This document outlines the contract price weightages for different stages of construction of a highway project in India. It assigns percentage weightages to various construction items such as earthwork, culverts, bridges, and road works. The highest percentage weightages are assigned to road works including culverts and widening/repair of culverts (36.68%), minor bridges/underpasses/overpasses (11.58%), and reconstruction and new culverts (11.61%). Payment for items will be made in stages upon completion of work like subgrade, base courses, wearing coat etc.

Uploaded by

YogeshDutt
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
218 views23 pages

Schedule H P2

This document outlines the contract price weightages for different stages of construction of a highway project in India. It assigns percentage weightages to various construction items such as earthwork, culverts, bridges, and road works. The highest percentage weightages are assigned to road works including culverts and widening/repair of culverts (36.68%), minor bridges/underpasses/overpasses (11.58%), and reconstruction and new culverts (11.61%). Payment for items will be made in stages upon completion of work like subgrade, base courses, wearing coat etc.

Uploaded by

YogeshDutt
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 23

National Highways Authority of India Request for Proposal – Bid Document

SCHEDULE-H
(See Clauses 10.1.4 and 19.3)

CONTRACT PRICE WEIGHTAGES

1.1 The Contract Price for this Agreement is Rs (…………….)

1.2 Proportions of the Contract Price for different stages of Construction of the
Project Highway shall be as specified below:

Weightage
Percentage
Item in % of Stage for Payment
weightage
CP

1 2 3 4

A- Widening and strengthening of existing


road
(1) Earthwork up to top of the sub-grade [**]

(2) Earthwork in Shoulders [**]

(3) Sub-base Course [**]

(4) Non-bituminous Base course [**]

(5) Bituminous Base course [**]


(6) Wearing Coat [**]

(7) Widening and repair of culverts [**]

Road Works including B.1- Reconstruction/New 8-Lane


Culverts, widening 36.68% Realignment / Bypass (Flexible Pavement)
and repair of culverts (1) Earthwork up to top of the sub-grade +
28.83%
Site Clearance

(2) Earthwork in Shoulders 2.25%

(3) Sub-base Course 14.26%

(4) Non-bituminous Base course 10.18%

(5) Bituminous Base course 16.58%

(6) Wearing Coat 10.39%

B.2- Reconstruction/New 8-Lane


Realignment / Bypass (Rigid Pavement)
(1) Earthwork up to top of the sub-grade [**]

(2) Earthwork in Shoulders [**]

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-1
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Weightage
Percentage
Item in % of Stage for Payment
weightage
CP

1 2 3 4
(3) Sub-base Course [**]
(4) Dry Lean Concrete (DLC) Course [**]

(5) Pavement Quality Control (PQC) Course [**]

C.1- Reconstruction/ New Service Road/


Slip Road (Flexible Pavement)
(1) Earthwork up to top of the sub-grade 0.24%

(2) Earthwork in Shoulders 0.03%


(3) Sub-base Course 0.59%

(4) Non-bituminous Base course 0.76%

(5) Bituminous Base course 1.31%

(6) Wearing Coat 0.75%

C.2- Reconstruction/New Service road


(Rigid Pavement)
(1) Earthwork up to top of the sub-grade [**]
(2) Sub-base Course [**]

(3) Dry Lean Concrete (DLC) Course [**]

(4) Pavement Quality Control (PQC) Course [**]

D- Reconstruction & New Culverts on


existing road, realignments, bypasses
Culverts (length < 6m) 11.61%

Additional Culverts 2.22%

A.1- Widening and repairs of Minor


Bridges (length>6m & <60m)

Minor Minor Bridges [**]


bridge/Underpasses/ A.2- New Minor bridges (length >6 m and
11.58% < 60 m)
Overpasses
(1) Foundation: On completion of the
foundation work including foundations
2.09%
for wing and return walls, abutments,
piers.

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-2
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Weightage
Percentage
Item in % of Stage for Payment
weightage
CP

1 2 3 4
(2) Sub-structure: On completion of
abutments, piers upto the abutment/ pier 7.58%
cap including wing/ return wall upto top

(3) Super-structure: On completion of the


super-structure in all respects including 12.80%
Girder, Deck slab, bearings.

(4) Approaches: On completion of


approaches including Retaining walls,
stone pitching, protection works complete 7.33%
in all respect, tests on completion in all
respect and fit for use.

(5) Guide Bunds and River Training Works:


On completion of Guide Bunds and river 0.00%
training works complete in all respects
(6) Other Ancillary Works: On completion of
wearing coat, expansion joints, hand rails,
1.83%
crash barriers, road signs & markings,
tests on completion in all respect.

B.1- Widening and repairs of


underpasses/overpasses
Underpasses/ Overpasses [**]

B.2- New Underpasses/Overpasses


(1) Foundation: On completion of the
foundation work including foundations
3.07%
for wing and return walls, abutments,
piers.

(2) Sub-structure: On completion of


abutments, piers upto the abutment/ pier 28.74%
cap including wing/ return wall upto top.

(3) Super-structure: On completion of the


super-structure in all respects including 7.78%
Girder, Deck slab, bearings.

