IS 2911-Part 1-Sec 3
IS 2911-Part 1-Sec 3
2016)
IS 2911 (Part 1/Sec 3) : 2010
Hkkjrh; ekud
(Reaffirmed 2015)
(Reaffirmed 2020)
(Reaffirmed 2014)
Hkkx 1 daØhV ikby
vuqHkkx 3 iwoZ<fyr daØhV dh fMªou ikby
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
( nwljk iqujh{k.k ) (Reaffirmed 2013)
(Reaffirmed 2009)
ICS 91.100.30 : 93.020
(Reaffirmed 2008)
(Reaffirmed 2007)
(Reaffirmed 2006)
(Reaffirmed 2005)
© BIS 2010
BUREAU OF INDIAN STANDARDS
MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
FOREWORD
This Indian Standard (Part 1/Sec 3) (Second Revision) was adopted by the Bureau of Indian Standards, after
the draft finalized by the Soil and Foundation Engineering Sectional Committee had been approved by the
Civil Engineering Division Council.
Piles find application in foundations to transfer loads from a structure to competent subsurface strata having
adequate load-bearing capacity. The load transfer mechanism from a pile to the surrounding ground is
complicated and is not yet fully understood, although application of piled foundations is in practice over
many decades. Broadly, piles transfer axial loads either substantially by friction along its shaft and/or by
d) Provision has been made for use of any established dynamic pile driving formulae, instead of
recommending any specific formula, to control the pile driving at site, giving due consideration to
limitations of various formulae.
e) Minimum grade of concrete to be used in pile foundations has been revised to M 25. Minimum time
of curing before handling of precast piles has been modified.
Driven precast concrete pile is a pile constructed in a casting yard and subsequently driven in the ground
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
with or without jetting, or other technics like preboring (depending on the conditions of soil) when the pile
has attained sufficient strength. By driving, the subsoil is displaced and remain in direct contact with the
pile. These piles find wide application particularly for structures, such as, wharves, jetties, etc, to act as a
free standing pile above the soil/water level or where conditions are unfavourable for use of cast in-situ
piles.
The recommendations for detailing for earthquake-resistant construction given in IS 13920 : 1993 ‘Ductile
detailing of reinforced concrete structures subjected to seismic forces — Code of practice’ should be taken
into consideration, where applicable (see also IS 4326 : 1993 ‘Earthquake resistant design and construction
of buildings — Code of practice’).
Indian Standard
DESIGN AND CONSTRUCTION OF PILE
FOUNDATIONS — CODE OF PRACTICE
PART 1 CONCRETE PILES
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
Section 3 Driven Precast Concrete Piles
( Second Revision )
1
IS 2911 (Part 1/Sec 3) : 2010
3.16 Ultimate Load Capacity — The maximum 4.2 As far as possible all informations given in 4.1
load which a pile can carry before failure, that is, shall be made available to the agency responsible
when the founding strata fails by shear as evidenced for the design and/or construction of piles and/or
from the load settlement curve or the pile fails as a foundation work.
structural member. 4.3 The design details of pile foundation shall give
3.17 Working Load — The load assigned to a pile the information necessary for setting out, layout of
as per design. piles, cut-off levels, finished cap level, layout and
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
3.18 Working Pile — A pile forming part of the orientation of pile cap in the foundation plan and
foundation system of a given structure. the safe capacity of each type of pile, etc.
4.1 For the satisfactory design and construction of 5.1 The equipments and accessories would depend
driven precast piles the following information would upon the type of precast driven piles, giving due
be necessary: consideration to the subsoil strata, ground-water
conditions, types of founding material and the
a) Site investigation data as laid down under
required penetration therein, wherever applicable.
