Building /site Permission /approval From Municipality/Nagar Panchayat

This document outlines the process for obtaining a building/site permission approval from a municipality or Nagar Panchayat in Andhra Pradesh. The competent authorities that can provide this approval are the Secretary of Panchayati Raj & Rural Development and the Commissioner of the Municipality. Applicants must submit documents such as ownership documents, land use certificates, tax receipts, structural designs, and affidavits. Once submitted, the application will be processed within 7 days. The fees must be paid online, and upon approval, a building permission proceeding document will be generated.

Uploaded by

omkar maharana
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
237 views2 pages

Building /site Permission /approval From Municipality/Nagar Panchayat

This document outlines the process for obtaining a building/site permission approval from a municipality or Nagar Panchayat in Andhra Pradesh. The competent authorities that can provide this approval are the Secretary of Panchayati Raj & Rural Development and the Commissioner of the Municipality. Applicants must submit documents such as ownership documents, land use certificates, tax receipts, structural designs, and affidavits. Once submitted, the application will be processed within 7 days. The fees must be paid online, and upon approval, a building permission proceeding document will be generated.

Uploaded by

omkar maharana
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Building /Site Permission /Approval from

Municipality/Nagar Panchayat
1 Name of Approval /
NoC/ Licence/ Building /Site Permission /Approval from Municipality/Nagar Panchayat
Registration
2 — Secretary, Panchayati Raj & Rural Development
Competent Authority
— Commissioner, Municipality
3 Applicability Criteria To all investor required land
4 Stage Pre-Establishment

SLA/ Number of Days 7 Days


5
6 (i) Self-Attested copies of Ownership Documents-lease-deed/sale-deed etc. giving
the physical description of the plot/property.
(ii) In case of any deviation from the terms and conditions stipulated in the lease
deed/ownership document, necessary clearance from the Authority.
(iii) Land Use Certificate (as per Perspective/Master/Zonal Plan or any other
statutory plan) issued by the concerned Authority.
(iv) Previous Sanctioned Plan copy with details of approval for the existing building if
any.
(v) An attested copy of Property Tax receipt/Vacant Land Tax receipt/NOC from the
Assessment Department of the concerned local authority.
(vi) If the site/plot falls in approved layout, the copy of the approved layout plan
duly marking the site/plot.
(vii) A declaration cum undertaking and indemnity bond by the
Owner/Builder/Developer/LTP in the prescribed Form (Annexure-3).
(viii) An affidavit/undertaking for handing over road widening portion, if any, shall
be submitted in the prescribed Form.(Annexure-4)
Documents Required (ix) NOC from the Competent Revenue Authority in case the land is declared as
surplus.
(x) NOC from the Revenue Department under the Andhra Pradesh Agricultural Land
(Conversion for Non-Agricultural Purpose) Act, 2006 for the sites falling outside the
Built up area and outside the Approved Layouts.
(xi) NOC from Irrigation Department in case of lands abut Water Bodies, Water
Courses & Nalas with sketch plan with measurements. (Wherever required).
(xii) No Objection Certificate from the Airport Authority of India (wherever
required).
(xiii) Any other information/document, which the Authority may require in case of
listed buildings or otherwise.
(xiv) For Buildings of above 10m height the following details shall be submitted:
(1) Soil Test Report/Geo-technical Investigation Report issued after personal
inspection by Institution/Consultant empanelled with/licensed by the local
authority.
(2) Structural designs and drawings prepared duly taking the soil bearing capacity
into consideration and certified by qualified Structural Engineer/Consultant Firm
empanelled with/licensed by the local authority.
[The Structural Engineer/Consultant Firm is held responsible for defect in the
design].
(3) Building Plan and Application shall be invariably signed by the owner of the
property, builder if any, the Architect and the Structural Engineer who designed the
structure.
(4) If the construction is being taken up by a builder, an attested copy of the
registered agreement entered between the owner of the property and the builder
shall be submitted. In case of any changes in the agreement at a later date, a copy of
the same shall also be submitted to the local authority.
(5) An undertaking on a Stamp Paper of Rs.100/-duly signed by the owner and
builder specifying that no flat or built-up area shall be given possession to the
purchaser/tenant unless they obtain the occupancy certificate from the local
authority and provide all regular service connections.
(6) Contractor/Builders/Developer/Owner shall submit All Risks Insurance Policy for
the construction period.
7 Form Submission https://www.apindustries.gov.in/APIndus/Default.aspx
8 1. The owner/ builder shall submit their proposals through registered professional
(LTPs details available in Web).
2.The details / documents shall entry / upload along with initial Fee in APDPMS Web
Procedure for getting 3. System automatically verifies the statutory provisions and if no query is raised, it
license will generate the details of requisite fees and further documents / undertakings to
be upload if any required.
4. Fee payment through On-line and upload the essential documents / undertakings.
5. Building permission proceedings with plan will generate.
9 Fee & Fee: Rs. 10,000 (Scrutiny fee of building plan) + Development fee and other fees
Mode of Payment which shall be generated after scrutiny and submitting full application.
Mode of Payment: Debit / NetBanking / RTGS etc