What is Project Management?
A project is an interrelated set of activities
that has a definite starting and ending
dates, and that results in a unique product.
(service)
In other words, a project is a temporary endeavor
undertaken to create a unique product or service.
■ Management is generally perceived
as concerned with planning,
organizing, and control of an
ongoing process or activity.
Additional Definitions
• A project is a unique venture with a
beginning and an end, conducted by
people to meet established goals within
parameters of cost, schedule, and quality.
Buchanan & Boddy 92
• Projects are goal-oriented, involve the
coordinated undertaking of interrelated
activities, are of finite duration, and are all,
to a degree unique.
Frame 95
Characteristics of Project
• A one-time focus
• A specific purpose and a desired result
• A start and a finish
• A time frame for completion
• A limited set of resources
• A logical sequence of interdependent
activities
• A clear user(customer, client) of the result
Elements of Project Planning
Define project objective(s)
Identify activities
Establish precedence relationships
Make time estimates
Determine project completion time
Compare project schedule objectives
Determine resource requirements to meet
objective
The Project Team
■ Project team typically consists of a group of individuals from
various areas in an organization and often includes outside
consultants.
■ Members of engineering staff often assigned to project work.
■ Project team may include workers.
■ Most important member of project team is the project
manager.
■ Project manager is often under great pressure because of
uncertainty inherent in project activities and possibility of
failure. Potential rewards, however, can be substantial.
■ Project manager must be able to coordinate various skills of
team members into a single focused effort.
Project Manager
Responsibilities
• Selecting a team
• Developing project objectives and a plan for
execution
• Performing risk management activities
• Cost estimating and budgeting
• Scheduling
• Managing resources
Steps in Managing a Project
Steps in Managing a Project
Define the problem
Develop solution options
Plan the Project : what must be done ?, who will do it?, How will it be done ?
How much will it cost? ,what do we need to do?
Execute the plan
Monitor & Control Progress
Close Project
What was done well?
What should be improved?
Project Life Cycles
Man Hours
Conceptualization Planning Execution Termination
Project Life Cycle
24-Oct-21 Dr.Bokkasam Sasidhar
Elements of Project Management
Work Breakdown Structure (WBS)
■ WBS breaks a project down into major components (modules).
■ Modules are further broken down into subcomponents,
components, activities, and finally, into individual tasks
(work packages).
■ Identifies activities, tasks, resource requirements and
relationships between modules and activities.
■ Helps avoid duplication of effort.
■ Basis for project development, management , schedule resources
and modifications.
■ Approaches for WBS development:
1. Top Down approach 2. Bottom Up approach
Work Breakdown Structure
24-Oct-21 Dr.Bokkasam Sasidhar
A Work Breakdown Structure (three levels)
for a new business
Elements of Project Management
Work Breakdown Structure
WBS for computerized order-processing system project
Elements of Project Management
Project Scheduling
■ Project schedule evolves from planning documents, with focus
on timely completion.
■ Critical element in project management – source of most
conflicts and problems.
■ Schedule development steps:
1. Define activities, 2. Sequence activities,
3. Estimate activity times, 4. Develop schedule.
■ Gantt chart and CPM/PERT techniques can be useful.
■ Computer software packages available, e.g. QM for Windows,
Microsoft Project.
Elements of Project Management
Gantt Chart
■ Popular, traditional technique, also known as a bar chart -
developed by Henry Gantt (1914).
■ Direct precursor of CPM/PERT for monitoring work progress.
■ A visual display of project schedule showing activity start
and finish times and where extra time is available.
■ Suitable for projects with few activities and precedence
relationships.
