Summary of Budget For Storage Tank & Base Foundation (09.06.2022)
Summary of Budget For Storage Tank & Base Foundation (09.06.2022)
New Storage tank No-127 Volume 3000 m3(Dia-19 m,Height-12.6 m).Reference previous storage tank pile design
Service Charges for pile of Tank 127 (Dia 19m, Height 12.6m)
New Storage tank No-129 Volume 1200 m3(Dia-11.8 m,Height-12.6 m).Reference previous storage tank pile design
New Storage tank No-135 Volume-2000 m3(Dia-15.2 m,Height-12.6 m).Reference previous storage tank pile design
New Storage tank No-139 Volume-1450 m3(Dia-13 m,Height-12.6 m).Reference previous storage tank pile design
Total Pile Unit Price
Sl No. Pile Dia(Inch) Pile Length(Rft). Pile No Total Amount (Tk.) Remarks
Length(Rft) (Tk.)/Rft
1 Pile boring (Dia-20") 44.00 60.00 2,640.00 150.00 396,000.00
Amount (Tk.) 396,000.00
New Reformer Unit-2 .Total Area=19215 Sft .Reference Previous Chemex plant Design(Cast in Situ Pile)
Service Charges for pile of Tank 127 (Dia 19m, Height 12.6m)
Pile Unit
Total
Sl No. Pile Dia(Inch) Length(R Pile Unit Price
Qty.
ft). (Tk.)
Pile boring (Dia-20") 89.00 3,916.00 Rft 150.00
Amount (Tk.)
Bill of Materials for pile Tank -127 (Dia 19m, Height 12.6m)
Unit
Work Extra Total
Sl No. Materials Name Unit Price
Qty. 5% Qty. Qty.
(Tk.)
1 Cement 1,958.00 97.90 2,055.90 bag 465.00
Stone chips 3/4"
2 7,387.00 369.35 7,756.35 cft 250.00
downgraded
3 1st class bricks 2,000.00 100.00 2,100.00 pcs. 10.20
4 Ms rod dia 16 mm 12,015.00 600.75 12,615.75 kg 88.00
5 Ms rod dia 8 mm 4,600.00 230.00 4,830.00 kg 88.00
6 Sylhet sand 1,869.00 93.45 1,962.45 cft 95.00
7 Local sand 1,869.00 93.45 1,962.45 cft 28.00
Amount (Tk.)
Total amount of Bill of Material & Service Charges
B) Total Amount for Tank 127 & Tank 128
New Storage tank No-130 Volume 1200 m3(Dia-11.8 m,Height-12.6 m).Reference previous storag
Unit
Work Extra Total
Sl No. Work Description Unit Price
Qty. 5% Qty. Qty.
(Tk.)
1 Pile boring (Dia-20") 55.00 0.00 2,420.00 Rft 150.00
Amount (Tk.)
Bill of Materials for pile Tank-129 (Dia-11.8 m, Height-12.6 m)
Unit
Work Extra Total
Sl No. Materials Name Unit Price
Qty. 5% Qty. Qty.
(Tk.)
1 Cement 1,210.00 60.50 1,270.50 bag 465.00
Stone chips 3/4" 250.00
2 4,549.05 227.45 4,776.50 cft
downgraded
3 1st class bricks 2,000.00 100.00 2,100.00 pcs. 10.20
4 Ms rod dia 16 mm 7,286.40 364.32 7,650.72 kg 88.00
6 Ms rod dia 8 mm 3,000.00 150.00 3,150.00 kg 88.00
7 Sylhet sand 1,155.00 57.75 1,212.75 cft 95.00
8 Local sand 1,155.00 57.75 1,212.75 cft 28.00
Amount (Tk.)
Total amount of Bill of Material & Service Charges
C) Total Amount for Tank 129, Tank 130
New Storage tank No-135 Volume-2000 m3(Dia-15.2 m,Height-12.6 m).Reference previous storag
Unit
Work Extra Total
Sl No. Work Description Unit Price
Qty. 5% Qty. Qty.
(Tk.)
1 Pile boring (Dia-20") 75.00 0.00 3,300.00 Rft 150.00
Amount (Tk.)
Bill of Materials for pile Tank -135 (Dia-15.2 m, Height-12.6 m)
Unit
Work Extra Total
Sl No. Materials Name Unit Price
Qty. 5% Qty. Qty.
(Tk.)
