Summer Internship at "G.S.E.C.L. Thermal Power Station Sikka''
Summer Internship at "G.S.E.C.L. Thermal Power Station Sikka''
Submitted by
ARJUN H. SOMAIYA
AUGUST 2022
CERTIFICATE
This is to certify that project work embodied in this report entitled Summer
Internship at GSECL Sikka Thermal Power Station was carried out by Mr.
ARJUN H. SOMAIYA at V.V.P. Engineering College for partial fulfilment
of B.E. degree to be awarded by Gujarat Technological University. This
project work has been carried out under my supervision and is to the
satisfaction of department. The student’s work has been published/accepted
for publication.
Date:
Place:
DECLARATION
I hereby certify that I am the sole author of this report and that neither any part
of this work nor the whole of the work has been submitted for a degree to any
other University or Institution.
I certify that, to the best of my knowledge, my work does not infringe upon
anyone’s copyright nor violate any proprietary rights and that any ideas, techniques,
quotations, or any other material from the work of other people included in my report,
published or otherwise, are fully acknowledged in accordance with the standard
referencing practices. Furthermore, to the extent that I have included copyrighted
material that surpasses the bounds of fair dealing within the meaning of the Indian
Copyright Act, I certify that I have obtained a written permission from the copyright
owner(s) to include such material(s) in my work and have included copies of such
copyright clearances to my appendix.
I declare that this is a true copy of my report, including any final revisions, as
approved by my supervisor.
Date:
Place:
ARJUN H. SOMAIYA
Table of Contents
Title Page i
Certificate Page ii
Declaration of Originality Page iii
Acknowledgements iv
Table of Contents v
Abstract 1
List of Figures 2
Chapter 1 About Company 3
1.1 Thermal Power Plant 4
1.2 Maintenance Departments 5
1.2. Main Plant 6
1.2 Switch Yard 7
Chapter 2 Different Types of Cycle 8
2.1 Coal & Ash Handling Cycle 8
2.2 Air & Gas Cycle 9
2.2 Water to Steam Cycle 10
2.2. Electrical Cycle 11
CONCLUSION 20
ABSTRACT
ABSTRACT
SUMMER INTERNSHIP AT
“G.S.E.C.L. THERMAL POWER STATION SIKKA’’
Submitted by
ARJUN H. SOMAIYA
1
Gujarat Technological University V.V.P. Engineering College
LIST OF FIGURES
List of Figures
Fig.1 Maintenance Department 5
Fig.2 Personal Protective Equipment 5
Fig.3 Coal & Ash Cycle 8
Fig.4 Air & Gas Cycle 9
Fig.5 Water & Steam Cycle 10
Fig.6 Scada System of 220 KV Switchyard 11
Fig.7 ICT Transformer Name Plate 16
Fig.8 Exciter Inner View 17
Fig.9 Generator Name Plate 17
Fig.10 Information from BHEL 18-19
2
Gujarat Technological University V.V.P. Engineering College
ABOUT COMPANY
States Unit Sizes – 500 Megawatt (2 units x 250 Megawatt) Units Operational – 2
Unit Commissioned
Stage 1 - Unit 1- 120 Megawatt – March 1988 – Retired
Stage 2 - Unit 2- 120 Megawatt – March 1993 – Retired
Stage 3 - Unit 3- 250 Megawatt – March 2015 - Operational
Stage 4 - Unit 4- 250 Megawatt – September 2015 – Operational
3
Gujarat Technological University V.V.P. Engineering College
ABOUT COMPANY
Thermal power plant or steam power plant is a generating station which converts heat
energy of fossil fuels into electrical energy. Generally bituminous, brown or peat type coal
is used as the fuel of coal based thermal power plant.
In a thermal power plant, coal is burnt in a big boiler which produces steam at high pressure
and temperature. This steam is passed through a steam turbine which converts steam's heat
energy into mechanical energy. The steam turbine acts as a prime mover and it is coupled
to an alternator. Now alternators collect the mechanical energy from the steam turbine and
convert into electrical energy. In this power plant, steam turbine sometimes acts as
auxiliary equipment like pumps, strokes etc. This is very basic introduction of coal based
thermal power plant.
Though thermal efficiency and overall efficiency of thermal power plant is comparatively
less than other power plant like nuclear power plant but still it is very popular. The only
reason behind that, is coal. It is very cheap and easily available as well. Still, now maximum
energy is supplied by the coal-based thermal power plant
A Thermal Power Plant converts the heat energy of coal into electrical energy. Coal is
burnt in a boiler which converts water into steam. The expansion of steam in turbine
produces mechanical power which drives the alternator coupled to the turbine. Thermal
Power Plants contribute maximum to the generation of Power for any country.
Thermal Power Plants constitute 75.43% of the total installed captive and non-captive
power generation in India. In thermal generating stations coal, oil, natural gas etc. are
employed as primary sources of energy.
In a Sikka Thermal Power Station there are 3 Department working in electrical systems:
EMD – 1
EMD – 2
EMD – 3
4
Gujarat Technological University V.V.P. Engineering College
ABOUT COMPANY
5
Gujarat Technological University V.V.P. Engineering College
ABOUT COMPANY
Do’s
1. Only Authorized person should enter in Electrical Installation.
2. Before starting work on electrical panel always wear arc flash suit and
electrical hand gloves.
