Surface Mounted
User Responsibility
The installation instructions provided are for the Amico standard products. Slight modifications to the installations may
be required. The product shipped to the job site may not be exactly as shown on the installation drawings. See additional
sheets for project specifics where required.
All on-site preparations must be done prior to the delivery of the panel wall units. Please contact Amico to confirm and
review all information listed below. Failing to do so may result in discrepancies/misalignments during installation.
WARNING: Steps where extra care should be taken to prevent injuries and damage.
1/4" - 20 Hex
Head Bolt
1"
Washer
0.164"
2 Amico Corporation
Preparation Before Installation
1. Review a copy of the final approved shop drawing(s) and/or submittal package. These documents will provide you
with technical information specific to your installation, such as:
• Equipment types and quantities
• Room numbers and locations
• Shop drawings of each unit type
• Wiring diagrams and rough-in locations
• Blocking locations
IMPORTANT: Before installation of units, make sure the blocking required for mounting the headwall is installed
at locations indicated on shop drawings.
2. Locate the panel wall from the shipping boxes that you wish to install. The contents of each shipping box are listed on
the shipping document(s). Product is shipped in multiple sections. Please see pictures below for reference:
• Type A Design – top access panels
• Type B Design – full length panels
www.amico.com 3
Installation
A) Typical Method
1. Mark two horizontal lines to locate drilling for mounting of hanging bracket on the wall as follows:
a. First Line: 7" below the ceiling line for the top set of mounting brackets.
b. Second Line (lower location): Refer to the height indicated on shop drawings.
NOTE: These lines will be used to locate drilling for mounting of hanging brackets on the wall.
2. Set up hanging brackets as indicated in technical drawing provided with the units. Brackets are located at the top of
each section for ease of identification.
3. Mount the brackets on the wall using hardware compliant to local building codes, as per setup diagram (Figure 2).
Figure 1
Ceiling Line
First Line: 7" Below
finished ceiling
Second Line: As
per approved shop
Floor Line drawings
Figure 2
Ceiling Line
Blocking
Stud
Floor Line
Setup
4 Amico Corporation
Installation
IMPORTANT: Ensure hanging brackets are secured to the wall studs or blocking behind the drywall using screws
(provided by others).
5. Align the sections and connect in 4 places along the vertical edges of each section, using the hardware provided
(Figure 3 and Hardware 1).
6. Lift the assembly and hang it over the brackets which are already installed on the wall.
NOTE: Make sure the assembly unit is fully engaged into the hanging brackets at all locations (Figure 6).
7. Connect the hanging bracket to the headwall support using the provided self-drilling screws (Figure 7 and
Hardware 2). Use the number of screws listed below based on section size:
a. 19" to 32" wide section = 2 screws
b. 32.1" to 48" wide section = 4 screws
NOTE: The positive mount will be at the top hanging bracket location (Figure 6).
Figure 3 Figure 4
www.amico.com 5
Installation
8. Make all electrical and piping connections.
Figure 6 Figure 7
Ceiling
Line
Screws
(provided
by others)
Stud
Floor
Line
Setup Setup
6 Amico Corporation
Installation
B) Alternate Method
Use Alternate Method when Ceiling Grid is in Place
IMPORTANT: Ceiling tiles must be removed during installation to allow for electrical and med gas piping to pass
through.
2. Connect sections using bolt nut connections (see Step 5 of Typical Method Installation).
3. Attach the hanging brackets to the top crosses designated for hanging brackets. Use the number of screws listed
below based on section size:
IMPORTANT: Do not overtighten the screws – these screws will be tightened more once the unit is attached to
the wall.
5. Secure the unit to the wall through the hanging brackets on the top.
6. Use hardware compliant to local building codes to mount brackets to the wall (Figure 9).
Figure 9
Ceiling Line
Blocking
Stud
Floor Line
Setup
www.amico.com 7
Panel Removal/Handling
Access Panels Figure 13
Part #: W-X-LIFTER-0475
WARNING:
8 Amico Corporation
Notes