;
(b) the Panel Secretary shall give notice of the adjourned meeting as far as practicable
in accordance with GR.8.
GR.10.4 If at the adjourned meeting there is not a quorum present within half an hour after the
time for which the meeting was convened, those present shall be a quorum.
GR.11 VOTING
GR.11.1 At any meeting of the Grid Code Review Panel any matter to be decided which shall
include the Grid Code Review Panel Recommendation Vote shall be put to a vote of
those Panel Members entitled to vote in accordance with these Governance Rules upon
the request of the Panel Chairman or any Panel Member.
GR.11.2 Subject to GR.11.4, in deciding any matter at any meeting of the Grid Code Review
Panel each Panel Member other than the Panel Chairman shall cast one vote.
GR.11.3 Except as otherwise expressly provided in the Grid Code, and in particular GR.6.2, any
matter to be decided at any meeting of the Grid Code Review Panel shall be decided by
simple majority of the votes cast at the meeting (an abstention shall not be counted as a
cast vote).
GR11.4 The Panel Chairman shall not cast a vote as a Panel Member but shall have a casting
vote on any matter where votes are otherwise cast equally in favour of and against the
relevant motion. Where the vote is in respect of a Grid Code Modification Proposal the
Panel Chairman may only use such casting vote to vote against such Grid Code
Modification Proposal. The Panel Chairman will have a free vote in respect of any
other vote. Where any person other than the actual Panel Chairman is acting as
chairman he shall not have a casting vote.
GR.11.5 Any resolution in writing signed by or on behalf of all Panel Members shall be valid and
effectual as if it had been passed at a duly convened and quorate meeting of the Grid
Code Review Panel. Such a resolution may consist of several instruments in like form
signed by or on behalf of one or more Panel Members.
GR.12.1 Subject to GR.12.2 all CUSC Parties shall jointly and severally indemnify and keep
indemnified each Panel Member, the Panel Secretary and each member of a
Workgroup (“Indemnified Persons”) in respect of all costs (including legal costs),
expenses, damages and other liabilities properly incurred or suffered by such
Indemnified Persons when acting in or in connection with his office under the Grid
Code, or in what he in good faith believes to be the proper exercise and discharge of the
powers, duties, functions and discretions of that office in accordance with the Grid Code,
and all claims, demands and proceedings in connection therewith other than any such
costs, expenses, damages or other liabilities incurred or suffered as a result of the wilful
default or bad faith of such Indemnified Person.
GR.12.2 The indemnity provided in GR.12.1 shall not extend to costs and expenses incurred in the
ordinary conduct of being a Panel Member or Panel Secretary, or member of a
Workgroup including, without limitation, accommodation costs and travel costs or any
GR.12.3 The Users agree that no Indemnified Person shall be liable for anything done when
acting properly in or in connection with his office under the Grid Code, or anything done
in what he in good faith believes to be the proper exercise and discharge of the powers,
duties, functions and discretions of that office in accordance with the Grid Code. Each
CUSC Party hereby irrevocably and unconditionally waives any such liability of any
Indemnified Person and any rights, remedies and claims against any Indemnified
Person in respect thereof.
GR.12.4 Without prejudice to GR.12.2, nothing in GR.12.3 shall exclude or limit the liabilityof an
Indemnified Person for death or personal injury resulting from the negligence of such
Indemnified Person.
PART C
GR.13.1 The Code Administrator shall establish and maintain a register (“Grid Code
Modification Register”) in a form as may be agreed with the Authority from time to
time, which shall record the matters set out in GR.13.3.
GR.13.2 The purpose of the Grid Code Modification Register shall be to assist the Grid Code
Review Panel and to enable the Grid Code Review Panel, Users and any other
persons who may be interested to be reasonably informed of the progress of Grid Code
Modification Proposals and Approved Modifications from time to time.
GR.13.3 The Grid Code Modification Register shall record in respect of current outstanding Grid
Code Review Panel business:
(a) details of each Grid Code Modification Proposal (including the name of the
Proposer, the date of the Grid Code Modification Proposal and a brief description
of the Grid Code Modification Proposal);
(c) the current status and progress of each Grid Code Modification Proposal, if
appropriate the anticipated date for reporting to the Authority in respect thereof, and
whether it has been withdrawn, rejected or implemented for a period of three (3)
months after such withdrawal, rejection or implementation or such longer period as
the Authority may determine;
(d) the current status and progress of each Approved Modification, each Approved
Grid Code Self-Governance Proposal, and each Approved Fast Track Proposal;
and
(e) such other matters as the Grid Code Review Panel may consider appropriate from
time to time to achieve the purpose of GR.13.2.
GR.13.4 The Grid Code Modification Register (as updated from time to time and
indicating the revisions since the previous issue) shall be published on the Website or (in
the absence, for whatever reason, of the Website) in such other manner and with such
frequency (being not less than once per month) as the Code Administrator may decide
in order to bring it to the attention of the Grid Code Review Panel, Users and other
persons who may be interested.
GR.14.1 The Code Administrator shall establish (and, where appropriate, revise from
Issue 5 Revision 37 1 August 2019
time to time) joint working arrangements for change co-ordination with each Core
Industry Document Owner and with the STC Modification Panel to facilitate the
identification, co-ordination, making and implementation of change to Core Industry
Documents and the STC consequent on a Grid Code Modification Proposal, including,
but not limited to, changes that are appropriate in order to avoid conflict or inconsistency
as between the Grid Code and any Core Industry Document and the STC, in a full and
timely manner.
GR.14.2 The working arrangements referred to in GR.14.1 shall be such as to enable the
consideration, development and evaluation of Grid Code Modification Proposals, and
the implementation of Approved Modifications, to proceed in a full and timely manner
and enable changes to Core Industry Documents and the STC consequent on an
amendment to be made and given effect wherever possible (subject to any necessary
consent of the Authority) at the same time as such Grid Code Modification Proposal is
made and given effect.
(a) by any User; any Authorised Electricity Operator liable to be materially affected by
such a proposal; the Citizens Advice or the Citizens Advice Scotland;
GR.15.2 A Standard Modification shall follow the procedure set out in GR.18 to GR.22.
GR.15.3 A Grid Code Modification Proposal shall be submitted in writing to the Panel Secretary
and, subject to the provisions of GR.15.4 below, shall contain the following information in
relation to such proposal:
(b) the name of the representative of the Proposer who shall represent the Proposer in
person for the purposes of this GR.15;
(c) a description (in reasonable but not excessive detail) of the issue or defect which the
proposed modification seeks to address;
(d) a description (in reasonable but not excessive detail) of the proposed modification
and of its nature and purpose;
(e) where possible, an indication of those parts of the Grid Code which would require
amendment in order to give effect to (and/or would otherwise be affected by) the
proposed modification and an indication of the nature of those amendments or
effects;
(f) the reasons why the Proposer believes that the proposed modification would better
facilitate achievement of the Grid Code Objectives as compared with the current
version of the Grid Code together with background information in support thereof;
(g) the reasoned opinion of the Proposer as to why the proposed modification should
not fall within a current Significant Code Review, whether the proposed modification
should be treated as a Self-Governance Modification or whether the proposed
modification fails to meet the Self- Governance Criteria and as a result should
Issue 5 Revision 37 1 August 2019
proceed along the Standard Modification route;
(h) the reasoned opinion of the Proposer as to whether that impact is likely to be material
and if so an assessment of the quantifiable impact of the proposed modification on
greenhouse gas emissions, to be conducted in accordance with such current
guidance on the treatment of carbon costs and evaluation of the greenhouse gas
emissions as may be issued by the Authority from time to time;
(i) where possible, an indication of the impact of the proposed modification on Core
Industry Documents and the STC;
(j) where possible, an indication of the impact of the proposed modification on relevant
computer systems and processes used by Users.
GR.15.4 The Proposer of a Grid Code Fast Track Proposal is not required to provide the items
referenced at GR.15.3 (f) – (j) inclusive, unless either:
(a) the Grid Code Review Panel has, pursuant to GR.26.5 or GR.26.6, not agreed
unanimously that the Grid Code Fast Track Proposal meets the Fast Track
Criteria, or has not unanimously approved the Grid Code Fast Track Proposal; or
(b) there has been an objection to the Approved Fast Track Proposal pursuant to
GR.26.12, whereupon the Proposer shall be entitled to provide the additional
information required pursuant to GR.15.3 for a Grid Code Modification Proposal
within 28 days of the Panel Secretary’s request. Where the Proposer fails to provide
the additional information in accordance with such timescales, the Panel Secretary
may reject such proposal in accordance with GR.15.5.
GR.15.5 If a proposal fails in any material respect to provide the information in GR.15.3 (excluding
(e), (i) and (j) thereof), the Panel Secretary may reject such proposal provided that:
(a) the Panel Secretary shall furnish the Proposer with the reasons for such rejection;
(b) the Panel Secretary shall report such rejection to the Grid Code Review Panel at
the next Grid Code Review Panel meeting, with details of the reasons;
(c) if the Grid Code Review Panel decides or the Authority directs to reverse the Panel
Secretary’s decision to refuse the submission, the Panel Secretary shall notify the
Proposer accordingly and the proposal shall be dealt with in accordance with these
Governance Rules;
(d) nothing in these Governance Rules shall prevent a Proposer from submitting a
revised proposal in compliance with the requirements of GR.15.3 in respect of the
same subject-matter.
