Practitioner Guide Information Security Risk Management V2.0
Practitioner Guide Information Security Risk Management V2.0
You are free to re-use this work under a Creative Commons Attribution 4.0 licence, provided you credit the
State of Victoria (Office of the Victorian Information Commissioner) as author, indicate if changes were
made and comply with the other licence terms. The licence does not apply to any branding, including
Government logos.
For further information, please contact the Information Security Unit on security@ovic.vic.gov.au
1. Background
The Office of the Victorian Information Commissioner (OVIC) issues security guides to support the Victorian
Protective Data Security Standards (VPDSS).
This document forms part of a suite of supporting security guides of the VPDSS.
2. Purpose
This document provides organisations with guidance on security risk management fundamentals to enable
them to undertake a Security Risk Profile Assessment (SRPA) as required under s89 of the Privacy and Data
Protection Act 2014 (PDP Act).
3. Audience
This document is intended for Victorian public sector organisations (including employees, contractors and
external parties) that are subject to the protective data security provisions under Part 4 of the PDP Act.
Please refer to the VPDSS Glossary for an outline of terms and associated definitions. For a current copy of
the glossary, please refer to the VPDSF Resources section of the OVIC website.
A process that organisations undertake to assess and manage information security risks. Most SRPAs
prepared under the VPDSS assess physical security risks and personnel security risks in addition to
information technology risks as it relates to information assets 1.
5. Scope
The activities set out in this document help organisations identify, analyse and evaluate their information
security risks more effectively, and then manage these with their existing risk management frameworks or
by referencing established risk management material, such as:
This document directly supports the VPDSS information security risk management standard, and also steps
1
Although information assets are the focus under the VPDSS, organisations can use the same process for identifying security risks for other assets
such as people and physical assets.
Freedom of Information | Privacy | Data Protection 5
Practitioner Guide | Information Security Risk Management
3 to 5 of the Five Step Action Plan 2 by identifying information risks, applying security controls and managing
risks across the information lifecycle.
6. Assumptions
The activities set out in this document assume organisations have basic risk management practices in place
and these are operating effectively 3.
Organisations deal with many categories of operational risk (financial, safety, people, operational, etc.). A
risk category helps to classify a ‘type’ of risk and manage it more effectively.
Risk within the context of this document, is focused on the protection of public sector information assets.
This is often referred to as security risk, information security risk or information risk and is a category of risk
to be considered along with other risk categories within an organisational risk management framework.
This makes it easier to understand the context of the risk and develop a profile of security risks of the
organisation.
Organisations should continue to utilise these practices and refer to this guidance for information security
risk advice to enable completion of the SRPA and Protective Data Security Plan (PDSP).
Organisations who have risk practitioners and/or security practitioners will be well placed to drive the
actions set out in this document.
The way in which your organisation identifies information assets as the subject of the SRPA is flexible.
Further guidance on information assets can be found in the Practitioner Guide: Identifying and Managing
Information Assets.
There are a wide range of threats that if given the opportunity to interact with an organisation’s
information and supporting systems, could pose risks to an organisation. Organisations that identify and
manage their risks will have greater confidence to minimise harm and damage, and recover from impacts
faster and in a more cost effective manner than those that do not.
The VPDSS and Victorian Protective Data Security Framework (VPDSF) are built upon the foundation of risk
management principles. It is imperative that organisations are aware of the application of those principles
to allow for the identification and management of information security risks to Victorian government
information.
A SRPA can be a powerful process for identifying and prioritising information security risks to provide
efficient, effective and economic investment in security controls. This process does not need to be overly
complicated or time consuming. The outcomes of the SRPA will allow organisations to provide a level of
confidence to citizens, businesses and the community as a whole when interacting with government.
Prior to undertaking the SRPA, you should develop risk evaluation and acceptance criteria that aligns to, or
uses, your organisation’s existing risk evaluation processes. This may need to be revised as part of the risk
evaluation process 4.