3. Check the gloves for leakage by inflating it and discard if damaged.
4. Use portable tools with 30mA ELCB/RCCB.
5. During welding ensure that earthing lead is connected to the job. In case of
electrical shock raise an alarm for help and use rescue hook to withdraw
the person from live conductor.
Don’t
1. Never work on electrical equipment without LC and work permit.
2. Do not operate VCS (Visual Cut-off Switch) when equipment is running.
3. Do not use damage/untested/unchecked portable tools.
4. Do not use gloves after expiry date.
5. Do not cross the arc flash protection boundary without proper PPE.
6. Do not carry out welding job during wet condition (rain or perspiration).
Main Plant
1. DM Water
2. Boiler
3. Main control room
4. Cooling tower
5. Turbine
6. Generator
7. Battery room
8. Air & Flue gas
9. ESP & Ash handling plant
6
Gujarat Technological University V.V.P. Engineering College
ABOUT COMPANY
Switchyard
1. Generator transformer
3. Station transformer
4. Interconnected transformer
6. Outgoing Feeder
7. Battery room
7
Gujarat Technological University V.V.P. Engineering College
ABOUT COMPANY
1. Wagon Tippler
2. Track Hopper
3. Paddle Feeder
4. Conveyer Belts
5. Stacker cum Reclaimer
6. Crusher House
7. Coal Yard
8. Coal Bunker
9. Coal Feeder
10. Coal Mills
11. Furnace
8
Gujarat Technological University V.V.P. Engineering College
ABOUT COMPANY
Air is taken from atmosphere action of forced draught (FD) fan and passes
on the furnace through air preheater. Flue gases are produced when coal is
combusted in the boiler. The flue gases after passing around boiler tubes and
superheater tubes in the furnace pass through an economizer and finally
through the air preheater before being exhausted to the atmosphere via
electrostatic precipitator (ESP) & chimney.
1. Fans
▪ Primary Air Fan
▪ Forced Draft Fan
▪ Induced Draft Fan
2. Air Preheater
3. Wind Box
4. Furnace
5. Super heater
6. Reheater
7. Economizer
8. Electrostatic Precipitator
9. Chimney
9
Gujarat Technological University V.V.P. Engineering College
ABOUT COMPANY
➢ Steam Cycle
➢ Turbine
• High Pressure Turbine
• Intermediate Pressure Turbine
• Low Pressure Turbine
➢ Steam Lines
➢ Condenser
10
Gujarat Technological University V.V.P. Engineering College
ABOUT COMPANY
❖ WATER CYCLE
❖ ELECTRICAL CYCLE
❖ GENERATOR
➢ Hydrogen gas is used to cool down the rotor.
➢ Lube oil is used to cool the bearings.
➢ DM water is used to cool the stator.
➢ Seal oil is used to prevent hydrogen leakage
➢ Seal oil coolers are present to cool the seal oil
➢ Hydrogen dryers are used which removes the moisture from hydrogen gas
and then is supplied to the generator.
➢ Clarified water in cooling tower is used to cool down the hydrogen gas.
11
Gujarat Technological University V.V.P. Engineering College
❖ GENERATOR SPECIFICATION
1. KW :250000
2. P.F: 0.85 lag
3. K.V.A: 294100
4. STATOR
• Volts: 16500
• Amps: 10291
5. ROTOR
• Volts: 299
• Amps: 2497
6. R.P.M: 3000
7. Hz: 50
8. Phase: 3
9. Conn: YY
10. Cooling type: Hydrogen
11. Gas pressure: 4 BAR
12. Insulation class: F
13. Types: THRI 108/44
14. Spec: IEC:34
15. Division: Haridwar
❖ GENERATING TRANSFORMER
GT #3 GT #4
320MVA 320MVA
16.5/235 KV 16.5/235 KV
❖ STATION TRANSFORMER
ST # 3 ST # 4
40 MVA 40 MVA
220/6.9 KV 220/6.9 KV
The Unit Auxiliary Transformer is the Power Transformer that provides power
to the auxiliary equipment of a power generating station during its normal
operation. This transformer is connected directly to the generator out-put by a
tap-off of the isolated phase bus duct and thus becomes cheapest source of power
to the generating station.
1. Lighting arrester
2. SF6 circuit breaker
3. Double break isolator
4. Double busbar
5. ½ breaker scheme
6. Insulator
7. Wave trap
8. CT & CVT
9. Earthing
10. Control room
11. Battery room
132 KV
• Bhatia
• Bhomiyavadar
• Jamnagar 2
• Dhrol
• RPL
• Naghedi
• ICT 2
• ICT 1
At present, thermal power generation accounts for approximately 70% of the total amount
of electricity produced around the world. However, thermal power generation, which uses
fossil fuels, causes more CO₂ emissions than other power generation methods. To reduce
CO emissions per unit power produced, Toshiba Group is developing next-generation
thermal power technologies aimed at improving plant efficiency and commercializing the
CO2 capture and storage system.
To improve the efficiency of thermal power generation, it is of vital importance that the
temperature of the steam or gas used to rotate the turbines is raised. Toshiba Group is
working on the development of ultra-high-temperature materials and cooling technologies
to commercialize an A-USC system (Advanced Ultra-Super Critical steam turbine
system) more efficient than previous models, which is designed to increase steam
temperature from 600°C to above the 700°C mark.