Final EIA Report of Netrakona EZ
Final EIA Report of Netrakona EZ
The Center for Environmental and Geographic Information Services (CEGIS) would like to
express its heartfelt thanks and gratitude to Mr. Paban Chowdhury, Executive Chairman
(Secretary), Bangladesh Economic Zones Authority (BEZA) for awarding the assignment of
Consultancy Services titled “Environmental Impact Assessment (EIA) Study of Netrokona
Economic Zone” Project.
CEGIS is also grateful to Mr. Ashoke Kumar Biswas (Additional Secretary), Executive
Member (Planning & Development), Mr. Md. Moniruzzaman, Joint Secretary (General
Manager, Investment Promotion) and Doyananda Debnath, Deputy Chief Manager (MIS &
Research) and Project Director, for extending their cordial cooperation and continuous
guidance to the Study Team from the very beginning in conducting the study. CEGIS is very
thankful to Dr. Tanveer Ahmed (Environment Specialist), Mr. Md. Abdul Quader Khan
(Social Consultant) and Md. Ashraful Islam (Legal Consultant) for their valuable support.
The EIA Team of CEGIS express its gratitude to the District Commissioner (DC), Netrokona
District, and Upazila Nirbahi Officer, Netrokona Sadar for their all-out cooperation during the
field visit and consultation process. The Team is also grateful to all respondents
/stakeholders for providing valuable data/information and participation in the group
discussions and consultation meetings.
i
ii
Table of Contents
Acknowledgements ............................................................................................. i
List of Tables ................................................................................................... viii
List of Figures .................................................................................................... x
Abbreviations and Acronyms ........................................................................... xiii
Executive Summary ......................................................................................... xix
1. Introduction ................................................................................................. 1
1.1 Background ............................................................................................... 1
1.2 Project Brief .............................................................................................. 2
1.3 Rationale of the Project .............................................................................. 7
1.4 Scope of the Study ................................................................................... 10
1.5 EIA Study Team ....................................................................................... 10
1.6 Report Structure ...................................................................................... 11
2. Policy, Legal and Administrative Framework .............................................. 13
2.1 Introduction ............................................................................................ 13
2.2 Procedure for Environmental Clearance Certificate ....................................... 13
2.3 Organizations Related with Enforcement of Environmental Standards ............. 14
2.4 National Legislations Relevant to Environment ............................................. 15
2.5 National Legislations Relevant to the Project (Other than Environment) .......... 16
3. Approach and Methodology ........................................................................ 23
3.1 EIA Process and Approach ......................................................................... 23
3.1.1 Project Desgn and Description ............................................................ 23
3.1.2 Policies and Legal Issues ................................................................... 24
3.1.3 Environmental and Social Baseline ...................................................... 24
3.1.4 Important Environmental and Social Component (Scoping) .................... 27
3.1.5 Bounding ......................................................................................... 27
3.1.6 Impact Assessment and Mitigation ...................................................... 29
3.1.7 Environmental Management and Monitoring Plan .................................. 31
3.1.8 Public Consultations and Disclosure .................................................... 31
4. Project Description ..................................................................................... 33
4.1 Introduction ............................................................................................ 33
4.2 Project Objective and Expected Benefits ..................................................... 33
4.3 Project Components and Activities ............................................................. 34
4.4 Master Plan of Netrokona EZ ..................................................................... 34
4.4.1 Layout and Zoning ............................................................................ 34
iii
4.4.2 Plots and General Land Use and Landscape Regulation .......................... 38
4.4.3 Parking and Traffic Management Regulations ....................................... 38
4.4.4 Entry and Gate System ..................................................................... 39
4.4.5 On-site Infrastructure ....................................................................... 39
4.4.6 Land Development by earthfilling ....................................................... 52
4.4.7 Off-site Infrastructure ....................................................................... 52
4.4.8 Utility Demand and Sources ............................................................... 53
4.4.9 Project Cost ..................................................................................... 55
4.4.10 Investment Plan ............................................................................... 55
5. Alternative Analysis ................................................................................... 57
5.1 Introduction ............................................................................................ 57
5.2 “No Action” Alternative ............................................................................. 57
5.3 Evaluation of Alternative Site..................................................................... 57
6. Environmental and Social Baseline ............................................................. 59
6.1 Introduction ............................................................................................ 59
6.2 Physical Environment ............................................................................... 59
6.2.1 Meteorology and Climate ................................................................... 59
6.2.2 Topography ..................................................................................... 63
6.2.3 Ambient Noise Level ......................................................................... 63
6.2.4 Ambient Air Quality .......................................................................... 67
6.2.5 Surface Water Hydrology ................................................................... 68
6.2.6 Groundwater Hydrology .................................................................... 78
6.2.7 Drought .......................................................................................... 85
6.2.8 Surface Physiography and Geology ..................................................... 85
6.2.9 Seismic Analysis ............................................................................... 86
6.3 Biological Environment ............................................................................. 88
6.3.1 The Bio-ecological Zone .................................................................... 88
6.3.2 Ecosystem ....................................................................................... 90
6.3.3 Fisheries Resources .......................................................................... 95
6.3.4 Agriculture..................................................................................... 100
6.3.5 Livestock and Poultry ...................................................................... 116
6.4 Socio-economic Resources ...................................................................... 118
6.4.1 Demographic Profile........................................................................ 118
6.4.2 Land Price ..................................................................................... 119
6.4.3 Employment and Livelihood ............................................................. 120
6.4.4 Literacy Rate ................................................................................. 121
6.4.5 Household Income and Expenditure .................................................. 122
6.4.6 Poverty ......................................................................................... 122
6.4.7 Standard of Living .......................................................................... 122
iv
6.4.8 Communication System ................................................................... 125
6.4.9 Social Conflicts ............................................................................... 126
6.4.10 Archeological Sites and Cultural Heritage ........................................... 126
6.4.11 Ethnic Community, Religion and Culture ............................................ 127
7. Identification and Analysis of Key Environmental Issues ......................... 129
7.1 Introduction .......................................................................................... 129
7.2 Environmental Sensitivity Investigation .................................................... 129
7.3 Environmental Asset ............................................................................... 129
7.4 Environmental Hotspots .......................................................................... 132
7.5 Impact Screening ................................................................................... 132
8. Environmental and Social Impacts ........................................................... 135
8.1 Introduction .......................................................................................... 135
8.2 Impacts during Pre-construction Phase ..................................................... 135
8.2.1 Physical Environment ...................................................................... 135
8.2.2 Biological Environment .................................................................... 135
8.2.3 Socio-economic Environment ........................................................... 136
8.3 Impacts during Construction Phase .......................................................... 136
8.3.1 Physical Environment ...................................................................... 136
8.3.2 Biological Environment .................................................................... 138
8.3.3 Socio-economic environment ........................................................... 140
8.4 Impacts during Operation Phase .............................................................. 141
8.4.1 Physical Environment ...................................................................... 141
8.4.2 Biological Environment .................................................................... 144
8.4.3 Socio-economic Environment ........................................................... 145
8.5 Impact Evaluation .................................................................................. 146
9. Environmental and Socio-economic Impact Mitigation Measure ............... 151
9.1 Environmental Impact and Mitigation Plan during Pre-Construction Phase ..... 151
9.2 Socio-Economic Impact and Mitigation Plan during Pre-Construction Phase ... 152
9.3 Environmental Impact and Mitigation Plan during Construction Phase ........... 153
9.4 Socio-Economic Impact and Mitigation Plan during Construction Phase ......... 160
9.5 Environmental Impact and Mitigation Plan during Operation Phase ............... 164
9.6 Socio-Economic Impact and Mitigation Plan during Operation Phase ............. 172
10. Public Consultation and Disclosure .......................................................... 175
10.1 Introduction .......................................................................................... 175
10.2 Objectives and Purpose of Stakeholder Consultation ................................... 175
10.3 Identification of Stakeholders .................................................................. 175
10.4 Approach and Methodology ..................................................................... 176
v
10.5 Major Problems and Suggested Measures .................................................. 176
11. Environmental and Social Management Plan ............................................ 181
11.1 Introduction .......................................................................................... 181
11.2 Objective of Environmental and Social Management Plan ............................ 181
11.3 Management Responsibility/Inclusion of EMP in Contract Documents ............ 181
11.4 Environmental Code of Practices .............................................................. 182
11.5 ESMP during Pre-construction .................................................................. 182
11.6 ESMP during Construction ....................................................................... 185
11.7 ESMP during Operation Phase .................................................................. 190
11.8 Special Environmental and Social Management Plan ................................... 197
11.9 Environmental and Social Management (ESMP) Cost .................................. 204
12. Disaster Impact, Hazard and Risk Assessment ......................................... 209
12.1 Introduction .......................................................................................... 209
12.2 Hazard Identification and Risk Assessment Process .................................... 209
12.3 Natural Disasters and Risk Management ................................................... 209
12.4 Climate Change Impact and Vulnerabilities ................................................ 212
12.4.1 Historical Climatic Trends ................................................................ 212
12.5 Future Climate Projection and Impacts of Climate Changes ......................... 214
12.5.1 Future Temperature and Rainfall Projections ...................................... 214
12.5.2 Flash Flood .................................................................................... 215
12.5.3 Monsoon Flood ............................................................................... 216
12.5.4 Hailstorm ...................................................................................... 219
12.5.5 Drought ........................................................................................ 219
12.5.6 Cold Snap ...................................................................................... 219
12.6 Emission of Short Lived Climatic Pollutant ................................................. 220
12.7 Climate Change Adaptation and Mitigation ................................................ 221
12.8 Technological Disasters and Risk Management ........................................... 222
12.9 Occupational Hazard and Safety .............................................................. 222
12.10 Emergency Management Strategy ........................................................... 231
12.10.1 On-site Emergency Response Plan .................................................... 231
12.10.2 Communication Plan ....................................................................... 231
12.10.3 Emergency Evacuation .................................................................... 232
12.10.4 Emergency Response Organization ................................................... 232
13. Environmental and Social Monitoring Plan ............................................... 235
13.1 Monitoring Plan ...................................................................................... 235
13.1.1 Compliance Monitoring .................................................................... 235
13.1.2 Impact Monitoring during Construction .............................................. 235
vi
13.1.3 Independent/External Monitoring...................................................... 235
13.2 Implementation of Environmental Monitoring Plan ...................................... 246
13.2.1 Responsible Agency ........................................................................ 246
13.3 Action during Emergent Operation ........................................................... 247
13.4 Performance Indicators ........................................................................... 247
13.5 Reporting and Feedback Mechanism ......................................................... 248
13.6 Budgets for Monitoring ........................................................................... 248
13.7 Organogram and Staffing for Ensuring ESMP and Environmental Monitoring .. 249
14. Conclusions and Recommendations ......................................................... 251
References ..................................................................................................... 253
Appendix I: Matrix of Comments and Reponses on the Draft Report .............. 255
Appendix II: Approved ToR and Exemption of IEE ......................................... 261
Appendix III: Participants List ....................................................................... 265
Appendix IV: Photographs of the Stakeholder Consultation Meetings ............ 269
Appendix V: Environmental Code of Practices ................................................ 271
Appendix VI: Scanned Copy of Surface Water Test Results ............................ 297
Appendix VII: Scanned Copy of Ground Water Test Results ........................... 303
vii
List of Tables
viii
Table 6.23: Major Diseases of Livestock and Poultry in Study Area .......................... 118
Table 6.24: Demographic Profile ......................................................................... 118
Table 6.25: Dependency Ratio in the Study Area ................................................... 119
Table 6.26: Land Price for Some Specific Location ................................................. 120
Table 6.27: Connectivity and Surroundings of Proposed Project Site ........................ 126
Table 7.1: Activity-wise Impacts Screening .......................................................... 133
Table 8.1: Impact Evaluation .............................................................................. 148
Table 10.1: Stakeholders Involved into the Project ................................................ 176
Table 10.2: Location of Consultation and Discussion during the Field Visit ................ 176
Table 10.3: Major Problems and Suggested Solution by the Stakeholders ................. 178
Table 11.1: Proposed livelihood restoration program ............................................. 184
Table 11.2: Cost for Environmental and Social management Plans .......................... 205
Table 12.1: Summary of the Natural Disaster, their Consequences and Management . 210
Table 12.2: Annual Average Temperature Anomalies in the North-East Bangladesh ... 215
Table 12.3: Prediction for Change in Seasonal Maximum and Minimum Temperature . 215
Table 12.4: Annual Average Rainfall Anomalies in the North-East Bangladesh ........... 215
Table 12.5: Prediction for Change in Seasonal Rainfall ........................................... 215
Table 12.6: Summary statistics of the flood extents (% area inundated) in pre-monsoon
period (Year 2005 – 2017) ................................................................................. 216
Table 12.7: Hazards and Risk Assessment ............................................................ 223
Table 12.8: Occupational Hazards and Safety ....................................................... 225
Table 13.1: Environmental Compliance Monitoring Plan .......................................... 236
Table 13.2: Impact Monitoring Plan ..................................................................... 243
Table 13.3: Environmental Compliance Monitoring Cost ......................................... 248
Table 13.4: Investment Cost of Environmental Monitoring ...................................... 249
Table 13.5: Cost of Independent Monitor ............................................................. 249
ix
List of Figures
x
Figure 6.7: Topography of Bangladesh and Digital elevation map of the project area ... 63
Figure 6.8: Noise Level monitoring Sites ................................................................ 66
Figure 6.9: Sensitive receptors around the project area ........................................... 67
Figure 6.10: River and canal network around the project area .................................. 69
Figure 6.11: Water Discharge Simulated Data of Kangsha and Mogra Rivers ............... 70
Figure 6.12: Water Level Hydrographs for 10 Year Return Period at Jaria-Jhanjail and
Mohanganj Station (Kangsha River) ....................................................................... 71
Figure 6.13: Maximum-minimum Water Level at Jaria-Jhanjail and Mohanganj Station
(Kangsha River) .................................................................................................. 71
Figure 6.14: Water Level Hydrographs for 10 Year Return Period and Maximum-minimum
Water Level at Atpara Station (Mogra River) ........................................................... 71
Figure 6.15: Existing Water Management Infrastructure within the Study Area ........... 73
Figure 6.16: Thakurakona and Krishnapur Sluice Gate ............................................. 74
Figure 6.17: Physical Conditions of the Sluice Gates ................................................ 74
Figure 6.18: Area Elevation Curve of the Project Area .............................................. 75
Figure 6.19: Surface Water Quality Monitoring Sites ................................................ 77
Figure 6.20: Borelog Characteristics and Specific Yield at Depths under Ground Level of
Netrokona Sadar ................................................................................................. 80
Figure 6.21: Depth of Dry-period Groundwater and Difference between Potential and Net
Recharge of Groundwater of Bangladesh ................................................................ 81
Figure 6.22: Groundwater Quality Monitoring Sites .................................................. 83
Figure 6.23: Annual Standardized Precipitaion Index of Netrokona Sadar Upazila ........ 85
Figure 6.24: Geology of Bangladesh ...................................................................... 86
Figure 6.25: Seismic zones of Banlgadesh .............................................................. 87
Figure 6.26: Map of Bio-ecological Zones of Bangladesh........................................... 89
Figure 6.27: Pond Heron in a Feeding Habitat at Soail Beel ....................................... 92
Figure 6.28: Little Egret in Social Interactions at Komol Beel .................................... 92
Figure 6.29: Homestead Vegetation at Borni Village ................................................ 93
Figure 6.30: Roadside Vegetation at Singher Bangla ................................................ 93
Figure 6.31: Present Situation of Project Area ......................................................... 96
Figure 6.32: Various Fish Species of Fish ................................................................ 97
Figure 6.33: Catching Fish in the Study Area ........................................................ 100
Figure 6.34: AEZ Map of the Study Area .............................................................. 102
Figure 6.35: Land Use Map of the Project Area ...................................................... 104
Figure 6.36: Land Use Map of the Study Area ....................................................... 105
Figure 6.37: Land Type Map in the Study Area ...................................................... 107
Figure 6.38: Soil Texture Map of the Study Area ................................................... 109
Figure 6.39: Drainage Characteristics Map in the Study Area .................................. 111
Figure 6.40: Present Farming Practices in the Project Area ..................................... 114
xi
Figure 6.41: Present Farming Practices in the Study Area ....................................... 114
Figure 6.42: Livestock and Poultry are in Project and Study Area ............................ 117
Figure 6.43: Age structure by population ............................................................. 119
Figure 6.44: Employment Status of the Study Area ............................................... 120
Figure 6.45: Occupation Status of the Studied Population....................................... 121
Figure 6.46: Literacy Rate among the Studied Population ....................................... 121
Figure 6.47: Household Income and Expenditure of the Study Area ......................... 122
Figure 6.48: Housing Condition by Households ...................................................... 123
Figure 6.49: Source of Drinking Water used by the Studied Population .................... 124
Figure 6.50: Hand Tubewell for Drinking Water and other Domestic Use .................. 124
Figure 6.51: Deep Tubewell used for Irrigation and Drinking ................................... 124
Figure 6.52: Sanitation Facility in the Study Area .................................................. 125
Figure 6.53: Pucca Road inside the Project Area .................................................... 126
Figure 6.54: Netrokona to Mohanganj Railway Line ............................................... 126
Figure 6.55: Abandoned Zamindar Residence in Singher Bangla .............................. 127
Figure 6.56: Garo Community in Bhattapara, Rouha upazila, Netrokona ................... 128
Figure 6.57: Khatriya (Hindu cast group) Community in Shogundia, Mougati Union,
Netrokona ........................................................................................................ 128
Figure 11.1: Tentative layout options of dredging pipeline ...................................... 198
Figure 11.2: General waste flow diagram for industrial symbiosis ............................ 199
Figure 11.3: Overall concept of Resource Efficiency and Cleaner Production .............. 201
Figure 12.1: Annual Cumulative rainfall (1981-2017) at Netrakona ......................... 213
Figure 12.2: Annual Average Maximum temperature (1981-2017) at Netrakona ....... 213
Figure 12.3: Annual Average Minimum temperature (1981-2017) at Netrakona ........ 214
Figure 12.4: Peak flood level at Sylhet during April against different return periods
(CEGIS, 2017) .................................................................................................. 216
Figure 12.5: Water level hydrograph at Jariajanjail in Kangsha river Thunderstorm ... 217
Figure 12.6: Rate of Fatalities and Injuries during different seasons ........................ 217
Figure 12.7: Lightning occurrence from 1990-2017 in Netrakona ............................ 218
Figure 12.8: Number of Lightening at Netrakona from 1990-2017 ........................... 218
Figure 12.9: Season wise Intensity of Hailstorm in Sylhet ...................................... 219
Figure 12.10: Cold Wave Days in Sylhet from 1990-2017 ....................................... 220
Figure 12.11: Emergency Evacuation Plan ............................................................ 234
Figure 13.1: Proposal Institutional Setting for Environmental Compliance and EHS Unit
during Construction ........................................................................................... 249
Figure 13.2: Proposed Institutional Setting and Organogram for the Environmental
Compliance and EHS Unit during the Operation of the NEZ ..................................... 250
xii
Abbreviations and Acronyms
xiii
ECA : Environmental Conservation Act
ECA : Ecologically Critical Area
ECC : Environmental Clearance Certificate
ECR : Environment Conservation Rules
EHS : Environmental Health & Safety
EHSU : Emergency Health and Safety Unit
EIA : Environmental Impact Assessment
EMoP : Environmental Monitoring Plan
EMP : Environmental Management Plan
EMP : Environmental Management Plan
EPC : Engineering, Procurement and Construction
EPZ : Export Processing Zones
ERG : Emergency Response Group
ERP : Emergency Response Plan
ESIA : Environmental and Social Impact Assessment
ESMP : Environmental and Social Management Plan
ESMP : Environmental and Social Management Plan
ETP : Effluent Treatment Plant
EZ : Economic Zone
FAO : Food and Agriculture Organization
FCDI : Flood Control, Drainage and Irrigation
FDI : Foreign Direct Investments
FGD : Focused Group Discussion
FMD : Foot and Mouth Disease
FRSS : Fisheries Resources Survey System
FS : Feasibility Study
FY : Financial Year
GDP : Gross Domestic Product
GIS : Geographic Information System
GoB : Government of Bangladesh
GPS : Global Positioning System
GRC : Grievance Redress Committee
GRM : Grievance Redress Mechanism
xiv
GTCL : Gas Transmission Company Limited
HHs : Households
HS : Hemorrhagic Septicemia
HVAC : Heating, Ventilation, and Air Conditioning
HYV : High-Yielding Varieties
IEE : Initial Environmental Examination
IESC : Important Environmental and Social Components
IESMC : Independent Environmental and Social Monitoring Consultant
IFC : International Finance Corporation
ILO : International Labour Organization
IPM : Integrated Pest Management
IRT : Incident Response Team
IUCN : International Union for Conservation of Nature
IWM : Institute of Water Modelling
Kharif-1 : March-June
Kharif-II : July-October
KII : Key Informant Interview
KV : Kilovolt
LGRC : local Grievance Redress Committee
LLP : Low Lift Pump
MO : Muriate of Potash
MoEF : Ministry of Environment and Forest
MoWR : Ministry of Water Resources
MSDS : Material Safety Data Sheets
MT : Metric Ton
MW : Megawatt
NATECH Natural Hazard Induced Technological Disaster
NCA : Net Cultivable Area
NEZ : Netrokona Economic Zone
NEZA : Netrokona Economic Zone Authority
NOx Oxides of Nitrogen
NT : Near Threatened
NWRC : National Water Resources Council
xv
NWRD : National Water Reuse Database
O3 : Ozone
OHS : Occupational Health and Safety
OHSE : Occupational Health, Safety and Environment
PCM : Public Consultation Meeting
PDO : Project Director Office
PGRC : Project Grievance Redress Committee
pH : Potential of Hydrogen
PIU : Project Implementation Unit
PMO : Prime Minister’s Office
PPE : Personal Protection Equipment
PPP : Public-Private Partnership
PPR : Diarrhoea and Pest Des Petits Ruminants
PSC : Project Steering Committee
RMG : Ready-Made Garments
RRA : Rapid Rural Appraisal
RS : Remote Sensing
SAAO : Sub-Assistant Agriculture Officer
SCC : Site Clearance Certificate
SDS : Safety Data Sheets
SME : Small and Medium-sized Enterprises
SO2 : Sulfur Di-Oxide
SPI : Standardized Precipitation Index
SPM : Suspended Particulate Matter
SRDI : Soil Resource Development Institute
SSP : Single Super Phosphate
STP : Sewerage Treatment Plant
STW : Shallow Tube Well
TDS : Total Dissolved Solids
ToR : Terms of Reference
TSP : Triple Super Phosphate
TSS : Total Suspended Solids
UAO : Upazila Agriculture Officer
xvi
UFO : Upazila Fisheries Office
ULO : Upazila Livestock Officer
UNDP : United Nations Development Programme
UNO : Upazila Nirbahi Officer
WARPO : Water Resources Planning Organization
WASA : Dhaka Water Supply and Sewerage Authority
WHO : World Health Organization
WWTP : Waste Water Treatment Plant
xvii
xviii
Executive Summary
With the pace of current economic growth, the government of Bangladesh has planned to
establish 100 Economic Zones (EZ) countrywide by 2030, intending to earn around $40
billion through export. Accordingly, Bangladesh Economic Zones Authority (BEZA) was
formed following the Bangladesh Economic Zones Act, 2010 to establish, license, operate,
manage and control economic zones in Bangladesh. In line, BEZA has planned to establish
an Economic Zone over 500-acre of land located at Sadar Upazila of Netrokona District. The
construction of Netrokona Economic Zone (NEZ) includes three major components: i)
development of 500 acre land for the NEZ, ii) construction of on-site infrastructures for
utilities including roads, power lines, water supply, effluent treatment plant, sludge treatment
plant, waste management system, administrative buildings, etc. and iii) off-site connectivity
and infrastructures. The BEZA evaluated two candidate sites at Netrokona for the proposed
economic zone viz. i) Singher Bangla Site and ii) Beel Guzabugi site. According to study
findings, the Singher Bangla site would have low impacts on socio-economy due to no
acquisition of homesteads and other factors; therefore, Singher Bangla site has been
selected for the development of NEZ.
Such as project and activities, according to the Environment Conservation Rules (ECR)
1997, amended in December, 2017, requires approval from the Department of Environment.
The ECR categorizes different industries/projects/units into three broad types: Green,
Orange, and Red, of which the proposed NEZ falls into Red category. In principle, the Red
category project requires ‘Site Clearance Certificate’ (SCC) through an approval of Initial
Environmental Examination (IEE), followed by Environmental Impact Assessment (EIA)
according to approved ToR for getting Environmental Clearance Certificate (ECC). However,
BEZA received an exemption from IEE, hence SCC, upon submission of an application to
the DG, DoE considering importance of the project to boost up economy of the country to
fulfill its targeted objectives to become a middle-income country by 2021 and a developed
country by 2041. Thus, EIA and ECC is required only for carrying out the project, for which
DoE already approved a ToR, following which this EIA has been prepared.
This EIA study follows the participatory approach and a standardized methodology from
beginning to the end of the study trajectory. Both primary and secondary stakeholders were
consulted at different layers through different consultation meetngs. The study steps
included: baseline assessment, scoping, bounding, major field investigation, impact
prediction, mitigation measures, environmental management and monitoring plan.
In describing the existing condition, three environmental components: physical, biological
and socio-economic environment were assessed. The physical environment includes:
meteorology, topography, ambient noise, ambient air quality, surface and ground water. The
biological environment includes: ecology, fishery, agriculture and land resources. The socio-
economic environment includes conditions of social/economic and cultural parameters in the
study area.
With respect to physical environment, it was found that the highest rainfall occurred during
April to October while November to March was the drier part of the year with very less
rainfall. On the other hand, the highest maximum temperature was recorded as 38.1o C in
April of 1992 and the lowest minimum temperature was recorded as 4.7o C in January of
2013. The highest values of humidity for all the months were recorded as 100% whereas the
xix
Executive Summary
minimum values ranged between 20% and 51%. The most humid months were from June to
October.
The general topography of the project area is more or less flat with an elevation of 6.6 to 8.1
mPWD. Out of this area, 37% is highland and 34%, 21% and 7% are medium highland,
medium lowland and lowland respectively. The area of the Komol Beel is approximately 43
acres although retention of water varies at different times of the year. At the time of survey,
the noise level inside the project area was found very calm and low whereas, at several
points surrounding the project area, medium to heavy noise was observed. The places were
recognized mostly as lightly dense residential areas. The existing air quality of the proposed
NEZ area as well as the surroundings were observed to be good. Within the project area the
predominant anthropogenic interventions were observed as farming of crops throughout the
year and for fishing for a certain period of the year.
There are three significant rivers in the study area namely; Kangsha River which is 3~4 km
north to the project area, Mogra River which is 4~5 km south to the project area and Dhalai
river. There are a number of perennial and seasonal beels within the study area: Kuria beel,
Kalabagua beel, Nalghuria beel, Megha beel, Joga Beel, Hailda beel, Komol Beel, Soai beel
etc. Among these, Komol Beel and Soai beel are located within the project area although at
present the Soai beel area is almost dry and used for agricultural purpose. The Komol Beel
is connected to the Kangsha River in the north through internal drainage (Fazar ali canal)
channel. Groundwater is the main source of drinking water for the people living around the
project area as well as in the adjacent area. Analysis of the existing bore logs of Netrokona
Sadar upazila shows that layers of fine to medium sand exist below the surface at different
depths. In one borehole of 59.45 m depth at Netrokona Sadar mouza, fine to medium sand
was found at a depth of 12 m to 29 m and medium sand was observed from 55 m to 59 m
depth.
The study area is in Brahmaputra-Jamuna Floodplain Bio-ecological Zone. Generally, the
vegetation of the area includes: i) submerged plants, ii) free floating plants, iii) rooted floating
plants, iv) sedges and meadows, v) floodplain grassland, vi) crop field vegetation, vii)
roadside vegetation, and viii) homestead vegetation. The project area is also under the Old
Brahmaputra Floodplain (AEZ-9) and Northern and Eastern Piedmont Plains (AEZ-22) agro-
ecological regions. The Net Cultivable Area (NCA) in the project area and Study area are
455 acres and 54,859 acres respectively. There are four land types within the study area
Among the land types, Medium Highland (F1) is dominant (47%) followed by Highland (F0)
which is 26% of the NCA.
The Population in the study area is 531,806 of which 265,632 are males and 266,175 are
female. The average size of the household is 4.7. Agriculture is the dominant source of
livelihood for local people. About 87% households are involved in this sector either directly or
indirectly. Only 3% people are involved in industrial sectors usually working in brickfields,
roads and construction works and many other non-farming sectors. Traditionally,
employment opportunities for women outside the homestead is very limited. Majority of the
women are involved in household activities (e.g. in rice milling, weaving etc.).
Apprehending the project driven impacts on environmental and social parameters, a number
of key issues were identified to assess the potential impacts and their magnitudes. The key
issues are: i) air quality, ii) noise quality, iii) groundwater, iv) surface water, v) drainage and
water logging, vi) flooding, vii) land type, viii) landscape, ix) land use, x) crop production, xi)
fish habitat, xii) fish production, xiii) fish species diversity, xiv) stock susceptibility, xv) wildlife
xx
Executive Summary
habitat, xvi) species composition, xvii) dispossession, xviii) livelihoods loss, xix) social
conflict, and xx) employment generation, xxi) off-site development, and xxii) urbanization and
economic development.
Impacts on these key issues were assessed by categorizing them into socio-economic and
environmental. According to plan, 500 acres of land will be acquired for the project, for which
rights of landholders and their livelihoods will be impacted. About 2,161 tons rice production
of project area would be permanently lost per year due to the acquisition of land. During land
acquisition total 392 acres fish habitat will be lost. About 243 MT of fish production would
loss annually due to conversion of fish habitat to NEZ. About 15 households are seasonally
dependent on the land for fishing. Besides, about 150 households are directly dependent on
the acquired land for agricultural activities. After the land acquisition, the farmers and
fishermen will lose their livelihoods. Moreover, 13 Garo households (ethnic group) are
dependent on kuchia catching on the proposed acquired wetland, who will be impacted due
to loss of livelihood. All landholders of the proposed 500 acres of land do not have legal
entitlements, and some have incomplete or no legal documents although they purchased or
occupied land. Thus, people “without documents” are not eligible to get compensation
(according to Law) but will be affected, which might lead to local agitation/conflict.
