Quantity Estimation and Construction
Quantity Estimation and Construction
QUANTUM SERIES
For
B.Tech Students of Third Year
of All Engineering Colleges Affiliated to
Dr. A.P.J. Abdul Kalam Technical University,
Uttar Pradesh, Lucknow
(Formerly Uttar Pradesh Technical University)
By
Vikas Yadav
TM
CONTENTS
Course Outcomes:
CO-1 Understand the importance of units of measurement and preliminary estimate for administrative approval of
projects.
CO-2 Understand the contracts and tender documents in construction projects.
CO-3 Analyze and assess the quantity of materials required for civil engineering works as per specifications.
CO 4 Evaluate and estimate the cost of expenditure and prepare a detailed rate analysis report.
CO-5 Analyze and choose cost effective approach for civil engineering projects.
Unit 1
Quantity Estimation for Buildings Measurement units for various building materials,
Centreline method, Long and short wall method of estimates, Types of estimates, PWD schedule
of rate. [8]
Unit 2
Rate Analysis, Specification and Tenders Analysis of rates knowing cost of material, labour,
equipment, overheads, profit, taxes etc, Specifications – Preparation of detailed and general
specifications, Legal aspects of contracts, laws related to contracts, land acquisition, labour
safety and welfare. Different types of contracts, their relative advantages and disadvantages.
Elements of tender preparation, process of tendering, pre-qualification of contracts, Evaluation of
tenders, contract negotiation and award of work, monitoring of contract extra items. [8]
Unit 3
Elements of Management & Network Techniques Project cycle, Organization, planning,
scheduling, monitoring, updating and management system in construction, Bar charts, milestone
charts, work break down structure and preparation of networks. Network Techniques like PERT
& CPM in construction management. Project monitoring and resource allocation through
network techniques. [8]
Unit 4
Equipment Management Productivity, operational cost, owning and hiring cost and the work
motion study. Simulation techniques for resource scheduling. Construction Equipment for earth
moving, earth compaction, Hauling Equipment, Hoisting Equipment, Conveying Equipment,
Concrete Production Equipment, Tunnelling Equipment [8]
Unit 5
Project Cost Management Budgeting, Cost planning, Direct Cost, Indirect cost, Total Cost
Curve, Cost Slope. Time value of money, Present economy studies, Equivalence concept,
financing of projects, economic comparison, present worthmethod Equivalent annual cost
method, discounted cash flow method, Depreciation and its type, depletion, Arbitration, and
break even cost analysis. [8]
References:
1.Dutta, B.N., “Estimating and Costing in Civil Engineering”, UBS Publishers &
Distributors Pvt. Ltd., 2003
2.Srinath, L.S., “PERT and CPM Principals and applications” Affiliated East-West Press Pvt.
Ltd., New Delhi.
3.Patil, B.S., “Civil Engineering Contracts and Estimates” University Press India, Pvt. Ltd.
Hyderabad –500 004
4.Construction Management by Ojha
5.Srivastava, U.K., “Construction Planning and Management”, Galgotia Publications Pvt. Ltd.,
New Delhi.
6.Construction Technology by Sarkar, Oxford
7.Delhi Schedule of Rates (latest version)
Quantity Estimation & Management 1–1 C (CE-Sem-5)
1 Quantity Estimation
for Buildings
PART-1
Measurement Units for Various Building Materials, Centre Line
Method, Long and Short Wall Method of Estimates,
PWD Schedule Rate, Delhi Schedule Rate.
Questions-Answers
Answer
Estimation : It is the process which guides us to determine the cost,
quantity, tools, plants and labours which are needed to complete the
project with in time of completion.
Purpose of Estimation : Following are the purposes of estimation :
1. To give a Reasonably Accurate Idea of the Cost : An estimate is
necessary to give the owner a reasonably accurate idea of the cost to
help him decide whether the work can be undertaken as proposed or
not, depending upon the availability of funds.
2. Estimating Materials : From the estimate of a work it is possible to
determine what materials (and in what quantities) will be required for
the work so that arrangements to procure them can be made.
3. Estimating Labour : The number and kind of workers of different
categories who will have to be employed to complete the work in the
specified time can be found out from the estimate.
4. Estimating Plant : An estimate will help in determining the amount
and kind of equipment needed to complete the work.
Quantity Estimation & Management 1–3 C (CE-Sem-5)
Answer
Types of Estimates : Estimates can be grouped into two main categories :
A. Approximate Estimates : An approximate estimate is an approximate
or rough estimate prepared to obtain an approximate cost in a short
time.
B. Detailed Estimates :
1. A detailed estimate of the cost of a project is prepared by determining
the quantities and costs of everything that a contractor is required to
provide and do for the satisfactory completion of the work.
2. It is the best and most reliable form of estimate.
3. A detailed estimate may be prepared in the following two ways :
i. Unit-quantity Method :
a. In the unit-quantity method, the work is divided into as many
operations or items as are required.
b. A unit of measurement is decided.
c. The total quantity of work under each item is taken out in the
proper unit of measurement.
d. The total cost per unit quantity of each item is analysed and worked
out.
e. Then the total cost for the item is found by multiplying the cost
per unit quantity by the number of units.
f. This method has the advantage that the unit costs on various jobs
can be readily compared and that the total estimate can easily be
corrected for variations in quantities.
ii. Total-quantity Method : In this method, an item of work is divided
into the following five subdivisions :
a. Materials,
b. Labour,
c. Plant,
d. Overheads, and
e. Profit.
The total quantities of each kind or class of material or labour are
found and multiplied by their individual unit cost. Similarly, the cost of
plant, overhead expenses and profit are determined.
Quantity Estimation for Buildings 1–4 C (CE-Sem-5)
Answer
Following are the steps in the preparation of an estimate :
1. Taking Out Quantities :
i. In the first step of taking out quantities, the measurements are taken
off from the drawings and entered on measurement sheet or dimension
paper.
ii. The measurements to be taken out would depend upon the unit of
measurement. For example, in the case of stone masonry length,
thickness and height of the walls would be entered on the measurement
sheet, whereas, in the case of plastering only the lengths and height of
the walls would be entered.
2. Squaring Out : The second step consists of working out volumes,
areas and so on, and casting up their total in recognised units.
3. Abstracting :
i. In the third step, all items along with the net results obtained in the
second step are transferred from measurement sheets to specially
ruled sheets having rate column ready for pricing.
ii. The second and third steps above are known as ‘working up’.
All calculations in these stages and every entry transferred should be
checked by another person to ensure that no mathematical or copying
error occurs.
Answer
Following are the principles of selection of unit of measurement :
1. The unit of measurement should be simple and convenient to measure,
record and understand.
2. It should be one which provides for fair payment for the work involved.
3. In the result it should yield quantities which are neither too minute nor
too large.
4. The price per unit should not be a very small figure or a very large one,
that is, generally costlier items will be measured in smaller units, cheaper
ones in larger units.
5. The unit of measurement may sometimes depend upon the unit for the
raw material and/or labour and/or important dimensions. For example,
stone masonry is measured in cubic metres because raw materials are
measured in cubic metres. Plastering or pointing is measured in square
metres as the labour is considerable.
Quantity Estimation & Management 1–5 C (CE-Sem-5)
Que 1.5. What are item of works ? Write the units required to
measure them.
Answer
Items of Works : Following are the main items of works and their
measure units :
1. Earthwork : Earthwork in excavation and earthwork in filling are
usually taken out separately under different items and quantities are
calculated in m3.
2. Concrete in Foundation : The concrete is taken out in m3 by length
× breadth × thickness. The length and breadth of foundation concrete
are usually the same as for excavation only the depth or thickness
differs.
3. Soiling : When the soil is soft or bad, one layer of dry brick or stone
soling is applied below the foundation concrete. The soling layer is
computed in m2 (length × breadth) specifying the thickness.
4. Damp Proof Course (DPC) : It is usually of 2.5 cm thick rich cement
concrete 1 : 1.5 : 3 or 2 cm thick rich cement mortar 1 : 2, mixed with
standard water proofing material is provided at the plinth level to full
width of plinth wall and the quantities are computed in m2 (length ×
breadth).
5. Masonry : It is computed in m3 (L × B × H). Foundation and plinth
masonry is taken under one item, and masonry in superstructure is
taken under a separate item.
Answer
Methods of Estimation for Building Works : The estimation of
building quantities like earth work, foundation concrete, brickwork in
plinth and superstructure etc. can be worked out by long wall-short wall
method and center line method.
1. Long Wall-Short Wall Method :
i. In this method, the wall along the length of room is considered to be long
wall while the wall perpendicular to long wall is said to be short wall.
ii. To get the length of longwall or shortwall, calculate first the centre line
lengths of individual walls. Then the length of long wall (out to out) may
be calculated after adding half breadth at each end to its centre line
length.
Quantity Estimation for Buildings 1–6 C (CE-Sem-5)
iii. Thus the length of short wall measured in to in and may be found by
deducting half breadth from its centre line length at each end.
iv. The length of long wall usually decreases from earth work to brick work
in super structure while the short wall increases. These lengths are
multiplied by breadth and depth to get quantities.
2. Centre Line Method :
i. This method is suitable for walls of similar cross sections. Here the total
centre line length is multiplied by breadth and depth of respective item
to get the total quantity at a time.
ii. When cross walls or partitions or verandah walls join with main wall,
the centre line length gets reduced by half of breadth for each junction.
iii. Such junction or joints are studied carefully while calculating total centre
line length. The estimates prepared by this method are most accurate
and quick.
iv. Center line method is suitably used for estimating circular, rectangular,
hexagonal, octagonal etc., shaped building
3. Partly Centre Line and Partly Cross Wall Method :
i. This method is adopted when external (i.e., around the building) wall is
of one thickness and the internal walls having different thicknesses. In
such cases, centre line method is applied to external walls and long wall-
short wall method is used to internal walls.
ii. This method suits for different thicknesses walls and different level of
foundations. Because of this reason, all Engineering departments are
practicing this method.
Answer
3.50 m.
30 cm
60 cm 40 GL
30 cm 50
30 cm 60
30 cm
90 Section on AB and CD
Quantity Estimation & Management 1–7 C (CE-Sem-5)
D
30 cm
c/c 4.30 m
4.00 m
A B
30 cm
30 cm
5.00 m
c/c 5.30 m 30 cm
C
Plan of superstructure wall
Fig. 1.7.1.
1. The length of long wall centre to centre
= 5.00 + 1/2 × 0.30 + 1/2 × 0.30 = 5.30 m
2. The length of short wall centre to centre
= 4.00 + 1/2 × 0.30 + 1/2 × 0.30 = 4.30 m
Item Particular of Height
No. Items No. Length Breadth or Quantity Explanatory note
Depth cum
1. Earthwork in
Excavation in
Foundation
Long walls ... 2 6.20 m 0.90 m 0.90 m 10.04 Length = 5.30 + 0.90 = 6.20 m
Short walls ... 2 3.40 m 0.90 m 0.90 m 5.51 Breadth = 4.30 – 0.90 = 3.40 m
Total 15.55 m3
2. Concrete in
Foundation Length same as
Long walls ... 2 6.20 m 0.90 m 0.30 m for excavation
Short walls ... 2 3.40 m 0.90 m 0.30 m 1.83 Quantity = 1/3 of excavation
Total 5.18 m3
3. Brickwork in
Foundation
and Plinth
Long walls
1st footing ... 2 5.90 m 0.60 m 0.30 m 2.13 Length = 5.30 + 0.60 = 5.90 m
2nd footing ... 2 5.80 m 0.50 m 0.30 m 1.74 Length = 5.30 + 0.50 = 5.80 m
Plinth walls ... 2 5.70 m 0.40 m 0.60 m 2.74 Length = 5.30 + 0.40 = 5.70 m
Short walls
1st footing ... 2 3.70 m 0.60 m 0.30 m 1.33 Length = 4.30 – 0.60 = 3.70 m
2nd footing ... 2 3.80 m 0.50 m 0.30 m 1.14 Length = 4.30 – 0.50 = 3.80 m
Plinth walls ... 2 3.90 m 0.40 m 0.60 m 1.87 Length = 4.30 – 0.40 = 3.90 m
4.
Total 10.95 m3
Brickwork in
Superstructure
Long walls ... 2 5.60 m 0.30 m 3.50 m 11.76 Length = 5.30 + 0.30 = 5.60 m
Short walls ... 2 4.00 m 0.30 m 3.50 m 8.40 Length = 4.30 – 0.30 = 4.00 m
Total 20.16 m3
Quantity Estimation for Buildings 1–8 C (CE-Sem-5)
Answer
K L
90 cm
A B
P Q
4.30 m. c/c
90 cm 90 cm
S R
D C
90 cm
N M
5.30 m. c/c
Fig. 1.8.1.
Quantity Estimation & Management 1–9 C (CE-Sem-5)
1. Earthwork in
Excavation in
Foundation 1 19.20 m 90 cm 90 cm 15.552 m2 Total centre length of all
walls = 19.20 m
2. Concrete in
Foundation 1 19.20 m 90 cm 30 cm 5.184 m2
3. Brickwork in
Foundation
and Plinth
1st footing 1 19.20 m 60 cm 30 cm 3.456
2nd footing 1 19.20 m 50 cm 30 cm 2.88
Plinth walls 1 19.20 m 40 cm 60 cm 4.608
Total 10.44 m2
4. Brickwork in
...
Superstructure 1 19.20 m 30 cm 3.50 cm 20.16 m2 Door and window opening,
lintels, etc. to be deducted.
Answer
A. General Specifications :
1. Foundation concrete shall be of lime concrete.
2. Foundation and plinth shall be of Ist class brickwork in lime mortar.
3. Damp proof course : 2.5 cm thick and ratio of concrete 1 : 1.5 : 3 with
water proofing compound.
4. Superstructure : Ist class brickwork in lime mortar.
5. Wall finishing : Inside wall 12 mm cement plastered 1 : 6 and white
washed 3 coats.
6. Outside wall 12 mm cement plastered 1 : 6 including 10 cm below
ground level and finished with two coats of colour wash over one coat
of white washing.
Quantity Estimation for Buildings 1–10 C (CE-Sem-5)
3.50 m
Outside Inside
Superstructure
wall
30
2.5 cm DPC cm
Plinth level
Plinth 40 60 cm
GL cm
20 cm
2nd footing 50 cm 20 cm
Ist footing 60 cm 20 cm
Lime conc 30 cm
80 cm 57
40 cm 30 cm
6.00 m
(b) Plan
Fig. 1.9.1. Plan and cross-section of the wall
with standard modular brick.
Quantity Estimation & Management 1–11 C (CE-Sem-5)
Que 1.10. How do you account for deductions for openings in the
wall ?
Answer
A. No Deduction : No deduction is made for the following :
1. Opening each up to 1000 sq cm or 0.1 sq m (1 sq ft).
2. Ends of beams, posts, rafters, purlins, etc. upto 500 sq cm or 0.05 sq m
in section.
3. Bed plate, wall plate, bearing of chajjas and the like upto 10 cm (4)
depth.
Bearings of floor and roof slabs are not deducted from wall masonry.
B. Deduction for Different Structure : Openings deductions are made
in the following manner :
1. Rectangular Openings : Full deduction is made.
Deduct = l × h × thickness of wall.
Quantity Estimation for Buildings 1–12 C (CE-Sem-5)
l
Fig. 1.10.1.
2. Doors and Windows with Small Segmental Arches :
i. Deduction is made for rectangular portion only up to the springing.
ii. The segmental portion is considered as solid to allow for the extra
expense in constructing the arch, and the filling up with thin wall.
Deduction = l × h × thickness of wall.
l
Fig. 1.10.2.
2 r3
The area of segmental portion = lr
3 2l
ii. But for deduction, the area of the segmental portion is obtained
approximately by taking 2/3 of span × rise, (2/3 × l × r) and the quantity
2
for deduction is × l × r × thickness of wall. (r3 / 2l being small is
3
neglected for simplicity.)
2
iii. The total deduction will be = (l h) l r × thickness of wall.
3
4. Semi-circular Arch Openings :
i. The area of semi-circular portion = 1/2 r2.
ii. But for the deduction, the area of the semi-circular portion is obtained
approximately by 3/4 of span × rise, (3/4 × l × r).
iii. The total deduction will be = [(l × h) + (3/4 × l × r)] × thickness of wall.
iv. Elliptical arches may be considered as semi-circular arches and may be
dealt in the same manner.
Quantity Estimation & Management 1–13 C (CE-Sem-5)
r Rise
l
Fig. 1.10.3.
5. For Large Arches : The actual area of opening should be calculated
correctly by Mensuration formulae, and deduction should be made for
actual area.
r
l
Fig. 1.10.4.
6. Arch Masonry Work :
i. Masonry work in arches is calculated in cu m separately by multiplying
the mean length of the arch by the thickness of arch and by the breadth
of the wall.
lm
t
s
Fig. 1.10.5.
ii. Quantity of arch masonry = lm × t × thickness of wall.
iii. Deduction = lm × t × thickness of wall.
7. Lintels over Openings :
i. Lintels are either of RCC or of RB, quantities are calculated in cu m.
ii. Length of the lintel is equal to the clear span plus two bearings. If
dimension of bearing is not given the bearing may be taken as same as
iii. Thus the length of the lintel, l= s + 2t, i.e., clear span plus two bearings.
iv. Quantity of lintel = l × t × thickness of wall.
v. Deduction = l × t × thickness of wall.
Quantity Estimation for Buildings 1–14 C (CE-Sem-5)
l
t
s
Fig. 1.10.6.
30 cm
W W
S
A A
6.00 m
W
Room 4 m × 6 m
W
Room 6 m × 6 m
S
30 cm
30 cm
30 cm
4.00 m 6.00 m
D D
30 cm
(a) Plan
7.5 cm LC Terrace over 13 cm RCC
2 cm DPC
2.5 cm cc Over 7.5 cm LC
40 60 cm
G L
cm 20 cm Doors D-1.20 m × 2.10 m
50 cm 10 cm Windows W-1.00 × 1.50 m
60 cm 10 cm Shelves S-1.00 m × 1.50 m
70 cm 80 cm 10 cm
20 cm
30 cm
1.10 m Lime concrete
(b) Cross-section of wall on AA
Fig. 1.11.1.
Quantity Estimation & Management 1–15 C (CE-Sem-5)
Answer
1. In this problem there are two junctions of the inter wall with the main
wall.