2
Refer to the Five Step Action Plan for further guidance on each of the steps https://ovic.vic.gov.au/data-protection/for-agencies/vpdsf-resources/.
3The Victorian Managed Insurance Agency (VMIA) provides guidance on implementing the Victorian Government Risk Management Framework
(VGRMF). Organisations should refer to VMIA https://vmia.vic.gov.au for further guidance on risk management principles and practices.
4 Further information is provided in section 10.4 – Risk evaluation.
This practitioner guide provides a simple-to-use methodology designed to assist you to undertake the SRPA
to manage information security risks. The content in this guide is consistent with the principles detailed in
local, national and international risk management standards and guidelines.
This walks you through the key stages of the standardised risk management process as visually represented
by Diagram 1. Each stage of the process is represented by colour coded dots located throughout the
document to keep track of where you are in the process.
The SRPA process leverages existing organisational risk management decisions, such as:
Organisations assess operational risk categories (such as OH&S, finance, etc.) in variety of ways. For
information security, you may consider developing a SRPA project plan that addresses the following:
• assumptions;
• relationships with other security functions (e.g. personnel security, physical security, fraud control,
anti-corruption.)
8. Consultation
Consultation across your organisation is important in order to identify all probable risks to information
assets, and the impact of these to your organisation.
Formalising the consultation process for larger organisations ensures that it receives senior management
support and includes all business areas and relevant third parties. This will also allow senior management
to set priorities on functions they consider critical.
The consultation process will also allow you to identify the individual risk owners who have knowledge of
risks and controls. These would normally be the information asset owners, although for critical risks the
level of ownership may be escalated to a more senior person in your organisation. It is also important to
understand the perspectives of each stakeholder as these will include natural biases.
8.1. Consultation with Information Owners, System Owners and Records Managers
Not all organisations will have the same information management (IM) roles and responsibilities, as these
are largely informed by the size, structure and resourcing of the business. Regardless, consultation should
start with information owners and supporting system owners (custodians), subsequently extending to
records managers and other stakeholders with an interest in, or influence over these assets.
These stakeholders can add valuable input and an understanding of the criticality of these assets as well as
probable threats to them. Stakeholders include internal and external parties.
There may be overlap between the controls implemented to protect information and other assets, such as
people, and physical assets (e.g. buildings and equipment). When undertaking the SRPA, it is important to
identify any existing or planned implementation of security controls for other areas of protective security
such as personnel security and physical security, that may have a material impact on, or assist in the
mitigation of risks to information assets. Working with other security risk areas will also allow the use of
single security controls that can mitigate multiple risks across the organisation and ensure that the risk
management approach established within your organisation and the SRPA process work in unison.
The practitioners in these other security risk areas will be able to provide specialist advice and assistance
throughout the SRPA by advising on the effectiveness of existing security controls and suitability of
proposed new controls to mitigate risks to information assets.
An organisation’s human resources unit develops a personnel screening program as part of the
recruitment and ongoing human resource management processes.
The security area (or equivalent) should engage with all business units so that all areas of the
business are aware that any changes to systems, processes or people should include engagement
with the security area. So in this example, this would be an opportunity for the human resources
unit to consult with the security area to ensure the planned security controls will help mitigate
identified risks (e.g. the risks of deliberate unauthorised disclosure of information, fraud, theft of
assets and employing unsuitable personnel for roles).
As part of the SRPA, it is important to consult with your third parties (e.g. contracted service providers), as
these type of engagements may introduce additional risks. These third parties may be able to offer
additional considerations that otherwise may not have been originally scoped.
You may also liaise with other Victorian government organisations such as the Victorian Managed
Insurance Authority (VMIA) or the Cyber Safety Unit (CSU) in Department of Premier and Cabinet who may
be able to provide insights and advice on the threats and risks in Victorian government.