(4) On completion of Retaining/ Reinforced


earth walls complete in all respect and fit 20.23%
for use.

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-3
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Weightage
Percentage
Item in % of Stage for Payment
weightage
CP

1 2 3 4
(5) Approaches and Other Ancillary Works:
On completion of wearing coat, expansion
joints, hand rails, crash barriers, stone
pitching, protection works, road signs &
markings, tests on completion in all
respect.
8.54%
Wearing Coat (a) in case of Overpass-
wearing coat including expansion joints
complete in all respects as specified and
(b) in case of underpass-rigid pavement
including drainage facility complete in all
respects as specified

A.1- Widening and repairs of Major


Bridges
(1) Foundation: On completion of the
foundation work including foundations [**]
for return walls, abutments, piers.

(2) Sub-structure: On completion of


abutments, piers upto the abutment/ pier [**]
cap upto top.

Major (3) Super-structure: On completion of the


bridge(length>60m) super-structure in all respects including [**]
works and Girder, Deck slab, bearings.
ROB/RUB/elevated
sections/flyovers 21.73% (4) Wearing Coat including expansion joints [**]
including viaducts, if
(5) Miscellaneous Items like hand rails, crash
any [**]
barrier, road markings etc.
(6) Wing walls/return walls upto top [**]

(7) Guide bunds, River Training works etc. [**]

(8) Approaches (including Retaining walls,


[**]
stone pitching and protection works)

A.2- New Major Bridges


(1) Foundation: On completion of the
foundation work including foundations 2.98%
for return walls, abutments, piers.

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-4
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Weightage
Percentage
Item in % of Stage for Payment
weightage
CP

1 2 3 4
(2) Sub-structure: On completion of
abutments, piers upto the abutment/ pier 4.23%
cap.

(3) Super-structure: On completion of the


super-structure in all respects including 18.98%
Girder, Deck slab, bearings

(4) Wearing Coat including expansion joints 1.55%

(5) Miscellaneous Items like hand rails, crash


1.00 %
barrier, road markings etc.

(6) Wing walls/return walls upto top 0.00%

(7) Guide bunds, River Training works etc. 0.00%

(8) Approaches (including Retaining walls,


2.43%
stone pitching and protection works)

B.1- Widening and repairs of


(a) ROB
(b) RUB
(1) Foundations [**]

(2) Sub-Structure [**]


(3) Super-Structure (Including bearings) [**]

(4) Wearing Coat (a) in case of ROB-


wearing coat including expansion joints
complete in all respects as specified and
[**]
(b) in case of RUB-rigid pavement under
RUB including drainage facility complete
in all respects as specified

(5) Miscellaneous Items like hand rails, crash


[**]
barrier, road markings etc.

(6) Wing walls/Return walls [**]

(7) Retaining/ Reinforced earth walls [**]

(8) Approaches and Other Ancillary Works


(Approaches, stone pitching, protection [**]
works, etc.)

B.2- New ROB/RUB


(1) Foundations 4.41%

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-5
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Weightage
Percentage
Item in % of Stage for Payment
weightage
CP

1 2 3 4
(2) Sub-Structure 6.48%
(3) Super-Structure (Including bearings) 34.76%

(4) Wearing Coat (a) in case of ROB-


wearing coat including expansion joints
complete in all respects as specified and
1.49%
(b) in case of RUB-rigid pavement under
RUB including drainage facility complete
in all respects as specified
(5) Miscellaneous Items like hand rails, crash 2.01%
barrier, road markings etc.
(6) Wing walls/Return walls 0.15%

(7) Retaining/ Reinforced earth walls 0.18%

(8) Approaches and Other Ancillary Works


(Approaches, stone pitching, protection 0.72%
works, etc.)
C.1- Widening and repair of Elevated
Section/Flyovers/Grade Separators
(1) Foundations [**]

(2) Sub-Structure [**]

(3) Super-Structure (Including bearings) [**]


(4) Wearing Coat including expansion joints [**]

(5) Miscellaneous Items like hand rails, crash


[**]
barrier, road markings etc.

(6) Wing walls/Return walls [**]

(7) Retaining/ Reinforced earth walls [**]

(8) Approaches and Other Ancillary Works


(Approaches, stone pitching, protection [**]
works, etc.)
C.2- New Elevated Section/Flyovers/Grade
Separators
(1) Foundation: On completion of the
foundation work including foundations
1.84%
for wing and return walls, abutments,
piers.

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-6
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Weightage
Percentage
Item in % of Stage for Payment
weightage
CP

1 2 3 4
(2) Sub-structure: On completion of
abutments, piers upto the abutment/ pier 3.33%
cap upto top.

(3) Super-structure: On completion of the


super-structure in all respects including
11.27%
Girder, Deck slab, bearings, tests on
completion in all respect

(4) Wearing Coat including expansion joints 0.64%


(5) Miscellaneous Items like hand rails, crash
1.00 %
barrier, road markings etc.