2. Total centre length of wall = 2 × c/c of long wall + 3 × c/c of short wall.
= 2 × 10.60 + 3 × 6.30 = 40.10 m
1.10 m
6.30 m c/c
1.10 m
1.10 m
1.10 m
B
1.10 m
10.60 m c/c
Fig. 1.11.2. Foundation trench plan.
3. If the total centre length is multiplied by the breadth and depth, at the
junction the portions A and B shown by hatch lines in Fig. 1.11.2 come
twice, and we get the quantity in excess by these portions, and these
excesses shall have to be deducted.
4. The deduction may be effected reducing the centre length by half
breadth for each junction.
5. Thus the quantity of earthwork in excavation :
= [Total centre length — (2 × ½ breadth)] × breadth × depth
= (40.10 – 2 × ½ × 1.10) × 1.10 × 1.00 = 39.00 × 1.10 × 1.00 = 42.9 cu m.
6. The same principle applies to foundation concrete, to footings, plinth
wall and superstructure wall.
7. At every stage deduction of half breadth of the main wall at that
particular level shall have to be made per junction (i.e. one breadth for
two junctions) from the total centre length, and this net centre length
after deduction shall be multiplied by the respective breadth and the
height of depth to get quantities.
Quantity Estimation for Buildings 1–16 C (CE-Sem-5)
Answer
Task : The capacity of doing work by an artisan or skilled labour in the
form of quantity of work per day in known as the task-work or out-
turn of the labour.
Quantity Estimation & Management 1–17 C (CE-Sem-5)
Quantity Estimation & Management 2–1 C (CE-Sem-5)
2 Analysis of Rates,
Specification
and Tenders
PART-1
Analysis of Rates Knowing Cost of Material, Labour,
Equipment,Overhead, Profit, Taxes etc.
Questions-Answers
Answer
1. The method of determination of rate per unit of a particular item of
work considering the cost of quantities of materials, the cost of labours,
hire of tools and plants, overhead charges, water charges, contractors
profit etc., is known as rate analysis or analysis of rate.
2. Rates of materials are usually taken as the rates delivered at the site of
work and include the first cost (cost at origin), cost of transport, railway
freight (if any), taxes etc.
3. If the materials are to be carried from a distant place, more than 8 km,
additional cost of transport may be added.
4. A contractor’s profit is added on all items of the particular work which
have been arranged by him.
Purposes of Rate Analysis : The purposes of rate analysis are as
follows :
1. To determine the current rate per unit of an item of work at the locality.
2. To examine the viability of rates quoted by contractors.
Quantity Estimation & Management 2–3 C (CE-Sem-5)
Que 2.2. Give the factors which affect the analysis of rates.
Answer
Factors Affecting Rate Analysis : Followings are the factors that
affect the rate of a particular item of work :
1. Specifications of works and materials, quality of materials, proportion of
mix, method of constructional operation etc.
2. Quantities of materials and their rates.
3. Number of different types of labour and their rates.
4. Location of site of work and its distance from the sources of materials
and rates of transport.
5. Availability of water.
6. Miscellaneous and overhead expenses of contractor.
7. Site conditions and the organizations.
Answer
1. The following information are required to fix up the rate for unit of an
item :
i. Out-turn or Task.
ii. Estimation of labour.
iii. Materials for different items of work.
iv. Current rate of materials.
v. Current rate of labour of different categories.
2. The analysis of rate is done for unit quantity of an item of work.
3. Details of various materials and labour are worked out and added together
to get the total cost of materials and labour.
1
4. This will also include miscellaneous and T and P cost. To this 1
% of it
2
is added for water charge (only in those items which require water in
any way). 10 % contractor’s profit is also added.
5. The summation all these costs is known as rate of unit quantity of an
item.
Analysis of Rates, Specification & Tenders 2–4 C (CE-Sem-5)
6. Mathematically :
i. Let cost of materials for unit item = x
ii. Let cost of labourers, T and P and sundries = y
iii. Cost of material and labour = (x + y)
1 1.5
iv. Add 1 % for water charge = ( x y)
2 100
1.5 10
v. Total cost with contractor profit (= 10 %) = ( x y) 1
100 100
vi. Rate for unit of the item = 1.115 (x + y)
Answer
A. Earthwork per 28.30 cu m (1000 cu ft) :
1. Excavation in foundations, trenches, etc. in ordinary soil including disposal
up to 30 m (100) and lift of 1.5 m (5 ft) – 5 Beldars and 4 Mazdoors can
do 28.30 cu m (1000 cu ft) per day.
2. Refilling excavated earth in foundations, plinth, etc., including
consolidation in 15 cm (6”) layers – 3 Beldars, 2 Mazdoors and 1/2 Bhishti
can do 28.30 cu m (1000 cu ft) per day.
3. Disposal of surplus earth within a lead of 30m (100) – 1 Mazdoor can do
2.83 cu m (100 cu ft) per day.
B. Cement Concrete Work per 2.83 cu m (100 cu ft) :
Laying cement concrete – 2 Beldars, 3 Mazdoors, 3/4 Bhishti and 1/4
Mason can do 2.83 cu m (100 cu ft) per day.
C. RCC Work :
1. Laying reinforced concrete – 3 Beldars, 3 Mazdoors, 1.1/3 Bhishti and
1/2 Mason can do 2.83 cu m (100 cu ft) per day.
2. Centering and shuttering for flat surfaces – 4 Beldars and 4 Carpenters
(II class) can do 9.6 sq m (96 sq ft) per day.
3. Reinforcement work for R.C.C. – 1 Blacksmith or fitter and 1 Beldar can
bend and place in position 1 quintal (2 cwt) of steel per day.
D. Stone Work per 2.83 cu m (100 cu ft) :
Random rubble masonry with blue stone in foundations – 3 Masons, 3
Beldars, 2 Mazdoors and 1/4 Bhishti can do 2.83 cu m (100 cu ft) per day.
E. Brickwork per 2.83 cu m (100 cu ft) :
First class brickwork in 1 : 4 cement mortar in superstructure partition
walls, junctions of roof, parapet walls and string course – 2 14 A Masons,
4 12 Mazdoors and 1/2 Bhishti can do 2.83 cu m (100 cu ft) per day.
Quantity Estimation & Management 2–5 C (CE-Sem-5)
F. Wood Work :
1. For the frames of doors and windows – 2 Carpenters and 1 Beldar can
work 0.18 cu m (6.40 cu ft) of wood equivalent to 4 door frames 7.5 cm ×
10 cm of 1.2m × 2.1 m (3 × 4 of 3 – 11 × 7) size per day.
2. For panelled, glazed, etc., shutters – 15 Carpenters and 4 Beldars can
Que 2.5. Calculate the rate of M15 grade concrete used in slabs of
a single storied building.
Answer
1. In the analysis of rates per cum, at first a volume of 10 cum (set volume)
has been considered to avoid one place of decimal.
2. 1 cum of set volume of concrete corresponds to 1.54 cum of dry volume
of concrete.
3. Therefore for 10 cum of set volume = 15.4 cum of dry volume.
Ratio of proportion in M20 is 1 : 2 : 4
Summation of proportions =1 + 2 + 4 = 7
15.4
4. Cement = = 2.2 cum = 66 bags ( 1 cum cement = 30 bags of
7
cement)
Sand = 2.2 × 2 = 4.4 cum
Stone chips = 2.2 × 4 = 8.8 cum.
Analysis of Rates, Specification & Tenders 2–6 C (CE-Sem-5)
19,925.05
Rate per cu m = = Rs. 1992.505
10
Quantity Estimation & Management 2–7 C (CE-Sem-5)
Que 2.6. Calculate the quantity and rate for 25 mm thick DPC.
Answer
1. The quantity of cement concrete may be calculated by multiplying the
area of DPC by the thickness and the quantity of each material may be
calculated as :
2. For 2.5 cm cement concrete DPC for 100 m2 of area, the quantity of
cement concrete = 100 × 0.025 = 2.5 m3
Add 10 % extra for unevenness of base concrete = 2.5 + 0.25 = 2.75 m3
3. For 2.5 cm thick DPC of 1 :1.5 : 3 proportion, for 100 m2 total dry volume
of materials 2.75 + 50 % = 2.75 + 1.375 = 4.125 m3
4.125
4. Therefore cement = 0.75 m3 = 22.5 bags
1 1.5 3
5. Quantity of sand = 0.75 × 1.5 = 1.13 m3
6. Quantity of stone aggregate = 0.75 × 3 = 2.25 m3
25 mm thick cement concrete 1 : 1.5 : 3 damp proof course (DPC) unit
1 sq m (Take 100 sq m)
Particulars Quantity or Rate Cost
Nos (Rs.) (Rs.)
a. Materials :
Stone chips 12 mm 2.25 cu m 1900 per cu m 4275
Coarse sand 1.13 cu m 1800 per cu m 2034
Cement (22.5 bag) 0.75 cu m 9700 per cu m 7275
Cem-seal or 22.5 kg 75 per kg 1687.5
impermo (1 kg per
bag of cement)
Total 15271.5
b. Labour
Head mason 1/3 425 per day 141.7
Mason 8 400 per day 3200
Mazdoor 8 250 per day 2000
Bhisti 1 230 per day 230
From insides Lumpsum 250 (LS) 250
Sundries, T and P Lumpsum 100 (LS) 100
Total 5921.7
Total of materials and labour 21193.2
c. Add water charge @ 1 ½ % of (a + b) 318
d. Contractor’s profit @ 10 % of (a + b) 2119.32
Grand Total for 100 m2 = Rs. 23630.52
23630.52
Rate per m2 = = Rs. 236.3052
100
Analysis of Rates, Specification & Tenders 2–8 C (CE-Sem-5)
Que 2.7. Find out rate analysis for excavation in a trench for
foundation.
Answer
Answer
To find the material for 10 m3 of concrete of 1 : 4 : 8 proportion cement
15.4 15.4
=
148 13
= 1.18 m3, say = 1.15 m3
Therefore sand = 1.15 × 4 = 4.6 m3 and aggregate = 8 × 1.15 = 9.20 m3
Quantity Estimation & Management 2–9 C (CE-Sem-5)
Que 2.9. Find out rate analysis for white washing three coats for
100 sqm.
Answer
White washing three cost-unit 100 m2.
Analysis of Rates, Specification & Tenders 2–10 C (CE-Sem-5)
1 3
White washer 1 no. 300 per day 300 = 450
2 2
1 3
Boy or woman coolie 1 no. 230 per day 230 = 345
2 2
Sundries, ladder, etc Lumpsum 12 LS 12
Total 807
Total of materials and labour 338 + 807 = 1145
c. Add water charge 1.5 % of (a + b) 17.175
d. Contractor’s profit @ 10 % of (a + b) 114.5
Grand Total for 100 m2 Rs. 1276.675
Que 2.10. Find out rate analysis for RB work in slab etc, 1 : 3
mortar.
Answer
Reinforced brick work (RB work) in slab, etc 1 : 3 mortar. Take
10 cu m.
Quantity Estimation & Management 2–11 C (CE-Sem-5)
a. Materials :
Brick (1 class @ 450 4500 8000 % nos 36000
nos/cu m
Cement (36 bags) 1.2 cu m 9700 per cu m 11640
Sand (coarse) 3.6 cu m 1800 per cu m 6480
Mild steel rods @
0.8 % = 0.08 cu m @
78.5 q/cu m = 6.25 q 6.25 q 4200 per q 26250
Total 80370
b. Labour :
Mistri 1/2 nos. 425 per day 212.5
Mason 10 nos. 400 per day 4000
Mazdoor (beldar) 10 nos. 250 per day 2500
Boy or woman coolie 10 nos. 230 per day 2300
Bhistri 4 nos. 230 per day 920
Sundries, T and P Lumpsum 150 (LS) 150
Total 10082.5
c. Bending and
Cracking Steel
Black smith 6 nos. 300 per day 1800
Mazdoor (Beldar) 6 nos. 250 per day 1500
T and P Lumpsum 100 LS 100
Total 3400
d. Centering and
shuttering
Timber planks and
ballies Lumpsum 2000 per day 2000
Carpenter (II class) 8 nos 300 per day 2400
Mazdoor (Beldar) 8 nos 250 per day 2000
Nails Lumpsum 200 LS 200
T and P Lumpsum 100 LS 100
Total 6700
Total of materials and labour 100552.5
e. Add water charge @ 1 ½ % of (a + b + c + d) 1508.3
f. Contractor’s profit @ 10 % of (a + b + c + d) 10055.25
Grand Total 112116.05 for 10 cu m
Rate per cu m Rs. 112116.05/10 = Rs. 11211.6
Analysis of Rates, Specification & Tenders 2–12 C (CE-Sem-5)
PART-2
Specification.
Questions-Answers
Que 2.11. What is specification and its objects ? Also explain its
types.
Answer
Specification : A specification is a statement of particulars.
Construction specifications may be defined as written instructions
distinguishing (or limiting) and describing in detail the construction
work to be undertaken.
Objects : Following are the objects of specification :
1. Contract Document : Specifications serve as a contract document
between the owner and the contractor, limiting and describing their
responsibilities.
2. Guide to Bidders : Specifications enable the estimators of the
contractors to arrive at a fair price for the work involved.
3. Guide to Supervisors : Specifications serve as a guide for the
fabrication and installation of materials and equipment.
Types of Specification : Following are the two types of specification :
1. General Specifications :
i. In general specifications, nature and class of works and names of
materials that should be used are described.
ii. Only a brief description of each and every item is given. It is useful for
estimating the project.
Quantity Estimation & Management 2–13 C (CE-Sem-5)
Answer
Importance of Specifications : Following are the importance of
specifications :
1. The cost of a unit quantity of work is governed by its specifications.
2. Specification of a work is required to describe the quality and quantity
of different materials required for a construction work and is one of
the essential contract documents.
3. This also specifies the workmanship and the method of doing the work.
4. A work is carried out according to its specification and the contractor is
paid for the same. Any change in specification changes the tendered
rate.
5. As the rate of work is based on the specification, a contractor can
calculate the rates of various items of works in tender with his
procurement rates of materials and labour. Thus tender rate without
specification of works is baseless, incomplete and invalid.
6. Specification is necessary to specify the equipment tools and plants to
be engaged for a work and thus enables to procure them beforehand.
7. The necessity of specification is to verify and check the strength of
materials for a work involved in a project.
Answer
Earthwork in Excavation in Foundation : Following are the points
consider in excavation in foundation :
Analysis of Rates, Specification & Tenders 2–14 C (CE-Sem-5)
1. Excavation :
i. Foundation trenches shall be dug out to the exact width of foundation
concrete and the sides shall be vertical.
ii. If the soil is not good and does not permit vertical sides, the sides
should be sloped back or protected with timber shoring.
iii. Excavated earth shall not be placed within 1 m of the edge of the
trench.
2. Finish of Trench :
i. The bottom of foundation trenches shall be perfectly leveled both
longitudinally and transversely and the sides of the trench shall be
dressed perfectly vertical from bottom up to the least thickness of
loose concrete so that concrete may be laid to the exact width as per
design.
ii. The bed of the trench shall be lightly watered and well rammed. Excess
digging if done through mistake shall be filled with concrete at the
expense of the contractor.
iii. Soft or defective spots shall be dug out and removed filled with concrete
or with stabilized soil.
iv. If rocks or boulders are found during excavation, these should be
removed and the bed of the trenches shall be leveled and made hard by
consolidating the earth.
v. Foundation concrete shall not be laid before the inspection and approval
of the trench by the engineer-in-charge.
3. Water in Foundation : Water, if any accumulates in the trench,
should be bailed or pumped out without any extra payment and
necessary precautions shall be taken to prevent surface water to enter
into the trench.
4. Trench Filling : After the concrete has been laid masonry has been
constructed the remaining portion of the trenches shall be filled up
with earth in layers of 15 cm and watered and well rammed.
5. Measurement :
i. The measurement of the excavation shall be taken in cu m (cu ft) as
for rectangular trench bottom width of concrete multiplied by the
vertical depth of foundation from ground level and multiplied, by the
length of trenches even though the contractor might have excavated
with sloping side for his convenience.
ii. Rate shall be for complete work for 30 m lead and 1.50 m lift, including
all tools and plants required for the completion of the works.
iii. For every extra lead of 30 m and every extra lift of 1.5 m separate extra
rate is provided.
Quantity Estimation & Management 2–15 C (CE-Sem-5)
Answer
Detailed Specification of Cement Concrete 1 : 2 : 4 : Following are
the point consider in specifications of cement concrete 1 : 2 : 4 :
1. Materials :
i. Aggregate shall be of invert materials and should be clean, dense,
hard, sound, durable, non-absorbent and capable of developing good
bond with mortar.
ii. Coarse aggregate shall be of hard broken stone of granite or similar
stone, free from dust, dirt and other foreign matters.
iii. The stone ballast shall be of 20 mm size and down and all should be
retained in a 5 mm square mesh and well graded such that the voids do
not exceed 42 per cent.
iv. For building work 20 mm gauge and for road work and mass work 40
to 60 mm gauge may be used.
v. Fine aggregate shall be of coarse sand consisting of hard, sharp and
angular grains and shall pass through screen of 5 mm square mesh.
vi. Cement shall be fresh Portland cement of standard ISI, specifications,
and shall have the required tensile and compressive stresses and
fineness.
vii. Water shall be clean and free from alkaline and acid matters and
suitable for drinking purposes.
2. Proportion :
i. The proportion of concrete shall be 1 : 2 : 4 as cement : sand : stone
ballast by volume unless otherwise specified.
ii. Minimum compressive strength of concrete of 1 : 2 : 4 proportion shall
be 140 kg per sq cm (2000 lbs/sq in) on 7 days.
iii. Stone aggregate and sand shall be measured by volume with boxes.
iv. Cement need not be measured by box, one bag of cement (50 kg)
should be considered as 1/ 30 cum.
v. Size of measured box may be 30 cm × 30 cm × 38 cm or 35 cm × 35 cm
× 28 cm equivalent to content of one bag of cement.
3. Hand Mixing :
i. Mixing shall be done in masonry platform or sheet iron tray.
ii. For concrete of 1 : 2 : 4 proportion, first two boxes of sand and one bag
of cement shall be mixed dry thoroughly and then this dry mix of
cement and sand shall be placed over a stack of 4 boxes of stone
aggregate and the whole mixed dry turning at least three times to
have uniform mix.
Analysis of Rates, Specification & Tenders 2–16 C (CE-Sem-5)
iii. Water shall then be added slowly and gradually according to water-
cement ratio with a water-can while.
iv. The whole shall be mixed thoroughly turning at least three times to
give a uniform concrete.
