Method Statement For Earthworks Sample
Method Statement For Earthworks Sample
i
Project:
Contractor:
Title:
1. Objective
This procedure provides a standardised framework for the control of excavation, earthwork and
filling to ensure compliance with conditions of contract and contract specifications. All excavation,
earthwork and filling will be carried out in accordance with the specification detailed in the project
contract documentation.
In any circumstances where specifications are not provided or they are in any way incomplete,
the matter shall be referred back to consultant for additional information.
2. Resources
Contractor shall employ the following machineries for the purpose of this work. Refer to enclosed
catalogue.
i. Hydraulic Excavator DX225LCA - Refer to Appendix 1.
ii. Hydraulic Excavator SH330-5 - Refer to Appendix 2.
iii. Tractor Ford 661O - Refer to Appendix 3.
iv. Vibratory Compacting Roller Sakai SV90 - Refer to Appendix 4.
v. Vibratory Compacting Roller Volvo SD100DC - Refer to Appendix 5.
vi. 10-Wheeler Lorry.
vii. Bulldozer.
3. Land Surveying
Prior to any commencement of any physical works, professional land surveyor shall be appointed
to carry out demarcation works and establish a few temporary bench marks (TBM) on site. Upon
obtaining all necessary survey data and clearing of site, a joint survey shall be conducted with
consulting engineer to check and confirm existing ground levels (OGL).
Contractor:
Title:
D
during earthworks
>
Form platform to receive Construct metal hoarding
metal hoarding along site along site boundary facing
boundary facing Taman Taman Krubong Perdana. 1
Krubong Perdana. Refer Attachment A.
n
Construct project signboard. 2
>
Construct wash trough and
washing bay at platform level
as per construction drawing
no. CM224/STD/EW/002.
Refer Attachment C.
1. Subjected to all necessary approvals.
2. Subjected to all necessary approvals.