Unionmatex v. Turkmenistan
Unionmatex v. Turkmenistan
1
© 2021 Kluwer Law International, a Wolters Kluwer Company. All rights reserved.
International 2020, Volume and also claimed for contractual breaches pursuant to the umbrella clause. (4)
37 Issue 5) pp. 649 - 664
As Unionmatex GmbH was insolvent, the claimant engaged a third-party funder, La
Française, to fund its costs in the proceedings. Importantly, the funding agreement
explicitly provided that La Française would not be liable to the claimant for any adverse
costs order made in favour of the State.
On 20 August 2019, the State filed a request for security for costs of USD 3 million, to be
deposited into an escrow account or provided as a bank guarantee (‘Security for Costs
Application’). (5)
On 30 September 2019, the claimant opposed the Security for Costs Application and also
made a counter-application for security for the claimant’s costs and for the enforcement
of any final award in the amount of approximately EUR 45 million. (6)
On 27 January 2020, a majority of the Tribunal granted the Security for Costs Application
and summarily denied the claimant’s counter-application for security, (7) labelling the
latter application as unprecedented. (8)
2
© 2021 Kluwer Law International, a Wolters Kluwer Company. All rights reserved.
in RSM v. Saint Lucia, where Article 47 was successfully used to order a claimant to
provide security for costs. (15)
Tribunals have been reticent to order security for costs for such hypothetical rights in
particular because they are premised on (1) the State winning on the merits; and (2) the
tribunal finding special circumstances which mean the claimant should pay the State’s
costs. (16) RSM v. Saint Lucia overrode these issues, holding that the State had a right to
an enforceable order for costs should it ultimately prevail and be awarded costs (17) ; a
right which RSM v. Saint Lucia found to be self-standing, without a further inquiry
required.
As an aside, it is to be remembered, however, that the object of a security for costs
inquiry is to determine whether the State deserves interim relief. This then raises the
obvious question of whether tribunals are able to consider the State’s prospects of
receiving an adverse costs award in making its determination. Notably, investor-State
tribunals have not done this openly to date, despite recommendations from bodies such
as the Chartered Institute of Arbitrators that the prospects of success of the claim(s) and
defence(s) be taken into account by arbitrators when they determine security for costs
applications. (18)
3
© 2021 Kluwer Law International, a Wolters Kluwer Company. All rights reserved.
make clear that the existence of a funding agreement is not sufficient for a grant of
security, (36) in part, as the authors note, because third-party funding is increasingly used
by solvent companies that simply wish to share risk and maintain liquidity so that they
P 656 can sustain their regular business while arbitral proceedings are on foot. (37)
5 DECISION IN UNIONMATEX
The majority held that the State satisfied the first two requirements as set out in AR 39(1)
as it found (1) the State’s right to an enforceable order for costs was an eligible right to be
preserved; and (2) the State had outlined the measure necessary to protect that right,
specifically, security for costs. (38)
The majority’s focus (and where the anonymous dissenting arbitrator diverged) was on the
third element, being whether the necessary circumstances existed to justify an order for
security for costs. (39) The majority was open to considering all the circumstances in the
case, but, as outlined above, the majority’s decision focused on resolving the tension
between the State’s right to enforce a costs award in its favour and the claimant’s right to
access justice.
In resolving this tension the majority focused on whether there was any prejudice to the
State which favoured the order, and then considered whether any prejudice to the
claimant overrode the prejudice to the State, such that security for costs should not be
ordered.
5.1 Prejudice to the state if security for costs were not ordered
The majority held that practically it was ‘effectively impossible’ for the State to enforce
and collect upon any costs award in its favour, (40) and thus that the State would be
unduly prejudiced without an order for security for costs. (41) This finding was based on a
combination of three factors: (1) Unionmatex GmbH being insolvent; (2) the claim was
being funded by a TPF; and (3) the funding agreement expressly absolved the TPF of
responsibility for an adverse costs award. (42) Importantly, the majority expressly held
that reliance on third-party funding was not sufficient in and of itself to meet this
standard, (43) and further, that a party’s impecuniosity, in and of itself, was also not
sufficient to meet the exceptional circumstances standard. (44) The majority therefore
anchored their finding on the substantive terms of the funding agreement, and not the
existence of the funding agreement itself.