2
IS 2911 (Part 1/Sec 3) : 2010
which are to be transmitted to the subsoil and shall applicable for cohesive and non-cohesive soil
be designed according to IS 456. respectively, are indicated in Annex B. Other formula
based on static cone penetration test [see IS 4968
6.2 Adjacent Structures (Parts 1, 2 and 3)] and standard penetration test (see
6.2.1 When working near existing structures care IS 2131) are given in B-3 and B-4.
shall be taken to avoid damage to such structures. 6.3.1.2 Dynamic formula
IS 2974 (Part 1) may be used as a guide for studying
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
qualitatively the effect of vibration on persons and Any established dynamic formula can be used to
structures. control the pile driving at site giving due
6.2.2 In case of deep excavations adjacent to piles, consideration to limitations of various formulae.
proper shoring or other suitable arrangement shall be Whenever double acting diesel hammers or hydraulic
made to guard against undesired lateral movement hammers are used for driving of piles, manufacturer’s
of soil. guidelines about energy and set criteria may be
referred to. Dynamic formulae are not directly
6.3 Pile Capacity applicable to cohesive soil deposits, such as,
saturated silts and clays as the resistance to impact
3
IS 2911 (Part 1/Sec 3) : 2010
undrained shear strength less than 0.01 N/mm2), interconnected by grade beams in two directions and
special considerations shall be made to determine for twin piles by grade beams in a line transverse to
whether the shaft would behave as a long column or the common axis of the pair so that the pile head is
not; if necessary, suitable reductions shall be made for fixed. In all other conditions the pile shall be taken
its structural strength following the normal structural as free headed.
principles covering the buckling phenomenon.
6.5.3 Raker Piles
When the finished pile projects above ground level
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
and is not secured against buckling by adequate Raker piles are normally provided where vertical
bracing, the effective length will be governed by the piles cannot resist the applied horizontal forces.
fixity imposed on it by the structure it supports and Generally the rake will be limited to 1 horizontal to
by the nature of the soil into which it is installed. The 6 vertical. In the preliminary design the load on a
depth below the ground surface to the lower point of raker pile is generally considered to be axial. The
contraflexure varies with the type of the soil. In good distribution of load between raker and vertical piles
soil the lower point of contraflexure may be taken at in a group may be determined by graphical or
a depth of 1 m below ground surface subject to a analytical methods. Where necessary, due
minimum of 3 times the diameter of the shaft. In weak consideration should be made for secondary bending
equations are in use. However, it is difficult to a) the reliability of the calculated value of
establish the accuracy of these efficiency equations ultimate load capacity of a pile;
as the behaviour of pile group is dependent on many
b) the types of superstructure and the type of
complex factors. It is desirable to consider each case
loading; and
separately on its own merits.
c) allowable total/differential settlement of the
6.7.2 The load-carrying capacity of a pile group
structure.
may be equal to or less than the load-carrying
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
capacity of individual piles multiplied by the number 6.8.2 When the ultimate load capacity is determined
of piles in the group. The former holds true in case from either static formula or dynamic formula, the
of friction piles, driven into progressively stiffer factor of safety would depend on the reliability of
materials or in end-bearing piles. For driven piles in the formula and the reliability of the subsoil
loose sandy soils the group capacity may even be parameters used in the computation. The minimum
higher due to the effect of compaction. In such cases factor of safety on static formula shall be 2.5. The
a load test may be carried out on a pile in the group final selection of a factor of safety shall take into
after all the piles in the group have been installed. consideration the load settlement characteristics of
the structure as a whole at a given site.
6.7.3 In case of piles deriving their support mainly
5
IS 2911 (Part 1/Sec 3) : 2010
6.11.3 Where exceptionally long lengths of piles are concrete piles for the entire length. All the main
required, hollow sections can be used. If the final longitudinal bars shall be of the same length and
condition requires larger cross-sectional area, the should fit tightly into the pile shoe if there is one.
hollow sections can be filled with concrete after Shorter rods to resist local bending moments may be
driving in position. added but the same should be carefully detailed to
6.11.4 Wherever final pile length is so large that a avoid any sudden discontinuity of the steel which
single length precast pile unit is either uneconomical may lead to cracks during heavy driving. The area
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
or impracticable for installation, the segmental of main longitudinal reinforcement shall not be less
precast RCC piles with a number of segments using than the following percentages of the cross-sectional
efficient mechanical jointing could be adopted. area of the piles:
Excessive whipping during handling precast pile a) For piles with a length less than 30 times the
may generally be avoided by limiting the length of least width — 1.25 percent,
pile to a maximum of 50 times the least width. As an b) For piles with a length 30 to 40 times the
alternative, segmental precast piling technique could least width — 1.5 percent, and
be used.