(b) a Rejected Grid Code Modification Proposal, where such proposal is made at any
time within two (2) months after the decision of the Authority not to direct The
Company to modify the Grid Code pursuant to the Transmission Licence in the
manner set out in such Grid Code Modification Proposal, and the Panel Secretary
shall notify the Proposer accordingly.
(a) allocate a unique reference number to the Grid Code Modification Proposal;
(b) enter details of the Grid Code Modification Proposal on the Grid Code
Modification Register.
GR.15.8 Subject to GR.8.6 and GR.26, where the Grid Code Modification Proposal is received
more than ten (10) Business Days prior to the next Grid Code Review Panel meeting,
the Panel Secretary shall place the Grid Code Modification Proposal on the agenda of
the next Grid Code Review Panel meeting and otherwise shall place it on the agenda of
the next succeeding Grid Code Review Panel meeting.
GR.15.9 It shall be a condition to the right to make a proposal to modify the Grid Code under this
GR.15 that the Proposer:
(a) grants a non-exclusive royalty free licence to all Users who request the same
covering all present and future rights, IPRs and moral rights it may have in such
proposal (as regards use or application in Great Britain); and
(b) warrants that, to the best of its knowledge, information and belief, no other person
has asserted to the Proposer that such person has any IPRs or normal rights or
rights of confidence in such proposal, and, in making a proposal, a Proposer which is
a Grid Code Party shall be deemed to have granted the licence and given the
warranty in (a) and (b) above.
(c) The provisions of this GR.15.9 shall apply to any WG Consultation Alternative
Request, and also to a Relevant Party supporting a Grid Code Modification
Proposal in place of the original Proposer in accordance with GR.15.10 (a) for these
purposes the term Proposer shall include any such Relevant Party or a person
making such a WG Consultation Alternative Request.
GR.15.10 Subject to GR.16.1, which deals with the withdrawal of a Grid Code Modification
Proposal made pursuant to a direction following a Significant Code Review, a
Proposer may withdraw his support for a Standard Modification by notice to the Panel
Secretary at any time prior to the Grid Code Review Panel Recommendation Vote
undertaken in relation to that Standard Modification pursuant to GR.22.4, and a
Proposer may withdraw his support for a Grid Code Modification Proposal that meets
the Self-Governance Criteria by notice to the Panel Secretary at any time prior to the
Grid Code Review Panel Self-Governance Vote undertaken in relation to that Grid
Code Modification Proposal pursuant to GR.24.9, and a Proposer may withdraw his
support for a Grid Code Fast Track Proposal by notice to the Panel Secretary at any
time prior to the Panel’s vote on whether to approve the Grid Code Fast Track
Proposal pursuant to GR.26 in which case the Panel Secretary shall forthwith:
(a) notify those parties specified in GR.15.1 as relevant in relation to the Grid Code
Modification Proposal in question (a “Relevant Party”) that he has been notified of
the withdrawal of support by the Proposer by publication on the Website and (where
relevant details are supplied) by electronic mail. A Relevant Party may within five (5)
Business Days notify the Panel Secretary that it is prepared to support the Grid
Code Modification Proposal in place of the original Proposer. If such notice is
received, the name of such Relevant Party shall replace that of the original
Proposer as the Proposer, and the Grid Code Modification Proposal shall
continue. If more than one notice is received, the first received shall be utilised;
(b) if no notice of support is received under (a), the matter shall be discussed at the next
Grid Code Review Panel meeting. If the Grid Code Review Panel so agrees, it may
notify Relevant Parties that the Grid Code Modification Proposal is to be
withdrawn, and a further period of five (5) Business Days shall be given for support
to be indicated by way of notice;
(c) if no notice of support is received under (a) or (b), the Grid Code Modification
Issue 5 Revision 37 1 August 2019
Proposal shall be marked as withdrawn on the Grid Code Modification Register;
Code Administrator as Critical Friend
GR.15.11 The Code Administrator shall provide assistance insofar as is reasonably practicable
and on reasonable request to parties with an interest in the Grid Code Modification
Proposal process that request it in relation to the Grid Code, as provided for in the Code
Administration Code of Practice, including, but not limited to, assistance with:
(c) Their involvement in, and representation during, the Grid Code Modification
Proposal process (including but not limited to Grid Code Review Panel, and/or
Workgroup meetings) as required or as described in the Code Administration
Code of Practice; and
GR.16.1 If any party specified under GR.15.1 (other than the Authority) makes a Grid
Code Modification Proposal during a Significant Code Review Phase,
unless exempted by the Authority or unless GR.16.4(b) applies, the Grid Code
Review Panel shall assess whether the Grid Code Modification Proposal
falls within the scope of a Significant Code Review and the applicability of the
exceptions set out in GR.16.4 and shall notify the Authority of its assessment,
its reasons for that assessment and any representations received in relation to it
as soon as practicable.
GR.16.2 The Grid Code Review Panel shall proceed with the Grid Code Modification
Proposal made during a Significant Code Review Phase in accordance with
GR.18 (notwithstanding any consultation undertaken pursuant to GR.16.5 and
its outcome), unless directed otherwise by the Authority pursuant to GR.16.3.
GR.16.3 Subject to GR.16.4, the Authority may at any time direct that a Grid Code
Modification Proposal made during a Significant Code Review Phase falls
within the scope of a Significant Code Review and must not be made during
the Significant Code Review Phase. If so directed, the Grid Code Review
Panel will not proceed with that Grid Code Modification Proposal, and the
Proposer shall decide whether the Grid Code Modification Proposal shall be
withdrawn or suspended until the end of the Significant Code Review Phase.
If the Proposer fails to indicate its decision whether to withdraw or suspend the
Grid Code Modification Proposal within twenty- eight (28) days of the
Authority’s direction, it shall be deemed to be suspended. If the Grid Code
Modification Proposal is suspended, it shall be open to the Proposer at the
end of the Significant Code Review Phase to indicate to the Grid Code
Review Panel that it wishes that Grid Code Modification Proposal to
proceed, and it shall be considered and taken forward in the manner decided
upon by the Grid Code Review Panel at the next meeting, and it is open to the
Grid Code Review Panel to take into account any work previously undertaken
in respect of that Grid Code Modification Proposal. If the Proposer makes no
indication to the Grid Code Review Panel within twenty-eight (28) days of the
end of the Significant Code Review Phase as to whether or not it wishes the
Grid Code Modification Proposal to proceed, it shall be deemed to be
withdrawn.
GR.16.4 A Grid Code Modification Proposal that falls within the scope of a Significant
Code Review may be made where:
(a) the Authority so determines, having taken into account (among other
things) the urgency of the subject matter of the Grid Code Modification
Issue 5 Revision 37 1 August 2019
Proposal; or
(b) the Grid Code Modification Proposal is made by The Company pursuant
to a direction from the Authority ; or
GR.16.5 Where a direction under GR.16.3 has not been issued, GR.16.4 does not apply
and the Grid Code Review Panel considers that a Grid Code Modification
Proposal made during a Significant Code Review Phase falls within the
scope of a Significant Code Review, the Grid Code Review Panel may
consult on its suitability as part of the Standard Modification route set out in
GR.19, GR.20, GR.21 and GR.22.
GR.16.6 If, within twenty eight (28) days after the Authority has published its
Significant Code Review conclusions:
(b) the Authority issues to the The Company a statement that no directions
under sub-paragraph (a) will be issued in relation to a Grid Code
Modification Proposal, The Company and all Users shall treat the
Significant Code Review Phase as ended on the date of such statement;
(d) the Authority issues a statement that it will continue work on the
Significant Code Review, The Company and all Users shall treat the
Significant Code Review Phase as continuing until it is brought to an end
in accordance with GR.16.7;
(e) neither directions under sub-paragraph (a) nor a statement under sub-
paragraphs (b) or (d) have been issued, nor a Grid Code Modification
Proposal under sub-paragraph (c) has been made, the Significant Code
Review Phase will be deemed to have ended.The Authority's published
conclusions and directions to The Company will not fetter any voting rights
of the Panel Members or the procedures informing the Grid Code
Modification Report.
(a) the Authority issues a statement that the Significant Code Review Phase
has ended;
GR.16.9 The Company may not, without the prior consent of the Authority, withdraw a
Grid Code Modification Proposal made pursuant to a direction issued by the
Authority pursuant to GR.16.4(b)).
GR.16.10 Where a Grid Code Modification Proposal has been raised in accordance
with GR.16.4(b) or GR.15.1(a), or by the Authority under GR.15.1(c) and it is in
respect of a Significant Code Review, the Authority may issue a direction (a
“backstop direction”), which requires such proposal(s) and any alternatives to
be withdrawn and which causes the Significant Code Review Phase to
recommence.
GR.17.2 An Authority-led modification may be submitted where the SCR phase is extended by a
statement issued by the Authority as described in GR.16.6(d), or where a direction is
issued under GR.16.10.
GR.17.3 The Authority may submit its proposed Authority-Led Modification to the Code
Administrator, together with such supplemental information as the Authority considers
appropriate.
GR.17.4 Upon receipt of the Authority’s proposal under GR.17.3, the Code Administrator shall
prepare a written report on the proposal (the "Authority-Led Modification Report").
