NAME OF WORK : PANCHAYAT BHAWAN RENOVATION WORK
WARD NO - 13 PANCHAYAT - SAHASRAM BLOCK - BIRAUL
ITEM NO. DESCRIPTION OF ITEMS WITH DETAILS UNIT QUANTITY RATE AMOUNT
DESMENTLING DOORS WINDOWS AND CLERESTORY WINDOWS
1 (STEEL OR WOOD) SHUTTERS INCLUDING CHOWKHATS,
15.12.2 ARCHITRAGE, HOLDFASTS ETC. COMPLETE AND STACKING
WITHIN 50M LEADS.
MAIN DOOR
2 6.75 3.25 43.88
1 6.75 3.00 20.25
DOOR(BATHROOM )
2 7.00 3.00 42.00
WINDOW
0 5.00 4.00 0.00
106.13 SQM 9.86 208.80 2058.63
DEMOLISHING DRY BRICK PITCHING IN FLOORS, DRAINS ETC.
2
INCLUDING STACKING SERVICEABLE MATERIAL AND
15.24
DISPOSAL OF UNSERVICEABLE MATERIAL WITHIN 50M LEADS
FLOOR (Hall)
1 21.5 15 0.25 80.625
FLOOR (Office Room)
1 15 10.333 0.25 38.74875
FLOOR (VARANDAH)
1 32.67 6.6 0.25 53.91
TOILET
0 5 4 0.25 0.00
173.27925 CUM 4.91 535.60 2628.04
3 DEMOLISING CEMENT CONCRETE(1:4:8) INCLUDING DISPOSAL
15.2.2 OF MATERIAL WITHIN 50M LEAD
Lintel
Over Door 3 5 0.75 0.6 6.75
Over M.
1 6 0.75 0.6 2.7
Door
CHAJJA (ABOVE WINDOW)
0 4 1.5 0.25 0.00
9.45 CUM 0.27 599.80 160.50
DISMENTLING OLD PLASTER OR SKIRTING RAKING OUT JOINTS
4 AND CLEANING THE SURFACES FOR PLASTER INCLUDING
15.56 DISPOSAL OF RUBBISH TO THE DUMPING GROUND WITHIN 50M
LEADS
FLOOR(ROOM,KITCHEN,VARANDA)
HALL 21.5 15 10 730.00
ROOM 15 10.33 10 506.60
VER 32.67 6.6 10 785.40
TOI 0 0 10 0.00
(OUTSIDE WALL)
34.336 24.099 10 1168.70
(FRONT OUTER)
0 28 4 0.00
DEDUCTION
OPENING 1 41.998 4.67 196.13
DOOR 3 6.75 3 60.75
WINDOW 5 3 4 60.00
2873.82
Working area 80% of the quantity 2299.06 SQM 213.59 21.70 4634.89
5
VIDING LOCAL SAND FILLING IN THE ROOM UNDER FLOORING ETC. --- --- --- DO ALL COMP. JOB.
2.28
FLOOR (Hall)
1 21.5 15 1 322.5
FLOOR (Office Room)
1 15 10.333 1 154.995
FLOOR (VARANDAH)
1 32.67 6.6 1 215.62
TOILET
0 5 4 0.25 0.00
693.117 CUM 19.63 287.30 5638.80
6 PROVIDING 100 A BRICK FLAT SOLING FILLING WITH LOCAL
11.72 SAND......ALL COMPL. JOB
FLOOR (Hall)
1 21.5 15 - 322.5
FLOOR (Office Room)
1 15 10.333 - 154.995
FLOOR (VARANDAH)
1 32.67 6.6 - 215.62
Path
1 30 3 - 90.00
783.12 SQM 72.75 283.30 20611.19
PROVIDING AND LAYING IN POSITION CEMENT CONCRETE
7
(1:2:4) OF SPECIFIED GRADE EXCLUDING THE COST OF
4.1.3
CENTRING AND SHUTTERING - ALL WORK UPTO PLINTH LEVEL
FLOOR (Hall)
1 21.5 15 0.25 80.625
FLOOR (Office Room)
1 15 10.333 0.25 38.74875
FLOOR (VARANDAH)
1 32.67 6.6 0.25 53.91
Path
1 30 3 0 0.00
173.28 CUM 4.91 3998.10 19617.56
8.
PROVIDING 15MM THICK CEMENT PLASTER (1:3) WITH 1.5MM
13.12.2
NEAT CEMENT PUNNING IN FLOOR
+13.26
VIDE ITEM 6 693.12 SQM 64.39 216.90 13966.77
PROVIDING AND LAYING PLAIN CEMENT CONCRETE WORK OF
9
SPECIFIED GRADE EXCLUDING THE COST CENTRING
4.1.3
SHUTTERING ALL WORK UP TO PLINTH LEVEL (1:2:4)
Lintel
Over Door 3 5 0.75 0.6 6.75
Over M.