4. Machine mixing :
i. Stone ballast sand and cement shall be put into the cement concrete
mixer to have the required proportion.
ii. Mixer, the machine shall then be revolved to mix materials dry and
then water shall be added gradually to the required quantity.
5. Formwork :
i. Formwork centering and shuttering shall be provided as required, as
per standard specifications before laying concrete to confine to support
or to keep the concrete in position.
ii. The inner surface of shuttering shall be oiled to prevent concrete
sticking to it.
iii. The base and formwork over which concrete to be laid shall be watered
by sprinkling water before concrete is laid.
iv. Forms should not be removed before 14 days in general, side forms
may however be removed after 3 days of concreting.
6. Laying :
i. Concrete shall be laid gently (not thrown) in layers not exceeding
15 cm and compacted by pinning with rods and tamping with wooden
tampers or with mechanical vibrating machine until a dense concrete
is obtained.
ii. Concrete shall be laid continuously, if laying is suspended for rest or
for the following day the end shall be sloped at an angle of 30° and
made rough for further jointing.
iii. When the work is resumed, the previous sloped portion shall be
roughened, cleaned and watered and a grout of neat cement shall be
applied and the fresh concrete shall be laid.
iv. For successive layer the upper layer shall be laid before the lower has
set.
7. Curing : After about two hours laying when concrete has begun to
harden, it shall be kept damp by covering with wet gunny bags or wet
sand for 24 hours, and then cured by flooding with water making mud
walls 7.5 cm high or by covering with wet sand or earth and kept damp
continuously for 15 days.
Answer
Following are the general specification of first class building :
1. Foundation and Plinth : Foundation and plinth shall be of 1st class
brickwork in lime mortar or 1 : 6 cement mortar over lime concrete or
1 : 4 : 8 cement concrete.
2. Damp Proof Course : DPC shall be 2.5 cm thick cement concrete
1: 1 12 : 3, mixed with one kg of Impermo per bag of cement or other
standard water proofing materials as specified and painted with two
coats of bitumen.
3. Superstructure : Superstructure shall be of 1st class brickwork with
lime mortar or 1:6 cement mortar. Lintels over doors and windows
shall be of RCC.
4. Roofing :
i. Roof shall be of RCC slab with an insulation layer and lime concrete
terracing above, supported over RS Joists or RCC beams as required.
ii. Height of rooms shall not be less than 3.7 m (12 feet).
5. Flooring :
i. Drawing room and dining room floors shall be of mosaic (terrazo).
ii. Bathroom and WC floors and dado shall be of mosaic (terrazo).
iii. Floors of bedrooms shall be coloured and polished of 2.5 cm cement
concrete over 7.5 cm lime concrete.
6. Finishing :
i. Inside and outside walls shall be of 12 mm cement lime plastered 1 : 6.
ii. Drawing, dining and bedrooms — inside shall be distempered, and
others — inside washed 3 coats.
iii. Outside shall be coloured snowcem washed two coats over one coat of
white wash.
7. Doors and windows : Chaukhats shall be seasoned teak wood.
Shutters shall be teak wood 4.3 cm thick panelled glazed or partly
panelled and partly glazed as required, with additional wire gauge
shutters.
8. Miscellaneous :
i. Rain water pipes of cast iron or of asbestos cement shall be provided
and finished painted.
ii. Building shall be provided with first class sanitary and water fittings
and electrical installations.
Answer
Following are the general specification of second class buildings :
1. Foundation and Plinth : Foundation and plinth shall be of 1st class
brickwork with lime mortar over lime concrete.
2. Damp Proof Course : DPC shall be of 2 cm thick cement concrete
1 : 2 mixed with 1 kg of Impermo per bag of cement or other standard
water proofing materials.
3. Superstructure : Superstructure shall be of 2nd class brickwork in
lime mortar. Lintels over doors and windows shall be of reinforced
brick (RB).
4. Roofing :
i. Roof shall be RB slab with 7.5 cm lime concrete terracing above (or hat
terraced roof supported over wooden battens and beams, or Jack arch
roof).
ii. Verandah roof may be of asbestos cement (AC) sheet or Allahabad
tiles.
5. Flooring : Floors shall be 2.5 cm cement concrete over 7.5 cm LC.
Verandah floor shall be of brick tile or flag stone over lime concrete,
finished cement painted.
6. Finishing :
i. Inside and outside walls shall be of 12 mm cement mortar plastered
1 : 6.
ii. Ceiling shall be cement plastered 1:3.
iii. Inside shall be white washed 3 coats, colour washed two coats over one
coat of white wash.
7. Doors and Windows :
i. Chaukhat shall be of RCC or well seasoned wood, shutters of shisham
wood or deodar wood 4 cm thick, panelled, glazed or partly panelled
and partly glazed as required, fitted with iron fittings.
ii. Doors and windows shall be painted two coats over one coat of priming.
8. Miscellaneous :
i. Rain water pipes shall be of cast iron finished painted.
ii. Electrification, and sanitary and water fittings may be provided if
required.
Quantity Estimation & Management 2–19 C (CE-Sem-5)
PART-3
Legal Aspect of Contracts, Law Related to Contracts, Land
Acquisition, Labour Safety and Welfare, Different Type of
Contract their Relative Advantages and Disadvantages.
Questions-Answers
Que 2.17. Explain the legal aspects of contracts and various laws
Answer
Legal Aspects :
i. Construction work on project takes on land. For a contract to be legally
valid the construction project must fit into the legal framework governing
the property.
ii. These include government regulations on the use of property and
obligation that are created in the process of construction.
iii. Since a contract is an exchange set of obligations between two or more
parties, it must be designed to ensure that each side is capable of
performing the obligation set out.
Following are the main requirements of a valid contract so that it may
be legal binding on both/all the involved parties.
1. Legally Competent Parties :
i. As per Indian Contract Act, the parties entering into contract should be
legally competent.
ii. Anyone who is of the age of majority and is of sound mind can enter into
a contract.
iii. Subordinate authority who has not been directed or authorised cannot
be involved in signing any contract.
2. Free Consent of Parties :
i. It means concurring of two minds in respect of the same opinion, purpose
or understanding as regards the course to be pursued.
ii. Contract is said to be free consent when :
a. It is not caused under any influence.
b. It is not caused by mistake.
c. It is not caused by misrepresentation.
d. It is not caused by fraud.
e. It is not caused under duress.
3. Proper and Valid Consideration :
i. Legally, valid consideration is termed as the act or a promise to do
something by a party in return of money or promise or grant of some
interests by other party.
ii. The consideration may not be adequate or a full return of the promise,
but it must be component, real and should not be illegal, ambiguous,
impossible or uncertain.
4. Meaningful Contract in Writing and Signed by Both Parties :
i. Meaning of agreement should be certain or capable of being made certain.
ii. According to the law, the contract must be signed by the authorised
persons of both the parties.
Quantity Estimation & Management 2–21 C (CE-Sem-5)
iii. In case of public bodies, an official duly authorised for this purpose signs
the contract fixing the seal of the public body on the agreement.
5. Various Laws :
i. The Law of Contracts is the basis of business law because the bulk of
transactions of the people engaged in trade, commerce and industry are
based on contracts.
ii. In India, the Law of Contracts is contained in the Indian Contract Act,
1872.
iii. Though the Partnership Act, the Sale of Goods Act; the Negotiable
Instruments Act, the Companies Act, technically belong to the Law of
Contracts yet they have been covered by separate enactments.
iv. However, the general principles of the Contract Law are the basis for all
such contracts as well.
The main features of the Law of Contracts are :
a. The parties to the contract make the law for themselves.
b. The Act is not exhaustive since, it does not take into its purview all the
relevant legislations.
c. It does not override customs or usages.
Answer
Land Acquisition : It refers to the process by which the union or a
state government in India acquires private land for the purpose of
industrialization, development of infrastructure facilitates or
urbanization of the private land and provides compensation to the
affected land owners and their rehabilitation and resettlement.
Following are the two bases of land acquired in India :
1. Permanent Land : Land is to be acquired permanently for the
expected life of the project.
For example, consider the case of laying a new pipeline. Land is acquired
permanently along the pipeline route and the facility sites such as
pump stations, metering stations, block valve station, anode ground
beds, power line pylons, etc.
2. Temporary Land :
i. All areas which are needed in addition to the permanently acquire land
in order to carry out the construction and installation of the pipelines
system and associated facilities are acquired on temporary basis.
ii. This includes contractor camp, storage yards and other auxiliary areas
needed for the storage of equipment and materials.
The Constitutional Framework :
“The Land Acquisition Act, 1894”.
Analysis of Rates, Specification & Tenders 2–22 C (CE-Sem-5)
Que 2.19. What are the various Indian laws related to labour safety
and welfare ?
Answer
Following are laws/act related to labour safety and welfare :
1. Payment of Wages Act :
i. This act is related to the payment of wages. This act was introduced to
regulate the payment of wages, imposition of fines, etc.
ii. According to this act, wages are to be paid promptly on a monthly basis
and if any person is terminated from services, his wages should be
settled within 2 days of the termination.
2. Minimum Wages Act :
i. According to this act, provision is made for the statutory fixation of a
minimum rate of wages in the establishment.
ii. According to this act, different minimum rates can be fixed depending
on the class of work, type of personnel employed-adults, permanent
employee or, apprentice and depending on the location of work.
3. Factories Act :
i. Under this act, the health, safety, welfare, working hours, annual
leave, accidents and any penalties are taken care of.
ii. Regarding health, arrangements for proper cleanliness of the premises,
disposal of wastes, ventilation and comfortable working temperature
are to be maintained.
iii. Normally, the working hours are restricted to 8 hours/day with a lunch
break for 1/2 hr and a total of not more than 48 hours/week.
iv. If the worker is engaged on holidays, compensatory leave is to be
given. Over time wages are at twice the ordinary rate of wages.
v. Women workers should be employed only from 6 a.m. to 7 p.m.
vi. In case of accident, proper compensation is to be paid as per the
provision.
4. Contract Labour (Regulation and Abolition) Act, 1970 (Amended
1986) :
Quantity Estimation & Management 2–23 C (CE-Sem-5)
i. This act contains the provisions for improving the condition of contract
labour.
ii. According to this Act contractors should get themselves registered and
obtain certificates of registration.
iii. The welfare and health provisions to be provided to the contract labour
include rest rooms, proper ventilation, lighting, water supply and
sanitary facilities.
iv. First aid facilities and washing are also contained in this act.
v. Payment of wages to each worker is to be made within the prescribed
period.
5. Workmen’s Compensation, Act, 1923 (Amended-1984) :
i. This act is for providing social security to the workers. Compensation
is to be paid to the workers in case of accidents sustained during the
course of employment and the amount is decided upon its seriousness.
ii. Under this act, financial relief is given in the following cases :
a. In case of death,
b. On account of occupational diseases,
c. For permanent/partial disablement, and
d. Half-monthly payments for temporary disablement.
6. The Trade Union Act, 1926 :
i. Trade union is an association of persons formed mainly for the purpose
of regulating the relations between employers and employees.
ii. A minimum of 7 workers can join together and form a trade union.
iii. The union has to get itself registered with the registrar of trade union.
The relevant details such as the name, address, the objectives of forming
the union and the subscription rate are all to be specified before
registration.
Answer
Types of Contract : The following are the various types of contracts
for execution of civil engineering works, with their relative merits and
demerits :
1. Item Rate Contract :
Analysis of Rates, Specification & Tenders 2–24 C (CE-Sem-5)
ii. By negotiating among the contractors, two or more may quote the same
rate in order to get a part of the work at a high rate. It may be difficult
to divide the work at equal amount among the contractors.
3. Lump-Sum Contract :
i. In this type of contract, a contractor is required to quote a fixed sum for
execution of work complete in all respect in the stipulated time according
to the drawing, design and specifications supplied to him with the tender.
ii. The departmental schedule of rate for various items of work is also
provided which regulates the payment of the contractor in respect of
any additions and alterations which are made over the original work.
iii. On the completion of the work, no detailed measurement of different
items of work is needed but the whole work done must be compared and
checked with the drawings and specifications.
Merits :
i. As the total cost of the work known before hand, the owner can arrange
the fund in time.
ii. Detailed measurements of the work done are not required except in
respect of additions and alterations.
iii. The contractor’s profit mainly lies in the completion time. Hence for
getting more profit the contractor tries to complete the work as early as
possible.
Demerits :
i. It is very essential that the work must be defined accurately, specifications
must be fully specified and the site conditions must be fully explained
otherwise disputes can arise later on.
ii. For any intermediate payment, the value of work done should not be
less than the payment being made.
4. Labour Contract :
i. In labour contract, the contractor undertakes contract for the labour
portion only excluding the materials which are arranged and supplied at
the work site by the department/owner.
ii. The contractor engages the requisite labour and gets the work done as
per drawings and specifications.
iii. It is an item rate basis for labour portion only and the contractor is paid
for the quantities of work done on measurement of different items of
work at the stipulated rate in the contract agreement.
Merits :
i. The materials stored by the department are thus utilised.
ii. The work done through labour contract is of superior quality as better
quality materials are arranged by the owner.
iii. The overall cost of construction may be less, as no profit is paid on the
cost of materials.
Analysis of Rates, Specification & Tenders 2–26 C (CE-Sem-5)
Answer
Following are the elements of tender preparation :
1. As part of the preparation work, and before any tender is advertised,
the procuring agency requires a realistic estimate of the cost of the
structure with a breakdown of significant cost items.
2. To prepare such an estimate, an engineer should be selected and be
appointed to not only carry out this preliminary work but continue to
supervise the contractor and ensure all works are carried out according
to the design and to the highest quality possible.
Quantity Estimation & Management 2–27 C (CE-Sem-5)
Answer
1. For execution of work through contract, especially in an open bidding
system, the jobs need to be given due publicity. A common practice is to
publish a formal notice inviting tender (NIT) in leading national and
local newspapers.
2. The NIT is also pasted on the notice boards of departments inviting
tenders. Now-a-days internet is also being used.
3. NIT is uploaded on company’s official website or the concerned
government department with the following details :
i. Name of the authority inviting the bids,
ii. Name of the project,
iii. Conditions for eligibility of contracting agencies to submit a bid,
iv. Brief details of the project,
v. Estimated cost and time of completion of the project,
vi. The cost of the tender documents,
vii. Earnest money to be deposited with the completed tender,
viii. Date and time by which the bids are to be submitted and the place of
submission,
ix. The date and time of opening of the bids, and
x. Validity of the tender, etc.
4. Tender notice also includes a number of information and conditions in
addition to a few mentioned in the typical tender notice viz., refund of
earnest money, period of validity of rates quoted, site inspection, not
relative of contractor, rates to include all taxes, (about 2 % of gross
amount), source and specification of materials, change of address, etc.
Analysis of Rates, Specification & Tenders 2–28 C (CE-Sem-5)
5. When tender form is obtained from the office, the tender notice will
include all such particulars. These items are not given in contract
document. Hence, the tender notice is very important document on
which the subsequent agreements with the contractors are based.
6. Therefore, it is necessary that the tender notice must be included in the
contract document.
PART-4
Process of Tendering, Pre-qualification of Contracts, Evaluation
of Tenders, Contract Negotiation and Award of Work,
Monitoring of Contract Extra Items.
Questions-Answers
Answer
A. Process of Tendering : The process of tendering consists of the
following steps :
1. Tender Process is Determined : The organization requesting the
tender will determine the type of tender that will be used, as well as
what will be involved in the tender process.
Quantity Estimation & Management 2–29 C (CE-Sem-5)
Answer
A. Tender Opening Procedure :
1. A member of the tender panel will collect the unopened tender envelopes
from secure storage and the panel shall assemble, preferably in a room
where they can be undisturbed.
2. Each envelope should be opened in turn and the tender date, name of
the tenderer, tender sum(s) and delivery time recorded on the schedule
of tenders.
3. All pages containing prices should be date stamped and initialed by a
member of the tender panel.
4. When all tenders have been recorded, each member of the tender Panel
should sign the schedule of tenders.
5. Where more than one copy of a tender is submitted the tender panel
should ensure that the tender sum(s) on each copy are identical.
6. One copy should be marked ‘Master Copy’ and retained by the person
responsible for the tender exercise, this will form part of the contract
documentation.
7. A copy of the completed schedule of tenders should be sent to the
Purchasing Office.
B. Acceptance Procedure :
1. Inform all tenders as soon as possible of the outcome.
2. Arrange for unsuccessful tenderers to return any retained documents.
3. Issue a letter of acceptance setting out any conditions or provisos which
have been agreed since issuing the documents and directing the
contractor to carry out all further correspondence with the ‘Engineer’
under the contract.
4. If there is a delay to formal acceptance, a letter of intent may be sent
containing instructions to proceed (or not to proceed) with design,
ordering materials etc, and setting a limit to financial liability before
formal acceptance.
C. Execution of Agreement : When concluding a contract or agreement,
the parties shall clearly state how they will perform their obligations.
1. The obligations under the contract shall be duly performed in accordance
with the conditions of the obligation and requirements of legislation,
and if there are no such conditions and requirements in accordance
with generally specified requirements.
2. Unilateral refuse to perform the obligation and unilateral change of its
condition shall not be admitted, unless otherwise results from legislation
or the contract.
3. The creditor is entitled not to accept the performance of the obligations
by parts, unless otherwise is provided by legislation or conditions of the
obligation.
4. When the obligation is performed the debtor has the right to demand
the evidence that the performance is accepted by the creditor or a person
Quantity Estimation & Management 2–31 C (CE-Sem-5)
Answer
The Prequalification Process :
1. Advertisement and Notification : It is the employer’s responsibility
to advertise the Invitation for Prequalification (IFP) on the ADB website
as well as in :
i. A newspaper of general circulation in the borrower’s country (at least
one English-language newspaper, if available)
ii. An internationally known and freely website in English.
2. Preparing and Issuing a Prequalification Document :
i. The e mplo ye r is respo nsible fo r pre paring and issuing the
prequalification document.
ii. The employer shall use ADB’s Standard Procurement Document for
the Prequalification of Bidders (SPQD).
iii. The employer shall prepare the prequalification document using the
published version of the SPQD without suppressing or adding text to
Section 1-Instructions to Applicants (ITA).
All information and data particular to each individual prequalification
process must be provided by the employer in the following sections of
the prequalification document :
Section 2 Application Data Sheet
Section 3 Qualification Criteria
Section 4 Application Forms
Section 5 Eligible Countries
Section 6 Scope of Contract
iv. The employer shall allow applicants a minimum period of 42 days to :
a. Study the prequalification document,
b. Prepare complete and responsive applications, and
c. Submit their applications.
