s10 TR Tank Rupture Tutorial
s10 TR Tank Rupture Tutorial
Wayne Johnson
[email protected]
Nick Abi-Samra
[email protected]
Survey On Transformer Rupture
Objectives
• Develop an understanding of the tank rupture process
associated with internal faults.
• Develop tools, and methods, for evaluating the influence
of tank designs on rupture characteristics
2
Background
3
Conclusions
4
Conclusions
5
Power Transformer
Tank Rupture
A Utility's Experience
Marc Foata
IEEE Transformers Committee
Houston, March 2010
Presentation
¾ Assessment of the risk
z Statistics
z Arc energy
¾ Prevention of tank rupture
z Venting
z Containment
¾ Specification of a Tank pressure withstand
requirement
2
Assessing the risk - Statistics
3
Assessing the risk - Statistics
4
Assessing the risk - Statistics
5
Arc energy - 4 MJ
6
Arc Energy - 8 MJ
7
Arc Energy - 12 MJ
8
Arc Energy - 14 MJ
9
Arc energy vs Damage
10
Arc Energy - Calculation
Earc = 0.9 V I t
¾ I – Arc current: Evaluated from short-circuit level
¾ T – Fault clearing time: Depends mainly on
protection
¾ V – Arc voltage: Very difficult to evaluate
¾ 0.9 – Factor introduced for square waveform of V
11
Arc Energy - Recordings
A 100
Unité Support et analyses - DESTT
E BN TT MAIS MICOUA
80
E BN L-7019 MICOUA
60 E BN L-7011 MICOUA
E BN L-7027 MICOUA
40
20
(kV)
0
-20
-40
-60
-80
205 210 215 220 225 230 235 240 245 250 255
(ms rel. à 05:34:32.2870)
2008-09-12 05:34:32.499 MICOUA 735-02 TENSION RÉSIDUELLE DÉFAUT TRANSFO T8-B
12
11
10
9
8
(MJoules)
7
6
5 ÉNTERGIE TOTALE (TT MAIS)
4 ÉNTERGIE TOTALE (TTC 7019)
3 ÉNTERGIE TOTALE (TTC 7011)
2 ÉNTERGIE TOTALE (TTC 7027)
1
0
-1
205 210 215 220 225 230 235 240 245 250 255
(ms rel. à 05:34:32.2870)
2008-09-12 05:34:32.499 MICOUA 735-02 ESTIMÉ DE L'ÉNERGIE TOTALE DANS LE DÉFAUT TRANSFO T8-B
20000
15000
10000
5000
(A)
-5000
-10000
COURANTS CÔTÉ 735 kV
-15000 COURANTS APROX. CÔTÉ 315 kV
-20000
190 200 210 220 230 240 250 260 270
(ms rel. à 05:34:32.2870)
2008-09-12 05:34:32.499 MICOUA 735-02 COURANTS DE DÉFAUT TRANSFO T8-B
13
Arc Energy - Pressure Effect
V = 55L P
¾ Constant 55 V/cm
¾ L is arc length (m)
¾ P is absolute pressure (atm)
¾ Pressure in the gas bubble at arc ignition
can reach extremely high values
14
Prevention of tank rupture –
Venting Simulations
15
Prevention of tank rupture –
Venting Simulations
16
Prevention of tank rupture – Vented
vs Non-vented Example
17
Prevention of tank rupture –
Conclusions on venting
18
Prevention of tank rupture -
Containment
19
Prevention of tank rupture -
Containment
20
New Specification - Philosophy
¾ Priority is given to the protection of the
workers
¾ Worst energy levels may not always be
containable by the tank
¾ First rupture point must be the cover
¾ Required calculation tools must be
accessible to transformer designers
¾ Must take into account the highly dynamic
phenomena involved
¾ Must be easily verified
21
New specification - Formula
⎡ ⎤
Ps= F
1 kE
⎢100 + − 50⎥
⎣ 4 100C ⎦
2,5
2
F
1,5
1
0 20 40 60 80 100 120 140 160 180 200
C/V (x 10 -5 kPa-1)
24
New specification - Implementation
25
Transformer Tanks
- Some Factors Related to Rupture
A Manufacturers Perspective
• Tank failed at
the cover joint
• Some stiffeners
on the tank wall
were permanently
deformed
• There were no
cracks in the oil
containment
welds in the tank
body
Rapid Rate of Pressure Increase
• Co-ordinates of
pressure source was
about 1/3 tank height
• 110MVAR 735 kV
shunt reactor
• The tank wall is
stressed in hoop
tension
• Typically the
cylinder walls can
sustain pressures
> 350 kPa (50 psig)
• Weakest point is
the cover weld
Design to Help Reduce Tank Rupture
Countermeasure
Tank
① Tank Strength Improvement ② Protection Relay Improvement
Explosion
③ System Improvement ④ Pressure Restrained Structure
Dynamics of Internal Fault (1)
10000
Arc
ArcTest
Test in
inOil
OilTank
Tank
100
Arc 10 100 1000
Arc Length (mm)
Oil Gas Volume
1
Pressure
(Single Line-Ground Fault at Upper Tank) Upper Tank
Time
Combustion Container
Φ300,L570 Middle Tank
Pressure
Upper Tank
Gas Outlet
(Φ12*72)
Time
Lower Tank
Pressure
Time
Middle Tank *Reference – T. KAWAMURA, M. UEDA, K. ANDO, Y. MAEDA, Y.
