Project - RVPN Setting Teco Status To Wbs Element End User Manual - Project System
Project - RVPN Setting Teco Status To Wbs Element End User Manual - Project System
Following are the steps need to be followed for setting up TECO status to WBS Element.
1. Activity confirmation
2. Short closure of Material P.O. and Service P.O.if any.
3. Transfer of Project Stock (MAS) to Storage location.
4. Entering DOC (Date of Commissioning / Completion).
5. Setting TECO status to WBS Element.
Once TECO status is set for WBS Element, we can’t do the following
a. No Purchase Requisition
b. No Purchase Order
c. No Goods Issue against project.
d. No Proejct Physical Progress Entry if any.
1. Activity Confirmation
a. Following steps need to be carried out to Confirman activity in a project.
Activity confirmation shoud be done for Internal Activities only.
Step Action
(1) Enter the T-Code: CJ20N at the command prompt and click on Enter
2016-12-06 1
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
Step Action
(1) Select Network Activity : 8000426 0010 under the WBS Element : CLIN/16.11.01
c.
2016-12-06 2
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
Step Action
By keeping Network Activity : 8000426 0010 in selection mode,
(1)
Go to Edit Activity Confirm
2 3
Step Action
2016-12-06 3
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
e.
Step Action
f.
2
2016-12-06 4
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
Step Action
For setting up TECO status to WBS Element, there should not be any open items in material P.O.
and in service P.O.
This process explains about the short closure of material P.O.’s and service P.O.’s., if any in the
project.
a.
Step Action
2016-12-06 5
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
b.
Step Action
2016-12-06 6
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
c.
Step Action
Enter WBS Element: CLIN/16.11.01 for which the Material P.O. and Service P.O. are
(1)
linked
(2) Enter Selection parameter always as: WE101
2016-12-06 7
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
2
3
Step Action
e.
1
Step Action
2016-12-06 8
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
f. This process explains about setting up delivery completion indicator for Material P.O. and Service
P.O. in the T-Code: ME22N(Change P.O.)
Step Action
2016-12-06 9
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
g.
3
Step Action
2016-12-06 10
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
Step Action
2016-12-06 11
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
i.
Step Action
2016-12-06 12
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
j.
Step Action
2016-12-06 13
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
a. If any materials are at Project Stock(MAS), we need to transfer those materials to the storage
location.
b. To know the Project Stock (MAS)at the WBS Element, we need to do the following process.
Step Action
2016-12-06 14
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
c.
Step Action
2016-12-06 15
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
d.
1 2 3
Step Action
As explained in the above process steps, we come to know the Project Stock (MAS) at the WBS Elements.
e. Following process explains about the transfer of materials from Project Stock(MAS) to Storage
Location using T-Code: MIGO
2016-12-06 16
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
Step Action
f.
1
13
2
3
7 9 8
10
11
12
Step Action
(1) Select A08 Transfer Posting
(2) System automatically select R10 Other
(3) Enter Material Slip Details
(4) Enter Doc. Header Text details
(5) Enter the material number that need to be transferred in From tab
(6) Enter the Plant
(7) Enter the storage location
(8) Enter the storage location in Desttab
(9) Enter “Q” which denotes as project stock
(10) Enter the WBS Element
2016-12-06 17
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
Step Action
(11) Enter the quantity need to be transferred
(12) check in at Item Ok
(13) Click on Post
h.
2016-12-06 18
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
Step Action
a. This process explains about setting Date of Commissioning / Completion for WBS Element.
Step Action
2016-12-06 19
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
Step Action
2016-12-06 20
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
c.
3
Step Action
By keeping WBS Element: CLIN/16.11.01 in selection mode,
(1)
Click on User fields tab
(2) Enter Date at DOC: 01.12.2016
2016-12-06 21
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
Step Action
2016-12-06 22
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
Step Action
c.
2016-12-06 23
Project – RVPN
SETTING TECO STATUS TO WBS ELEMENT
End User Manual – Project System
Step Action
By keeping WBS Element: CLIN/16.11.01 in selection mode,
(1)
Go to Edit Status Complete Technically Set
d.
2
Step Action
(1) System Status TECO has been set to WBS Element: CLIN/16.11.01
2016-12-06 24