Where the Code Administrator does not reasonably believe the information provided by
the Authority under 17.3 to be sufficient for it to prepare an Authority-Led Modification
Report the Code Administrator will notify the Authority as soon as reasonably
practical. The Authority-Led Modification Report must be consistent with the
information provided by the Authority under GR.17.3, and shall:
(b) set out the legal text of the proposed Authority-Led Modification;
(d) include a summary of the views (including any recommendations) from parties
consulted in respect of the proposed Authority-Led Modification;
(e) include an analysis of whether (and, if so, to what extent) the proposed Authority-
Led Modification would better facilitate achievement of the Grid Code Objective(s)
with a detailed explanation of the Authority’s reasons for its assessment, including,
where the impact is likely to be material, an assessment of the quantifiable impact of
the proposed Authority-Led Modification on greenhouse gas emissions, to be
Issue 5 Revision 37 1 August 2019
conducted in accordance with such current guidance on the treatment of carbon
costs and evaluation of the greenhouse gas emissions as may be issued by the
Authority from time to time, and providing a detailed explanation of the Authority’s
reasons for that assessment;
(i) the impact of the proposed Authority-Led Modification on the Core Industry
Documents and the STC;
(ii) the changes which would be required to the Core Industry Documents and the
STC in order to give effect to the proposed Authority-Led Modification;
(iii) the mechanism and likely timescale for the making of the changes referred to in
(ii);
(iv) the changes and/or developments which would be required to central computer
systems and, if practicable, processes used in connection with the operation
of arrangements established under the Core Industry Documents and the
STC;
(v) the mechanism and likely timescale for the making of the changes referred to in
(iv);
(vi) an estimate of the costs associated with making and delivering the changes
referred to in (ii) and (iv), such costs are expected to relate to: for (ii) the costs
of amending the Core Industry Document(s) and STC and for (iv) the costs
of changes to computer systems and possibly processes which are
established for the operation of the Core Industry Documents and the STC,
together with an analysis and a summary of representations in relation to
such matters, including any made by Small Participants, the Citizens
Advice and the Citizens Advice Scotland;
(h) contain, to the extent such information is available to the Code Administrator, an
assessment of the impact of the proposed Authority-Led Modification on Users in
general (or classes of Users), including the changes which are likely to be required to
their internal systems and processes and an estimate of the development, capital and
operating costs associated with implementing the changes to the Grid Code and to
Core Industry Documents and the STC;
(i) include copies of (and a summary of) all written representations or objections made
by parties consulted by the Authority in respect of the proposed Authority-Led
Modification and subsequently maintained; and
(j) have appended a copy of any impact assessment prepared by Core Industry
Document Owners and the STC committee and the views and comments of the
Code Administrator in respect thereof.
GR.17.5 Where the Authority-Led Modification Report is received more than ten (10) Business
Days prior to the next Grid Code Review Panel meeting, the Panel Secretary shall
place the proposed Authority-Led Modification on the agenda of the next Grid Code
Review Panel meeting and otherwise shall place it on the agenda of the next succeeding
Grid Code Review Panel meeting.
GR.17.6 In the case of Authority-Led Modifications GR.22 shall apply, save for GR.22.1 and
GR.22.2 and the Authority-Led Modification Report shall be used as the draft Grid
Code Modification Report.
GR.17.7 Where an Authority-Led Modification has been approved in accordance with Section
GR.22, GR.25 (Implementation) shall apply.
GR.18.2 A Grid Code Modification Proposal shall, subject to GR.15.8, be discussed by the Grid
Code Review Panel at the next following Grid Code Review Panel meeting convened.
GR.18.3 The Proposer’s representative shall attend such Grid Code Review Panel meeting and
the Grid Code Review Panel may invite the Proposer’s representative to present his
Grid Code Modification Proposal to the Grid Code Review Panel.
GR.18.4 The Grid Code Review Panel shall evaluate each Grid Code Modification Proposal
against the Self-Governance Criteria.
GR.18.5 The Grid Code Review Panel shall follow the procedure set out in GR.24 in respect of
any Modification that the Grid Code Review Panel considers meets the Self-
Governance Criteria unless the Authority makes a direction in accordance with
GR.24.2 and in such a case that Modification shall be a Standard Modification and
shall follow the procedure set out in GR.19, GR.20, GR.21 and GR.22.
GR.18.6 Unless the Authority makes a direction in accordance with GR.24.4, a Modification that
the Grid Code Review Panel considers does not meet the Self-Governance Criteria
shall be a Standard Modification and shall follow the procedure set out in GR.19,
GR.20, GR.21 and GR.22.
GR.18.7 The Grid Code Review Panel shall evaluate each Grid Code Fast Track Proposal
against the Fast Track Criteria.
GR.18.8 The Grid Code Review Panel shall follow the procedure set out in GR.26 in respect of
any Grid Code Fast Track Proposal. The provisions of GR.19 to GR.24 shall not apply
to a Grid Code Fast Track Proposal.
GR.19.1
(a) The Code Administrator and the Grid Code Review Panel shall together establish
a timetable to apply for the Grid Code Modification Proposal process. That
timetable must comply with any direction(s) issued by the Authority setting and/or
amending a timetable in relation to a Grid Code Modification Proposal that is in the
respect of a Significant Code Review.
(b) The Grid Code Review Panel shall establish the part of the timetable for the
consideration by the Grid Code Review Panel and by a Workgroup (if any) which
shall be no longer than six months unless in any case the particular circumstances of
the Grid Code Modification Proposal (taking due account of its complexity,
importance and urgency) justify an extension of such timetable, and provided the
Authority, after receiving notice, does not object, taking into account all those issues.
(c) The Code Administrator shall establish the part of the timetable for the consultation
to be undertaken by the Code Administrator under these Governance Rules and
separately the preparation of a Grid Code Modification Report to the Authority.
Where the particular circumstances of the Grid Code Modification Proposal (taking
due account of its complexity, importance and urgency) justify an extension of such
timescales and provided the Authority, after receiving notice, does not object, taking
into account all those issues, the Code Administrator may revise such part of the
timetable.
(d) In setting such a timetable, the Grid Code Review Panel and the Code
Administrator shall exercise their respective discretions such that, in respect of each
Grid Code Modification Proposal, a Grid Code Modification Report may be
submitted to the Authority as soon after the Grid Code Modification Proposal is
made as is consistent with the proper evaluation of such Grid Code Modification
Proposal, taking due account of its complexity, importance and urgency.
GR.19.2 In relation to each Grid Code Modification Proposal, the Grid Code Review Panel
shall determine at any meeting of the Grid Code Review Panel whether to:
(a) amalgamate the Grid Code Modification Proposal with any other Grid Code
Modification Proposal;
(b) establish a Workgroup of the Grid Code Review Panel, to consider the Grid Code
Modification Proposal;
(c) review the evaluation made pursuant to GR.18.4, taking into account any new
information received; or
(d) proceed directly to wider consultation (in which case the Proposer’s right to vary his
Grid Code Modification Proposal shall lapse).
GR.19.3 The Grid Code Review Panel may decide to amalgamate a Grid Code Modification
Proposal with one or more other Grid Code Modification Proposals where the subject-
matter of such Grid Code Modification Proposals is sufficiently proximate to justify
amalgamation on the grounds of efficiency and/or where such Grid Code Modification
Proposals are logically dependent on each other. Such amalgamation may only occur
with the consent of the Proposers of the respective Grid Code Modification Proposals.
The Authority shall be entitled to direct that a Grid Code Modification Proposal is not
amalgamated with one or more other Grid Code Modification Proposals.
GR.19.4 Without prejudice to each Proposer’s right to withdraw his Grid Code Modification
Proposal prior to the amalgamation of his Grid Code Modification Proposal where
Grid Code Modification Proposals are amalgamated pursuant to GR.19.3:
(a) such Grid Code Modification Proposals shall be treated as a single Grid Code
Modification Proposal;
(b) references in these Governance Rules to a Grid Code Modification Proposal shall
include and apply to a group of two or more Grid Code Modification Proposals so
amalgamated; and
(c) the Proposers of each such Grid Code Modification Proposal shall cooperate in
deciding which of them is to provide a representative for any Workgroup in respect
of the amalgamated Grid Code Modification Proposal and, in default of agreement,
the Panel Chairman shall nominate one of the Proposers for that purpose.
GR.19.5 In respect of any Grid Code Modification Proposal that the Grid Code Review Panel
determines to proceed directly to wider consultation in accordance with GR.19.2, the Grid
Code Review Panel, may at any time prior to the Grid Code Review Panel
Recommendation Vote having taken place decide to establish a Workgroup of the Grid
Code Review Panel and the provisions of GR.20 shall apply. In such case the Grid
Code Review Panel shall be entitled to adjust the timetable referred to at GR.19.1(b) and
the Code Administrator shall be entitled to adjust the timetable referred to at
GR.19.1(c), provided that the Authority, after receiving notice, does not object.
GR.20 WORKGROUPS
GR.20.1 If the Grid Code Review Panel has decided not to proceed directly to wider consultation
(or where the provisions of GR.19.5, GR.23.10 or GR.25.5 apply), a Workgroup will be
established by the Grid Code Review Panel to assist the Grid Code Review Panel in
evaluating whether a Grid Code Modification Proposal better facilitates achieving the
Grid Code Objectives and whether a Workgroup Alternative Grid Code
Modification(s) would, as compared with the Grid Code Modification Proposal, better
Issue 5 Revision 37 1 August 2019
facilitate achieving the Grid Code Objectives in relation to the issue or defect identified
in the Grid Code Modification Proposal.
GR.20.2 A single Workgroup may be responsible for the evaluation of more than one Grid Code
Modification Proposal at the same time, but need not be so responsible.