(6) Wing walls/Return walls 0.12%

(7) Retaining/ Reinforced earth walls 0.21%

(8) Approaches and Other Ancillary Works


(Approaches, stone pitching, protection 0.24%
works, etc.)

(i) Toll Plaza 1.99%

(ii) Road side drains 0.00%


Lined Drain 1.14%

Unlined Drain 0.13%

(iii) Road signs, safety Devices, Road


0.53%
Furnitures etc.

(iv) Road markings & Studs 0.03%

Other Works (v) Crash Barrier 21.08%


26.51%
(vi) Project facilities 0.00%

a) Bus Bays 0.00%


b) Wayside Amenities excluding Slip
Roads & but including all internal
0.56%
roads (Service areas including Truck
Lay-Byes)

c) Others 0.30%

(vii) Rain Water Harvesting 0.33%

(viii) Protection Works

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-7
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Weightage
Percentage
Item in % of Stage for Payment
weightage
CP

1 2 3 4
Retaining Wall/Toe wall/Gravity Wall 27.24%
(ix) RE Wall 4.77%

(x) Street Lighting 0.41%

(xi) Utility Ducts 0.00%

(xii) ATMS 3.94%

(xiii) Road side Plantation including


1.92%
Horticulture in Wayside Amenities
(xiv) Protection Works other than approaches
to the bridges, elevated sections/ flyover/ 3.46%
grade separators and ROBs/ RUBs
(xv) Boundary wall 24.60%

(xvi) Safety & Traffic Management during


1.08%
const.

(xvii) Other miscellaneous works including


Connecting road & Junction under 6.48%
Grade separator

(i) EHT line 66.47%

(ii) EHT crossings 0.00%


(iii) HT/LT line 12.73%
Electrical utilities and
public Health Utilities (iv) HT /LT crossings 20.80%
3.80%
(Water pipe lines and (v) Water pipeline 0.00%
sewage lines)
(vi) Water pipeline crossings. 0.00%

(vii) Sewage lines 0.00%

(viii) Sewage line Crossings. 0.00%

1.3 Procedure of estimating the value of work done.

1.3.1 Road works

Procedure for estimating the value of road work done shall be as follows:

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-8
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Table 1.3.1

Percentage
Stage of Payment Payment Procedure
weightage
A- Widening & Strengthening of road
[**]
(1) Earthwork up to top of the sub-grade

(2) Earthwork in Shoulders [**] Unit of measurement is linear length.


Payment of each stage shall be made
(3) Sub-base Course [**] on pro rata basis on completion of a
stage in a length of not less than 10
(4) Non-bituminous Base course [**] (ten) percent of the total length.

(5) Bituminous Base course [**]

(6) Wearing Coat [**]

Cost of ten completed culverts shall be


determined on pro rata basis with respect
(7) Widening and repair of culverts [**] to the total number of culverts. Payment
shall be made on the completion of at
least five culverts.
B.1- Reconstruction/New 8-Lane Realignment /
Bypass (Flexible Pavement)
(1) Earthwork up to top of the sub-grade
28.83%
+ Site Clearance
Unit of measurement is linear length.
(2) Earthwork in Shoulders 2.25%
Payment of each stage shall be made on
(3) Sub-base Course (CTSB) 14.26% pro rata basis on completion of a stage
in full length or 5(five) km length,
(4) Non-bituminous Base course (WMM) 10.18% whichever is less.

(5) Bituminous Base course 16.58%

(6) Wearing Coat 10.39%

B.2- Reconstruction/New 8-Lane Realignment /


Bypass (Rigid Pavement)

(1) Earthwork up to top of the sub-grade [**]


Unit of measurement is linear length.
(2) Earthwork in Shoulders [**] Payment of each stage shall be made on
pro rata basis on completion of a stage
(3) Sub-base Course [**] in full length or 5(five) km length,
whichever is less.
(4) Dry Lean Concrete (DLC) Course [**]

(5) Pavement Quality Control (PQC)


[**]
Course

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-9
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Percentage
Stage of Payment Payment Procedure
weightage
C.1- Reconstruction/ New Service Road/ Slip Road
(Flexible Pavement)

(1) Earthwork up to top of the sub-grade 0.24%

(2) Earthwork in Shoulders 0.03% Unit of measurement is linear length.


Payment of each stage shall be made on
(3) Sub-base Course (GSB) 0.59% pro rata basis on completion of a stage
in full length or 5(five) km length,
(4) Non-bituminous Base course (WMM) 0.76% whichever is less.