c) For piles with a length greater than 40 times
The design of joints shall take care of corrosion by
6.13.3 The pile cap should be rigid enough so that 7.3 Concrete
the imposed load could be distributed on the piles
in a group equitably. 7.3.1 Consistency of concrete to be used for driven
precast piles shall be consistent with the method of
6.13.4 In case of a large cap, where differential
installation of piles. Concrete shall be so designed
settlement may occur between piles under the same
or chosen as to have a homogeneous mix having a
cap, due consideration for the consequential moment
slump/workability consistent with the method of
should be given.
concreting. The minimum grade of concrete to be
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
6.13.5 The clear overhang of the pile cap beyond used for piling shall be M 25.
the outermost pile in the group shall be a minimum
7.3.2 For the concrete, water and aggregates
of 150 mm.
specifications laid down in IS 456 shall be followed
6.13.6 The cap is generally cast over a 75 mm thick in general.
levelling course of concrete. The clear cover for
main reinforcement in the cap slab shall not be less 8 WORKMANSHIP
than 60 mm.
6.13.7 The embedment of pile into cap should be 8.1 Casting and Tolerance
7
IS 2911 (Part 1/Sec 3) : 2010
shall be adjusted to suit the increased length of piles. Table 2 Time for Curing of Precast Piles
The reinforcement at the top of the pile will need to (Clause 8.2.2)
be exposed for a distance of 40 times the bar Type of Cement Minimum Periods from the
diameter and the new bars overlapped for the Time of Casting
distance. The central duct will also have to be
Strike Roll Pile End of Lift from
carefully extended. Where facilities at site are Side off Bottom Wet Casting
available, welding of reinforcement shall be as per Shutters Shutter Curing Yard
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
the relevant Indian Standard referred for welding in (h) (days) (days) (days)
the product specification standard for steel (1) (2) (3) (4) (5)
reinforcing bars. Ordinary Portland 8 48 7 8 /211)
cement/Sulphate
Extension of piles length 150 mm or lesser should
resisting Portland
be avoided and instead pile cap depths increased cement
suitably 150 mm all around the pile. 1)
When pile length is more than 15 m.
8.1.6 For precast piles, the following tolerances
should be adhered: 8.3 Storing and Handling
4) Additional for every 6 mm 8.4.1 The hammer blow generates a stress wave
subsequent 6 m which traverses the length of the pile, and failure,
whether by compression or tension, may occur
8.1.7 All precast piles shall be inspected for any anywhere along the pile.
defects/honeycombing, etc, and approved for 8.4.2 Failure due to excessive compressive stress
installation as per structural requirements. most commonly occurs at the head. Head stresses
8.1.8 Piles shall be identified by marking in paint depend upon the ground conditions, weight of the
the number of the pile, length of the pile and its date hammer, its drop and the stiffness of head cushion.
of casting. 8.4.3 The maximum set for a given stress is obtained
by using the heaviest hammer and the softest
8.2 Curing packing the hammer drop being adjusted to suit the
8.2.1 Though from consideration of speed and allowable stress in the concrete.
economy precast concrete piles will have to be in 8.4.4 Head-packing materials increase in stiffness
place with the least possible delay after casting, it with repeated use. Hence, optimum driving
shall be kept in mind that a thorough curing and conditions can be maintained only by regular
hardening is necessary before the piles are driven and replacement of the packing.
proper schedule to take care of this shall be decided 8.4.5 Failure in the lower sections of a pile can only
for casting, stacking and placing. The most occur in exceptionally hard driving where in theory
important factors effecting the time of curing are the the compressive stress at tip can reach twice the head
method of curing, weather during hardening, stresses. In practice, however, this rarely occurs and
probable hardness of placing and the method of the maximum compressive stress tends to be fairly
lifting and pitching. uniform over considerable length of the pile.
