Construction of A Superadobe Dome: Marco Aurelio López-Gómez M de Las Nieves González-García
Construction of A Superadobe Dome: Marco Aurelio López-Gómez M de Las Nieves González-García
CONSTRUCTION OF A SUPERADOBE
DOME
Marco Aurelio López-Gómez a; Mª de las Nieves González-García b; Nuria Llauradó-Pérez c
Abstract—Superadobe Technology consists on filling long polypropylene sacks with a moist mixture of clay, sand, gravel and
lime/cement; placing and compacting one on top of another forming concentric rings of decreasing radius and describing a double
curvature monolith.
From the 26th of August till the 6th of September of 2017, a group of 10 students at the “Domoterra” Institute of Earthbag
construction, in the province of Teruel, autonomous community of Aragon, Spain, participated in the construction of what would
become a Superadobe domed shelter of internal diameter 4m, roughly 3.5m high with the capacity to enclose 17.5m^2 of habitable
surface, using approximately 250m of polypropylene sack and 20 m³ of earth.
The structure advanced from an initial base cylinder of 0.5 m to the height of 2.1 m in 7 effective work days of 8 hours each day, and
such an experience is taken into account together with existing literature, to describe the construction process of a Superadobe dome.
M.A. López is a PhD student. He studies at Universidad Politécnica de M.N. González & N. Llauradó. Both authors are with Universidad
Madrid, Av. Juan de Herrera, 6, 28040 Madrid, SPAIN (e-mail: Politécnica de Madrid, Av. Juan de Herrera, 6, 28040 Madrid, SPAIN (e-mail:
[email protected]). He completed a master's degree at the Institute of [email protected], [email protected]).
Civil Engineering. Dept. of unique buildings and structures at Peter the Great
Polytechnic University of Saint Petersburg.
countries live in shelters of earth, and the concience for its use The behavior of the building through time depends
is expanding today. fundamentally on the adjustment of the correct proportions of
What folows is a description of how an earth quake-resistant, gravel, sand and clay, of the soil used in its construction.
earthen monolyth: a Superadobe dome of 17 m2 area and more We must first do several field tests at the foundation site and
than 3.5 m of height, can be constructed by a team of 10 at the extraction area, and we must do jar granulometric tests
students with little more than soil, a bunch of hand- tools, good and take mean values, making sure there are no important
will, and good guidance. granulometric variations from the different sources to be used.
A jar granulometric test is done by picking up soil without
THE PROCESS OF CONSTRUCTION OF A SUPERADOBE DOME remnants of organic matter from about 30 cm deep into the
A. materials and preparations ground, and introducing it in a jar of glass of known volume,
better square than cylindrical. Then, mixing its contents with
1) Tools needed
water and leaving it stand 3 days. If we add salt, the process
Among other virtues such as being a social potentiator, one accelerates: about 3 spoonful’s for a normal pot of chickpeas,
of the greatest virtues of Superadobe technology, is its relative for example.
accessibility: although training is necessary, it can be practiced To know the percentage of the granulometry, a ruler is used.
by all peoples given that the techniques are learned, among We measure on one side of the jar, the different lengths of layers
other reasons because hardly any heavy machinery or expensive
of stored earth, (the centimeters of clay, silt, sand, and gravel as
tools are required. The equipment that will be necessary for
they deposit with time and differentiate themselves in such
building a Superadobe dome includes comfortable/ resistant
layers). By doing this, we deduce the proportions in which each
clothes for work, cap, sunglasses, reinforced boots, work
gloves, impermeable gloves, a knife, and an indelible thick particle type is present in the soil of our site in a volumetric
marker: sense.
Besides this basic personal equipment, little more is needed: As we will read below, if we know the percentages (mean
pointed tip shovels, spades, pickaxes, wheelbarrows, and a percentages) of each particle type in our soil, then we can
concrete mixer with a suitable power supply if possible. Also, correct or fix these proportions (by adding specific types of
for the plaster, trowels can work but hawks are ideal. Finally particles to our mixer), in order to make a mixture which is ideal
"rammers" or “stompers”, which are used to strike filled for a Superadobe dome.
polypropylene sacks in order to compact the mixture inside of We look for 30% binding materials (20% clay and 10%
them. Anything heavy but manageable, with a flat striking a binding stabilizer) and 70% sandy soil (35% gravel and
surface will do the job. It may be necessary to make a tool of 35% sand). A rich variety of sandy soil particle sizes is
this type, according to Figure 2. desirable. The ideal binder, reinforcer or stabilizer, is lime.