3. Preparation and Submission of Applications :
i. The applicant is solely responsible for the preparation and submission
of its application.
ii. During this stage, the employer shall :
a. Promptly respond to requests for clarifications from applicants and
amend, as needed, the prequalification document; and
b. Amend the prequalification document only with the prior approval of
ADB.
Analysis of Rates, Specification & Tenders 2–32 C (CE-Sem-5)
Answer
A. Reciprocal Promises :
i. Promises which form the consideration or a part of consideration for
each other are called reciprocal promises.
ii. An agreement may consist of either :
a. A promise supported by consideration given, or
b. A promise supported by another promise.
iii. In the latter case, when an agreement is supported by another promise,
it will be a reciprocal promise.
iv. Thus, in reciprocal promises each party gives a promise for a promise.
Reciprocal promises are of the following types :
i. Mutual and Independent Reciprocal Promises : When each party
performs his promise independently and irrespective of the fact whether
the other party has performed, or is willing to perform his promise or
not, the promises are mutual and independent.
Example : X agrees Y to supply milk daily, while Y agrees to pay the
price of milk every month. Both these are mutual and independent
promises.
ii. Conditional and Dependent Reciprocal Promises : When the
performance of a promise by one party depends upon the prior permission
of the other party, it will be a conditional and dependent promise.
Example : X promises to construct Y ’s house, provided that Y supplies
cement and bricks. This will be a conditional and dependent promise.
Here, X need not perform the promise if Y fails to supply cement and
bricks.
iii. Mutual and Concurrent or Simultaneous Reciprocal Promises :
This is the state when two contracts are to be performed simultaneously.
Example : All cash sales are examples of simultaneous or concurrent
promises, as delivery of goods and payment of price take place
simultaneously.
B. Breach of the Contract : Breach is non-fulfillment of an agreed
promise under the contract such as :
i. Not handing over the assignment mentioned in the contract on stipulated
timelines.
ii. Not furnishing the relevant document to the promisor for making the
payment.
iii. Not making payments on time as per the contract for work done.
iv. Not confirming to the schedule mentioned in the contract.
v. Not completing the works as per milestones mentioned in the contract.
Answer
Retention Money : It is an amount held back from a payment made
under a construction contract. It is usually a percentage (5%) of the
amount payable of each installment. It is generally held to ensure that
a contractor performs all of its obligations under the contract, and is
then released either on practical completion or after the end of a defects
notification period.
Purpose of Retention Money :
1. In general, Retention Money provides protection to the employer.
Retention money gives the idea of importance of completing the signed
project as per its terms and designs.
2. With such retention held, the contractor takes the responsibility to
complete the construction project as per the design and quality stated in
the initial contract.
Condition for Reduced Rate : If the contractor fails to carry out the
work strictly in accordance with the drawings and specifications, and, if
in the opinion of the engineer, the work is structurally sound, he may
accept the work, but the contractor will be paid at reduced rates which
will be decided by the engineer.
Example : Assume that the specification for teak wood panelled
windows and doors mentions that the thickness of the shutters should
be 4 cm and if the shutters actually provided by the contractor are only
3.5 cm thick, the engineer may accept the work and reduce the rate per
square metre of the shutters by an amount equal to the reduction in the
cost of the materials used in the work.
Answer
1. Earnest Money :
i. Earnest money is an assurance or guarantee on the part of the contractor
to keep the offer for consideration and to confirm his intention to take
up the work if accepted in his favour for execution as per terms and
conditions in the tender.
2. Following are the importance of earnest money :
i. Compensation : In case, the contractor refuses to take up the work or
runs away when his tender is accepted, the work can be allotted to the
next lowest bidder. The earnest money forfeited compensates the loss
of owner/department to a great extent.
Quantity Estimation & Management 2–35 C (CE-Sem-5)
ii. Punishment : In case the contractor quotes lower rate without intention
of doing the work, the earnest money shall be forfeited as a punishment.
iii. Restriction on Unnecessary Competition : The provision of earnest
money will restrict the entry of many contractors who may not have
enough resources to do the work.
2. Security Deposit :
i. The contractor whose tender has been accepted is to deposit 10 % of the
tendered amount as security money with the department inclusive of
the earnest money already deposited.
ii. This amount is kept as a check so that the contractor fulfils all the terms
and conditions and carries out the work satisfactorily within the
prescribed time limit.
iii. If the contractor fails on this part, his whole or part of the security
money is forfeited by the department as a punishment.
iv. The security money also serves as a security against the materials or
the tools and machineries provided by the department to the contractor
on loan.
3. Maintenance Liability Period of Contract :
i. The maintenance period is the period following completion of a
construction project during which the contractor is responsible for certain
maintenance issues under the many building or engineering contracts.
ii. During this period, the contractor needs to maintain insurance in force,
the extent of which will depend on the contract and on his own concern
for the risk he is facing.
iii. Normally the maintenance period will last for twelve months from the
completion of the contract but this may be longer or shorter.
4. Debitable agency : When the contractor fails to fulfill his contractual
obligation in respect of progress or quality of work even after being
given due notice by the owner, a debitable agency is appointed. The
expenses incurred will be charged from the bills of contractor or security
money deposited earlier.
5. Registration of Contractors and Suppliers by Engineering
Departments :
i. The contractor and suppliers must get himself registered in the
departments (or Government) for which he is interested to take up
works.
ii. Government contractors are entitled to do government jobs if awarded.
iii. Contractors are classified according to the registration and registration
fees and depending on this they can undertake works up to certain
amount.
Analysis of Rates, Specification & Tenders 2–36 C (CE-Sem-5)
Quantity Estimation & Management 3–1 C (CE-Sem-5)
3 Elements of
Management and
Network Techniques
• Project Cycle
• Organization
• Planning
• Scheduling
• Monitoring
• Updating and Management System in Construction
• Bar Charts
• Milestone Charts
• Work Break Down Structure and Preparation of Networks
• Network Techniques Like PERT and CPM in Construction
Management
• Project Monitoring and Resource Allocation Through Network
Techniques
PART-1
Project Cycle, Organization, Planning, Scheduling, Monitoring
Updating and Management System in Construction.
Questions-Answers
Answer
A. Project Life Cycle : All projects can be mapped to the following simple
life cycle structure :
Starting the project organizing and preparing carrying out the
work closing the project.
Quantity Estimation & Management 3–3 C (CE-Sem-5)
Answer
Organization :
i. Organization is the systematic arrangement of people working together
towards a common purpose.
ii. It is composed of a group of individuals acting as a unit for the attainment
of an objective.
Types of Organization : Following are the various types of
organization :
1. Line Organization :
i. Under line organization, each department is generally a complete self-
contained unit. A separate person will look after the activities of the
department and he has full control over the department.
ii. The same level executives do not give or receive orders amongst
themselves. But they receive orders from their immediate boss and
give orders to their subordinates.
Characteristics of Line Organization :
i. It consists of direct vertical relationships.
ii. Authority flows from top-level to bottom level.
iii. Departmental heads are given full freedom to control their departments.
iv. A senior member has direct command over his subordinates.
v. Existence of direct relationship between superiors and subordinates.
vi. The superior takes decisions within the scope of his authority.
Advantages :
i. It is simple in form with a clear cut division of authority.
ii. The decisions are speedy and their implementation is quick.
iii. It promotes greater co-ordination and keeps better discipline.
Quantity Estimation & Management 3–5 C (CE-Sem-5)
Advantages :
i. Facilitates to work faster and better.
ii. Officers can take sound advice.
iii. Promotes efficient functioning of line officers.
Disadvantages :
i. There may be confusion about the relation between staff and line
employees.
ii. If power are not defined then get confusion.
iii. Line officers may reject advice without any reason for their action.
iv. Line officers blame staff officers for unfavorable results and want to
get rewards for favorable results.
Answer
Answer
Following are the six main functions of management in construction
project :
1. Planning :
i. The first managerial function involves planning. The function is about
creating a detailed plan towards achieving a specific organizational
objective.
ii. When you are planning, you are identifying the tasks, which are required
to achieve the desired goals, outlining how the tasks should be performed,
and identifying when and by whom they must be performed.
iii. The focus of planning is about achieving the objectives and it does require
knowledge of the organization’s objectives and vision.
2. Organizing :
i. The next function of management follows planning and it is about
organizing. It’s about using the plan to bring together the physical,
financial and other available resources and use them to achieve the
organizational goal.
ii. It involves a certain pattern of relationship of authority and responsibility
among the members of groups, so that the work is performed with
speed, accuracy and economy to achieve the organizational objectives.
3. Staffing :
i. Staffing is a process of matching the jobs with individuals.
ii. After organizing the total activities to be done, management is in a
position to know manpower requirements of the company at different
level in the organization.
iii. Management is to take necessary steps for recruitment, selection,
training and placement of employees.
iv. Staffing is a continuous process because existing employees may leave
the organization and the new employees may join it.
4. Directing :
i. Management is, essentially, an art of getting the work done with the
people. Therefore, management has the responsibility not only of
planning and organizing the operations but also of guiding and directing
the subordinates towards the common goal of the enterprise.
ii. It is the most important function of the management which is performed
by managers/supervisors at all the levels of the organization.
iii. When any decision is taken, it must be converted into action and for
converting into action, direction is required.
5. Co-ordinating :
i. The process of co-ordination involves synchronizing individual efforts
with the goals of the enterprise.
Elements of Management 3–8 C (CE-Sem-5)
Answer
Following are the activities involved in construction planning :
1. Defining the Scope of Work : Since all activities involve consumption
of different resources to different extents, it is important that the scope
of work involved is properly and, to the extent possible, completely
defined.
2. Identifying Activities Involved :
i. This part of planning is very closely linked to defining the scope, and
involves identifying activities in a particular job.
ii. Since different activities involved consume different physical resources
to varying extents, it is crucial that these activities are exhaustively
listed, along with the resources required.
3. Establishing Project Duration :
i. This can be done only with a clear knowledge of the required resources,
productivities and interrelationships.
ii. This information is used to prepare a network and other forms of
representations outlining the schedules.
Quantity Estimation & Management 3–9 C (CE-Sem-5)
Answer
Principles of Planning : Following are the various principles of
planning :
1. Contribution to Objectives :
i. The plans are made for the purpose of achieving the organizational
goals.
Elements of Management 3–10 C (CE-Sem-5)
ii. In this way, both the major as well as the derivative plans are made with
a view to contribute in the achievement of organizational goals.
2. Primacy of Planning :
i. According to this principle, the process of planning is the primary function
of all the managers.
ii. The managers are required to plan all their actions and then they should
proceed with other functions.
3. Planning Premises : For the purpose of making the process of planning
effective, there are certain presumptions or premises that have to be
made and the planning is undertaken on the basis of these premises.
4. Principle of Alternatives : The process of planning involves the
development of several alternatives and then the planners select the
alternative that is most appropriate for achieving the organizational
goals.
5. Principle of Timing : The plans have the capability of contributing
significantly in the achievements of the organizational goals if the plans
are properly timed. Therefore the planning premises as well as the
policies are not much helpful if the plans are not properly timed.
6. Principle of Flexibility :
i. According to this principle, there should be flexibility in the plans. This is
very important because flexibility allows the plans to deal with the
contingencies that may develop later on.
ii. Therefore, the plans should be adjustable so that they can deal with the
changes that may develop after the plans have been formulated.
7. Principle of Comparative Strategies :
i. This requires that while formulating their plans, the managers should
also consider the plans made by their competitors.
ii. In this way, the managers should formulate their plans by considering
what the competition would have done in such a case.
8. Principle of Commitment : According to this principle, a time frame
should be provided by the plan during which the commitments made in
the plan have to be fulfilled. This commitment allows the managers to
achieve the targets in time.
Advantages of Planning : Following are the advantages of planning :
1. Planning helps in determining the objectives of an enterprise.
2. Planning avoids chaos because all efforts are directed towards a
predetermined goals of the enterprise.
3. Planning helps in control by distributing the responsibilities of different
persons and jobs.
4. Planning minimizes the cost by utilizing the available resources in the
best way.
Quantity Estimation & Management 3–11 C (CE-Sem-5)
Answer
Following are the various types of scheduling :
1. Material Scheduling :
i. It provides advanced capabilities for scheduling different types of
commodities and products which include procured raw material, stores,
spares and consumables.
ii. The scheduling of raw material is done on daily production schedule
basis for short lead and cycle time materials, master production schedule
for longer lead time items and on replenishment basis for imported
items with long lead/cycle time.
2. Labour Scheduling :
i. It is used to create, update, and review employee labour schedules. A
labour schedule specifies how an employee’s pay is to be distributed to
oracle grants accounting, oracle projects, or oracle general ledger.
ii. Multiple labour schedules can be created for each employee assignment.
iii. Each schedule contains schedule lines with charging instructions for
grants accounting, projects, or general ledger.
iv. Each payroll is distributed according to the schedule lines in effect for
the period of the payroll to be distributed. An employee can have an
unlimited number of schedule lines.
3. Equipment Scheduling :
i. A civil engineering project needs a variety of equipments and it is
imperative for the engineer/contractor to know what type of equipments
and what number of the equipment and for how many days (with exact
dates) for each will be needed for the purpose.
ii. So that he may arrange them timely by hiring or by purchasing or by
any other means and the work may not be delayed because of non-
availability of equipment.
Elements of Management 3–12 C (CE-Sem-5)
4. Financial Scheduling :
i. It contained in an audited annual report, summarizes the audited financial
position of the audited entity.
ii. Other application of the term is the scheduling of amounts, not
necessarily by date, of major financial events by any given category as to
projected receipts, payments, costs, etc.
Answer
1. Project monitoring and reporting involves :
i. The monitoring of actual project progress as compared to the planned
project progress and the collection of key progress metrics such as
risks, issues, changes and dependencies; and
ii. The reporting of project status, costs and outputs and other relevant
information to the project stakeholders.
2. Project monitoring typically involves tracking five variables :
i. Schedule : The estimated effort and duration versus the actual effort
and duration.
ii. Costs : The estimated cost versus the actual costs.
iii. Deliverables : What products or components have been delivered and
plan to be delivered.
iv. Quality : How well are the deliverables being completed.
v. Benefits : Are the processes in place to achieve and to measure the
lead indicators for benefits realization.
3. To provide increased project visibility it is necessary to maintain an
appropriate reporting and monitoring system in a construction project.
Que 3.9. What is updating ? What are the various steps in up-
dating process ?
Answer
Updating : It can be defined as planning and programming of the
remaining portion of an activity job by introducing the latest information
available.
Steps in the Process of Updating :
i. Describe : The point in time at which updating is to be done according
to the original plan.
Quantity Estimation & Management 3–13 C (CE-Sem-5)
ii. Record : What has happened actually till the updating point.
iii. Summarize : The knowledge attained presented in the tabulated form.
iv. Place : The information contained in the updating table onto the original
network. This is done by :
a. Assigning the time of update as the earliest occurrence time for
the tail event of the project,
b. Allotting a zero time duration for all activities which have been
completed,
c. Entering the remaining estimated durations of those activities
which are in progress, and
d. Entering the estimated durations based on new knowledge of
activities which are still to be commenced.
v. Perform : Calculations of earliest occurrence time and latest
occurrence time and mark these on the network known as updated
network.
Answer
1. Role of Architects :
i. Architects were responsible both in pre-project and project phases, and
they were acting on client’s behalf.
ii. In pre-project phase, they were responsible for preparation of drawings,
preparation of tender document and contractor selection.
iii. In project phase, they were responsible for checking the measurement,
certification of bills and overall project management functions.
iv. In the case of Public Sector, there may be a separate department
(Engineering Department) which is responsible for the tender
preparation and contractor selection.
2. Role of Client (Owner) :
i. The client is often the person or organization that will manage the
facilities or structures upon completion of the project.
ii. The client is in a position to judge the use of funds to execute the project
and they are at his discretion.
3. Role of Constructor :
i. The constructor is sometimes called the construction contractor.
ii. The job is an important one : Completing the project on schedule according
to the contract concluded with the client, and in accordance with design
drawings and specifications.
Elements of Management 3–14 C (CE-Sem-5)
Answer
Following are the various types of civil engineering construction :
1. Agricultural : Typically economical buildings, and other improvements,
for agricultural purposes. Examples include barns, equipment and animal
sheds, specialized fencing, storage silos and elevators, and water supply
and drains such as wells, tanks, and ditches.
2. Residential : Residential construction includes houses, apartments,
townhouses, and other smaller, low-rise housing, small office types.
3. Commercial : This refers to construction for the needs of private
commerce, trade, and services. Examples include office buildings, “big
Quantity Estimation & Management 3–15 C (CE-Sem-5)
Answer
To ensure smooth working in the project work, certain key elements
must be placed in the organization.
The project management system consists of seven components or sub-
systems. These are as follows :
1. Project Planning and Design :
i. The planning and designing system is perhaps the most important
component, on it depends the successful completion of a project.
ii. Project planning is concerned with laying down certain objectives, goal
and strategies. Better results can be achieved if the design of the
project work is systematized.
2. Project Information System :
i. In organizing the implementation of project work, the information
system must be good.
ii. However, one of the problems some organizations have is that the
data on project status is collected, processed and distributed at such
large time intervals so as to make the information useless in terms of
control.
3. Project Control System :
i. Monitoring and control are the important sub-sets of the project
implementation process. The objective of monitoring is to see deviations
from the planned project performance.
Elements of Management 3–16 C (CE-Sem-5)
Answer
1. Project controls system encompass the people, processes and tools used
to plan, manage and mitigate cost and schedule issues and any risk
events that may impact a project.
2. The traditional measures of project success are the accomplishment of a
scope in budget, on time, and with required quality.
3. Control system helps in successful completion of a project with respect
to :
Quantity Estimation & Management 3–17 C (CE-Sem-5)
i. Cost :
a. The financial commitment of the project is dependent on several
variables. There are the resources involved, from materials to people,
which include labor costs.
b. Cost processes include cost estimating to figure out the needed financial
commitment for all resources necessary to complete the job.
c. Control system helps in ensuring that your estimates are as accurate as
possible.
ii. Scope :
a. Scope deals with the specific requirements or tasks necessary to complete
the project.
b. Scope is important to manage on any project, because if you can’t control
the scope of the project, you’re not likely to deliver it on time or under
budget.
c. Control system helps in controlling the scope of the project.
iii. Time :
a. The schedule is the estimated amount of time allotted to complete the
project, or producing the deliverable.
b. This is achieved by noting all the tasks necessary to move from the start
to the finish of the project.
c. Control system helps the project stay on track.
iv. Quality :
a. Quality is critical and the most important factor for completion of a
project on time and within the allocated budget.
b. If proper quality checks are not in place, defective materials or work
may cause damage to equipment and facilities.
c. Control system helps in maintaining the quality in the project.