The dissenting arbitrator disagreed, expressing the view that it was ‘not appropriate [for
P 657 the majority] to conclude that Turkmenistan is certain not to recover its costs’ (45) if it
receives an award in its favour because (1) under German insolvency law, obligations
incurred after the opening of the bankruptcy proceedings take precedence over prior
obligations; and (2) Unionmatex GmbH’s balance sheet showed that it still had some
assets of value which may be able to fund a costs award in favour of the State. (46)
5.3 Resolving the tension between the state and the claimant
As above, the dissenting arbitrator found that security for costs should not be ordered as
there was a real risk that it would impede the claimant’s access to justice. (52) The
majority similarly held that it was ‘mindful not to impede a party’s right to bring a claim
before an international tribunal to seek redress for perceived wrongs’. (53)
Therefore, the case turned on the facts. The majority only ordered security for costs on
the basis that it would not impede the claimant’s access to justice; and the majority
expressly provided that it would reconsider its order if the claimant brought forward
P 658 evidence that it was financially incapable of posting security. (54) Thus, as a matter of
law, access to justice was not a clear point of difference between the arbitrators.
One point of difference that did emerge, however, was whether the Tribunal could take
into account the claimant’s allegation that the State was responsible for Unionmatex
GmbH’s impecuniosity. At paragraph 66 the majority stated:
In balancing the Parties’ competing prejudice claims, the Tribunal must ignore
4
© 2021 Kluwer Law International, a Wolters Kluwer Company. All rights reserved.
[the claimant’s] allegation that it is unreasonable for [the State] to obtain
security for costs when it was [the State] that allegedly caused the insolvency
of Unionmatex [GmbH].
The dissenting arbitrator disagreed, and remarked that the reason why Unionmatex
GmbH was insolvent cannot just be ‘ignored’ in a security for costs application when it is
alleged that it was the State’s breach of standards of international law which caused or
contributed to the insolvency. (55) The dissenting opinion also noted that the majority’s
judgment appeared internally inconsistent on this point, as the majority had previously
provided at paragraph 55 that:
A party’s impecunity, in and of itself, is not sufficient to meet the exceptional
circumstances standard. One reason is that a claimant may be able to prove
on the merits that the respondent wrongfully caused its financial difficulty.
It appears that the majority were of the view that the alleged cause of Unionmatex
GmbH’s impecuniosity was only a relevant factor to be considered in circumstances
where a tribunal had already found that a claimant could not afford to post security.
Conversely, it appears the dissenting arbitrator’s view was that allegations of the State’s
substantive conduct could be assessed as a stand-alone indicia when weighing the
prejudice between the parties, if the allegations made were not ‘entirely arbitrary’. (56)
6 CONCLUSION ON UNIONMATEX
The decision in Unionmatex represents the first time in ICSID proceedings that a tribunal
has ordered security for costs without finding a history of misconduct on the part of a
claimant (and only the third time security for costs has been ordered in investor-State
arbitration). Despite this result, it is important to note that the decision in Unionmatex
turned on its facts, and in particular (1) whether the claimant was capable of satisfying
the security conditions imposed by the majority; and (2) the terms of the third-party
funding agreement in place, namely, that the funder would not be liable to pay an
adverse costs order.
It should also be noted that the decision reinforces the principle that a tribunal must be
5
© 2021 Kluwer Law International, a Wolters Kluwer Company. All rights reserved.
‘mindful not to impede a party’s right to bring a claim before an international tribunal’,
(67) and that investors should be able to access justice, even if they do not have sufficient
financial standing to meet a possible costs award. (68)
In practical terms, there would appear to be two main lessons in the Unionmatex
decision:
– First, for a claimant investor opposing a security for costs application, it is
important not to allow the issue of access to justice to remain abstract or
hypothetical. Dr Herzig, as administrator of Unionmatex GmbH, stopped short of
declaring that the company would not be able to post security if it was ordered, and
as a result the majority of the arbitrators felt comfortable that the claimant would
not be denied access to justice if they granted Turkmenistan’s request.
– Second, claimant investors (and TPF) should take particular care in drafting the
terms of their funding agreements, as these terms may be the object of close
scrutiny in any future security for costs applications. In particular, the Unionmatex
decision represents the second time an investment tribunal has ruled that the fact
a funder has no liability to pay adverse costs is determinative in a security for costs
application (the first time being in the Armas case). A new line of authority may
therefore be emerging on this point, and thus investors should be aware of this risk
if they include such clauses in their funding contracts.
P 661
6
© 2021 Kluwer Law International, a Wolters Kluwer Company. All rights reserved.
nature of the claims asserted by a party as well as the requesting party’s non-
payment of advances on costs. Other comments suggested that the Tribunal be
required to take into account the cause of a party’s alleged inability to comply with
an adverse cost award, to address the concern that a party could be denied access
to justice by an order for security for costs if its impecuniosity is the result of
actions of the host State.