(5) Bituminous Base course 1.31%

(6) Wearing Coat 0.75%

C.2- Reconstruction/New Service road (Rigid


Pavement)

(1) Earthwork up to top of the sub-grade [**] Unit of measurement is linear length.
Payment of each stage shall be made on
(2) Sub-base Course [**] pro rata basis on completion of a stage
in full length or 5(five) km length,
(3) Dry Lean Concrete (DLC) Course [**] whichever is less.
(4) Pavement Quality Concrete (PQC)
[**]
Course

D- Reconstruction & New Culverts on existing road,


realignments, bypasses Cost of each culverts shall be determined
on pro rata basis with respect to the total
Culverts (length <6m) 11.61% number of culverts. Payment shall be
made on the completion of at least five
Additional Culverts 2.22% culverts

@ For calculation of payment stage for main-carriageway the project length shall be converted
into equivalent 2 lane length. For example, if the total length of 4 lane main carriageway is
100 km, then the equivalent length for calculation of payment stage will be 2 x 100 km.
Now, if the total length of bituminous work to be done is 100 km, the cost per km of
bituminous work shall be determined as follows:

Cost per km = P x weightage for road work x weightage for bituminous work x (1/L)

Where P = Contract Price

L = Total equivalent 2-Lane length in km as defined above

Similarly, the rates per km for other stages shall be worked out accordingly.

Note: The length affected due to law and order problems or litigation during execution
including the length not handed over to the Contractor under clause 8.3 of this Contract
Agreement due to which the Contractor is unable to execute the work, may be deducted from
Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-10
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

the total project length for payment purposes. The total length calculated here is only for
payment purposes and will not affect and referred in other clauses of the Contract
Agreement

1.3.2 Minor Bridges and Underpasses/Overpasses

Procedure for estimating the value of Minor bridge and Underpasses/Overpasses shall be as
stated in table 1.3.2:

Table 1.3.2

Stage of Payment Weightage Payment Procedure


1 2 3
A.1- Widening and repairs of Minor Cost of each minor bridge shall be determined
Bridges (length>6m & <60m) on pro rata basis with respect to the total linear
[**] length of the minor bridges. Payment shall be
made on the completion of widening & repair
works of a minor bridge
A.2- New Minor Bridges (length>6m & Foundation: Cost of each minor bridge shall
<60m) be determined on pro- rata basis with respect to
the total linear length (m) of the minor bridges.
Payment against foundation shall be made on
(1) Foundation: On completion of the pro-rata basis on completion of a stage i.e. not
foundation work including 2.09%
less than 25% of the scope of foundation of
foundations for wing and return each bridge.
walls, abutments, piers.
In case where load testing is required for
foundation, the trigger of first payment shall
include load testing also where specified.

Sub-structure: Cost of each minor bridge


shall be determined on pro- rata basis with
(2) Sub-structure: On completion of
respect to the total linear length (m) of the
abutments, piers upto the abutment/
7.58% minor bridges. Payment against sub-structure
pier cap including wing/ return upto
top shall be made on pro-rata basis on completion
of a stage i.e. not less than 25% of the scope of
sub-structure of each bridge.

Super-structure: Payment shall be made on


pro-rata basis on completion of a stage i.e.
completion of super structure of atleast one
(3) Super-structure: On completion of span in all respects as specified in the column
the super-structure in all respects 12.80% of "Stage of Payment" in this sub-clause. In
including Girder, Deck slab, bearings case of structures where pre-cast girders have
been proposed by the Contractor, 50% of the
stage payment shall be due and payable on
casting of girders for each span and balance
50% of the stage payment shall be made on
Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-11
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Stage of Payment Weightage Payment Procedure


1 2 3
completion of stage specified as above

(4) Approaches: On completion of Approaches: Payment shall be made on pro-


approaches including Retaining rata basis on completion of a stage i.e.
walls, stone pitching, protection 7.33% completion of approaches in all respect as
works complete in all respect and fit specified in the column of "Stage of Payment"
for use in this sub-clause.
Guide Bunds and River Training Works:
(5) Guide Bunds and River Training
Works: On completion of Guide Payment shall be made on pro-rata basis on
0.00% completion of a stage i.e. completion of Guide
Bunds and river training works
complete in all respects Bunds and River training Works in all respects
as specified
(6) Other Ancillary Works: On Other Ancillary Works: Payment shall be
completion of wearing coat, made on pro-rata basis on completion of a stage
expansion joints, hand rails, crash 1.83% in all respects as specified
barriers, road signs & markings, tests
on completion in all respect.

B.1- Widening and repairs of Cost of each underpass/overpass shall be


underpasses/ overpasses determined on pro rata basis with respect to the
[**] total linear length of the underpasses/
overpasses. Payment shall be made on the
completion of widening & repair works of a
underpass/overpass.
B.2- New Underpasses/Overpasses
Foundation: Cost of each Underpass/ Overpass
shall be determined on pro- rata basis with
Foundation: On completion of the
respect to the total linear length (m) of the
foundation work including foundations for
Underpasses/Overpasses.
wing and return walls, abutments, piers.
3.07% Payment against foundation shall be made on
pro-rata basis on completion of a stage i.e. not
less than 25% of the scope of foundation of
each Underpasses/ Overpasses.
In case where load testing is required for
foundation, the trigger of first payment shall
include load testing also where specified.

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-12
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Stage of Payment Weightage Payment Procedure


1 2 3
(2) Sub-structure: On completion of Sub-structure: Cost of each Underpass/
abutments, piers upto the abutment/ pier Overpass shall be determined on pro- rata basis
cap including wing/ return/ wall upto top with respect to the total linear length (m) of the
Underpasses/ Overpasses. Payment against sub-
28.74%
structure shall be made on pro-rata basis on
completion of a stage i.e. not less than 25% of
the scope of sub-structure of each
Underpasses/Overpasses.