Answer
Cost Control Techniques : Cost can be controlling by employing the
following methods :
1. Materials Control :
i. Materials control may be defined as the systematic control over the
procurement, storage and usage of materials so as to maintain an even
flow of materials and at the same time avoiding excessive investment in
inventories.
ii. From the above definition we can derive the following important aspects :
a. To ensure the smooth flow of production without interruptions.
b. Prevention of excessive investments in materials stock.
2. Labor Control :
i. In order to achieve the effective utilization of manpower resources, the
management has to apply proper system of labour cost control.
Elements of Management 3–18 C (CE-Sem-5)
PART-2
Bar Charts, Milestone Charts, Work Breakdown Structure
and Preparation of Networks, PERT and CPM,
Project Monitoring and Resource Allocation.
Questions-Answers
Que 3.15. What is the bar chart ? Also explain its limitations.
OR
Discuss in details about the limitations of a bar chart.
AKTU 2015-16, Marks 10
Answer
Bar Chart : A bar chart or bar graph is a chart that presents categorical
data with rectangular bar with height or length proportional to the
values that they represent.
Limitations of Bar Chart : These are the following limitations of bar
chart :
1. Only major activities are shown in bar chart and sub activities cannot be
separated out. Hence effective control over the activities in big projects
cannot be achieved.
2. A bar chart does not show progress of work hence it cannot be used as
a control device.
3. It does not show the interdependencies between the various activities
clearly.
4. Delays in the work cannot be detected.
5. Bar chart cannot distinguish between critical and non-critical activities.
Hence resource smoothening and resource levelling cannot be done.
6. The financial aspect involved is not known i.e., whether the project cost
is within the estimated one or exceeded.
Que 3.16. Draw a bar chart and compute the total duration of the
project from the data given below :
Task (1) and (4) will be started together. Task(2) will start after
completion of task (3) and task (3) will the place after task (1). Task(5)
and (6) will be taken up together but only after completion of task
(3). AKTU 2013-14, 2014-15; Marks 10
Quantity Estimation & Management 3–21 C (CE-Sem-5)
Answer
i. Bar Chart :
7
6
5
Item
4
3
2
1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
(Time in days)
Fig. 3.16.1. Bar chart.
Que 3.17. Explain the milestone chart. Also give its limitations.
OR
State how project controlling and activity inter relationship can be
achieved in a modified bar chart. Determine the critical path with
the scheduled completion time of 21 days.
Fig. 3.17.1.
Answer
A. Milestone Chart :
1. Milestone chart is a modification over the original Gantt chart.
2. Milestones are key events of a main activity represented by bar. These
are specific points in time which mark the completion of certain portions
of the main activity.
3. These points are those which can be easily identified over the main bar.
Elements of Management 3–22 C (CE-Sem-5)
Finishing
B. Numerical :
2 4
5 2
2
8 8 14 14
7 7
0 0 1 5 9 21 21
6
3 3
3 5 1
3
3
6 8
5
Fig. 3.17.3.
Note : In this question activity numbers and activity times are not
given, so we assume activity numbers and times suitably.
1. The network has following path :
i. 1-2-4-7-9 = 2 + 5 + 2 + 7 = 16 days
ii. 1-2-4-7-8-9 = 2 + 5 + 2 + 3 + 3 = 15 days
iii. 1-3-5-7-9 = 3 + 5 + 6 + 7 = 21 days
iv. 1-3-5-6-8-9 = 3 + 5 + 1 + 5 + 3 = 17 days
v. 1-3-5-7-8-9 = 3 + 5 + 6 + 3 + 3 = 20 days
vi. 1-3-6-8-9 = 3 + 3 + 5 + 3 = 14 days
2. For 21 day the critical path is 1-3-5-7-9 = 3 + 5 + 6 + 7 = 21 days
Answer
A. Work Breakdown Structure :
1. Work breakdown structure or schedule is a pictorial representation of
the entire program.
2. It is a preliminary diagram illustrating the way in which all the supporting
objectives go together and mesh to ensure the attainment of the major
objective.
3. Such a breakdown structure is more essential in complex projects
consisting of hundreds of events and activities.
4. In work breakdown structure, the top-down approach to planning is
adopted. Such an approach ensures that the total project is fully planned.
5. The work breakdown schedule aids in the identification of objective and
allows the planner to see the picture of the project.
6. The development of the work breakdown structure begins at the highest
level of the program with the identification of project end items.
7. The major end items are then divided into their sub-component parts
(i.e., system, sub systems, components) and the component parts are
further divided into their more detailed units.
8. The subdivision of the work breakdown structure continues to
successively lower levels, until it reaches the level where the end item
Elements of Management 3–24 C (CE-Sem-5)
Fig. 3.18.1.
B. Breakdown Structure for the Launching of a Communication
Satellite :
Ground segment
Land assets
Crew
Servicing Planning
Video
streaming Equipment
Interfaces
Fig. 3.18.2.
Que 3.19. Define networks. Describe the various rules for prepare
a network.
Quantity Estimation & Management 3–25 C (CE-Sem-5)
Answer
Network : This is an arrow-diagram (consisting only arrows and circles)
drawn to represent the inter-relationship and sequence of all the required
construction activities of a project as shown in Fig. 3.19.1.
3
F
B
Initial A H
event 1 Activity 2 D 5 6 Find
E event
C G
4 Dual role event
Fig. 3.19.1.
Network Rules : Following are the rules used for prepare a network :
1. In a network, there are three types of events :
i. Initial event,
ii. Final event, and
iii. Dual role event.
2. The completion of a project, which constitutes of a number of activities,
passes through a number of events. These events must occur at definite
time and in a particular sequence or order. As per sequence or order the
events may be specified as predecessor events and successor events.
3. Similar to that of an event, activity also may be predecessor activity and
successor activity.
4. It is customary to assume that time flows from left to right which gives
the direction of arrows.
5. Arrows should normally not cross each other.
6. It is essential to number the events in a discrete manner. Every activity
in a network is identified by its own i-node and j-node number.
Fulkerson’s Rule of Node Numbering :
i. There will be a single initial event in a network which has only arrows
coming out of it. The event is first given number (say 1).
ii. All the arrows coming out of event (1) are neglected. This provides us
with one or more initial events. These events are numbered as (2), (3),
(4), etc.
iii. Again, neglect all arrows coming out of these events. A few more initial
events will be created, number them similarly.
iv. This operation is continued until the last event is reached and numbered.
Answer
1. Bar Chart :
B
Item
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
(Time in week)
(a) Bar chart.
2. Milestone Chart :
Critical item
B Non critical item
C
Item
1 2 3 4 5 6 7 8 9 10 11 12
Time in week
(b) Milestone chart.
Fig. 3.20.1.
Answer
CPM (Critical Path Method) : The critical path method is step by step
project management technique for process planning that defines critical
and non-critical tasks with the goal of preventing time-frame problems
and process bottlenecks.
Quantity Estimation & Management 3–27 C (CE-Sem-5)
Answer
1. Slack :
i. Slack is amount of time that a task in a project network can be delayed
without causing a delay to subsequent tasks and project completion
data.
ii. The difference between TE and TL of an event is called the slack of that
event.
Slack = TE – TL
2. Float :
i. Float denotes the flexibility range within which the activity start and
finish times may fluctuate without affecting the total project duration.
ii. The float is similar to ‘slack’ in PERT. The difference is that float is
associated with the activity times while slack is with event times.
Elements of Management 3–28 C (CE-Sem-5)
C 4
2 6
A
3 G
1 D 4 9
B
4
E H K
3 6 11 7 11 8
2
F I J
7 2 7
5
Fig. 3.23.1.
Answer
Que 3.24. Draw the network and design the critical path and
calculate the completion time of the project whose activities are as
follows.
Elements of Management 3–30 C (CE-Sem-5)
A-B 7 –
B-C 10 A-B
B-D 15 A-B
C-D 7 B-C
C-E 12 B-C
Answer
1. Network :
7 7 17 17 29 29 34 34
7 10 12 5
A B C E F
0 0 7
15
3
24 26
Fig. 3.24.1.
2. Critical Path : There are three possible path for completion this project,
such as :
i. A-B-C-E-F
Total time taken = 7 + 10 + 12 + 5 = 34 days
ii. A-B-D-E-F
Total time taken = 7 + 15 + 3 + 5 = 30 days
iii. A-B-C-D-E-F
Total time taken = 7 + 10 + 7 + 3 + 5 = 32 days
Quantity Estimation & Management 3–31 C (CE-Sem-5)
Maximum time taken path is path (i), so this is called as critical path.
Hence completion time for project is 34 days.
Answer
1. The network diagram for the given problem is shown in Fig. 3.25.1.
20 2
3
40
5
10
6 4
50
30
Answer
There are three different estimates of activity duration in PERT :
1. Optimistic, 2. Pessimistic and 3. Most Likely.
1. Optimistic Time : It expressed as ‘to’, represents estimate of minimum
possible time by which an activity can be completed assuming that
everything is in order according to the plan and there can be only
minimum amount of difficulty.
2. Pessimistic Time : It expressed as ‘tp’ represents estimate of maximum
possible time by which an activity can be completed assuming that things
may not be in accordance with the plan and there can be incidence of
difficulties in carrying out the activity.
3. Most Likely Time : It expressed as ‘tm’, represents estimate of time for
completion of an activity, which is neither optimistic nor pessimistic,
assuming that things should go in a normal way, and if the activity is
repeated several times, in most of the cases, it will be completed in time
represented by t.
4. The expected mean time (te) (duration) of a project is calculate by formula,
to 4 tm t p
te =
6
tp to
5. Standard deviation, t =
6
(tp to )2
6. Variance, t = (t)2 =
36
Que 3.27. Describe the various terms which are related to PERT
Analysis.
Quantity Estimation & Management 3–33 C (CE-Sem-5)
Answer
Following are the various term associated with PERT :
1. The Earliest Expected Time (TE) : It is the time when an event can be
expected to occur earliest. The calculation of TE of an event is as follows :
(TE)j = (TE)i + ti – j
2. The Latest Allowable Occurrence Time (TL) :
i. The latest time by which an event must occur to keep the project on
schedule is called the latest allowable occurrence time.
ii. The calculation of TL of an event is given by,
(TL)i = (TL)j + ti – j
3. Slack : The slack is difference between event times denoting the range
within which an event time can vary.
Slack = TL – TE
Slack may be positive, zero or negative depending upon the value of TE
and TL of that event.
i. Positive Slack : When TL is more than TE, positive slack is obtained.
It indicates the project is ahead of schedule meaning thereby the excess
resources.
ii. Zero Slack : When TL is equal to TE, zero slack is obtained. It indicates
that the project is going on schedule meaning thereby adequate
resources.
iii. Negative Slack : When the schedule completion time TS (and hence
TL) is less than TE, negative slack is obtained. It indicates the project is
behind schedule meaning thereby the lack of resources.
4. Critical Event : The event having the least slack value is known as a
critical event.
5. Critical Path : The path joining the critical events is called a critical
path of the PERT network. Timewise, the critical path is the longest
path connecting the initial event to the final event.
Que 3.28. The time estimates for the activity P, Q and R in a project
are as follows :
Activity to tm tp
P 10 12 14
Q 6 8 12
R 5 10 12
i. Determine the expected time and variance of each activity.
ii. Which activity has more reliable time estimates ?
AKTU 2015-16, Marks 05
Elements of Management 3–34 C (CE-Sem-5)
Answer
t0 4 tm t p
1. Expected time, te =
6
10 4 12 14
i. For activity P : te = 12
6
6 4 8 12
ii. For activity Q : te = 8.33
6
5 4 10 12
iii. For activity R : te = 9.5
6
2
t p t0
2. Variance, 2 =
6
i. For activity P : t0 = 10, tm = 12, tp = 14
2
14 10
2 = 0.44
6
ii. For activity Q : t0 = 6, tm = 8, tp = 12
2
2 = 12 6 1
6
iii. For activity R : t0 = 5, tm = 10, tp = 12
2
12 5
2 = 1.36
6
3. te = 12, so activity P has more reliable time estimate.
Answer
1. For A to = 5, tm = 7, tp = 9
to 4 tm t p 5 4 7 9 42
te = 7 weeks
6 6 6
Quantity Estimation & Management 3–35 C (CE-Sem-5)
2. For B to = 4, tm = 6, tp = 7
to 4 tm tp4 4 6 7 35
te = 5.84 weeks
6 6 6
3. For C to = 3, tm = 5, tp = 8
to 4 tm t p
3 (4 5) 8
te = 5.17 weeks
6 6
4. te = 7 weeks, so engineer A is more certain about the time of completion
of job.
Answer
Difference between CPM and PERT :
S. No. CPM PERT
1. It is basically having deterministic It is basically having
approach in the de sign o f probabilistic approach in the
network. design of network.
2. Only one time estimate is required Three time estimate (in the
for each activity. form of Pessimistic time,
Optimistic time and Most likely
time) for each activity.
3. It is built-up of activity-oriented It is built-up of event-oriented
diagram. diagram.
4. Time and cost both are controlling Time only is the controlling
factors. There is an optimum factor and the cost is assumed
duration of the project at which proportional to the project
the project cost is minimum and duration.
this can be obtained by crashing
the network.
5. Critical events must have zero Critical events may be positive/
slack. zero/negative depending upon
the project sche dule d
completion time.
6. It is recommended for repetitive It is re co mmende d fo r
nature o f wo rk whe re past research and development
e xperie nces are ade quately project where no past
available. experiences are available or
where great uncertainty lies
in the time estimation.
Elements of Management 3–36 C (CE-Sem-5)
Answer
Work Breakdown Structure : Refer Q. 3.18, Page 3–23C, Unit-3.
Contract Planning :
1. A contract planning programme assists contract managers to properly
manage contracts by addressing transition management, performance
monitoring and by helping to ensure that both parties fulfill their
commercial and contractual commitments.
2. Contract planning programme is developed for all medium to high risk
contracts.
3. Following key components should be considered when drafting a contract
planning programme to complete the project in specified time :
i. Contract Summary and Background of the Scope of Work : In
this section, provide a summary of the program. This section should
include the type of work being performed, the goals of the contract, the
place of performance, and significant features of the contract.
ii. Contract Management Team Coordination : The contract planning
programme should incorporate detail regarding identification of the
members of the contract planning programme team and their
responsibilities.
iii. Contract Identification : The contract planning programme should
include the contract information like, Contractor name, Contract value,
and Contractor key personnel.
iv. Contract Management Processes : In this section, identify the critical
process or guidelines for successfully managing the contract and
reference sections of the contract (e.g., conditions, instructions, contract
clauses, etc.) that support these functions.
v. Method for Monitoring Performance-Based Objectives : Describe
the methods for monitoring and evaluating the performance-based
objectives, for example, Quality Assurance Surveillance Plan (QASP)
addresses the methods for monitoring performance against the contract.
This section should also address contractor oversight (e.g., field
inspe ctions, monthly assessment of pro ject status, contract
administration, deliverable reports, budgetary data, physical inspections,
etc.).
vi. Contract Deliverables : Identify critical milestones and contract
deliverables (e.g., Transition Plan, Risk Mitigation Plan, Project
Management, Quality Surveillance Assurance Plan, etc.); and the
individuals responsible for the requirement.
vii. Performance Risk Areas : Identify known performance risks and the
individuals responsible for mitigating these risks.
Quantity Estimation & Management 3–37 C (CE-Sem-5)
viii. Key Performance Metrics : The section should identify any key
performances for determining contractor progress.
Answer
Resources Allocation :
i. Resource allocation simply means deciding what resources each activity
of the project requires. For this resource usage profile i.e., Histogram is
drawn either on earliest start of each activity or latest start of each
activity basis.
ii. The process of resource allocation consists essentially of fitting activities
into pattern of resource availability within stipulated time period and it
is achieved by the following ways, namely.
1. Resource Smoothing : In this approach the total project duration is
not changed but some of the activity start times are shifted by their
available float so that more or less uniform demand is generated and
this is called Resource Smoothing.
Example :
i. The project duration (6 days) is maintained, so the critical activity
(10 – 40) will start earliest and finish in 6 days.
ii. But the path (10 – 20 – 40) has 3 days float and path (10 – 30 – 40) has 2
days float.
iii. The float period may be distributed among the activities lying on the
path or the float may be distributed over one activity on the path.
2m
20 1
m
On
at
2
1d d e
lo
da
f
y
ys
flo
da
4 Resource at
2
availability 1m
men
3
2 10 40
1 1m 6d
1m
2d s
0 1 2 3 4 5 6 ay 2d
2d
days
lo at
30 f
20 2
da
flo ys
at 1m
m
2d 2d
4
2
3 at
1m
men
2 10 40
1 one day float 6d
1d 1m
ay
0 1 2 3 4 5 6 7 flo ys
2d
a
day at 2d
at
project period extended 30 flo
for 1 days
Fig. 3.32.2.
Quantity Estimation & Management 4–1 C (CE-Sem-5)
4 Equipment
Management
• Productivity
• Operational Cost
• Owning and Hiring Cost and the Work Motion Study
• Simulation Techniques for Resource Scheduling
PART-1
Productivity, Operational Cost, Owning and Hiring Cost and the
Work Motion Study, Simulation Techniques for Resource Scheduling.
Questions-Answers
Answer
Productivity : A productivity measure is expressed as the ratio of
output to input used in a production process, i.e., output per unit of
input.
Output
Productivity =
Input
Methods : Following are the methods to measure the productivity :
1. Partial Productivity : It is the ratio of output to one class of input
among many factors of production.
Output
i. Labour productivity =
Labour input
Output
ii. Capital productivity =
Capital employed
Output
iii. Material productivity =
Material input
2. Total Factor Productivity : It is the ratio of net output to the sum of
associated labour and capital (factor) inputs. Net output means output
minus material, capital, energy and other input expenses.
Net output
Total factor productivity =
Labour inputs + Capital inputs
3. Total Productivity : It is the ratio of total output to the sum of all input
factors. It represents the joint impact of all the input factors in producing
the output.
Total tangible (measurable) output
Total productivity =
Total tangible input
Total tangible output = Value of finished product + Value of partially
finished unit + Dividends from securities + Interest + Other income.