Prior to undertaking any form of risk assessment, you need to understand the context in which the
assessment is being undertaken. By establishing the context you can properly understand, align, plan and
prepare the most appropriate activities to support the SRPA process.
When gaining an understanding of the context, consider both internal business functions, as well as the
broader environment in which your organisation is operating.
An essential foundation for the SRPA is having a thorough appreciation of your organisation’s core
functions and services, as well as the supporting information assets that are critical to meeting its business
objectives.
By understanding your organisation’s business you will be able to select security controls that:
Prior to undertaking a risk assessment, your organisation will need to know the information assets across
the business. Identifying information assets is Step 1 of the Five Step Action Plan. Guidance on identifying
information assets is contained in the Practitioner Guide: Identifying and Managing Information Assets 5.
Organisations are also required to conduct a security value assessment of the information assets to
understand the criticality of the information. Performing a security value assessment of your organisation’s
information assets is Step 2 of the Five Step Action Plan. Guidance on conducting a security value
assessment is contained in the Practitioner Guide: Assessing the Security Value of Information 6.
Use the outcomes from Steps 1 and 2 of the Five Step Action Plan to enable you to prioritise which
information assets to focus your risk assessment.
Additionally, most organisations rely on contracted service providers for some of their services or
functions. Organisations should consider all contracted service providers and their specific roles as part of
undertaking a SRPA.
Environmental considerations may also impact the risks to your information. These could include natural
and manmade environmental considerations (e.g. flood/ bushfire and local crime statistics).
5
Refer to the Resources published on the OVIC website https://ovic.vic.gov.au/data-protection/for-agencies/vpdsf-resources/.
6 Refer to the Resources published on the OVIC website https://ovic.vic.gov.au/data-protection/for-agencies/vpdsf-resources/.
• submit their revised PDSP to OVIC every two years, or where there is a significant change.
To support these requirements, organisations should undertake the SRPA regularly (e.g. at least annually)
to assist with completing their PDSP and align with other risk management activities across the
organisation.
In addition, your organisation will have its own legislative and regulatory requirements relating to the
management of public sector information. You should confirm these prior to undertaking the SRPA, as they
may impact on how the risks to your organisation’s information are managed.
• risk identification;
• risk analysis;
• risk treatment.
These steps are detailed in Diagram 2. SRPA phases. It is important that the person undertaking the SRPA
consult with all affected stakeholders at each step in the process.
The SRPA will help you identify information security risks which should be recorded in your risk register. In
order to manage security risks, some organisation have a separate register for security risks – whichever
process you choose it should reflect your organisation’s approach to managing categories of risk. A generic
risk register template is available on the VMIA website 8. The template should outline the minimum details
to record each information security risk and should be tailored to fit your organisation’s current risk
management practices. The risk references in the register will also feed into your organisation’s PDSP.
Guidance on filling in the PDSP is contained in the PDSP form 9.
Identifying risks, prior to implementing security controls, enables the efficient, effective and economic
investment in information security. To perform this risk identification, organisations should utilise their
existing processes where available.
8
Refer to https://www.vmia.vic.gov.au/tools-and-insights/tools-guides-and-kits/risk-management-tools.
9 Refer to the Resources published on the OVIC website https://ovic.vic.gov.au/data-protection/agency-reporting-obligations/pdsp-submission/.
Risk identification defines the ‘risk’ problem and provides insight into ‘uncertainty’ and the probable effect
on achieving the business objectives. A well-described risk will:
• provide context and meaning of the event, cause and impact for management;
Recent incidents and security trends, along with results from audits, will also help to identify risks and
inform your selection of security controls to best address these risks.
As part of undertaking a risk assessment, your organisation will need to select the information assets that
become the focus of the SRPA.
Given the large number of information assets that some organisations may have, initially prioritise the
security risk assessment process to critical information assets (i.e. by prioritising protecting the most
valuable assets, which Step 2 of the Five Step Action Plan will identify for you). The outcomes of the
security value assessment 10, will not only inform which assets to focus on but will also be used during the
consequence rating activity of the risk assessment process.