2. In practice, Tribunals have found that ‘abuse’ or ‘serious misconduct’ by a party
could weigh in favour of ordering that party to provide security for costs. On the
other hand, it is widely accepted that security for costs would not be appropriate
where a claimant’s impecuniosity is the result of the respondent’s actions. [AR 53(3)
(d)] is stated in broad terms to encompass any relevant conduct by either party.
In light of this explanation of AR 53(3)(d), when there is a case that a State has caused a
claimant’s impecuniosity, this should weigh against a tribunal ordering security for costs
under the new rule. Similarly, it is possible that, under AR 53(3)(d), Unionmatex may have
been decided differently. As the minority noted, it would be unreasonable for a State to
P 663 obtain security for costs where the State caused the claimant’s insolvency.
8 POSTSCRIPT
Subsequent to this article’s authorship, Global Arbitration Review (GAR) reported that on 9
June 2020 a majority of the Tribunal rescinded its order requiring security for costs to be
posted by the claimant. (73)
The report notes that the majority rescinded its order because it found that it would be
commercially impossible for Dirk Herzig to secure a USD 3 million bank guarantee, and
further, due to the terms of the funding agreement, even an after-the-event (ATE)
insurance policy for USD 1.5 million was not feasible.
GAR further reported that ‘the majority said that to deny Herzig an opportunity to
proceed to the merits of his claim – in circumstances where Turkmenistan’s actions are
alleged to be the cause of the company’s insolvency – would be to deny him access to
justice’, and for that reason the order for security for costs could not be maintained.
In practical terms, there would appear to be two main lessons from the Tribunal’s
decision to rescind its order:
– First, the order underscores that access to justice is the over-arching consideration
for tribunals, and will prevent an order of security for costs where such an order
would prevent a claimant from pursuing its claim – especially where it is alleged
that it was the State’s very actions that caused the claimant’s impecunity.
– Second, participants in the Investor-State dispute settlement (ISDS) process should
be aware that commercially it is very unlikely that impecunious investors will be
able to secure a bank guarantee on account of the investor’s risk profile. Further,
although ATE insurance policies may be available to investors, they are also
unlikely to be a viable option, as the commercial reality of TPF is that they will
likely cost the investor three to six times the insurance payout – which is patently
unfair to the investor, especially in the situation where it is alleged that the State
has caused the investor’s impecunity. This means that when requesting security for
costs, States should be aware that the higher the security requested the lower the
chances of the order being successful – where in Unionmatex, security of only USD
1.5 million was ultimately deemed to be too high by the Tribunal.
P 663
References
*) Associate, Clifford Chance, Perth Email: [email protected].
1) Dirk Herzig as Insolvency Administrator over the Assets of Unionmatex Industrieanlagen
GmbH v. Turkmenistan (ICSID Case No. ARB/18/35) (‘Unionmatex’), Decision on
Security for Costs on (27 Jan. 2020), paras 58, 65, 75, and 79.
2) Ibid., para. 83.
3) Ibid., para. 1.
4) Ibid., para. 2.
5) Ibid., paras 4 and 11.
6) Ibid., para. 5.
7) Ibid., para. 84.
8) Ibid., para. 68.
9) See Emilio Agustín Maffezini v. Kingdom of Spain (ICSID Case No. ARB/97/7), Decision on
Request for Provisional Measures (28 Oct. 1999), para. 8; most recently applied in
Nova Group Investments, B.V. v. Romania (ICSID Case No. ARB/16/19), Procedural
Order No. 7 Concerning the Claimant Request for Provisional Measures (29 Mar. 2017),
para. 228.
7
© 2021 Kluwer Law International, a Wolters Kluwer Company. All rights reserved.
10) S. Luttrell, ICSID Provisional Measures ‘In the Round’, 31 Arb. Int’l 393, at 397 (2015); S.
Luttrell, The ICSID Convention, Regulations and Rules – A Practical Commentary (2019),
para. 25.07.
11) S. Luttrell, Observations on the Proposed New ICSID Regime for Security for Costs, 26(3)
J. Int’l Arb. 388 (2019).
12) Unionmatex, supra n. 1, paras 51–53.
13) Ibid., para. 67.
14) See e.g. Maffezini v. Spain, supra n. 9, para. 13.
15) RSM Production Corp. v. Saint Lucia (ICSID Case No. ARB/12/10), Decision on Saint
Lucia’s Request for Security for Costs (13 Aug. 2014), paras 65–66.
16) Maffezini v. Spain, supra n. 9, para. 17.
17) RSM v. Saint Lucia, supra n. 15, paras 65–66.
18) See CIArb’s International Arbitration Practice Guidelines on Applications for Security for
Costs, Art. 1, https://www.ciarb.org/media/4196/guideline-5-security-for-costs-
2015.pdf (accessed 8 Apr. 2020).