Super-structure: Payment shall be made on pro-


rata basis on completion of a stage i.e.
completion of super-structure of atleast one
span in all respects as specified in the column of
(3) Super-structure: On completion of the "Stage of Payment" in this sub-clause. In case of
super-structure in all respects including 7.78% structures where pre-cast girders have been
Girder, Deck slab, bearings proposed by the Contractor, 50% of the stage
payment shall be due and payable on casting of
girders for each span and balance 50% of the
stage payment shall be made on completion of
stage specified as above

(4) On completion of Retaining / Payments shall be made on pro rata basis on


Reinforced earth walls complete in all 20.23% completion of 20% of the total area.
respect and fit for use

(5) Approaches and Other Ancillary Payment shall be made on pro-rata basis on
Works: On completion of wearing coat, completion of a stage in all respects as specified
expansion joints, hand rails, crash barriers,
8.54%
road signs & markings, stone pitching,
protection works, tests on completion in
all respect.

1.3.3 Major Bridge works, ROB/RUB and Structures

Procedure for estimating the value of Major Bridge works, ROB/RUB and Structures Work shall be
as stated in table 1.3.3:
Table 1.3.3

Stage of Payment Weightage Payment Procedure

A.1- Widening and repairs of


Major Bridges
Foundation: Cost of each Major Bridge shall be
determined on pro rata basis with respect to the total
linear length (m) of the Major Bridge. Payment
Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-13
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Stage of Payment Weightage Payment Procedure

Foundation: On completion of against foundation shall be made on pro-rata basis


the foundation work including on completion of a stage i.e. not less than 25% of
[**]
foundations for wing and return the scope of foundation of the major Bridge.
walls, abutments, piers.
In case where load testing is required for foundation,
the trigger of first payment shall include load testing
also where specified.
Sub-structure: Payment against sub-structure shall
be made on pro-rata basis on completion of a stage
Sub-structure: On completion of i.e. not less than 25% of the scope of sub-structure
abutments, piers upto the [**] of major bridge.
abutment/ pier cap upto top.

Super-structure: Payment shall be made on pro-rata


basis on completion of a stage i.e. completion of
Super-structure: On completion super-structure including bearings of atleast one
of the super-structure in all span in all respects as specified. In case of structures
respects including Girder, Deck [**] where pre-cast girders have been proposed by the
slab, bearings, tests on Contractor, 50% of the stage payment shall be due
completion in all respect and payable on casting of girders for each span and
balance 50% of the stage payment shall be made on
completion of stage specified as above

Wearing Coat: Payment shall be made on


Wearing Coat including completion of wearing coat including expansion
[**]
expansion joints joints complete in all respects as specified.

Miscellaneous: Payments shall be made on


Miscellaneous Items like hand
completion of all miscellaneous works like hand
rails, crash barrier, road [**]
rails, crash barriers, road markings etc. complete in
markings etc.
all respects as specified.
Wing walls/return walls: Payments shall be made on
Wing walls/return walls [**] completion of all wing walls/return walls complete
in all respects as specified.

Guide bunds, River Training Guide Bunds, River Training works: Payments
works etc. shall be made on completion of all guide bunds/river
[**]
training works etc. complete in all respects as
specified.

Approaches (including Approaches: Payments shall be made on pro rata


Retaining walls, stone pitching [**] basis on completion of 10% of the scope of each
and protection works) stage.

A.2- New Major Bridges

2.98% Foundation: Cost of each Major Bridge shall be


determined on pro rata basis with respect to the total
Foundation: On completion of
linear length (m) of the Major Bridge. Payment
the foundation work including
Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-14
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Stage of Payment Weightage Payment Procedure

foundations for wing and return against foundation shall be made on pro-rata basis
walls, abutments, piers. on completion of a stage i.e. not less than 25% of
the scope of foundation of the major Bridge.
In case where load testing is required for foundation,
the trigger of first payment shall include load testing
also where specified.
Sub-structure: Payment against sub-structure shall
Sub-structure: On completion of
be made on pro-rata basis on completion of a stage
abutments, piers upto the 4.23%
i.e. not less than 25% of the scope of sub-structure
abutment/ pier cap upto top
of major bridge.

Super-structure: Payment shall be made on pro-rata


basis on completion of a stage i.e. completion of
Super-structure: On completion super-structure including bearings of atleast one
of the super-structure in all span in all respects as specified. In case of structures
respects including Girder, Deck 18.98% where pre-cast girders have been proposed by the
slab, bearings, tests on Contractor, 50% of the stage payment shall be due
completion in all respect and payable on casting of girders for each span and
balance 50% of the stage payment shall be made on
completion of stage specified as above

Wearing Coat: Payment shall be made on


Wearing Coat including
1.55% completion of wearing coat including expansion
expansion joints
joints complete in all respects as specified.

Miscellaneous: Payments shall be made on


Miscellaneous Items like hand
completion of all miscellaneous works like hand
rails, crash barrier, road 1.00 %
rails, crash barriers, road markings etc. complete in
markings etc.
all respects as specified.

