0% found this document useful (0 votes)
116 views1 page

Penawaran Harga Pekerjaan

The document is a quotation for construction work containing various line items with quantities, units, unit prices, and totals. It includes items for project management, insurance, site office, security, water, accommodations, electricity, mobilization of equipment, bored piling work down to 600mm diameter including soil boring, slurry stabilization, rebar installation, and concrete pouring. The subtotals for various parts and a grand total are provided along with taxes.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
116 views1 page

Penawaran Harga Pekerjaan

The document is a quotation for construction work containing various line items with quantities, units, unit prices, and totals. It includes items for project management, insurance, site office, security, water, accommodations, electricity, mobilization of equipment, bored piling work down to 600mm diameter including soil boring, slurry stabilization, rebar installation, and concrete pouring. The subtotals for various parts and a grand total are provided along with taxes.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PENAWARAN HARGA PEKERJAAN

No. Item Pekerjaan Qt'y Unit Harga Satuan Jumlah Keterangan


(Rp.) (Rp.)

I PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG

a. Proyek manajemen dan biaya-biaya administrasi


b. Asuransi Tenaga Kerja (Jamsostek)
d. Site Office
20,000,000.00 20,000,000.00
e. Keamanan dan Koordinasi Lingkungan 1.00 ls by Clien
f. Air Kerja (Sumur Kerja)
g. Akomodasi Tenaga Kerja dan test covid
i. Listrik Kerja - -
j. Mobilisasi dan Demobilisasi Aksesoris dan Equipment 1.00 ls 200,000,000.00 200,000,000.00
(Rig bor, excavator, crane services, dan aksesories)

k. Excavator
Sub Total I 220,000,000.00

II JASA PEKERJAAN BORED PILE Dia 600mm

a. Pengeboran Tanah Lunak (NSPT ˂ 40) Bored Pile dia. 600 mm 2,016.00 m' 250,000.00 504,000,000.00
b. Pengeboran Tanah Lunak (NSPT > 40) Bored Pile dia. 600 mm 1.00 m' 1,300,000.00 rate only
e. Stabilisasi Tanah (Slurry) 569.72 m' 55,000.00 31,334,688.00
f. Pembesian Rakit (Include Install dan Handling Besi) 28,486.08 kg 1,000.00 28,486,080.00
g. Install Tremi dan pengecoran Bored Pile 569.72 m3 90,000.00 51,274,944.00
h. Buang Tanah sisa pengeboran 569.72 m3 - by Client
Sub Total I 615,095,712.00
Sub Total I + Sub Total II 835,095,712.00
PPH 3% 25,052,871.36
PPN 11 % 91,860,528.32
Total 901,903,368.96

Diajukam Oleh,
PT. SOLUSI UTAMA GLOBAL

Andy
Direktur Utama