TEAM TEC CONSTRUCTION PTE LTD
Date :05-01-2022 METHOD OF STATEMENT Doc No.: TTC / MS/074
Revision: 00 Trial hole Excavation Pages -4
Main Contractor : ADDCEL ENGINEERING PTE LTD
Sub-Contractor : TEAM TEC CONSTRUCTION PTE LTD
Location : TUAS SOUTH AVE 3
Prepared By Reviewed By Approved By
Signature
Name
Date
1
CONTENTS
1. Introduction
2. Site Preparation & Investigation
3. Equipment & Tools
4. Procedure/Work Sequence
Introduction
This proposal of methods to be used for Cable Detection, manual excavation up to
1.9m depth, shoring, backfilling, compaction, re-instate turfs.
Site preparation & Investigation
Equipment & Tools
Procedure / work Sequence
Housekeeping
The following statement covers the method of statement of the above said job.
Site Preparation &Investigations
Relevant permits will be prepared by Client and approved by authorized person
prior to start work.
Cable detection will be carried out as per the Layout Drawings.
Excavation location to be mark as per marked drawing and witnessed by client.
All equipment & tools should be in good condition prior to mobilize to site and all
the hand tools.
Provide the Barricade along the work area.
Site survey & Marking
Site preparation, marking &setting out will be carried out as per Client instruction
received.
All marking will be witnessed by client prior to start work.
Equipments & Tools
Plate compactor
Shovel
Hoe
Wheel barrow
Hammer
2
Procedure / Work Sequence
Mobilization / Demobilization of Tools
Loading / Unloading of tools by using 10foot lorry.
Tools are delivered the allocated storage area possible to where they will be
used.
All the vehicle movements controlled by banksman.
Cable Detection Works
Cable detection shall be carried out & clear drawing with indication shall be in
place before starting any excavation works.
Cable detection works to be carried out by third party and the results has been
submitted to Client in advanced prior to start works.
All the underground services marked by spray paint and highlight in site layout
Drwg.
Trial hole Excavation works
Manual excavation tools such as hoe and spade all the hand tools should be in
good condition.
During excavation, worker to position himself on firm ground so that he does not
loose balance.
Worker will work in a safe distance interval in between each other.
Manually excavate the soil layer by layer and throw 1m away from the excavated
zone. In-case of any rain stockpile should be covered with canvas.
Excavation depth will be until 1.9m.
During excavation if we found any underground facilities, STOP work and
highlighted to the Client immediately.
Entry and Exit access will be provided at both sides of the trench.
Timber Shoring works
After the excavation timber shoring will be provided along the excavated trench.
All the shoring props and support should be rigid.
After completion of excavation works the shoring will be removed by manually.
Backfilling & Compaction works
After the completion of timber shoring dismantling works and trenches shall be
cleaned and free of wooden waste or trash.
Backfilling with excavated material and free of waste material such as wooden or
other organic materials.
Backfilling shall be carried out in layer and compact using plate compactor.
3
Housekeeping
Work area shall be maintained clear of scattered tools and materials.
Equipment & tools shall be kept in one place such that is does not obstruct the
work activity which may cause tripping hazards.
At the end of daily activity, all the tools shall be stored and kept in one place
away from obstruction.
Good housekeeping should be maintained at all time.