MS For Trial Hole Excavation.

This method statement is for trial hole excavation works by Team Tec Construction Pte Ltd as a sub-contractor for Addcel Engineering Pte Ltd. The works include site preparation, cable detection, excavation of trial holes up to 1.9m depth manually, installation of timber shoring, backfilling and compaction. Safety and housekeeping measures such as permits, markings, barricades and good storage of equipment will be followed. Cable detection results will be submitted to the client before excavation works start. Excavated material will be placed 1m away and covered in case of rain.

Uploaded by

Tamilananth
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
377 views4 pages

MS For Trial Hole Excavation.

This method statement is for trial hole excavation works by Team Tec Construction Pte Ltd as a sub-contractor for Addcel Engineering Pte Ltd. The works include site preparation, cable detection, excavation of trial holes up to 1.9m depth manually, installation of timber shoring, backfilling and compaction. Safety and housekeeping measures such as permits, markings, barricades and good storage of equipment will be followed. Cable detection results will be submitted to the client before excavation works start. Excavated material will be placed 1m away and covered in case of rain.

Uploaded by

Tamilananth
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

TEAM TEC CONSTRUCTION PTE LTD

Date :05-01-2022 METHOD OF STATEMENT Doc No.: TTC / MS/074

Revision: 00 Trial hole Excavation Pages -4

Main Contractor : ADDCEL ENGINEERING PTE LTD

Sub-Contractor : TEAM TEC CONSTRUCTION PTE LTD

Location : TUAS SOUTH AVE 3

Prepared By Reviewed By Approved By

Signature

Name

Date

1
CONTENTS

1. Introduction

2. Site Preparation & Investigation

3. Equipment & Tools

4. Procedure/Work Sequence

Introduction

This proposal of methods to be used for Cable Detection, manual excavation up to


1.9m depth, shoring, backfilling, compaction, re-instate turfs.
 Site preparation & Investigation
 Equipment & Tools
 Procedure / work Sequence
 Housekeeping
The following statement covers the method of statement of the above said job.
Site Preparation &Investigations

 Relevant permits will be prepared by Client and approved by authorized person


prior to start work.
 Cable detection will be carried out as per the Layout Drawings.
 Excavation location to be mark as per marked drawing and witnessed by client.
 All equipment & tools should be in good condition prior to mobilize to site and all
the hand tools.
 Provide the Barricade along the work area.

Site survey & Marking


 Site preparation, marking &setting out will be carried out as per Client instruction
received.
 All marking will be witnessed by client prior to start work.

Equipments & Tools


 Plate compactor
 Shovel
 Hoe
 Wheel barrow
 Hammer

2
Procedure / Work Sequence

Mobilization / Demobilization of Tools


 Loading / Unloading of tools by using 10foot lorry.
 Tools are delivered the allocated storage area possible to where they will be
used.
 All the vehicle movements controlled by banksman.

Cable Detection Works
 Cable detection shall be carried out & clear drawing with indication shall be in
place before starting any excavation works.
 Cable detection works to be carried out by third party and the results has been
submitted to Client in advanced prior to start works.
 All the underground services marked by spray paint and highlight in site layout
Drwg.
Trial hole Excavation works
 Manual excavation tools such as hoe and spade all the hand tools should be in
good condition.
 During excavation, worker to position himself on firm ground so that he does not
loose balance.
 Worker will work in a safe distance interval in between each other.
 Manually excavate the soil layer by layer and throw 1m away from the excavated
zone. In-case of any rain stockpile should be covered with canvas.
 Excavation depth will be until 1.9m.
 During excavation if we found any underground facilities, STOP work and
highlighted to the Client immediately.
 Entry and Exit access will be provided at both sides of the trench.
Timber Shoring works
 After the excavation timber shoring will be provided along the excavated trench.
 All the shoring props and support should be rigid.
 After completion of excavation works the shoring will be removed by manually.
Backfilling & Compaction works
 After the completion of timber shoring dismantling works and trenches shall be
cleaned and free of wooden waste or trash.
 Backfilling with excavated material and free of waste material such as wooden or
other organic materials.
 Backfilling shall be carried out in layer and compact using plate compactor.

3
Housekeeping
 Work area shall be maintained clear of scattered tools and materials.
 Equipment & tools shall be kept in one place such that is does not obstruct the
work activity which may cause tripping hazards.
 At the end of daily activity, all the tools shall be stored and kept in one place
away from obstruction.
 Good housekeeping should be maintained at all time.