GR.20.3 A Workgroup shall comprise at least five (5) persons (who may be Panel Members)
selected by the Grid Code Review Panel from those nominated by Users, the Citizens
Advice or the Citizens Advice Scotland for their relevant experience and/or expertise in
the areas forming the subject-matter of the Grid Code Modification Proposal(s) to be
considered by such Workgroup (and the Grid Code Review Panel shall ensure, as far
as possible, that an appropriate cross-section of representation, experience and expertise
is represented on such Workgroup) provided that there shall always be at least one
member representing The Company and if, and only if, the Grid Code Review Panel is
of the view that a Grid Code Modification Proposal is likely to have an impact on the
STC, the Grid Code Review Panel may invite the STC committee to appoint a
representative to become a member of the Workgroup. A representative of the
Authority may attend any meeting of a Workgroup as an observer and may speak at
such meeting.
GR.20.4 The Code Administrator shall in consultation with the Grid Code Review Panel appoint
the chairman of the Workgroup who shall act impartially and as an independent
chairman.
GR.20.5 The Grid Code Review Panel may add further members or the Workgroup chairman
may add or vary members to a Workgroup.
GR.20.6 The Grid Code Review Panel may (but shall not be obliged to) replace any member or
observer of a Workgroup appointed pursuant to GR.20.3 at any time if such member is
unwilling or unable for whatever reason to fulfil that function and/or is deliberately and
persistently disrupting or frustrating the work of the Workgroup.
GR.20.7 The Grid Code Review Panel shall determine the terms of reference of each
Workgroup and may change those terms of reference from time to time as it sees fit.
GR.20.8 The terms of reference of a Workgroup must include provision in respect of the following
matters:
(a) those areas of a Workgroup’s powers or activities which require the prior approval of
the Grid Code Review Panel;
(b) the seeking of instructions, clarification or guidance from the Grid Code Review
Panel, including on the suspension of a Workgroup Alternative Grid Code
Modification(s) during a Significant Code Review Phase;
(c) the timetable for the work to be done by the Workgroup, in accordance with the
timetable established pursuant to GR.19.1 (save where GR.19.5 applies); and
In addition, prior to the taking of any steps which would result in the undertaking of a
significant amount of work (including the production of draft legal text to modify the Grid
Code in order to give effect to a Grid Code Modification Proposal and/or Workgroup
Alternative Grid Code Modification(s), with the relevant terms of reference setting out
what a significant amount of work would be in any given case), the Workgroup shall seek
the views of the Grid Code Review Panel as to whether to proceed with such steps and,
in giving its views, the Grid Code Review Panel may consult the Authority in respect
thereof.
GR.20.9 Subject to the provisions of this GR.20.9 and unless otherwise determined by the Grid
Code Review Panel, the Workgroup shall develop and adopt its own internal working
procedures for the conduct of its business and shall provide a copy of such procedures to
the Panel Secretary in respect of each Grid Code Modification Proposal for which it is
Issue 5 Revision 37 1 August 2019
responsible. Unless the Grid Code Review Panel otherwise determines, meetings of
each Workgroup shall be open to attendance by a representative of any User, (including
any Authorised Electricity Operator; The Company or a Materially Affected Party),
the Citizens Advice, the Citizens Advice Scotland, the Authority and any person
invited by the chairman, and the chairman of a Workgroup may invite any such person to
speak at such meetings, other than the Authority who may speak at any time as per
GR.20.3.
GR.20.10 After development by the Workgroup of the Grid Code Modification Proposal, and (if
applicable) after development of any draft Workgroup Alternative Grid Code
Modification(s), the Workgroup may (subject to the provisions of GR.20.16) consult
(“Workgroup Consultation”) on the Grid Code Modification Proposal and, if
applicable, on any draft Workgroup Alternative Grid Code Modification(s) with:
(c) The date proposed by the Code Administrator as the Proposed Implementation
Date.
GR.20.12 Workgroup Consultation papers will be copied to Core Industry Document Owners
and the secretary of the STC committee.
GR.20.13 Any Authorised Electricity Operator; the Citizens Advice or the Citizens Advice
Scotland, The Company or a Materially Affected Party may (subject to GR.20.17)
raise a Workgroup Consultation Alternative Request in response to the Workgroup
Consultation. Such Workgroup Consultation Alternative Request must include:
(a) the information required by GR.15.3 (which shall be read and construed so that any
references therein to “amendment proposal” or “proposal” shall be read as “request”
and any reference to “Proposer” shall be read as “requester”); and
(b) sufficient detail to enable consideration of the request including details as to how the
request better facilitates the Grid Code Objectives than the current version of the
Grid Code, than the Grid Code Modification Proposal and than any draft
Workgroup Alternative Grid Code Modification(s).
GR.20.14 The Workgroup shall consider and analyse any comments made or any Workgroup
Consultation Alternative Request made by any User (including any Authorised
Electricity Operator; The Company or a Materially Affected Party) ), the Citizens
Advice and the Citizens Advice Scotland in response to the Workgroup Consultation.
GR.20.15 If a majority of the members of the Workgroup or the chairman of the Workgroup
believe that the Workgroup Consultation Alternative Request will better facilitate the
Grid Code Objectives than the current version of the Grid Code, the Workgroup shall
develop it as a Workgroup Alternative Grid Code Modification(s) or, where the
chairman of the Workgroup agrees, amalgamate it with one or more other draft
Workgroup Alternative Grid Code Modification(s) or Workgroup Consultation
Alternative Request(s);
GR.20.16 Unless the Grid Code Review Panel directs the Workgroup otherwise pursuant to
Issue 5 Revision 37 1 August 2019
GR.20.17, and provided that a Workgroup Consultation has been undertaken in respect
of the Grid Code Modification Proposal, no further Workgroup Consultation will be
required in respect of any Workgroup Alternative Grid Code Modification(s)
developed in respect of such Grid Code Modification Proposal.
GR.20.17 The Grid Code Review Panel may, at the request of the chairman of the Workgroup,
direct the Workgroup to undertake further Workgroup Consultation(s). At the same
time as such direction the Grid Code Review Panel shall adjust the timetable referred to
at GR.19.1(b) and the Code Administrator shall be entitled to adjust the timetable
referred to at GR.19.1 (c), provided that the Authority, after receiving notice, does not
object. No Workgroup Consultation Alternative Request may be raised by any User
(including any Authorised Electricity Operator; The Company or a Materially Affected
Party), the Citizens Advice and the Citizens Advice Scotland during any second or
subsequent Workgroup Consultation.
GR.20.18 The Workgroup shall finalise the Workgroup Alternative Grid Code Modification(s)
for inclusion in the report to the Grid Code Review Panel.
GR.20.19
(a) Each Workgroup chairman shall prepare a report to the Grid Code Review Panel
responding to the matters detailed in the terms of reference in accordance with the
timetable set out in the terms of reference.
(b) If a Workgroup is unable to reach agreement on any such matter, the report must
reflect the views of the members of the Workgroup.
(c) The report will be circulated in draft form to Workgroup members and a period of not
less than five (5) Business Days or if all Workgroup members agree three (3)
Business Days given for comments thereon. Any unresolved comments made shall
be reflected in the final report.
GR.20.20 The chairman or another member (nominated by the chairman) of the Workgroup shall
attend the next Grid Code Review Panel meeting following delivery of the report and may
be invited to present the findings and/or answer the questions of Panel Members in
respect thereof. Other members of the Workgroup may also attend such Grid Code
Review Panel meeting.
GR.20.21 At the meeting referred to in GR.20.20 the Grid Code Review Panel shall consider the
Workgroup’s report and shall determine whether to:-
(a) refer the proposed Grid Code Modification Proposal back to the Workgroup for
further analysis (in which case the Grid Code Review Panel shall determine the
timetable and terms of reference to apply in relation to such further analysis); or
GR.20.22 Subject to GR.16.4 if, at any time during the assessment process carried out by the
Workgroup pursuant to this GR.20, the Workgroup considers that a Grid Code
Modification Proposal or any Workgroup Alternative Grid Code Modification(s) falls
within the scope of a Significant Code Review, it shall consult on this as part of the
Workgroup Consultation and include its reasoned assessment in the report to the Grid
Code Review Panel prepared pursuant to GR.20.19. If the Grid Code Review Panel
considers that the Grid Code Modification Proposal or the Workgroup Alternative Grid
Code Modification(s) falls within the scope of a Significant Code Review, it shall consult
with the Authority. If the Authority directs that the Grid Code Modification Proposal or
Workgroup Alternative Grid Code Modification(s) falls within the scope of the
Significant Code Review, the Grid Code Modification Proposal and any Workgroup
Alternative Grid Code Modification(s) shall be suspended or withdrawn during the
Significant Code Review Phase, in accordance with GR.16.3.
GR.20.24 The Grid Code Review Panel may (but shall not be obliged to) require a Grid Code
Modification Proposal to be withdrawn if, in the Panel’s opinion, the Proposer of that
Grid Code Modification Proposal is deliberately and persistently disrupting or
frustrating the work of the Workgroup and that Grid Code Modification Proposal shall
be deemed to have been so withdrawn. In the event that a Grid Code Modification
Proposal is so withdrawn, the provisions of GR.15.10 shall apply in respect of that Grid
Code Modification Proposal.
GR.21.1 In respect of any Grid Code Modification Proposal where a Workgroup has been
established GR.21.2 to GR.21.6 shall apply.
GR.21.2 After consideration of any Workgroup report on the Grid Code Modification
Proposal and if applicable any Workgroup Alternative Grid Code Modification(s) by
the Grid Code Review Panel and a determination by the Grid Code Review Panel to
proceed to wider consultation, the Code Administrator shall bring to the attention of and
consult on the Grid Code Modification Proposal and if applicable any Workgroup
Alternative Grid Code Modification(s) with:
GR.21.3 The consultation will be undertaken by issuing a Consultation Paper (and its provision in
electronic form on the Website and in electronic mails to Users and such other persons,
who have supplied relevant details, shall meet this requirement).
