PT INDO TRANS Document No : 01/ITP/ACT-ITK/22
KONSTRUKSI
INSPECTION TESTING PLAN
ACSET PROJECT : PENSTOCK
INSPECTION AND TEST PLAN
FABRICATION & INSTALLATION
Approval Sheet
Name Title Date Signature
Revision Status
Rev Issue Date Prepared Checked Approved Issue Purpose Owner Signature
0 01 Januari 2022 Issue for Approval
INSPECTION TEST PLAN
PENSTOCK PIPE FABRICATION AND INSTALATION
Doc. No. : 01/ITP/ACST-ITK/22
No Work Activities Reference Document Verified Documents
1 DOCUMENT REVIEW AND APPROVAL
1.1 Shop Drawing AFC Drawing Approval Drawing
1.2 Fabrication Procedure Fabrication Procedure; Fabrication Procedure
Code/Standard
1.3 Hidro Testing Procedure Hidro Testing Procedure Hidro Testing Procedure
1.4 WPS/PQR ASME B31.3 WPS/PQR Register
ASME Sec IX
1.5 Welder Performance Qualification Test ASME B31.3 Welder Certificate Register
ASME Sec IX
1.6 NDT Procedure ASME Section V Approval General Piping NDT
ASME B31.3 Procedure
1.9 Painting Procedure Specification for Protection -
Coatings
1.10 Non Conformance Procedure Non Conformance Procedure Approval Procedure
INSPECTION TEST PLAN
PENSTOCK PIPE FABRICATION AND INSTALATION
Doc. No. : 01/ITP/ACST-ITK/22
No Work Activities Reference Document Verified Documents
2 MATERIAL
2.1 Review Material Certificate Material Certificate Material Certificate Register
2.2 Material Inspection & Verification Material Specification; Material Receiving Report
3 FABRICATION
3.1 Marking and cutting AFC Drawing Cutting Report
3.2 Bending or Forming (if any) AFC Drawing Dimensional Report
ASME B31.3
3.3 Surface Preparation and Fit-Up Approved WPS Welding Report
ASME B31.3
3.4 Check qualified welder / operator Approved WPS Welding Report
ASME Sec. IX
4 VISUAL INSPECTION / DIMENSIONAL CHECK
4.1 Weld visual check Piping Fabrication Visual Report
ASME B31.3
4.2 Temporary Attachment (tack weld) Piping Fabrication Visual Report;
ASME B31.3 NDT Report
4.3 Identification Weld Approved Drawing Traceability Report
ASME B31.3
INSPECTION TEST PLAN
PENSTOCK PIPE FABRICATION AND INSTALATION
Doc. No. : 01/ITP/ACST-ITK/22
No Work Activities Reference Document Verified Documents
5 NDT
5.1 Ultrasonic Test UT Procedure; UT Report
ASME SEC V
5.2 NDT Clearance General Piping NDT Procedure Welding Completion Summary
6 Pressure Testing
6.1 Hydro Testing Hydro Testing Procedure. Piping Completion (MP1)
ASME B31.3
7 PAINTING
7.1 Blasting Specification for Protection Blasting Report
Coatings
7.2 Visual inspection of surface preparation Specification for Protection Painting Report
Coatings
7.3 Dry film thickness check Specification for Protection Painting Report
Coatings Final Paint Completion (AS1)
8 HANDOVER
8.3 Final Inspection prior delivery/ shipment Handover System & Certification IRN
Manual
INSPECTION TEST PLAN PENSTOCK PIPE INSTALAT
Doc. No. : 02/ITP/ACST-ITK/22
No Work Activities Reference Document Verified Documents Acceptance Crite
1 DOCUMENT REVIEW
1.1 Material/Equipment Certificate Standart Spes
Contract
1.2 Installation Procedure Instalation Methode Approved Pro
1.3 Hydro Testing Procedure Piping Pressure Testing Approved Pro
Procedure ASME B 31.3
1.4 Drawings AFC Drawings AFC Drawing
