Scope of Work BoP For With GIS 300 MW
Scope of Work BoP For With GIS 300 MW
Project
Date: 15.10.2020
The Scope shall comprise, but not limited to the design, engineering, manufacture,
testing and inspection at manufacturers works, packing supply ,transportation,
transit insurance, delivery to site, unloading, storage and equipment erection
including associated civil works, fire detection & prevention system, structural works,
cabling, lighting, earthing, any other electrical, mechanical auxiliary
equipment/system, supervision of erection, site testing and commissioning of the
Substation, training of ReNew personnel’s and also meeting ReNew’s or CEA Technical
Standard whichever is superior. It may be noted that those specifications &
requirements, which are not explicitly specified herein, CEA Technical Standards
of construction will have precedence. The entire substation should also meet the
requirements of CEIG/other statutory agencies. The works related to tariff metering
and communication systems should be carried out as per CEA /LDC specifications
only.
The CONTRACTOR shall make his own estimate of quantities for all items, systems such
as equipment, power & control cables/cabling system, lighting system, earthing,
lightning protection, auxiliary power distribution, civil works etc. It should be clearly
understood that the contract will be on turnkey basis and no(+) variation will be
allowed for items of works not foreseen or omitted by the CONTRACTOR at the
proposal stage. Meaning that, the contractor shall be responsible for providing all
material, equipment and services specified or otherwise which are required to
fulfil the intent of ensuring operability, maintainability and the reliability of the
complete work. All consumables, wastages and damages shall be in the scope of
contractor. BOQ, Technical Specification and other documents attached elsewhere
shall form the guidelines only for the entire scope of activities.
It is presumed that the contractor already has, or has access to the technical
knowledge/approvals necessary to undertake the design, and has carried out similar
projects for ReNew’s /State Utility/PGCIL. Details with respect to the substation
location, its approach, geography has been provided to the level possible. The
contractor shall make necessary visit to the substation site and should fully appraise
himself before bidding and shall be fully responsible for complete design and
engineering of the substation.
Contractor shall be responsible obtaining the necessary approval from the concerned
statutory agencies on behalf of ReNew Power and payment of necessary fees
thereof.
A) Connection Diagram
B) Schematic diagram:
C) Line Bays & Metering Arrangement at PGCIL’s SS: 220kV Line bays hall be
constructed as per PGCIL specification & requirements.
a.Interface Energy Metering arrangement complete with CT, PT, ABT Meters etc.,
shall be as per latest CEA's metering regulation (latest) & respective Regional
Load Dispatch center requirements.
b. Space provision for Standby metering in 33kV feeder panel
c. The necessary bus bar extension and any augmentation etc. required for the
completion of the scope within the Substation.
• Max conductor loading 30 MW for Panther & 16.8 MW for Dog conductor.
• All conductor shall be Al‐59 type with details as below:
▪ AL59 Panther: TW/353sqmm
▪ AL59 Dog: 19 strands/3.26 mm
G) Unit Substation / DP Yard: DP Pole Structure with Isolator, HG fuse, LA &
other accessories as required.
• All Structures shall be HDG (double dip) with Min. Zn coating thickness as 610
gm/sqm.
• All insulators (even for Isolator, LA etc.); Composite Polymer, CD> 25mm/kV
Important: The above are the broad requirements for establishing eBoP
infrastructure. This needs to be read in conjunction with ReNew’s Minimum
Requirement List and other specifications shared.