8.2.2 Before the handling of the piles, the minimum 8.4.6 Longitudinal tension is caused by reflection
periods counted from the time of casting shall be as of the compressive wave at the ‘free’ end. Tensile
given in Table 2. stresses, therefore, may arise when the ground
8
IS 2911 (Part 1/Sec 3) : 2010
resistance is low and/or when the head conditions avoided and greater rates and depths of penetration
result in hammer rebound, that is, with hard packing can be achieved by reducing the tip resistance by
and light hammer. jetting than by percussive methods. Jetting is
8.4.7 In addition, a relatively long length of pile effective in cohesionless soils, such as, sand, gravel
unsupported above a hard stratum may encourage and also in fine-grained soils provided the
transverse or flexural vibrations, which may be set percentage of clay is small. Jetting is not effective
up if the hammer below becomes non-axial or the in clay soils.
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
pile is not restrained. 8.4.14 Jetting of piles shall be carried out only when
8.4.8 Pile may be driven with any type of hammer, it is desired and in such a manner as not to impair
provided the pile penetrate to the prescribed depth the bearing capacity of the piles already in place, the
or attain the specified resistance without being stability of the ground or the safety of any adjoining
damaged. The hammer, helmet, dolly and pile shall buildings.
be coaxial and shall sit squarely one upon the other. 8.4.15 The quantity of water required for effective
It is always preferable to employ the heaviest jetting is directly related to the cross-sectional area
hammer practicable and to limit the stroke/drop so of the piles (including external jet piles). Pile in
as not to damage the pile. The stroke/drop of a single dense cohesionless soils may require water up to
9
IS 2911 (Part 1/Sec 3) : 2010
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
the worst combination of the above tolerances in
position and inclination. In case of piles deviating such difference. If the boring shows that the strata
beyond these limits and to such an extent that the contain pockets of highly compressive material
resulting eccentricity can not be taken care of by a below the level of shorter pile, it may be necessary
re-design of the pile cap or pile ties, the piles shall to take such piles to a level below the bottom of the
be replaced or supplemented by additional piles. zone, which shows such pockets.
8.9 Deviations
8.6 Sequence of Piling
Any deviation from the designed location, alignment
8.6.1 In a pile group the sequence of installation of or load-carrying capacity of any pile shall be noted
10
IS 2911 (Part 1/Sec 3) : 2010
9 ADDITIONAL PROVISION FOR 9.3.1.1 For diesel hammers the minimum prestress
PRESTRESSED CONCRETE PILES should be 5 N/mm2.
9.3.2 A considerably greater prestress may be
9.1 General required for raking piles, particularly if these are
The stresses set up when handling prestressed piles driven in ground which may tend to deflect the piles
of given length can be resisted by smaller cross- from their true alignments.
section and thus economy in materials may be 9.3.3 Loss of prestress should be calculated in
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
achieved. The small cross-section may permit or accordance with IS 1343.
necessitate greater penetration. The bearing capacity
9.4 Prestressing Wires and Stirrups
may govern the cross-section of a pile and could
preclude the use of the smaller sizes that would be 9.4.1 The prestressing wires should be evenly
possible from strength considerations alone. The spaced parallel to faces of the pile.
tensile stresses caused by the action of stress waves 9.4.2 Mild steel stirrups of not less than 6 mm
when driving can be reduced by the prestress. The diameter should be placed at pitch of not more than
reduction of tensile cracks may give greater the side dimension less 50 mm. At the top and bottom,
durability to the pile, particularly if the pile is for a length of three times the side dimensions, the
Ratio of hammer to pile weight not less than 0.9 0.8 0.7 0.6
Minimum prestress for normal driving, N/mm2 2.0 3.5 5.0 6.0
Minimum prestress for easy driving, N/mm2 3.5 4.0 5.0 6.0
11
IS 2911 (Part 1/Sec 3) : 2010
Piles should not be removed from the place of reinforced concrete piles as in 8.4, 8.5 and 8.9.
casting until after the transfer of prestress. Although the effect of prestressing is to reduce
The piles should be cast in one operation using tension cracks induced by stress waves, such
internal and external vibrators to assist compaction cracking may still occur, particularly when driving
of the concrete. is ‘light’, or if too light a hammer is used. A careful
check for tension cracks should be made during the
Care should be taken to ensure that vibration from
driving of the first pile and, if these occur, the
adjoining work does not affect the placed concrete
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
hammer drop should be reduced. If the cracks persist
during the setting period. Care should be taken that
or recur when the full drop has to be used, then a
the head of the piles is finished plane and normal to
heavier hammer should be substituted.