(a) the proposed drafting for the Grid Code Modification Proposal and any
Workgroup Alternative Grid Code Modification(s) (unless the Authority decides
none is needed in the Grid Code Modification Report under GR.21.5) and will
indicate the issues which arose in the Workgroup discussions, where there has been
a Workgroup and will incorporate The Company’s and the Grid Code Review
Panel’s initial views on the way forward; and
(b) the date proposed by the Code Administrator as the Proposed Implementation
Date and, where the Workgroup terms of reference require and the dates proposed
by the Workgroup are different from those proposed by the Code Administrator,
those proposed by the Workgroup. In relation to a Grid Code Modification
Proposal that meets the Self-Governance Criteria, the Code Administrator may
not propose an implementation date earlier than the sixteenth (16) Business Day
following the publication of the Grid Code Review Panel’s decision to approve or
reject the Grid Code Modification Proposal. Views will be invited on these dates.
GR.21.5 Where the Grid Code Review Panel is of the view that the proposed text to
amend the Grid Code for a Grid Code Modification Proposal or Workgroup
Alternative Grid Code Modification(s) is not needed in the Grid Code Modification
Report, the Grid Code Review Panel shall consult (giving its reasons as to why it is of
this view) with the Authority as to whether the Authority would like the Grid Code
Modification Report to include the proposed text to amend the Grid Code. If it does not,
no text needs to be included. If it does, and no detailed text has yet been prepared, the
GR.21.6 Consultation Papers will be copied to Core Industry Document Owners and the
secretary of the STC committee.
GR.21.7 In respect of any Grid Code Modification Proposal where a Workgroup has not been
established GR.21.8 to GR.21.11 shall apply.
GR.21.8 After determination by the Grid Code Review Panel to proceed to wider consultation,
such consultation shall be conducted by the Code Administrator on the Grid Code
Modification Proposal with:
GR.21.9 The consultation will be undertaken by issuing a Consultation Paper (and its provision in
electronic form on the Website and in electronic mails to Users and such other persons,
who have supplied relevant details, shall meet this requirement).
(a) the proposed drafting for the Grid Code Modification Proposal (unless the Authority
decides none is needed in the Grid Code Modification Report under GR.21.11) and
will incorporate The Company’s and the Grid Code Review Panel’s initial views on
the way forward; and
(b) the date proposed by the Code Administrator as the Proposed Implementation
Date. Views will be invited on this date.
GR.21.11 Where the Grid Code Review Panel is of the view that the proposed text to amend the
Grid Code for a Grid Code Modification Proposal is not needed, the Grid Code
Review Panel shall consult (giving its reasons to why it is of this view) with the Authority
as to whether the Authority would like the Grid Code Modification Report to include
the proposed text to amend the Grid Code. If it does not, no text needs to be included. If
it does, and no detailed text has yet been prepared, the Code Administrator shall
prepare such text to modify the Grid Code in order to give effect to such Grid Code
Modification Proposal and consult those identified in GR.21.2.
GR.22.1 Subject to the Code Administrator’s consultation having been completed, the Grid
Code Review Panel shall prepare and submit to the Authority a report (the "Grid Code
Modification Report") in accordance with this GR.22 for each Grid Code Modification
Proposal which is not withdrawn.
GR.22.2 The matters to be included in a Grid Code Modification Report shall be the following (in
respect of the Grid Code Modification Proposal):
(a) A description of the Grid Code Modification Proposal and any Workgroup
Alternative Grid Code Modification(s), including the details of, and the rationale for,
any variations made (or, as the case may be, omitted) by the Proposer together with
the views of the Workgroup;
(c) a summary (agreed by the Grid Code Review Panel) of the views (including any
recommendations) from Panel Members in the Grid Code Review Panel
Issue 5 Revision 37 1 August 2019
Recommendation Vote and the conclusions of the Workgroup (if there is one) in
respect of the Grid Code Modification Proposal and of any Workgroup Alternative
Grid Code Modification(s);
(d) an analysis of whether (and, if so, to what extent) the Grid Code Modification
Proposal and any Workgroup Alternative Grid Code Modification(s) would better
facilitate achievement of the Grid Code Objective(s) with a detailed explanation of
the Grid Code Review Panel’s reasons for its assessment, including, where the
impact is likely to be material, an assessment of the quantifiable impact of the Grid
Code Modification Proposal and any Workgroup Alternative Grid Code
Modification(s) on greenhouse gas emissions, to be conducted in accordance with
such current guidance on the treatment of carbon costs and evaluation of the
greenhouse gas emissions as may be issued by the Authority from time to time, and
providing a detailed explanation of the Grid Code Review Panel’s reasons for that
assessment;
(e) an analysis of whether (and, if so, to what extent) any Workgroup Alternative Grid
Code Modification(s) would better facilitate achievement of the Grid Code
Objective(s) as compared with the Grid Code Modification Proposal and any other
Workgroup Alternative Grid Code Modification(s) and the current version of the
Grid Code, with a detailed explanation of the Grid Code Review Panel’s reasons for
its assessment, including, where the impact is likely to be material, an assessment of
the quantifiable impact of the Workgroup Alternative Grid Code Modification(s) on
greenhouse gas emissions, to be conducted in accordance with such current
guidance on the treatment of carbon costs and evaluation of the greenhouse gas
emissions as may be issued by the Authority from time to time, and providing a
detailed explanation of the Grid Code Review Panel’s reasons for that assessment;
(f) the Proposed Implementation Date taking into account the views put forward during
the process described at GR.21.4 (b) such date to be determined by the Grid Code
Review Panel in the event of any disparity between such views and those of the
Code Administrator;
(i) the impact of the Grid Code Modification Proposal and any Workgroup
Alternative Grid Code Modification(s) on the Core Industry Documents
and the STC;
(ii) the changes which would be required to the Core Industry Documents and the
STC in order to give effect to the Grid Code Modification Proposal and any
Workgroup Alternative Grid Code Modification(s);
(iii) the mechanism and likely timescale for the making of the changes referred to in
(ii);
(iv) the changes and/or developments which would be required to central computer
systems and, if practicable, processes used in connection with the operation
of arrangements established under the Core Industry Documents and the
STC;
(v) the mechanism and likely timescale for the making of the changes referred to in
(iv);
(vi) an estimate of the costs associated with making and delivering the
changes referred to in (ii) and (iv), such costs are expected to relate to: for (ii) the
costs of amending the Core Industry Document(s) and STC and for (iv) the
costs of changes to computer systems and possibly processes which are
established for the operation of the Core Industry Documents and the STC,
together with an analysis and a summary of representations in relation to such
matters, including any made by Small Participants, the Citizens Advice and the
Citizens Advice Scotland;
(i) copies of (and a summary of) all written representations or objections made by
consultees during the consultation in respect of the Grid Code Modification
Proposal and any Workgroup Alternative Grid Code Modification(s) and
subsequently maintained;
(j) a copy of any impact assessment prepared by Core Industry Document Owners
and the STC committee and the views and comments of the Code Administrator in
respect thereof;
(k) whether or not, in the opinion of The Company, the Grid Code Modification
Proposal (or any Workgroup Alternative Grid Code Modification(s)) should be
made.
GR.22.3 A draft of the Grid Code Modification Report will be circulated by the Code
Administrator to Users, Panel Members and such other persons who may properly be
considered to have an appropriate interest in it (and its provision in electronic form on the
Website and in electronic mails to Users and Panel Members, who must supply relevant
details, shall meet this requirement) and a period of no less than five (5) Business Days
given for comments to be made thereon. Any unresolved comments made shall be
reflected in the final Grid Code Modification Report.
GR.22.4 A draft of the Grid Code Modification Report shall be tabled at the Panel
Meeting prior to submission of that Grid Code Modification Report to the Authority as
set in accordance with the timetable established pursuant to GR.19.1 at which the Panel
may consider any minor changes to the legal drafting and:
(i) if the change required is a typographical error the Grid Code Review
Panel may instruct the Code Administrator to make the appropriate change
and the Panel Chairman will undertake the Grid Code Review Panel
Recommendation Vote; or
(ii) if the change required is not considered to be a typographical error then
the Grid Code Review Panel may direct the Workgroup to review the change.
If the Workgroup unanimously agree that the change is minor the Grid Code
Review Panel may instruct the Code Administrator to make the appropriate
change and the Panel Chairman will undertake the Grid Code Review Panel
Recommendation Vote otherwise the Code Administrator shall issue the
Grid Code Modification Proposal for further Code Administrator consultation
after which the Panel Chairman will undertake the Grid Code Review Panel
Recommendation Vote.
(iii)if a change is not required after consideration, the Panel Chairman will
undertake the Grid Code Review Panel Recommendation Vote.
GR.22.5 A draft of the Grid Code Modification Report following the Grid Code Review
Panel Recommendation Vote will be circulated by the Code Administrator to
Panel Members (and in electronic mails to Panel Members, who must supply
relevant details, shall meet this requirement) and a period of no less than five
(5) Business Days given for comments to be made on whether the Grid Code
Modification Report accurately reflects the views of the Panel Members as
expressed at the Grid Code Review Panel Recommendation Vote. Any
unresolved comments made shall be reflected in the final Grid Code
Modification Report.
GR.22.6 Each Grid Code Modification Report shall be addressed and furnished to the
Authority and none of the facts, opinions or statements contained in such may
be relied upon by any other person.