Once these have been completed, it is expected that all other information assets (i.e. assessed as non-
critical) are subsequently considered.
For the purposes of the risk statement, there is only one ‘risk event’. While there may be a number of
‘contributing events’ as a result of the way in which causes (threats) interact with your organisation’s
information, the ‘risk event’ will typically be the most significant event. This one event is likened to a
‘headline’ (e.g. how would it be presented if it were to be reported in the press).
A natural weather occurrence may be the initiating cause of ‘data loss’ (risk event) but as a result
of the weather occurrence, a lightning strike can damage power lines (event), a plant room can
flood (event) and a backup generator can be submerged in water (event). All of these events can
contribute to the data loss.
10
Refer to the BIL table published on the OVIC website https://ovic.vic.gov.au/data-protection/for-agencies/vpdsf-resources/.
Understanding the composition of causes can be useful in gaining a deeper understanding of the overall
threat environment in which you operate. This knowledge will be of benefit in the later stages of a risk
assessment process, particularly in establishing the likelihood of risks eventuating, security controls
required, and prioritising risk treatment.
The causes of risks to information assets can come from a variety of areas and may be accidental,
deliberate or natural (environmental). Broadly they fall into two categories:
• external causes – vectors (people, organisations, governments, etc.) outside of the organisation’s
control; and
• internal causes – actions/ failures of people, processes or systems within the organisation.
It is helpful to identify all of the probable (not possible) risk causes to your information in each category,
including the identification of the root cause (i.e. the initiator – what started it all).
A list of typical threats to information are available from AS/NZS ISO/IEC 27005:2012 Information
Technology – Security techniques – Information security risk management, Annex C.
It is important that during the process, organisations work on probable events, causes and impacts rather
than possible. It is unrealistic to cover off all situations (possible). Organisations are far better placed to
work on situations that are more likely (probable) to ensure the most effective, efficient and economic use
of resources.
Perhaps an extreme example to illustrate: You could plan for a meteorite hitting your data centre, and
whilst this is possible, it is not probable and you should focus on more realistic scenarios like a cyber threat
(for instance).
‘Impacts’ are described as the effects of the event on your organisation, government operations or
individuals, if the risk event occurred.
To help your organisation identify potential impacts, refer to the impact categories from the VPDSF
Business Impact Level (BIL) table 11. Use the BIL table categories to describe the resulting impacts to
government operations, organisations or individuals if there were a compromise of the confidentiality,
integrity and availability of public sector information.
Once you have established the three principal elements of risk (risk event, cause and impact) you now
combine them to identify the final risk statement. The process contained in example 4, provides guidance
on how to construct a risk statement using the three elements.
A well-formulated risk statement is fundamental to the assessment and evaluation of risks as it documents
and sets the scope of an identified risk. If you leave any aspects of the risk statement out, analysis of the
risks you get back will be influenced by assumptions and may not meet the initial intent or scope you
desired.
Risk statement The risk of the deletion (loss) or modification (data quality) of
financial records (events)
caused by unauthorised use of the financial system by a
disgruntled employee (cause)
resulting in impact to the delivery of services (impacts).
‘The risk of the deletion (loss) or modification (data quality) of financial records caused by
unauthorised use of the financial system by a disgruntled employee resulting in impact to the
delivery of services’.
As a threat may have multiple probable events or vice versa, you could combine these as a single risk as
above. However, it may be more beneficial to break them down into separate statements to allow each risk
to be treated in its own right (as below).
Example 4 (Cont.)
1. The risk of the modification (data quality) of financial records caused by a disgruntled
employee resulting in impact to service delivery.
2. The risk of the deletion (loss) of financial records caused by a disgruntled employee resulting
in impact to service delivery.