■ Drawback: precedence relationships are not always
discernible which limits chart’s use for smaller projects
Gantt Chart
• Visual scheduling tool
• Graphical representation of information
• Show dependencies between tasks,
personnel, and other resources
allocations
• Track progress towards completion
Building a Gantt Chart
• List all tasks and milestones from the
project along the vertical axis
• List time frame along the horizontal axis
Activity 1
Activity 2
Milestone
Time Frame: day 1 day 2 day3
Building a Gantt Chart
• Activities: Create box the length of each activity time
duration
– E.g., activity one is scheduled from day1-day3
Activity 1
Activity 2
Time Frame: day 1 day 2 day3
Building a Gantt Chart
• Dependencies: Show dependencies between
activities with arrows
– E.g., activity 2 cannot start until activity 1 is complete
Activity 1
Activity 2
Time Frame: day 1 day 2 day3…
Sequence of Activities of The Project -
House Building
Number Activity Predecessor Duration
1 Design house and obtain -- 3
financing months
2 Lay foundation 1 2
months
3 Order and receive materials 1 1 month
4 Build house 2,3 3
months
5 Select paint 2, 3 1 month
6 Select carper 5 1 month
7 Finish work 4, 6 1 month
Gantt Chart for House Building Project
A Gantt chart
Gantt Charts
Establish a time-phased network
Can be used as a tracking tool
Benefits of Gantt charts
1. Easy to create and comprehend
2. Identify the schedule baseline network
3. Allow for updating and control
4. Identify resource needs
Gantt Charts – Resource Allocation Example
Use the Gantt chart and the activity list to determine when
resource 5 is free.
Activity Resources Activity Resources
A 1 F 1
B 5 G 2
C 4 H 5
D 3 J 3
E 2 K 4
A) between 0 and 15
B) between 15 and 30
C) between 30 and 45
D) between 45 and 60
Answer: D
Gantt Charts – Resource Allocation Example
Use the Gantt chart and the activity list to determine when
resource 2 is free.
Activity Resources Activity Resources
A 1 F 1
B 5 G 2
C 4 H 5
D 3 J 3
E 2 K 2
A) between 0 and 15
B) between 15 and 30
C) between 30 and 45
D) between 45 and 60
Answer: A
NETWORK ANALYSIS
• It is a technique for planning and controlling
large projects, such as computerization of
systems, R&D projects, etc.
• Its primary aim is to program and monitor the
progress of a project so that the project is
completed in the minimum time.
CPM And PERT
• Network analysis is operated in various
forms under different titles, which include:
• Critical Path Method (CPM) (Deterministic)
• Project Evaluation and Review Technique
(PERT) (Probabilistic)
Drawing the network diagram
• Estimate the time needed to complete each
individual activity or task that makes up a
part of the project
• Sort out what activities must be done one
after another, and which can be done at the
same time, if required
• Represent these in a network diagram
The Project Network - CPM/PERT
Activity on Node (AON) Network
■ A branch reflects an activity of a project.
■ A node represents the beginning and end of activities, referred to as
events.
■ Branches in the network indicate precedence relationships.
■ When an activity is completed at a node, it has been realized.
The Project Network
Concurrent Activities
■ Activities can occur at the same time (concurrently).
■ Network aids in planning and scheduling.
■ Time duration of activities shown on branches.
■ A dummy activity shows a precedence relationship but
reflects no passage of time.
■ Two or more activities cannot share the same start and end
nodes.
Figure: ©Concurrent
Copyright activities
2013 Pearson Educationfor house-building project
The Project Network
House Building Project Data
Number Activity Predecessor Duration
1 Design house and obtain -- 3
financing months
2 Lay foundation 1 2
months
3 Order and receive materials 1 1 month
4 Build house 2,3 3
months
5 Select paint 2, 3 1 month
6 Select carper 5 1 month
7 Finish work 4, 6 1 month
30
The Project Network
House Building Project Data
Path Events
A 1247
B 12567
C 1347
D 13567
The Project Network
The Critical Path
The critical path is the longest path through the network; the
minimum time the network can be completed. From previous Figure:
• Path A: 1 2 4 7 3 + 2 + 3 + 1 = 9 months
• Path B: 1 2 5 6 7 3 + 2 + 1 + 1 + 1= 8 months
• Path C: 1 3 4 7 3 + 1 + 3 + 1 = 8 months
• Path D: 1 3 5 6 7 3 + 1 + 1 + 1 + 1 = 7 months
Slack is the amount of time an activity can be delayed without
delaying the project
Slack Time exists for those activities not on the critical path.
Class Exercise Activity
Draw the AON network for this project.
What is the Critical Path and Project Duration?
Probabilistic Activity Times
■ Activity time estimates usually cannot be made
with certainty.
■ PERT used for probabilistic activity times.
■ In PERT, three time estimates are used: most
likely time (m), the optimistic time (a), and the
pessimistic time (b); using Beta Distribution.
■ These provide an estimate of the mean and
variance of a beta distribution:
2
variance: v b
- a
6
t a 4m b
mean (expected time):
6 34