Wing walls/return walls: Payments shall be made on


Wing walls/return walls upto
0.00% completion of all wing walls/return walls complete
top
in all respects as specified.

Guide bunds, River Training Guide Bunds, River Training works: Payments
works etc. shall be made on completion of all guide bunds/river
0.00%
training works etc. complete in all respects as
specified.

Approaches (including Approaches: Payments shall be made on pro rata


Retaining walls, stone pitching 2.43% basis on completion of 10% of the scope of each
and protection works) stage.

B.1- Widening and repairs of


(a) ROB
Foundation: Cost of each ROB/RUB shall be
(b) RUB
determined on pro rata basis with respect to the total
linear length (m) of the ROB/RUB. Payment against
foundation shall be made on pro-rata basis on
Foundation

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-15
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Stage of Payment Weightage Payment Procedure

[**] completion of a stage i.e. not less than 25% of the


scope of foundation of the ROB/RUB.
In case where load testing is required for foundation,
the trigger of first payment shall include load testing
also where specified.

Sub-structure: Payment against sub-structure shall


be made on pro-rata basis on completion of a stage
Sub-structure [**]
i.e. not less than 25% of the scope of sub-structure
of ROB/RUB.

Super-structure: Payment shall be made on pro-rata


basis on completion of a stage i.e. completion of
super-structure including bearings of atleast one
span in all respects as specified. In case of structures
Super-structure (including
[**] where pre-cast girders have been proposed by the
bearing)
Contractor, 50% of the stage payment shall be due
and payable on casting of girders for each span and
balance 50% of the stage payment shall be made on
completion of stage specified as above

Wearing Coat: Payment shall be made on


completion
Wearing Coat including
(a) in case of ROB- wearing coat including
expansion joints in case of
expansion joints complete in all respects as specified
ROB. In case of RUB-rigid [**]
and
pavement under RUB including
drainage facility as specified (b) in case of RUB-rigid pavement under RUB
including drainage facility complete in all respects
as specified.

Miscellaneous: Payments shall be made on


Miscellaneous Items like hand
completion of all miscellaneous works like hand
rails, crash barrier, road [**]
rails, crash barriers, road markings etc. complete in
markings etc.
all respects as specified.

Wing walls/return walls: Payments shall be made on


Wing walls/return walls [**] completion of all wing walls/return walls complete
in all respects as specified.

On completion of Retaining/ Payments shall be made on pro rata basis on


Reinforced earth walls complete [**] completion of 20% of the total area.
in all respect and fit for use.

Approaches and Other Ancillary Payment shall be made on pro-rata basis on


Works: On completion of completion of a stage in all respects as specified
approaches, stone pitching, [**]
protection works, tests on
completion in all respect.

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-16
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Stage of Payment Weightage Payment Procedure

B.2- New ROB/ RUB


Foundation: Cost of each ROB/RUB shall be
determined on pro rata basis with respect to the total
Foundation
linear length (m) of the ROB/RUB. Payment against
foundation shall be made on pro-rata basis on
4.41%
completion of a stage i.e. not less than 25% of the
scope of foundation of the ROB/RUB.
In case where load testing is required for foundation,
the trigger of first payment shall include load testing
also where specified.

Sub-structure: Payment against sub-structure shall


be made on pro-rata basis on completion of a stage
Sub-structure 6.48%
i.e. not less than 25% of the scope of sub-structure
of ROB/RUB.

Super-structure: Payment shall be made on pro-rata


basis on completion of a stage i.e. completion of
super-structure including bearings of atleast one
span in all respects as specified. In case of structures
Super-structure (including
34.76% where pre-cast girders have been proposed by the
bearing)
Contractor, 50% of the stage payment shall be due
and payable on casting of girders for each span and
balance 50% of the stage payment shall be made on
completion of stage specified as above

Wearing Coat: Payment shall be made on


completion
Wearing Coat including
(a) in case of ROB- wearing coat including
expansion joints in case of
expansion joints complete in all respects as specified
ROB. In case of RUB-rigid 1.49%
and
pavement under RUB including
drainage facility as specified (b) in case of RUB-rigid pavement under RUB
including drainage facility complete in all respects
as specified.

Miscellaneous: Payments shall be made on


Miscellaneous Items like hand
completion of all miscellaneous works like hand
rails, crash barrier, road 2.01%
rails, crash barriers, road markings etc. complete in
markings etc.
all respects as specified.

Wing walls/return walls: Payments shall be made on


Wing walls/return walls 0.15% completion of all wing walls/return walls complete
in all respects as specified.

Payments shall be made on pro rata basis on


On completion of Retaining/ completion of 20% of the total area.
Reinforced earth walls complete 0.18%
in all respect and fit for use.

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-17
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Stage of Payment Weightage Payment Procedure

Approaches and Other Ancillary Payment shall be made on pro-rata basis on


Works: On completion of completion of a stage in all respects as specified
approaches, stone pitching, 0.72%
protection works, tests on
completion in all respect.