1 Cement 1,650.00 82.50 1,732.50 bag 465.00
Stone chips 3/4"
2 6,203.25 310.16 6,513.41 cft 250.00
downgraded
3 1st class bricks 2,000.00 100.00 2,100.00 pcs. 10.20
4 Ms rod d 16 mm 9,936.00 496.80 10,432.80 kg 88.00
5 Ms rod d 8 mm 3,650.00 182.50 3,832.50 kg 88.00
6 Sylhet sand 1,575.00 78.75 1,653.75 cft 95.00
7 Local sand 1,575.00 78.75 1,653.75 cft 28.00
Amount (Tk.)
Total amount of Bill of Material & Service Charges
D) Total Amount for Tank 135, Tank 136, Tank 137, Tank 138
New Storage tank No-139 Volume-1450 m3(Dia-13 m,Height-12.6 m).Reference previous storage
Unit
Work Extra Total
Sl No. Work Description Unit Price
Qty. 5% Qty. Qty.
(Tk.)
1 Pile boring (Dia-20") 60.00 0.00 2,640.00 Rft 150.00
Amount (Tk.)
Unit
Work Extra Total
Sl No. Work Description Unit Price
Qty. 5% Qty. Qty.
(Tk.)
1 Pile boring (Dia-24") 273 0 12085 Rft 170.00
Amount (Tk.)
Bill of Materials for Tank 133 (Dia-26 m,Height-16.2 m)
Unit
Work Extra Total
Sl No. Materials Name Unit Price
Qty. 5% Qty. Qty.
(Tk.)
1 Cement 9,009.00 450.45 9,459.45 bag 465.00
Stone chips 3/4"
33,306.00 1,665.30 34,971.30 cft 250.00
2 downgraded
3 1st class bricks 2,800.00 140.00 2,940.00 pcs. 10.20
4 Ms rod dia 20 mm 66,885.00 3,344.25 70,229.25 kg 88.00
5 Ms rod dia 12 mm 5,460.00 273.00 5,733.00 kg 88.00
6 Ms rod dia 10 mm 32,760.00 1,638.00 34,398.00 kg 88.00
7 Sylhet sand 16,926.00 846.30 17,772.30 cft 95.00
8 Local sand 100.00 5.00 105.00 cft 28.00
9 Bentonite Powder 3,750.00 0.00 3,750.00 kg 25.00
Amount (Tk.)
Total amount of Bill of Material & Service Charges
F) Total Amount for Tank 133
``
New Storage tank No-134 no Volume-7600 m3(Dia-26 m,Height-16.2 m).Consultant d
Unit
Work Extra Total
Sl No. Work Description Unit Price
Qty. 5% Qty. Qty.
(Tk.)
1 Pile boring (Dia-24") 283 0 12523 Rft 170.00
Amount (Tk.)
Bill of Materials for Tank 134 (Dia-26 m,Height-16.2 m)
Unit
Work Extra Total
Sl No. Materials Name Unit Price
Qty. 5% Qty. Qty.
(Tk.)
1 Cement 9,339.00 466.95 9,805.95 bag 465.00
Stone chips 3/4"
34,526.00 1,726.30 36,252.30 cft 250.00
2 downgraded
3 1st class bricks 2,800.00 140.00 2,940.00 pcs. 10.20
4 Ms rod dia 20 mm 69,335.00 3,466.75 72,801.75 kg 88.00
5 Ms rod dia 12 mm 5,660.00 283.00 5,943.00 kg 88.00
6 Ms rod dia 10 mm 33,960.00 1,698.00 35,658.00 kg 88.00
7 Sylhet sand 17,546.00 877.30 18,423.30 cft 95.00
8 Local sand 100.00 5.00 105.00 cft 28.00
9 Bentonite Powder 3,750.00 0.00 3,750.00 kg 25.00
Amount (Tk.)
Total amount of Bill of Material & Service Charges
G) Total Amount for Tank 134
New Reformer Unit-2 .Total Area=19215 Sft .Reference Previous Chemex plant Design(Cast
Unit
Work Extra Total
Sl No. Work Description Unit Price
Qty. 5% Qty. Qty.
(Tk.)
1 Pile boring (Dia-20") 110 0 4840 Rft 150.00
Amount (Tk.)
Bill of Materials for New Reformer unit-2 pile work
Unit
Work Extra Total
Sl No. Materials Name Unit Price
Qty. 5% Qty. Qty.
(Tk.)
1 Cement 2,420.00 121.00 2,541.00 bag 465.00
Stone chips 3/4"
9,098.10 454.91 9,553.01 cft 250.00
2 downgraded
3 1st class bricks 2,800.00 140.00 2,940.00 pcs. 10.20
4 Ms rod dia 16 mm 14,850.00 742.50 15,592.50 kg 88.00
5 Ms rod dia 12 mm 300.00 15.00 315.00 kg 88.00
6 Ms rod dia 10 mm 8,910.00 445.50 9,355.50 kg 88.00
7 Sylhet sand 2,310.00 115.50 2,425.50 cft 95.00
8 Local sand 2,410.00 120.50 2,530.50 cft 28.00
Amount (Tk.)