1 6 0.75 0.6 2.7
Door
CHAJJA (ABOVE WINDOW)
0 4 1.5 0.25 0.00
9.45 CUM 0.27 3998.10 1069.87
10 12MM CEMENT PLASTER WITH A FLOATING COAT OF NEAT
13.17.1 CEMENT OF CM 1:3
Toilet
Outside 1 7.26 5 8 196.16
inner 2 3 4 8 224
Deduction 2 3 7- 42
FOR RTPS
COUNTER 4 6.333 4.67 - 118.30
1 5.2 4.67 - 24.28
DEDUCT
DOOR 1 3 7 - 21.00
WINDOW 1 3 4 - 12.00
VIDE ITEM NO. 4 2299.06
Total Area 2786.80 SQM 258.90 203.60 52712.48
11
PROVIDING FINISHING WALL WITH WATER PROOFING CEMENT
13.78.1
PAINT DO--E/I
+13.79.1
CEILING(ROOM,HALL,TOILET,VARANDA)
HALL 1 21.5 15 322.50
ROOM 1 15 10.333 155.00
VER 1 32.67 6.6 215.62
TOILET 2 3 4 24.00
VIDE ITEM NO. 4 & 8 3251.98
3969.10 SQM 368.74 119.80 44175.19
PROVIDING AND FIXING 1 MM THICK M.S. SHEET DOOR WITH
FRAME OF 40X40X6 MM ANGLE IRON AND 3MM MS GUSSET
12
PLATES AT THE JUNCTION AND CORNERS.ALL NECESSARY
10.5.1
FITTINGS COMPLETEJNCLUDING APPLYING A PRIMING COAT
OF APPROVED STEEL PRIMER.
DOOR 3 7 3 63.00
WINDOW 1 4 3 12.00
75.00 SQM 6.97 3653.00 25453.11
PROVIDING AND FIXING PANELLED OR PANELLED AND GLAZED
13
SHUTTERS FOR DOORS, WINDOWSS AND CLERESTORY
9.5.3.1
WINDOWS ETC. - - - DO ALL COMP. JOB.
DOOR 2 6.75 3.25 43.88
1 6.75 3 20.25
64.13 SQM 5.96 2748.50 16373.93
11 M. S. WORK FOR WINDOW FRAME AND GRILL ETC. ----- DO ALL
9.48.1 COMP. JOB.
WINDOW 1 4 3 12
OUTER 0 25 7 0
12.00 SQM 1.11
2
1.11 @ 27 KG/M 30.10 KG 30.10 144.50 4349.53
14 PROVIDING PAINTING WITH READY MIX PAINT ETC. TWO OR
13.82.1 MORE COAT DO---E/I
DOOR 2 6.75 3.25 43.88
1 6.75 3 20.25
3 7 3 63.00
WINDOW 6 4 3 72.00
199.13 SQM 18.50 83.50 1544.69
15
PROVIDING 100A ONE BRICK WORK IN CM (1:4) FOR RTPS
6.1.12/1 +
COUNTER WITH COARSE SAND ETC. ---- DO ALL COMP. JOB.
6.3A
2 6.333 4.67 0.833 49.27
1 5.2 4.67 0.833 20.23
DEDUCT
DOOR 1 3 7 0.833 17.49
WINDOW 1 3 4 0.833 10.00
42.01 CUM 1.19 5860.10 6971.12
16 PROVIDING AND PLACING ON TERRACE POLYTHYLENE WATER
LTR. 500.00 9.70 4850.00
18.48 STORAGE TANK, ISI : 12701 -- -- -- DO ALL COMP. JOB.
PROVIDING AND FIXING CHLORINATED POLYVINYL CHLORIDE
(CPVC) PIPES, HAVING THERMAL STABILITY FOR HOT & COLD
WATER SUPPLY, INCLUDING ALL CPVC PLAIN & BRASS
17
THREADED FITTINGS, UNCLUDING FIXING THE PIPE WITH
18.7.3
CLAMPS AT 1.00 M SPACING. THIS INCLUDES JOINTING OF PIPES
& FITTINGS WITH ONE STEP CPVC SOLVENT CEMENT AND
TESTING OF JOINTS COMPLETE AS PER DIRECTION OF E.I.
25 MM NOMINAL OUTER DIA PIPES 80.00 M 24.39 317.30 7739.02
CONSTRUCTION OF 40MM DIA X 50 M DEEP TUBE WELL WITH
18 SHALLOW HAND PUMP NO.-06 WITH G.I. PIPE UPVC PIPE,UPVC NO. 1.00 30000.00
STRAINER AD INCLUDING P.C.C. PLATFORM
CONSTRUCTING SOAK PIT 1.20 X 1.20 X 1.20 M FILLED WITH
19
VRICKBATS INCLUDING S.W. DRAIN PIPE 100 MM DIA AND 1.20M NO. 1.00 4117.30 4117.30
19.33
LONG COMPLETE AS PER STANDARD DESIGN.
20 CARRIAGE OF MATERIALS
BRICKS NOS 2944 984.95 2899.84
STONE CHIPS CUM 4.7 3186.28 14838.14
COURSE SAND CUM 7.38 2330.04 17195.87
CEMENT MT 6.33 467.40 2956.92
LOCAL SAND CUM 20.74 319.68 6628.78
313192.18
DEDUCT C.P-9.09% 28469.17
284723.01
Add extra cost of brick K 2944 352.05 1036.49
Add extra cost of cement NOS 127 46.70 5930.90
ADD ELECTRIFICATION,MOTOR, FANS, BOARDS, STABILISER
21 65000.00
AND WIRING ETC. AS PER ACTUAL BILL AND VOUCHER
356690.40
21 ADD 1% CONTINGENCIES FOR UNSEEN WORK 3566.90
22 SIGNBOARD & PHOTOGRAPHS 5000.00
TOTAL AMOUNT 365257.30
SAY AMOUNT 365000.00