With respect to environmental impacts, ambient air quality will be deteriorated due to dust
generated from vehicular movements and gaseous emissions of the construction vehicles
and equipment, and alongside, noise will be generated. Due to the land development and
the construction of on-site structures, the natural drainage pattern may get temporarily
blocked at certain places by the land soil and construction debris which can occur water
logging problems in case of heavy rainfall. In addition, during the wet periods floodwater may
not pass through the natural ways and hence can cause water logging at the northeast
corner of the project area as floodwater flows over the project area through this corner.
Groundwater is another important issues for the project. The study area already witnessed
groundwater stress in the past years. Therefore, the withdrawal of groundwater, might cause
depletion of groundwater table, resulting water crisis for the local community and for the
project itself. The project area is the combination of terrestrial and aquatic ecosystem, which
includes large trees and roadside vegetation as well as lowland with five beels that has been
recognized as feeding habitats to many resident and migratory waterfowls. Wetland
associated with different aquatic vegetation is providing support to this wildlife for breeding
and escape from predators. Due to land development work, all habitats with associated
vegetation will permanently be damaged. In addition, wildlife habitat in the project-influenced
area will also be deteriorated due to sand mining.
The EIA study proposed a number of environmental and social management measures to be
strictly considered during pre-construction, construction and operation phases of the project.
These plans include: i) Compensation plan, ii) Labor recruitment plan,iii) Livelihood
restoration plan, iv) Stakeholder engagement plan, v) Grievance Redress Mechanism, vi)
Land development management plan, vii) Occupational Health and Safety (OHS) Plan, viii)
Drainage and flood management plan, ix) Water pollution management plan, x) Air pollution
management plan, xi) Noise pollution management plan, xii) Waste management plan, xiii)
Transportation management plan, xiv) Fisheries resources Management Plan, xv)
Prevention of soil spillage to adjacent agricultural land management plan, xvi) Protection of
standing crop management plan, xvii) Water resources management plan, xviii) Green park
management plan, xix) Sustainable land use management plan, xx) Reduce crop damage by
Integrated Pest Management (IPM). In addition, the study also provided some special
xxi
Executive Summary
Environmental and Social Management Plan, which are essential to consider for this project.
These include: i) Dredging and Land Development Management Plans, ii) Industrial
Symbiosis Plans, iii) Resource Efficiency and Cleaner Production (RECP) Plans, iv) Water
Conservation and Saving Plan, v) Komol Beel management plan, and 2) East-site Gate
Management Plan. Alongside, the cost of implementing ESMP is tentatively estimated BDT
234.7 million. Alongside, ESMP, three types of environmental and social monitoring plan
have been provided in the report: 1) compliance monitoring, 2) impacts monitoring during
construction, and 3) independent/external monitoring. The monitoring cost for the first one is
BDT 51.5 million, for the next one is BDT 73.5 million, and for the last one is BDT 50 million.
By assessing potential disaster, hazard and risk, and climate change issue, the study
suggested some mechanism to be followed for the project. The hazard assessment has
been carried out to identify the potential hazard associated with or inherent in the design
process and to identify possible measures to avoid the hazard along with the safety plan for
minimizing the risk. Incorporation of these measures and safety plans in design, planning
and operational procedure of the proposed NEZ would eliminate the potential hazards.
The proposed project appears as one of the key cornerstones of the country’s development
activites. Similar to other development project, this project will bring negative consequences
for the local envrironment, landowners and dependent communities; but would be mitigated
with propoer measures, management plan and monitoring. Thus, ground water, surface
water networks, waterbody, aqauatic and wildlife, landlosers and dependent population
should be given special focus following the measures suggested in this report. Alongside,
the project will also bring immense positive impacts for local-regional and national economy,
and socio-economic benefits for the communities. Hence, measures suggested in this report
for enhancing of these positive impacts should be given special focus.
xxii
1. Introduction
1.1 Background
Bangladesh economy has steadily increased its average decadal growth rate over the last
few decades since its independence in 1971. The average growth rate of Gross Domestic
Product (GDP) increased from less than 4% per year during 1970-90 to 4.8% in 1990-2000.
During the last two decades, it rose to 5.8% in 2001-2010, and above 6% during the current
decade (2011-2020). Government of Bangladesh (GoB) has been successfully providing
land, infrastructure, and a favorable business environment through establishing Export
Processing Zones (EPZs) Program in 1980 under the Bangladesh Export Processing Zone
Authority (BEPZA). Since then, the EPZs have been used as a strategic instrument for
attracting Foreign Direct Investments (FDIs) in Bangladesh and in dealing with the
shortcomings in the overall investment climate in Bangladesh. The EPZ program was the
first systematic initiative to provide fully serviced land and a better business environment for
investors, targeting large scale export-oriented manufacturing. Since 1993, EPZs have
triggered impressive growth in exports, mainly in the Ready-Made Garments (RMG) sector,
at an average annual rate of 23 percent, reaching nearly US$5 billion by FY2018 and have
created half a million jobs within the EPZs.
Having a very positive experiences of EPZs the GoB has planned to generate about 10
million employment opportunities and boost up export earnings around $40 billion through
establishment of 100 Economic Zones (EZ) countrywide by 2030. Bangladesh Economic
Zones Authority (BEZA) has been emerged by the Bangladesh Economic Zones Act, 2010
to establish, license, operate, manage and control economic zones in Bangladesh and
accordingly placed under the Prime Minister’s Office (PMO) and governed by a Board
chaired by the Hon’ble Prime Minister. The law provides legal coverage for attracting and
leveraging private investment in the development of economic zones as zone developers or
operators, and in the provision of tailored infrastructure services, such as, private provision
of power, effluent treatment, wastewater treatment etc. The law also allows for development
of EZs and support infrastructure through a Public-Private Partnership (PPP) mechanism.
Keeping the target to be a middle-income country by 2021 and developed country by 2041,
BEZA is working with the aim to establish economic zones in all potential areas in the
country including backward and underdeveloped regions with a view to encouraging rapid
economic development through increasing and diversifying industry, employment, production
and export. For achieving the national agenda, BEZA has got approval to establish 88
Economic Zones (EZ) countrywide comprising 59 under government and the remaining 29
under private initiatives.
In line with the above initiatives, BEZA is planning to establish an EZ at Sadar Upazila of
Netrokona District, for which a Feasibility Study has been carried out by the Institute of
Water Modelling (IWM), a Public Trust under the Ministry of Water Resources (MoWR),
GoB. Since the government intends to establish EZ countrywide, Netrokona has been
selected as a potential area.
In accordance with the Environmental Conservation Act (ECA), 1995 and Environmental
Conservation Rules (ECR), 1997 including related amendments, the proposed Netrokona EZ
(NEZ) falls under “Red” category and requires simultaneously both Site Clearance Certificate
(SCC) and Environmental Clearance Certificate (ECC) upon approval of the Initial
1
Introduction
Environmental Examination (IEE) and Environmental Impact Assessment (EIA) study reports
by the Department of Environment (DoE). Considering the importance of establishing EZ
aiming to fulfil the long vision of GoB, BEZA requested DoE to get necessary exemption
from carrying out IEE for obtaining the SCC. In a request letter, BEZA desired to conduct an
Environmental Impact Assessment (EIA) study based on a Terms of Reference (ToR)
(through attaching with that letter) to obtain ECC from the DoE. Taking the noted issues in
consideration, DoE provided exemption order (vide the Memo no.
22.02.0000.018.72.131.19.569; dated 22 December, 2019) from conducting IEE and
approved the ToR for conducting a comprehensive EIA of NEZ. The copy of DoE’s approved
ToR is attached in at Appendix-II. In order to conduct the EIA, BEZA assigned CEGIS, a
Public Trust under the Ministry of Water Resources (MoWR), GoB Government of
Bangladesh (GoB) for conducting the study.
2
Introduction
In order to make NEZ more attractive to the investors and to make the zones more
technically and economically feasible the proposed Master Plan has outlined a number of
on-site and off-site infrastructures. The on-site infrastructures are:
i. Road Network (Circular Road, Internal roads, Walkway, Bicycle tract);
ii. Utility ducts and drainage passages (water line, cables, electric power lines, gas
pipelines);
iii. Electric Lighting;
iv. Power Supply System;
v. Water Supply;
vi. Sewage Treatment Plant (STP);
vii. Common Effluent Treatment Plant (CETP);
viii. Sludge Management;
ix. Fire Protection;
x. Data Connectivity;
xi. Solid Waste Management; and
xii. Administration/One-stop Service Building and Other Supporting Buildings.
The proposed off-site infrastructures are:
i. Improvement and rehabilitation of adjacent railway line and establishing a railway
station;
ii. Two lane road adjacent to the NEZ to be extended to four lane regional highway
connecting Dhaka and Sylhet (via Tahirpur – Sunamganj);
iii. Upgrade function of nearby river port at Gaglajur Bazar exclusively for the NEZ to
connect with Ashuganj;
iv. Connectivity with Sylhet Osmani International Airport (146 km) through Netrokona-
Tahirpur-Sunamganj-Sylhet highway; and
v. Connectivity with Dhaka Shahjalal International Airport (150km) through
Netrokona-Dhaka highway.
3
Introduction
4
Introduction
Figure 1.2: Base Map of the Proposed Netrokona Economic Zone (1km radius)
5
Introduction
Figure 1.3: Base Map of the Proposed Netrokona Economic Zone (10km radius)
6
Introduction
7
Introduction
8
Introduction
9
Introduction
10
Introduction
11
Introduction
12
2. Policy, Legal and Administrative Framework
2.1 Introduction
In this chapter, all relevant policies and legislations pertaining to the GoB, particularly, the
Environment Conservation Act (ECA) 1995 (with subsequent amendments) and the
Environment Conservation Rules (ECR) 1997, amended in December, 2017 were assessed.
The Project Proponent, Bangladesh Economic Zone Authority (BEZA), will ensure
adherence to all applicable regulations and standards for environmentally acceptable
operation of this Project.
The Netrokona Economic Zone project includes land development activities for industrial
purposes in Netrokona. The Environment Conservation Rules (ECR) 1997, amended in
December, 2017 is the main legal instrument, which obliges industries/projects/units to get
either site and/or environmental clearances from the competent authority. The
Environmental Conservation Act (ECA) 1995 (subsequent amendment 2002), clearly states
in serial no. 12 that an Environmental Clearance Certificate (ECC), that follows the ECR
1997 (with subsequent amendments), must be approved by the Director General (DG) of the
Department of Environment (DoE) prior to establishing/ undertaking any industrial unit/
project. The ECR categorizes different industries/projects/units into three broad types:
Green, Orange, and Red. According to the industrial unit classification, mentioned in the
ECR 1997 (amended), this proposed project is under the ‘Red’ category: serial 39-industrial
estate. The Red category project, primarily requires ‘Site Clearance Certificate’ (SCC)
through approval of Initial Environmental Examination (IEE), followed by Environmental
Impact Assessment (EIA) according to approved ToR for getting Environmental Clearance
Certificate (ECC). However, BEZA received an exemption from IEE, hence SCC, upon
submission of an application to the DG, DoE. Thus, EIA and ECC is required only for
carrying out the project, for which DoE had already approved a ToR, following which this EIA
has been prepared. In the following Sections, summary of relevant legislations and policies
are presented:
13
Policy, Legal and Administrative Framework
Department of Environment
In order to expand the scope of environmental management and to strengthen the power for
achieving it, the Government adopted the Environmental Pollution Control Ordinance in
1977. The ordinance provided the opportunity for the establishment of an Environmental
Pollution Control Board, which was assigned with the responsibility of formulating policies
and proposing measures for their implementation. In 1982, the Board was renamed as the
Department of Environmental Pollution Control (DEPC). Six divisional offices were
established in Dhaka, Chattogram, Khulna, Barishal, Sylhet and Rajshahi.
A special presidential order again renamed the DEPC as the Department of Environment
(DoE) and placed it under the newly formed MoEF in 1989.
The DoE is a Department of the MoEF and is headed by a Director General (DG). The
power of the DG, as given under the Act, may be outlined as follows:
The DG has the power to close down activities considered harmful to human life
or the environment. The operator has the right to appeal and procedures are in
place for this. However, if the incident is considered an emergency, there is no
opportunity for any appeal.
The DG has the power to declare an area affected by pollution as an ecologically
critical area. The DoE governs the type of work or process, which can take place
in such an area.
Before undertaking any new development project, the project proponent must
take Environmental Clearance Certificate (ECC) from the DoE. The procedures to
take such clearance are in place.
Failure to comply with any part of the Environment Conservation Act (ECA), 1995
with subsequent amendments may result in punishment by imprisonment or a
fine of or both.
Forest Department
This department under the MoEF is responsible for the protection and management of all
reserve forests in the country. Department personnel extend down to the union level in areas
where there are reserve forests. The department has recently started some agroforestry
programs and its officers are also responsible for the protection of wildlife in the forests.
14
Policy, Legal and Administrative Framework
15
Policy, Legal and Administrative Framework
16
Policy, Legal and Administrative Framework
17
Policy, Legal and Administrative Framework
18
Policy, Legal and Administrative Framework
1 (b) loss of crops or trees; (c) loss of affected immovable property separated from existing immovable property;
(d) loss of other immovable property or movable property or income; (e) transfer cost of affected residential and
commercial properties.
19
Policy, Legal and Administrative Framework
20
Policy, Legal and Administrative Framework
21
Policy, Legal and Administrative Framework
22
3. Approach and Methodology
Activities to be carried out at each stage of the EIA process are described in the following
sections.
23
Approach and Methodology
a) Physical Environment
Water Resources
Water resources data of river/wetland in terms of hydrology, drainage pattern, flooding
history, groundwater reserve, water use were collected from available secondary sources
and analysed. Flood inundation extent and flood depth map were also produced using GIS
technology considering present and future climate change scenario. Besides, relevant water
quality parameters were tested following both ex-situ and in-site methods to ascertain the
baseline situation.
Air quality
Air quality data in terms of Fine Particulate Matter (PM2.5), Respirable Dust Content (PM10),
Suspended Particulate Matter (SPM), Sulfur Di-Oxide (SO2), Oxides of Nitrogen (NOx),
Carbon Mono-Oxide (CO), Ozone (O3) were collected from Singher Bangla, Chan Mia Mor
and Durgasrom sites to get an idea of the baseline situation.
24
Approach and Methodology
Figure 3.2: View of Air Quality Monitoring Figure 3.3: View of Air Quality Monitoring
at Singher Bangla (AQ1) at Chan Mia Mor (AQ2) & Durgasrom
(AQ3)
Noise
Noise levels were measured for twice in a day (Day and night time) within the project
influenced area. Each time, noise level was recorded for a five minutes time span with a 30
second intervals by using portable noise level meter. Depending on the site condition and
acoustic environment, the noise meter was set up and calibrated each time.
25
Approach and Methodology
b) Biological Environment
Fisheries Resources
Fisheries resources (both natural and capture fishery) data and information were collected
based on different parameters such as available fish species, production of fish, and loss of
fish habitat. Primary data was collected through questionnaire survey and Focus Group
Discussion (FGD). Secondary data was collected from concerned Upazila Fisheries Office
(UFO) and from review of Fisheries Resources Survey System (FRSS) of Department of
Fisheries (DoF). Fisheries habitat (water bodies) was identified using satellite images.
Agricultural Resources
Agricultural resources data interims of farming practices, crop production constraints,
existing cropping patterns, crop variety, crop yield, crop damage and agricultural inputs were
collected from both primary and secondary sources. Primary agriculture data was collected
through questionnaires, key informant interview and focused group discussions. Secondary
data was collected from Upazila Agricultural Office of Department of Agricultural Extension
(DAE). High resolution recent images were used to compute net cropped area. Crop
production was determined using the formula: Total crop production = damage free area ×
normal yield + damaged area × damaged yield. The crop damage (production loss) was
calculated using the formula: Crop production loss = Total cropped area ×normal yield-
(damaged area ×damaged yield+ damage free area × normal yield). The crop damage data
was collected from the field for last three years.
26
Approach and Methodology
Livestock resources
Secondary livestock data like population feed and fodder shortage diseases was collected
from Department of Livestock Services (DLS). Primary data was collected through
questionnaires, key informant interview and focused group discussions.
c) Socio-economic Environment
Socio-economic baseline information including demography, occupation, literacy rate, public
utilities (drinking water, electricity facilities), etc. were collected from secondary sources, i.e.
Bangladesh Bureau of Statistics and other relevant literatures. Data on income, expenditure,
social overhead capitals and quality of life, livelihood pattern, communication system,
proposed project impact on socio-economic status and cultural and heritage features of the
project area was collected mainly from primary sources through questionnaire survey, Focus
Group Discussion (FGD), discussion with BEZA officials and local stakeholders.
3.1.5 Bounding
Area likely to be impacted by the proposed project was delineated in consultation with the
project proponent in addition to feedback received from the local people during baseline
consultation. The entire project area was defined as “Project Area.” On the other hand, the
area within surrounding 10 km radius of the project area was defined as “Study Area” or
“Project Influence Area”. Both Project area and Project Influence Area were taken into
account in the EIA study
27
Approach and Methodology
28
Approach and Methodology
29
Approach and Methodology
30
Approach and Methodology
Sensitivity of Receptors
Magnitude of Impact
Very High High Medium Low
Major Critical Major Moderate Minimal
Moderate Major Major Moderate Minimal
Minor Moderate Moderate Minor Minimal
Minimal Minimal Minimal Minimal Minimal
31
Approach and Methodology
32
4. Project Description
4.1 Introduction
The proposed Netrokona Economic Zone (NEZ) is a part of the government’s plan of
establishing new 100 EZs across the country especially in areas which are underdeveloped
and backward. The aim is to promote domestic investment and as well as foreign investment
for local and regional economic development. The BEZA was the proponent of the NEZ and
engaged Institute of Water Modelling for carrying out the feasibility study. This chapter
outlines the overall master plan of the NEZ developed by IWM. The master plan includes
layout description, zoning, NEZ facilities, on-site and off-site infrastructures, etc. The salient
features of NEZ are provided in Table 4.1.
Division Mymensingh
District Netrokona
Upazila Netrokona Sadar
Mouza Barni, Kashipur, Singher Bangla, Bhadrapara
24°55'34.15"N to 24°54'31.99"N
Coordinates
90°46'24.00"E to 90°47'30.92"E
Area 500 acres
Current land-use Agriculture
Average land elevation 7.25 mPWD
The distance along road from Dhaka 150 km
Distance along road from Chittagong 401 km
Distance from nearest airport 150 km (Hazrat Shah Jalal International Airport, Dhaka)
Distance from nearest river Kangsha 3 km
Distance from nearest railway line Adjacent
Distance from nearest highway Adjacent
Distance from nearest 33 KVA electric line Adjacent
Distance from nearest gas supply line 4 km
Groundwater, Kangsha River, rainwater harvesting inside
Probable water sources
waterbody
Source: Feasibility Study Report prepared by IWM (BEZA, 2019)
33
Project Description
The feasibility study approximately allocated area for different zones and facilities which is
presented in Table 4.4.
34
Project Description
35
Project Description
Table 4.4: Allocated land area for different zones and facilities
Area Percentage of
Type of Zone Type of Land Use
(Acres) Total Area
Ceramic Ind. (16 plots) 15.79 3.11%
Food Processing (28 plots) 27.71 5.45%
Garments (47 plots) 47.16 9.27%
Zone A: Industrial Area
Integrated Textiles (26 plots) 25.7 5.05%
(39.99% of total NEZ area)
Light Engineering (16plots) 16 3.15%
Pharmaceuticals (22 plots) 22.02 4.33%
Small and Cottage Industries(49 plots) 49.01 9.64%
Zone B: Residential Area
Residential Area 29.53 5.81%
(5.81% of total NEZ area)
Club, Playground & Food Plaza 4.5 0.88%
Eco Park 7.59 1.49%
Green 16.4 3.22%
Zone C: Recreational Area Landscaping & Slope Protection 28.3 5.56%
(24.76% of total NEZ area) Park 1.18 0.23%
Playground 1.53 0.30%
Water body (Lake & Canal) 66.45 13.07%
Administration 5.65 1.11%
Central Truck Stand & Workshop 7.12 1.40%
CETP 5.83 1.15%
Commercial Area 7.5 1.47%
Day Care Center 1 0.20%
DTW 1.09 0.21%
Education 3.43 0.68%
Entrance, Parking & Security 6.1 1.20%
Fire Station 2 0.39%
Zone D: Administrative & Health Care 2 0.39%
Service Area (29.44% of total Lifting Station 0.6 0.12%
NEZ area) Logistics & Helipad 2 0.39%
Power Sub-station 1.88 0.37%
Religious Facilities 2 0.39%
Rest house 4 0.79%
Road Network 69.46 13.66%
School & Playground 6.12 1.20%
Solid Waste Management Site 1.83 0.36%
STP 6 1.18%
Utility Services Management 3.93 0.77%
WTP 10.16 2.00%
Total 100%
36
Project Description
37
Project Description
38
Project Description
a) Road Network
The detail of the road network is illustrated in the general layout shown in Figure 4.2 above.
Four (04) lane roads: The length of the four-lane road is approximately 3.66 km. The right of
way (RoW) of this road is 30m. Typical cross- section of road is Shown in Figure 3. Two
(02) lane roads: The length of the two-lane road is approximately 8.79 km. The right of way
(RoW) of this road is 20m. Typical cross- section of road is Shown in Figure 3.
Walkway: Walkways are proposed along the periphery of the Kamal lake and the Channel.
The walkway should be at least 3m wide.
39
Project Description
e) Conservation of lake
The Komol beel area will be preserved as a lake, which is expected to provide an essential
part in the internal drainage system of NEZ by retaining the rainwater. Figure 4.7 shows the
layout of the provision of lake. The lake will be connected with the adjacent canal at the
northern side of the project area through an open drainage channel. A water regulator will be
established at this connection point to control overflow inside the NEZ area. A walkway and
bicycle path will be established around the lake, which will also have provision to cross the
40
Project Description
lake. A small island and bird watching tower will be built at the center of the lake for
recreational purposes.
41
Project Description
42
Project Description
Figure 4.7: Layout of Water Supplly System and Provision of Lake to Preserve Rainwater
43
Project Description
44
Project Description
45
Project Description
46
Project Description
Figure 4.11: A General Layout of the WWTP and CETP Discharge Drain
47
Project Description
k) Integrated Waste Management Facilities (IWMF) including Waste Sorting and Material
Recovery facility
Generated solid waste will be transported to Secondary Transfer Stations (STS) from
individual plots. Location of STSs has been proposed in the plot of Integrated Waste
Management Facility. The area of this site is about 1.83 acres. There will be four (04)
Secondary Transfer Station (STS) in this integrated waste management facility (IWMF);
among which one (01) will be used for residential zone and three (03) will be used for
industrial zone. Sufficient nos. of dustbin should be placed along the road network and in
public places (i.e. parks, playgrounds, etc.). A waste sorting facility will be constructed to
process waste and recover material from industrial and municipal waste, including metals,
glass, paper, textiles, and plastics, as well as domestic food waste, roads and building
construction waste and electronic waste. Mechanical sorting technologies will be used to
ensure effective and safe material recovery from industrial and municipal waste. The facility
will screen, sort, shred, separate and store industrial and municipal solid waste to be
recycled.
48
Project Description
49
Project Description
Figure 4.13: Elevation and Floor Plan of the Secondary Transfer Station
50
Project Description
l) Sludge Management
When a liquid sludge is produced, further treatment may be required to make it suitable for
final disposal. Typically, sludge is thickened (dewatered) to reduce the volumes for disposal.
Near the settling tank, there is a sludge drying bed. By dewatering the sludge and proper
treatment, sludge cake will be produced. The Feasibility study proposes a few possibilities of
using slugde:
Use of sludge as land-filling material;
Use of sludge as filling material for public works (road, pipe laying) provided
that sludge contents in organic matter are acceptable;
Use of sludge as material for brick manufacturing by incorporating sludge in clay;
Use of sludge as material for agricultural soil improvement, providing that lime is
added and aluminum concentration is acceptable (aluminum is toxic for humans
and plants);
Evacuation of sludge to dumping site.
m) Fire Protection
For the fire protection system, a fire station and two fire trucks have been considered in case
of fire incidence.
n) Data Connectivity
A robust infrastructure for high-speed internet connectivity is essential for ensuring the
sustainable operation of the zone. On top of that, it is imperative to have connectivity from
multiple operators to maintain high uptime and seamless service levels to the tenants. An
operator with sufficient capability may provide network connectivity inside the zone and
maintain clientele among tenants independently.
51
Project Description
52
Project Description
53
Project Description
54
Project Description
55
Project Description
Amount
Sl.
Item Unit Quantity Rate (BDT) (Million
No.
BDT)
5.3 Power Supply System incl. sub station LS 288
5.4 Gas Supply System LS 165
CETP incl. effluent & discharge pipeline, lift Km
5.5 13.99 873
station
IWMF (Integrated Waste Management
5.6 375
Facilities)
6 Project Preparatory Costs of the Sponsors 152
Consultancy Fees for Design, Construction and LS
6.1 48
Supervision
6.2 Off-site Infrastructure Consultancy Fees LS 50
6.3 Legal Support LS 24
6.4 Administrative & Marketing Promotions LS 10
6.5 Vehicle LS 20
Sub-total (1 to 6) 14,315
7 Contingency (2% of sub-total) 286
8 Cost Escalation LS 358
Total Cost (BDT in Million) 14,959
Source: Feasibility Study Report Prepared by IWM
56
5. Alternative Analysis
5.1 Introduction
The BEZA evaluated two candidate sites at Netrokona for the proposed economic zone – i)
Singher Bangla Site, ii) Beel Guzabugi site before finally selecting the Singher Bangla site.
According to BEZA, the Singher Bangla site would have low impacts on socio-economic
condition since there will be no acquisition of settlements.
57
Alternative Analysis
58
6. Environmental and Social Baseline
6.1 Introduction
This section provides the baseline condition of physical, biological and socio-economic
resources in both study and project area. As mentioned before, project area refers to the
location where the economic zone will be established; whereas the study area refers to the
area within 10 km radius of the proposed project site.
Rainfall
Rainfall data was collected from Netrokona Sadar BWDB station and Mymensingh BWDB
station. From the available data, the analysis at Netrokona station was done for the period
from 1978 to 2008 and at Mymensingh station for the period from 1983 to 2013. Both the
areas receive high rainfall during April to October while November to March is the drier part
of the year with very less rainfall. The analysis shows that the monthly average rainfall varies
from 6.4 mm to 673.4 mm at Netrokona and from 6.68 mm to 447.19 mm at Mymensingh. At
Netrokona the maximum rainfall for an amount of 1218.6 mm occurred in July, 1982 while at
Mymensingh the maximum rainfall of 865 mm occurred in July, 1983. The monthly
maximum, minimum and average rainfall is shown in Figure 6.1 and, the annual rainfall at
Netrokona (1978 – 2008) and Mymensingh (1978 – 2017) are presented in Figure 6.2. The
maximum annual rainfall of 4327.4 mm was recorded at Netrokona in 1988 and 3312 mm at
Mymensingh in 1991. The linear trend line of the annual rainfall shows a slight increasing
trend at Netrokona and slight decreasing trend at Mymensingh.
59
Environmental and Social Baseline
Figure 6.1: Monthly maximum, minimum and average rainfall at Netrokona BWDB
station and Mymensingh BMD station
Figure 6.2: Annual rainfall at Netrokona BWDB station and Mymensingh BMD station
Temperature
The temperature data was collected from the nearest meteorological station at Mymensingh
and analyzed. The highest and the lowest temperature values for each month for the period
from 1988 to 2017 is presented in the Figure 6.3. The highest maximum temperature was
recorded as 38.1o C in April, 1992 and the lowest minimum temperature was recorded as
4.7o C in January, 2013. It revealed from the values that the warmer months are June, July,
August and September and the cooler months are November to March.
60
Environmental and Social Baseline
Figure 6.3: Monthly maximum and minimum temperature at Mymensingh BMD station
Relative Humidity
Relative Humidity data was also collected from the BMD station at Mymensingh and
analyzed. The analysis of monthly relative humidity data for the period from 1988 to 2018 is
shown in Figure 6.4. The analysis shows that the highest Relative Humidity in all the months
were recorded as 100% whereas the minimum values vary between 20% and 51%. The
most humid months are from June to October.
61
Environmental and Social Baseline
changes from sea to land (Khatun, Rashid, & Hygen, 2016). The monsoon period plays a
vital role in the wind distribution. Wind rose diagrams at Mymensingh station for the period of
1971 to 2010 are obtained from Khatun et al. and are shown in Figure 6.6. Wind distribution
diagrams show that wind speeds at winter (November, December, and January) and post
monsoon (September and October) were comparatively lower than in monsoon (May, June,
July and August) and pre-monsoon period (February, March and April). The direction of wind
was predominantly eastward but in winter both multidirectional.
Figure 6.6: Wind Rose Diagram at Mymensingh BMD Station; (i) Winter, (ii) Pre-
monsoon, (iii) Post monsoon), (iv) Monsoon
62
Environmental and Social Baseline
6.2.2 Topography
Netrokona District falls within the old Brahmaputra alluvial floodplain which has an elevation
of 10 m above sea level (Rashid, 2019). Floodplains are not always totally flat, but comprise
with slightly higher parts (ridges) separated by depressions (basin) and spatial patterns
change over time (Uddin, Hooda, Mohiuddin, Smith, & Waller, 2019). Figure 6.7 shows a
topography map of Bangladesh (Awal, 2014) and the location of the project area. According
to the classification of land types of Bangladesh, land which is above normal flood level is
called highland, lands which are flooded up to 90 cm and between 90 cm and 180 cm deep
during flood are called medium highland and medium lowland respectively (Uddin et al.,
2019). The general topography of the project area is more or less flat with an elevation of 6.6
to 8.1 mPWD. Out of this area, 37% is highland and 34%, 21% and 7% are medium
highland, medium lowland and lowland respectively(IWM, 2019). Figure 6.7 shows digital
elevation model of the project area. The area of the Komol Beel is approximately 43 acres
and its water retention changes at different times of the year.