Total tangible input = Value of human, material, capital, energy and
other inputs used.
Answer
Following are the techniques for improving the productivity :
1. Value Analysis : This is systematic investigation of the project to reduce
cost and improve value. It reduces excess work content.
Equipment Management 4–4 C (CE-Sem-5)
Answer
1. The cost of possession of an equipment is called cost of owning to which
can be added the cost of fuel for running the equipment. It is generally
estimated on hourly basis.
2. This is the amount by which equipment should be hired. It does not
include the labour cost.
Necessity : In cases where the machine and the elements of production
are not rented, a calculation of the owning and operating costs is
necessary to derive the machine rate.
Factor : Following are the factors affect the cost of owning and
operating :
1. Initial cost of the equipment which consists the price of equipment,
transportation cost, loading and unloading charge and installation
cost.
2. Severity of service condition under which it is to be used.
3. Number of hours it is used per year.
4. The care with which it is maintained and repaired.
Quantity Estimation & Management 4–5 C (CE-Sem-5)
5. The demand for equipment after its useful period i.e., the salvage
value.
6. Useful life of equipment in years.
Que 4.4. How will you maintain the cost records of the
equipments ?
Answer
1. Depreciation and Replacement Cost :
i. For consideration of replacement cost of the equipment, it is necessary
to know the salvage value of the similar equipment for each year of its
life separately.
ii. Since the average cost of the construction equipment has been increasing
at a rate of approximately 5 % per year during the past 10 years.
iii. So, the replacement cost must be increased 5 % per year to accommodate
the increase in the cost of equipment.
2. Investment Cost : The investment cost is assumed to be 10 to 12 % per
year of the value of the equipment at the beginning of the year.
3. Maintenance and Repair Cost :
i. The cost of maintenance and repair cost largely varies with the condition
under which the equipment is used and the care with which it is handled.
ii. So, it is essential to keep accurate records of these costs.
4. Downtime Cost :
i. Downtime is the time which is lost when the equipment is undergoing
repairs and adjustments.
ii. It increases with the passage of time. If an equipment is down 5 percent
of time, its availability for actual production is 95 percent of working
hours.
iii. Supposing the operating cost is Rs. 5.00 per hour with an average
downtime of 5%.
iv. The cost per hour for this downtime will be 0.05 × 5 = Rs. 0.25 and if the
machine is used 2000 hours per year, the annual cost of downtime will
be 2000 × Rs. 0.25 = Rs. 500.
5. Obsolescence Cost :
i. The continuous improvements in the design of construction equipments
have resulted in lower production cost.
ii. For example, if a new equipment reduces the production cost by 5 percent
when compared with the production cost for an existing machine, the
existing machine will suffer a loss in value equal to 5 % and this is
defined as obsolescence cost.
Equipment Management 4–6 C (CE-Sem-5)
iii. During the past years, experience shows that productive improvement
have averaged about 5 % per year and it appears that future
improvements may continue at the same rate.
Table 4.4.1. Summary of cumulative cost per hour
Item 1 year 2 years 3 years 4 years 5 years 6 years
Answer
Advantages of Owning a Construction Equipment :
1. Buying results in direct ownership of the equipment.
2. One of the main advantages of owning the equipment by outright cash
purchase is that it may result in lowest cost per operating hour as
compared to renting or leasing.
3. Complete control of the owner over use of the equipment and its
maintenance and replacement of equipment when it is no more
economical.
4. There is also income tax benefit associated with depreciation of the
equipment.
5. Economically attractive option when there is more work load leading to
higher utilization rate of the equipment over its useful life.
Disadvantages of Owning a Construction Equipment :
1. Acquisition of equipment by buying is done through cash purchase.
However cash purchase can have an adverse effect on company’s cash
flow as it reduces the liquid asset thus affecting company’s working
capital.
2. Risk of not getting the required return on the capital investment if
there is not enough utilization of the equipment.
Quantity Estimation & Management 4–7 C (CE-Sem-5)
Answer
Work Study :
i. Work study is a means of enhancing the production efficiency
(productivity) of the firm by elimination of waste and unnecessary
operations.
ii. It is a technique to identify non-value adding operations by investigation
of all the factors affecting the job.
iii. It is the only accurate and systematic procedure oriented technique to
establish time standards.
iv. It is going to contribute to the profit as the savings will start immediately
and continue throughout the life of the product. Method study and work
measurement is part of work study.
v. Part of method study is motion study, work measurement is also called
by the name ‘Time study’.
Motion Study :
1. It can be defined as “a science of eliminating wastefulness resulting
from ill-directed and inefficient motion”.
2. The main objective of the motion study is to find a scheme of the least
wastage of labour.
3. Basically this technique analyses each operation of a given piece of
work very closely in order to eliminate unnecessary operations and to
approach the quickest and easiest methods of performing each necessary
operation.
Equipment Management 4–8 C (CE-Sem-5)
Answer
Following are the software's used in construction management :
1. Primavera :
i. Primavera Systems, Inc. is the world’s leading provider of project,
program and portfolio management software solutions.
ii. It provides the software foundation that enables all types of businesses
to excel in managing their portfolios, programs, projects and resources.
iii. Primavera helps companies make better portfolio investment decisions,
improve governance, prioritize their project investments and resources,
and deliver tangible results back to the business.
Quantity Estimation & Management 4–9 C (CE-Sem-5)
PART-2
Construction Equipment for Earth Moving, Earth Compaction,
Hauling Equipment, Hoisting Equipment, Conveying Equipment,
Concrete Production Equipment, Tunneling Equipment.
Questions-Answers
Answer
Excavating and Earth Moving Equipment : Following are the
excavating and earth moving equipment :
1. Power Shovel :
i. Basic parts of power shovel including the track system, cabin, cables,
rack, stick, boom foot-pin, saddle block, boom, boom point sheaves and
bucket.
ii. Bucket size varies from 0.375 m3 to 5 m3.
iii. Uses :
a. Suitable for close range of work.
b. Capable of digging very hard materials.
c. Can remove big sized boulders.
d. To excavate the earth and to load the trucks.
Quantity Estimation & Management 4–11 C (CE-Sem-5)
Que 4.9. What are the various types of heavy hauling equipment
vehicles ?
OR
Explain hauling equipments with neat sketch.
Answer
A. Hauling Equipments.
1. Haulage of heavy construction equipment carriage and disposal of
excavated earth transportation of building materials.
2. Haulers may operate on the roadways or railways.
B. Types of Hauling Equipments : Following are the various types of
hauling equipments :
Quantity Estimation & Management 4–13 C (CE-Sem-5)
Liftarm
Piston rod
Hoist cylinder
Tension line Body
Hinge
Tail board
Gear pump
Power take off
Fig. 4.9.1.
Answer
Hoisting Equipment : Hoisting is the operation of lifting the load.
Equipment used for hoisting lift the load from place to place, hold it in
suspension during transfer from one location to other.
Types of Hoisting Equipment : Following are the different types of
hoisting equipment :
1. Pulley : It is used for lifting rough surfaced and heavy objects.
2. Chain Hoists : It is used for lifting loads up to 50 tonnes. System
consists of hand chain and land chain.
3. Jacks : It is based on the principle of inclined plane. The smallest jack
may have capacities for 5 tonnes used for lifting an automobile wheel,
while the bigger variety may be of 100 tonnes capacity.
Jacks are of two types :
i. Mechanical : Load is mounted on platform.
ii. Hydraulic : Pressure is exerted by liquid.
4. Winch : A combination of gears, clutches and brakes. Operation is
controlled through a series of levers.
5. Cranes : Lifting capacity varies from 1/2 tonne to 500 tonnes.
Following are the different types of cranes :
i. Derrick Cranes :
a. Derrick cranes consist of a mast, a boom and a bull wheel on which the
boom rotates about a vertical axis and guys or supporting members.
b. Electrically operated, diesel operated or diesel-electrically operated.
c. The boom can revolve through 360º.
Quantity Estimation & Management 4–15 C (CE-Sem-5)
Answer
A. Conveying Equipment :
i. Transporting material from one place to another over a stationary
structure.
Equipment Management 4–16 C (CE-Sem-5)
ii. Caries material in continuous stream with its distinct feature such as
endless chain or belt.
iii. When the equipment does horizontal conveying, it is known as conveyor
and when it does vertical, it is known as elevator.
iv. Conveying are mainly used in mining, construction and in some of the
industries.
v. In construction industry, conveyors are mainly used for concreting
purpose.
B. Type of Conveyors Equipment : Following are the types of conveyors
equipment.
1. Belt Conveyor :
i. It used when large quantities of materials have to be conveyed over long
distances at fast speed.
ii. It consists of a belt running over a pair of end drums or pulleys and
supported at regular intervals by a series of rollers called idlers.
iii. Generally, rubber is most commonly used as conveyor belt.
Feeder Head pulley Screw takeup
Screw takeup
Belt Head drive
Height
Tail pulley
Snub pulley
Snub pulley
Length
Tail drive
(a) (b)
2. Screw Conveyor :
i. A screw conveyor consists of a helix mounted on a bearing at the ends
and at intermediate points and is driven by a motor from one end.
ii. The material enters the through at one end is carried to the other end
by screwing action of helix.
Bearing
Blockage detector temperature
sensor
Bucket
Rubber conveyor belt
Fig. 4.11.3.
4. Aerial Transport :
i. Aerial transportation through cableways, rope-ways and tram ways.
ii. It is used with advantage for transportation of material in hilly regions.
iii. It is reducing the distance of transportation as well as cost of
transportation.
iv. The load being passed over intermediate towers or stations for long
distances.
Answer
Following are the various compaction equipments used in construction
industry.
1. Smooth-Wheel Rollers :
i. It is plain steel roller and Self-propelled type.
ii. It has weighing from 5 to 15 tonnes
Equipment Management 4–18 C (CE-Sem-5)
iii. It is used for ordinary rolling work where deep compaction is not required
iv. The rear wheels being usually larger in diameter and the front one
being winder.
v. Weight of rollers may be increased by filling water or sand ballast in
hollow cylinder.
vi. These rollers are effective in compacting granular soils, such as sand,
gravel and crushed stone.
2. Sheep-foot Rollers :
i. It is used for compacting earth work in embankments and canals (where
compaction deep into the layer of the earth is required)
ii. These gives best result in compaction when the soil is clay or
predominantly cohesive and impervious.
iii. The sheep foot rollers may weigh upto 15 tonnes or more. It is travel at
a speed of 25 kmph.
iv. As roller moves over the surface, the feet penetrate the soil to produce
a kneading action and a pressure to mix and compact the soil from
bottom to top layer.
3. Pneumatic-tyred Rollers :
i. It is most suitable for compacting fine-grained soil and well graded sands.
ii. Ballasting is done using water, sand or pig iron in order to increase the
self weight.
iii. Major advantages are the ability to control the ground contact pressure
by :
a. Altering the weights of machines,
b. Increasing the number of wheels,
c. Increasing the tyre width, and
d. Changing the contact area of the tyre by altering the contact pressure.
Answer
Following are the types of mixing used in construction site :
A. Hand Mixing : It is adopted for small works where the quantity of
concrete is small. The procedure is as follows :
1. A platform is constructed by brick or lean concrete or iron sheet as per
the requirement of the concrete to be mixed.
2. A measured quantity of sand is uniformly spread and requisite amount
of cement is dumped over it. Sand and cement is mixed uniformly.
Quantity Estimation & Management 4–19 C (CE-Sem-5)
3. On the top of this the measured quantity of stonechips are also spread
uniformly and mixed by shovels from centre to the side and then back to
centre for three times.
4. A hollow in the middle of mixed pile is created and a half to three
quarters of required quantity of water is added in the hollow while the
materials are turned in towards the centre with shovel. The mixing time
should never exceed three minute.
B. Machine Mixing :
1. Where a large quantity of concrete of the desired quality is to be produced,
the machine mixing becomes imperative. Concrete can be produced at a
faster rate with better quality.
2. Machine used for the purpose is called concrete mixer which may be
batch type or continuous type.
i. Continuous Concrete Mixers :
a. Continuous mixer, the name itself telling its duty that the loading, mixing
and discharging of mix is continuously done until the work is complete
or work break occurs. The loading of materials is done continuously by
screw feeders.
b. Continuous mixtures are used for very large projects such as dams,
bridges, construction of high rise buildings, etc.
ii. Batch Concrete Mixers :
a. Batch mixers are widely used machines for concrete mixing. Concrete
mix obtained by this mixer is collected batch by batch and time by time.
So, it is called as batch mixer.
b. After pouring all the materials into pan or drum, it mixes all of those for
some time and finally discharges. This process is repeated until required
amount of concrete mix is obtained.
Following are two types of batch mixers :
1. Drum Type Mixers : In case Drum type mixers concrete ingredients
are mixed in a drum which is actually in double conical frustum shape.
2. Pan Type Concrete Mixers : Pan type mixers consists a circular pan
in which concrete is mixed. The mixing is done by blades which are
arranged in star shape inside the pan.
Advantages of Concrete Mixer :
1. The quality of concrete is good and fast.
2. Since mixing is done in machine; area is less untidy and cleaning is easy.
3. Multiple jobs can be worked without the needs of sending the equipment
back to the batch plant. You will mix what you are going to pour only.
4. Ideal for a remote location or when the batch plant cannot be installed at
the job site.
5. Reduce the amount of concrete waste and minimize shortages by mixing
the amount you need.
Equipment Management 4–20 C (CE-Sem-5)
6. Concrete is always fresh, and you will not need to worry about concrete
being too hot or over mixed.
7. Concrete mixers will be available at your convenience anytime/ any
date, like having your concrete ready 24 × 7.
8. As with any regular concrete plant, these mixers can also be customized
to add color and admixtures to the concrete batch
Answer
Concrete production equipments : Refer Q. 4.13, Page 4–18C,
Unit-4.
Concrete Placement Equipment : Following are the equipment used
for concrete placement :
1. Paving Mixers :
i. Paving mixers are used for concreting the pavement of highways/runways
to have mobility of the mixer along with the placement of concrete.
ii. They are mounted on crawler tractors. They may have single
compartment drums or double compartment drums.
2. Bottom-Dump Bucket : It is a common equipment used for placing
concrete. These buckets can be used for both vertical and horizontal
movements.
3. Wheelbarrows : These are usually used to transport concrete in the
horizontal direction, provided there is a smooth and rigid runway to
operate on.
4. Hand Buggies : These are safer compared to wheelbarrows because
they have two wheels while wheelbarrows have only one wheel. These
means of horizontal transportation are preferred when the distance to
be covered is less than 60 m.
5. Drop Pipes and Chutes : These are used to transfer concrete from
higher elevations to lower elevations.
i. The chutes used are round-bottomed and have sufficient slopes to allow
the free flow of concrete.
ii. Drop pipes are used in wall or column constructions to avoid the
segregation of concrete by allowing the free flow of concrete through
the reinforcement.
6. Conveyor Belts : They are used to transport low slump concrete. They
provide rapid movement of fresh concrete.
7. Pump : They are commonly used simple equipment. By applying
appropriate pressure, concrete can be moved through large distances in
both horizontal and vertical directions provided a proper lubricating
layer is provided within the pipe.
Quantity Estimation & Management 4–21 C (CE-Sem-5)
Answer
RMC is economical and desirable at site of construction because it
possesses some advantages as compared to conventional site mixed
concrete :
1. Uniform and Assumed Quality of Concrete : Since RMC is factory
produced, the raw material and production process quality is better than
conventional site mixed concrete.
2. Durability of Concrete : RMC ensures that correct water-cement
ratio is maintained. Hence the durability of RMC is consistent and better.
3. Faster Construction Speed :
i. In site mixed concrete, the contractor needs to mobilize labour for mixing
as well as placing.
ii. In RMC, fresh concrete is supplied in a placeable condition and can
directly be placed by pumping. Hence, a faster construction speed can be
achieved.
Equipment Management 4–22 C (CE-Sem-5)
Answer
Tunneling Equipment : Following are the equipment used in
tunnelling operations.
1. Tunnel Boring Machine :
i. Tunnel boring machine TBM also known as a ‘mole’, is a machine used
to excavate tunnels with a circular cross section through a variety of
soil and rock strata.
ii. They can bore through anything from hard rock to sand.
Shield
Hydraulic push arms Rock cutter head
iii. Tunnel diameters can range from a meter (done with micro-TBMs) to
19.25 m.
Quantity Estimation & Management 4–23 C (CE-Sem-5)
iv. Tunnels of less than a meter or so in diameter are typically done using
trenchless construction methods or horizontal directional drilling rather
than TBMs.
Drilling Equipments : Following are the various drilling equipments :
1. Drifter :
i. A drifter is an air-operated percussion type drill, similar to a jackhammer
but it is so large that it requires mechanical mounting.
ii. It varies in weight from 45 to 68 kg and is capable of drilling holes up to
11 cm in diameter and 12 m in depth.
iii. It is extensively used in mining and tunnelling.
2. Blast-hole Drill :
i. It is a rotary drill consisting of a steel-pipe drill stem at the bottom of
which is a roller-bit that disintegrates the rock as it rotates over it.
ii. A continuous blast of compressed air is forced down the pipe to remove
the rock cuttings.
iii. This drill is suitable for drilling soft to medium rock, such as hard
dolomite and limestone, but is not suitable for drilling the harder
igneous rock.
3. Fusion Piercing Drill :
i. Fusion piercing is produced by burning a mixture of oxygen and a flux-
bearing fuel such as kerosene oil, at the end of the blow pipe.
ii. When the flame is directed towards the rock, the high temperature
about 4000 °F causes the rock to melt.
iii. Water is used to quench the heated rock, resulting in small fragments,
which are blown out of the hole.
iv. It is mainly used for blasting purposes.
4. Other drilling equipments are :
i. Jackhammer or sinker.
ii. Wagon drill.
iii. Shot drill.
Que 4.17. What are the various operations associated with the
earth work for providing basement and raft foundation for
constructing a multi storied building. Describe the various
equipments which shall be deployed for carrying out these
operations.
Answer
A. Operations : Following are the operations associated with earth work :
1. Excavation : Excavation work generally means work involving the
removal of soil or rock from a site to form an open face, hole or cavity
using tools, machinery or explosives.