2) Earth preparation and mixture Lime as a binder and stabilizer for the mixture, allows the
passage of the environmental humidity of a house and the dome
Domes in principle, are made with the sieved earth that is dug
"breathes". The phenomenon is known as breathability. These
to make the foundations, and also with that which accumulates
qualities of lime will eliminate the possibility of condensation
when cleaning the area of construction. This is the “base”
within the Superadobe walls. Lime also has the property of not
construction material; local seived soil. Yet additional soil from
letting rain water pass, hence turning our dome into a Natural
the site should be gathered and sieved, since a medium to big
Goretex.
dome could demand more quantity of earth. (A dome of four
Slaked lime comes from calcinating calcic rock, (its calcium
meters in diameter consumes about 20 m3, or roughly 30 tons
carbonate), CaCO3, and adding water to the resulting calcium
of soil.
oxide CaO, thus becoming Ca(OH)2. This is calcium hydroxide.
It is not recommended that fresh air lime Ca(OH) 2 be used
for construction (just watered live lime), as it is better to use air
lime which has been submerged in water for at least six months,
acquiring better properties for binding and hardening with time.
Hydraulic lime is the same lime but with pzzolans and ashes
that provide a more optimal qualities in low oxygen media and
humidity, which allows an optimal setting for the foundation.
It's much better (and also more expensive).
The reasoning used to prepare (or fix) the soil of our land
for Superadobe construction is as follows:
If we do a jar granulometric test on the soil of our site (or
many, and we take a mean result), and we obtain different mean
volumes, namely Cn, for different particles n, then we would
Fig. 2. Handmade Rammers. like to find what volume of each material n, namely Xn, we must
add to our land in order to obtain desired proportions, namely
𝑃𝑑𝑛 , of each material n, in the resulting mixture.
3 Universidad Politécnica de Madrid
One or two drainage pipes (with wholes performed on the and the dynamics of this cycles (one taking place at the mixer
top to allow the entrance of water, marked in red in Fig 5.) area, and the other at the building area), involves two teams,
should circle the foundation, both of them above sand level (one one team per area, and having ideally three persons each (figure
along the exterior of the trench, the other circling around the 7).
outer edge of the base sack), and given an inclination of 2
degrees (going 3.5cm deep every meter of length, as in diagram
above), respecting the natural terrain inclination as to catch
water accumulation and drive it away.
Geotextile material should insulate the building foundation
from the gravel barrier within the trench as seen in the diagram
above as well, as marked in green in Fig 5.
2) Compasses
As seen in Fig. 6, two compasses must be set for the
construction of a dome. The center compass (see below,
centered at C) must already be set up prior the opening of the
foundation trench, for with the aid of this central compass, the
circle of the trench is drawn on the ground.
after compacted. If it does not, two or three people using the length, wire length and compass length for the new ring
scaffold if needed, can move the bag portion (pull or push in a placement:
synchronized manner) to reposition it further or closer to the After placing a new level / ring / superblock, you must
center. As the sack is being laid, its placement with respect definitely trample at least 3 - 4 times along the stomper, as
to the center compass must be checked continuously so as illustrated in the figure 11 (a person who is ideally strong and
not to have to rectify and lose time. who, as the sack placer, is confident working on heights).
Note: It is important to mention that one of the most
demanding parts of the job carried out at the dome area, is that
of the placement of the sack. As the rings are curved, and this
curvature intensifies with each higher level, a sufficient amount
of mixture must be successfully managed/ driven/ manipulated,
while enough torsion (for the curvature) must be given to the
portion of sack being placed, who’s weight can range from 15-
30 kg, all while trying to maintain equilibrium at a determined
height over the previous ring’s stomped surface (not greater
than 35-40 cm wide).