Source: Awal, 2014 and Feasibility study report of NEZ (IWM, 2019)
Figure 6.7: Topography of Bangladesh and Digital elevation map of the project area
63
Environmental and Social Baseline
corner of the project area which could be defined by mixed areas. The monitoring site at the
south-west corner was designated as silent area because of the presence of a high school
although, a local market place and few residential houses were also located there. As there
was no industry close by, the major sources of noise at the locations were the movements of
vehicles and hydraulic horns. Table 6.1 shows the monitoring data at the locations with
standard values of residential and mixed area as per Noise Pollution Control Rule, 2006.
The survey data shows that most of the noise levels slightly exceeded the standard values.
64
Environmental and Social Baseline
Residential area 55
Day time (12:23 pm to 12.33 pm) 65 77 45
South-East (surrounded by few houses,
24°54'56.9"N
1 corner of agricultural land and a small
90°47'30.0"E
project area connecting road to the Night time (7:28 pm to 7:38 pm) 49.5 68 42 45
highway)
South-Middle Residential area 55
24°54'34.8"N Day time (12:09 pm to 12.19 pm) 71.5 90 43
2 part of (Surrounded by households
90°46'58.4"E
project area and highway) Night time (7:14 pm to 7:24 pm) 56 86 42 45
South-West Silent area (Surrounded by
24°54'34.8"N Day time (12:52 pm to 1.02 pm) 60.5 75 48 50
3 corner of several households, small
90°46'35.5"E
project area market and a high school) Night time (6:55 pm to 7:05 pm) 52.5 65 42 40
Residential area 55
North-West Day time (10:30 am to 10.40 am) 56.6 63 41
24°55'14.1"N (Surrounded by several
4 corner of
90°46'26.1"E households and agricultural
project area Night time (6:37 pm to 6:47 pm) 47 60 40 45
land)
North-Middle Mixed area (Surrounded by Day time (9:17 am to 9:27 am) 69 83 57 60
24°55'29.7"N
5 part of few households, few small
90°46'59.5"E Night time (6:52 pm to 7:02 pm) 55 70 41 50
project area shops, school)
Residential area Day time (9:54 am pm to 10:04
North-East 56 75 45 55
24°55'31.5"N; (surrounded by few small am)
6 corner of
90°47'33.6"E houses, agricultural land and
project area Night time (7:16 pm to 7:26 pm) 45 59 41 45
a small village road)
Source: Field data, 2019
2 Noise Standards are adopted from Bangladesh Noise Pollution (Control) Rules, 2006.
3 According to the Noise Pollution control Rules, ‘Silent Area’ is defined by the places where hospital, educational institute, office is located.
4 According to the Noise Pollution control Rules, ‘Residential Area’ is defined by the places where people live with their families.
5 According to the Noise Pollution control Rules, ‘Mixed Area’ is defined by the areas which are combinedly used as residential, commercial and/or industrial areas.
65
Environmental and Social Baseline
66
Environmental and Social Baseline
Figure 6.9 shows a google earth image with the sensitive receptors of noise at a 4 km radius
of the project area. The receptors are not assembled in a single area but scattered. The
major receptors are several mosques and a few educational institutes. The rural settlements
around the project area are mostly households which might be affected due to the
establishment of heavy industries. It should be noted that, it will not be appropriate to select
the total area of the Economic Zone as Industrial area as there are plans to establish parks,
educational institutes and office areas which do not fall under industrial area.
67
Environmental and Social Baseline
6
Standard set for an averaging time period of 24 hours
7 Standard set for an averaging time period of 8 hours
8 Standard set for an averaging time period of 1 year
68
Environmental and Social Baseline
this river. But, when the flow boosts during the monsoon, it overflows its banks. Total length
of this river is approximately 163 km (CEGIS, 2013).
There are a number of perennial and seasonal beel areas within the study area- Kuria Beel,
Kalabagua Beel, Nalghuria Beel, Megha Beel, Joga Beel, Hailda Beel, Komol Beel, Soai
Beel etc. Among these, Komol Beel and Soai Beel are located within the project area
although at present, the Soai Beel is almost dry and used for agricultural purpose. One
distributary channel named Thakurakona Canal that originates from Kangsha River near
Thakurakona bus station and reaches the project area with a name of Fazar Ali canal
through the south-east corner. At the western side of Komol Beel another channel offtakes
namely Krishna Khali canal and after flowing for 3 km joins with Kuria Beel which eventually
flows further south to meet with the Mogra River. Figure 6.10 shows the water resources
network within 5~6 km radius of the project area.
Figure 6.10: River and canal network around the project area
69
Environmental and Social Baseline
Figure 6.11: Water Discharge Simulated Data of Kangsha and Mogra Rivers
There are two water level gauge stations at the Kangsha River- one is at Jaria-Jhanjail,
around 17 km upstream from the project area and the other one is at Mohanganj, around 20
km downstream from the project area. Analysis of 10-year averaged water level hydrographs
shows that at Jaria-Jhanjail station the hydrographs are almost similar throughout the past
50 years while at Mohanganj station dry season water levels showed a rising trend during
the last three decades. The maximum water level varies from 9.5 mPWD to 12.5 mPWD at
Jaria-Jhanjail station and from 7 mPWD to 9 mPWD at Mohanganj station. Minimum water
levels ranges between 2 mPWD and 5.5 mPWD at both stations.
There is another waterlevel gauge station on the Mogra River at Atpara, which is around 15
km downstream from the project site. The 10-year averaged water level analysis showed a
decreasing trend in the recent past. The water level data of 1980-1989 to 2000-2009 shows
that the water level has lowered down by at least 1.5 mPWD in the dry periods and 2 mPWD
in the monsoon periods. The maximum and minimum water level at Atpara station ranged
from 6.7 mPWD to 11.2 mPWD and from 1.1 mPWD to 3.4 mPWD respectively.
70
Environmental and Social Baseline
Source: Feasibility study report of river management at the haor areas (CEGIS, 2013)
Figure 6.12: Water Level Hydrographs for 10 Year Return Period at Jaria-Jhanjail and
Mohanganj Station (Kangsha River)
Source: Feasibility study report of river management at the haor areas (CEGIS, 2013)
Source: Feasibility study report of river management at the haor areas (CEGIS, 2013)
Figure 6.14: Water Level Hydrographs for 10 Year Return Period and Maximum-
minimum Water Level at Atpara Station (Mogra River)
71
Environmental and Social Baseline
72
Environmental and Social Baseline
Figure 6.15: Existing Water Management Infrastructure within the Study Area
73
Environmental and Social Baseline
74
Environmental and Social Baseline
Flooding
Flooding occurs due to the flow and rise of the water level of Kangsha River and intensive
rainfall. Approximately 10.1% of the total Upazila area is homestead and 1% is water bodies
(very low land) (IWM, 2019). The area elevation curve of the project area as shown in
Figure 6.18 and the flooding statistics as shown in Table 6.4, depicts that the project area
would be inundated during the peak flooding. 100% area of the proposed economic zone is
below the annual maximum peak water level (8.8 mPWD) of Kangsha River. The peak
normally comes in the month of April and receding starts in the month of October. Historical
maximum peak flood level (11.50 mPWD) was recorded in the month of June, 1988 while
the minimum flood level (4.16 mPWD) occurred in the month of April, 1994 (CEGIS, 2012).
During the last 15 years, heavy floods had occurred in 2007 and 2017. Excessive rainfall in
the upstream catchment areas was the main reason for those flash floods. According to the
local people, every year during the seasons of flooding the flood level around the project
area rises close to the existing embankments and at several points the embankments are
overtopped.
75
Environmental and Social Baseline
Table 6.4: Inundated Area under Different Water Level of Kangsha River
Collection date
Sample ID Location GPS Coordinate
& time
Kongsha river, near Thakurakona bridge N 240 54´ 38.2´´ 06/01/2020; 5:05
SW-1
(Thakurakona, Netrokona) E 90º 49´ 36.8´´ pm
East side of Komol/Rupsha Beel N 240 55´ 08.0´´ 06/01/2020; 5:40
SW-2
(Thakurakona, Netrokona) E 90º 48´ 17.6´´ pm
West side of Komol/Rupsha Beel (Shingher N 240 55´ 03.3´´ 07/01/2020; 1:05
SW-3
Bangla, Netrokona) E 90º 45´ 44.4´´ pm
Several parameters were assessed through lab analysis. Acidified and non-acidified bottles
were used for sampling to test metallic and non-metallic concentrations respectively. The
results along with the methods of tests are presented in Table 6.6. In the Environmental
Conservation Rules of Bangladesh, 1997, standards for inland surface water were found for
only a few parameters which are also provided in the same table. The samples were found
to be within the acceptable range for the parameters available with standard values. From
the results, it can be observed that, the sample SW-1, which was sampled at the Kangsha
River was better in quality than the other two samples. All the samples showed some
similarities for a few parameters such as temperature, pH and color. However, the sample
SW-2, which was collected from a canal connected to the Komol beel (Fazar Ali canal)
showed way higher value than the other two samples for several parameters such as
turbidity, TDS, TSS, COD, electric conductivity, sulphate, ammonia-nitrogen. The reason for
such contamination could be the agricultural emission (fertilizers, pesticides) from the
adjacent lands. Also, the sample was taken from a location where the depth of water was
very shallow and organic matter as well as solids from the bed level could be mixed with the
sample. The sample SW-3 which was also taken from the canal connected to the beel
(Krishna Khali canal) showed better quality than SW-2 but worse than SW-1.
76
Environmental and Social Baseline
77
Environmental and Social Baseline
Aquifer characteristics
Groundwater is the main source of drinking water for the people living around the project
area as well as within the impact area. In this regard, lithological investigation was
conducted to ascertain the characteristic of aquifer of the area. Analysis of the existing bore
logs of Netrokona Sadar Upazila shows that layers of fine to medium sand exist below the
surface at different depths (Figure 6.20). The lithology of the area at different depths are
given in the following table.
9 Standard of inland surface water usable for recreational use, irrigation, fisheries.
10 Standard of inland surface water usable for pisiculture.
78
Environmental and Social Baseline
The specific yields of sand layers in this area ranges between 0.12 and 0.15 which indicates
that aquifer quality is favourable for groundwater abstraction but not at all depts.
79
Environmental and Social Baseline
Figure 6.20: Borelog Characteristics and Specific Yield at Depths under Ground Level
of Netrokona Sadar
80
Environmental and Social Baseline
Availability of groundwater
Intensive groundwater abstraction and depletion of groundwater level are common issues in
Bangladesh. Mean annual groundwater recharge is found to be higher (300-600 mm) in the
north-western and the south-western areas than the south-eastern and north-eastern areas
(<100 mm) where rainfall and potential recharge are greater (Shamsudduha, Taylor, Ahmed,
& Zahid, 2011). Figure 6.21 shows a map of Bangladesh indicating the nation-wide
distribution of groundwater depth and the difference between potential and net recharge of
groundwater over a period of 1975 to 2007. The dry-period depth of groundwater beneath
the project area including the impact area was found within 5-7 m below ground level, which
is not alarming but the location of Netrokona is very close to the areas where groundwater
level is the lowest. From the following figure, it can also be seen that Netrokona has a higher
difference between potential and net recharge of groundwater, which means the rate of
recharge at the project area is very slow.
Figure 6.21: Depth of Dry-period Groundwater and Difference between Potential and
Net Recharge of Groundwater of Bangladesh
It was observed during the field visit that majority of the local people use electric motors to
abstract groundwater from a depth more than 120 m below the ground level. Several deep
tube-wells were also found to draw groundwater from the depth of 120~150 m. Local people
also stated that wells are dug to such long depth not because of availability issue but
because of quality issues such as iron and odor.
81
Environmental and Social Baseline
Quality of groundwater
According to the Department of Public Health of Bangladesh, groundwater up to the depth of
30~40 m in and around the project area contain iron and groundwater from 73 m to 105 m is
suitable for drinking (IWM, 2019).
Groundwater quality was assessed in the field from three sample locations surrounding the
proposed NEZ project area. Water samples were collected from deep tube wells. The
locations of the sampling sites are presented in Table 6.8 and Figure 6.22.
Depth from
Sample GPS Collection
Location surface
ID Coordinate date & time
(m)
North-West Corner of the project area 85 m N 240 55´ 14.3´´ 06/01/2020;
GW-1
(Shingher Bangla, Netrokona) E 90º 46´ 26.5´´ 10:50 am
North-middle side of the project area 68 m N 240 55´ 31.3´´ 06/01/2020;
GW-2
(Thakurakona, Netrokona) E 90º 46´ 57.6´´ 9:37 am
South-West corner of Komol/Rupsha 95 m N 240 55´ 33.8´´ 06/01/2020;
GW-3
Beel (Shingher Bangla, Netrokona) E 90º 46´ 27.9´´ 12:50 pm
82
Environmental and Social Baseline
83
Environmental and Social Baseline
A number of parameters were tested in the laboratory. Acidified and non-acidified bottles
were used for samples to measure metallic and non-metallic concentrations respectively.
Test results, analysis method as well as Bangladesh standards for drinking water (according
to Bangladesh Environmental Conservation Rules, 1997) are presented in Table 6.9. From
the monitoring data, it can be observed that most of the parameters of the samples, GW-1
and GW-3 were within the standard limits except for COD, chloride at both locations and
fluoride, manganese for GW-1. The sample, GW-2 showed higher concentrations than the
maximum acceptable values for turbidity, COD, manganese, iron and lower concentrations
than the minimum acceptable value of DO and chloride. The reason of such bad quality
could be that the water was being abstracted from a higher elevation underground than the
other two samples. However, parameters such as pH, temperature, color, TDS, TSS,
Sulphate, phosphate for the sample GW-2 were within the standard values. Chloride was
found to be very low while COD was observed to be very high at all the locations.
Note: NTU- Nephelometric Turbidity Unit; UVS- UV- Visible Spectrophotometer; CRM- Closed Reflex Methods;
AAS- Atomic Absorption Spectrophotometer; LOQ- Limit of Quantification; LOQ for Nitrite-N is 0.02 mg/l
84
Environmental and Social Baseline
6.2.7 Drought
Drought conditions for the Netrokona Sadar Upazila was assessed based on Standardized
Precipitation Index (SPI) of annual rainfall. The analysis was based on gridded rainfall data
for the period from 1965 to 2012 (Figure 6.23). During this period, it was found that in this
Upazila, 15% of the years were dry: one extremely dry year, one severely dry year and 5
moderately dry years (IWM, 2019).
85
Environmental and Social Baseline
86
Environmental and Social Baseline
87
Environmental and Social Baseline
88
Environmental and Social Baseline
89
Environmental and Social Baseline
6.3.2 Ecosystem
The study area lies in the North-eastern haor region. The haor ecosystem possess unique
characteristics with many beels, canals and river system especially in the northeast region of
Bangladesh. Climate, and its influence on soil water availability, is the most important driver
of the density and diversity of plants found in the ecosystems. Interactions between plants
and water play a central role in the energy, water, and carbon cycles, which we rely on to
grow food and maintain a habitable climate. To forecast critical earth system functions such
as water availability and agricultural productivity, study is conducted to investigate how
rainfall variability at daily, seasonal, and inter-annual scales impacts ecosystem structure
and functions.
The prominent river systems and their tributaries and distributaries crisscross the study area.
The existing scenario of the haor ecosystem with low lying area for crop cultivation,
homesteads with planted fruiting trees and built-up area as embankments and floodplains
mostly inundated in the monsoon and post-monsoon seasons.
The vegetation, one of the major components of the ecosystem especially in the haor area
can be considered as a number of classes. Each type is assemblage of particular plant
species on the basis of a characteristic of particular environmental conditions such as hydro-
period, flow regime, water and soil quality. Therefore, wetland condition ranges from
perennial aquatic lowlands to seasonally dry uplands.
The vegetation of the project influence area including project area can be categorized into
eight groups, namely - 1) Submerged plants, 2) Free floating plants, 3) Rooted floating
plants, 4) Sedges and meadows, 5) Floodplain grassland, 6) Crop field vegetation, 7)
Roadside vegetation, and 8) Homestead vegetation. Detail description of these vegetation
types is given in appropriate subsections under the ecosystem resources.
90
Environmental and Social Baseline
Aquatic vegetation has been classified into submerged vegetation, free-floating vegetation,
rooted vegetation, sedges and meadows. The population and diversity of these aquatic
vegetation types in this project area (500 acre) is comparatively low due to human induced
pressures and regular cultivation practice as well as fishing and practice of bio-fertilizer and
bio-gas production. People involved in cultivation and capture fishery were also consulted to
gather information on aquatic ecosystem. A few aquatic vegetation found during the major
field investigation are presented in Table 6.10.
91
Environmental and Social Baseline
frequently seen in the project area. Habitats are the edges of crop field, canal and river
banks associated with bushes and standing crops.
The large mammals have been affected by hunting and almost on the verge of extinction.
Currently, small to medium-sized mammal species were reported available in this project
area namely; Rats, Common Mongoose, Indian Civet, Jungle Cat, Bengal Fox (Vulpes
bengalensis), and Jackals (Canis aurues). Except Rats and Jungle Cats, all are threatened.
In the aquatic habitat, the Skipper Frog (Euphlyctis cyanophlyctis) is frequently observed
species. Of the reptiles, common aquatic snakes include the Checkered Keelback
(Xenochrophis piscator) and Water Snake (Atretium schistosum) are also observed.
Besides, a good number of waterfowl including migratory birds were found during the field
visit namely; Little Egret (Egretta garzetta), Little Cormorant (Phalacrocorax niger), Indian
Pond Heron (Ardeola grayii), Great Egret (Ardea alba), Common Snipe (Gallinago
gallinago), Spot-billed Duck (Anas poecilorhyncha), and Asian Openbill (Anastomus
oscitans) which were observed roaming in beels, ditches, and, floodplains. The above
aquatic species have been categorized as threatened by the IUCN-Bangladesh (2015).
Photographs of aquatic fauna are given in Figure 6.25 & 6.26.
Figure 6.27: Pond Heron in a Feeding Figure 6.28: Little Egret in Social
Habitat at Soail Beel Interactions at Komol Beel
92
Environmental and Social Baseline
Coconut (Cocos nucifera), Papaya (Carica papaya) and various kinds of plums. The most
important species are Banana, Jackfruit, and Date Palm (Phoenix sylvestris).
The important timber trees are Gazari (Shorea robusta), Tamarind (Tamarindus indica),
Karoi (Albizzia procera), Simul (Bombax ceiba) and Aswatha (Ficus religlosa). In addition to
Gazari and Mango, other timber trees are Jarul (Legerstroemia speciosa), Karoi (Albizzia
procera), Jackfruit (Artocarpus heterophyllus), Cotton (Bombax ceiba), and Palmyra Palm
(Borassus flabelliformis). The latter is useful for its juice and fruit. The bamboo and cane are
common floral species and have multiple uses. Besides, palms are also available and work
against lightening.
The Banyan (Ficus benghalensis) is considered as keystone species globally and was found
common in the study area. Among the shrub Hill Glory Bower (Clerodendrum infortunatum),
Turkey Berry (Solanum torvum) and Hairy Fig (Ficus hispida) were seen to occupy most
habitats. The common herb species are Arum (Alocasia esculenta), Indian Nettle (Urtica
Sp.), Prickly Chaff Flower (Achyranthes aspera), Tulsi (Ocimum americanum), and Bermuda
Grass (Cynodon dactylon).
The crop-field vegetation has low diversity of all types, but it is more important for food and
shelter to wildlife. The major species (weed) that grows with the crop in this area are
Bermuda Grass (Cynodon dactylon), Beefsteak Plant (Perilla frutescens), Spiny Amaranth
(Amaranthus spinosus), Indian Heliotrope (Heliotropium indicum), and Creeping Wood
Sorrel (Oxalis corniculata).
The major roadside vegetation which are mostly planted are; Rain Tree, Mahogony and
Chambul. Some part of roadside is covered with Toddy Palm and Date Palm. Common
shrub species along the roadside are Tulsi (Ocimum americanum), Crown Flower
(Calotropis gigantea), Hill Glory Bower (Clerodendrum infortunatum), Banana (Musa Sp.),
etc. Terrestrial vegetation of the study area is presented in Figure 6.27 & 6.28.
The aquatic ecosystem especially the floodplains possess high density and diversity of
aquatic plants. Water Hyacinth (Eicchornia crassipes) is the most common free-floating
hydrophytes that covers maximum portion of water area of river. Topapana (Pistia
strateotes), Khudipana (Lemna minor) were also found in beel and river water mixed with
hyacinth. Chandmala (Nyphoides cristata) are dominating the floodplain vegetation
community. It was reported that Sedges are quite common during monsoon along the river
bank lines. Helencha (Enhydra fluctuans), Jungle rice (Echinochola Sp.), Asian Water Grass
93
Environmental and Social Baseline
(Hygrorhyza aristata) are the main floral composition of marginal sedges vegetation.
Occurrences of submerged hydrophytes are low inside the beels and river water due to
excessive aggregation of water hyacinth. The floodplains have low density of free-floating
hydrophytes and submerged plants like Hydrilla, Vallisneria, Potramogeton and Otellia.
94
Environmental and Social Baseline
The Bar-headed Goose (Anser indicus) arrives about the first week of November and
departs at the end of February.
Ecosystem Services
Contribution of ecosystem services from the beels and allied ecosystems are widely
recognized. The beels are the main source of water in the project surrounding areas for
sustaining all types of vegetation as well as faunal resources. The seasonal Komol Beel,
Soail Beel, Kaittarashi Beel and Kajapuria Beel water is main source of irrigation. Seasonal
inundation enhances fertility of the floodplains. The aquatic plants of the beels provide good
habitat to local fishes. River and floodplains water is the main habitat as well as breeding
ground for fisheries that meet up partial protein demand of the local people. Cereal crops are
produced from crop field vegetation provide feeds for local people.
Water hyacinth is used as cattle feed during monsoon and afterwards. Water hyacinth is also
used as compost and natural fertilizer to crop fields. Levees vegetation protects settlements
from wave action and erosion. Demand of domestic fuel for cooking and timber for making
furniture are met from homestead vegetation. River levees vegetation also supply fuel and
thatching materials, help carbon sequestration, maintain ecosystem stability and the integrity
of other ecosystems, fish breeding grounds, maintain biological and genetic diversity,
support food chains and habitat for wildlife and protect wildlife It also help pollination,
habitats to a variety of resident waterfowl and a significant number of endangered species of
international interest. Besides it provides shelter to migratory waterfowl, principally ducks
and shorebirds during winter.
In addition, terrestrial ecosystem also provides services via plants used mainly for medicinal
purposes for common diseases from the bark and roots of the Mango, Tulsi, Simul and other
generally useful trees. The wood apple (Aegle marmelos), Gab (Diospyros precatorius) and
Babla (Acacia arabica) provide gum, the seeds of the tamarind produce oil which is used in
painting idols, and the bark of the guava is used for tanning.
Threats to ecosystem
The anthropogenic pressure is the main threat to ecosystem like hunting of waterfowl, and
overexploitation of natural resources like overfishing that has triggered scarcity of
nourishment for waterfowl in their feeding habitat.
11http://www.netrokona.gov.bd/site/page/0416ce70-1e86-11e7-8f57-
286ed488c766/%E0%A6%8F%E0%A6%95%20%E0%A6%A8%E0%A6%9C%E0%A6%B0%E0%A7%87%20%
95
Environmental and Social Baseline
E0%A6%A8%E0%A7%87%E0%A6%A4%E0%A7%8D%E0%A6%B0%E0%A6%95%E0%A7%8B%E0%A6%A3
%E0%A6%BE
96
Environmental and Social Baseline
A list of mostly abundant fish species in the project area is given in Table 6.12 with IUCN
status.
97
Environmental and Social Baseline
a) Indicator Species
Various types of fish species are found in this area, mainly during winter season from
October-December. According to local fishers punti, Kholisha, koi, kakila, baim, batashi,
kachki, kajuli, taki, shol, magur, ayre, pabda, kuchia etc. fish are found abundantly during
post monsoon season, but in monsoon season Goinna, Rani, Puiya, chela, ghora, bacha,
kalibaus, boal, chiatal etc. are also found.
98
Environmental and Social Baseline
(IUCN Bangladesh, 2000). Kuchia inhabits in mud holes in shallow beels and boro paddy
field throughout Bangladesh especially in Sylhet, Mymensingh and Tangail Districts
(Rahman, 1989 and 2005). It often spends its daytime hiding under stones and mud.
Fish Migration
During the monsoon period, some riverine fishes migrate to the floodplain area for breeding,
grazing and nursing purpose. But in winter season, the floodplain area dries up (observed
during field visit) and farmers cultivate crops in that low land area. Fazar Ali canal between
floodplain habitats and river channels act as a lateral fish migratory route or connectivity.
c) Fishing Efforts
During monsoon, all the private lands goes under water and become a single water body;
and as such people avails free access opportunity for fishing. People of this project area are
depended on a single crop (Boro) and fishing (only from natural sources) to earn their
livelihoods. According to local people, around 10% are fishermen who live in Singher
Bangla. They are directly engaged in fishing. But, no permanent fishermen were found in
project area. During monsoon season maximum local people fishes in this area to fulfil their
protein intake. During winter season some ethnic group (Khotrio and Garo) from Rouha
Union comes to catch fish specially Kuchia in Komol and Kazapuria Beel.
99
Environmental and Social Baseline
d) Fisheries Management
Fisheries sector is contributing significantly to the haor economy. During field visit, it was
gathered from the local fishers and elderly people that there is no fishing comity in the
project area. However, Upazila Fisheries officer (UFOs) in Netrokona District informed that,
there is fishing community in the study area who culture fish commercially.
6.3.4 Agriculture
Land Resources
Agro-ecological Zones
The study area and the proposed project area has fallen under the Old Brahmaputra
Floodplain (AEZ-9) and Northern and Eastern Piedmont Plains (AEZ-22) agro-ecological
regions. Details are shown in the Table 6.14 and Figure 6.32.
100
Environmental and Social Baseline
content is low on the ridges and moderate in the basins; topsoils are moderately acidic but
sub-soil is neutral in reaction. General fertility level is low.
101
Environmental and Social Baseline
102
Environmental and Social Baseline
Land use
Gross study area of the proposed project is 77,544 acres of which 500 acres has been
selected for project area. Net Cultivable Area (NCA) in the project area and Study area are
455 acres and 54,859 acres respectively. Detailed land use of the project area and Study
area are presented in Table 6.15 and Figure 6.33 & 6.34.
Table 6.15: Land Use Pattern in both the Project and Study Area
103
Environmental and Social Baseline
104
Environmental and Social Baseline
105
Environmental and Social Baseline
Land Types
There are four land types in the study area. Among the land types, Medium Highland (F1) is
dominant (47%) followed by Highland (F0) which is 26% of the NCA. Distribution of area
under different land type is presented in the following Table 6.16 & Figure 6.35.
Table 6.16: Area under Land Types in the Project Area and Study Area
106
Environmental and Social Baseline
107
Environmental and Social Baseline
Soil Texture
Soil texture is the relative proportions of sand, silt and clay. It influences many other
properties of great significance to land use and management. There are four types of soil
texture in the study area which are clay, clay loam, clay loam/loam and loam. Detailed
distribution of soil texture in the project area and Study area is presented in Table 6.17 &
Figure 6.36.
Table 6.17: Soil Texture in the Project Area and Study Area
Soil Quality
Soil quality data is derived from Upazila Nirdeshika of SRDI. According to that database,
organic matter concentration of that area is medium (1.71-3.4%). Nitrogen concentration is
also follows the similar trend. Soils of the study area suffers with Phosphorus deficiency.
This element’s concentration varies from low (6.1-12 ppm) to very low (<6.1 ppm). The area
is also rich is Zinc concentration in soil. In case of Boro and Sulphur concentration, the study
area shows a mixed situation with both high and low concentration. But in combination of
these elemental composition, this area is suitable for agricultural practice. According to
BARC, soil fertility status of this area is high.
108
Environmental and Social Baseline
109
Environmental and Social Baseline
Drainage Characteristics
Drainage plays a vital role in the management of soil. Drainage classes of the project area
and Study area is Imperfectly Drained (51% of NCA) followed by Poorly Drained (49% of the
NCA) as shown in Table 6.18 & Figure 6.37.
110
Environmental and Social Baseline
111
Environmental and Social Baseline
Agricultural Resources
Existing cropping pattern by land type, cropping intensity, cropped area, crop yield and
production, inputs and irrigation are discussed below.
Farming Practice
Agricultural crops are grown by cropping seasons. There are two distinct cropping seasons
in a year viz. Kharif and Rabi seasons. The Kharif season starts from March and ends in
October while the Rabi season starts from November and ends in February. Based on crop
adaptability and crop culture, the Kharif season has been further sub-divided into Kharif-1
(March-June) and Kharif-II (July-October) season.
The Kharif-I season is characterized by the uncertainty of weather of alternating dry and wet
spells. Some agricultural potential land remains fallow in this season in the project area. In
the Study area, mainly Aus (both Local and HYV) and summer vegetables are grown in this
season.
The Kharif-II season experiences wet and cloudy environment and heavy rainfall but uneven
distribution, low solar radiation, high temperature and humidity. According to local farmers,
HYV T. Aman crop is grown in the project area and in the study area Local Aman, HYV T.
Aman, maize, and summer vegetables are grown in this season under rain-fed condition.
Rabi season crops are favoured with high solar radiation, low humidity and temperature, but
lack of adequate soil moisture depresses the crop yield. HYV Boro crop is grown in the
project area and in the Study area HYV Boro, maize, wheat, mustard and winter vegetables
are grown in the in this season.
