Project Management: Cpm/Pert

This document contains a Gantt chart and activity schedule for a candlelight choir service project. It shows 14 activities (A-O) with start and finish dates. The critical path activities are A, B, C, D, E, M, N and O, with a total project duration of 92 days. Float values are provided to indicate slack or flexibility in the schedule for non-critical activities.

Uploaded by

Nurina Z Wahid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
72 views

Project Management: Cpm/Pert

This document contains a Gantt chart and activity schedule for a candlelight choir service project. It shows 14 activities (A-O) with start and finish dates. The critical path activities are A, B, C, D, E, M, N and O, with a total project duration of 92 days. Float values are provided to indicate slack or flexibility in the schedule for non-critical activities.

Uploaded by

Nurina Z Wahid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

PROJECT MANAGEMENT:

CPM/PERT
PROJECT MANAGEMENT: CPM/ PERT
E

F G M
B

A D H L

C N
I

J K
E 19 89
70 19 89
S 0 0

B 2 16 F 19 33 G 33 34 M 89 90
14 2 16 14 74 88 1 88 89 1 89 90
S 0 0 S 55 55 S 55 55 S 0 0

A 0 2 D 16 19 H 19 20 L 40 41
START

2 0 2 3 16 19 1 89 90 1 88 89
S 0 0 S 0 0 S 70 70 S 48 48
N 90 91
C 2 16 I 19 26
1 90 91
14 2 16 7 84 91
S 0 0
S 0 0 S 65 65
O 91 92

FINISH
J 19 26 K 26 40
1 91 92
7 67 74 14 74 88
S 0 0
S 48 48 S 48 48

Forward pass
Backward pass
Table Activity Schedule for Candlelight Choir Service Project
Earliest Start Latest Start Earliest Finish Latest Finish
Activity Float (LS –ES) Critical Path
(ES) (LS) (EF) (LF)
A 0 0 2 2 0 Yes
B 2 2 16 16 0 Yes
C 2 2 16 16 0 Yes
D 16 16 19 19 0 Yes
E 19 19 89 89 0 Yes
F 19 74 33 88 55
G 33 88 34 89 55
H 19 89 20 90 70
I 19 84 26 91 65
J 19 67 26 74 48
K 26 74 40 88 48
L 40 88 41 89 48
M 89 89 90 90 0 Yes
N 90 90 91 91 0 Yes
O 91 91 92 92 0 Yes
Project completion time = 92 days

Critical activities are A, B, C, D, E, M, N and O

Critical path:
A – B – D – E –M – N – O
A–C–D–E–M–N–O