the axis of the pile. Each pile should be marked with
a reference number and date of casting. Curing 9.8 Embedment of Pile Head into Pile Cap
should be carried out as described in 8.2 or the piles
may be steam cured. The concrete of the pile may be stripped to expose
the prestressing wires. The concrete should be
9.6.3 Transfer of Prestress stripped to such a level that the remaining concrete
Whenever a batch of piles if cast, four test cubes projects 75 mm into the pile cap. Where tension has
12
IS 2911 (Part 1/Sec 3) : 2010
ANNEX A
(Clause 2)
LIST OF REFERRED INDIAN STANDARDS
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
grade — Specification (fourth test for soils (first revision)
revision) 2911 Code of practice for design and
construction of pile foundations:
432 (Part 1) : Specification for mild steel and
(Part 3) : 1980 Under-reamed piles (first
1982 medium tensile steel bars and
revision)
hard-drawn steel wire for concrete
(Part 4) : 1984 Load test on piles (first revision)
reinforcement: Part 1 Mild steel
and medium tensile steel bars 2974 (Part 1) : Code of practice for design and
(third revision) 1982 construction of machine
foundations: Part 1 Foundation
13
IS 2911 (Part 1/Sec 3) : 2010
ANNEX B
(Clauses 6.3.1.1 and 6.3.2)
LOAD-CARRYING CAPACITY OF PILES-STATIC ANALYSIS
B-1 PILES IN GRANULAR SOILS PDi = effective overburden pressure for the ith
layer, in kN/m2;
The ultimate load capacity (Qu) of piles, in kN, in δi = angle of wall friction between pile and
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
granular soils is given by the following formula: soil for the ith layer; and
Asi = surface area of pile shaft in the ith layer,
Qu = Ap (½ Dγ Nγ + PD N q )∑ ni =1 K i PDi tan δ i Asi ...(1)
in m2.
The first term gives end-bearing resistance and the NOTES
second term gives skin friction resistance. 1 N γ factor can be taken for general shear failure
according to IS 6403.
where 2 Nq factor will depend on the nature of soil, type
Ap = cross-sectional area of pile tip, in m2; of pile, the L/B ratio and its method of construction.
The values applicable for driven piles are given in
D = diameter of pile shaft, in m; Fig. 1.
14
IS 2911 (Part 1/Sec 3) : 2010
B-2 PILES IN COHESIVE SOILS B-3.2 Ultimate end-bearing resistance (qu), in kN/m2,
may be obtained as:
The ultimate load capacity (Qu) of piles, in kN, in
cohesive soils is given by the following formula: qc0 + qc1
+ qc2
qu = 2
Qu = Ap Nc c p + ∑ni = 1 α i ci Asi …(2) 2
The first term gives the end-bearing resistance and where
the second term gives the skin friction resistance.
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
qc0 = average static cone resistance over a depth
where of 2D below the pile tip, in kN/m2;
Ap = cross-sectional area of pile tip, in m2; qc1 = minimum static cone resistance over the
Nc = bearing capacity factor, may be taken same 2D below the pile tip, in kN/m2;
as 9; qc2 = average of the envelope of minimum static
cp = average cohesion at pile tip, in kN/m2; cone resistance values over the length of
pile of 8D above the pile tip, in kN/m2; and
∑i =1
n
= summation for layers 1 to n in which the
D = diameter of pile shaft.
15
IS 2911 (Part 1/Sec 3) : 2010
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
Qu = 30 N Ap + …(4)
Lb N As D 0.60
Qu = 40 N Ap + …(3) The meaning of all terms is same as for equation 3.
D 0.50
The first term gives the end-bearing resistance and B-5 FACTOR OF SAFETY
the second term gives the frictional resistance.
The minimum factor of safety for arriving at the safe
where pile capacity from the ultimate load capacity
N = average N value at pile tip; obtained by using static formulae shall be 2.5.
