Building 261
Building 261
(a) The data from a survey, are shown below. Use either the Rise and Fall method or the Height of
Plane of Collimation (HPC) method to reduce the data. Use arithmetic checks to support your answer
TBM 43.000, Level readings: 0.771, (1.552, 0.802), 2.311, (1.990, 3.580), 1.220, 3.675, (4.020, 2.408),
0.339, 0.157
Question 2:
The following readings were taken with a level and 4 m staff. Draw up a level book page and reduce
the levels by both the Rise and Fall method and the height of instrument method. Show your
computations and checks.
0.578 B.M.(= 58.000 m), 0.933, 1.768, 2.450, (2.265 and 0.560) C.P., 1.888, 1.181, (3.579 and 0.616)
C.P., 0.705, 1.810
Question 3:
(c) Three groups carried out a levelling survey. The measurements of the elevation of the same point
are shown in the following tables for each group. The true elevation of the point measured is
+50.000m. Describe the results of each group in terms of accuracy and precision.
Question 4:
The angles at the stations of a closed traverse ABCDEFA were observed as given below:
Question 5:
A closed-loop traverse ABCDA was run around an area and the following observations were made:
Length A-B = 177.5m, included angle at A = 86°30′03″ and Azimuth AB = 140°11′39″. Length BC =
386.7, included angle at B = 80°59′36″. Length CD = 116.1m and included angle at C= 91°31′27″.
Length DA = 360.8 and included angle at D = 100°59′15″.
Adjust the angular error, if any, and calculate the coordinates of other stations if the coordinates of
the station A are E1500 m and N1500 m.
Question 6:
The data given in Table below, were obtained for an anti-clockwise closed-loop traverse. The
coordinates of the station A are E1000 m and N1000 m. Determine the correct coordinates of all the
traverse stations after adjusting the traverse by