GR.22.8 The Code Administrator shall copy (by electronic mail to those persons who
have supplied relevant details to the Code Administrator) the Grid Code
Modification Report to:
(a) specify that the revised Proposed Implementation Date shall not be prior
to a specified date;
(b) specify a reasonable period (taking into account a reasonable period for
consultation) within which the Grid Code Review Panel shall be requested
to submit its recommendation; and
(c) provide such reasons as the Authority deems appropriate for such request
(and in respect of those matters referred to in GR.22.9.2 (a) and (b) above).
GR.22.9.3 Before making a recommendation to the Authority, the Grid Code Review
Panel will consult on the revised Proposed Implementation Date, and may in
addition consult on any matters relating to the Grid Code Modification Report
which in the Grid Code Review Panel’s opinion have materially changed since
the Grid Code Modification
Report was submitted to the Authority and where it does so the Grid Code
Review Panel shall report on such matters as part of its recommendation under
Grid Code GR.22.9.4, with:
GR.22.9.4 Following the completion of the consultation held pursuant to GR.22.9.3 the Grid Code
Review Panel shall report to the Authority with copies of all the consultation responses
and recommending a Revised Proposed Implementation Date.
GR.22.9.5 The Authority shall notify the Grid Code Review Panel as to whether or not it intends to
accept the Revised Proposed Implementation Date and where the Authority notifies
the Grid Code Review Panel that it intends to accept the Revised Proposed
Implementation Date, the Revised Proposed Implementation Date shall be deemed to
be the Proposed Implementation Date as specified in the Grid Code Modification
Report.
If:
(a) the Authority has not given notice of its decision in respect of a Grid Code
Issue 5 Revision 37 1 August 2019
Modification Report within two (2) calendar months (in the case of an Urgent
Modification), or four (4) calendar months (in the case of all other Grid Code
Modification Proposals) from the date upon which the Grid Code Modification
Report was submitted to it; or
(b) the Grid Code Review Panel is of the reasonable opinion that the circumstances
relating to the Grid Code Modification Proposal and/or Workgroup Alternative
Grid Code Modification which is the subject of a Grid Code Modification Report
have materially changed, the Grid Code Review Panel may request the Panel
Secretary to write to the Authority requesting the Authority to give an indication of
the likely date by which the Authority’s decision on the Grid Code Modification
Proposal will be made.
GR.22.11 If the Authority determines that the Grid Code Modification Report is such that the
Authority cannot properly form an opinion on the Grid Code Modification Proposal and
any Workgroup Alternative Grid Code Modification(s), it may issue a direction to the
Grid Code Review Panel:
(a) specifying the additional steps (including drafting or amending existing drafting
associated with the Grid Code Modification Proposal and any Workgroup
Alternative Grid Code Modification(s)), revision (including revision to the
timetable), analysis or information that it requires in order to form such an opinion;
and
(b) requiring the Grid Code Modification Report to be revised and to be resubmitted.
GR.22.12 If a Grid Code Modification Report is to be revised and re-submitted in accordance with
a direction issued pursuant to GR.22.11, it shall be re-submitted as soon after the
Authority’s direction as is appropriate, taking into account the complexity, importance
and urgency of the Grid Code Modification Proposal and any Workgroup Alternative
Grid Code Modification(s). The Grid Code Review Panel shall decide on the level of
analysis and consultation required in order to comply with the Authority’s direction and
shall agree an appropriate timetable for meeting its obligations. Once the Grid Code
Modification Report is revised, the Grid Code Review Panel shall carry out its Grid
Code Review Panel Recommendation Vote again in respect of the revised Grid Code
Modification Report and re-submit it to the Authority in compliance with GR.22.4 to
GR.22.6.
GR.23.1 If a Relevant Party recommends to the Panel Secretary that a proposal should be
treated as an Urgent Modification in accordance with this GR.23, the Panel Secretary
shall notify the Panel Chairman who shall then, in accordance with GR.23.2 (a) to (e)
inclusive, and notwithstanding anything in the contrary in these Governance Rules,
endeavour to obtain the views of the Grid Code Review Panel as to the matters set out
in GR.23.3. If for any reason the Panel Chairman is unable to do that, the Panel
Secretary shall attempt to do so (and the measures to be undertaken by the Panel
Chairman in the following paragraphs shall in such case be undertaken by the Panel
Secretary).
GR.23.2
(a) The Panel Chairman shall determine the time by which, in his opinion, a decision of
the Grid Review Panel is required in relation to such matters, having regard to the
degree of urgency in all circumstances, and references in this GR.23.1 to the “time
available” shall mean the time available, based on any such determination by the
Panel Chairman;
(b) The Panel Secretary shall, at the request of the Panel Chairman, convene a
meeting or meetings (including meetings by telephone conference call, where
appropriate) of the Grid Code Review Panel in such manner and upon such notice
as the Panel Chairman considers appropriate, and such that, where practicable
within the time available, as many Panel Members as possible may attend;
(d) Where:
(e) Where the Panel Chairman is unable to contact at least four Panel Members within
the time available and where:
(i) It is only The Company, who has recommended that the proposal should be
treated as an Urgent Modification, then those Panel Members contacted shall
decide such matters, such decision may be a majority decision. Where in such
cases no decision is made for whatever reason, the Panel Chairman shall
proceed to consult with the Authority in accordance with GR.23.5; or
(ii) any User (including any Authorised Electricity Operator; The Company or a
Materially Affected Party), the Citizens Advice or the Citizens Advice Scotland
has recommended that the proposal should be treated as an Urgent Modification,
then the Panel Chairman may decide the matter (in consultation with those Panel
Members (if any) which he managed to contact) provided that the Panel Chairman
shall include details in the relevant Grid Code Modification Report of the steps
which he took to contact other Panel Members first.
(b) the procedure and timetable to be followed in respect of such Urgent Modification.
GR.23.4 The Panel Chairman or, in his absence, the Panel Secretary shall forthwith provide the
Authority with the recommendation (if any) ascertained in accordance with GR.23.2 (a)
to (e) inclusive, of the Grid Code Review Panel as to the matters referred to in GR.23.2,
and shall consult the Authority as to whether such Grid Code Modification Proposal is
an Urgent Modification and, if so, as to the procedure and timetable which should apply
in respect thereof.
GR.23.5 If the Grid Code Review Panel has been unable to make a recommendation in
accordance with GR.23.2.(d) or GR.23.2(e) as to the matters referred to in GR.23.3 then
the Panel Chairman or, in his absence, the Panel Secretary may recommend whether
he considers that such proposal should be treated as an Urgent Modification and shall
forthwith consult the Authority as to whether such Grid Code Modification Proposal is
an Urgent Modification and, if so, as to the procedure and timetable that should apply in
respect thereof.
(a) not treat any Grid Code Modification Proposal as an Urgent Modification except
with the prior consent of the Authority;
(b) comply with the procedure and timetable in respect of any Urgent Modification
Issue 5 Revision 37 1 August 2019
approved by the Authority; and
(c) comply with any direction of the Authority issued in respect of any of the matters on
which the Authority is consulted pursuant to GR.23.4 or GR.23.5.
GR.23.7 For the purposes of this GR.23.7, the procedure and timetable in respect of an Urgent
Modification may (with the approval of the Authority pursuant to GR.23.4 or GR.23.5)
deviate from all or part of the Grid Code Modification Procedures or follow any other
procedure or timetable approved by the Authority. Where the procedure and timetable
approved by the Authority in respect of an Urgent Modification do not provide for the
establishment (or designation) of a Workgroup the Proposer’s right to vary the Grid
Code Modification Proposal pursuant to GR.15.10 and GR.20.23 shall lapse from the
time and date of such approval.
GR.23.8 The Grid Code Modification Report in respect of an Urgent Modification shall include:
(a) a statement as to why the Proposer believes that such Grid Code
Modification Proposal should be treated as an Urgent Modification;
(b) any statement provided by the Authority as to why the Authority believes
that such Grid Code Modification Proposal should be treated as an
Urgent Modification;
(c) any recommendation of the Grid Code Review Panel (or any
recommendation of the Panel Chairman) provided in accordance with
GR.23 in respect of whether any Grid Code Modification Proposal should
be treated as an Urgent Modification; and
(d) the extent to which the procedure followed deviated from the process for
Standard Modifications (other than the procedures in this GR.23).
GR.23.9 Each Panel Member shall take all reasonable steps to ensure that an Urgent
Modification is considered, evaluated and (subject to the approval of the
Authority) implemented as soon as reasonably practicable, having regard to
the urgency of the matter and, for the avoidance of doubt, an Urgent
Modification may (subject to the approval of the Authority) result in the Grid
Code being amended on the day on which such proposal is submitted.
GR.24 SELF-GOVERNANCE
GR.24.1 If the Grid Code Review Panel, having evaluated a Grid Code Modification
Proposal against the Self-Governance Criteria, pursuant to GR.18.4,
considers that the Grid Code Modification Proposal meets the Self-
Governance Criteria, the Grid Code Review Panel shall submit to the
Authority a Self-Governance Statement setting out its reasoning in
reasonable detail.
GR.24.2 The Authority may, at any time prior to the Grid Code Review Panel’s
determination made pursuant to GR.24.9, give written notice that it disagrees
with the Self-Governance Statement and may direct that the Grid Code
Modification Proposal proceeds through the process for Standard
Modifications set out in GR.19, GR.20, GR.21 and GR.22;
GR.24.4 The Authority may issue a direction to the Grid Code Review Panel in
relation to a Modification to follow the procedure set out for Modifications that
meet the Self-Governance Criteria, notwithstanding that no Self-Governance
Statement has been submitted or a Self
Governance Statement has been retracted.