Thinking of your organisation, would you treat the two sample risk statements differently or the same? This
will differ organisation to organisation. The important outcome of the statement is that you treat the risk in
a manner that provides you with the most assurance and is consistent with your risk management
framework.
10.2.6. Introduction and overview of the ‘Bowtie method’ to determine risks
Organisations may gain further assistance to identify the risk elements and links between event, causes
(threat) and impacts by undertaking a bowtie analysis of each risk. Diagram 3 is a sample of the bowtie
method.
The first step in a bowtie analysis is understanding the ‘risk event’ (centre) followed by identifying the
causes (threats) and impacts. A bowtie analysis will also help you identify possible root causes for risks and
where in the activity any corresponding controls are needed to mitigate the risk.
The discovery of risk elements using a bowtie analysis gives great insight into selection of security controls
that target all the factors contributing to the risk (i.e. preventative, detective and corrective security
controls). The financial information risk in example 4 is represented using the bowtie model in Diagram 4 to
enable you to visually see the risk statement.
Risk analysis is the process of determining a rating for the level of each risk, also known as the ‘risk rating’.
Identification of security controls currently implemented at this stage of risk analysis is imperative to rating
the likelihood of a risk event occurring and the business impacts associated as a result.
Evaluation of the effectiveness of existing security controls should also be conducted prior to determining
the rating of the business impacts or likelihood. Evaluation of effectiveness should be supported by audit
activities and information that can be tested to confirm the effectiveness of security controls. Organisations
should have their own evaluation of control effectiveness to guide the process.
Additional advice on evaluating effectiveness of existing security controls is available from the VGRMF
Practice Guide 12.
Assigning a security value to information assets is equivalent to rating the ‘impact’ (consequence) identified
in a risk event. That is, once a risk event has been identified, an organisation is well positioned to
understand the impact from a compromise to the information asset, as the assessment has already been
conducted as part of the information security value assessment.
The organisation’s BIL table can be aligned with your risk consequence ratings table. An ‘indicative only’
mapping is shown in Diagram 5. Alignment of BIL table and risk consequence ratings table.
The ‘security value’ of the information as derived from the BIL table will directly correspond to your risk
consequence ratings table once mapping has occurred (i.e. negates the requirement to ‘rate business
impacts’ as a stand-alone exercise).
By aligning your organisation’s BIL table with the risk consequence ratings, this will not only strengthen the
alignment with your internal risk management framework but will ensure the security controls used for the
protection of information assets are selected in a consistent manner across your organisation and enable
alignment with other internal control frameworks your organisation may be required to implement.
12
Refer to the VGRMF Practice Guide published on the VMIA website https://www.vmia.vic.gov.au/tools-and-insights/tools-guides-and-
kits/victorian-government-risk-management-framework.
It is worth noting that the effectiveness of any existing security controls in place may directly influence the
likelihood of the risk occurring and should also be considered when determining the actual likelihood.
When determining likelihood, you should consider both previous occurrences and future considerations
(e.g. the intent, motivation or the capability of human or adversarial threats) 13.
Example 6. Likelihood
An organisation’s threat intelligence data indicates that they could expect a malware attack against
their firewall almost weekly and therefore attract an ‘almost certain’ rating.
When the organisation considers its existing security controls (e.g. a cloud ‘Security as a Service’
provider which filters and stops known malware attacks reaching the organisation’s firewall), they
assess the likelihood rating as ‘unlikely’.
You should use the risk ratings matrix developed in your organisation’s risk management framework. If
your organisation doesn’t have one, you can refer to the Risk Criteria Examples published by VMIA under
their Risk management tools 15.
After you have identified and analysed the risks to your organisation’s information assets, you should
evaluate which risks are rated at an acceptable level and which need to be prioritised for further action.
The evaluation of risk appetite and prioritisation is a key component in determining the next steps in
implementing additional security controls in order to bring the risks to levels that are considered
acceptable by your organisation.
