Forward and Backward Pass

The document summarizes the forward pass and backward pass of an activity network for a construction project. It lists 20 activities with their duration, predecessors, earliest start and finish times, latest start and finish times, total float, and free float calculated using the forward and backward pass algorithms. The forward pass is used to calculate earliest start and finish times while the backward pass calculates latest start and finish times.

Uploaded by

Nemo Secret
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views1 page

Forward and Backward Pass

The document summarizes the forward pass and backward pass of an activity network for a construction project. It lists 20 activities with their duration, predecessors, earliest start and finish times, latest start and finish times, total float, and free float calculated using the forward and backward pass algorithms. The forward pass is used to calculate earliest start and finish times while the backward pass calculates latest start and finish times.

Uploaded by

Nemo Secret
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SAMPLE COMPUTATION OF FORWARD PASS AND

BACKWARD PASS
activity ACTIVITY description Durati pred

previous activity
ES=largest EF o f
on in eces

LF=lowest LS of
days sor

FF=ESnext-EF
(D)

TF=LS-ES
EF=ES+D

LS=LF-D

prev
Early Ear Lat Lat To Fre
start ly e e tal e
fini sta fini flo flo
sh rt sh at at
Forward Backwar
pass d pass
1-2 A Ground beam excavation 1 start 0 1 0 1 0 0
2-3 B Fabrication and assembly of ground 2 A 1 3 1 3 0 0
beam reinforcement
2-4 C Fabrication and installation of ground 1 A 1 2 2 3 1 1
beam form work
2-5 D Fabrication and assembly of slab on fill 2 A 1 3 1 3 0 0
reinforcement
4-6 E Pouring of concrete delivered by transit 1 B,C, 3 4 3 4 0 0
mixers D
6-7 F 14 day curing 14 E 4 18 4 18 0
7-9 G Removal of formwork 1 F 18 19 23 24 5
2-8 H Fabrication of column and beam 3 A 1 4 21 24 20 20
formwork
2-11 I Fabrication of column and beam 3 A 1 4 21 24 20 20
reinforcement
7-10 J Scaffolding assembly 6 F 18 24 26 27 8
10-12 K installation of beam and column 2 J,H,I, 24 26 24 26 0
formwork G
12-13 L Pouring of concrete delivered by transit 1 K 26 27 26 27 0
mixers
13-14 M 14 day curing 14 L 27 41 27 41 0
14-15 N Removal of form and scaffold 2 M 41 43 41 43 0
7-15 O Delivery of steel, roofing and masonry 1 F 18 19 42 43 24
materials
15-19 P Steel truss fabrication and installation 7 O,N 43 50 50 57 7
19-18 Q Placing of corrugated GI sheet and 3 P 50 53 57 60 7
accessories
15-16 R Masonry works 8 N,O 43 51 43 51 0
16-17 S Window and door installation 4 R 51 55 51 55 0
17-18 T plastering 5 S 55 60 55 60 0
18-20 U Finishing works 7 T,Q 60 62 60 62 0