Equipment Management 4–24 C (CE-Sem-5)
Tunneling Road
Excavators Backhoe Dumpers Cranes & handling rollers
equipment
Road making
machines Stone
Skid steer Trenchers Tippers Fortifies crushers
loaders (conactors)
Slurry
Motor Motor Trailors Hoists Pavers seal
graders scrappers machines
Quantity Estimation & Management 5–1 C (CE-Sem-5)
5 Project Cost
Management
• Cost Planning
• Direct Cost
• Indirect Cost
• Total Cost Curve
• Cost Slope
• Time Value of Money
• Present Economy Studies
• Equivalence Concept
• Financing of Projects
• Economic Comparisons Present Worth Method
• Equivalent Annual Cost Method
• Discounted Cash Flow Method
• Depreciation and Break Even Cost Analysis
PART-1
Cost Planning, Direct Cost, Indirect Cost, Total Cost Curve,
Cost Slope, Time Value of Money, Present Economy Studies,
Equivalence Concept.
Questions-Answers
Answer
Budgeting :
1. Budgeting is the process of creating a plan to spend your money. This
spending plan is called a budget.
2. Creating this spending plan allows you to determine in advance whether
you will have enough money to do the things you need to do or would
like to do.
Quantity Estimation & Management 5–3 C (CE-Sem-5)
Importance of Budgeting :
1. A process of tracking your expenses.
2. A safety valve to prevent over expenditures.
3. Financial control of inputs.
4. Management of ongoing activities.
5. Planning and setting priorities.
6. Accountability.
7. Ensures that the finances are spent for true purpose of spending.
Answer
Cost Planning :
1. Once the resource requirement is obtained, the estimate to complete
each of these can be prepared based on the unit cost of the resources
and the total unit of the resources required. This process is called cost
planning and it is a must for project cost management.
2. The essential components of a cost plan are the project schedule and
estimates.
Advantages of Cost Planning :
1. Tender sum is likely to be closer to the estimate derived from the cost plan.
2. Less likelihood of revising the design.
3. Ensure cost-effectiveness and value for money design is obtained.
4. Ensure a balanced distribution of expenditure. A more rational design
would be obtained.
Disadvantages of Cost Planning :
1. Time consuming to prepare.
2. Insufficient information. Architect has not firmed up on the
specifications.
3. Architect has to draw more details and make design decisions earlier to
prepare the cost plan.
Que 5.3. Write a short note on direct cost and indirect cost.
OR
Compare direct and indirect cost in the construction project.
AKTU 2016-17, Marks 10
Project Cost Management 5–4 C (CE-Sem-5)
Answer
1. Direct Cost :
i. Direct costs are directly attributable to the object and it is financially
feasible to do so.
ii. In construction, the costs of materials, labour, equipment, etc., and all
directly involved efforts or expenses for the cost object are direct costs.
2. Indirect Cost :
i. Indirect costs are, not directly attributable to a cost object.
ii. It should be financially infeasible to do so.
iii. Indirect costs are typically allocated to a cost object on some basis.
iv. In construction, all costs which are required for completion of the
installation, but are not directly attributable to the cost object are indirect,
such as overhead.
v. In manufacturing, costs not directly assignable to the end product or
process are indirect.
3. Difference between Direct Cost and Indirect Cost :
S.No. Basis for Direct Cost Indirect Cost
Comparison
Answer
Total Cost : The direct cost and indirect cost added together constitute
the total project cost.
Quantity Estimation & Management 5–5 C (CE-Sem-5)
1. Fig. 5.4.1 shows the indirect cost curve, direct cost curve and the
corresponding total cost curve.
2. From the total cost curve, we find that the minimum total cost (optimum
cost) is obtained at some duration known as optimum duration. The
corresponding cost is known as the minimum cost.
3. If the project duration is increased, total cost will be the highest.
4. In figure 5.4.1, we observe two types of times–normal and crash. These
will have two types of cost associated with them. These are defined as
follows :
i. Normal Time (tn) : It is the standard time that an estimator would
usually allow for an activity.
ii. Crash Time (tc) : It is the minimum possible time in which an activity
can be completed by employing extra resources. Crash time is that time
beyond which the activity cannot be shortened by any amount of increase
in resources.
Total cost
Direct cost
Optimum
Cost
cost
Indirect cost
Answer
1. Scope of Engineering Economics : Following are the scope of
economics in engineering :
i. It has wide scope in manufacturing, construction, mining and other
engineering industries. Examples of economic applications are as follows :
a. Selection of location and site for a new plant.
b. Production planning and control.
c. Selection of equipment and their replacement analysis.
d. Selection of a material handling system.
ii. Better decision making on the part of engineers.
iii. Efficient use of resources results in better output and economic
advancement.
iv. Cost of production can be reduced.
v. Alternative courses of action using economic principles may result in
reduction of prices of goods and services.
vi. Elimination of waste can result in application of engineering economics.
vii. Competitive strength on the part of the firm in adopting engineering
economics.
viii. More capital will be made available for investment and growth.
ix. Improves the standard of living with the result of better products, more
wages and salaries, more output, etc. from the firm applying engineering
economics.
2. Material Selection in New Product Development :
Following are the steps used in material selection :
Step 1 : Identify the Design Requirements :Identifying as many of
the requirements as possible is critical for increasing the likelihood of
learning whether potential materials exist. As the number of
requirements increases, the chance of finding a set of potential materials
decreases.
Step 2 : Identify Materials Selection Criteria : The materials
selection criteria are specific materials properties derived from the
requirements identified during Step 1. For example, for a component
that must support a specific load, the minimum yield stress that is required
for the component's material can be determined. This will be one of the
material selection criteria.
Step 3 : Identify Candidate Materials : Use the materials selection
criteria to rule out materials that will not satisfy all the materials selection
criteria.
Quantity Estimation & Management 5–7 C (CE-Sem-5)
Que 5.6. Explain the concept of time value of money and also
give its importance.
Answer
A. Time Value of Money :
1. The time value of money (TVM) is the idea that money available at the
present time is worth more than the same amount in the future due to
its potential earning capacity.
2. This core principle of finance holds that, provided money can earn
interest, any amount of money is worth the more the sooner it is received.
3. Time value of money (TVM) is an important concept in financial
management. It can be used to compare investment alternatives and to
solve problems involving loans, leases, savings.
4. TVM help us in knowing the value of money invested. As time changes
value of money invested on any project/firm also changes. And its present
value is calculated as :
FV
PV =
(1 i)n
where, PV = Present value.
FV = Future value (Money to be received in the future).
i = Discount rate.
n = Number of periods until FV is received.
B. Importance : Following are the importance of time value of money :
1. Valuation of loans and other assets.
2. Capital budgeting (criteria of investment).
3. Lease analysis.
4. Working capital.
Answer
1. The graphical representation of the cash flows i.e., both cash outflows
and cash inflows with respect to a time scale is generally referred as
cash flow diagram.
Project Cost Management 5–8 C (CE-Sem-5)
2. A typical cash flow diagram is shown in Fig. 5.7.1. The cash flows are
generally indicated by vertical arrows on the time scale as shown in
Fig. 5.7.1.
Cash inflow End of year 1 P1 P2 S
End of year 10
Time 0 1 2 3 4 5 6 7 8 9 10
Year 1 Year 7
Cash outflow P F1 F2
Answer
1. Cash flow forecasting is the process of obtaining an estimate or forecast
of a company future financial position and is a core planning component
of financial management within a company.
2. A cash flow forecast is a projection of an organizations future financial
position based on anticipated payments and receivables. The process of
deriving a cash flow forecast is called cash flow forecasting.
Goals of Cash Flow Forecasting :
1. The main goal of a cash flow forecasting is to assist with managing
liquidity within an organization and ensuring that the business has the
necessary cash to meet its obligations and avoid funding issues, essentially
better management of working capital.
2. Underneath the high level goal of liquidity management, there are
often a number of reasons why companies set up a cash flow forecasting
process, these include :
i. Covenant forecasting and half/ full year reporting visibility.
ii Interest and debt reduction.
iii. Short term liquidity planning.
iv. Long term planning / budgeting purposes (e.g. 3 year plan)
Quantity Estimation & Management 5–9 C (CE-Sem-5)
Answer
Following are the various types of interest formulae.
A. Interest Formulae for Single Payment Series :
Fig. 5.9.1 shows a cash flow diagram involing a present single sum (P), a
future single sum (F), separated by n year with interest rate i per year.
Case 1 : Finding F, when given P.
1 2 3 4 5 n–1 n
1
P=F n ...(5.9.2)
(1 i)
1
ii. The quantity is called single payment present worth factor
1 i n
P
indicated by the functional symbol as , i, n
F
Project Cost Management 5–10 C (CE-Sem-5)
1 2 3 4 n–1 n
P Fig. 5.9.2.
i. The present worth is obtained by summing the present worth of each
payment of amount A,
A A A A
P= ............
(1 i) (1 i)2 (1 i)3 (1 i) n
1 rn 1
ii. From the GP, Sum of payment = a , where r =
1r (1 i)n
iii. Present worth at zero time
(1 i)n 1 P
P= A n
A , i, n ...(5.9.3)
i(1 i) A
P
, i, n = Equal payment series present worth factor
A
Case 2 : Finding A, when given P.
From eq. 5.9.3, we get
i(1 i)n
A=P n
(1 i) 1
Single payment, A = P(A/P, i, n)
A
, i, n = Capital recovery factor
P
Case 3 : Finding F, when given A.
F
Substituting, P= in eq. (5.9.3), we get
(1 i) n
F n
n
= A (1 i) 1
(1 i) n
i(1 i)
(1 i)n 1 F
Future worth, F= A A , i, n ...(5.9.4)
i A
F
, i, n = Equal payment series compound amount factor.
A
Case 4 : Finding A, when given F.
from eq. (5.9.4), we get
Quantity Estimation & Management 5–11 C (CE-Sem-5)
Answer
Present Economy Studies : These are engineering economy analysis
where alternatives for accomplishing a specific task are being compared
over one year or less and the influence of time on money can be ignored.
Two rules shall be followed in conducting present economy studies :
Rule 1 : When revenues and other economic benefits are present and
vary among alternatives, choose the alternative that maximizes overall
profitability based on the number of defects free units of a product or
service product.
Rule 2 : When revenues and other economic benefits are not present or
are constant among all alternatives, consider only the costs and select
the alternative that minimizes total cost per defect free unit of product
service output.
Present Economy Studies Occur in the Following Situations :
1. Selection in present economy.
2. Selection of method to be used.
3. Selection of design.
4. Selection of location or site for a project.
4. Comparison of proficiency among workers.
6. Economy of tool and equipment maintenance.
7. Economy of number of laborers.
Que 5.11. Write a short note on project cost analysis.
Answer
Project Cost Analysis : It is act of breaking down a cost summary into
its constituents and studying and reporting on each factor.
Project cost analysis is done by following solutions :
1. The normal solution is the one corresponding to the normal durations of
all the activities giving the minimum direct cost for the project.
2. The crash solution is the one giving the minimum direct cost
corresponding to the minimum project duration.
Project Cost Management 5–12 C (CE-Sem-5)
Answer
A. Element of Cost Control : Following are the element of cost control :
1. Materials :
i. Materials costs are the tangible goods used in producing the product.
These costs can be direct or indirect.
ii. Direct materials are the quantifiable and traceable costs of materials
used in production.
iii. Indirect materials either cannot be traced to products or it is not cost
effective to do so.
2. Labour :
i. Wages and salaries paid to employees involved in manufacturing are
known as labour costs.
ii. These costs can be broken down into direct and indirect labour.
iii. Direct labour costs include the wages that are paid to employees that
physically handle the product.
iv. For this reason, direct labor is also referred to as touch labour. Indirect
labour costs are any other wages and salaries related to production,
but are not traceable back to units of product.
3. Overhead :
i. Overhead costs are those costs that are related to production, but are
not classified as direct labour or direct materials.
ii. This includes all indirect labour and materials costs, as well as any
other untraceable costs.
Quantity Estimation & Management 5–13 C (CE-Sem-5)
Que 5.13. A person deposits a sum of Rs. 20,000 at the interest rate
of 18 % compounded annually for 10 years. Find the maturity value
after 10 years.
Answer
10
18
= 20,000 1 = 1,04,680
100
F = Rs. 1,04,680
2. The maturity value of Rs. 20,000 invested now at 18 % compounded
yearly is equal to Rs. 1,04,680 after 10 years.
Que 5.14. A person wishes to have a future sum of Rs. 1,00,000 for
his son’s education after 10 years from now. What is the single-
payment that he should deposit now so that he gets the desired
amount after 10 years ? The bank gives 15 % interest rate
compounded annually.
Answer
100000
P= 10
15
1
100
P = Rs. 24720
2. The person has to invest Rs. 24,720 now so that he will get a sum of Rs.
1,00,000 after 10 years at 15 % interest rate compounded annually.
Que 5.15. A person who is now 35 years old is planning for his
retired life. He plans to invest an equal sum of Rs. 10,000 at the end
of every year for the next 25 years starting from the end of the next
year. The bank gives 20 % interest rate, compounded annually. Find
the maturity value of his account when he is 60 years old.
Answer
F
i = 20 %
0 1 2 3 4
25
Answer
A A A A A
Fig. 5.16.1. Cash flow diagram of equal-payment series sinking fund.
i 0.18
2. Equal payment, A=F = 5,00,000
(1 i)n 1 (1 0.18)15 1
A = 5,00,000 × 0.0164 = Rs. 8,200
Annual equal amount which must be deposited for 15 years is Rs. 8,200.
Project Cost Management 5–16 C (CE-Sem-5)
PART-2
Financing of Projects, Economic Comparisons present worth Method,
Equivalent Annual Cost Method, Discounted Cash Flow Method,
Depreciation and Break Even Cost Analysis.
Questions-Answers
Que 5.17. What are the different bases of comparing the worthiness
of the projects ?
OR
Discuss the following methods used in engineering economic
analysis for evaluating and comparing alternatives :
a. The present worth method.
Quantity Estimation & Management 5–17 C (CE-Sem-5)
Answer
A. The Present Worth Amount : The method is described as follows :
1. Indicate all expenses and benefits at appropriate point of time in the
form of cash flow separately for each alternative. Represent downward
arrows for expenses (costs) and upward arrows for benefits or savings.
In the algebraic expression + sign for expenses and – sign for benefits.
2. Shift the amount at zero time by using proper interest formulae and
find total present worth amount of each alternative and compare. There
may be two cases.
i. Case I : When service life of each alternative is same.
Item no. (2) will clearly indicate which alternative has lower present
worth. The alternative having lower present worth is economically
accepted.
ii. Case II : When service life of alternatives is different.
The cycle of item no. (2) is repeated till the common service life is
obtained. The common life is taken as the LCM value of the given lives.
The overall present worth of alternatives are obtained and then
compared for the selection of economical alternative.
B. Annual Equivalent Amount :
1. In this method, cash flow is converted into a series of equal annual
amount by first calculating the present worth amount for the original
Answer
1. Equipments and machines used in industries and in military deteriorate
with time, as a result of which their efficiency decreases and in turn
increases their maintenance cost.
2. Hence, there arises a need to formulate a replacement policy which
would enable us in deciding the age at which the replacement of the old
equipment by new one is most economical than continuation of old
equipment at an increased maintenance cost.
Causes Reasons for Replacement : Following are the reasons for
replacement :
1. Deterioration : Deterioration is the decline in performance of
equipment as compared to new equipment identical to the present one.
It may occur due to equipment wear, tear and misalignment.
It causes :
i. Increases maintenance costs.
ii. Reduces product quality.
iii. Decreases rate of production.
iv. Causes loss in operating time.
v. Increases labour costs.
2. Obsolescence :
i. Technology is progressing rapidly newer and better equipments are
being developed and produced every year.
ii. Obsolescence is due to improvement in technology. It causes loss in
value of machinery.
iii. If management of a concern does not go for a change in the equipment
or machinery, the unwarranted manufacturing costs arising from
obsolete equipment will :
i. Reduce profits.
ii. Impair competition.
iii. Cause loss in value of machinery.
Quantity Estimation & Management 5–19 C (CE-Sem-5)
Answer
Discount cash flow method :
1. Discounted cash flow (DCF) analysis is a method of valuing a project,
company, or asset using the concepts of the time value of money.
2. All future cash flows are estimated and discounted by using cost of
capital to give their present values (PVs).
3. The sum of all future cash flows, both incoming and outgoing, is the net
present value (NPV), which is taken as the value of the cash flows in
question.
4. Discounted cash flow analysis is widely used in investment finance, real
estate development, a financial management and patent valuation.
Discounted Cash Formula : This discounted cash flow formula is
derived from the future value formula for calculating the time value of
money and compounding returns.
CF1 CF2 CFn
DCF = ...
(1 r )1 (1 r)2 (1 r )n
FV = DCF (1 + r)n
Discounted present value (for one cash flow in one future period) is
expressed as :
FV
DVD = (1 r ) n
where, DPV = Discounted present value of the future cash
flow.
FV= Nominal of a cash flow amount in a future
period.
r = Interest rate or discount rate,
n = Time in years before the future cash flow occurs.
Project Cost Management 5–20 C (CE-Sem-5)
Answer
Depreciation : It is the decrease in value of asset resulting from
deterioration, wear and tear from you, obsolescence arising from
improvement in design and new technology.
Types of Depreciation : Following are the various types of depreciation :
1. Physical Depreciation :
i. Depreciation resulting in physical impairment of an asset is known as
physical depreciation. This results in lowering the ability of the asset to
render its intended service.
ii. The primary cause of physical depreciation is wear and tear because of
its constant use such as abrasion, shocks, vibration, and impact etc. and
the deterioration due to action of elements such as corrosion of pipe,
chemical decomposition.
2. Function Depreciation : Functional depreciation often called
obsolescence is defined as the loss in the value of the property due to
change in fashion, design or structure due to inadequate to meet the
growing demand, necessity of replacement due to new invention be
more economical and more efficient etc.
3. Contingent Depreciation : It causes due to :
i. Accident (due to negligence),
ii. Diseases (pollution of water, parasites), and
iii. Diminution of supply (natural gas, electricity, water etc.)
Answer
Following are the methods for determining depreciation :
A. Straight-Line Depreciation Method :
1. Straight-line depreciation is a very common and simple method of
calculating the expense. In straight-line depreciation, the expense amount
is the same every year over the useful life of the asset.
2. Depreciation Formula for the Straight Line Method.
Quantity Estimation & Management 5–21 C (CE-Sem-5)
Que 5.22. What is the break even cost analysis ? Give assumptions
and limitations of break even chart.