Lb = length of penetration of pile in the bearing B-6 PILES IN STRATIFIED SOIL
ANNEX C
(Clause 6.5.2)
ANALYSIS OF LATERALLY LOADED PILES
16
IS 2911 (Part 1/Sec 3) : 2010
C-2.2 The lateral soil resistance for preloaded clays C-3 CRITERIA FOR SHORT RIGID PILES
with constant soil modulus is modelled according to AND LONG ELASTIC PILES
the equation: Having calculated the stiffness factor T or R, the
p criteria for behaviour as a short rigid pile or as a long
y =K elastic pile are related to the embedded length L as
where given in Table 7.
k 0.3 Table 7 Criteria for Behaviour of Pile
K = 1 ×
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
1.5 B Based on its Embedded Length
where k1 is Terzaghi’s modulus of subgrade reaction Sl Type of Pile Relation of Embedded
as determined from load deflection measurements on No. Behaviour Length with
a 30 cm square plate and B is the width of the pile Stiffness Factor
(diameter in case of circular piles). The recommended Linearly Constant
values of k 1 are given in Table 6. Increasing
(1) (2) (3) (4)
Table 6 Modulus of Subgrade Reaction
i) Short (Rigid) Pile L ≤ 2T L ≤ 2R
for Cohesive Soil, k1, in kN/m3
L ≥ 4T L ≥ 3.5R
× 103
C-2.3.2 For Piles in Preloaded Clays 12 EI
…for fixed head pile
4 EI where
Stiffness factor R, in m =
KB H = lateral load, in kN;
where
y = deflection of pile head, in mm;
E = Young’s modulus of pile material, in
MN/m2; E = Young’s modulus of pile material, in
I = moment of inertia of the pile cross- kN/m2;
section, in m4; I = moment of inertia of the pile cross-section,
k1 0.3 in m4;
K = × (see Table 6 for values of k 1, in
1.5 B zf = depth to point of fixity, in m; and
3
MN/m ); and
e = cantilever length above ground/bed to the
B = width of pile shaft (diameter in case of point of load application, in m.
circular piles), in m.
17
IS 2911 (Part 1/Sec 3) : 2010
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
ON 25/07/2022 15:48:51 (165.225.122.241) VALID UPTO 22/02/2023 00:00:00
FIG. 3 DEPTH OF FIXITY
C-4.3 The fixed end moment of the pile for the The fixed end moment, M F of the equivalent
equivalent cantilever may be determined from the cantilever is higher than the actual maximum
following expressions: moment M in the pile. The actual maximum moment
b g
Fixed end moment, MF = H e + z f may be obtained by multiplying the fixed end
moment of the equivalent cantilever by a reduction
…for free head pile
H be + z g
factor, m, given in Fig. 4.
f
Fixed end moment, M =F
2
…for fixed head pile
ANNEX D
(Clause 6.11.6)
PROBABLE VALUES OF n, EFFICIENCY OF THE BLOW
D-1 The formula for efficiency of the blow, Ratio of e = 0.5 e = 0.4 e = 0.32 e = 0.25 e = 0
representing the ratio of energy after impact to P/W
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
striking energy of ram, n, is: 3½ 0.39 0.33 0.30 0.27 0.22
Where W is greater than P.e and the pile is driven 4 0.36 0.31 0.28 0.25 0.20
into penetrable ground,
5 0.31 0.27 0.24 0.21 0.16
n=
d
W + P ⋅ e2 i 6 0.27 0.24 0.21 0.19 0.14
W+P 7 0.24 0.21 0.19 0.17 0.12
8 0.22 0.20 0.17 0.15 0.11
Where W is less than P.e and the pile is driven into
penetrable ground, NOTES
MN W + P PQ − MMN W + P PPQ
2
tonne.
n=
2 Where the pile finds refusal in rock, 0.5P should
be substituted for P in the above expressions for n.
