This document provides a job method statement for applying partial hot insulation on piping prior to pressure testing at the Petronas Penapisan facility in Terengganu, Malaysia. It outlines responsibilities for quality management and safety supervision. Reference documents for hot insulation specifications and testing plans are listed. Procedures are described for delivering and storing insulation materials, applying insulation in layers to straight pipes and welded joints, and terminating insulation at valves, flanges, drains, vents, elbows, and tees. Temporary weather protection of insulation is also addressed.

Uploaded by

Raaj Chandran
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
218 views7 pages

JMS - Partial Insulation For Hot Piping - Rev1

This document provides a job method statement for applying partial hot insulation on piping prior to pressure testing at the Petronas Penapisan facility in Terengganu, Malaysia. It outlines responsibilities for quality management and safety supervision. Reference documents for hot insulation specifications and testing plans are listed. Procedures are described for delivering and storing insulation materials, applying insulation in layers to straight pipes and welded joints, and terminating insulation at valves, flanges, drains, vents, elbows, and tees. Temporary weather protection of insulation is also addressed.

Uploaded by

Raaj Chandran
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

BLACK CONDENSATE & HEAT INTEGRATION PROJECT

PETRONAS PENAPISAN (TERENGGANU) SDN BHD

JOB METHOD STATEMENT HSE OFFICE USE

JMS NO:
Contractor KAEFER (M) SDN BHD
ISSUE DATE:
Contract No.
REVISION STATUS:
Contract Title INSULATION WORKS
Document DATE:

No. Rev 00 Date


RISK ASSESSMENT NO:
Task Hot Insulation Application Prior To Pressure Test
JHA NO:
Location

TABLE OF CONTENTS
1.0 PURPOSE.................................................................................................................................1
2.0 RESPONSIBILITIES .................................................................................................................1
3.0 REFERENCE ............................................................................................................................2
4.0 APPLICATION OF HOT INSULATION PARTIAL (EXCLUDING WELD JOINTS) ....................3
5.0 PIPE WORK APPLICATION PARTIAL (EXCLUDING WELD JOINTS) ...................................3

1.0 PURPOSE

The purpose of this Method Statement is to ensure a detailed control of the partial insulation
on hot pipping insulation service as requested by TOYO construction team.

2.0 RESPONSIBILITIES

2.1 The Quality Manager shall be responsible for ensuring the correct applications of this
Method Statement. And the QC Inspector shall be responsible for all the inspection and
testing works, the preparation of documents, and for maintaining all records.

2.2 The Site In charge shall be responsible to the Area Manager for the overall
implementation of this Method Statement. And ensure the safe work site environment
conditions.

2.3 The Supervisor shall be responsible to the Site In-charge for the overall implementation
of this Method Statement. Supervisor shall carry out a toolbox talk

Page 1 of 7
BLACK CONDENSATE & HEAT INTEGRATION PROJECT
PETRONAS PENAPISAN (TERENGGANU) SDN BHD

detailing any safety requirements and pertinent points of the specification relating to the
work to be done.

2.4 The safety supervisor shall be responsible for ensuring the client safety requirements
and ensure the KAEFER employees are complies.

3.0 REFERENCE

Document No. Document Name.


PTS 151301 SPECIFICATION FOR HOT INSULATION
BCHI-000-EXE-TOYO-000-QAC-ITP-0006 ITP FOR HOT INSULATION

3.1 MATERIAL DELIVERY AND STORAGE

3.1.1 Insulation materials shall be preventing from damage and harmful temperature
extremes shall be protected from time of delivery until weather protection is
applied.

3.1.2 Temporary shade shall be used during working hours with the materials being
kept off the ground to prevent damage from drainage rain and condensation.

3.1.3 Keep insulation materials in manufacture bag / box and cover sheet during
transportation and before installation.

3.1.4 Adhesives and sealant which require special storage conditions as


recommended by the manufacturer shall be stored in air-conditionedmrde5

3.1.5 sea containers.

3.1.6 Insulation material from storage shall be applied at the same day and no
unprotected insulation shall remain on the job site overnight.

3.1.7 Temporary weather protection shall be applied to each day’s work. Protected by
polyethylene sheeting wrapped 360 degrees around the insulated pipe or vessel
with overlap in a water shed position where possible.

3.1.8 Insulation which becomes wet due to lack of, or inadequate weather protection
either temporary or permanent, shall be removed and replaced with dry
insulation. Wet insulation shall be discarded and not reused.

Page 2 of 7
BLACK CONDENSATE & HEAT INTEGRATION PROJECT
PETRONAS PENAPISAN (TERENGGANU) SDN BHD

4.0 APPLICATION OF HOT INSULATION PARTIAL (EXCLUDING WELD JOINTS)

4.1 Ensure the item to be insulated is released for insulation has had all the previous works
including touch up painting completed and is in a fit state dry and clean to commence
the insulation work except the welded area.

4.2 It shall be the responsibility of the Supervisor to ensure the materials are applied in the
correct order of layering and all the securements are applied correctly.

4.3 Due to immediate climate changes and sudden rain the insulation team shall always be
prepared and placed the temporary weather protection materials at workplace for immediate
action

4.4 The materials shall be applied in the following order and shall conform to the details
shown on the relevant KAEFER Typical insulation detail drawings and will be monitored
by the Quality Inspectors.

4.5 Refer to Hot insulation specification (PTS 151301).

5.0 PIPE WORK APPLICATION PARTIAL (EXCLUDING WELD JOINTS)

5.1 Pipe Section shall be applied as per the agreed specification.

5.1.1 Insulation application shall be excluding weld joints.

5.1.2 All the insulation termination shall be covered by clear Polyethylene sheeting and
secure with Masking tape at both ends.

5.1.3 All Unit in = mm.

Page 3 of 7
BLACK CONDENSATE & HEAT INTEGRATION PROJECT
PETRONAS PENAPISAN (TERENGGANU) SDN BHD

6.0 STRAIGHT PIPE FIELD WELD TERMINATION.

914

50 50 500 typ 500 typ 50 50


Jacket

Polyethylene sheeting

Masking Tape
7.0 WELDED PIPE SUPPORT

914

50 50 700 typ 50 50
Jacket

100

Polyethylene sheeting

Masking Tape

Page 4 of 7
MELAKA REFINERY DIESEL EURO 5 PROJECT

8.0 ELBOW

50
50 Polyethylene sheeting
450
350 Masking Tape

350 50 50

450

9.0 VALVE AND FLANGE

Bolt Length + 30mm

Permanent End Cap

Jacket

Page 5 of 7 KAE-JMS-005
MELAKA REFINERY DIESEL EURO 5 PROJECT

10.0 DRAIN AND VENT

914

50 50 360 typ 360 typ 50


Jacket

Polyethylene sheeting
Masking Tape

914

50 50 360typ 360 typ 50 50


Jacket

Polyethylene sheeting
Masking Tape

Page 6 of 7 KAE-JMS-005
MELAKA REFINERY DIESEL EURO 5 PROJECT

11.0 TEE

Polyethylene sheeting
Masking Tape
Jacket

50 50 200 typ 200 typ 50

914
If small tee the insulation shall be optimized the
distance for single cladding.

Page 7 of 7 KAE-JMS-005