Contractor Safe Work Method Statement
Contractor Safe Work Method Statement
Contractors must complete a Safe Work Method Statement (SWMS) prior to commencing the contract work if the
contract work involves high risk construction work (refer to the WHS Construction Activities Guidance Checklist
(Document No. 12.3.35.13.1) if high risk construction work is being undertaken to check legislative requirements
are met).
A SWMS sets out the work activities in a logical sequence and identifies hazards and describes control measures.
The description of the process should not be so broad that it leaves out activities with the potential to cause
accidents and prevents proper identification of the hazards, nor is it necessary to go into fine detail of the tasks.
The SWMS must be able to be easily read by those who need to know what has been planned to manage the risks,
implement the control measures and ensure the work is being carried out in accordance with the SWMS.
Relevant persons include the:
(a) Supervisor of the high risk construction work
(b) Worker carrying out the high risk construction work
(c) Principal Contractor (if it is a construction project) or the person who has management and control over the
high risk construction work.
(d) If the risk still remains, minimise the remaining risk by implementing administrative controls i.e.
establish policies, procedures & work practices, provide training
(e) If the risk still remains, minimise the remaining risk by ensuring the provision and use of suitable
personal protective equipment (PPE).
High Risk Construction Work: ☐ Risk of a person falling more than 3 metres ☐ Work in an area with movement of powered mobile plant ☐ Demolition of load-bearing structure
[as defined by the Work Health & ☐ Likely to involve disturbing asbestos ☐ Work on or near chemical, fuel or refrigerant lines ☐ Work in or near a confined space
Safety Regulations 2012 (291)] ☐ Work on a telecommunication tower ☐ Work in areas with artificial extremes of temperature ☐ Diving work
☐ Work on or near pressurised gas mains or ☐ Involves structural alterations or repairs that require ☐ Use of explosives
piping temporary support to prevent collapse
☐ Work on or near energised electrical ☐ Work in or near water or other liquid that involves a risk ☐ Tilt-up or precast concrete elements
installations or services of drowning
☐ Work on, in or adjacent to a road, railway or ☐ Work in an area that may have a contaminated or ☐ Work in or near a shaft or trench deeper than
other traffic corridor in use by traffic other flammable atmosphere 1.5 m or a tunnel
than pedestrians
Person Responsible for ensuring Date SWMS Received:
compliance with SWMS
What measures are in place to ensure
compliance with the SWMS?
Person(s) Responsible for reviewing the Date SWMS Received by Reviewer:
SWMS
How will SWMS control measures be
reviewed?
Review Date: Reviewer’s Signature:
What are the tasks involved? What are the hazards and risks? What are the control measures?
(What is the problem?) (Describe the control measures and how they will be used)
Think about the workplace and each stage of the work, including preparation and clean-up.
List the work tasks in a logical order Identify the hazards and risks that may SWI # to be followed Describe what will be done to control the risk. What will you do to make the
cause harm to workers or the public. activity as safe as possible?