The following are the values of n in relation to e and 3 e is the coefficient of restitution of the materials
under impact as tabulated below:
to the ratio of P/W:
a) For steel ram of double-acting hammer striking
Ratio of e = 0.5 e = 0.4 e = 0.32 e = 0.25 e = 0 on steel anvil and driving reinforced concrete
P/W pile, e = 0.5.
b) For cast-iron ram of single-acting or drop
½ 0.75 0.72 0.70 0.69 0.67 hammer striking on head of reinforced concrete
1 0.63 0.58 0.55 0.53 0.50 pile, e = 0.4.
c) Single-acting or drop hammer striking a well-
1½ 0.55 0.50 0.47 0.44 0.40 conditioned driving cap and helmet with hard
2 0.50 0.44 0.40 0.37 0.33 wood dolly in driving reinforced concrete piles
or directly on head of timber pile, e = 0.25.
2½ 0.45 0.40 0.36 0.33 0.28 d) For a deteriorated condition of the head of pile
3 0.42 0.36 0.33 0.30 0.25 or of dolly, e = 0.
19
IS 2911 (Part 1/Sec 3) : 2010
ANNEX E
(Clause 8.10.2)
DATA SHEET
Site ..........................................................................................................................................................................
Title .........................................................................................................................................................................
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
Date of enquiry ......................................................................................................................................................
Date piling commenced .........................................................................................................................................
Actual or anticipated date for completion of piling work .................................................................................
Number of pile ........................................................................................................................................................
Shape — Round/Square
.........................................................................................................................................
Sequence of piling: From centre towards the periphery or from periphery towards the centre
(for groups)
Test loading:
........................................................................................................................................................................
20
IS 2911 (Part 1/Sec 3) : 2010
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
Method of Taking Observations:
General Remarks:
.................................................................................................................................................................................
.................................................................................................................................................................................
21
IS 2911 (Part 1/Sec 3) : 2010
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
.................................................................................................................................................................................
BORE-HOLE LOG
22
IS 2911 (Part 1/Sec 3) : 2010
ANNEX F
(Foreword)
COMMITTEE COMPOSITION
Soil and Foundation Engineering Sectional Committee, CED 43
Organization Representative(s)
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
In personal capacity (188/90, Prince Anwar Shah Road, DR N. S OM (Chairman)
Kolkatta 700045)
A.P. Engineering Research Laboratories, Hyderabad SHRI P. SIVAKANTHAM
S HRI P. JOHN VICTOR (Alternate)
AFCONS Infrastructure Limited, Mumbai SHRI A. D. LONDHE
S HRI V. S. KULKARNI (Alternate)
Central Board of Irrigation & Power, New Delhi DIRECTOR
Central Building Research Institute, Roorkee SHRI Y. PANDEY
S HRI R. DHARMRAJU (Alternate)
23
IS 2911 (Part 1/Sec 3) : 2010
Organization Representative(s)
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
S HRI S. RAY (Alternate)
The Pressure Piling Co (I) Pvt Limited, Mumbai SHRI V. C. DESHPANDE
SHRI PUSHKAR V. D ESHPANDE (Alternate)
University of Jodhpur, Jodhpur SHRI G. R. CHOWDHARY
BIS Directorate General SHRI A. K. S AINI, Scientist ‘F’ & Head (CED)
[Representing Director General (Ex-officio)]
Member Secretary
SHRIMATI MADHURIMA MADHAV
Scientist ‘B’ (CED), BIS
24
Bureau of Indian Standards
BIS is a statutory institution established under the Bureau of Indian Standards Act, 1986 to promote
harmonious development of the activities of standardization, marking and quality certification of goods
and attending to connected matters in the country.
Copyright
SUPPLIED BY BOOK SUPPLY BUREAU UNDER THE LICENSE FROM BIS FOR TATA CONSULTING ENGINEERS LIMITED - MUMBAI
BIS has the copyright of all its publications. No part of these publications may be reproduced in any form
without the prior permission in writing of BIS. This does not preclude the free use, in the course of
implementing the standard, of necessary details, such as symbols and sizes, type or grade designations.
Enquiries relating to copyright be addressed to the Director (Publications), BIS.
Amendments are issued to standards as the need arises on the basis of comments. Standards are also reviewed
This Indian Standard has been developed from Doc No.: CED 43 (7284).