Project Charter: PMC-108-Providing Water Supplies in Hilly Areas Submitted By-Ashish Dahiya

The project aims to provide water supply in remote hilly areas of Himachal Pradesh from February 2022 to September 2022. It will lay pipelines from water sources to households using a 75HP motor pump, providing clean water access. Key milestones include identifying the pipeline route and required materials in the first 35 days, then laying larger pipes from sources to localities over 3 months followed by smaller pipes to households over the next 4 months. The goals are to deliver clean water at minimal cost and generate revenue through user fees while managing risks from weather and safety issues.

Uploaded by

Harpreet Kaur
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
49 views4 pages

Project Charter: PMC-108-Providing Water Supplies in Hilly Areas Submitted By-Ashish Dahiya

The project aims to provide water supply in remote hilly areas of Himachal Pradesh from February 2022 to September 2022. It will lay pipelines from water sources to households using a 75HP motor pump, providing clean water access. Key milestones include identifying the pipeline route and required materials in the first 35 days, then laying larger pipes from sources to localities over 3 months followed by smaller pipes to households over the next 4 months. The goals are to deliver clean water at minimal cost and generate revenue through user fees while managing risks from weather and safety issues.

Uploaded by

Harpreet Kaur
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Project Charter

PMC-108-Providing water supplies in hilly areas

Submitted by- Ashish Dahiya

Project scope overview- To provide water supply in hilly areas of Himachal Pradesh by
water supply organization of Himachal from the source to households by 75 HP motor
pump.
Estimated Dates- 12 February 2022 to 10 September 2022

Business case-

 To provide the clean water to remote areas


 To provide clean water at doorsteps of house holds
 To generate revenue for the government
 Laying the water pipeline from water source to households by using 75 HP
motor pump

Background-

There is no continuous water supply in the hilly area of Himachal Pradesh. To


remove the scarcity of water in that area government has decided to lay a
pipeline from water source to their household buy laying underground pipes and
to provide 24-hour clean water to the people of that area.
Milestones-

Milestones Time duration


 Identify the areas from where  15 Days
pipeline will pass.
 Identify the amount of raw  10 Days
materials and number of
equipment’s and labour needed.
 Choose the contactor and other  10 Days
supervisors which are needed.
 Start the work of laying the  3 Months
pipelines by digging the holes from
water source to households  2 Months
 Start laying the larger pipes from
source to the locality  1 Month
 Start laying the smaller pipes from
locality to doorstep  1 Month
 Start laying the meter pipes from
doorsteps to houses  1 Month
 Start the supply of water

Success criteria-

 To provide the clean water supply to the remote area at minimal cost and
water should be available 24 hours.
 To generate some revenue for government by charging some amount for
water.
Risks, Assumption and constraints-

Risks Assumptions Constraints


 Climatic conditions  Start the project in  Approval of permits and
licences at specific time
 Approvals right weather
 Work is done in set budget
 Safety (Breaking the conditions to avoid
rocks by use of and risk
explosives which may  Provide regular
cause any accidents) updates and work
 Transportation of done in limited time
material in hilly areas  No disturbance in
 Freezing of pipes in work due to any
winters circumstance

Resources-

 Raw materials
 Equipment’s
 Labours
 Contractors
 Engineers

Stakeholders-

 Government
 Contractors
 Engineers
 Supplier
Team Operating Principles-

 Team should regular update to supervisor and manager.


 Team should work with honesty and team work should be there.

Signature and commitment

Signature and commitment


1) Government employee-
2) Project manager-
3) Contractors-