C.1- Widening and repairs of


Elevated Section/ Flyovers/
Foundation: Cost of each structure shall be
Grade Separators
determined on pro rata basis with respect to the total
linear length (m) of the structure. Payment against
Foundation foundation shall be made on pro-rata basis on
completion of a stage i.e. not less than 25% of the
[**] scope of foundation of the structure.
In case where load testing is required for foundation,
the trigger of first payment shall include load testing
also where specified.

Sub-structure: Payment against sub-structure shall


be made on pro-rata basis on completion of a stage
Sub-structure [**]
i.e. not less than 25% of the scope of sub-structure
of structure.

Super-structure: Payment shall be made on pro-rata


basis on completion of a stage i.e. completion of
Super-structure: On completion super-structure including bearings of atleast one
of the super-structure in all span in all respects as specified. In case of structures
respects including Girder, Deck [**] where pre-cast girders have been proposed by the
slab, bearings, tests on Contractor, 50% of the stage payment shall be due
completion in all respect and payable on casting of girders for each span and
balance 50% of the stage payment shall be made on
completion of stage specified as above

Wearing Coat: Payment shall be made on


Wearing Coat including
[**] completion of wearing coat including expansion
expansion joints
joints complete in all respects as specified.

Miscellaneous: Payments shall be made on


Miscellaneous Items like hand
completion of all miscellaneous works like hand
rails, crash barrier, road [**]
rails, crash barriers, road markings etc. complete in
markings etc.
all respects as specified.

Wing walls/return walls: Payments shall be made on


Wing walls/return walls [**] completion of all wing walls/return walls complete
in all respects as specified.

Payments shall be made on pro rata basis on


On completion of Retaining/ completion of 20% of the total area.
Reinforced earth walls complete [**]
in all respect and fit for use.

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-18
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Stage of Payment Weightage Payment Procedure

Payment shall be made on pro-rata basis on


Approaches and Other Ancillary completion of a stage in all respects as specified
Works: On completion of
approaches, stone pitching, [**]
protection works, tests on
completion in all respect.

C.2- New Elevated Section/


Flyovers/ Grade Separators
Foundation: Cost of each structure shall be
determined on pro rata basis with respect to the total
linear length (m) of the structure. Payment against
foundation shall be made on pro-rata basis on
Foundation: On completion of 1.84%
completion of a stage i.e. not less than 25% of the
the foundation work including
scope of foundation of the structure.
foundations for wing and return
walls, abutments, piers. In case where load testing is required for foundation,
the trigger of first payment shall include load testing
also where specified.

Sub-structure: Payment against sub-structure shall


Sub-structure: On completion of
be made on pro-rata basis on completion of a stage
abutments, piers upto the 3.33%
i.e. not less than 25% of the scope of sub-structure
abutment/ pier cap upto top.
of structure.

Super-structure: Payment shall be made on pro-rata


basis on completion of a stage i.e. completion of
Super-structure: On completion super-structure including bearings of atleast one
of the super-structure in all span in all respects as specified. In case of structures
respects including Girder, Deck 11.27% where pre-cast girders have been proposed by the
slab, bearings, tests on Contractor, 50% of the stage payment shall be due
completion in all respect and payable on casting of girders for each span and
balance 50% of the stage payment shall be made on
completion of stage specified as above

Wearing Coat: Payment shall be made on


Wearing Coat including
0.64% completion of wearing coat including expansion
expansion joints
joints complete in all respects as specified.

Miscellaneous: Payments shall be made on


Miscellaneous Items like hand
completion of all miscellaneous works like hand
rails, crash barrier, road 1.00 %
rails, crash barriers, road markings etc. complete in
markings etc.
all respects as specified.

Wing walls/return walls: Payments shall be made on


Wing walls/return walls 0.12% completion of all wing walls/return walls complete
in all respects as specified.

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-19
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Stage of Payment Weightage Payment Procedure

On completion of Retaining/ Payments shall be made on pro rata basis on


Reinforced earth walls complete 0.21% completion of 20% of the total area.
in all respect and fit for use.

Approaches and Other Ancillary Payment shall be made on pro-rata basis on


Works: On completion of completion of a stage in all respects as specified
approaches, stone pitching, 0.24%
protection works, tests on
completion in all respect.

1.3.4 Other Works.


Procedure for estimating the value of other works done shall be as stated in table 1.3.4:
Table 1.3.4
Stage of Payment Weightage Payment Procedure

(i) Toll Plaza Unit of measurement is each


completed toll plaza. Payment of each
1.99% toll plaza shall be made on pro rata
basis with respect to the total of all toll
plaza.
(ii) Road side drains

Lined Drain 1.14%

Unlined Drain 0.13% Unit of measurement is linear length


in km. Payment shall be made on pro
(iii) Road signs, safety Devices, Road rata basis on completion of a stage in
0.53% a length of not less than 10% (ten per
Furnitures etc.
cent) of the total length.
(iv) Road markings & Studs 0.03%

(v) Crash Barrier 21.08%

(vi) Project facilities 0.00%

a) Bus Bays 0.00%

b) Wayside Amenities excluding Slip


Roads & but including all internal Payment shall be made on pro rata
0.56%
roads (Service areas including Truck basis for completed facilities.
Lay-Byes)

c) Others 0.30%

(vii) Rain Water Harvesting 0.33%

(viii) Protection Works Payments shall be made on pro rata

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-20
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Stage of Payment Weightage Payment Procedure

Retaining Wall 27.24% basis on completion of 20% of the total


area.
(ix) RE Wall 4.77%

(x) Street Lighting 0.41%

(xi) Utility Ducts 0.00%

(xii) ATMS 3.94% Unit of measurement is linear length.