GR.24.5 Subject to the Code Administrator’s consultation having been completed pursuant to
GR.21, the Grid Code Review Panel shall prepare a report (the “Grid Code
Modification Self- Governance Report”).
GR.24.6 The matters to be included in a Grid Code Modification Self-Governance Report shall
be the following (in respect of the Grid Code Modification Proposal):
(a) details of its analysis of the Grid Code Modification Proposal against the Self-
Governance Criteria;
(c) the date on which the Grid Code Review Panel Self-Governance Vote shall take
place, which shall not be earlier than seven (7) days from the date on which the Grid
Code Modification Self- Governance Report is furnished to the Authority in
accordance with GR.24.8; and
(d) such other information that is considered relevant by the Grid Code Review Panel.
GR.24.7 A draft of the Grid Code Modification Self-Governance Report will be circulated by the
Code Administrator to Users and Panel Members (and its provision in electronic form
on the Website and in electronic mails to Users and Panel Members, who must supply
relevant details, shall meet this requirement) and a period of no less than five (5)
Business Days given for comments to be made thereon. Any unresolved comments
made shall be reflected in the final Grid Code Modification Self-Governance Report.
GR.24.8 Each Grid Code Modification Self-Governance Report shall be addressed and
furnished to the Authority and none of the facts, opinions or statements contained in
such Grid Code Modification Self-Governance Report may be relied upon by any other
person.
GR.24.9 Subject to GR.24.11, if the Authority does not give written notice that its decision is
required pursuant to GR.24.2, or if the Authority determines that the Self-Governance
Criteria are satisfied in accordance with GR.24.4, then the Grid Code Modification Self-
Governance Report shall be tabled at the Panel Meeting following submission of that
Grid Code Modification Self-Governance Report to the Authority at which the Panel
Chairman will undertake the Grid
Code Review Panel Self-Governance Vote and the Code Administrator shall give
notice of the outcome of such vote to the Authority as soon as possible thereafter.
GR.24.10 If the Grid Code Review Panel vote to approve the Grid Code Modification Proposal
pursuant to GR.24.9 (which shall then be an “Approved Grid Code Self-Governance
Proposal”) until implemented).
GR.24.11 The Grid Code Review Panel may at any time prior to the Grid Code Review Panel’s
determination retract a Self-Governance Statement subject to GR.24.4, or if the
Authority notifies the Grid Code Review Panel that it has determined that a Grid Code
Modification Proposal does not meet the Self-Governance Criteria the Grid Code
Review Panel shall treat the Grid Code Modification Proposal as a Standard
Modification and shall comply with GR.22, using the Grid Code Modification Self-
Governance Report as a basis for its Grid Code Modification Report.
GR.24.12 The Code Administrator shall make available on the Website and copy (by electronic
mail to those persons who have supplied relevant details to the Code Administrator) the
Grid Code Modification Self-Governance Report prepared in accordance with GR.24
Issue 5 Revision 37 1 August 2019
to:
GR.24.13 A User (including any Authorised Electricity Operator; The Company or a Materially
Affected Party), the Citizens Advice or the Citizens Advice Scotland may appeal to
the Authority the approval or rejection by the Grid Code Review Panel of a Grid Code
Modification Proposal and any Workgroup Alternative Grid Code Modification(s) in
accordance with GR.24.9, provided that the Panel Secretary is also notified, and the
appeal has been made up to and including fifteen (15) Business Days after the Grid
Code Review Panel Self-Governance Vote has been undertaken pursuant to GR.24.9.
If such an appeal is made, implementation of the Grid Code Modification Proposal shall
be suspended pending the outcome. The appealing User (including any Authorised
Electricity Operator; The Company or a Materially Affected Party), the Citizens
Advice or the Citizens Advice Scotland must notify the Panel Secretary of the appeal
when the appeal is made.
GR.24.14 The Authority shall consider whether the appeal satisfies the following criteria:
(a) The appealing party is, or is likely to be, unfairly prejudiced by the implementation
or non-implementation of that Grid Code Modification Proposal or Workgroup
Alternative Grid Code Modification(s); or
(b) The appeal is on the grounds that, in the case of implementation, the Grid Code
Modification Proposal or Workgroup Alternative
(c)
(d) Grid Code Modification(s) may not better facilitate the achievement of at least
one of the Grid Code Objectives; or
(e) The appeal is on the grounds that, in the case of non-implementation, the Grid
Code Modification Proposal or Workgroup Alternative Grid Code
Modification(s) may better facilitate the achievement of at least one of the Grid
Code Objectives; and
(f) It is not brought for reasons that are trivial, vexatious or have no reasonable
prospect of success and if the Authority considers that the criteria are not
satisfied, it shall dismiss the appeal.
GR.24.15 Following any appeal to the Authority, a Grid Code Modification Proposal or
Workgroup Alternative Grid Code Modification(s) shall be treated in accordance with
any decision and/or direction of the Authority following that appeal.
GR.24.16 If the Authority quashes the Grid Code Review Panel’s determination in respect of a
Grid Code Modification Proposal or Workgroup Alternative Grid Code
Modification(s) made in accordance with GR.24.9 and takes the decision on the relevant
Grid Code Modification Proposal and any Workgroup Alternative Grid Code
Modification(s) itself, following an appeal to the Authority, the Grid Code Review
Panel’s determination of that Grid Code Modification Proposal and any Workgroup
Alternative Grid Code Modification(s) contained in the relevant Grid Code
Modification Self Governance Report shall be treated as a Grid Code Modification
Report submitted to the Authority pursuant to GR.22.6 (for the avoidance of doubt,
subject to GR.22.8 to GR.22.12) and the Grid Code Review Panel’s determination shall
be treated as its recommendation pursuant to GR.22.4.
GR.24.17 If the Authority quashes the Grid Code Review Panel’s determination in respect of a
Grid Code Modification Proposal or Workgroup Alternative Grid Code
Modification(s) made in accordance with GR.24.9, the Authority may, following an
appeal to the Authority, refer the Grid Code Modification Proposal back to the Grid
Issue 5 Revision 37 1 August 2019
Code Review Panel for further re-consideration and a further Grid Code Review Panel
Self-Governance Vote.
GR.24.18 Following an appeal to the Authority, the Authority may confirm the Grid Code Review
Panel’s determination in respect of a Grid Code Modification Proposal or Workgroup
Alternative Grid Code Modification(s) made in accordance with GR.24.9.
GR.25 IMPLEMENTATION
GR.25.1 The Grid Code shall be modified either in accordance with the terms of the direction by
the Authority relating to, or other approval by the Authority of, the Grid Code
Modification Proposal or any Workgroup Alternative Grid Code Modification(s)
contained in the relevant Grid Code Modification Report, or in respect of Grid Code
Modification Proposals or any Workgroup Alternative Grid Code Modification(s)s
that are subject to the determination of the Grid Code Review Panel pursuant to
GR.24.9, in accordance with the relevant Grid Code Modification Self-Governance
Report subject to the appeal procedures set out in GR.24.13 to GR.24.18.
GR.25.2 The Code Administrator shall forthwith notify (by publication on the Website and, where relevant
details are supplied by electronic mail):
GR.25.3 A modification of the Grid Code shall take effect from the time and date specified in the
direction, or other approval, from the Authority referred to in GR.25.1 or, in the absence
of any such time and date in the direction or approval, from 00:00 hours on the day falling
ten (10) Business Days after the date of such direction, or other approval, from the
Authority. A modification of the Grid Code pursuant to GR.24.9 shall take effect , subject
to the appeal procedures set out in GR.24.1313 to GR.24.18, from the time and date
specified by the Code Administrator in its notice given pursuant to GR.25.2, which shall
be given after the expiry of the fifteen (15) Business Day period set out in GR.24.13 to
allow for appeals, or where an appeal is raised in accordance with GR.24.13, on
conclusion of the appeal in accordance with GR.24.15 or GR.24.18 but where conclusion
of the appeal is earlier than the fifteen (15) Business Day period set out in GR.24.13,
notice shall be given after the expiry of this period. A modification of the Grid Code
pursuant to GR.26 shall take effect from the date specified in the Grid Code
Modification Fast Track Report.
GR.25.4 A modification made pursuant to and in accordance with GR.25.1 shall not be impaired or
invalidated in any way by any inadvertent failure to comply with or give effect to this
Section.
GR.25.5 If a modification is made to the Grid Code in accordance with the Transmission
Licence but other than pursuant to the other Grid Code Modification Procedures in
these Governance Rules, the Grid Code Review Panel shall determine whether or not
to submit the modification for review by a Workgroup established on terms specified by
the Grid Code Review Panel to consider and report as to whether any alternative
modification could, as compared with such modification better facilitate achieving the
Grid Code Objectives in respect of the subject matter of the original modification. Where
such a Workgroup is established the provisions of GR.20 shall apply as if such a
modification were a Grid Code Modification Proposal.
Transitional Issues
GR.25.6 Notwithstanding the provisions of GR.25.3, Modification GC0086 changes the Grid
Code process for Grid Code Modification Proposals and therefore may affect other
GR.26.1 Where a Proposer believes that a modification to the Grid Code which meets the Fast
Track Criteria is required, a Grid Code Fast Track Proposal may be raised. In such
case the Proposer is only required to provide the details listed in GR.15.3 (a), (b), (c),
(d), (e) and (k).