Cropping Pattern
The most prominent cropping patterns in the project area is Fallow – Fallow – HYV Boro in
F2 land and Study area dominant cropping patterns is Fallow – HYV Aman – HYV Boro in F1
land. Detailed cropping patterns by land type in different blocks are presented in Table 6.19.
In the project area 148 acres of land is medium low land (F2), land which normally is flooded
between 90 -180 cm deep of inundation continuously for few months in flood season and
141 acres of land is Low land (F3), Land which normally is flooded between 180 and 360 cm
deep of inundation continuously for few months in flood season. In the project area F2 land
is much closed to the F3 because it’s very risky to grow more than one crop.
112
Environmental and Social Baseline
Table 6.19: Cropping Patterns in the Project Area and Study Area
Project Area Study Area excluding project area
Land Total Study % of
Type Area % of Area % of Area (acre) NCA
Cropping Pattern Cropping Pattern
(acres) NCA (acres) NCA
90 20 Fallow – HYV Aman – HYV Boro 7,890 14 7,980 14
Fallow – HYV Aman – HYV HYV Aus – HYV Aman – HYV Boro 4,918 9 4,918 9
F0
Boro HYV Aus – Summer vegetables -
1,580 3 1,580 3
Maize
28 6 Fallow – HYV Aman – HYV Boro 8,990 16 9,018 16
Fallow – HYV Aman – HYV
HYV Aus – HYV Aman – HYV Boro 5,480 10 5,480 10
Boro
F1 HYV Aus – Maize – W. vegetables 4,370 8 4,370 8
Fallow – Local Aman – HYV 48 11 Fallow – Local Aman – HYV Boro 3,750 7 3,798 7
Boro Fallow – HYV Aman - Maize 3,270 6 3,270 6
Fallow – HYV Aman - Mustard 1,990 4 1,990 4
Fallow – HYV Aman - Wheat 1,267 2 1,267 2
F2 Fallow – Fallow – HYV Boro
148 33 Fallow - Fallow - HYV Boro 3,280 6 3,428 6
Fallow – HYV Aman - HYV Boro 3,280 6 3,280 6
141 31 Fallow – Fallow – HYV Boro 3,515 6 3,656 7
F3 Fallow – Fallow – HYV Boro
Fallow – Local Aman – HYV Boro 1,280 2 1,280 2
Total 455 100 54,860 100 55,315 100
Source: CEGIS, 2020 (estimated by CEGIS based on field data collected from UAO, SAAO of DAE and local farmers)
113
Environmental and Social Baseline
Aman Rice straw in the project area Boro seed bed in the project area
Farmers are preparing field for Boro Rice Transplanted Boro Rice Cultivation
Crop production
In the project area, the annual clean rice production stands at 2,161 metric tons while in the
Study area, clean rice production is 298,624 metric tons and non-rice crop production is
105,900 metric tons. Detailed data on crop area, yield rate and crop production in project
area and Study impact area are presented in Table 6.20.
114
Environmental and Social Baseline
Table 6.20: Cropped Area, Yield and Production of the Project Area and Study Area
Study Area excluding
Project Area
project area
Total Total
Production
Production
Cropped Production
Yield (ton /
Yield (ton /
Crop Name
Area (Metric
(acres)
(acres)
(Metric
(Metric
(acre) tons)
tons)
tons)
acre)
acre)
Area
Area
HYV Aus 0 1.9 - 16,348 1.9 31,061 16,348 31,061
Local Aman 48 1.9 91 5,030 1.9 9,557 5,078 9,648
HYV Aman 118 2.5 295 37,085 2.5 92,713 37,203 93,008
HYV Boro 455 3.9 1,775 42,383 3.9 165,294 42,838 167,068
Total: Rice 621 2,161 100,846 298,624 101,467 300,785
S. Vegetables 0 12.5 0 1,580 12.5 19,750 1,580 19,750
W. Vegetables 0 13.5 0 4,370 13.5 58,995 4,370 58,995
Mustard 0 0.99 0 1,990 0.99 1,970 1,990 1,970
Wheat 0 3.8 0 1,267 3.8 4,815 1,267 4,815
Maize 0 4.2 0 4,850 4.2 20,370 4,850 20,370
Total: Non-rice 0 0 14,057 105,900 14,057 105,900
Grand Total 621 114,903 115,524
Source: CEGIS field estimation, January 2020, UAO, SAAO of DAE and local farmers. * Clean rice
Cropping Intensity
In the project area, net cultivated area is 455 acres and total cropped area is 621 acres,
resulting the cropping intensity to be 136%.
On the otherhand, in the Study area, net cultivated area is 54,859 acres and total cropped
area is 114,903 acres giving rise to 209% cropping intensity in the area.
Crop Damage
Crop damage information over the last five years were collected from the Sub-Assistant
Agriculture Officer (SAAO) and local farmers both for project area and Study area. A total of
5.5 Metric tons HYV T Aman crop was damaged in the project area while a total of 22 Metric
tons HYV T Aman crop was damaged in the Study area.
Irrigation
The farmers are using LLP and STW in the project area. On the other hand they are using
LLP, STW and Deep tube well in the study area. Mainly irrigation is provided for growing
HYV Boro, in the project area and HYV Boro, vegetables and other crops in the Study area.
Agricultural Inputs
Seed, labor, fertilizer and pesticide are the major inputs for crop production. The seed rate
used by the farmers in the project and Study area are given in Table 6.21. In case of rice,
the farmers are using more seed than recommended as they normally use more seedlings
per hill. In the project area, almost 70% of the cultural practices for crop production are being
done manually. So, agricultural labor for seed sowing, intercultural operations, harvest and
115
Environmental and Social Baseline
post-harvest technologies is considered as one of the essential inputs for crop production.
The labor requirement is not uniform throughout the year. The rate of fertilizer use per acre
varies considerably from farmer to farmer depending on soil fertility, cropping pattern,
financial ability etc. The major fertilizers used in this area are Urea, TSP/SSP, MP and
Gypsum. Farmers reported that they were using TSP but during the field visit, it was found
they applied SSP in vegetables. The use of pesticides depends on the degree of pest
infestation. The major insects as reported by the farmers are stem borer, green leaf hopper,
and Rice bug. Local farmers reported that they were using different types of pesticides such
as Basudin, Furadan, Fighter, Rovral, Ridomil gold etc.
Table 6.21: Agricultural Inputs Used in the Project and Study Area
Pesticide
Seed Labor Fertilizer (Kg/acre) Used by Farmers Used by
Crop Name Farmers
No./ No. of Liq. (ml/
Kg/ acre Compost Urea TSP MP Zn
acre application acre) aprx.
HYV Aus 20 57 0 25 20 15 0 0 150
Local Aman 25 60 0 20 10 0 0 1-2 0
HYV Aman 20 65 0 90 30 25 0 0 125
HYV Boro 18 81 0 55 40 33 0 0 600
S. Vegetables 0.25-1.5 40 405 45 40 33 1kg 2 to 2.5 800
W.
0.25-1.5 40 405 45 40 33 1kg 2 to 2.5 800
Vegetables
Mustard 2.5 49 0 33 15 15 0 0 100
Maize 6-8 30 0 65 50 38 27 2 600
Source: CEGIS field estimation, January 2020, UAO, SAAO of DAE and local farmers
Livestock Population
Livestock population in the project area is very small but a large number of populations of
the Study area earn their livelihood from raising livestock / poultry. Farmers are using cattle
for land preparation but cattle health was observed very poor in both the areas. Detailed
status of livestock and poultry in the household level is presented in Table 6.22.
Table 6.22: Status of Livestock/Poultry in the Project and Study Impact Area
Project area Study area excluding project are Total study
Livestock/Poultry
No. Livestock/Poultry No. Livestock/Poultry area
Cattle/cow/bullock 490 26,605 27,095
Buffalo - 3 3
Goat 55 12,390 12,445
Sheep - 102 102
Duck 15,900 122,890 138,790
Chicken 2,650 953,400 956,050
Source: CEGIS field estimation, January 2020, ULO, DLS and local people
116
Environmental and Social Baseline
Cattles are grazing in crop land under project Goats are at project area
area
Figure 6.42: Livestock and Poultry are in Project and Study Area
Livestock/Poultry Diseases
Productions of livestock and poultry are mainly constrained due to diseases and death of the
population. Livestock population is affected by different diseases like Tarka, Anthrax, Foot
and Mouth Disease (FMD), Black Quarter (BQ) and Hemorrhagic Septicemia (HS),
Diarrhoea and Pest Des Petits Ruminants (PPR). Major poultry diseases are duck plague,
Ranikhet (Newcastle), Fowl Pox and Fowl cholera. Moreover, the unhygienic condition of the
courtyard during this season increases the diseases of poultry birds. July to October (rainy
season) is period of spreading diseases to livestock and poultry population in large scale.
117
Environmental and Social Baseline
There are many deaths of animal and birds every year because of outbreaks of diseases
due to poor drainage conditions. Detailed status of livestock and poultry diseases is
presented in Table 6.23.
12Annual growth rate of Netrokona District, Community Report Netrokona Zila, Population and Housing Census
2011 (BBS, 2012)
118
Environmental and Social Baseline
119
Environmental and Social Baseline
Employment status
Figure 6.42 shows that about 42.2% of the population is employed in different sectors of
which 39.8% are male and 2.4% are female. Around 40.6% of the women are engaged in
household works.
The occupation of the people in the study area is mainly centred upon the agricultural sector
(87%). About 3% people are enged in industrial sector which is very low. Field findings show
that the tendency of the people growing towards non-farming sectors. They are working in
brick fields, roads and construction and many other non-farming sectors. Traditionally,
employment opportunities for women outside the homestead is very limited. Majority of the
labor activities performed by women is at household level (e.g. in rice milling, weaving etc.)
Here, most important factor is that women are moving forward to income generation
activities. Ethnic women are also working in agricultural sector.
120
Environmental and Social Baseline
121
Environmental and Social Baseline
6.4.6 Poverty
Poverty was measured through self-assessment of the people in the study area. This
measurement is mainly based on monetary value. Self-assessed poverty is a well-known
method where people/farmer themselves assess their poverty on the basis of their year-
round food security and income. Their responses were assembled into three categories such
as deficit, balance/breakeven and surplus.
No poverty related data is directly provided in the Census 2011. Local people assessed that
on an average about 55% of total population living in the project area are in balanced or
breakeven condition. Their economic activities are subsistence oriented. They also reported
that 15% people belong to deficit category; they borrow money throughout the year for their
consumption. It was gathered during the field visit that about 30% people belong to surplus
category; who are either large land owner or related to business, some of them live in foreign
countries.
122
Environmental and Social Baseline
Housing condition
In the study area, overall housing condition is not good. On an average, only 0.9% house is
pucka whereas 7.3% are semi-pucka, 79% houses are kutcha, remaining houses are jhupri
(Census 2011). These indicate the low economic status of the people of the area. From the
field survey it was observed that most people are living in kutcha and jhupri houses. The
household pattern shows a grim picture of poverty in the proposed EZ area. The housing
condition is presented in Figure 6.46.
Drinking water
Fresh water which is drinkable to maintain people’s lives in a good manner is regarded as
another indicator to assess standard of living in the study area. Different sources of water
were analysed using both primary and secondary data. Most of the people collect water from
tube-well (some use submersible pump) and other sources but tap water is very negligible
(0.2%). On an average, 89.8% people collect drinking water from tube well and the
remaining 23% collect drinking water from other sources such as ponds (Census 2011).
According to the local people, during the dry season the ground water level drops down and
the operation of hand tube-wells become difficult. Figure 6.47 shows the sources of drinking
water in the study area.
123
Environmental and Social Baseline
Figure 6.50: Hand Tubewell for Drinking Figure 6.51: Deep Tubewell used for
Water and other Domestic Use Irrigation and Drinking
Sanitation facility
Figure 6.50 presents the sanitation facilities prevailing in the study area. It illustrates that till
now about 45% of population are using non sanitary toilet which is not satisfactory. It is also
a matter of anxiety that still 15% households have no sanitation facility. Besides, only 40%
households have sanitary toilet facilities of which 11% are water-sealed and another 29%
are non-water-sealed. So, the overall sanitation scenario of the study area is alarming from
the present perspective.
124
Environmental and Social Baseline
Access to electricity
In the study area, electricity supply is not satisfactory. Only 26% household of the study area
has electricity connection from national grid and remaining 74%, a large portion of the
population are out of electricity facilities. So, access to electricity of the people in the study
area is not satisfactory.
125
Environmental and Social Baseline
Figure 6.53: Pucca Road inside the Figure 6.54: Netrokona to Mohanganj
Project Area Railway Line
126
Environmental and Social Baseline
127
Environmental and Social Baseline
environmental conditions, political ignorance, carelessness and lack of awareness. They are
experiencing countless challenges. As a result, they are moving away from their professions
to seek urban jobs with government and private offices, garment stores, beauty parlars, tea
gardens, factories, police and military services.
Figure 6.56: Garo Community in Figure 6.57: Khatriya (Hindu cast group)
Bhattapara, Rouha upazila, Netrokona Community in Shogundia, Mougati
Union, Netrokona
128
7. Identification and Analysis of Key Environmental Issues
7.1 Introduction
This chapter presents results of environmental screening which were conducted before
carrying out the impact assessment. This screening exercise helped to understand the key
environmental issues, to identify environmental impacts and in general it helped to
understand the scope of environmental and social impact assessment.
129
Identification and Analysis of Key Environmental Issues
As per the master plan of NEZ, the natural drainage pattern will be disrupted
by developing a higher land than the adjacent area as well as isolating the
project area from the connecting canals and thus, free flowing of water
Drainage congestion through the project area would be ceased. This might potentially cause
and Water Logging drainage congestion and water logging problems during a heavy rainfall event
in the construction phase as well as by the improper management of drainage
during the operation phase. Therefore, drainage congestion and water logging
are considered as an IESC.
Due to the establishment of the NEZ, the natural drainage connection will be
disturbed and the natural water storage capacity of the project area will be
Flooding encroached. These might exacerbate both the flash flood and monsoon flood
situation within and around the project area. Hence, flooding has been
considered as an IESC.
Construction activities might change the visual landscape of the project area.
Development of land, site preparation, mobilization of construction equipment
Landscape and
and materials, construction of on-site road network, residential area on green
scenic beauty
field site might affect the scenic beauty. So, landscape and scenic beauty has
been taken as an IESC.
The existing land type in the study area will be changed by the construction of
the proposed project as well as new industries and associated development in
Land use
nearby area. Thus, present agricultural land would be converted into non-
agriculture land. Therefore, land use has been considered as one of the IESC.
The crop production in the project site will be lost permanently due to its
conversion for industrial use. As such, crop production in the surrounding area
Crop production
would be changed because of the changes in land type and land use pattern.
Therefore, crop production is taken as an IESC.
The project area is ‘floodplain’ as it is inundated with tidal and monsoon flood,
which then becomes an ideal fish habitat during wet season. The land
Fish habitat development for the proposed project will convert this floodplain into high land,
and eventually would damage the seasonal fish habitat. Therefore, fish habitat
has been considered as an IESC.
130
Identification and Analysis of Key Environmental Issues
500 acres of land will be acquired for the proposed project. There are seven
semi-pucca structures (shops) and a kindergarten school located inside this
Land Acquisition and
proposed site. Thus, through acquisition, landholders will be dispossessed
Dispossession
and the structures will be evicted. Therefore, Land Acquisition and
Dispossession have been selected as an IESC.
According to field data, all landholders of the proposed project site do not
have legal entitlement. Eventually, landholders without entitlements do not
receive any compensation according to the country’s land acquisition Act.
Local Conflict of Although people with legal entitlements are positive toward the project, people
Interest without legal documents expressed concerns. Thus, conflict could arise
between ‘with’ and ‘without’ entitlement holders as well as voice against the
project might also be raised. Therefore, local conflict of interest has been
considered as an IESC.
About 150 to 200 nearby households are earning their livelihoods from the
proposed project area by means of crop production (during summer) and
Loss of Livelihoods catching fish (during wet season). Therefore, the proposed project will
interrupt their livelihood source. So, the Loss of Livelihood has been selected
as an IESC.
131
Identification and Analysis of Key Environmental Issues
The rural area of study area will be transformed into urban area due to the
Urbanization and
Economic Zone-led industrial development, which, on the one hand, will bring
Economic
economic development, and on the other hand, affect local environment
Development
negatively. Therefore, this has been chosen as IESC.
132
Identification and Analysis of Key Environmental Issues
Employment Opportunity
Groundwater Availability
Species composition
Off-site development
Stock Susceptibility
Loss of Livelihoods
Additional traffic
Crop production
Fish Production
Wildlife habitat
Water Quality
Noise Quality
Fish habitat
Air Quality
Land use
Flooding
Pre-construction Phase
Land acquisition and compensation - - - - - - - - - - - - - - - - √ √ √ √ √ - - - - -
Demarcation of land - - - - - - - √ √ - - - - - - - - √ - - - - - - - -
Engagement of Contractors - - - - - - - - - - - - - - - - - √ - √ - - - - - -
Procurement of labor - - - - - - - - - - - - - - - - - - - √ - - - - - -
Setting Project's bill boards - - - - - - √ √ - - - - - - - - - - - - - - - - - -
Transportation of construction materials √ √ - √ √ √ √ √ √ √ √ √ √ √ √ √ - √ - √ √ √ √ - - -
Construction Phase
Land development √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ - - -
Labor shed construction √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ - - -
Boundary wall construction √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ - √ - √ √ √ √ - - -
Off-site infrastructure development √ √ - √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ - - √
On-site infrastructure development √ √ - √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ - - √
Lake development √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ - - -
133
construction
Operation Phase
CETP construction
sewerage, power, gas, etc.)
√
√
√
√ Air Quality
√
√
√
√
Noise Quality
-
-
-
√
Groundwater Availability
√
√
√
√
Water Quality
Physical
√
√
√
√
Flooding
√
√
√
√
Land use
-
√
√
√
Crop production
-
√
√
√
Fish habitat
-
√
√
√
Fish Production
-
Biological
√
√
√
Stock Susceptibility
-
√
√
√
Wildlife habitat
-
√
√
√
Species composition
-
√
√
√
Loss of Livelihoods
√
√
√
√
Employment Opportunity
√
√
√
√
√
√
√
√
Off-site development
-
-
√
√
Identification and Analysis of Key Environmental Issues
134
Additional traffic
8. Environmental and Social Impacts
8.1 Introduction
The anticipated impacts driven by the proposed project on key environmental and social
components in different phases of the project are discussed in this chapter. If there are no
impacts, anticipated in any phase, also mentioned here. Project phase refers to timeframe
for the project completion, and thus is divided into three: pre-construction phase,
construction phase and operation phase. Pre-construction phase refers to the timeframe
from project formulation to just before the land development activities is started. The land
development work for NEZ is considered construction phase. Finally, when the NEZ
becomes ready and invites investors and their subsequent operations are started, this
timeframe is defined as operation phase.
Water Resources
No impact is anticipated against the selected IECs.
Environmental quality
No impact is anticipated against the selected IECs.
Ecological resources
No impact is anticipated against the selected IECs.
Fisheries
Land acquisition on the proposed 500-acre area will permanently convert the floodplain, beel
and pond into a planned area for the NEZ. The estimated loss of floodplain is about 347
acres and beel is about 43 acres. The estimated fish production loss would be about 333
MT/year.
Agriculture
135
Environmental and Social Impacts
Loss of Livelihoods
There is no resettlement and rehabilitation or land acquisition provision for development of
off-site infrastructures. Seven structures and a kindergarten on the acquired land will be
displaced and would require rehabilitation. Number of affected people will lose their structure
and livelihood. In addition, for the displacement of the kindergarten a large number of
children will be deprived from education opportunity.
About 15 HHs are seasonally dependent on the land by fishing. Besides, about 150 HHs are
directly dependent on the acquired land by agricultural activities. After the land acquisition,
the farmer and fisherman will lose their livelihoods. Moreover, 13 households of Garo
community (minor ethnic group) earn their livelihood partially from the proposed project area
by means of catching kuchia. Their livelihoods will also be affected.
136
Environmental and Social Impacts
educational institute, playground, health care facility etc. The impacts of these interventions
on various environmental aspects are described in the following sections.
Air Quality
Air pollution can occur due to the construction activities as heavy machineries and
construction vehicles will be on operation. Burning of fuel to operate the engines is the main
source of the emission of toxic gases (sulfur, nitrogen, carbon). If low emission measures
could not be undertaken, the pollution will be high, dispersed to the surrounding area, and
affect the residential areas nearby. Besides, generation of fugitive dust particles during
construction and movement of vehicles might affect the air quality. Another source of air
quality deterioration might be the incineration of any waste at the project area. The dredging
interventions required for the land development may also cause air pollution due to emission
from dredgers and houseboats.
Noise Quality
Due to the operations of heavy construction equipment, the noise level would exceed the
existing level. The primary effects of noise pollution would be on the workers. If high noise
could not be controlled, the sensitive receptors near the project area would be affected.
There is a high school very close to the project area. Besides, there are several mosques,
temples and local markets which could be impacted due to noise pollution. High noise could
also disturb the birds and other faunas, specially the migratory birds. These could eventually
impact on the overall ecosystem of this area. Besides the dredging activities may also
increase the ambient noise level.
Groundwater Availability
During the construction period groundwater will be abstracted for the civil interventions as
well as the domestic uses by the workers such as drinking, cooking, bathing and washing.
The additional demand of water will pose negative impact on the availability of groundwater,
although the degree of impact cannot be predicted without detailed study (it is beyond the
scope of this study). However, several studies/literatures already identified the study area as
ground water-stressed, and therefore, this withdrawal of water will accelerate the depletion
further. Moreover, it was gathered from the field that groundwater is available at a larger
depth benath the ground. The additional abstraction during the construction and opeeation
period could further lower the groundwater level.
Water Quality
The quality of both surface water and groundwater might get affected in the construction
phase. If the soil, which will be used for land development, contains toxic concentrations, the
toxicity could contaminate the surface water nearby. Toxicity could also leach through the
ground slowly and contaminate groundwater in the long run. During the mobilization of soil
carrying vehicles and operation of construction equipment, various wastes such as oil, mud,
dust, scrap metal, paper etc. could be generated and dispersed around. Solid wastes and
wastewater will be generated from the labor camps as well. Improper management of these
wastes could contaminate the canals nearby and deteriorate the water quality. Especially,
during the times of rainfall all the wastes from the protect area could be washed away to the
nearby waterbodies and even be travelled to Kangsha River. During dredging the river water
quality could get deteriorated from the turbulence of dredger equipment, spillage of oil and
137
Environmental and Social Impacts
bilge water, improper management of waste inside the dredger etc. Contaminated water
could potentially cause diseases to the local people in case of domestic uses such as
cooking, drinking, bathing. The bad quality of water could also harm the existing fish
resources as well as the health of the micro ecosystem of invertebrates.
Flooding
Almost every year during the monsoon times flooding occurs around the project area. Due to
land development, the natural drainage system will be disrupted which could potentially
increase the flood risk at the surrounding areas. Especially, the areas beside the Kangsha
River might face more flood risks than the existing condition as water flowing capacity will be
partially reduced. Also, during the events of heavy rainfall, flash flood might occur within the
project area due to poor drainage capacity.
Ecosystem
Wildlife habitat
The project area is the combination of terrestrial and aquatic ecosystem that include large
trees and roadside vegetation. Tree community is composed of small to tall trees with
indigenous and exotic species to the peripheries of the project area. Some of them are
138
Environmental and Social Impacts
providing shelter to local wildlife as breeding habitats. Besides, croplands within the project
area also provide macro habitats to some tiny wildlife like Bengal Lizard, Checkered
Keelback, Rat Snake, House Sparrow, Common Myna, Red-vented Bulbul, Rats, Common
Mongoose, Indian Civet, and so on. On the other hand, this project area is lowland with five
beels which has been recognized as feeding habitats to many resident and migratory
waterfowls like Little Egret, Little Cormorant, Indian Pond Heron, Great Egret, Common
Snipe, Spot-billed Duck, and Asian Openbill. Wetland associated with different aquatic
vegetation is also providing support to this wildlife for breeding and shelters for escaping
from predators. As per land development requirement, all habitats with associated
vegetation will permanently be damaged. In addition, wildlife habitat in project influence area
will also get deteriorated during sand mining.
During installation of utility facilities like gas, water, electricity services to the project area will
involve some earth works for pipe setting and overhead transmission lines for electricity
those will definitely destroy existing micro habitats of wildlife in the project influence area. Of
the shrub and herbs, Hill Glory Bower, Turkey Berry and Hairy Fig found associated with
micro habitats might get damaged. Therefore, it is anticipated that a good numbers of wildlife
habitats might be destroyed in this phase.
Species composition
There will be no impact on species composition with this intervention in this phase.
Fisheries
139
Environmental and Social Impacts
production loss from beel and Ponds would be insignificant. Moreover, degradation of water
quality of Kangsha River would decline fish productivity of the river. During land development
activities, if proper management are not taken like fencing/making wall within the project
area the fish habitat of the nearby area might be affected.
Agriculture
140
Environmental and Social Impacts
pollution due to dust while land filling, demolishing structures, construction of industrial
infrastructures etc. There would also be risk of accidents due to operation and movement of
heavy equipment, vehicles and machineries. The labour influx in the local area may have
chance to spread COVID-19 disease, therefore, special measures are needed.
Employment opportunity
Construction of the proposed EZ requires both skilled and non-skilled labourers, which would
create employment opportunities for poor people near the study area. Employment
opportunities will be ensured through two channels (i) direct employment for unskilled labour,
(ii) indirect employment to the local community and women workers (both skilled and
unskilled). Direct employment includes site clearance, excavation, loading and offloading of
materials and deliveries, mason and construction works. The local community members
could take advantage of these opportunities. Employment generation benefits improve the
quality of life of the labourers and enhance their productivity and living standards.
Employment generation, both direct and indirect, through Netrokona EZ will have a
tremendous impact on human development and poverty reduction in this area.
Off-site development
During the construction period, many infrastructural development will take place, which on
the one hand, will provide facilities to the local communities; on the other hand, landowners
will lose their land.
Air Quality
During the operation stage, air quality might deteriorate due to different activities. The major
sources of air pollution could be vehicles and the industries. Unless low emission measures
are adopted by the industries, the emissions of toxic gases would deteriorate the air quality.
Deteriorated air quality have potential negative impacts on public health. In addition, the
ecosystem could get affected by the air pollution.
141
Environmental and Social Impacts
Noise Quality
The noise level of the project area could be changed due to operation of industrial
machineries. The movement of vehicles within the project would also raise noise level. The
hydraulic horns and the sounds of engines could be other sources of noise pollution if
honking could not be controlled. There would be three distinct zones (residential areas
including offices, commercial and industrial zones) within the project area wherein of noise
level should be maintained according to the standard noise rule of Bangladesh. If the
distinction is not considered carefully in terms of noise generation, sensitive receptors such
as residents living inside NEZ, patients in the hospital, young community at the schools or
playgrounds, workers and officials working inside the production chambers would be badly
impacted.
Noise may potentially spread outside and increase the noise level of the environment.
Exposure to loud noises for any length of time causes fatigue of the ear’s sensory cells
which results a temporary hear loss and if the time period is long term irreversible and
permanent hearing problems can occur. For the young children learning disabilities, anxiety,
attention-seeking behavior, reduced motivation and concentration are some of the most
likely negative impacts of loud noises (Kozak & Grundfast, 2009).
Groundwater Availability
During the operation stage, water availability will be a major issue. As stated in the master
plan, among the large industries, there will be integrated textile units, food processing
factories, ceramic industries and pharmaceutical companies. Other small and medium
industries will be light engineering and small/medium manufacturing units. The large
industries consume a lot of water per day. Depending on the specific stages of a composite
textile unit the water consumption ranges from 0.5 to 300 liter of water per 1 kg of production
(Shaikh, 2009). Food processing unit is also one of the most water intensive industries and
for the production of 1 kg of food (of various kinds such as potato, wheat, corn, rice chicken,
beef etc.) approximately 500 to 70000 liter of water is required (Kirby, Bartram, & Carr,
2003). As the numbers and types of the industries are not finalized yet, the exact demand of
water could not be assessed.
Water is not only used for manufacturing purposes, but also for drinking and domestic
purposes by the workers in the industries and the residents. According to the standard value
used by WASA, averagely a person consumes 100 to 150 liter of water per day. According
to the master plan, 40 million liters of water will be required daily based on a rough
estimation and groundwater was selected as the major reliable source of the water supply.
Surface water from Kangsha River will also be used in the wet season. Hence, in the dry
periods groundwater would be the only source of water.
As a result of various uses, the groundwater level might get depleted which would affect the
surrounding area of NEZ as well. Water scarcity could potentially affect the agriculture if
irrigation water would not be available as per requirement. The lowering of groundwater
could even lead to land subsidence in the long run. It was gathered from the field that water
availability is already an issue at certain places and the full operation of NEZ would increase
the problem. To assess the availability problem in detail a separate study is recommended
with more accurate data of demand and resources as well as scenarios with extreme
demand condition such as the combination of dry period and maximum production of the
industries.
142
Environmental and Social Impacts
Water Quality
Water quality of both surface water and groundwater could be impacted if proper
management of solid and liquid wastes would not ensure. As per plan of the project, the pre-
treated effluents as well as the wastewater from the residential and administrative areas
would be collected through a sewerage network and conveyed to a Common Effluent
Treatment Plant (CETP) and Sewerage Treatment Plant (STP) respectively. Due any faulty
operation or any leakage in the collection network the surface water quality of the nearby
water bodies could be deteriorated and would not be fit for domestic use. Besides, it would
also pollute the water of Kangsha River wherein it has been planned to be disposed finally.
If this discharge is carried through open channel and the quality of treated water is not up to
the required level, local agriculture might get affected due to contamination of pollution with
irrigation water.
The solid wastes generated within the project area could be another source of pollution if not
properly managed. There will be separate collection network for the drainage of storm water.