1.5 NDE UT Procedure Procedure UT Standart ASM
2 INSTALLATION PROCESS
2.1 Dimensional Check Erection Drawing Erection Drawi
Installation Procedures Installation Pro
2.2 Welding Joint AFC Drawing AFC Drawing
Welding Standart ASME Sec. VIII
3 COMMISSIONING AND TESTING
3.1 Joint Inspection AFC Drawing Joint Integrity Certificate (JI1) AFC Drawing
3.2 Re – Instatement Joint Integrity Testing Procedure Drawing/Instal
INSPECTION TEST PLAN PENSTOCK PIPE INSTALAT
Doc. No. : 02/ITP/ACST-ITK/22
No Work Activities Reference Document Verified Documents Acceptance Crite
Installation Procedure
4 PAINTING
4.1 Cleaning Power tools (SP – 3) Specification for Protection Specification fo
Coatings Coatings
4.2 Finish Painting Painting Procedure Specification fo
Coatings
5 HANDOVER
6.1 NCR (Non Conformance Report) Non Conformance Procedure NCR NCR Close
6.2 Handover Process Repair Record Document Repair Dosier Approved Repa
Procedure
o : 01/ITP/ACT-ITK/22
PENSTOCK
Signature
Owner Signature
Legend :
ST PLAN M : Monitor P : Perform
ON AND INSTALATION A : Approve R : Review
ST-ITK/22 W : Witness H : Hold Point
Level Inspection Remark
Acceptance Criteria
ITK QA/QC ACSET
Shop Drawing P R/A
Relevant specification P R/A
Hidro Testing Procedure; P R/A
ASME B31.3 Par.345.1
ASME Sec. IX, Art-2 P R/A
ASME B31.3, P.328.2
ASME Sec. IX, Art-3 P R/A
ASME B31.3, P.328.2
ASME B31.3; Table 341.3.2 P R/A
Specification for Protection P R/A
Coatings
Non Conformance Procedure P R/A
Legend :
ST PLAN M : Monitor P : Perform
ON AND INSTALATION A : Approve R : Review
ST-ITK/22 W : Witness H : Hold Point
Level Inspection Remark
Acceptance Criteria
ITK QA/QC ACSET
Data Sheet; P R
Drawing;
ASTM Material.
ASME B31.3 Par-323.1 P W
AFC Drawing, P M
AFC Drawing, P M
ASME B31.3 Par.332.1
Approved WPS; P M
ASME B31.3,Par.328.4
Approved WPS; P M
ASME Sec IX, Artikel-3
ASME B31.3 T.341.3.2 P W
ASME B31.3 T.341.3.2 P W
ASME B31.3 T.341.3.2 P W
Legend :
ST PLAN M : Monitor P : Perform
ON AND INSTALATION A : Approve R : Review
ST-ITK/22 W : Witness H : Hold Point
Level Inspection Remark
Acceptance Criteria
ITK QA/QC ACSET
ASME B31.3, T.341.3.2 P W
General Piping NDT Procedure P R
Piping Pressure Testing P H
Procedure
ASME B31.3 Par.345.4
Specification for Protection P W
Coatings
Specification for Protection P W
Coatings
Specification for Protection P W
Coatings
Complete Testing Report P A
Legend :
TOCK PIPE INSTALATION M : Monitor P : Perform
ST-ITK/22 A : Approve R : Review
W : Witness H : Hold Point
Level Inspection
Acceptance Criteria ITK ACSET OPS
Remark
Standart Spesification As per P R - -
Contract
Approved Procedure P R R R
Approved Procedure P R R R
ASME B 31.3
AFC Drawing P R R R
Standart ASME Sec V P R R R
Erection Drawing P W - -
Installation Procedures
AFC Drawing P W R -
ASME Sec. VIII
AFC Drawing P W W W
Drawing/Installation Procedures P W W W
Legend :
TOCK PIPE INSTALATION M : Monitor P : Perform
ST-ITK/22 A : Approve R : Review
W : Witness H : Hold Point
Level Inspection
Acceptance Criteria ITK ACSET OPS
Remark
Specification for Protection P M R R
Coatings
Specification for Protection P M R R
Coatings
NCR Close P A R R
Approved Repair Dossier P R/A A A