Boq of Retaining Wall

This document provides a bill of quantities (BOQ) for construction of a retaining wall for a property called Mustang. It includes 8 items with descriptions, units, rates, quantities, and costs for earthwork excavation, filling, concrete work, stone masonry, gravel packing, piping, and stone pointing. The total cost for the retaining wall project is estimated at 7,952,650.51 Indian rupees.

Uploaded by

avs kfle
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
534 views1 page

Boq of Retaining Wall

This document provides a bill of quantities (BOQ) for construction of a retaining wall for a property called Mustang. It includes 8 items with descriptions, units, rates, quantities, and costs for earthwork excavation, filling, concrete work, stone masonry, gravel packing, piping, and stone pointing. The total cost for the retaining wall project is estimated at 7,952,650.51 Indian rupees.

Uploaded by

avs kfle
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

BOQ for Retaining wall For Mustang

S.N. Description of works Unit Rate Quantity Amount Remarks


Site Clearance including cutting Shrubs 2
1 m 25.13 226.00 5,679.38
removing trees etc all complete
Earthwork excavation in foundation in soft and
2 hard soils including disposal upto 10m lead and m3 900.22 389.36 350,509.66
1.5m lift

Providing and filling earth material laying in 15


3 cm layer, spray water with compaction all m3 548.26 129.79 71,158.67
complete as per instruction of the site incharge

75mm thick PCC work in 1:3:6 including lead


4 m3 16,310.91 7.99 130,324.17
upto 30m
Stone Masonry work in 1:6 C/S mortar all
5 m3 13,161.84 415.17 5,464,401.11
complete
Gravel Packing Works including breaking,
6 carying and laying of gravel/stone inorder to m3 7,196.21 204.46 1,471,337.10
prevent seepage of soil
100 mm Dia. High Density Pipes covered by
7 Rm 136.73 297.90 40,731.87
Geotextile
20mm Thick Stone pointing work with 1:2 C/S
8 m2 439.76 510.60 224,541.46
all complete
Subtotal 7,758,683.42
2.5%
193,967.09
Contigency
Grand Total 7,952,650.51