A final inclination outward of the molds can be achieved height, for a dome of up to 2.4m in radius, must exceed the
through the bricks at their base, as to help the structure with starting line of the curvature (Springline) in 50 cm (Figure 20).
excess rainfall drainage. For example: If after
We must not remove the mold base bricks and the molds until our foundation we
after 2 weeks at least for the mixture to acquire its final strength. build a cylinder wall of
Once the whole arches of doors and windows harden, molds 50 cm, (3 rings or so),
are removed tossing away the bricks. After the whole structure our springline will be at
has been finished, the installation of definitive window and 50 cm above ground
door frames on the structure openings can take place. level. We would in this
Fig. 19. Sewing sacks from different rings case, build the buttress
with barbed wire. together with the first
six rings (the three first
rings of the cylinder base wall plus the three rings that follow,
of 50 – 60 cm high, which come after the initial 50 cm
springline, so the the buttress would total one 1m-1.2m in
height).
A single Superadobe module of radius greater than 2.5 m, is
Fig. 17. Window opening after removal of the mold. Notice the self-
sustainable arch form of the window according to the steps described
above.
Fig. 21. A pair of points of intersection between main dome and apse, where
(The filling of the sack will reduce its nominal width in 7 cm
the rings are sewn together and alternated. - 12 cm).
• Having divided the dome in imaginary quadrants, only one
opening (window or door) can exist on each quadrant, in such
The center of this ideal apse should have to coincide with the way the length of the remaining arch walls have bases of length
outer edge of the base sack of the main dome, and the line (curved) equal or greater than 1.25 m (figure 23).
segment that passes through the outer edge of the base sack of
the apse and the apex (top) of the main dome should form a 45
degree angle with the ground, as in the next figure 22:
Through finite element and other types of structural a mixture of one or several binders (lime is most strongly
analyses, all of these notions and rules should be challenged, recommended), sand, pure water and eventually other additives
and their reasons understood. with thermal or other properties.
7) Additional protection and levels
Description of three recommended plaster layers:
The supports for a small loft can be inserted directly into the
wall above the level of the windows if the height of the dome is • The grout or first coat:
sufficient for a second floor. A suspended stepladder can be Thickness of 1 to 5mm. To be used to "fill" all the slits
made by building the steps directly into the wall as cantilever. between bag and bag: The channels between sack and sack
These can be placed to a depth of 0.3m being held in the wall, provide good support for this first layer. The mixture should be
extending 0.7m into the dome. As the bending moments in the composed of 4 measures of sand for 1 measure of lime. Cut or
stairs could cause problems with plaster stability, it is beneficial crushed straw can be introduced into the mixture to give more
to add further support to these [6]. roughness to this first layer, for the next ones to hold onto better.
Also, regarding water management, supports for awnings can A mortar ball is grabbed with the hand and applied to the
be placed on the wall over the door and windows, extending out dome from bottom to top taking advantage of the cracks
of the dome, and rebar lengths can be placed between rows with between sack and sack. It is important to work in discrete areas
reo - mesh tied on, to provide a base for ferroconcrete gutters of the dome and finish, for example, 1.60m high throughout the
[6]. perimeter of the dome, that is, the first layer must not be applied
8) Waterproofing from the bottom of the dome up to its peak but rather in different
Our Superadobe is very resistant to earthquakes, cold and phases: lower, middle and upper part of the dome.
heat, but It cannot efficiently resist water by itself, as water The plaster may be applied with the trowel but it is very
degrades our mixture and bag resistance. That's why our dome important not to "smooth" this layer, for its gripping surface
is recyclable and if we do not pay attention to the finishing, with should be rough, to facilitate the adhesion of the second layer
the pass of time, water enters and undoes the structure in a few (fig 25). proponemos incorporar esta figura luego de la
years. revisión).