13 An indicative list of potential threats to information are available from AS/NZS ISO/IEC 27005:2012 Information technology — Security techniques
— Information security risk management, Annex C.
14 Refer to the VGRMF Practice Guide published on the VMIA website https://www.vmia.vic.gov.au/tools-and-insights/tools-guides-and-
kits/victorian-government-risk-management-framework.
15
Refer to the VMIA B2 Risk criteria examples published on the VMIA website https://www.vmia.vic.gov.au/tools-and-insights/tools-guides-and-
kits/risk-management-tools.
Good governance of the identified risks becomes increasingly important at this stage and the use of your
risk register is recommended to track your progress, allocate accountability and encourage a perpetual
cycle of monitoring and review.
(1) accept – if the risk is within the risk appetite for your organisation then ongoing monitoring will be the
primary requirement;
(2) share – parts of the risk can be shared with a third party, although overall ownership of the risk will
remain with the information owner (i.e. your organisation). While this may reduce financial
consequences to an organisation, it is unlikely to reduce other BIL categories;
(3) reduce – you can attempt to minimise the risk by introducing additional security controls to reduce the
impact (consequence) and/ or likelihood of the risk; or
(4) avoid – if an activity produces a risk that is higher than your organisation is willing to accept and it
cannot be treated by other means, you may cease that activity altogether in order to avoid the risk.
However, if the function is mandated by government then this may not be possible.
You should determine which option is best for your organisation for each risk after considering your
organisation’s risk appetite, tolerance and priorities.
Risk appetite is the amount and type of risk that your organisation is willing to take to achieve its business
objectives. Risk appetite is set at the strategic level, it influences and guides decision-making, and will vary
from organisation to organisation. Risk appetite may also vary within your organisation depending on
criticality of information/ services that may be affected by the risk.
In an ideal world, the acceptable level of risk would be the lowest available rating. However, due to cost
restrictions and other considerations, this may simply not be practical. When you consider what level
would be acceptable for each risk, you should take into account what is reasonably practical to achieve.
If the identified risk is within your organisation’s risk appetite, the risk may be accepted.
The organisation’s readiness to endure the risk after risk treatment in order to achieve objectives. Risk
tolerances are articulated at the operational level of an organisation because the business understands
how much risk they can withstand are based on the maximum level of acceptable risk and may be
expressed as a range.
The Articulate risk appetite tolerance document published by VMIA under their Risk management tools 16
includes example risk appetite and tolerance statements.
To determine with what urgency you should address risks, they must first be prioritised. Risks with the
highest risk rating are normally attended to first.
16
Refer to the A6 Articulate risk appetite tolerance document published on the VMIA website https://www.vmia.vic.gov.au/tools-and-
insights/tools-guides-and-kits/risk-management-tools.
Your organisation may choose to identify a default level at which risks rated above this level must be
attended to more urgently and where increasingly more senior levels of management need to be kept up-
to-date on progress. For example, internal standards may state that risks rated as ‘high’ or ‘very high’ must
be addressed immediately with the organisation’s most senior person or body notified whereas risks rated
at ‘medium’ require action at the local level.
With the risks grouped according to their risk rating, further criteria now needs to be considered in order to
prioritise them further. Typically, additional considerations may include:
• cost – how much will it cost to reduce the risk (and will the benefits outweigh the expenditure)?
• reputation – what is the likely effect on reputation if the risk is not treated?
• legal obligations – is the organisation likely to be unable to meet its legal obligations if the risk is
left in its current state?
SECRISK01. The risk of disclosure of personal address information caused by disgruntled customer
resulting in personal serious injury due to assault of personnel: ‘high’
SECRISK02. The risk of disclosure of critical asset location information leading to vandalism of assets
caused by malicious contractor resulting in service delivery outage: ‘high’
SECRISK03. The risk of failure of the Client Relationship Management system database caused by
natural event (power outage) resulting in personal stress related injuries due to verbal
abuse of call centre staff from customers: ‘medium’
With risks first prioritised by rating, the organisation considers safety to be its priority so the
assault related risk is ranked first, with the vandalism related risk ranked second and the call centre
risk ranked third.
