URS For Carton Packing Machine
URS For Carton Packing Machine
PRODUCTION DEPARTMENT
PROTOCOL No. :
Page 1 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
Page 2 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
Production
Production
Quality Assurance
Engineering
Head Engineering
Head Manufacturing
Head Quality
Page 3 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
The purpose of this document is to ensure that all the critical aspects of the Equipment, cGMP & Safety
features have been considered in designing the equipment/instrument and is properly documented.
3.0 Responsibilities:
In accordance with the document, following functions shall be responsible for initiation and finalization of
Equipment user requirement specification. When the work is carried by contract/ consulting staff, all the work
is to be performed under the oversight of …………….
• To be reviewed by Head of the user department and functional department ( Engineering & Quality assurance)
4.2 Purpose:
Purpose of equipment is to carry out the Carton packing in oral Packing area .
Page 4 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
13. Requirements for any power failure To be backed up by installed in-house DG set.
backup’s (In case of
Equipment /Instrument)
Page 5 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
Page 6 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
6.1 Training
6.2.1 The System or its parts as provided for in the scope of supply YES
shall be pre-installed at the vendors shop prior to delivery to
customer site. Installation will be completed and documented
including mechanical parts as well as electrical connections
of all parts to facilitate taking over tests at Vendors shop
prior to delivery.
• Spare part list List of spares required for smooth operation will
be
provided by the Vendor at the time of ordering.
Page 7 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
8.1 In accordance with cGMP guidelines the units must be easy to clean, to disinfect, and where necessary, to
sterilize.
8.2 The Supplier should guarantee that, if required, a service team can be on site within one working day.
8.3 The design should be such as to allow mechanical cleaning of the surface and that the cleanliness of the
surface can be checked easily.
8.4 All machine parts, in particular instrumentation, should be constructed so that they can be easily removed and
calibrated.
8.5 All special tools required for running and maintenance should be best.
Page 8 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
10.1 Units described in the specific system requirements including all necessary controls YES
and instrumentation.
10.2 The complete mechanical and electrical installation. YES
10.3 The Connections to all the necessary utilities, exhaust, and waste lines necessary for Yes
its operation.
10.4 All piping and cabling of the units itself. YES
10.5 Wiring and cable run: all wiring and cable run is part of the supply. ……………….. YES
will supply the main power switches to be located in correspondence to the electrical
and control cabinets delivered by the equipment supplier.
10.6 All internal contacts of the supplied equipment for the required utilities. YES
10.7 Unload on site of the equipment: the supplier is required to define all the necessary YES
handling devices required to the unloading operation.
The supplier will inform at least 4 weeks in advance the day of delivery and the list of
required handling devices.
10.8 Assembling operation: the required consumable, the internal transportation, the YES
assembling tools and the required personal are part of the supply.
10.9 A complete set of commissioning spare parts. YES
10.10 All special tools necessary for use and maintenance of the supplied equipment. YES
10.11 A complete set of two years spare parts should be listed quoted and offered as option. YES
11.1 General
11.1.1 The Contractor must specify for each piece of equipment the Guaranteed YES
performance and the guaranteed system performance. These values will be tested
during the acceptance tests.
11.1.2 In addition the functionality described in the user requirements and detailed in the YES
system specifications will be tested.
Page 9 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
11.2.1 The commissioning tests will be carried out in accordance with a written test plan YES
developed by the supplier with clearly stated test procedures and acceptance criteria.
11.2.2 The contractor will approve successfully completed tests and will specify items YES
requiring additional work. Representatives from …………… Will attend and
participate in the commissioning tests as required.
11.2.3 The installation and commissioning of the system will be performed at the YES
………………… Facility by the contractor.
11.2.4 The commissioning can only start once all the foreseen documents have been YES
delivered by the supplier to ……………………
11.2.5 All equipment should be properly installed, adjusted, leveled, tagged, and connected YES
with utilities.
11.2.6 Point to point checks on wiring and pneumatic should be performed. YES
11.2.8 A equipment ( instrument) used for qualification must be listed and approved by YES
………………………
11.2.9 The calibration equipment must have all the necessary documents to demonstrate YES
their maintenance & use.
11.2.10 The last calibration of all this equipment must be less than 6 months old, and YES
evidenced by certificate.
11.2.11 Verification that the interior surfaces of equipment are free of practices and dirt and YES
all points of product contact meet the specified material requirements.
11.2.12 All the clearances and tolerances specified in the drawing or recommended by YES
component manufacturers are correct.
11.2.13 On site verification that valves and other equipment with moving parts are in their YES
normal position if in a power down condition and move in the correct direction with
the correct speed and precision.
11.2.14 Verification that all the Input and Output points are connected and labeled according YES
to the documentation and that all the along the input values have been scaled in
accordance with the system specification and process requirements. That all
equipment components requiring configuration
11.2.15 The commissioning should demonstrate that the system supplied by the contractor YES
has been properly installed and that the functions are in accordance with
Page 10 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
11.3.1 This test will be carried out once the commissioning will be completed. The scope YES
will be to verify the performance and the functionality of the system integrated with
the other factory systems (Including sterility testing of at least 02 days).
11.3.2 The test will be carried out to verify the system response with the expected YES
productivity of the system.
11.3.3 Details on the test realization will be defined during the project Phase. The supplier YES
is asked to specify the proposed duration for SAT and the standard procedure
proposed.
11.3.4 During SAT the required functionality, performances and system reliability are met. YES
11.3.5 The Functionality described in the User Requirements Specification and in the YES
System Specifications are verified and met.
11..3.6 All the documentation agreed has been delivered. YES
12.1 The maintenance Qualification is responsibility of the customer. However, the YES
supplier is responsible for delivering the basic documents for maintenance
qualification.
12.2 This includes all side costs such as : calibration measuring equipment and YES
instruments: manpower (IQ and OQ will take place completely on ………………
12.3 Time Schedule for IQ/OQ execution will be developed by ……………. With the YES
supplier.
12.4 Suppliers personnel used for IQ/OQ must be well trained and experienced. This YES
should be documented.
12.5 The onsite test run performed by the supplier might become part of the IQ. YES
12.6 Main IQ/OQ steps such as calibration must be performed and documented in YES
accordance to a SOP approved by ………………….
12.7 All equipment used for qualification must be listed and approved by …………… YES
The calibration equipment should be well documented.
12.8 The last Recalibration of all this equipment should be less than 06 month old. YES
Proofed by Certificate.
12.9 OQ can only start after IQ approved by …………………. YES
12.10 IQ will be carried out by ……………….. During Installation phase. IQ will include YES
the tests performed by the contractor.
12.11 Part of the OQ will be carried out by ……………. During commissioning and SAT YES
phase. OQ will include the tests performed by the contractor.
12.12 After installation of the equipment at customers site. Complementary IQ & OQ tests YES
will be performed by the Customer and may be supervised by a member of
Page 11 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
Technical staff.
13.0 GAURANTEE/WARRANTEE
14.1 The System must be guaranteed including all the sub- system and components for a YES
period of 12 months from the date of the system acceptance for a 03- shift operation.
14.2 The servicing companies involved for the Sub- systems maintenance must be YES
declared and the maintenance group organization described. Furthermore, the
contractor will be directly responsible of the system assistance and the required
operation will be co- ordinate by him.
14.3 In case of failures, the intervention will be guaranteed by the contractor within a YES
maximum time limit. The contractor is asked to specify the maximum time limit.
14.4 The supplier is asked to propose as option maintenance and assistance contract after YES
the guarantee expiration.
Page 12 of 12