Fabric of goretex type (a membrane for the control of water Hence, the mortar mixture that is used must have medium to
vapor and a 100% barrier to air infiltration) is recommended for thick sand. The optimum sand is quarry sand and has to be
the inner wall of the dome. When installed on the hot face of bought. It is possible to use the sand of the sack mixture or filter
the internal insulation, the rate of heat lost by convection sand from the terrain, previously screening away the fine parts
through the structure of the building decreases, and it offers a and impurities.
barrier to infiltration and air loss from living spaces within the Finally, pressure is applied with the trowel, and a barbed
building. brush or other abrasive tool is passed to generate furrows or
For the exterior, a membrane which should be extremely patterns. We must wait for the plaster to lose water to "tighten",
resistant to water must be included, tight to air and wind and, at between 20 and 30 minutes depending on the weather. Water
the same time, high permeability to water vapor to avoid must be applied in the case of a sunny day. This tightening
condensations inside the walls. In general terms, three layers of phase must be done once the layer acquires certain plasticity but
plaster are recommended and will be described below. has already begun to set (figure 25).
As for thermal insulation, it is a well-known fact that a • The 2nd layer:
Superadobe possesses a high thermal mass, providing high Thickness of 15 to 20 mm. It ensures the waterproofing of
thermal inertia, minimizing the effect of temperature the wall. Should be applied after seven days from setting of the
fluctuations. Thermal insulation is not discussed in this article, previous layer for alternating dry and wet weather.
yet many passive strategies such as window orientation with The wall is moistened previously on the cured last layer, and
respect to the sun, wind tunnels, chimneys, and natural and the second coating applied by projecting with the palette or
synthetic thermal insulation barriers might be used depending throwing plaster balls against the dome.
on the many possible weather patterns on the place where the The proportions are also 4 parts of sand by 1 part of lime.
dome is built. After the projection, a rule is passed over the wall. This layer
must also be “tightened” with the trowel to eliminate the
Plaster general description:
The main additive of a general purpose superadobe plaster possibility of fissure generation. As in the first layer, this
should be lime, as lime adheres well to different supports, is a second one is to be expected to have plastic behavior. Apply
natural and biological product, adapts to construction water if it is necessary to tighten.
movements and prevents the appearance of cracks in the walls. Finally, a toothed brush or a saw is passed to make patterns
Also, during and after setting, lime mortars are permeable to as in the first layer (figure 26) (proponemos incorporar esta
water vapor yet impermeable to water. This way, they favor the figura luego de la revisión).
evaporation of water contained in the walls that breathe.
Lime mortars are easily colored, which is also an aesthetic • The finishing layer:
benefit. The impermeabilization mortar must be constituted by Thickness of 5 to 8 mm. It is used for decoration, also for
protecting the wall and the two preceding layers. It is applied
on the body of the humidified second layer, after a minimum of 10) Conclusions:
4 to 7 days since this second layer was applied (after 15 days if
pure lime is to be used in this third coating, although the Although the following could be regarded as subjective, an
composition for this layer can also be 3 parts of fine sand per 1 important conclusion that I have drawn from the experience of
part of lime). building a Superadobe dome is that the method has the potential
After the projection is done throughout, the rule is passed, to bond the people who participate with one another. Teamwork
then pressure and work is applied to the drying mortar to obtain and good faith was indeed the driving force behind the project:
the finish wanted. This coating finish layer must be regularly as is a tradition in many parts of rural Africa when a public
"tight" with the use of a trowel. building or the house of a member of a village is built or
In the smaller / more delicate areas such as arches of doors repaired, all members of a community work together regardless
and / or windows, a metal spoon can be used to "tighten" the of who’s home is it, or any other difference. This may have to
layer. do with the fact that satisfyng a basic human need with one’s
It is always important to wait for the plaster to lose water to own hands reminds of our fragility in life, as being there for one
be "tightened", between 20 and 30 minutes after initial contact another makes us less fragile indeed.
with the dome depending on the weather conditions.