Total amount of Bill of Material & Service Charges
G) Total Amount for Reformer Unit-2
reformer unit-2(Pile work)
imited.
,chattogram
.Reference previous storage tank pile design
Total Amount
Remarks
(Tk.)
587,400.00
587,400.00
ght 12.6m)
Total Amount
Remarks
(Tk.)
955,993.50
1,939,087.50
An additional 5
21,420.00 percent has been
added for site
1,110,186.00 conditioning and
425,040.00 miscellaneous waste
186,432.75
54,948.60
4,693,108.35
5,280,508.35
10,561,016.70
Total Amount
Remarks
(Tk.)
363,000.00
363,000.00
8 m, Height-12.6 m)
Total Amount
Remarks
(Tk.)
590,782.50
1,194,125.63
An additional 5
percent has been
added for site
conditioning and
miscellaneous waste
An additional 5
21,420.00 percent has been
added for site
673,263.36
conditioning and
277,200.00 miscellaneous waste
115,211.25
33,957.00
2,905,959.74
3,268,959.74
6,537,919.47
Total Amount
Remarks
(Tk.)
495,000.00
495,000.00
.2 m, Height-12.6 m)
Total Amount
Remarks
(Tk.)
805,612.50
1,628,353.13
An additional 5
21,420.00 percent has been
added for site
918,086.40 conditioning and
337,260.00 miscellaneous waste
157,106.25
46,305.00
3,914,143.28
4,409,143.28
17,636,573.10
Total Amount
Remarks
(Tk.)
396,000.00
396,000.00
m, Height-12.6 m)
Total Amount
Remarks
(Tk.)
644490.00
An additional 5
percent has been
added for site
conditioning and
1302682.50 An additional 5
21420.00 percent has been
added for site
734469.12 conditioning and
286440.00 miscellaneous waste
125685.00
37044.00
3,152,230.62
3,548,230.62
10,644,691.86
Total Amount
Remarks
(Tk.)
2054450.00
2,054,450.00
m,Height-16.2 m)
Total Amount
Remarks
(Tk.)
4,398,644.25
8,742,825.00 An additional 5
percent has been
29,988.00 added for site
6,180,174.00 conditioning and
miscellaneous waste
504,504.00
3,027,024.00
1,688,368.50
2,940.00
93,750.00
24,668,217.75
26,722,667.75
26,722,667.75
Total Amount
Remarks
(Tk.)
2128910.00
2,128,910.00
m,Height-16.2 m)
Total Amount
Remarks
(Tk.)
4,559,766.75
9,063,075.00
An additional 5
29,988.00 percent has been
6,406,554.00 added for site
522,984.00 conditioning and
miscellaneous waste
3,137,904.00
1,750,213.50
2,940.00
93,750.00
25,567,175.25
27,696,085.25
27,696,085.25
Total Amount
Remarks
(Tk.)
726000.00
726,000.00
nit-2 pile work
Total Amount
Remarks
(Tk.)
1,181,565.00
2,388,251.25
An additional 5
29,988.00 percent has been
1,372,140.00 added for site
27,720.00 conditioning and
miscellaneous waste
823,284.00
230,422.50
70,854.00
6,124,224.75
6,850,224.75
6,850,224.75
Super Petrochemical limited. Dangarchar,charlakshya,karnaphuli,chattogram
Final Budget O f New Storage tank No of Pile Estimating & costing
F) Service Charges for all new Storage Tanks piling work
Tank No Tank Volume-m3 Foundation volume Materials Cost Construction Cost Unit Price/m3 Amount G.Total Amount Remarks
Thickness-m m3
T-133 7600 1.5 839 16,539,577.00 2,666,565.00 22,891.71 19,206,142.00
37,830,188.00 Consultant Design
T-134 7600 1.5 839 15,769,164.00 2,854,882.00 22,197.91 18,624,046.00
T-127 3000 0.375 153 3,089,025.00 542,146.00 23,733.14 3,631,171.00
7,262,342.00
T-128 3000 0.375 153 3,089,025.00 542,146.00 23,733.14 3,631,171.00
T-129 1200 0.375 72 1,883,119.00 266,642.00 29,857.79 2,149,761.00
4,299,522.00
T-130 1200 0.375 72 1,883,119.00 266,642.00 29,857.79 2,149,761.00
T-135 2000 0.375 114 3,608,352.00 407,388.00 35,225.79 4,015,740.00
Existing Tank
T-136 2000 0.375 114 3,608,352.00 407,388.00 35,225.79 4,015,740.00
16,062,960.00 Design Reference
T-137 2000 0.375 114 3,608,352.00 407,388.00 35,225.79 4,015,740.00
T-138 2000 0.375 114 3,608,352.00 407,388.00 35,225.79 4,015,740.00
T-139 1450 0.375 85 2,055,307.00 458,335.00 29,572.26 2,513,642.00
T-140 1450 0.375 85 2,055,307.00 458,335.00 29,572.26 2,513,642.00 7,540,926.00
T-141 1450 0.375 85 2,055,307.00 458,335.00 29,572.26 2,513,642.00
72,995,938.00
#REF!
