Net Metering Procedure External

The document outlines the net metering connection procedure between a customer and ZETDC District Office. The customer first applies by filling out form ENM1 and paying an application fee. ZETDC then checks if the information and capacity can be accommodated. If approved, the customer fills form ENM2 and pays for metering connection. ZETDC sets a commissioning date where the customer's installation is tested with a representative. If passed, the customer can operate in net metering mode for 20 years under contract.

Uploaded by

Trevoh LayHit
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
160 views1 page

Net Metering Procedure External

The document outlines the net metering connection procedure between a customer and ZETDC District Office. The customer first applies by filling out form ENM1 and paying an application fee. ZETDC then checks if the information and capacity can be accommodated. If approved, the customer fills form ENM2 and pays for metering connection. ZETDC sets a commissioning date where the customer's installation is tested with a representative. If passed, the customer can operate in net metering mode for 20 years under contract.

Uploaded by

Trevoh LayHit
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Net Metering Connection Procedure

Customer ZETDC District Office

Start Applicant pays


application fee

Customer applies for Net


Metering by filling ENM1 form

Checks if
information on
No
ENM1 form is
correct
Customer
adviced to
Customer corrects correct
information on the ENM1 information
form accordingly Yes

Zetdc checks if
applied capacity can
be accommodated
No
Yes

Application not approved


and reasons cited
Application is approved
Applicant fills in
and submits
ENM2 form
Zetdc sets commisioning
dates

Applicant pays
for metering
connection
Applicant carries out
commissioning test with
ZETDC representative
Customer operates in net Metering present
Yes
mode with valid contract for 20 years.

Does installation
pass commisisoning
tests

Customer Rectifies failure


points
End