Payment shall be made on pro rata
(xiii) Road side Plantation including basis on completion of a stage in a
1.92%
Horticulture in Wayside Amenities length of not less than 10% (ten per
cent) of the total length.
(xiv) Protection Works other than
approaches to the bridges, elevated
3.46%
sections/ flyover/ grade separators and
ROBs/ RUBs

(xv) Boundary wall Unit of measurement is linear length.


Payment shall be made on pro rata basis
24.60% on completion of a stage in a length of
not less than 10% (ten per cent) of the
total length.
(xvi) Safety & Traffic Management during Payment shall be made on
1.08%
const. prorate basis every six months.
(xvii) Other miscellaneous works including
Connecting road & Junction under 6.48% Payment shall be made on pro rata
Grade separator. basis on completion of each stage.

1.3.5 Utility Shifting

Stage of Payment Weightage Payment Procedure


1 2 3
(i) EHT Line Unit of measurement is as per completed
activities. Cost per activity shall be
determined on pro-rata basis as per its
weightage with reference to total cost of
EHT line. Payment shall be made for
completed activity. (The average
66.47% weightage of major activities (only for
payment purpose) in shifting work is (i)
Erection of Poles-20%, (ii) Conductor
stringing including laying of cable-30%,
(iii) DTR erection (if involved)-15% and
(iv) Charging of line including
dismantling and site clearance-35% (with
DTR) and 50% without DTR)

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-21
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Stage of Payment Weightage Payment Procedure


1 2 3
(ii) EHT Crossings
Cost of each crossing shall be
determined on pro-rata basis with
0.00% reference to total no. of crossings.
Payment shall be made for not less than
25% of the crossings subject to a
minimum of 4 crossings.

Unit of measurement is as per completed


activities. Cost per activity shall be
determined on pro-rata basis as per its
weightage with reference to total cost of
LT/HT line. Payment shall be made for
completed activity. (The average
(iii) HT/LT line (including Transformers 12.73% weightage of major activities (only for
if any) payment purpose) in shifting work is (i)
Erection of Poles-20%, (ii) Conductor
stringing including laying of cable-30%,
(iii) DTR erection (if involved)·10% and
(iv) Charging of line including
dismantling and site clearance-40% (with
DTR) and 50% without DTR)
Cost of each crossing shall be determined
on pro-rate basis with reference to total
(iv) HT/LT crossings 20.80% no. of crossings. Payment shall be made
for not less than 25% of the crossings
subject to a minimum of 10 crossings.
Unit of measurement is as per completed
activities. Cost per activity shall be
determined on pro-rata basis as per its
weightage with reference to total cost of
pipe line. Payment shall be made for
(v) Water pipeline 0.00% completed activity. (The average
weightage of major activities (only for
payment purpose) in shifting work is
laying of pipe-50%, Charging of line
including all miscellaneous works and
dismantling and site clearance- 50%)
Cost of each crossing shall be determined
on pro-rata basis with reference to total
(vi) Water pipeline crossings 0.00% no. of crossings. Payment shall be made
for not less than 25% of the crossings
subject to a minimum of 8 crossings.

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-22
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.

`
National Highways Authority of India Request for Proposal – Bid Document

Stage of Payment Weightage Payment Procedure


1 2 3
Unit of measurement is as per completed
activities. Cost per activity shall be
determined on pro-rata basis as per its
weightage with reference to total cost of
pipe line. Payment shall be made for
(vii) Sewage lines 0.00% completed activity. (The average
weightage of major activities (only for
payment purpose) in shifting work is
laying of pipe-50%, Charging of line
including all miscellaneous works and
dismantling and site clearance- 50%)
(viii) Sewage line crossings Cost of each crossing shall be determined
on pro-rata basis with reference to total
no. of crossings.
Payment shall be made for completed
0.00% activity. (The average weightage of major
activities in shifting work is laying pipe-
50%, Charging of line including all
miscellaneous works and dismantling and
site clearance-50%)

2. Procedure for payment for Maintenance

2.1 The cost for maintenance shall be as stated in Clause 14.1.1.

2.2. Payment for Maintenance shall be made in quarterly installments in accordance with the
provisions of Clause 19.7.

Construction of Six lane access controlled Highway from Km 40+080 to Km 86+513 Page H-23
( Mator to Barodameo Section of Paniyala-Barodameo ICR) in the State of Rajasthan on EPC Mode
under Bharatmala Pariyojana.