GR.26.2 Provided that the Panel Secretary receives any modification to the Grid Code which the
Proposer considers to be a Grid Code Fast Track Proposal, not less than ten (10)
Business Days (or such shorter period as the Panel Secretary may agree, provided that
the Panel Secretary shall not agree any period shorter than five (5) Business Days)
prior to the next Grid Code Review Panel meeting, the Panel Secretary shall place the
Grid Code Fast Track Proposal on the agenda of the next Grid Code Review Panel
meeting, and otherwise, shall place it on the agenda of the next succeeding Grid Code
Review Panel meeting.
GR.26.3 To facilitate the discussion at the Grid Code Review Panel meeting, the Code
Administrator will circulate a draft of the Grid Code Modification Fast Track Report to
Users, the Authority and Panel Members (and its provision in electronic form on the
Website and in electronic mails to Users, the Authority and Panel Members, who must
supply relevant details, shall meet this requirement) for comment not less than five (5)
Business Days ahead of the Grid Code Review Panel meeting which will consider
whether or not the Fast Track Criteria are met and whether or not to approve the Grid
Code Fast Track Proposal.
GR.26.4 It is for the Grid Code Review Panel to decide whether or not a Grid Code Fast Track
Proposal meets the Fast Track Criteria and if it does, to determine whether or not to
approve the Grid Code Fast Track Proposal.
GR.26.5 The Grid Code Review Panel’s decision that a Grid Code Fast Track Proposal meets
the Fast Track Criteria pursuant to GR.26.4 must be unanimous.
GR.26.6 The Grid Code Review Panel’s decision to approve the Grid Code Fast Track
Proposal pursuant to GR.26.4 must be unanimous.
GR.26.7 If the Grid Code Review Panel vote unanimously that the Grid Code Fast Track
Proposal meets the Fast Track Criteria and to approve the Grid Code Fast Track
Proposal (which shall then be an “Approved Fast Track Proposal”) until implemented,
or until an objection is received pursuant to GR.26.12), then subject to the objection
procedures set out in GR.26.12 the Grid Code Fast Track Proposal will be implemented
by The Company without the Authority’s approval. If the Grid Code Review Panel do
not unanimously agree that the Grid Code Modification Proposal meets the Fast Track
Criteria and/or do not unanimously agree that the Grid Code Fast Track Proposal
should be made, then the Panel Secretary shall, in accordance with GR.15.4(a) notify
the Proposer that additional information is required if the Proposer wishes the Grid
Code Modification Proposal to continue.
GR.26.9 The matters to be included in a Grid Code Modification Fast Track Report shall be the
following (in respect of the Grid Code Fast Track Proposal):
(a) a description of the proposed modification and of its nature and purpose;
(b) details of the changes required to the Grid Code, including the proposed legal text to
modify the Grid Code to implement the Grid Code Fast Track Proposal;
(d) the intended implementation date, from which the Approved Fast Track Proposal
will take effect, which shall be no sooner than fifteen (15) Business Days after the
date of notification of the Grid Code Review Panel’s decision to approve; and
(e) details of how to object to the Approved Fast Track Proposal being made
GR.26.10 Upon approval by the Grid Code Review Panel of the Grid Code Modification Fast
Track Report, the Code Administrator will issue the report in accordance with
GR.26.11.
GR.26.11 The Code Administrator shall copy (by electronic mail to those persons who have
supplied relevant details to the Code Administrator) the Grid Code Modification Fast
Track Report prepared in accordance with GR.26 to:
GR.26.12 A User, any Authorised Electricity Operator; The Company or a Materially Affected
Party, the Citizens Advice, the Citizens Advice Scotland or the Authority may object
to the Approved Fast Track Proposal being implemented, and shall include with such
objection the reasons for the objection. Any such objection must be made in writing
(including by email) and be clearly stated to be an objection to the Approved Fast Track
Proposal in accordance with this GR.26 of the Grid Code and be notified to the Panel
Secretary by the date up to and including fifteen (15) Business Days after notification of
the Grid Code Review Panel’s decision to approve the Grid Code Fast Track
Proposal. If such an objection is made the Approved Fast Track Proposal shall not be
implemented. The Panel Secretary will notify each Panel Member and the Authority of
the objection. The Panel Secretary shall notify the Proposer, in accordance with
GR.15.4A that additional information is required if the Proposer wishes the Grid Code
Modification Proposal to continue.
1. The election process has two main elements: nomination and selection.
2. The process will be used to appoint Panel Members in the category of Supplier, Generator, Offshore
Transmission Owner and Onshore Transmission Owner.
3. The Code Administrator will publish the Election timetable by [September] in the year preceding the start
of each term of office of Panel Members.
4. Each step of the process set out below will be carried out in line with the published timetable.
5. The Code Administrator will establish an Electoral Roll from representatives of parties listed on CUSC
Schedule 1 or designated by the Authority as a Materially Affected Party as at 31st August in the year
preceding the start of each term of office of Panel Members.
6. The Code Administrator will keep the Electoral Roll up to date.
Nomination Process
7. Each party on the Electoral Roll may nominate a candidate to stand for election for the GCRP.
8. Parties may only nominate a candidate for their own category; a Supplier may nominate a candidate for
the Supplier Panel Member seat and a Generator may nominate a candidate for the Generator Panel
Member seats. If a party able to nominate a candidate is both a Supplier and a Generator, they may
nominate a candidate in each category.
9. The nominating party must complete the nomination form which will be made available by the Code
Administrator and return it to the Code Administrator by the stated deadline.
10. The Code Administrator will draw up a list of candidates for each category of election.
11. Where there are fewer candidates than seats available or the same number of candidates as seats
available, no election will be required and the nominated candidate(s) will be elected. The Code
Administrator will publish a list of the successful candidates on the Grid Code website and circulate the
results by email to the Grid Code circulation list.
Selection Process
12. The Code Administrator will send a numbered voting paper to each party on the electoral roll for each of
the elections in which they are eligible to vote. The voting paper will contain a list of candidates for each
election and will be sent by email.
13. Each eligible party may vote for one [1] candidate for each of the Supplier, Offshore Transmission Owner
and Onshore Transmission Owner seats and four [4] candidates for the Generator seats.
14. Panel Members will be elected using the First Past the Post method.
15. In the event of two or more candidates receiving the same number of votes, the Code Administrator will
draw lots to decide who is elected.
16. The Code Administrator will publish the results of the election on the Grid Code website and circulate the
results by email to the Grid Code circulation list.
17. The Code Administrator will send an Election Report to Ofgem after the election is complete.
R.1 The Company’s Transmission Licence sets out the way in which changes to the Grid Code
are to be made and reference is also made to The Company's obligations under the General
Conditions.
R.2 All pages re-issued have the revision number on the lower left hand corner of the page and date
of the revision on the lower right hand corner of the page.
R.3 The Grid Code was introduced in March 1990 and the first issue was revised 31 times. In March
2001 the New Electricity Trading Arrangements were introduced and Issue 2 of the Grid Code
was introduced which was revised 16 times. At British Electricity Trading and Transmission
Arrangements (BETTA) Go-Active Issue 3 of the Grid Code was introduced and subsequently
revised 35 times. At Offshore Go-active Issue 4 of the Grid Code was introduced and has been
revised 13 times since its original publication. Issue 5 of the Grid Code was published to
accommodate the changes made by Grid Code Modification A/10 which has incorporated the
Generator compliance process into the Grid Code.
R.4 This Revisions section provides a summary of the sections of the Grid Code changed by each
revision to Issue 5.
R.5 All enquiries in relation to revisions to the Grid Code, including revisions to Issues 1, 2, 3, 4 and 5
should be addressed to the Grid Code development team at the following email address:
[email protected]
Revision Section Related Effective Date
Modification
Secretary of State
8 Planning Code 10 June 2014
direction –
Revision Section Related Effective Date
Modification
Generator
Commissioning
Clause
Secretary of State
8 Connection Conditions 10 June 2014
direction –
Generator
Commissioning
Clause
Secretary of State
8 Compliance Processes 10 June 2014
direction –
Generator
Commissioning
Clause
Secretary of State
8 Operating Code No. 5 10 June 2014
direction –
Generator
Commissioning
Clause
Secretary of State
8 Operating Code No. 7 10 June 2014
direction –
Generator
Commissioning
Clause
Secretary of State
8 Operating Code No. 8 10 June 2014
direction –
Generator
Commissioning
Clause
Secretary of State
8 Operating Code No. 8A 10 June 2014
direction –
Generator
Commissioning
Clause
Secretary of State
8 Operating Code No. 8B 10 June 2014
direction –
Generator
Commissioning
Clause
Secretary of State
8 Balancing Code No. 2 10 June 2014
direction –
Generator
Commissioning
Clause
26 September 2018
26 Glossary Definitions GC0115
26 September 2018
26 Operating Code 1 GC0115
26 September 2018
26 Operating Code 2 GC0115
26 September 2018
26 Operating Code 6 GC0115
26 September 2018
26 Operating Code 7 GC0115
26 September 2018
26 Operating Code 8 GC0115
26 September 2018
26 Operating Code 8B GC0115
26 September 2018
26 Operating Code 9 GC0115
26 September 2018
26 Operating Code 10 GC0115
26 September 2018
26 Operating Code 11 GC0115
26 September 2018
26 Operating Code 12 GC0115
26 September 2018
26 Balancing Code 3 GC0115
26 September 2018
26 General Conditions GC0115
26 September 2018
26 Governance Rules GC0115