For risks identified as being beyond your organisation’s risk appetite, apply additional security controls in
order to reduce risks.
A list of high-level security measures called the VPDSS Elements have been derived from the ‘primary
sources’ listed within the VPDSS Implementation Guide 17. Organisations should implement specific controls
appropriate to their organisation considering:
• associated risks.
The selection of these elements (or granular controls) will form your internal control library and will also
enable you to fill in your PDSP.
When selecting security controls to mitigate risks, consider the most effective, efficient and economic use
of your budget. The grouping of like risks, or risks from similar threats, even when they have different
ratings, may allow you to achieve better value for money.
Identify a range of security controls that when used singularly or in combination will allow you to mitigate
the risks to an acceptable level. Additionally, when selecting a range of security controls, not all controls
should be of a technical nature, and may also relate to processes and people. Consider selecting controls
across all the security areas (governance, information, personnel, Information Communications Technology
(ICT), and physical).
Security controls should also provide ‘defence-in-depth’ (i.e. a number of controls may provide overlapping
risk mitigation which can provide some surety if one control fails).
For instance, it may be possible for you to lower the business impact from a risk event by separating
information into multiple repositories, thereby limiting the amount of information that can be
compromised. This control could lower the overall impact of an information security incident if it were to
occur.
It is more probable that you could select security controls that lower the likelihood of a compromise to
your information assets.
Security controls, or groups of controls, that lower the likelihood of compromise of information are ideal,
as they will give the greatest overall reduction to achieve the desired target risk.
Consider using the bowtie model to visualise the controls. Although applying controls will generally assist to
modify the risk, you may find preventative controls are more effective as they prevent the risk event from
occurring in the first place. Example controls to mitigate the financial information risk in Example 4 are
represented using the bowtie model in Diagram 5 to enable you to visually see where the controls sit with
respect to the risk statement. Some controls (e.g. staff training and awareness), may be both a preventative
and corrective control.
It may be useful to undertake a cost benefit analysis of the selected security controls to support your
submission to senior management.
The controls are more likely to receive endorsement if you can demonstrate that your selected security
controls not only reduce the risk to an acceptable level (where possible) and meet the business needs of
your organisation, but also provide other benefits to your organisation or improvements to business
processes.
18
Term as used by VMIA. Some organisations may also use the term residual in their risk management framework or refer to ‘resulting risk’ as per
AS ISO 31000.
Freedom of Information | Privacy | Data Protection 23
Practitioner Guide | Information Security Risk Management
All risks identified as part of the SRPA are subject to ongoing monitoring and review. The frequency and
depth of attention you give each risk should reflect its rating and priority.
Review risks if there are any changes to your organisation’s operating environment as these changes may
impact the existing risks, introduce new risks or change the criticality of your assets.
If your organisation has not already done so, allocate an owner to each identified security risk to ensure it is
reviewed with an appropriate frequency and that any additional actions and controls identified are
undertaken within a designated timeframe.
In most circumstances the information owner/ custodian could be the risk owner, as they are most likely to
be aware of changes to the threat environment of the asset. However, for higher risks to critical
information assets it may be more appropriate to assign a senior officer as the risk owner to ensure the risk
receives the level of oversight commensurate with the risk to your organisation.
The overall owner of the SRPA is the public sector body Head. The Head may delegate the management of
the SRPA to a senior officer who should be independent of the information owners to ensure all risks to
information are given appropriate priority.
As part of continuous improvement, the SRPA process should be regularly reviewed (e.g. annually, upon
significant change) to ensure it is fit for purpose and aligned with your organisation’s risk management
framework.