This last coat is naturally the most artistic of the three phases. Cities are overpopulated, and according to simple
We can customize the dome by drawing on the plaster while is mathematical logic, they will become more overpopulated
still fresh, or placing geometric shapes, stones, mosaics and / or unless we look outside of cities to embody our compulsory
ecological colors (figure 27) (proponemos incorporar esta population growth. At this growth rate, all construction
figura luego de la revisión). companies working at full capacity could not satisfy the world’s
housing demands, so it makes sense to think of a modern world
9) Time and Cost:
where families will able to cover their housing needs for
According to our experience, 40 m of foundation can be dug themselves, and Superadobe is in my opinion, an idoneous
in three 8-hour days (for a straight walled regular adobe method to inspire this model.
structure used for practice). As it was carried out by a team of
10 in this time frame, 40 m of foundation equates to 240 man We can imagine a sustainable model of population growth,
hours. Hence, 0.17 m of foundation equates to one man hour. where state and investors could provide with water, power, road
Similarly, 15 m of sack were laid per day on an average day on and other basic infrastructure in areas outside of cities, and
the domed structure. Since the team size was 10, 15m of sack families themselves, including those with low income, with the
equates to 80 man hours. Hence 0.1875 m of sack equate to one use of earth, could take on the construction of the houses and
man hour. community centers themselves, assuming the costs of labor in
A dome of internal base diameter of 4 m, vertical compass of these spaces. This would dramatically lower project costs, and
4.4 m length, base cylinder wall 0.5m high, sack width of 0.4 m monthly payments to return the initial investment (public or
and sack height of 0.2 m would have a total height of approx. private) would be lower than common mortages of today. In
3.8 m, it would have some 36 m of foundation and roughly 250 such model, it is conceivable that investors will be able to
m of sack, (having approx 20 m³ of earth and weighing 34 tons). achieve high interest rates on their investments in lower times.
It would need at least 1500 man hours of work: roughly 40 days
of work carried out by a team of 5, working 8 hours a day. Methods to safely build with one’s own hands and low
An example budget of approx. $2500 could be allocated on impact materials should exist and be constantly perfected,
other documented projects[6]. The major costs involved should be lagalized, and what’s more: encouraged, through
include: such concerted projects between state, private entities and
Just over 20 cubic meters of sand, about $250 . families, for the result of applying the technique described in
30 cubic meters of building/plastering mix, $750 this article is nothing less than an earthquake resistant house,
10 tons of 20mm aggregate, $250 with comparable functions of that of a counterpart appartment
1000m by 0.41m wide woven polypropylene: UV – built in a conventional place, in a conventional way, costing 40
stabilized, circular woven tube) $600, which is about four times more.
times the length needed for two domes of this size (internal
base diameter of 4 m, vertical compass of 4.4 m length,
sack with of 0.4 m and a total height of building of about
3.5 m. )
Earthworks $300
2 rolls of high tensile barbed wire $130
Recycled windows $85
Materials for compass and tamper construction $100 [6]
Another example of a dome project with a similar costs, carried
out in Port-au-Prince, Haiti, is documented in [8].
13 Universidad Politécnica de Madrid
REFERENCES
[1] Khalili, N. & Vittore, P. (1998). Earth Architecture and
Ceramics, the Sandbag/Superadobe/Superblock
Construction System, Call-Earth Institute. International
Conference of Building Officials, Building Standards,
September-October 1998.
[2] Erbil, Y. (2018). An Alternative Approach to Building
Construction: Natural Building Techniques. European
Journal of Sustainable Development, 7(1), 17-24.
[3] Danso, H. (2018). Identification of Key Indicators for
Sustainable Construction Materials. Advances in Materials
Science and Engineering, 2018, Article ID 6916258, 7
pages. DOI 10.1155/2018/6916258.
[4] Araya-Letelier, G. et al. (2018). Influence of Natural Fiber
Dosage and Length on Adobe Mixes Damage-Mechanical
Behavior. Construction and Building Materials, 174, 645-
655.
[5] M. Ciutad Martín. “Manual de Superadobe”. April 2015.
[6] Wainwright, R. (2018). Building an earthbag dome. TOB,
145, 6-11. www.theownerbuilder.com.au
[7] López, M., González, M.N. & Llauradó, N. (2017).
Equations that describe the geometry of Superadobe domed
structures. 3er. International Conference on Tecnological
Innovation in Building. CITE 2018. Libro de Actas, 227.
[8] Haft, R., Husain, H., Johnson, A. & Price, J. (2010). Green
Building in Haiti.
https://enst.umd.edu/sites/enst.umd.edu/files/_docs/ENST
%20481%20Group%205.pdf