This network will be designed to meet the Komol Beel through four outfall points and Komol
Beel will be connected with the natural drainage at the northern part of the project area. No
treatment of the storm water is proposed by the master plan. Rainwater would likely to wash
out all types of wastes and debris from the land area of the economic zone. The direct
disposal of storm water might deteriorate the water quality of Komol Beel.
Flooding
The flood plain area would be reduced due to filling of project area. However, l the Komol
Beel would be excavated to form a reservoir to store flood water. If the capacities of the
drainage network as well as the reservoir (Komol Beel) are not adequately designed for the
extreme conditions, then the storm water collection pipes and the Komol Beel might overflow
at the time of high flood. There were two sluice gates to control the natural drainage between
Kangsha River and Mogra River although the conditions of those gates were poor. During
operation stage of NEZ, this natural connection will be disrupted and as such, the sluice
gates will become useless unless any diversion channel is developed. There is a FCDI
143
Environmental and Social Impacts
(Flood Control Drainage and Irrigation) project of BWDB at Netrokona Sadar Upazila. The
infrastructures established under this project were intended to facilitate agriculture in this
area. Due to the possible change of land use of the surrounding area of NEZ from
agricultural to residential or commercial, the irrigation outlets might no longer be required,
rather embankments to control flood would be required. As the natural drainage of the
project area will be disturbed, flooding situation might aggravate, unless need based water
management infrastructures are built.
Ecosystem
Wildlife habitat
The wildlife habitat would be impacted during operation phase of the project if appropriate
measures would not be taken as per DoE standard. It is anticipated that some air borne
particles (PM10, PM2.5) will be produced during industries’ daily activities. Similarly, pollutants
e.g. chemicals, oil, grease, etc. might get released through drains to the main river system
and deteriorate water quality. It will also deteriorate healthy aquatic habitats. Feeding
habitats to waterfowls might also decline due to industrial pollution in the nearby aquatic
habitats.
Species composition
Various types of affluent would be released from different industries during construction and
operation phase of the NEZ. The effluents if not properly treated might impact tiny organisms
of both flora and fauna like minor phyla e.g. planktons, benthos, other sensitive species
which might even disappear from existing ecosystem.
144
Environmental and Social Impacts
Fisheries
Agriculture
145
Environmental and Social Impacts
Employment Opportunity
After construction, the proposed economic zone would create huge employment opportunity.
Besides, expansion of industrialization and other associated set up would also generate
additional employment opportunities and associated facilities in future for the local people.
The local market and business will also be expanded. Indirect employment would also be
generated through other opportunity such as agriculture, food production, and retail
business. Besides, the proposed EZ could create some job opportunity for the local
educated young people and outsiders. This employment generation, through Netrokona EZ
will have a tremendous impact on human development and poverty reduction in this area.
146
Environmental and Social Impacts
The ESIA study preliminary found most of the impacts (24 out of 35) will be “major” due to
their magnitude and sensitivity if no mitigation measure is adopted. Thereafter, the ESIA
team carefully identified mitigation measures to avoid, minimize or offsetting which were
discussed in the previous chapter. The residual impacts, impact assuming mitigation
measures would at place, were again assessed. The result says among the 35 identified
impacts, 30 impact will be reduced to “minimal” and five will be reduced to “moderate.” Most
of the moderate significant residual impacts are related to occupation health and safety, and
community health, safety and security.
To understand the risk associated with the occupation health safety and security and
community health safety and security, a further analysis was carried out. Thereafter, further
advance mitigation measures and management plan have been proposed.
147
Environmental and Social Impacts
Temporal Aspects
Residual Impact15
Spatial Aspects
Significance14
Reversibility
Magnitude13
Compliance
Sensitivity
Likelihood
Potential Impacts
Pre-construction Phase
Loss of lands M Mn M Mn M M Md Md Ml
Loss of livelihood of fishermen and farmers M Mn M Mn M M Md Md Ml
Land use of the project area will be permanently changed M Mn M Mn M M Md Md Ml
Loss agriculture production (rice and fish) M Mn M Mn M M Md Md Ml
Construction Phase
Loss of natural water storage due to the encroachment of water bodies M Ml M Mn M Md H M Ml
Temporary water logging due to the disturbance of natural drainage pattern Mn Ml Md Mn Md Md H M Ml
Flooding due to loss of natural drainage connection Mn Ml Md Mn Md Md H M Ml
Deterioration of water quality by dumping toxic/ polluted soil for the land development
Mn Md Md Md Md Md H M Ml
purpose, and improper waste and wastewater management
Deterioration of air quality because of dust and gaseous emissions from vehicles and
Md M Mn Md M M Md Md Ml
equipment
Increased noise level due to construction activities, transportation, equipment running, etc. Mn Md Mn M Md Md Md Md Ml
13 Magnitude has been assessed considering temporal aspect, spatial aspect, reversibility, compliance and likelihood.
14 Significance of an impact has been assessed by its magnitude and sensitivity
15 Residual impact is the significance of an impact which was judged considering mitigation measures proposed in Chapter-9
148
Environmental and Social Impacts
Temporal Aspects
Residual Impact15
Spatial Aspects
Significance14
Reversibility
Magnitude13
Compliance
Sensitivity
Likelihood
Potential Impacts
149
Environmental and Social Impacts
Temporal Aspects
Residual Impact15
Spatial Aspects
Significance14
Reversibility
Magnitude13
Compliance
Sensitivity
Likelihood
Potential Impacts
150
9. Environmental and Socio-economic Impact Mitigation
Measure
The mitigation measures of impacts have been assessed according to three basic
subsequent principles: avoidance, minimizing and off-setting of impacts. In the assessment,
“impact avoidance measures” refer to the adoption of any mitigation measure to avoid those
impacts. “Impact minimizing measures” refer to mitigation measures that can minimize
impacts at best. Finally, “impact off-setting measures” refer to mitigation measures that
would be adopted to compensate the impacts. In the following table, both environmental and
Socio-economic Impacts and associated Mitigation Plan are given. In the table, all three
principles are not discussed; instead, the applicable proposed measures are given only.
151
Environmental and Socio-economic Impact Mitigation Measure
152
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
A2 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
local
agitation/conflict.
3 ISC: Loss of Livelihoods
Impact Offsetting Measures:
Proper compensation should be
ensured (cash/land for land);
Introducing deferent training
scheme (capacity building,
vocational, agricultural, fisheries,
livestock and SME training) for the
About 150 project affected people;
households earn their Arrange different special training
livelihoods (either scheme (sewing, cattle, livestock
fully or partially) from and SME training) for the Project
Appointed
the proposed land. vulnerable project affected implemented
consultancy firm
Therefore, the land women; authority
acquisition would Ensure the alternative livelihood
affect their for project affected people
livelihoods. using/living in the khas land;
Give priority to the affected people
by engaging them in different
project activities based on their
skill;
Ensure special scheme for the
ethnic community for the
restoration of livelihood;
153
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
B1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
mobilization and need to be kept isolated form the the project area
operation of the environment by keeping the
construction doors shut or putting layer of
vehicles, equipment curtains to minimize the
and dredger loudness.
Dredging activities should be
limited to daytime only.
Unnecessary honking should be
avoided.
3 IEC: Groundwater Availability
Impact Minimizing Measures:
Depletion of Surface water from the nearby
BEZA and
groundwater level rivers should be used for
Contractors
due to additional construction purposes at least in BEZA
operating inside
demand for the the wet periods of the year.
the project area
construction works Consumption of water should be
optimized and efficient.
4 IEC: Water Quality
Impact Avoiding Measures:
Deterioration of
water quality by The pollution/ toxicity level of the Contractor
dumping toxic/ soil that will be dumped for land deployed for the
4.1 development should be tested BEZA
polluted soil for the land development
land development before dumping. activities
purpose Polluted soil must not be used for
land development or any other
construction activity.
Impact Avoiding Measures:
Construction of wastewater
treatment plant at the very
begging of land development
phase or at least before other
construction works start should
be initiated and wastewater
Deterioration of
treatment should be practiced. If
water quality due to BEZA and the
not possible to make proper
improper solid contractors
4.2 drainage collection network, BEZA
waste and operating inside
ditches can be excavated to carry
wastewater the project area
the wastewater.
management
Solid wastes should be
preliminarily managed by the
workers at wherever the
construction work is going on.
Then collection, gathering and
proper dumping should be
ensured by a common authority.
154
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
B1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
Impact Minimizing Measures:
Temporary wastewater retention
basin should be installed at the
proposed site for wastewater
treatment plant and ditches
should be excavated to carry the
wastewater. Wastewater should
retain there for a certain period
before disposing into the
environment. Moreover, planting
of aquatic vegetation in the BEZA and/or the
retention basin would enhance main land
BEZA
the performance of it. development
The contractors should be contractor
complied to manage their solid
waste in a competent manner
and monitoring activities should
be operated at a regular basis to
check if any soil is dumped on
the open environment.
Natural drainage pattern should
be kept open and active so that
no clogging of wastewater or
construction effluents occurs.
Impact Avoiding Measures:
No solid waste and wastewater
produced inside dredger should
not be disposed into the river,
rather collected inside the
Deterioration of dredger and disposed at
designated places. Dedging
4.3 water quality due to BEZA
contractors
dredging activiteis Impact Minimizing Measures:
Re-suspension of dredged soil
could be minimized by pausing
the dredging activities during high
discharge scenarios (rainy day,
flooding)
5 IEC: Drainage Congestion and Water logging
Impact Avoiding Measures:
Natural drainage connections
Temporary water could be kept unchanged and BEZA and/or Civil BEZA and/or
logging due to the untouched contractors Civil contractors
disturbance of No blocage could be caused by working for NEZ working for NEZ
natural drainage the placement of dredger
pattern equipment
Impact Minimizing Measures: BEZA and/or
BEZA
Regular monitoring should be another
155
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
B1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
applied to check if any perennial consultant
natural drainage way is clogged engaged by
or reduced in capacity by any BEZA
intervention
6 IEC: Flooding
Impact Avoiding Measures:
The formation level of the land
should be designed at an
elevation higher than the
historical peak flood level (say at
100 yr. return period flood level
plus free board). Considering the
historical maximum flood level
BEZA and/or Civil
around 12 mPWD or more than
contractor
this can be chosen as the BEZA
deployed by
minimum land elevation.
BEZA
To avoid the monsoon flood,
temporary high dykes should be
built around the project area.
Dykes would be helpful at the
preliminary stages of land
development. This will be a hard
measure on the environment and
not certainly preferable.
Flooding due to Impact Minimizing Measures:
loss of flood Temporary water storage could
retention area and be developed by excavating pond
natural drainage alike water bodies inside the
connection project area.
Major rivers and canals around
BEZA and/or Civil
the project area should be
contractor
enhanced in terms of discharge BEZA
deployed by
capacity so that they would not
BEZA
overflow during wet periods
To minimize the effects of internal
flooding, local drainage system
should be developed by
excavating temporary canals to
flash out the storm water.
Temporary wastewater retention
basin should be installed at the
proposed site for wastewater
BEZA and/or the
treatment plant and ditches main land
should be excavated to carry the BEZA
development
wastewater. Wastewater should
contractor
retain there for a certain period
before disposing into the
environment. Moreover, planting
156
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
B1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
of aquatic vegetation in the
retention basin could enhance
the performance of it.
Natural drainage pattern should
be kept open and active so that
no clogging of wastewater or
construction effluents occurs.
7 IEC: Solid waste and Wastewater
Impact Avoiding Measures:
Solid wastes should be
preliminarily managed by the
workers at wherever the
construction work is going on.
BEZA and the
Then collection, gathering and
contractors
proper dumping should be BEZA
operating inside
ensured by a common authority.
the project area
Wastewater produced anywhere
should be carried out through
proper collection network and
discharge with the existing and
the closest sewerage network.
Impact Minimizing Measures:
Contractors should spray water to
Accumulation of avoid the dispersion of debris
construction debris, while the land development
solid waste and works.
wastewater that Curtains should be used around
might impact the each site of construction works.
environment
Construction wastes should be
collected by each contractor and
transport to the proper dumping
site. Contractors
Wastewater retention area could operating inside BEZA
be developed where all the the project area
wastewater would be retained for
a certain period before disposing
outside of the project site.
The contractors should be
complied to manage their solid
waste in a competent manner
and monitoring activities should
be operated at a regular basis to
check if any soil is dumped on
the open environment
8 IEC: Wildlife habitat
The project area is Impact Minimizing Measures: BEZA and
DoE
the combination of Sand should not be collected contractors
157
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
B1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
terrestrial and from the vegetative area to fill the
aquatic ecosystem proposed project area;
include large trees Loading and carrying sands to
and roadside destination should be done in a
vegetation as well careful manner to avoid damage
as lowland with five to outside wildlife habitats;
beels which has
Spray water to entire land filling
been recognized as
area to keep adjacent location
feeding habitats to
out of dust pollution; and
many resident and
migratory Do not overload truck in order to
waterfowls. keep sand amount manageable
Wetland associated not to damage other wildlife
with different habitats on the way.
aquatic vegetation Dredging activities should not be
is providing support done during night time
to this wildlife for
breeding and
escape from
predators. Due to
land development
work, all habitats
with associated
vegetation will
permanently be
damaged. In
addition, wildlife
habitat in project
influence area will
also get
deterioration during
sand mining.
9 IEC: Fish habitat
Impact Minimizing Measures:
The Komol Beel area might be
conserved for fisheries
Land development activities
The proposed land
should be done by making wall or
development would
fencing. BEZA,
cause permanent
loss of flood plain, Land development should be
Independent
beels and avoided during fish breeding BEZA, Environmental
season (May-September). Contractor, DoF and Social
waterbodies
Consultant, DoE
prevailing within the Land development activities
and Local DoF
proposed 500 acre should be done in dry season.
of land Collaboration could be made with
BIWTA and BWDB for dredging
the Kangsha river and the
dredged materials might be used
for land development after proper
158
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
B1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
test of dredged materials.
A detail feasibility study and ESIA
should be conducted for dredging
as well
A detail survey should be carried
out under this study before
selecting the dredging alignment
in the Kangsha River for avoiding
important fish habitat area.
Impact Offsetting Measures:
DoF might promote and
strengthen fish conservation
activities in nearby beels and
permanent wetlands.
DoF could also extend training
program on advance aquaculture
technology in other beels and
wetland areas surrounding the
proposed NEZ.
10 IEC: Fish Production
Impact Minimizing Measures:
The proposed Lake (converted
from the Komol Beel) of the NEZ
should be used for fish
production.
The lake should be connected to
nearby canal outside of the
project area.
About 243 MT of
The water quality of the lake
fish production
should be conserved and
would loss annually BEZA, Contractor BEZA, DoE and
monitored.
due to conversion and DoF Local DoF
of fish habitat to Impact Offsetting Measures:
NEZ DoF might promote and
strengthen fish conservation
activities in nearby beels and
permanent wetlands.
DoF could extend training
program on advance aquaculture
technology in other beels and
wetland areas surrounding the
proposed NEZ.
10 IEC: Land use change
Existing land use Minimizing measures
would be changed
into permanent The government should restrict BEZA, contractor BEZA, IESMC,
unplanned and unsustainable contractor
structures in the
growth of industries outside the
project area.
159
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
B1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
Besides, adjacent NEZ area.
area might also get The local government should
changed due to prepare an integrated plan to
induced guide overall economic
development. development, land use change,
transition from rural to urban area
etc.
Agricultural land, permanent
wetland, important ecological
area, etc. should be protected
from unplanned and
unsustainable development.
11 IEC: Production loss
Minimizing measures
The notice of economic zone
activities would be circulated to
the affected farmers before
starting of farming activities.
The work should not be
continued through the ripened
crop fields.
The project work should be
Damage of
delayed for allowing the farmers
standing crop in the
to harvest their standing crop. BEZA, IESMC,
project area and BEZA and DoE
area adjacent to the Adequate compensation should
Contractor, DoE
project area. be provided to the farmers for
loss of crop production for three
years for economic zone.
Proper fencing, run-on and run-
off drainage should be
constructed to prevent spillage of
sediment during rain or flood.
The construction activity must be
confined within the project
boundary.
160
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
B2 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
Be careful of touching eyes, nose
or mouth.
Clean hands often. Use soap and
water, or an alcohol-based hand
rub.
Equipment to be used by
competent (trained) operators;
One/two paramedics doctors for
preliminary treatment, first aid
tool box, all time ambulance
facilities should be arranged;
Some basic facilities e.g. safe
drinking water, proper sanitation,
labor shed with light and air
should be arranged for the labor;
Provide health insurance to avoid
accidental events like disabilities
or death of workers during this
phase of the project;
Impact Offsetting Measures
An induction training on
occupational health & safety
should be arranged for all the
labors and professionals before
starting the construction;
Arrangement of firefighting
equipment with training to the
staffs from workers to officers;
Staff should be trained on
emergency hazard handling
procedures;
Safety and awareness talk should
be ensured through EPC Project
Appointed
contractor in each day prior to implemented
consultancy firm
starting the work; authority
Awareness knowledge should be
disseminated using local
language and instruments;
EPC contractor should establish
grievance mechanism for the
labors with proper
documentation;
Modern equipment and
machinery should be deployed to
reduce noise;
Provision and use of high visibility
clothing by workers;
Air plug should be used by the
161
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
B2 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
workers;
2 ISC: Community Health and Safety
Impact Offsetting Measures
Using modern and properly fit
equipment and machineries so
that sound generation is reduced;
Using noise absorptive Panels in
order to reduce noise levels in
buildings and enclosed spaces.
Using Sound Barrier Walls;
Need proper danger signs/
posters to avoid accident at
construction site;
Public awareness campaign on
The adjacent living COVID-19, safety and health
community might risks should be conducted with
get affected during local communities prior to and
Project
the construction during construction phase of the Appointed
implemented
phase by means of project; consultancy firm
authority
noise, dust, Waste management plan, air,
accident and other soil, noise and water pollution
risks controls are required to be
adopted;
Project area should be well
fenced;
Ensure regular water spraying
vehicle to reduce dust (at least
twice in a day) at both project
area and adjacent project area;
Directions given by DoE should
be obeyed during implementing
noise producing activity;
Using water spraying vehicle to
absorb dust;
3 ISC: Employment opportunity
Impact Offsetting Measures
Construction of the
Project surrounding unemployed
proposed EZ
potential people should get
requires both skilled
prioritized in recruitment;
and non-skilled
Labor wage should be fixed
laborers, which Project
based on the current wage rate of Appointed
would create implemented
the project area; consultancy firm
employment authority
opportunities for Equal employment opportunities
poor people in the should be given to women;
vicinity of the study Provide the skill enhancement
area. training to locals to carry out
specific tasks and enhance the
162
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
B2 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
skill of local people;
Process of labor recruitment and
their payment process should be
transparent and influenced free
by the local influential parties.
4 ISC: Roadway and Communication
Impact Avoiding Measures:
Construct an alternative road for
movement of the people to go to Project
Appointed
the other side of the project or implemented
consultancy firm
allow people to use the authority
The development connecting road through the
project site.
project may disrupt
the communication Impact Offsetting Measures:
of the two village. Should deploy traffic guards in
Besides, for the the entry gate with using
operation and adequate traffic management
movement of heavy tools;
equipment, vehicle, The existing road should be
Project
machineries, the widened to four lane road; Appointed
implemented
normal Using adequate signs and signals consultancy firm
authority
communication to the adjacent areas;
might be disrupted Existing earthen road should be
and might damage converting to paved road;
the road. If possible, equipment movement
should be carried out in non-peak
hours;
5 Off-site development
During the
construction period,
many infrastructural
development will Impact Offsetting Measures:
take place, which
Recruit local people in the Project
on the one hand, Appointed
development work implemented
will provide facilities consultancy firm
Provide compensation to the authority
to the local
affected landholders
communities; on
the other hand,
landowners will lose
their land
163
Environmental and Socio-economic Impact Mitigation Measure
164
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
C1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
Regular monitoring should be
carried out to check the noise
level generated from the
industries. Penalty should be
imposed in case of n
exceeding event of the
permissible standards.
Noise minimizing measures
such as isolation of the
engine rooms, putting layers
of curtain to cover open noise
sources should be practiced
by the industries.
Sensitive areas including
school, hospital and office
areas should be declared as
‘silent area’ and honking
within these areas should be
restricted.
In addition, unnecessary
honking in the industrial areas
should be discouraged.
3 IEC: Groundwater Availability
BEZA, NEZ BEZA, NEZ
Impact Avoiding Measures: authority, authority,
Alternate source like surface authorities authorities
water or other sustainable mandated to mandated to
source of water should be supply water and supply water and
explored. manage water manage water
resources resources
Impact Minimizing Measures:
Facilities to harvest rainwater
should be set up to reduce
the pressure on groundwater
as water source.
Water scarcity due to
high amount of water Recycle and Reuse principle
should be adopted i.e. waste BEZA, NEZ BEZA, NEZ
abstraction
water should be treated and authority, authority,
used in flushing toilet,
authorities authorities
gardening, car washing etc. mandated to mandated to
Efficient and reduced use of supply water and supply water and
water should be practiced. In manage water manage water
this regard good quality resources resources
fittings should be used to
avoid leakage and misuse.
Nearby water bodies should
be regularly maintained to
facilitate the safe recharge of
groundwater.
165
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
C1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
Abstraction from groundwater
during wet period could be
restricted.
Impact Offsetting Measures:
Water meter should be set to
measure water usage for
each consumer and introduce
‘pay per use’ policy.
The rate of groundwater
should be set comparatively
higher than the other NEZ authority NEZ authority
sustainable sources to
discourage groundwater
abstraction. Moreover, the
extra earning from
groundwater could be
invested to install the other
options of sustainable water
sources.
4 IEC: Water quality
Impact Avoiding Measures:
Open discharge of
wastewater specially from the
NEZ authority, all
industries must be restricted NEZ authority
the water users
by enforcing law, introducing
penalty and effective
monitoring
Impact Minimizing Measures:
The sewerage and
Deterioration of wastewater networks should
groundwater quality be monitored and maintained
due to contamination regularly. Minimum leakage
of pollutants from from the source to the
4.1
storm water, sewerage disposal point should be
NEZ authority NEZ authority
pipes, open discharge achieved.
of wastewater and Regular monitoring to
industrial effluents etc. maintain a good water quality
of the Komol Beel and other
water bodies nearby should
be done for safe recharge of
groundwater.
Impact Offsetting Measures:
Water treatment plant could
be set up to treat groundwater NEZ authority NEZ authority
before supply and additional
payment could be imposed.
Deterioration of water Impact Avoiding Measures:
4.2 quality of Komol Beel, The CETP and STP should NEZ authority NEZ authority
Kangsha River and be properly maintained so
166
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
C1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
other water bodies that treatment of waste water
nearby due to, and effluents is properly done.
discharge of improper The disposal network should
treated wastewater be frequently checked
and industrial effluents undertake necessary
etc. due to fault in measures to repair leakage, if
treatment plants. any.
Impact Minimizing Measures:
The industries could be
provided with incentive for
proper treatment of effluents
and waste water by operating
treatment plants
efficiently.The CETP, STP
and the pre-treatment plants
should be regularly monitored
and appropriate actions
should be undertaken
including replacement of the
plants if necessary. Regular
monitoring should be
conducted to prevent all types
of open discharge of NEZ authority NEZ authority
wastewater as well as
effluents.
The quality of water of the
water bodies should be
monitored and eco-friendly
measures should be adopted
to restore water quality.
167
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
C1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
networks should be regularly
cleaned to eliminate the
clogging problems.
The retention capacity of
Komol Beel should be
adequate to store drainage
disposal.
6 IEC: Flooding
Impact Avoiding Measures:
Regulators should be
constructed at the connection
points of Komol Beel and the
existing drainage canals to
control the water level inside NEZ authority NEZ authority
the project area.
Storm water collection
network should function
efficiently and regular
maintenance should be done.
Impact Minimizing Measures:
Dykes could be built around
the NEZ area to prevent flood
water entering from Kangsha
River. However, this might
occur additional flooding in
the surrounding areas.
Occurrence of flash Water retention capacity of
flood and monsoon the surrounding area should
flood due to reduction be enhanced by rejuvenating
of flood plain by land the dried up beels nearby.
filling Emergency management
plans should be developed NEZ authority and NEZ authority
integrating automatic water and water
monitoring of water level, management management
simulation and forecast of
authorities authorities
climate conditions, effective
regulation of water
management structures and
provision for emergency water
diversion facilities.
Volume of induced flood
generated due to filing of land
could be worked out through
model and find out quantum
of runoff that could be
retained in Komol Beel,
neighboring area and balance
tothe Kangsha River.
Impact Offsetting Measures: NEZ authority and NEZ authority
168
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
C1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
Compensation should be paid water and water
to private land owners for management management
taking their lands, if structures structures
necessary, to convert it for
flood water retention basin.
7 IEC: Solid Waste and Wastewater
Impact Avoiding Measures:
All types of industrial and
residential wastes (solid
waste and wastewater) must
be disposed to the designated
BEZA and water BEZA and water
dumping place after proper
management management
treatment according to the
authorities authorities
available best practices.
No wastewater should be
discharged in the open nature
but through the proper
collection networks.
Impact Minimizing Measures:
Accumulation of solid Industries should adopt new
wastes and dispersion technologies to reduce the
of wastewater due to production of wastes. 3R
illegal and principle of Waste
irresponsible management (encouraged by
discharge GoB) should be included in
the production cycle.
Recycling and reusing of BEZA and water BEZA and water
wastewater should be
management management
practiced viz. after treatment
authorities authorities
of waste water could be
recycled for use in cooling of
plants, gardening, toilets, car
washing etc.
Efficiencies of the waste
management measures
should be monitored regularly
and incentive policies might
be adopted.
Impact Minimizing Measures:
Industries and hospitals
Contamination of soil, should have special plans to
surface water and handle the hazardous and
groundwater by toxic toxic wastes. NEZ authority,
materials due to the The pre-treatment plants of industries, NEZ authority
irresponsible the industries should have hospital
management of special features according to
hazardous waste the specific hazardous waste
produced.
Potential hazardous wastes
169
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
C1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
should be dumped and
carried by separate collection
system and final disposal
should be integrated with the
waste management systems
of the Netrokona Sadar area.
10 IEC: Wildlife habitat
Air borne particles
(PM10, PM2.5) will be
produced during
industries daily Impact Minimizing Measures:
activities. Similarly, Keep air and noise quality as
chemicals, oil, grease, per standard directed by the
etc. might be released Department of Environment
to the main river (DoE)
system. Pollutants Set CETP, ETP and STP as
would deteriorate per standard prescribed by
BEZA DoE
water qualities (WQs). DoE
As a consequence, Regular monitor the effluent
aquatic habitat health treatment plant to take care of
would be deteriorated. any problem if occur.
Feeding habitats to Do not release untreated
waterfowls might also garbage outside of the
decline habitat quality industrial park.
due to industrial
pollution in the nearby
aquatic habitats.
11 IEC: Fish Habitat Condition
170
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
C1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
DoE should regularly inspect
the industrial activities and
treatment plants.
Impact Offsetting Measures:
DoF might promote and
strengthen fish conservation
activities in nearby beels and
permanent wetlands.
DoF might extend training
program on advance
aquaculture technology in
other beels and wetland areas
surrounding the proposed
NEZ.
12 IEC: Stop Stock Susceptibility
Impact Avoiding Measures: DoE and DoF DoE and Local
Stock susceptibility of
Natural waterbody/adjacent DoF
fish (SIS) would be
beel should be conserved so
increased of the
that these waterbodies could
adjacent fish habitat
be used as a shelter ground
area.
for fish.
13 IEC: Land use change
Minimizing measures
The government should
restrict unplanned and
unsustainable growth of
industries outside the NEZ
area.
The local government should
Change in land use prepare an integrated plan to BEZA, NEZ,
BEZA, District
due to induced guide overall economic DC/Local
Commissioner
development. development, land use Government
change, transition from rural
to urban area.
Agricultural land, permanent
wetland, important ecological
area, etc. should be protected
from unplanned and
unsustainable development.
13 IEC: Crop production loss
Minimizing measures
171
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
C1 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
guide overall economic
development, land use
change, transition from rural
to urban area.
Agricultural land, permanent
wetland, important ecological
area, etc should be protected
from unplanned and
unsustainable development.
Offsetting measures
Pest infestation that would
increase due huge lighting of
area could be minimized by
Integrated Pest Management
(IPM) through “Light Trap”.
172
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
C2 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
2 ISC: Occupational Health and Safety
Minimizing measures
Wear mask and hands gloves
during the construction work;
Maintain a social distancing;
Be careful of touching eyes,
nose or mouth.
Clean hands often. Use soap
and water, or an alcohol-
based hand rub.
Impact Offsetting Measures:
Risks (i.e. fire,
explosion and Arrangement for firefighting
accident) for workers equipment with appropriate
training to all concerned Project
and employee will be Appointed
workers and officers; implemented
created because of consultancy firm
use of machineries Staff should be trained on authority
and other equipment emergency hazard handling
of the project. procedures;
Safe handling and storage of
flammable chemicals and
fuels;
Equipment to be used by
competent operators;
Appropriate choice of modern
equipment and machinery to
reduce risk of accident; and
Keep provision for use of high
visibility clothing by workers.
3 ISC: Employment opportunity
Impact Offsetting Measures:
Project surroundings
unemployed potential people
should get prioritized in
recruitment;
Labor wage should be fixed
Expansion of
based on the current wage
industrialization will
rate of the project area;
generate additional Project
employment Equal employment implemented Appointed
opportunities should be given consultancy firm
opportunities and authority
to women;
associated facilities in
future for the local Provide the skill enhancement
people. training to locals to carry out
specific tasks;
Process of labor recruitment
and their payment process
should be transparent and
influenced free by the local
173
Environmental and Socio-economic Impact Mitigation Measure
Institutional Responsibilities
C2 Potential Impacts Mitigation Measures Supervision
Implementation
and Monitoring
influential parties;
Affected ethnic community
should get priority in
recruitment;
4 Urbanization & economic development
The establishment of
economic zone in this
area, and coming of
various industries will
lead to transform this Impact Offsetting Measures:
area into an urban
Proper compensation and
center; eventually,
rehabilitation of
regional/national poor/smallholders
economy will be Coming industries NEZA
Prefer affected people into the
developed. However,
recruitment of industrial jobs
this process will
transform agricultural Arrange training for local
youths for employment
land into industrial
enterprises, and
dispossessed
poor/smallholder
people.