Budget Summary of Civil work for Tank Work
Tank No Total Materials Cost Construction Cost Total Amount Grand Total Grand Total(Similar
Tank)
Unit Price
Sl No. Work Description Work Qty. Total Qty. Unit
(Tk.)
1 Earth excavation 2,500.00 2,625.00 cft 8.00
2 BFS Work 1,650.00 1,732.50 cft 5.00
3 Rcc work 2,541.00 2,668.05 cft 75.00
4 Pile Head breaking 140.00 147.00 Rft 155.00
5 Back filling 1,500.00 1,575.00 cft 6.00
Amount (Tk.)
Materials for Tank No -130 (Dia-11.8 m, Height-12.6 m)
Unit Price
Sl No. Materials Name Work Qty. Total Qty. Unit
(Tk.)
1 Cement 599.00 628.95 bag 465.00
Stone chips 3/4" 250.00
2 3,827.76 4,019.15 cft
downgraded
3 1st class bricks 3,000.00 3,150.00 pcs. 10.20
4 Ms rod dia 16 mm 4,962.88 5,211.02 kg 88.00
5 Ms rod dia 12 mm 4,900.00 5,145.00 kg 88.00
6 Ms rod dia 8 mm 200.00 210.00 kg 88.00
7 Sylhet sand 745.00 782.25 cft 95.00
8 Local sand 745.00 782.25 cft 28.00
9 Filling sand 1,500.00 1,575.00 cft 6.00
10 Polythene Roll 3.00 3.00 roll 1,750.00
Amount (Tk.)
Total amount oF Material & Service Charges
B) Total Amount for Tank 129, Tank 130
*** 5 percent materials cost considered from actual quantity.
New Storage tank No-135 Volume-2000 m3(Dia-15.2 m,Height-12.6 m).Reference previous storage tank basement floo
Unit Price
Sl No. Work Description Work Qty. Total Qty. Unit
(Tk.)
1 Earth excavation 4,000.00 4,200.00 cft 8.00
2 BFS Work 2,200.00 2,310.00 sft 5.00
4 Rcc work 4,000.00 4,200.00 cft 75.00
5 Pile Head breaking 188.00 197.40 Rft 155.00
8 Back filling 2,000.00 2,100.00 cft 6.00
Amount (Tk.)
Materials for Tank 135 (Dia-15.2 m, Height-12.6 m)
Unit Price
Sl No. Materials Name Work Qty. Total Qty. Unit
(Tk.)
1 Cement 840.00 882.00 bag 465.00
Stone chips 3/4"
2 3,713.25 3,898.91 cft 250.00
downgraded
3 1st class bricks 6,100.00 6,405.00 pcs. 10.20
4 Ms rod d 16 mm 4,064.00 4,267.20 kg 88.00
5 Ms rod d 12 mm 6,000.00 6,300.00 kg 88.00
6 Ms rod d 8 mm 200.00 210.00 kg 88.00
7 Sylhet sand 925.00 971.25 cft 95.00
8 Local sand 925.00 971.25 cft 28.00
9 Filling Sand 1,400.00 1,470.00 cft 6.00
10 Polythene Roll 4.00 roll 1,750.00
Amount (Tk.)
Bill of Material & Service Charges
C) Total Amount for Tank 135, Tank 136, Tank 137, Tank 138
*** 5 percent materials cost considered from actual quantity.
New Storage tank No-139 Volume-1450 m3(Dia-13 m,Height-12.6 m).Reference previous storage tank basement floor
New Storage tank No-139 Volume-1450 m3(Dia-13 m,Height-12.6 m).Reference previous storage tank basement floor
New Reformer unit -2 (Reference Design Chemex xylene production facility unit basement stuctural design)
mited.
attogram
e previous storage tank basement floor design
eight 12.6m)
Total Amount
Remarks
(Tk.)