Lower Tank
Cartridge increment ABIRU, M. WATANABE, K. MORITSU “Prevention of Tank
(Max.7500g) Rupture Due to Internal Fault of Oil Filled Transformers”, CIGRE,
12-02, 1988.
Results of Analysis
• Decomposed gas generation calculated to be around
0.5L/kW sec for larger 275 kV class transformers at HV lead.*
Connecting Part
Alleviation of Stress Improvement of Connecting Part
Concentration Strength by Tie Reinforcement
Pressure Reducing Space
• Diaphragm type Conservator Tanks can be used as
effective pressure reducing space if the connection duct to
the main tank is short, the cross sectional area of the duct
is large (approx. 1.4 m dia.), and the air space in the
conservator diaphragm is adequate
Connection duct
100
100 Tank Strength
8080
6060
Oil-Immersed
Transformer
4040 Gas Insulated
2020 Transformer
00
00 0.0.22 0.0.44 0.0.66 0.0.88 11
Fault Time (sec)
Application Example
More Recently
THEY HAVE BEEN USED IN MULTIPLE SETS ALONG
THE TOP AND BOTTOM OF A SINGLE TRANSFORMER
TO MAXIMIZE THE PRESSURE RELIEF AREA AND TO
BE LOCATED AS CLOSE AS POSSIBLE TO ANY
POTENTIAL FAULT LOCATION.
THEY ARE THE RELIEF MECHANISM FOR
COMBINATION PRESSURE RELIEF/FIRE
SUPPRESSION SYSTEMS
THERE WERE SEVERAL DIFFERENT
DESIGN APPROACHES TO RE-SEALING
PRDs MADE BY VARIOUS
MANUFACTURERS
• location of fault
• magnitude of fault
• duration of fault
TEST 1: 1958 AT GE SCHENECTADY
The test tank was approximately 6 ft in diameter and 4 ft deep, with the
PRD mounted in the center of the 6 ft. diameter cover.
The gas space was 10 inches below the cover which resulted in about 700
gallons of oil and 23 cu. ft. of gas (air).
Ball nosed copper electrodes (2) were threaded with a small copper wire to
trigger the arc, the highest of which was 25K amps and 20K volts. Oil,
smoke, mist, spray blasted out of the relief device over a radius of about 40
feet.
9 TTR is a complex problem. The severity is a function of arc location, arc I and T
as well as oil volume and tank expansion characteristics.
9 It’s possible to reduce the risk of TTR by performing modifications to the tank.
9 PRDs help to protect the tank against low energy internal arcing faults.
9 Fluids with high fire point will reduce the consequences of a tank rupture;
however it is not yet proven if these fluids will prevent tank rupture.
9 Improved electrical protection and electrical system design can also help
prevent TTR.
9 The IEEE currently has no standards that provide guidance on TTR mitigation.
IEEE TRANSACTIONS ON POWER DELIVERY
Volume: 24 Issue: 4 Date: Oct. 2009
Page(s): 1959 - 1967