174
10. Public Consultation and Disclosure
10.1 Introduction
Stakeholder consultation (a two-way flow of information and opinion exchange), or simply
consultation, is a regulatory process of EIA by which the people's input on matters affecting
them is sought. Its main goals are to improving the efficiency, transparency and community
involvement in policies, programs and projects. Stakeholder Consultation is mandatory for
any development project according to guidelines of DoE, which includes approaching people
to engage them in the project and take their concerns about the impact and benefit of the
project from their point of view.
During the consultation process, the proposed Netrokona Economic Zone as well as its
impacts were discussed with local people. In the consultation process, the stakeholders got
involved with the study consultants in reforming/ developing the project interventions
considering the local needs and aspirations in line with the problems and solutions
suggested by them. The proposed interventions, findings of the EIA and the EMP were
shared with the project stakeholders for obtaining their perceptions, views and feedbacks on
the probable changes likely to happen within the project area.
175
Public Consultation and Disclosure
Type of
Sl. Stakeholders
stakeholders
Local representatives, project affected people, household owners, small
1 Primary
business community, shopkeepers, pedestrians, students and women group.
Zila Parishad, Upazila Parishad, Union Parishad, BWDB, Department of
2 Secondary
Forest, civil society representatives, NGOs and others.
Source: CEGIS, 2019
Table 10.2: Location of Consultation and Discussion during the Field Visit
Type of Number of
District Upazila Place Date Time
consultation Participants
Netrokona Upazila
Netrokona PCM 12.01.2020 11.00 AM 40
Sadar Parishad
Netrokona Key Informant
Netrokona Zila Parishad 11.01.2020 2.30 PM 1
Sadar Interview
Netrokona Upazila Key Informant
Netrokona 12.01.2020 10.00 AM 1
Sadar Parishad Interview
Netrokona Singher Bangla Key Informant
Netrokona 11.01.2020 3:00 PM 1
Sadar Union Parishad Interview
Netrokona Thakurakona Informal Group
Netrokona 11.01.2020 4:30 PM 8
Sadar village Discussion
Netrokona Informal
Netrokona Project area 11.01.2020 9.00 AM 8
Sadar Discussion
Netrokona Informal
Netrokona Jamtola village 12.01.2020 4.30 PM 3
Sadar Discussion
Netrokona Informal
Netrokona Barni village 11.01.2020 10:30 AM 35
Sadar Discussion
Netrokona Bhadrapara Informal
Netrokona 11.01.2020 12.30 AM 10
Sadar village Discussion
176
Public Consultation and Disclosure
they feel that implementation of this project would play great role for development of the
region as well as the country. However, the participants expressed their concerns on several
issues which seemed reasonable.
People’s suggestions about the site are presented below in brief:
Local people expressed positive attitude toward the proposed project
interventions as people will get employment, business opportunity;
People are aware about the project and expect good employment generation
from the EZ;
Local people should be provided employment opportunity in the EZ as most of
the people of this area are labor and practice agriculture;
They emphasized that jobs should be given to locals during both construction and
operation phase preferably as there is large scale unemployment;
People expect agro based industries to come up in region which will help them
selling their products easily. Also they expect the authority will train them to
enhance their productivity by using HYV seeds and modern equipment’s.
Fish based industries should be established as there are lots of people are
dependent on fishing;
People of Bhadrapara, Singher Bangle and other villages expressed their positive
attitude regarding the quick implementation of the project;
They also aware about the pollution and they want only non-polluting industries
should come up in this region and measures should be taken by industries to
control the pollution levels;
They insisted that polluting industries should not be set up in the EZ zone;
They (local people) suggested that the water discharge from the EZ should be
handled properly;
The land acquisition and compensation process should be in proper way;
Construct an alternative road instead of the connecting road passing through the
project site; or the road will be open for the local people;
There is no problem to construct a EZ but the proposed EZ should be eco-
friendlier;
According to the Barni village people, about 30% of land is three cropped land
and they would not lose the land permanently;
They also showed their negative attitude about the project as they would lose
their livelihood (both agriculture and fisheries);
During consultations, local people identified that the proposed project might create some
problems but they showed keenness to proactively work to resolve these minor problems.
They expressed that after implementation, the project would be beneficial for the region as
well as for the country.
A combined table on multidisciplinary problems/issues and solutions/measures is given
below.
177
Public Consultation and Disclosure
The proposed land The Komol Beel area might be conserved for
Fisheries development will cause fisheries.
Resources permanent loss of flood Adequate compensation should be provided to the
plain, beels and waterbodies pond owner for loss of their land.
178
Public Consultation and Disclosure
179
Public Consultation and Disclosure
180
11. Environmental and Social Management Plan
11.1 Introduction
With the aim of ensuring avoidance, minimization, and offsetting of adverse environmental
impacts and enhancement of beneficial impacts The Environmental and Social Management
Plan (ESMP) has been prepared. The ESMP includes Environmental Code of Practices, and
ESMP during pre-construction phase, construction phase and operation phase, and special
ESMP. Generally, the impacts, which are minor or moderate, will be mitigated by adopting
Environmental Code of Practices during construction and operations. On the other hand,
impacts which are critical or major are to be prevented or mitigated by adopting mitigation
measures as discussed in the earlier chapter.
181
Environmental and Social Management Plan
The Contractor must be made accountable through contract documents for the obligations
regarding the environmental and social components of the project.
Compensation Plan
About 2,161 tons rice production of project area would be permanently lost per year due to
the acquisition of land for development of NEZ. The following measures should be followed:
Project Affected Persons (PAPs) losing agriculture land should be compensated
as per the Law of the Land.
Adequate compensation should be provided to the farmers for loss of crop
production for three years for economic zone.
Proper compensation should be given to the land owners by their bank account.
182
Environmental and Social Management Plan
183
Environmental and Social Management Plan
Training Implementing
Selected business/enterprise Households
components organization
Vegetables and crops 150 farming households BEZA
(depending on need
Agriculture assessment and crop (any other affected (by appointing
suitability of the settlement households willing to implementing
area) participate) agency)
Other than those benefits the Project should higher unskilled laborers from the affected
households for the construction activities under the Project. The contractor will give
preference to hiring affected persons willing to work in Project construction activities. In the
operation phase the Proponent can take initiative for employment opportunities in different
industries based on their (affected persons) skill. Employment in the Project construction and
post construction periods will act as an added source of income in the income and livelihood
restoration processes of the affected households.
Relocation of Kinder Garten School
The affected Kinder Garten School should be relocated before the commencement of the
Project implementation so that the Project activities do not interrupt the regular educational
activities of the school.
184
Environmental and Social Management Plan
185
Environmental and Social Management Plan
186
Environmental and Social Management Plan
187
Environmental and Social Management Plan
Workers should use ear muffs while operating heavy equipment and machinery
generating noise of >85 dBA continuously for 8 hours or more.
Equipment and machineries should be of good condition and should be operated
carefully to avoid disruption of the daily activities of the project site.
The contractors should mobilize all construction equipment, machineries and
materials during night time instead of day due to existence of school and
Paurashava office in front of the project area
Equipment and machineries should be of good quality and should be operated
carefully so that it does not make high noise that might disrupt the daily activities
of nearby educational institutions, offices and religious centers;
Construction machineries should have proper mufflers and silencers;
Noise levels from the construction machineries should comply with national noise
standards;
Provision should be made for noise barriers at construction sites if needed.
188
Environmental and Social Management Plan
appropriate times of the day to limit disruption. The transportation problems should be solved
according to the following plans:
Mobilization and transportation of construction materials carrying vehicle should
be limited during day time and could be mobilized at off-peak hour or at night
There should be new temporary road network for the mobilization of the
construction vehicles. The road should be designed especially for heavy vehicles.
For the local people there should be a separate road or a separate lane in a
newly developed road that will cross the project area from the north to the south
so that the existing communication would not get interrupted.
If possible the Netrokona-Sunamganj highway which is adjacent to the project
area should be improved at this stage. In the master plan of off-site
infrastructures, this highway is proposed to be widened from 2 lanes to 4 lanes.
This should be implemented simultaneously so that traffic congestion could be
avoided.
There should be two temporary gates and surveillance should be available there
including temporary office room, guards, monitoring panel with footage from close
circuit cameras etc. The guards should play active roles while entering or exiting
of any construction vehicle which could potentially cause traffic congestion at the
gates.
Traffic signs and flagmen should be placed at the strategic locations to facilitate
easy movement of traffic.
189
Environmental and Social Management Plan
190
Environmental and Social Management Plan
If any water retention basin is excavated to increase the water storage capacity,
their maintenance should be done periodically considering the accumulation in
the basin bed and decrease of capacity.
Regulators at the both connection points of the Komol Beel with the surrounding
canals should be operating according to the requirements.
Other water management structures should be constructed or improved to
enhance the drainage pattern of the overall basin of Kangsha River.
Planning for the irrigation requirements should be taken into account while
planning for new water management infrastructures.
Flood warning system should be developed and in the time of emergency the
operation of the sluice gates and regulators within the overall hydrological area
should be done accordingly.
191
Environmental and Social Management Plan
A smart payment system should be developed. This should include subsidies for
the industries to run their pre-treatment plants and charges on the basis of the
volume or quality of their effluents. Win-win situations for both the industries and
the treatment plant operators should be considered. Subsidies will encourage the
industries to operate their pre-treatment plants and payment for their effluents will
encourage them to maintain the efficiency of their plants.
The treated wastewater from both the STP and CETP should be disposed into
the Komol Beel considering the quality of the treated discharge will be safe for
disposing into the nature. This will at the same time refrain the surrounding water
bodies from being potentially polluted and highlight the urge of the effectiveness
of the treatment plants.
There should be provisions for storm water to be treated up to a certain level of
degree before disposing into Komol Beel. Dry retention areas could be
established at the outfall points of the storm water into the Komol Beel. The
retention basins should be designed in such a way that in the times of rainfall
water could be captured as well as detained at the basin for some period of time.
It will increase the storage capacity, reduce the velocity of storm water inflow into
the beel and in the process improve the quality of water naturally. Screening
facilities should also be available at the connection points of the retention basin
and Komol Beel to capture the coarse solids and other large materials. The
retention basin, especially the screening points must be cleaned after a rainfall
event occurs.
The Komol Beel should be cleaned after periodic intervals to maintain the good
water quality of the beel and eradicate water-logging problems in the natural
drainage system.
192
Environmental and Social Management Plan
Buffer zone should be constructed by planting trees around each plot of the
industries.
The vehicles plying within the NEZ must have ‘fitness certificates’ and the
certificates must be renewed periodically after proper examinations.
The authorities of the industries and the vehicle owners should be acknowledged
about the permissible standards of emissions.
NEZ authority should monitor the emission quality of the industries as well as the
vehicles occasionally and penalty should be charged in case of exceeding of
permissible standards
Plantation of trees along the boundary of the NEZ and at the both sides of the
roads should be done and maintained properly. The green areas, parks should
also be preserved in pristine conditions.
193
Environmental and Social Management Plan
and the consequences will hamper the smoothness of NEZ operation. The waste
management plan of NEZ should address the following activities:
Overall solid waste management should be handled centrally by NEZ authority
along with the primary management by the waste generators.
A team of waste collectors should go from door to door in the residential areas to
collect the solid waste and dump in the primary dumping site built at a suitable
location close to the residential area. The collection could be done twice/ thrice a
week. Dustbins and communal waste dumping facilities should also be placed at
certain locations within the community.
In the industrial and commercial areas, primary dumping sites should be placed
at several locations where the industries would dump their solid wastes every
day.
The waste collection team will plan for effective routes to collect the wastes from
all the primary dumping sites and dump into the secondary dumping site located
within the project area.
Organic and inorganic wastes should be collected separately. The community
and the industries should be trained and well informed about the sorting of
organic and inorganic. Inorganic wastes should be accumulated separately in the
secondary dumping site and materials such as plastic, paper, glass etc. should
be used for recycling purposes.
The domestic and industrial wastewater should be collected to the STP and
CETP respectively. Industries should pre-treat their effluent before discharge.
The treated wastewater from the plants should be disposed into Komol beel
considering the treatment standards will be within the acceptable limits. This will
help the wastewater not to be dispersed into the surrounding nature of NEZ as
well as provoke the treatment mechanisms to be perfect.
The storm water should be collected through separate network and transported to
the Komol Beel. There should be provisions for the storm water to be detained
and preliminarily treated before flowing into the beel. The storm water network as
well as the detention basins should be regularly cleaned. The solid wastes and
the sludge should be carried out to the secondary dumping site and sludge
treatment plant respectively.
The hazardous wastes should be separately gathered by the generators and
collected by the NEZ authority. Depending on the nature of the wastes, suitable
site/s should be selected for the best possible management of the hazardous
wastes.
194
Environmental and Social Management Plan
Along with the official vehicles of the industries, offices and private vehicles of the
residents, there should be provision for a public transportation facility. The people
living adjacent to the project area will use no other mode of transportation but the
public transportation.
Vehicles plying inside the NEZ should have recognizable sign/ sticker on their
bodies. Vehicles having no sticker should have permission from the NEZ
authority to enter the NEZ area.
There could be rickshaws/ auto-rickshaws of a fixed amount of numbers for the
local transportation within the residential areas. However, these vehicles should
not be allowed into the industrial units. If required, a large industry should have its
own transportation system for the workers and professionals inside its area
At the crossings, automatic road signals should be placed and the traffics should
comply the traffic rules.
Appropriate authority should monitor the traffics if they are obeying the laws.
195
Environmental and Social Management Plan
The lake should be connected to nearby canal outside of the project area.
DoF might promote and strengthen fish conservation activities in nearby beels
and permanent wetlands.
Awareness building program should be carried out for the local fishermen.
DoF could extend training program on advance aquaculture technology in other
beels and wetland areas surrounding the proposed NEZ.
196
Environmental and Social Management Plan
197
Environmental and Social Management Plan
198
Environmental and Social Management Plan
To apply such a concept into the operational framework of NEZ the following steps could be
undertaken:
Industries should have their own facilities where wastes would be primarily sorted
into recyclable, reusable, residual and green wastes.
Responsible division for waste management of NEZ should collect the industrial
wastes separately and transport to distinguished chambers of solid waste
management facility. Final separation of wastes should be done here based on
the requirements of raw materials and market opprotunities.
Reusable wastes can directly be transported to the industries where those could
be used as secondary raw materials.
Facilities such as recycling plant, mechanical treatment plant, composting plant
and biological treatment plant should be available at the solid waste management
and sludge management facility.
A technical committee should be formed to apply and monitor the symbiosis
process comprising of specialists from both the NEZ waste management team
and the industries. The industries should share their information regarding
production cycle, production capacity, requirements for raw materials, amount
and quality of their wastes etc. Based on the information, the industries should
come to an agreement of applying industrial symbiosis into their production
pathway.
Third parties from outside the NEZ could be involved for the production of
recycling materials usable for secondary uses from wastes such as paper, glass,
metal, plastic etc. The industries of NEZ should have provisions to buy these
products at a lower cost than the usual market price. In this case, the NEZ could
199
Environmental and Social Management Plan
provide subsidies to those third party producers by either selling the raw materials
at cheaper cost or providing certain amount of money on monthly or yearly basis.
A composting plant at the sludge management facility should handle the organic
wastes and sludge from the wastewater treatment plant. One major part of this
type of waste could be decomposed to fertilizers through aerobic processes.
These fertilizers should be used for the green areas inside NEZ and could also
be sold to the local market. The residual part of these wastes could be used for
biogas production into an anaerobic digestion chamber. The biogas could be
directly used as raw fuel or turned into electricity which could contribute to the
energy source of the composting plant itself.
NEZ should promote recycling and attract investors to create a market for the
recycled products at a national level. If proper sorting of solid wastes of not only
the industries but also from the residential wastes could be done NEZ could sell
various types of wastes as raw materials for the production of building materials,
furniture, fuel and textile. The revenue could be used for the operation of
management facilities as well as the subsidies for the industries.
The symbiosis efficiency and waste flow should be regularly monitored by the
technical committee using available ICT tools. Based on the monitoring, the
committee should suggest changes and adaptations required at any step.
Workshops and meetings should be conducted at a regular interval to share the
observations of the monitoring aspects as well as to raise knowledge and
awareness.
200
Environmental and Social Management Plan
RECP approach can be implemented by the industries through three basic steps:
i) Inventory of sources: where are wastes and emissions generated?
ii) Analysis of cause: why are wastes and emissions generated?
iii) Generation of efficient options: how can those causes be avoided or minimized?
In order to establish a sustainable economic zone NEZ authority should encourage the
industries to adapt RECP techniques by addressing the following aspects and management
plans:
The industries should conduct ‘Life Cycle Assessment’ for each of their products
to identify use of resources, generation of wastes and emissions per unit of
production.
Considering on the resource efficiency and pollution intensity, industries should
review their production methodologies to find alternative measures to achieve
greater resource efficiency and lesser pollution intensity.
If required, the industries should opt for alternative and environmentally better
final product which might not be conventional.
In case of water resources, NEZ authority should impose ‘polluters pay’ and ‘pay
per use’ concepts for the industries. Both the water use and discharge of
wastewater by each of the industry should be measured separately and billing
criteria should be set accordingly. This could introduce the urges of achieving
efficiency within the industries.
Energy efficiency should be considered from an architectural point of view while
constructing any building (both offices and plants). NEZ authority should enforce
all the industries to have provision for solar energy with a capacity of at least 20%
201
Environmental and Social Management Plan
to 40% (depending on the scale of the industries) of total energy requirement for
each industry.
Waste heat can be produced due to thermal and mechanical processes by
means of sources like hot combustion gases, heated wastewater etc. Industries
should adopt technologies to capture and transform the heat into energy in form
of electricity to be used as an extra energy source.
Vertical gardening at possible places should be promoted by NEZ authority by
financing the initial cost. This could contribute to minimize the emission of net
carbon gases as well as heat stress from NEZ.
In case of gaseous emission, the plants should have facility to treat the emission
to minimize the release of greenhouse gases. For the plants which produce
greater amount of carbon gases, provision for facilities to filter and capture
carbon gases from the outflowing channel and later the captured carbon gases
should be sequestrated underground following the best available practices.
‘Eco-labelling’ on the products could be introduced by NEZ authority. Based on
the life cycle assessment results a grading criteria could be determined with
provisions for both positive and negative labels. The idea of eco-labelling should
be explained well and decently to the consumers so that products with positive
eco-labels get promoted in the market. This could create competitions among the
industries to achieve greater efficiencies and lesser environmental impacts.
NEZ authority should have provision for subsidies for industries which will
achieve positive eco-label certificates so that they could set the market price of
their products within the standard limit.
The eco-labelling certificates should be re-examined and renewed after every
three or four years.
Monitoring activities and sudden inspections should be undertaken by NEZ
authority at regular frequencies to validate the information shared by the
industries. If the industries fail to show that they do follow the operations as they
supposed to, penalty could be imposed and their eco-labelling certificates should
get downgrading.
The industries should share technical knowledge among themselves to achieve
better technological advantages as well as apply industrial symbiosis.
Workshops and technical training activities should be arranged by NEZ authority
at a regular interval to enhance the ‘capacity building’ of the industries by
promoting new ideas and innovations in the field of RECP.
202
Environmental and Social Management Plan
The operation of water treatment plant to treat surface water from potential
sources should be introduced as soon as possible. The major portion of water
demand should be supplied from surface water.
Awareness should be spread to reduce the misuse of water both in domestic and
industrial sectors.
Industries should be encouraged to have facilities to recycle water for their
production. Special incentives could be awarded for the industries with
exceptional techniques to optimize the use of water.
All the industries need to be obliged to have rain water harvesting facilities to
meet up their water demand.
For the domestic purposes a common water retention facility should be
established and connected with the water treatment plant.
203
Environmental and Social Management Plan
Swimming, bathing, washing etc. should not be allowed in the Komol Beel
considering health of aquatic ecosystem.
There should be no point source of wastewater inflow into the beel except for the
discharge points of treated wastewater and storm water.
204
Environmental and Social Management Plan
Cost (in
ESMP Item Purpose Responsibility Remarks
Million BDT)
Land Development and Construction phase
Rehabilitation and
Mitigating local
livelihood restoration of
agitation and Needs to be
dependent households 2.0 NEZA
compensating loss included in DPP
(compensation, training,
of livelihood
etc.)
Mitigating drainage
On-site run-on and run-off
problem, sediment Land
facilities (Fencing, Needs to be
runoff, water 0.2 development
wastewater and storm included in DPP
pollution during Contractor
water collection network)
land development
Construction waste Controlling
Land
management (use of dispersion of dust,
Development
sprinkler, curtain and gaseous emission,
Contractor Needs to be
barrier, separate vehicle other construction 0.25
and included in DPP
washing facility, storage, materials and
Construction
collection and disposal of minimizing the
Contractor
solid wastes) noise level
Land
Safety of the Development
Personal Protective
construction Contractor, Needs to be
Equipment (A standard set 0.5
worker and project Construction included in DPP
for each individual)
personnel Contractor,
and NEZA
Land
Construction of well Health and safety Development
facilitated labor sheds, of the workers, Contractor, Needs to be
0.5
hygiene toilets and Waste Construction included in DPP
adequate septic tanks management Contractor,
and NEZA
Provision for pure drinking Health of the Needs to be
0.25 NEZA
water workers included in DPP
Monitoring of Described in
Environmental
environmental quality Environmental
Monitoring (air, NEZA and/or
(Procurement of Monitoring
noise and water), 18.5 environmental
equipment, sampling, Chapter. Needs
Compliance consultant
testing or engagement of to be included in
requirement
consultants) DPP
Fish production
(Conservation of Komol
Beel by fencing, offsetting Minimize loss of Not Department
the production in the fish production Estimated of Fisheries
nearby beels/new
wetlands)
Temporary roads including Local
Needs to be
proper signboards of communication, 0.5 NEZA
included in DPP
instructions mobilization of
205
Environmental and Social Management Plan
Cost (in
ESMP Item Purpose Responsibility Remarks
Million BDT)
construction
vehicles and
equipment
Operation phase
Flood alert system
(stationary water level
Disaster
measuring equipment, 0.5 NEZA
Management
online monitoring, Data
logger, installation)
For monitoring
Online water quality Needs to be
discharge from the 0.5 NEZA
monitoring system included in DPP
CETP and STP
Establishing Environmental Environmental Needs to be
3.5 NEZA
Lab Monitoring. included in DPP
Daily weather Needs to be
Micro Weather Station 0.5 NEZA
recording included in DPP
Environmental monitoring Compliance Described in
51.5 NEZA
(three years cost) requirement Environmental
Third party Environmental Monitoring
Monitoring (3 years Compliance Chapter. Needs
50 NEZA to be included in
construction and 3-year requirement
operation period) DPP
Development of
‘Greenbelt’ along the
Minimizing air
boundary of NEZ, Needs to be
pollution, providing
roadsides and Parks at the included in DPP;
biological habitat 5 NEZA
designated areas recurring cost
and recreational
proposed in the master will be required
uses
plan (Tree plantation and
maintenance)
Needs to be
included in DPP;
Public toilets Public facility 0.5 NEZA
recurring cost
will be required
Provision for emergency
situations and accidents Management of Needs to be
(fire alarms, fire hydrants, risks, accidents, NEZA and the included in DPP;
50
emergency medical team, Health and safety industries recurring cost
training, central of the community will be required
communication)
Surveillance and security Needs to be
(CCTV coverage, central Ensuring safety NEZA and the included in DPP;
50
monitoring, security and security industries recurring cost
personnel) will be required
206
Environmental and Social Management Plan
207
Environmental and Social Management Plan
208
12. Disaster Impact, Hazard and Risk Assessment
12.1 Introduction
This chapter both covers Disaster Impact Assessment and the Hazard and Risk Assessment
which are newly practiced requirements of EIA and are always recommended by the
Department of Environment. The requirement of DIA is linked to the decision of the National
Disaster Management Council chaired by the Honorable Prime Minister of Bangladesh.
Hazard and Risk Assessment are required by national and international guidelines including
the IFC standards for environmental and social safeguards.
209
Disaster Impact, Hazard and Risk Assessment
Table 12.1: Summary of the Natural Disaster, their Consequences and Management
Sl. Natural
Impact on NEZ Disaster Risk Reduction/management Implementation
No. Disaster
Before developing the land, an embankment along the boundary of
the project should be constructed
While developing the land proper drainage (run-on and run-off)
should be constructed
Might affect the land
The proposed lake (which to be constructed by conserving the
development activities
existing Komol Beel) and allied structures (e.g. regulator, gate)
Might cause flooding of the should be properly maintained for ensuring its function as a flood
NEZ retention pond NEZ, Individual
The 500 acres of land to be The nearby flood management infrastructures (e.g. Thakurakona Industries, BWDB.
Flash Flood developed for NEZ would no sluice, an embankment along the Kangsha, and other infrastructure Monitored by BEZA, DoE
1 and Monsoon longer function as flood of Thakurakona project of BWDB, etc.) should be rehabilitated in line and an independent
Flood retention area which might with the proposed NEZ Environmental and Social
thereby impact on nearby
To prevent waterlogging around the NEZ, existing canals should be Consultant (IESC)
water management
excavated regularly to ensure proper drainage
infrastructure.
To prevent accidental discharge of effluent robust automatic system
Might cause an accidental
should be established for monitoring
discharge of industrial effluent
in the case of non-function ETP, the industrial discharge should be
stored in a temporary pond.
Strict measures should be adopted to prevent running of industrial
operation in a case of non-functional ETP
NEZ, Individual
While developing land wind-
Industries.
driven wave might cause The boundary of the project should be protected from wave erosion
Monitored by BEZA, DoE
2 Wave erosion erosion Bank of the proposed lake should be protected by in a combination
and an independent
Erosion might take place at of biological and structural measures
Environmental and Social
the bank of the proposed lake
Consultant (IESC)
210
Disaster Impact, Hazard and Risk Assessment
Sl. Natural
Impact on NEZ Disaster Risk Reduction/management Implementation
No. Disaster
NEZ, Individual
Heavy rain might cause wash Before developing the land, an embankment along the boundary of Industries.
out of sand or sediment
the project should be constructed Monitored by BEZA, DoE
3 Heavy Rain spillage during land
development and construction While developing the land proper drainage (run-on and run-off) and an independent
should be constructed Environmental and Social
phase
Consultant (IESC)
There should be adequate numbers of shelters where workers could
Thunder and lightning could
take shelter at the time of thunderstorm
cause injury and death of
labors, construction workers Mandatory training should be conducted to aware all personnel of NEZ, Individual
and project staffs during land NEZ about the lightning and safety. Industries, Dept. of
development and construction All the power transmission lines should be buried underground. Disaster Management
5 Thunderstorm activities Equipment installed outside should be protected from lightning by Monitored by BEZA, DoE
Lightning could damage installing proper measure (e.g. lightning arrester) and an independent
industrial complex, electric Lightning arrester should be installed at each industrial complex, Environmental and Social
facilities (e.g. substation) or open space, parks of common facility area, etc. Consultant (IESC)
any equipment installed
A safety distance should be demarcated around each open-air
outside
electric facility to keep away passerby/worker/personnel
211
Disaster Impact, Hazard and Risk Assessment
Rainfall
Rainfall is the most distinctive component of climate in Netrakona and in the haor region.
Climate is dominated by distinctive geographical characteristics of the region, which
ultimately plays a major role in determining the spatial and temporal distribution of rainfall,
evapotranspiration and hydrology of surface and groundwater.
The pre-monsoon season is characterized by increasing rainfall and flash floods. The bulk of
the annual rainfall occurs during the monsoon season when flash floods are regular and
frequent and the central part of the Northeast Region is flooded over to a depth of several
meters. The post-monsoon is characterized by decreasing rainfall and by the draining out of
flood water which is usually accumulated in the monsoon season. The dry season is one of
little or no rain, and river discharges are greatly reduced.
The available recent climate data in the study area show that the yearly average rainfall in
the study area is around 2300mm. Usually, most precipitation is recorded in the month of
June and the minimum in the month of January. Figure 12.1 presents the annual rainfall
trend in Netrakona based on BMD data.
Available rainfall data for Netrakona was collected from Bangladesh Meteorological
Department. Cumulative annual rainfall data from 1981 to 2017 was examined to conduct
the trend analysis for those locations.
Annual cumulative rainfall at Netrakona shows some variability. A slight increasing trend was
found in annual rainfall during the past-observed period. In addition to the cumulative annual
rainfall, an increase of pre-monsoon rainfall was reported in last few decades which might
increase the chances of extreme flash flood events during the pre-monsoon periods.
Evidence has been found from analysis of pre-monsoon rainfall that, pre-monsoon rainfall at
sylhet station has increased from 18%-24% (from the period 1691-1990) to 25%-27% in
recent years (1991-onwards) due to climate change (CEGIS, 2017).
212
Disaster Impact, Hazard and Risk Assessment
Temperature
The available data on temperature for the study area has been collected from BMD. The
annual trend analysis of maximum and minimum temperature are presented in figures 12.2
and 12.3. The figures show that the average maximum temperature in that area varies
between 24°C to 30°C and the average minimum temperature varies between 16°C to 22°C.
January is the coolest month of the year and August is the warmest month in this region. In
the recent time (1991-2017), the year 2009 was considered to as be the warmest year
having an annual maximum temperate of 30.4°C. In addition, trend analysis of temperature
data of Sylhet station was also performed. It has been seen that, the mean maximum annual
temperature varies between 29°C to 31.5°C.
213
Disaster Impact, Hazard and Risk Assessment
The figures show that there is increasing trend in both maximum and minimum temperatures
in the study area. The rate of change of increase is much higher in maximum temperature
than in minimum temperature. So, there are increasing tendency of hotter climate in the
area.