42,000.00
18,375.00
425,250.00
36,130.50
15,750.00
537,505.50
eight 12.6m)
Total Amount
Remarks
(Tk.)
1,537,987.50
1,210,912.50
88,357.50
529,914.00
702,240.00
18,480.00
112,817.25
33,251.40
107,100.00
8,750.00
4,349,810.15
4,887,315.65
9,774,631.30
al quantity.
ce previous storage tank basement floor design
Total Amount
Remarks
(Tk.)
21,000.00
8,662.50
200,103.75
22,785.00
9,450.00
262,001.25
ight-12.6 m)
Total Amount
Remarks
(Tk.)
292,461.75
1,004,787.00
32,130.00
458,570.11
452,760.00
18,480.00
74,313.75
21,903.00
9,450.00
5,250.00
2,370,105.61
2,632,106.86
5,264,213.72
al quantity.
ce previous storage tank basement floor design
Total Amount
Remarks
(Tk.)
33,600.00
11,550.00
315,000.00
30,597.00
12,600.00
403,347.00
ht-12.6 m)
Total Amount
Remarks
(Tk.)
410,130.00
974,728.13
65,331.00
375,513.60
554,400.00
18,480.00
92,268.75
27,195.00
8,820.00
7,000.00
584,410.23
987,757.23
3,951,028.90
al quantity.
eight-12.6 m)
Total Amount
Remarks
(Tk.)
25,200.00
16,800.00
373,275.00
28,969.50
9,450.00
453,694.50
eight-12.6 m)
Total Amount
Remarks
(Tk.)
405247.50
823567.50
64260.00
374330.88
480480.00
18480.00
73815.00
27636.00
9450.00
7000.00
2,284,266.88
2,737,961.38
8,213,884.14
al quantity.
ht-16.2 m).Consultant design
ight-16.2 m)
Total Amount
Remarks
(Tk.)
169814.40
1207.50
2252250.00
88861.50
86100.00
63680.40
2,661,913.80
t-16.2 m)
Total Amount
Remarks
(Tk.)
3,403,590.75
6,495,300.00
52,668.00
9,310,940.10
571,032.00
2,817,276.00
2,653,998.38
26,460.00
196,350.00
12,250.00
25,539,865.23
28,201,779.03
al quantity.
ight-16.2 m)
Total Amount
Remarks
(Tk.)
169814.40
1207.50
2252250.00
92116.50
86100.00
63680.40
2,665,168.80
ght-16.2 m)
Total Amount
Remarks
(Tk.)
3,354,765.75
6,495,300.00
52,668.00
4,132,497.60
148,302.00
280,896.00
1,242,286.50
26,460.00
196,350.00
12,250.00
15,941,775.85
18,606,944.65
18,606,944.65
al quantity.
Unit-2
Total Taka Remarks
363174.00
1155.00
4567500.00
44756.25
3763.20
1075.20
202020.00
5,183,443.65
2
Total Taka Remarks
6757380.00
13632911.25
23562.00
2881401.60
203280.00
92400.00
1294256.25
378525.00
10500.00
25,274,216.10
$ 30,457,659.75
30,457,659.75
al quantity.
Summary Of Storage Tank Pile,Base foundation Matrials Cost & service charges
Tank No Pile Driving/Boring Cost Base Foundation Cost
Service Charges Materials Cost Service Charges
127 587,400.00 4,693,108.35 537,505.50
128 587,400.00 4,693,108.35 537,505.50
129 363,000.00 2,905,959.74 262,001.25
130 363,000.00 2,905,959.74 262,001.25
135 495,000.00 3,914,143.28 403,347.00
136 495,000.00 3,914,143.28 403,347.00
137 495,000.00 3,914,143.28 403,347.00
138 495,000.00 3,914,143.28 403,347.00
139 396,000.00 3,152,230.62 453,694.50
140 396,000.00 3,152,230.62 453,694.50
141 396,000.00 3,152,230.62 453,694.50
133 2,054,450.00 24,668,217.75 2,661,913.80
134 2,128,910.00 25,567,175.25 2,665,168.80
Reformer 726,000.00 6,124,224.75 5,183,443.65
n Matrials Cost & service charges
Base Foundation Cost
Materials Cost
4,349,560.15
4,349,560.15
1,996,477.82
1,996,477.82
584,210.23
584,210.23
584,210.23
584,210.23
2,284,066.88
2,284,066.88
2,284,066.88
15,987,258.35
15,941,425.85
25,274,216.10