WORK METHOD STATEMENT
PROJECT NAME – ITC Infotech - Green Center
WORK METHOD STATEMENT FOR POP PUNNING / POP PLASTRING
OBJECTIVE:
The objective of this method statement is to carry out the POP PUNNING /Plastering work
by meeting the technical specification and complying with Standards.
SCOPE:
The scope of this method statement includes POP PUNNING works at ITC Infotech -Green
Center while executing, it in accordance with technical specifications.
REFERENCE:
Manufacturer Specification
BOQ Ref No -5.01
Approved Drawing
TOOLSAND TACKLES
Straight edge, Plumb
Trowel, Aluminium Bottom
Measuring tape (steel),
Thread, plumb bob, right angle,
POP mixing Tray.
Tarpaulin, PVC sheet
Hand gloves
MATERIAL USED:
Approved POP
Water
SAFETY PRECAUTION:
Induction to all the personnel involved by Vendor safety manager.
Issue of a permit by PMC
Use of appropriate PPE.
Barricading if required
Prevention of use of any hazardous material
Appropriate supervision
WORK METHOD STATEMENT
WORK METHOD STATEMENT
PROCEDURE:
Background Preparation
Surfaces should be reasonably dry, clean and protected from the weather, and suitable for
the chosen specification. In addition, before plastering concrete backgrounds, ensure that
any mould oil or other agents present are removed from the surface. No-fines concrete does
not require wetting prior to plastering. Plaster should not be applied onto a ‘green’
background or when any free water is visible. Clean water should be applied 5-10 minutes
before plaster application to control the suction. In-situ or pre-cast concrete which are
exceptionally smooth or having low suction will require pre-treatment with Gyproc Bond-It
bonding agent. Additional projection over the wall to be trimmed off and bull marking to be
before to obtain the thickness level and if thickness is increased by more than 13 mm same
to be plaster with cement & sand before initiating punning with prior approval .
Mixing
POP is mixed with only clean water for preparation. Mixing should be carried out in a clean
tray or bucket. Excessive mechanical mixing should be avoided. Tools and water used in
mixing must be clean. Contamination from previous mixes can shorten the setting time and
in turn reduce the strength of the plaster when set. Water to plaster ratio (1 part of water:
1.25 part of plaster by weight) should be maintained to have good cohesive workable mix.
Prepare plaster mix as much as required depending upon the immediate scope of work.
Once the mix has begun to set, water addition is not recommended, as performance
properties of plaster will get altered, thus affecting workability, cohesiveness, adhesion
properties and strength.
Application
POP should be applied with firm pressure, built out to the required thickness, and ruled to
an even surface and left as an undercoat to form a key for finish coat. A thin plaster mix is
made and applied as a finish coat to provide smooth surface. It can be applied to an average
thickness range of 3-15 mm on walls in one coat and up to 10 mm on ceilings. For punning
S/C plaster surface should be wetted before application to provide firm bonding. After
complete drying for usually 72 hours (depends upon thickness and weather conditions) the
plain smooth levelled surface is ready for painting.
Precautions
Dissimilar expansion and contraction of RCC and brick / stone masonry could cause
stresses and at times separation. To reduce the separation cracks, use of 145 GSM glass fiber
mesh (at the junction) is recommended. • It is not suitable for use in long continuously
damp or severely humid conditions.
WORK METHOD STATEMENT
WORK METHOD STATEMENT
RESPONSIBILITIES.
Construction Manager: He shall be responsible for overall management of
construction activities.
Site Engineer: He shall be responsible for Executing in safe work method as per
Drawings and guide the supervisors and work men.
QA/QC In charge: He shall be responsible for ensuring the quality of work &
materials as per the Specifications and standards.
HSE Manager/Engineer: He shall be responsible for assisting to
engineer/supervisor to ensure the safety of workers during the progress of work.
Safety inductions of each staff and workers shall be done and daily PPE check to be
done and toolbox talk shall be carried out before the start of work. General safety
awareness as well as safety precautions and guidelines for activity to be carried out
in that day shall be discussed.
Stores officer: He shall be responsible for storing of all materials. Also responsible
for maintaining the record of incoming and outgoing and up to date stock details of
materials.
WORK METHOD STATEMENT