214
Disaster Impact, Hazard and Risk Assessment
Table 12.3: Prediction for Change in Seasonal Maximum and Minimum Temperature
On the other hand, rainfall occurrence would increase during pre-monsoon season i.e.
March-April-May (MAM) and decrease in post-monsoon i.e. October-November (ON) (Table
12.5). Specially, pre-monsoon rainfall occurrence will be increased by 5%-6% in north-
eastern region than the base period, which clearly depicts that the study area will be more
prone to early rainfall as well as early flash floods in future.
Annual average rainfall anomalies reveal that total annual rainfall over the study area will be
increased up to 11%-12% by 2080s in consideration of both RCP4.5 and RCP8.5. Table
12.4 and 12.5 shows variations of future rainfall changes annually and in different seasons.
Change in Rainfall, %
RCP4.5 RCP8.5
2030s 2050s 2080s 2030s 2050s 2080s
Rainfall 8.0 10.0 12.0 8.0 8.0 11.0
Rainfall
RCP 4.5 RCP 8.5
Season
2030 2050 2080 2030 2050 2080
DJF 4 13 12 7 4 14
MAM 35 29 29 36 33 35
JJAS 35 35 36 2 3 9
ON -14 -15 -18 -16 -20 -23
215
Disaster Impact, Hazard and Risk Assessment
inundated with water were found in May. However, analysis results showed a time
dependent variations of peak flood extents for Netrakona district (Table 12.6). Most
importantly, the majority of the extreme flood events were found occurring during May. In
May of 2006, 2007, 2010 and 2015, more than 15% of the lands were flooded with water at
several haor districts. In May 2010, about 35% land areas were flooded in Netrokona.
Table 12.6: Summary statistics of the flood extents (% area inundated) in pre-
monsoon period (Year 2005 – 2017)
March April May
District
Min. Max. Median Min. Max. Median Min. Max. Median
Netrakona 0.079 8.45 2.7 1.15 5.17 2.05 0.98 35.15 4.02
Figure 12.4: Peak flood level at Sylhet during April against different return periods
(CEGIS, 2017)
Though the flood trends yet have not significantly increased over the past thirteen years’
period in the North-East haor areas, the frequency of high magnitude extreme flash flood
events have increased (CEGIS, 2017). Increase of the pre-monsoon rainfall as stated in the
earlier rainfall section, might be the most possible reason for such increase of extreme flash
floods in those areas, which comes earlier than usual time and hampers crop production.
Figure shows that flash floods for more than 10 years return period is increasing in recent
years, whereas flash floods of 5-year return period (before 2010) are a regular event
nowadays. These phenomena state that the intensity as well as frequency is increasing in
case of early flash floods. Under future climate scenarios, this will further increase as shown
from increase in pre-monsoon rainfall increases.
216
Disaster Impact, Hazard and Risk Assessment
levels at this station in Kangsha river during flood events of 1998, 2017 and 2018. Based on
the future projections of the rainfall distribution during pre-monsoon and monsoon seasons,
it is clear that rainfall is expected to rise by more than 30% in the future. So, the monsoon
flood events and their impacts will increase in the future due to climate change.
Source: FFWC
(a) (b)
Figure 12.6: Rate of Fatalities and Injuries during different seasons
217
Disaster Impact, Hazard and Risk Assessment
Netrakona is in the sixth position in terms of causality and second position in terms of
injuries occurs due to thunderstorm in Bangladesh. 2.95% of total fatality of Bangladesh due
to thunderstorm occurs in Netrakona. With passage of time, intensity of lightening is
increasing as evident from Figure 127. From Figure 12.8 it can also be noted that, about
62% of total lightening in Netrakona happened during pre-monsoon. As the trend is
increasing in recent times, it can be concluded that, lighting events might increase in the
future due to climate change, as the pre monsoon rainfall amount and variability is expected
to rise.
218
Disaster Impact, Hazard and Risk Assessment
12.5.4 Hailstorm
Hail is a form of solid precipitation. It is distinct from ice pellets, though these two are often
confused. It consists of balls or irregular lumps of ice, each of which is called a hailstone.
Any thunderstorm which produces hail and reaches the ground is known as a hailstorm.
From the available data it is observed that, in Sylhet, a total of 50 hailstorm occurred from
1988-2012 with maximum 8 hailstorms in 1988 and minimum single hailstorm in 1997, 2001,
and 2012; Besides, hailstorm occurs mostly in monsoon (61%) and pre-monsoon (31%)
(Figure 12.9). A total of 28 hailstorm events occurred during monsoon while 17 hailstorm
events took place during pre-monsoon. The study area is closer to Sylhet and has similar
characteristics. So, hailstorm can also be an increasing phenomena in the future along with
the increase in thunderstorms.
12.5.5 Drought
Drought is a serious concern for agriculture during winter season. As, the haor areas receive
large amount of rainfall during pre- and monsoon seasons, the soil moisture and
groundwater conditions are better in the area. As a result the effect of absence of rainfall
during winter is negligible in the study area. The area does not face drought impacts as
prominently as other areas of the country. So, drought condition is not of much concern for
the area at present and also in future scenarios.
219
Disaster Impact, Hazard and Risk Assessment
Based on future climate data of minimum temperature and trend, it is expected that, cold
wave events will decrease in the future.
220
Disaster Impact, Hazard and Risk Assessment
221
Disaster Impact, Hazard and Risk Assessment
Mandatory training should be conducted to aware all personnel of NEZ about the
lightning and safety measures.
All the power transmission lines should be buried underground. A safety distance
should be demarcated around each open-air electrical facility to keep away
passerby/ worker/ personnel.
As the NEZ will include industrial activities, proper measures should be
maintained and implemented to reduce SLCPs from the area and also to reduce
environmental pollutants (e.g., exhaust gas, solid waste, chemical waste,
industrial effluents, heavy metal etc.). Regular monitoring and environmental law
enforcement is essential in this regard.
222
Disaster Impact, Hazard and Risk Assessment
Potential Hazard/
Consequence Safety/ Risk Reduction Measures
NATECH
Spillage of Sediment Construction/installation of Adequate drainage system
during
Environmental Protection of boundary
landfilling/development
Pollution/Damage Construction of embankment along the project boundary before starting the land development to
due to heavy rain or
flood impound the area of land development
Strict enforcement of fire safety rules e.g. BNBC, Bangladesh Economic Zones (Construction of
Fire due to any Building) Rules, 2017
accidental event, Human death/Injury Conduction of regular training including a drill for all personnel related to the NEZ construction and
explosion or human error operation
A detailed assessment should be carried out by each industry at the time of carrying out ESIA
Accidental Discharge of Strict enforcement of ECR 1997
Industrial Effluent due to
The CETP should be automatic and robust. It should be equipped by an automatic shutdown of the
human error, technical Environmental
discharge in case of any accidental event, a rise of any pollution parameter above the danger level, etc.
error or a natural Pollution/Damage
disaster like heavy rain, Automatic and online monitoring of water quality at the discharge canal.
flood, etc. NEZ authority should regularly inspect each industry confirm operation of ETP
Strict enforcement of fire safety rules e.g. BNBC, Bangladesh Economic Zones (Construction of
Building) Rules, 2017
The NEZ authority should prepare a detail traffic operation and management plan
Each road should be properly equipped with traffic safety lights and signs.
Provide signs at strategic locations of the roads complying with the schedules of signs contained in the
Traffic Accident Human death/Injury National Traffic Regulations as well as engagement of flagman at strategic locations.
The entrance and exit of the NEZ should be equipped with an automatic system to alarm the passerby or
other vehicles when any vehicle approaches to enter or exit
Enforce on-site speed limits, especially close to the sensitive receptors, schools, health centers, etc.
NEZ authority should have a mechanism of mandatory safe driving training for all drivers, each industry
must send their drivers to such training
223
Disaster Impact, Hazard and Risk Assessment
Potential Hazard/
Consequence Safety/ Risk Reduction Measures
NATECH
The utility services including gas distribution should be monitored automatically
Human The check valve and regulators should be automatically and centrally operated
Explosion of any Gas death/Injury, Integrated and Smart (monitor & control, GIS interface) Utility (Gas, Water, Power, Firefighting, etc.) The
Pipeline or Storage Environmental design would further ensure the interest of investors
Pollution/Damage Strict enforcement of Gas Safety Rules, BNBC, and Bangladesh Economic Zones (Construction of
Building) Rules, 2017
The NEZ authority should instruct each industry to prepare its hazardous chemical handling and safety
procedure. The procedure must include the following:
Collect chemical wastes in 200liter drums (or similar sealed containers), appropriately labeled for safe
transport to an approved chemical waste depot.
Human Store, transport and handle all chemicals avoiding potential environmental pollution.
Accidental Leakage of death/Injury, Store all hazardous wastes appropriately in bunded areas away from watercourses.
Hazardous Chemicals Environmental Make available all Safety Data Sheets (SDS) for hazardous materials on-site during construction.
Pollution/Damage Collect hydrocarbon wastes, including lube oils, for safer transport off-site to reuse, recycle, treatment or
disposal at approved locations.
Construct concrete or other impermeable hard-stand to prevent seepage in case of spills.
Keep sufficient stock of absorbents for generally used chemicals or for petrochemicals (e.g., dirt,
sawdust, etc.) within the storage area to contain accidental spills.
224
Disaster Impact, Hazard and Risk Assessment
Risk/ Hazard/
Source/ Activity Consequences Safety Measures/ Precautions/ Contingency Plans
Incident
Keeping all safety and precautionary measures in order;
Enforcement of BNBC and relevant law to ensure workplace safety
Physical injury,
Unsafe work place Strict enforcement of safety rules relevant to the use of PPEs
electrocution, disease
during and post Lack of management; Strict enforcement of Bangladesh EZ Labor Law
breakout, loss of health,
construction
loss of life; Responsibility: During construction and prior to handover: Engineering,
Procurement and Construction (EPC) Contractor. Post-handover: Industry
operator/owner and NEZ.
Health hazards such as
Heavy transports, Use of water spraying during SPM generating activities to reduce the
respiratory problems,
Air pollution during construction machines degradation of air quality; vehicles and heavy machines should have
visibility issues etc. Low
construction and trucks, demolition proper fitness to perform the activities; water-spraying may be taken into
visibility may trigger an
works; consideration to reduce flying dust particles in the air;
accident;
Building codes should be followed to withstand an earthquake up to
Potential damage to civil certain level; Muster points during earthquakes will be defined and made
Earthquake during
structure of the station, part of drills; Responsibility: NEZ, EPC Contractor; Control Guideline:
and post A natural phenomenon;
loss of life, properties, BNBC; Responsibility: During construction and prior to handover:
construction
process etc.; Engineering, Procurement and Construction (EPC) Contractor. Post-
handover: Industry operator/owner and NEZ.
Waste management of both human-generated and project component
An outbreak of diseases
Waste generation Not handled properly, generated should be handled accordingly; Coolants, insulation gas
and other health related
and leakage during no adequate waste leakage should be monitored; painting will be done as sealant; SF6 will be
issues; impairment of
and post management/ disposal sucked out before maintenance works; Responsibility: During construction
environment due to air
construction process; and prior to handover: Engineering, Procurement and Construction (EPC)
and water pollution;
Contractor. Post-handover: Industry operator/owner and NEZ.
Construction site should be kept under surveillance and made
Site invasion Site invaded by
Physical injury and inaccessible to outsiders; The facility should be under constant
during construction outsiders during land
damage to property; surveillance and personnel should be in place of active duty to look out for
and post filling and preliminary
trespassers at all times; Close-Circuit Television (CCTV) monitoring to be
225
Disaster Impact, Hazard and Risk Assessment
Risk/ Hazard/
Source/ Activity Consequences Safety Measures/ Precautions/ Contingency Plans
Incident
construction construction works; in place to assist catching trespassers or any suspicious activity in and
around the vicinity of the facility; Responsibility: During construction and
prior to handover: Responsibility: During construction and prior to
handover: Engineering, Procurement and Construction (EPC) Contractor.
Post-handover: Industry operator/owner and NEZ.
Keeping all safety and precautionary measures in order; Responsibility:
Diseases outbreak Construction workers, Health loss due to During construction and prior to handover: EPC Contractor. Post-
during and post staff, employees having disease, loss of handover: Responsibility: During construction and prior to handover:
construction contagious diseases; productivity; Engineering, Procurement and Construction (EPC) Contractor. Post-
handover: Industry operator/owner and NEZ.
Follow the national building code; Provide proper fire-fighting equipment,
May result in tripping, or such as fire extinguisher, water hose and adequate capacity water
Short circuit, reserve, installation of Active Fire Suppression (AFS) system (if possible,
temporary forced
thunderstorm and in selected locations); proper grounding of power outlets, installation of
Fire and/ or shutdown resulting in
lightning, presence of lightning arrester at each Building to avoid damage through thunderstorm;
explosion during power outage, injury of
flammable substances
and post personnel, loss of life, Strict enforcement of Bangladesh Economic Zones (Construction of
such as lubricants;
construction and damage to Building) Rules, 2017
explosion of cylinders
properties, working hours, Responsibility: EPC Contractor; Control Guideline: BNBC Part 7-Section
etc.;
etc.; 2.1.2 and 2.2.17: Storage, Stacking and Handling of Flammable Materials;
BNBC Part 7- 3.10.2.2: Flammable Material and Explosive;
High humidity is a Will damage the
No humidity/ Appropriate Heating, Ventilation, and Air Conditioning (HVAC) system
natural condition of equipment and age the
condensation must be engineered so that the internal humidity is controlled. A
almost the entire internal structures faster;
control, inadequate centralized system should be in place; Responsibility: Land development
country and this respiratory problems will
ventilation and air contractor, EPC Contractor; Control Guideline: BNBC and: Worker Health
condition is not an arise in occupational
circulation during and Safety; Bangladesh Economic Zones (Construction of Building) Rules,
exception for Dhaka environment inside the
post construction 2017
Metropolitan; Bhaban;
Transportation of Bringing in or taking out Transportation should be conducted during off peak hours; Responsibility:
Traffic congestion will
heavy and large of the site using the EPC Contractor; Land development contractor; Control Guideline: Road
impact the daily lives of
components during existing road; use of Transport and Road Traffic Management and construction best practices,
city dwellers;
construction oversized local traffic laws and signage;
226
Disaster Impact, Hazard and Risk Assessment
Risk/ Hazard/
Source/ Activity Consequences Safety Measures/ Precautions/ Contingency Plans
Incident
transportation;
All emergency exits should be properly designed considering the nearest
occupancy, the maximum number of occupancy etc.; Emergency exits
should always be open from the inside and have proper guide towards it in
Improper emergency exit case of a power-outage resulted from any kind of incident; the exits should
Unplanned may result in dire also never have anything on the way, and for this proper management
emergency exits Emergency evacuation situations leading to practice should be in place; emergency drills should be conducted from
during and post process; failure of evacuation, time to time; Responsibility: During construction and prior to handover:
construction stampede causing severe EPC Contractor and Post-handover: NEZ authority and Emergency
injury and/ or death; Response Plan (ERP) Team;
Control Guideline: Worker Health and Safety and Construction and
Operation Phase Security; Bangladesh Economic Zones (Construction of
Building) Rules, 2017
Existing road-size and
Alternative access route should be considered; Responsibility: During
Narrow and only the surrounding May lead to slow
construction: NEZ authority, Land development contractor, EPC
access route environment including construction activity and
Contractor; Control Guideline: Road Transport and Road Traffic
during construction immovable structures, delay in the project;
Management;
private properties, etc.;
Drivers/ operators should strictly follow the rules and regulations; Drivers,
During site visit for operators, operator guides, site visitors should take care before coming
inspections, surveying, out of or getting onboard any vehicle; Proper traffic marking on the road
planning, equipment and effective signaling system should be implemented in and around the
and components project site; Oversized vehicle permit from the authority should be taken
Traffic or heavy
transportation, use of Physical injury, loss of before mobilizing such vehicles; Traffic safety should be ensured for
vehicle accident
oversized vehicle, life, vehicle and/ or oversized and slow moving vehicles; Provision and use of high visibility
during and post
onsite and offsite property damage, etc.; clothing for workers, operators, operator guides; Provision of safe
construction
activities including walkways onsite etc. Underground parking facility should have proper
movement of guiding marks/ signs to ensure they are well instructed. Personnel should
construction trucks, be included to guide vehicle entry, exit and parking; Responsibility: During
employee vehicles etc.; construction and prior to handover: EPC Contractor and Post-handover:
NEZ Authority and ERP Team; Control Guideline: Road Transport and
227
Disaster Impact, Hazard and Risk Assessment
Risk/ Hazard/
Source/ Activity Consequences Safety Measures/ Precautions/ Contingency Plans
Incident
Road Traffic Management, Protection of Public and Workers and Worker
Health and Safety;
Use of Personal Protective Equipment (PPE), such as lineman’s gloves,
Cutting and welding
safety goggles, safety shoes, or welding shield etc.; Proper training and
activity, short circuit,
awareness; Proper tools usage; Proper grounding of equipment, keeping
faulty grounding in
safe distance from hazardous points; Prepare regular maintenance and
equipment; faulty
inspection of electrical outlets, switch panels, electronics such as
wiring, loose Physical injury including
computers, printers etc. appliances as air conditioners, refrigerators,
Electrocution connections, during burning and loss of life;
ovens etc., lighting arresters; Maintain the inspection schedule properly
during and post repair and maintenance May cause station
through experienced technicians; Proper warning signs and labels in
construction work of cable gallery, shutdown due to an
place; Use of lock outs and tag outs and maintain hot work permit during
control panel, incident;
any work on electrical components; Keep all the personnel present in the
switchyard,
workplace aware of any undergoing hot work at all times; Responsibility:
instrumentation, etc.;
During construction and prior to handover: land development contractor,
power cable cut due to
EPC Contractor and Post-handover: NEZ Authority and ERP Team;
thunderstorm;
Control Guideline: Worker Health and Safety;
Welding activity,
electric works, come in
contact with hot surface Use of proper PPEs including safety goggles, appropriate gloves,
(ex. heat sink); Cutting Physical injury, eye injury, appropriate tools, or welding shield, appropriate training, warning signs
Burning and
and welding, arc temporary blinding and labels identifying potential hazards; Responsibility: EPC Contractor;
blinding during
flashovers, sparks due resulting in falling, Control Guideline: BNBC Part 7- 3.10.3: Health Hazards, BNBC Part 7-
construction
to faulty or loose tripping, electrocution 3.10.4: Skin Hazard, BNBC Part 7- Section 3.10.2 Fire Hazards;
connections, Bangladesh Economic Zones (Construction of Building) Rules, 2017
component malfunction
etc.;
Noise and vibration Hearing complexity and Compliance with the National Noise Control Rules and Regulations;
generated by heavy cause of headaches for Equipment should be used by competent operators; Provision of
Hearing
machineries, placing human beings resulting in equipment with low noise and vibration outputs i.e., equipment that come
impairment during
electrical heaving loss of concentration with dampers where possible or appropriate choice of modern equipment
construction
components such as resulting in the trigger of and machinery to reduce noise; Personal Protective Equipment (PPEs)
power transformers another potential hazard, provided and used where necessary; Consider suitable timing of
228
Disaster Impact, Hazard and Risk Assessment
Risk/ Hazard/
Source/ Activity Consequences Safety Measures/ Precautions/ Contingency Plans
Incident
and civil construction Scare local people, health construction work to reduce disturbance to the locality; Use components
works such as drilling, hazard for people with with lower noise level that falls in the same category or under the regular
piling, excavation weak constitution or heart decibel level of the locality and silencer where possible; Responsibility:
works etc.; conditions amongst Land development contractor, EPC Contractor; Control Guideline: ECP 7:
workers or employees as Noise and Vibration Management and BNBC Part 7- 3.10.4: Noise
well as bystanders; Hazard; Bangladesh Economic Zones (Construction of Building) Rules,
2017
Proper path management, such as use of bamboo base for walking during
Muddy plain during
construction; Regular scheduled maintenance and hire cleaners to remove
construction, leading to
moss from the path below the bus bars; Proper PPE shoes with slip grip
slipping/ falling off
will reduce chance of slipping significantly; use of sands and gravels in the
workers, water or any
pathway; Clean moss grown on the pathways; Wipe any water or liquid
liquid spilled on facility
(proper procedure for wiping corrosive, flammable or toxic) off using
floor and not wiped off.
appropriate cleaning materials/ tools; Use of warning signs/ labels in
Tripped by stray pipe,
places that may trigger a tripping incident and properly managed items
rope, rods, unmanaged
Slipping, tripping and equipment; Use of PPEs; Manage items at all times to keep the site
tools, cables, May cause physical injury
and falling during tripping free; Keep the outdoor pathways clear of weeds; Fall protection
miscellaneous items, such as fracture, broken
and post such as use of nets or temporary boundary; creating awareness; use of
and equipment in the bones;
construction PPEs such as hard hat, gloves, safety belts; Proper signs/warnings in
station, construction
locations where falling can result to an incident; Use proper climbing tools
equipment and tools,
such as harnesses, lanyards, capstan hoists etc. to support activities that
weeds on the outdoor
require hanging and working; Use buddy system to work on elevated
pathways etc. Fall from
areas; Responsibility: During construction and prior to handover: EPC
elevated areas in the
Contractor and Post-handover: NEZ Authority and ERP Team; Control
station such as steps,
Guideline: BNBC Part 7-Section 2.1.3, BNBC Part 7- Section 3.10:
ladders, other high
Construction Hazards; Bangladesh Economic Zones (Construction of
heights;
Building) Rules, 2017
Potential damage to civil Structures should be designed to withstand thunderstorms and lightning
Thunderstorm and
structures of the station, using well-established procedures in accordance with relevant national
Lightning during
A natural phenomenon; loss or interruption of and/ or international standards; Fire extinguishing facilities to be provided;
and post
power, loss of life, Lightning arresters will be checked for condition at regular intervals;
construction
process, triggering Preparation should be in place during a moderate or severe weather alert;
229
Disaster Impact, Hazard and Risk Assessment
Risk/ Hazard/
Source/ Activity Consequences Safety Measures/ Precautions/ Contingency Plans
Incident
hazards such as fire/ Responsibility: During construction and prior to handover: EPC Contractor
explosion; and Post-handover: NEZ Authority and ERP Team; Control Guideline:
BNBC Part 7-Section 2.1.2 Protection Against Fire; Bangladesh Economic
Zones (Construction of Building) Rules, 2017
Maintain connection with local police; Maintain vigilance of the
surroundings for any suspicious activities around the station area; Station
Evil intention of
Injury or loss of life, loss trained security guards at the entrance at all times and security round at
damaging or disrupting
Sabotage post of power, interruption of intervals during night time; Active CCTV surveillance at all times; Provide
the operation in the
construction power, loss of process, adequate lighting inside the facility for high visibility during night time;
facility by planned
etc.; Responsibility: During construction and prior to handover: EPC Contractor
carnage, intrusion, etc.;
and Post-handover: NEZ Authority; Control Guideline: Protection of Public
and Private Property, Utility, Construction and Operation Phase Security;
230
Disaster Impact, Hazard and Risk Assessment
231
Disaster Impact, Hazard and Risk Assessment
232
Disaster Impact, Hazard and Risk Assessment
communication with IRT of each industry, on-site and off-site emergency facilities e.g. fire
service, hospital, security forces, etc. and the local government e.g. Netrokona UNO office
and DC office. The ERG would also keep close communication with the BEZA. ERG would
mobilize its resources at the event of any industrial accidents, social crisis, un-rest.
Whenever ERG would mobilize its resources, it should inform the Incident Management
Team of the BEZA Head Quarter.
233
Disaster Impact, Hazard and Risk Assessment
234
13. Environmental and Social Monitoring Plan
235
Environmental and Social Monitoring Plan
236
Environmental and Social Monitoring Plan
237
Environmental and Social Monitoring Plan
238
Environmental and Social Monitoring Plan
16These monitoring parameters will be revised after monitoring the effluent water quality from the discharge channel. Some parameters might become redundant if
the effluent water does not contain them.
239
Environmental and Social Monitoring Plan
240
Environmental and Social Monitoring Plan
241
Environmental and Social Monitoring Plan
242
Environmental and Social Monitoring Plan
243
Environmental and Social Monitoring Plan
Responsible Agency
Parameter / Means of
Location Frequency Implemented Supervised
Activity Monitoring
By By
locations
Visual inspection
to observe growth
of saplings around OE/
Designated
Plantation neutralization Monthly Contractor Independent
sites
pond and Monitor
asbestos disposal
site
Excavation of
OE/
Lake/Conserva
NEZ area Visual Inspection Monthly Contractor Independent
tion of Komol
Monitor
Beel
Visual inspection
that solid waste is
disposed at OE/
Waste Construction
designated site Monthly Contractor Independent
Management camps
Solid Wastes are Monitor
managed in
efficient way
Hazardous Visual Inspection
Material of safe handling
Hazardous OE/
Storage Area and storage of
Waste Monthly Contractor Independent
Hazardous hazardous waste
Handling Monitor
Waste and hazardous
Disposal Area materials
Ensure the
construction
workers are OE/
Drinking water Camps,
provided with Weekly Contractor Independent
and sanitation offices
potable water and Monitor
sanitation facilities
in the site
OE,
After
Restoration of Independent
All Work Sites Visual Inspection completion Contractor
Work Sites Monitor,
of all works
BEZA
Usage of Personal
Safety of
Protective OE,
workers
equipment, Safety Independent
Monitoring and At work sites Monthly Contractor
Sign, Safety Monitor,
reporting
Documentation, BEZA
accidents
safety training, etc.
Inspection of
OE,
Emergency Emergency
Independent
Response At work sites Preparedness and Monthly Contractor
Monitor,
Plan Response
BEZA
mechanism
244
Environmental and Social Monitoring Plan
Responsible Agency
Parameter / Means of
Location Frequency Implemented Supervised
Activity Monitoring
By By
visual inspection
OE,
and enquiry to
Grievance Independent
At work site know the Monthly Contractor
Mechanism Monitor,
Grievance
BEZA
Mechanism.
During Operation and Maintenance
Monitoring of
Inspection and
Environmental
Record checking
Quality
As specified in of Monitoring
(Ambient Air, Quarterly IESC BEZA
Table 1.1 activities carried
Noise, Water,
out by EHSU circle
effluent, Soil,
of NEZ
etc)
Inspection of
laboratory
Environmental Condition,
NEZ Complex Six-monthly PIU IESC, BEZA
Laboratory accreditation and
certification (from
GOB) status
Checking and
compiling climatic
Meteorological data collected and
NEZ Quarterly IESC BEZA
Condition recorded by micro
weather station
installed in NEZ
Noise nuisance/
Township
disturbance
area,
perceived by NEZ
Ambient Noise Administrative
personnel and Six-monthly IESC BEZA
Level area and
nearby community
nearby
to be surveyed by
community
interview and FGD
Treat effluent
Visual inspection
discharge
of fish mortality
Fisheries point at Six-monthly IESC BEZA
Interviewing local
Kangsha
fishermen
River
Blooming of
flowers and
fruits in plants
Plant Health Visual inspection Six-monthly IESC BEZA
within the
NEZ, number
of tree felling
Satellite image
10km buffer
Land use and analysis of land
area of the yearly IESC BEZA
land cover use and land
plant
cover
Hazardous Hazardous Visual Inspection Quarterly EHS Circle IESC, BEZA
245
Environmental and Social Monitoring Plan
Responsible Agency
Parameter / Means of
Location Frequency Implemented Supervised
Activity Monitoring
By By
Waste and Material of safe handling
Hazardous Storage Area and storage
Material and Use Area hazardous waste
Handling Hazardous and hazardous
Waste materials
Disposal Area
At monitoring
well location
Interview of local
population to
check whether
NEZ complex grievance
Grievance
and nearby mechanism is Quarterly EHS Circle IESC, BEZA
Mechanism
community working or not.
Checking records
of complaints and
redresses
Inspection of
Emergency Emergency
Response At work sites Preparedness and Quarterly EHS Circle IESC, BEZA
Plan Response
mechanism
Inspection of
training list, safety
Health and
meetings records,
Safety NEZ Complex Quarterly EHS Circle IESC, BEZA
means of
Preparedness
awareness
growing
Inspection of
community relation
NEZ Complex, maintaining
Community
Nearby procedures, Quarterly EHS Circle IESC, BEZA
Relation
Community relation building
activities, FGD
with community
Inspection of
NEZ Complex, record completed
CSR Program Nearby and planned CSR Six-monthly IESC BEZA
Community programs and
activities
246
Environmental and Social Monitoring Plan
247
Environmental and Social Monitoring Plan
248
Environmental and Social Monitoring Plan
13.7 Organogram and Staffing for Ensuring ESMP and Environmental Monitoring
For ensuring effective implementation of ESMP and environmental and social monitoring the
NEZ construction project and the NEZ management (during operation) must have special
unit/department focusing on environmental management and compliance. Figure 13.1 and
13.2 illustrate organogram for the proposed environmental management and compliance
unit.
Figure 13.1: Proposal Institutional Setting for Environmental Compliance and EHS
Unit during Construction
249
Environmental and Social Monitoring Plan
Figure 13.2: Proposed Institutional Setting and Organogram for the Environmental
Compliance and EHS Unit during the Operation of the NEZ
250
14. Conclusions and Recommendations
The aim of the proposed NEZ is to promote local as well as regional and national economic
development by establishing appropriate industries in an enabling environment. The
economic benefits of the project as envisiged in the master plan includes contribution to
increasing GDP,value addition by creating employments opportunities, increase of national
foreign reserve through inflow of direct foreign investment.. However, these benefits may
also incur some environmental cost.
The proposed acquisition of 500 acre land may result permanent loss of seasonal
waterbodies including beels, agricultural lands (mostly signle crops), fish habitats
and livelihood of some people.. However, the people owning the land would get
compensation as per the rules of the country. Unfortunately, people who do not
have appropriate paper to produce their land right would not get any
compensation which might cause a social tension.
The proposed land acquisition would cost 2160 MT of rice and 243 MT of fish
production annualy.