19) See Burlington Resources Inc. v. Republic of Ecuador (ICSID Case No. ARB/08/5),
Procedural Order No. 1 on Burlington Oriente’s Request for Provisional Measures (29
June 2009), para. 81; most recently applied in Nova v. Romania, supra n. 9, paras 238–
242. For a detailed discussion, see Luttrell, supra n. 10, para. 25.49.
20) In addition to Unionmatex, supra n. 1, para. 50, see also EuroGas v. Slovak Republic,
infra n. 29, para. 121 and Sergei Viktorovich Pugachev v. Russian Federation, UNCITRAL,
Interim Award (17 July 2017), para. 377. In the context of annulment proceedings, see
also Commerce Group Corp. & San Sebastian Gold Mines, Inc. v. Republic of El Salvador
(ICSID Case No. ARB/09/17), Decision on El Salvador’s Application for Security for
Costs (20 Sept. 2012).
21) See RSM v. Saint Lucia, supra n. 15, para. 27.
22) Ibid., para. 90.
23) See ibid., Assenting Decision of Gavan Griffith, para. 15.
24) Manuel García Armas et al v. Bolivarian Republic of Venezuela (PCA Case No. 2016–08),
Procedural Order 9, Decision on Respondent’s Request for Provisional Measures (20
June 2018).
25) Ibid., para. 250.
26) See EuroGas v. Slovak Republic, infra n. 29, para. 120; RSM Production Corp. v. Grenada
(ICSID Case No. ARB/10/6), Tribunal’s Decision on Respondent’s Application for
Security for Costs (14 Oct. 2010), para. 5.19; Lighthouse Corp. Pty. Ltd. & Lighthouse
Corp. Ltd., IBC v. Democratic Republic of Timor-Leste (ICSID Case No. ARB/15/2),
Procedural Order No. 2 − Decision on Respondent’s Application for Provisional
Measures (13 Feb. 2016), para. 60; Víctor Pey Casado Fondation Président Allende v. la
République du Chili, Affaire CIRDI/ARB/98/2, Decision on Provisional Measures on 25
Sept. 2001, para. 86.
27) RSM v. Grenada, supra n. 26, para. 5.19.
28) Lao Holdings N.V. v. Lao People’s Democratic Republic (ICSID Case No. ARB(AF)/16/2),
Procedural Order No. 6, Decision on Respondent’s Application for Security for Costs of
(26 June 2018), n. 76.
29) EuroGas Inc. & Belmont Resources Inc. v. Slovak Republic (ICSID Case No. ARB/14/14),
Procedural Order No. 3 – Decision on the Parties’ Requests for Provisional Measures
(23 June 2015).
30) Ibid., para. 121.
31) Ibid.
32) South American Silver Ltd. v. Bolivia (PCA Case No. 2013–2015), Procedural Order No. 10
(11 Jan. 2016).
33) Ibid., para. 74.
34) Ibid., para. 63.
35) International Counsel for Commercial Arbitration, in Report of the ICCA-Queen Mary
Task Force on Third-party Funding in International Arbitration Ch. 6, 176–183 (S.
Brekoulakis, A. Sheppard QC, S. Dunn, M. Smith & J. Göler eds, Apr. 2018).
36) Ibid., at 176.
37) Ibid., at 180.
38) Unionmatex, supra n. 1, para. 52.
39) Ibid., para. 53.
40) Ibid., para. 58.
41) Ibid., para. 63.
42) Ibid., paras 58 and 59.
43) Ibid., para. 54.
44) Ibid., para. 55.
45) Ibid., para. 74.
46) Ibid., para. 73.
47) Ibid., para. 65.
48) Ibid., para. 65.
49) Ibid., para. 83.
50) Ibid., para. 76.
51) Ibid., para. 77.
52) Ibid., paras 79–83.
53) Ibid., para. 64.
8
© 2021 Kluwer Law International, a Wolters Kluwer Company. All rights reserved.
54) Ibid., para. 65.
55) Ibid., para. 77.
© 2021 Kluwer Law International, a Wolters Kluwer Company. All rights reserved.
Kluwer Arbitration is made available for personal use only. All content is protected by copyright and other intellectual property
laws. No part of this service or the information contained herein may be reproduced or transmitted in any form or by any means, or
used for advertising or promotional purposes, general distribution, creating new collective works, or for resale, without prior
written permission of the publisher.
If you would like to know more about this service, visit www.kluwerarbitration.com or contact our Sales staff at lrs-
[email protected] or call +31 (0)172 64 1562.
KluwerArbitration
9
© 2021 Kluwer Law International, a Wolters Kluwer Company. All rights reserved.