The proposed land development for establishing NEZ by converting seasonal
flooded area to flood free area would have impacts on surrounding drainage and
flooding situation. The surrounding water management infrastructures e.g. sluice
gates, canals, embankment which are not effectively functioning at present,
would be under further stress due permanent loss of flood retention area and
groundwater recharge potential areas. However, the poposed lake in the NEZ
might minimize the impacts.
The construction activities might increase SPM in the local air . Construction
activities might also generates noise. The EIA proposes appropriate mitigation
measures to control such impacts.
The EIA proposes automated monitoring system for CETP/ETP/STP/pollution
mitigation measures. However, during operation, pollution (air pollution, water
pollution) might take place due to non-functioning of CETP/ETP/STP/pollution
mitigation measures.
Ground water has been considered as a major source of water supply.
Considering the large demand of water for operating NEZ, the impact on
groundwater availability is inevitable unless the NEZ apply water saving
technology and make arrangement for groundwater recharge. The Master plan
includes a large lake and several green areas which might enhance groundwater
recharge.The feasibility study did not cover detail assessment on groundwater
availability. Therefore, a further study should be carried out to evaluating
sustainability of groundwater.
The proposed NEZ and allied infrastructural development would induce local and
national economic development which would directly benefit the local community.
Living standard of local people would be improved.
An important objective of establishing EZ is to promote planned industrial development by
creating enabling environment and facilities at a place equipped with environmental
management rules and regulations and pollution abatement measures,which would prevent
251
Conclusions and Recommendations
unplanned and isolated growth of industries and thereby would prevent diffusive
environmental pollution. It is quite common that unplanned and isolated growth of industries
do not always comply environmental regulation and it often stay out of the reach of
environmental regulating agencies. Therefore, an EZ looks better in the context of
implementing environmental regulation and environmental monitoring. Such benefit of EZ is
also forseeable in case of NEZ. However, to ensure minimum environmental and social
impacts during land acquisition, construction and operation, the EIA recommends the
following:
An autometed and online monitoring system should be established to operate
and monitor CETPs. The NEZ authority should establish a strict environmental
compliance policy and practice with strict penalty for any non-compliance.
An integrated approach of infrastructural development is needed to ensure
attractiveness of the NEZ to investors
Integrated and Smart (monitor & control, GIS interface) Utility (Gas, Water,
Power, Firefighting, etc.) Design would further ensure interest of investors
Industries should adopt water saving technology
The Komol Beel which will be converted to a lake for the sake of NEZ, should be
maintained ensuring its ecological and hydrological functions. It should be
maintained in such a way that it it would provide local biodiversity an important
shelter.
The mitigation measures proposed in EIA should be strictly implemented.
This EIA should be a part of all the tender documents and contracts related to the
establishment of the NEZ.
The monitoirng plan proposed in the EIA should be strictly followed.
Since the local people have a high hope of local, regional and national economic
benefit from the project, long delay of the construction and operation may cause
public disappointment. Therefore, the project schedule should be strictly followed.
252
References
Alam, M. J., & Islam, M. S. (2018). Geological Aspects of Soil Formation of Bangladesh.
(December 2009). Retrieved from
https://www.researchgate.net/publication/268391538_Geological_Aspects_of_Soil_For
mation_of_Bangladesh
Awal, M. A. (2014). Water logging in south-western coastal region of Bangladesh: local
adaptation and policy options. Science Postprint, 1(1).
https://doi.org/10.14340/spp.2014.12a0001
BEZA. (2019). Feasibility Study of Netrokona Economic Zone. Dhaka, Bangladesh.
CEGIS. (2012). Environment Management Study on Thakurakona Scheme.
CEGIS. (2013). Feasibility Study of river management by enhancing the navigability,
minimizing drainage congestion, wetland ecosystem, irrigation and landing facilities in
the Haor areas. Journal of Chemical Information and Modeling.
https://doi.org/10.1017/CBO9781107415324.004
Chowdhury, U. K., Biswas, B. K., Chowdhury, T. R., Samanta, G., Mandal, B. K., Basu, G.
C., … Chakraborti, D. (2000). Groundwater arsenic contamination in Bangladesh and
West Bengal, India. Environmental Health Perspectives, 108(5), 393–397.
https://doi.org/10.1289/ehp.00108393
Curray J., M. D. G. (1971). Growth of the Bengal deep sea fan and denudation in the
Himalaya. Geological Scoiety of American Bulletin, 82, 563–572.
European Commission. (2018). Industrial Symbiosis: Kujala Waste Centre, Lahti, Finland
and Pécs ‐ Kökény Waste Management Centre, Hungary. Europa. Retrieved from
https://ec.europa.eu/environment/europeangreencapital/wp-
content/uploads/2018/05/Industrial_Symbiosis.pdf
FAO. (2011). Irrigation in Southern and Eastern Asia in figures: AQUASTAT Survey.
Retrieved from http://www.fao.org/docrep/016/i2809e/i2809e.pdf
Hussain, M. M., & Adbullah, S. K. . (2001). Geological Setting Of The Areas of Arsenic Safe
Aquifers. Annex I Ministry of Local Government, Rural Development & Cooperatives
Local Government Division Ground Water Task Force Interim Report No. 1.
IWM. (2019). Bangladesh Economic Zones Authority Feasibility Study of Netrokona
Economic Zone.
Khatun, M. A., Rashid, M. B., & Hygen, H. O. (2016). Climate of Bangladesh. MET Report,
(08/2016 ISSN 2387-4201), 159. Retrieved from http://www.bmd.gov.bd/?/p/=Climate-
Report
Kirby, R. M., Bartram, J., & Carr, R. (2003). Water in food production and processing:
Quantity and quality concerns. Food Control, 14(5), 283–299.
https://doi.org/10.1016/S0956-7135(02)00090-7
Kozak, A. T., & Grundfast, K. M. (2009). Hearing Loss. Otolaryngologic Clinics of North
America, 42(1), 79–85. https://doi.org/10.1016/j.otc.2008.09.008
Rashid, H. E. (2019). Geography of Bangladesh. Geography of Bangladesh.
https://doi.org/10.4324/9780429048098
Shaikh, M. A. (2009). Water conservation in textile industry. Pakistan Textile Journal, 58(11),
48–51.
Shamsudduha, M., Taylor, R. G., Ahmed, K. M., & Zahid, A. (2011). The impact of intensive
groundwater abstraction on recharge to a shallow regional aquifer system: Evidence
253
References
254
Appendix I: Matrix of Comments and Reponses on the Draft
Report
Sl.
Comments Responses by CEGIS
No.
1. Paban Chowdhury, (Secretary) Executive Chairman, BEZA
All the alternative economic opportunities for the
Discussed in Livelihood Restoration Plan,
1.1 people dependent on the land of the project area
in EMP Chapter
should be discussed properly.
Abstraction of water from the nearby surface water
Agreed. The EIA also recommends the
1.2 sources should be encouraged along with the
same.
uses of groundwater.
2. Dr. Md. Sohrab Ali, Director, Department of Environment, Dhaka Metropolitan Office
2.1 Executive summary should be brief and conscinse Executive summary has been rearranged
The government planned to establish 100
EZ throughout the county, which covers
Why Netrokona was selected as a potential place
almost all district. In that sense, selction
to establish Economic Zone? - a more logical
2.2 of Netrokona is normal. Anyway, a bit
explanation should be presented at the relevant
description is given in Introduction
section.
Chapter
255
Appendix
Sl.
Comments Responses by CEGIS
No.
types of wastes could be identified. The capacity, capacity of treatment plants have been
design and layout of the treatment plants should discussed in the ‘project description’
also be included. The operation of the pre- chapter (4.4.5) which are based on the
treatment plants by the industries should be available information of the feasibility
should be ensured. Also, the technological, study.
managerial and financial aspects of the treatment However, at this stage, the numbers and
plants should be re-considered as the experiences types of the industries are not certain and
of the existing examples of such treatment plants so, the design capacity of the treatment
in our country are not pleasant and favorable. plants are not possible to identify.
The ESIA report expects that BEZA will
design the treatment plants according to
the actual scenario of the types of the
industries and there will be provision for
further improvement of the plants. BEZA
should also ensure the proper
maintenance of the treatment plants.
Water discharge data have been included
in the subsection 6.2.5 under the heading
‘discharge and water level of nearby
rivers’.
Actual water discharge and seasonal variation of Water modeling could not be done
the rivers could be included. In case of the because, at this stage, the types and
2.10 abstraction of groundwater for the industrial uses, numbers of the industries are not certain.
the availability of drinking water for the local At the same time, according to the
people should be assessed and included. master plan, the dependency of water for
NEZ will be shifted from groundwater to
surface water eventually with connection
to the operational progress of NEZ from
initial stage to maximum production.
Baseline water quality report has been
Baseline water quality report should be included included in the subsection 6.2.5, under
2.11 according to Environment Conservation Rules the heading ‘quality of surface water’ and
1997, schedule 3. ECR, 1997, schedule 3 has been
followed to present the data.
Possible measures to treat gaseous
Possible measures that could be taken by the emissions by the industries have been
2.12 industries to treat the gaseous emission should be discussed in the subsection 11.7 under
discussed. the heading ‘Air Pollution Management
Plan’.
Monitoring of biodiversity should be included in the Monitoring indicators have been
2.13
‘Environmental Monitoring’ chapter. mentioned in monitoring Chapter
3. Syed Nazmul Ahsan, Director (ECC), Department of Environment
Update the missing acronyms and correction of
3.1 Action Taken
wrong ones (PPR, STP)
Map of project location should be updated. Two
Two updated map have been inserted in
3.2 maps should be included in the report which are
Introduction Chapter
one km. and 10 km radius;
Conservation of lake has been discussed
In the project description chapter the conservation
3.3 in the project description under the
of existing lake should be discussed;
subsection 4.4.5
256
Appendix
Sl.
Comments Responses by CEGIS
No.
The proportionate distribution of land into
The proportion of public and private land among
government and private cannot be given
3.4 the total of the project area should be presented in
in EIA report, since it is a part of Land
the report;
Acquisition Plan (LAP) study.
There is a confusing information in the report
Data on beel area has been changed
3.5 about the beel area. Provide accurate information
(please see relevant Sections)
about the nature of the land particularly beel area;
Mitigation of hydrological impacts of the
There might be created hydrological impact by the
project area have been addressed in the
3.6 development of the project. Provide proper
subsection 11.7 under the heading
drainage management system during flooding;
‘drainage and flood management plan’
4. Dr. Tanveer Ahmed, Environment Specialist, Support to Capacity Building of BEZA Project,
BEZA
Executive summary has been rearranged
Executive Summary sections should include key
following other comment as well (see.
findings of each chapter beside the general
Comment 2.1). Also, a summary of
4.1 descriptions along with site specific critical
concerns and a wayforward has been
environmental concerns and ways forward for the
given at the concluding remark of the
study area in the conclusion;
executive summary
Indicative outline along with environmental
Environmental guideline and description
guideline and description on CETP, STP, Solid
on CETP, STP and Solid waste
waste Treatment Plant and Integrated waste
management facility have been
4.2 management plan with 3R strategies based on the
discussed in the project description
projected demand should be discussed in the
based on the available information of the
project description chapter of the report as part of
feasibility study.
the EIA guideline requirements by DoE for EZ.
Physiography, geology and seismic analysis in
page 22 is missing, this section should also Physiography, Geology and Seismic
4.3 include relevant environmental implications for analysis have been included in the report
implementation of the proposed project under the subsections: 6.2.8 and 6.2.9
interventions in the study area;
Surface water quality data along with its
environmental interpretation for the proposed Water quality data of surface water and
project is missing inn page 70; Status of Arsenic groundwater along with their
4.4
(As) and its environmental implication for the study interpretation have been included in the
area should be included in the groundwater subsection 6.2.5.
monitoring data in page 77;
Baseline soil Elemental composition data and Action Taken: A brief soil quality
graphical interpretation is missing in the report information is presented based on
4.5
although it is mentioned in page 22 under the available data in Upazila Nirdeshika of
section of soil and land resources; SRDI.
Primary laboratory report of water quality
All primary Air/noise/ water/soil quality data should
has been included in the annexures.
4.6 be backed by original lab test reports and
Noise and air quality was monitored by
references in the annexures;
field tests.
Noise quality section in page 127, it is mentioned Noise modeling could not be conducted
the project activities shall cause high noise because, at this stage, the types and
4.7 impacts on the nearby community receptors. numbers of the industries are not certain.
However, no quantitative noise quality baseline However, an indication of noise during
data as well as predicted spatial impacts during operation phase has been addressed in
257
Appendix
Sl.
Comments Responses by CEGIS
No.
construction and operation of the EZ have been the subsection 8.4.1
included in the report;
The caption for figure 4.7 has been
Figure 4.7 caption in page 44 under wastewater
4.8 corrected under the wastewater
treatment section should be corrected;
treatment section
In page 125 it is mentioned that 455 acres of
agricultural land out of 500 acres will be converted
to industrial area with an annual loss of 2161 tons
of rice due to the NEZ. This statement should be Verified and found ok. Also, discussed in
4.9
verified with specific field/land use data and similar Alternative Analysis Chapter.
findings should be discussed in alternative
analysis section as agricultural/socio-economic
section which is missing in page 52.
Considering observation no. 6 alternative
4.10 Livelihood Restoration Plan (LRP) for project Agreed: included in EMP Chapter
affected people should be included in the report.
Dredging impacts was not possible to
It is mentioned in page 148 that a detailed explore extensively because the selection
feasibility and ESIA should be conducted for of dredging location and the design
dredging and land filling the project site which is layout requires separate study including
not correct as land filling is an important hydro-morphological and social
component of onsite EZ development activities assessments of the nearby rivers.
4.11
and lies within the scope of this study. Therefore, However, a general and tentative
the ESIA study should include an indicative land dredging and land development
development plan with the source and layout of management plan has been prepared
dredging considering the identified environmental and presented in the subsection 11.8
impacts in the study area. under the heading ‘dredging and land
development management plan’
As the report identifies the study area as
groundwater stressed as mentioned in page132,
the report should suggest environmentally viable Suggestions and measures regarding the
supply mix of industrial and drinking water sources sustainable use of water have been
considering the projected demand and local particularly addressed in two subsection:
4.12
available natural resources of the study area. In i) water resource management plan in
this context, the provision of surface/groundwater 11.7 and ii) water conservation and
treatment plant, water storage reservoir, rainwater saving plan in 11.8
harvesting should be discussed as integrated
water management plan for the entire project.
Identified impacts of global pandemic outbreak
of COVID-19 disease on the project affected
people in the study area due to project activities
and their associated occupational health safety Preventive measures have been
4.13
precautionary measures should be discussed in suggested in Mitigation Chapter
the relevant section of the environmental social
impacts and occupational health safety measures
in the report.
Promotion of Green EZ practices such as role of Measures to optimize energy efficiency
renewable energy (roof top/floating solar panels) and greener production have been
4.14 in the total energy supply mix, necessity for green discussed in the subsection 11.8 under
building, environmental audit, ISO certification of the headings ‘ Industrial Symbiosis Plans’
the EZ and individual investors should be and ‘ Resource Efficiency and Cleaner
258
Appendix
Sl.
Comments Responses by CEGIS
No.
discussed in the environmental management plan Production plans’.
of the study with a view to develop sustainable
and resilient EZ.
Table nos. in page 216 and 179 is section II of
Table nos. are corrected at page 220 and
4.15 Additional Benefit Package for the affected HHs
181.
should be corrected.
Minimum level of land elevation and development
of the project area in MPWD unit based on
historical flood level analysis in the report should Minimum level of land elevation has been
4.16
be clearly recommended in the climate change recommended in both sections.
adaptation & mitigation section page 214 and in
EMP section page 151.
Depth of the three sampling GW tube-wells along
with status of Arsenic and its environmental Depths of collected groundwater are
4.17
interpretation in the Quality of Groundwater mentioned in table 6.8 (page 79)
section should be discussed in page 78.
Section 11.8 details the general guideline for
dredging and landfilling but the section also needs
Tentative source of sand for the lad
to discuss the tentative source of sand from the
development purpose and tentative
nearest location for the proposed landfilling along
4.18 pipeline for sand transportation have
with a layout of the dredging pipeline network from
been addressed in section 11.8 (page
the source should be discussed: (ref: similar ESIA
195, 196)
reports on other EZs may be consulted for this
issue).
General and indicative impacts of Dredging on
Indicative impacts and mitigation
soil, water, aquatic ecology, socioeconomic
measures have been addressed for
4.19 condition of the project area along with their
different IECs in the section 8.3 and 9.3
mitigation measures should be discussed in the
respectively.
EMP section 9.0.
List of on-going (not the proposed one) off-site
development activities around the project area and Plan to mitigate the cumulative impacts
their cumulative environmental impacts along with has been addressed in the section 11.8
4.20
the proposed on-site development activities with under the title ‘integrated plan for other
mitigation measures should be discussed in the off-site infrastructure’ (page 202)
report.
Proportion of the total land area allocated for Proportions of allocated lands of different
4.21 different zones and facilities in percentages inside zones to total area are mentioned in table
NEZ should be mentioned in table 4.4. 4.4 (page 35)
Comments on CETP, STP, solid waste treatment
and integrated waste management issues in
section 2.9 from DoE and 4.2 from BEZA were not General description, and management
addressed which needs to be addressed in the aspects of waste, CETP, STP etc. are
report prior to the review by DoE for final approval mentioned in section 4.2 and 11.8.
4.22 of the ESIA report; (it is suggested to provide a Details design criteria of STP, CETP are
general and tentative detail of the layout, process not possible to mention as the number
flow description for liquid/solid waste management and scales of the industries are not
including construction, dredging debris, hazardous finalized yet.
and E-waste etc. addressing the regulatory
requirements of ZLD, ZDHC, 3R strategies, sludge
259
Appendix
Sl.
Comments Responses by CEGIS
No.
management guideline of DoE. The study should
be more technical than descriptive as pointed out
in the presentation by DoE.
5. Md. Abdul Quader Khan, Social Specialist, Support to Capacity Building of BEZA Project, BEZA
Environmental and social impacts and mitigation
measures: The consultancy firm can highlight the
5.1 only social impacts in separate head. Though the Action Taken (See, Impact Chapter)
heading is Environmental and social impacts but
here is no major discussion on social part.
Please provide the summary of social impact in
5.2 the Executive summary including affected HHs Action Taken
and number of persons
In Impact Assessment Chapter, an ISC
Please add separate section for off-site for assessing Social Impact of off-site
5.3 development plan and its social impact both in developed has been considered and
executive summary and details. discussed in relevant Section including
Executive Summary.
An ISC on off-site development has been
Please provide the mitigation measures for social
considered, impacts have been assessed
5.4 point of views in the report based on proposed
and mitigation measures have been
utility connection e.g. .road, gas, electricity etc.
suggested (in Impact Chapter)
National Legislations Relevant to Environment: In
this chapter there is no discussion about
Economic Zone labor law 2019. They have National Child Labor Elimination Policy,
5.5 discussed only National Child Labor Elimination 2010 has been deleted and Economic
Policy, 2010 which is not applicable according to Zone labor law 2019 has been discussed
BEZA Act-2010. Please update this chapter
according to comments.
In the social part, please incorporate the socio-
The general description of socio-
economic profile of land owner including their
economic profile of population living in
education, male-female ratio, Occupation Status,
5.6 the study is presented. However, profile
Literacy Rate, Employment Status, Age structure,
of landowners –to be dispossessed- by
source of drinking water, Household Income and
the project
Expenditure etc.
Please add chapter for livelihood restoration plan
5.7 Action Taken
for affected land owners
260
Appendix II: Approved ToR and Exemption of IEE
261
Appendix
262
Appendix
263
Appendix
264
Appendix III: Participants List
265
Appendix
266
Appendix
267
Appendix
268
Appendix IV: Photographs of the Stakeholder Consultation
Meetings
Formal Stakeholder Consultation Meeting at Key Informant Interview (KII) with Netrokona
Netrokona upzila parishad Deputy Commissioner (DC) at Netrokona zila
parishad
Meeting with Upazila Nirbahi Officer (UNO) at Meeting with Chairman at Singher Bangla union
Netrokona upazila parishad parishad
Meeting with Chairman at Thakurakona union Discussion meeting with local people at Singher
parishad Bangla village, Netrokona
269
Appendix
Discussion with local people at project area Discussion meeting with Garo Community at
Netrokona
Discussion meeting with local people at Barni Discussion meeting with local people at Barni
village, Netrokona sadar village, Netrokona sadar
270
Appendix V: Environmental Code of Practices
Introduction
The objective of the Environmental Code of Practices (ECPs) is to address all potential and
general construction related impacts during the land development and construction phase of
Netrokona Economic Zone. The ECPs will provide guidelines for best operating practices
and environmental management guidelines to be followed by the contractors for sustainable
management of all environmental issues. These ECPs shall be annexed to the general
conditions of all the contracts, including subcontracts, carried out under the Project.
The list of ECPs prepared for the Project is given below.
ECP 1: Waste Management
ECP 2: Fuels and Hazardous Goods Management
ECP 3: Water Resources Management
ECP 4: Drainage Management
ECP 5: Soil Quality Management
ECP 6: Erosion and Sediment Control
ECP 7: Top Soil Management
ECP 8: Topography and Landscaping
ECP 9: Quarry Areas Development and Operation
ECP 10: Air Quality Management
ECP 11: Noise and Vibration Management
ECP 12: Protection of Flora
ECP 13: Protection of Fauna
ECP 14: Protection of Fish
ECP 15: Road Transport and Road Traffic Management
ECP 16: Construction Camp Management
ECP 17: Cultural and Religious Issues
ECP 18: Worker Health and Safety
ECP 19: Construction and Operation Phase Security
Contractors will prepare site specific management plans, namely Construction
Environmental Management Plan (CEMP), in compliance with the World Bank and
Environmental Conservation Rules, 1997 of Bangladesh and based on the guidance given in
the ECPs. The CEMP will form the part of the contract documents and will be used as
monitoring tool for compliance. It is mandatory for the main contractors procured directly by
the project to include these ECPs in their subcontracts. Violation of this requirements will be
treated as non-compliance leading to the corrections or otherwise imposing penalty on the
contractors.
271
Appendix
272
Appendix
273
Appendix
274
Appendix
275
Appendix
276
Appendix
Project Activity/
Environmental Impacts Mitigation Measures/ Management Guidelines
Impact Source
Regularly inspect and maintain all drainage
channels to assess and alleviate any drainage
congestion problem.
Do not allow ponding of water especially near
the waste storage areas and construction
Health hazards due to camps.
Ponding of water
mosquito breeding Discard all the storage containers that are
capable of storing of water, after use or store
them in inverted position.
277
Appendix
278
Appendix
279
Appendix
280
Appendix
281
Appendix
282
Appendix
283
Appendix
284
Appendix
285
Appendix
286
Appendix
Project Activity/
Environmental Impacts Mitigation Measures/ Management Guidelines
Impact Source
arrangements showing all detours, temporary
road, temporary bridges, temporary
diversions, necessary barricades, warning
signs/lights, road signs, construction
schedule etc.
Provide signs at strategic locations of the
roads complying with the schedules of signs
contained in the National Traffic Regulations.
The Contractor shall
Restrict truck deliveries, where practicable,
to day time working hours.
Restrict the transport of oversize loads.
Accidents and spillage of
??????
fuels and chemicals Operate vehicles, if possible, to non-peak
periods to minimize traffic disruptions.
Enforce on-site speed limit, especially close
to the sensitive receptors, schools, health
centers, etc.
287
Appendix
Project Activity/
Environmental Impacts Mitigation Measures/ Management Guidelines
Impact Source
power supply generators), solid waste
management and dumping locations, and
drainage facilities, prior to the development of
the camps.
Local authorities responsible for health,
religious and security shall be duly informed
on the set up of camp facilities so as to
maintain effective surveillance over public
health, social, and security matters.
Contractor shall provide the following facilities in
the campsites
Adequate housing for all workers.
Safe and reliable water supply, which should
meet national/WHO standards. Drinking
water to be chlorinated at source, and ensure
presence of residual chlorine 0.1 ~ 0.25 ppm
as minimum after 30 minutes of chlorine
contact time (WHO guideline).
Hygienic sanitary facilities and sewerage
system. The toilets and domestic waste water
will be collected through a common
Lack of proper sewerage. Provide separate latrines and
infrastructure facilities, bathing places for males and females with
such as housing, water total isolation by location. The minimum
supply, and sanitation number of toilet facilities required is one toilet
Construction facilities will increase for every ten persons.
Camp Facilities pressure on the local
Treatment facilities for sewerage of toilet and
services and generate
domestic wastes.
substandard living
standards and health Storm water drainage facilities.
hazards. Paved internal roads.
Provide child crèches for women working at
construction site. The crèche should have
facilities for dormitory, kitchen, indoor and
outdoor play area. Schools should be
attached to these crèches so that children
are not deprived of education whose mothers
are construction workers.
Provide in-house community/common
entertainment facilities. Dependence of local
entertainment outlets by the construction
camps to be discouraged/prohibited to the
extent possible.
288
Appendix
Project Activity/
Environmental Impacts Mitigation Measures/ Management Guidelines
Impact Source
The Contractor shall
Ensure proper collection and disposal of solid
wastes within the construction camps.
Insist waste separation by source; organic
wastes in one container and inorganic wastes
in another container at household level.
Management of wastes is Store inorganic wastes in a safe place within
Disposal of waste crucial to minimize impacts the household and clear organic wastes on
on the environment daily basis to waste collector. Establish waste
collection, transportation and disposal
systems with the manpower and
equipment/vehicles needed.
Do not establish site specific landfill sites. All
solid waste will be collected and removed
from the work camps and disposed in
approved waste disposal sites.
The Contractor shall
Provide fuel to the construction camps for
their domestic purpose, in order to
discourage them to use fuel wood or other
biomass.
Illegal sourcing of fuel
wood by construction Made available alternative fuels like natural
Fuel supplies for
gas or kerosene on ration to the workforce to
cooking purposes workers will impact the
natural flora and fauna prevent them using biomass for cooking.
Conduct awareness campaigns to educate
workers on preserving the protection of
biodiversity and wildlife of the project area,
and relevant government regulations and
punishments on wildlife protection.
The Contractor shall
Provide adequate health care facilities within
construction sites.
Provide first aid facility round the clock.
Maintain stock of medicines in the facility and
There will be a potential for appoint fulltime designated first aider or
diseases to be transmitted nurse.
including malaria, Provide ambulance facility for the laborers
exacerbated by inadequate during emergency to be transported to
Health and health and safety nearest hospitals.
Hygiene practices. There will be an Initial health screening of the laborers coming
increased risk of work from outside areas.
crews spreading sexually
Train all construction workers in basic
transmitted infections and
sanitation and health care issues and safety
HIV/AIDS.
matters, and on the specific hazards of their
work.
Provide HIV awareness programming,
including STI (sexually transmitted infections)
and HIV information, education and
communication for all workers on regular
289
Appendix
Project Activity/
Environmental Impacts Mitigation Measures/ Management Guidelines
Impact Source
basis.
Provide adequate drainage facilities
throughout the camps to ensure that disease
vectors such as stagnant water bodies and
puddles do not form. Regular mosquito
repellant sprays during rainy season in
offices and construction camps and yards.
Not dispose food waste openly as that will
attract rats and stray dogs.
Carryout short training sessions on best
hygiene practices to be mandatorily
participated by all workers. Place display
boards at strategic locations within the camps
containing messages on best hygiene
practices.
The Contractor shall
Provide appropriate security personnel
(police or private security guards) and
enclosures to prevent unauthorized entry in
to the camp area.
Maintain register to keep a track on a head
count of persons present in the camp at any
given time.
Encourage use of flameproof material for the
Inadequate security and construction of labor housing / site office.
safety provision in
Also, ensure that these houses/rooms are of
construction camps may sound construction and capable of
Security and
create security and safety
Safety withstanding wind storms/cyclones.
problems of workforces
and assets and fire Provide appropriate type of firefighting
hazards equipment suitable for the construction
camps.
All construction material storage should be sit
a visible location secured with fence or solid
walls with locks to avoid theft and vandalism.
Display emergency contact numbers clearly
and prominently at strategic places in camps.
Communicate the roles and responsibilities
of laborers in case of emergency in the
monthly meetings with contractors.
The Contractor shall
Dismantle and remove from the site all
facilities established within the construction
Restoration of the
camp including the perimeter fence and
construction camps to
lockable gates at the completion of the
Site Restoration original condition requires
construction work.
demolition of construction
camps. Dismantle camps in phases and as the work
gets decreased and not wait for the entire
work to be completed.
Give prior notice to the laborers before
290
Appendix
Project Activity/
Environmental Impacts Mitigation Measures/ Management Guidelines
Impact Source
demolishing their camps/units.
Maintain the noise levels within the national
standards during demolition activities.
Different contractors should be hired to
demolish different structures to promote
recycling or reuse of demolished material.
Reuse the demolition debris to a maximum
extent. Dispose remaining debris at the
designated waste disposal site.
Handover the construction camps with all
built facilities as it is if agreement between
both parties (contactor and land-owner) has
been made so.
Restore the site to its condition prior to
commencement of the works or to an agreed
condition with the landowner.
291
Appendix
292
Appendix
293
Appendix
294
Appendix
295
Appendix
Project Activity/
Impacts /Concerns Mitigation Measures/ Management Guidelines
Impact Source
security risk for Maintain register to keep track of number of
construction workers persons present in the camp at any given time.
and especially foreign Provide appropriate security personnel at job
staff on construction sites as mentioned above.
sites.
Ensure proper fencing as mentioned above.
Ensure controlled access points to job site as
mentioned above.
Ensure works have easily identified credentials
as mentioned above.
Ensure job sites are properly lighted at night, as
mentioned above.
296
Appendix VI: Scanned Copy of Surface Water Test Results
297
Appendix
298
Appendix
299
Appendix
300
Appendix
301
Appendix
302
Appendix VII: Scanned Copy of Ground Water Test Results
303
Appendix
304
Appendix
305
Appendix
306
Appendix
307
Appendix
308