Answer
A. Break Even Cost Analysis :
i. Break even cost analysis in economics, business, and cost accounting
refers to the point in which total cost and total revenue are equal.
ii. A break even point analysis is used to determine the number of units or
revenue needed to cover total costs (fixed and variable costs).
iii. The break even analysis is important to business owners and managers
in determining how many units (or revenues) are needed to cover fixed
and variable expenses of the business.
B. Assumptions of Break Even Cost Analysis :
Following are the assumptions of break even cost analysis :
i. The total costs may be classified into fixed and variable costs. It ignores
semi-variable cost.
ii. The cost and revenue functions remain linear.
iii. The price of the product is assumed to be constant.
iv. The volume of sales and volume of production are equal.
v. The fixed costs remain constant over the volume under consideration.
vi. It assumes constant rate of increase in variable cost.
vii. It assumes constant technology and no improvement in labour efficiency.
viiii. The price of the product is assumed to be constant.
Que 5.23. What is break even chart ? What are the functions and
limitations of break even chart ?
Answer
A. Break Even Chart :
i. A break even chart is a graphical representing of the relationship
between costs and revenue for all possible volumes of output.
ii. The main objective of the graphic device is to determine the break even
point and profit potential under varying condition of output and costs.
iii. In brief it may be called a continuous income (profit and loss) statement.
Therefore, the Concept of Break Even Point is as follows :
1. Profit when Revenue > Total Variable cost + Total Fixed cost
2. Break-even point when Revenue = Total Variable cost + Total Fixed
cost
Quantity Estimation & Management 5–23 C (CE-Sem-5)
3. Loss when Revenue < Total Variable cost + Total Fixed cost
Sales (S)
Profit
Total cost (TC)
Break-even BEP
sales Variable cost (VC)
Loss
Fixed cost (FC)
Production quantity
Answer
(1 i)n – 1 (1 0.15)15 1
P A , i, n =
i(1 i) n 0.15 (1 0.15)15
1 0.15 15 1
iii. PW(15%) = 4,50,000 27,000 15
0.15 1 0.15
Quantity Estimation & Management 5–25 C (CE-Sem-5)
Answer
Given :
Present Machine New Machine
Purchase price Rs. 2,00,000 Rs. 1,50,000
Present value (P) Rs. 1,20,000
Salvage value (F) Rs. 25,000 Rs. 20,000
Annual maintenance Rs. 25,000 Rs. 14,000
cost (A)
Life (n) 6 years 6 years
Interest rate (i) 12 % 12 %
To Find : Replacement of machine is possible or not.
Project Cost Management 5–26 C (CE-Sem-5)
–2 –1 0 1 2 3 4 5 6
1,20,000
2,00,000
Fig. 5.25.1. Cash flow diagram for alternative 1.
ii. The annual maintenance cost for the preceding is not shown in this
figure.
iii. The annual equivalent cost is computed as
AE(12 %) = (P – F) (A/P, 12% , 6) + F × i + A
i(1 i) n
(A/P, 12 %, 6) = n
(1 i) 1
0.12 (1 0.12)6
= 6 = 0.2432 ...(5.25.1)
(1 0.12) 1
= (1, 20,000 – 25,000)(0.2432) + 25,000 × 0.12 + 25,000
AE(12 %) = Rs. 51,104
2. New Machine :
i. The cash flow diagram of the new machine is depicted in Fig. 5.25.2.
20,000
0 1 2 3 4 5 6
1,50,000
Fig. 5.25.2. Cash flow diagram for alternative 2.
Quantity Estimation & Management 5–27 C (CE-Sem-5)
Answer
( P F ) 2,50,000 1,00,000
1. Depreciation, Dt = = 21428.57
n 7
2. In straight line method of depreciation, the value of Dt is same for all the
year.
Table. 5.26.1
End of Year Depreciation Book Value
(Dt) (Bt = Bt–1 – Dt)
0 2,50,000
1 21428.57 228571.43
2 21428.57 207142.86
3 21428.57 185714.29
4 21428.57 164285.72
Answer
Answer
FC 20,00,000
1. Break-even sales quantity, =
S V 200 100
= 20,00,000/100 = 20,000 units
FC
2. Break-even sales, = × s (Rs.)
SV
20,00,000
= 200 = Rs. 40,00,000
200 100
3. i. Contribution = Sales – Variable cost
= S×Q–V×Q
= 200 × 60,000 – 100 × 60,000 = Rs. 60,00,000
ii. Margin of safety
a. Method I :
MS = Sales – Break-even sales
= 60,000 × 200 – 40,00,000 = Rs. 80,00,000
b. Method II :
Profit
MS = × Sales
Contribution
Profit = Sales – (FC + V × Q)
= 60,000 × 200 – (20,00,000 + 100 × 60,000)
= 1,20,00,000 – 80,00,000 = Rs. 40,00,000
40,00,000
MS = × 1,20,00,000 = Rs. 80,00,000
60,00,000
80,00,000
MS as a percent of sales = × 100 = 67 %
1,20,00,000
Project Cost Management 5–30 C (CE-Sem-5)
Quantity Estimation & Management SQ–1 C (CE-Sem-5)
1 Quantity Estimation
for Buildings
(2 Marks Questions)
1.3. List the data required to make out estimation for a work.
Ans. To make out an estimate for a work, the following data is necessary :
i. Drawings (plan and section).
ii. Specification.
iii. Rates.
Quantity Estimation & Management SQ–3 C (CE-Sem-5)
Analysis of Rates,
2 Specification
and Tenders
(2 Marks Questions)
2.9. Write down the different laws related to labour safety and
welfare.
Ans. Laws related to labour safety and welfare are :
i. Payment of wages act, ii. Minimum wages act,
iii. Factories act, iv. Contract labour act,
v. Labour welfare fund act,
vi. Workmen’s compensation act, and
vii. Trade union act.
i. In case of death.
ii. On account of occupational diseases.
iii. For permanent/partial disablement.
iv. Half monthly payments for temporary disablement.
2 Marks Questions SQ–6 C (CE-Sem-5)
Element of
3 Management and
Network Techniques
(2 Marks Questions)
Ans. The objective of IPM is to establish and manage the project and the
involvement of relevant stakeholders according to an integrated
and defined process that is tailored from the organization’s set of
standard processes.
3.5. Define network with example.
Ans. N e two rk is an arro w diagram drawn to re pre se nt the
interrelationship and sequence of all the required construction
activities of a project.
Example :
Fig. 3.5.1.
1 3
B
2 Dummy
Fig. 3.9.1.
2 Marks Questions SQ–8 C (CE-Sem-5)
3.17. How can you calculate the earliest expected time and latest
allowable occurrences time in PERT ?
AKTU 2015-16, Marks 02
Ans. Earliest Expected Time (TE) : It is the time when an event can be
expected to occur earliest. TE calculated as : (TE)j = (TE)i + ti – j.
Latest Allowable Occurrence Time (TL) : The latest time by
which an event must occur to keep the project on schedule is called
the latest allowable occurrence time (TL). TL is determine as :
(TL)i = (TL)j – ti – j
Ans. In applying the CPM, there are several steps that can be summarized
as follows :
i. Define the required tasks and put them down in an ordered
(sequenced) list.
ii. Create a flow chart or other diagram showing each task in relation
to the others.
iii. Identify the critical and non-critical relationships (paths) among
tasks.
iv. Determine the expected completion or execution time for each
task.
v. Locate or devise alternatives (backups) for the most critical paths.
3.19. Suggest a suitable method for submitting the periodical
reports for effective control through CPM.
AKTU 2015-16, Marks 02
Ans. PERT is suitable method for submitting the periodical reports for
effective control through CPM.
Quantity Estimation & Management SQ–11 C (CE-Sem-5)
4 Equipment
Management
(2 Marks Questions)
Quantity Estimation & Management SQ–15 C (CE-Sem-5)
5 Project Cost
Management
(2 Marks Questions)
Direct cost
Optimum
Cost
cost
Indirect cost
i. This is the physical loss in the This is functional loss in the value
value of property due to wear of the property due to change in
and tear and decay etc. design, structure, fashion, utility,
demand, etc.
ii. It depends upon its original It depends upon the technological
conditions, quality o f advancement, art, etc.
maintenance and mode of use.
iii. It varies with age. Not dependent on age.
Quantity Estimation & Management SP–1 C (CE-Sem-5)
B. Tech.
(SEM. VI) EVEN SEMESTER THEORY
EXAMINATION, 2015-16
CONSTRUCTION TECHNOLOGY
AND MANAGEMENT
Section-A
1. Attempt all parts. All parts carry equal marks. Write answer of
each part in short. (10 × 2 = 20)
e. How can you calculate the earliest expected time and latest
allowable occurrences time in PERT ?
Section-B
Section-C
Solved Paper (2015-16) SP–4 C (CE-Sem-5)
Section-A
1. Attempt all parts. All parts carry equal marks. Write answer of
each part in short. (10 × 2 = 20)
e. How can you calculate the earliest expected time and latest
allowable occurrences time in PERT ?
Quantity Estimation & Management SP–5 C (CE-Sem-5)
Ans. Earliest Expected Time (TE) : It is the time when an event can be
expected to occur earliest. TE calculated as : (TE)j = (TE)i + ti – j.
Latest Allowable Occurrence Time (TL) : The latest time by
which an event must occur to keep the project on schedule is called
the latest allowable occurrence time (TL). TL is determine as :
(TL)i = (TL)j – ti – j
Section-B
Ans.
S. No. Line and Functional
Staff Organization Organization
1. Fig. 1 shows the indirect cost curve, direct cost curve and the
corresponding total cost curve.
2. From the total cost curve, we find that the minimum total cost
(optimum cost) is obtained at some duration known as optimum
duration. The corresponding cost is known as the minimum cost.
3. If the project duration is increased, total cost will be the highest.
4. In figure 1, we observe two types of times–normal and crash. These
will have two types of cost associated with them. These are defined
as follows :
i. Normal Time (tn) : It is the standard time that an estimator would
usually allow for an activity.
ii. Crash Time (tc) : It is the minimum possible time in which an
activity can be completed by employing extra resources. Crash time
is that time beyond which the activity cannot be shortened by any
amount of increase in resources.
Total cost
Direct cost
Optimum
Cost
cost
Indirect cost
Ans.
i. Network comparisons : Network comparison is the comparison
between critical path method (CPM) and program evaluation and
review technique (PERT).
3. Overhead Control :
i. Aggregate of all expenses relating to indirect material cost, indirect
labour cost and indirect expenses is known as overhead.
ii. Measures to controlling overhead costs :
a. Inventory counts (avoid excessive/wrong inventory items).
b. Renegotiate interest terms.
c. Renegotiate rental terms.
d. Decrease working capital.
e. Implement quality control system.
f. Re-evaluate sales and marketing costs.
g. decrease transportation cost.
4. Standard Costing :
i. Implementing this level of control can have a profound positive
impact on profits over the long term.
ii. The following four steps are associated with standard costing :
a. Create a baseline.
b. Calculate a variance.
c. Investigate variances.
d. Take action.
5. Budgetary Control :
i. Budgetary control is the process of determining various actual results
with budgeted figures for the enterprise for the future period and
standards set then comparing the budgeted figures with the actual
performance for calculating variances, if any.
ii. The comparison of budgeted and actual figures will enable the
management to find out discrepancies and take remedial measures
at a proper time.
6. Capital Expenditure Controlling :
i. Capital expenditure controlling refers to the actions, processes and
tools used to identify, forecast, assess, decide and manage capital
expenditure.
ii. Capital expenditure can be used to replace or expand existing plant
and equipment, to invest in new equipment or to make use of
strategic opportunities in new production or market contexts.
iii. In the broader sense capital expenditure controlling is also applied
to expenditure incurred in the context of campaigns or projects
typical for areas such as marketing or research and development.
Section-C
Fig. 2.
B. Breakdown Structure for the Launching of a
Communication Satellite :
Ground segment
Land assets
Crew
Servicing Planning
Video
streaming Equipment
Interfaces
B
Item
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
(Time in week)
(a) Bar chart.
2. Milestone Chart :
Critical item
B Non critical item
C
Item
1 2 3 4 5 6 7 8 9 10 11 12
Time in week
(b) Milestone chart.
Fig. 4.
Ans.
t0 4 tm t p
1. Expected time, te =
6
10 4 12 14
i. For activity P : te = 12
6
6 4 8 12
ii. For activity Q : te = 8.33
6
5 4 10 12
iii. For activity R : te = 9.5
6
2
t p t0
2. Variance, 2 =
6
i. For activity P : t0 = 10, tm = 12, tp = 14
2
14 10
2 = 0.44
6
ii. For activity Q :t0 = 6, tm = 8, tp = 12
2
2 = 12 6 1
6
iii. For activity R : t0 = 5, tm = 10, tp = 12
2
12 5
2 = 1.36
6
3. te = 12, so activity P has more reliable time estimate.
Liftarm
Piston rod
Hoist cylinder
Tension line Body
Hinge
Tail board
Gear pump
Power take off
Fig. 5.
Solved Paper (2015-16) SP–22 C (CE-Sem-5)
B. Conveying Equipment :
1. Transporting material from one place to another over a stationary
structure.
2. Caries material in continuous stream with its distinct feature such
as endless chain or belt.
3. When the equipment does horizontal conveying, it is known as
conveyor and when it does vertical, it is known as elevator.
4. Conveying are mainly used in mining, construction and in some of
the industries.
5. In construction industry, conveyors are mainly used for concreting
purpose.
6. Type of Conveyors Equipment : Following are the types of
conveyors equipment.
i. Belt Conveyor :
a. It used when large quantities of materials have to be conveyed
over long distances at fast speed.
b. It consists of a belt running over a pair of end drums or pulleys
and supported at regular intervals by a series of rollers called
idlers.
c. Generally, rubber is most commonly used as conveyor belt.
Feeder Head pulley Screw takeup
Screw takeup
Belt Head drive
Height
Tail pulley
Snub pulley
Snub pulley
Length
Tail drive
(a) (b)
Fig. 6. Belt conveyor system.
ii. Screw Conveyor :
a. A screw conveyor consists of a helix mounted on a bearing at
the ends and at intermediate points and is driven by a motor
from one end.
b. The material enters the through at one end is carried to the
other end by screwing action of helix.
Bearing
Blockage detector temperature
sensor
Bucket
Rubber conveyor belt
Fig. 8.
iv. Aerial Transport :
a. Aerial transportation through cableways, rope-ways and tram
ways.
b. It is used with advantage for transportation of material in hilly
regions.
c. It is reducing the distance of transportation as well as cost of
transportation.
d. The load being passed over intermediate towers or stations for
long distances.
C. Tunneling Equipment : Following are the equipment used in
tunnelling operations.
i. Tunnel Boring Machine :
a. Tunnel boring machine TBM also known as a ‘mole’, is a
machine used to excavate tunnels with a circular cross section
through a variety of soil and rock strata.
b. They can bore through anything from hard rock to sand.
c. Tunnel diameters can range from a meter (done with micro-
TBMs) to 19.25 m.
d. Tunnels of less than a meter or so in diameter are typically
done using trenchless construction methods or horizontal
directional drilling rather than TBMs.
Solved Paper (2015-16) SP–24 C (CE-Sem-5)
Shield
Hydraulic push arms Rock cutter head
Quantity Estimation & Management SQ–1 C (CE-Sem-5)
B. Tech.
(SEM. VI) EVEN SEMESTER THEORY
EXAMINATION, 2016-17
CONSTRUCTION TECHNOLOGY
AND MANAGEMENT
SECTION-A
g. Define arbitration.
SECTION-B
2. Attempt any five of the following questions : (5 × 10 = 50)
a. Define organization and explain its types.
c. Draw the network and design the critical path and calculate
the completion time of the project whose activities are as
follows :
Solved Paper (2016-17) SQ–2 C (CE-Sem-5)
SECTION-C
Solved Paper (2016-17) SQ–4 C (CE-Sem-5)
SECTION-A
1. Explain the following : (10 × 2 = 20)
a. What is the term planning ?
Ans. Planning is the process of thinking about and organizing the
activities required to achieve a desired goal. It involves the creation
and maintenance of a plan such as psychological aspects that require
conceptual skills.
Total cost
Direct cost
Optimum
Cost cost
Indirect cost
g. Define arbitration.
Ans. Arbitration is the process of the settlement of a dispute not by a
regular and ordinary court but by impartial references selected or
agreed upon by the parties concerned.
Ans. Organization :
i. Organization is the systematic arrangement of people working
together towards a common purpose.
ii. It is composed of a group of individuals acting as a unit for the
attainment of an objective.
Types of Organization : Following are the various types of
organization :
1. Line Organization :
i. Under line organization, each department is generally a complete
self-contained unit. A separate person will look after the activities
of the department and he has full control over the department.
ii. The same level executives do not give or receive orders amongst
themselves. But they receive orders from their immediate boss
and give orders to their subordinates.
Characteristics of Line Organization :
i. It consists of direct vertical relationships.
ii. Authority flows from top-level to bottom level.
iii. Departmental heads are given full freedom to control their
departments.
iv. A senior member has direct command over his subordinates.
v. Existence o f dire ct re lationship betwee n supe riors and
subordinates.
vi. The superior takes decisions within the scope of his authority.
Advantages :
i. It is simple in form with a clear cut division of authority.
ii. The decisions are speedy and their implementation is quick.
iii. It promotes greater co-ordination and keeps better discipline.
iv. The responsibility can be easily fixed.
v. More economical and flexible.
Disadvantages :
i. Lack of specification and initiative.
ii. Overloading.
iii. Limited communication and subjective approach.
2. Functional Organization :
i. Under functional organization, various specialists are for various
functions performed in an organization.
ii. These specialists will attend to the work which is common to
different functions of various departments.
iii. Workers, under functional organization, receive instructions from
various specialists.
Characteristics of Functional Organization :
i. The work is divided according to specified functions.
ii. Authority is given to a specialist to give orders and instructions in
relation to specific function.
iii. Functional authority has right and power to give command
throughout the line with reference to his specified area.
Quantity Estimation & Management SQ–7 C (CE-Sem-5)
ii. In this way, both the major as well as the derivative plans are made
with a view to contribute in the achievement of organizational
goals.
2. Primacy of Planning :
i. According to this principle, the process of planning is the primary
function of all the managers.
ii. The managers are required to plan all their actions and then they
should proceed with other functions.
3. Planning Premises : For the purpose of making the process of
planning effective, there are certain presumptions or premises that
have to be made and the planning is undertaken on the basis of
these premises.
4. Principle of Alternatives : The process of planning involves the
development of several alternatives and then the planners select
the alternative that is most appropriate for achieving the
organizational goals.
5. Principle of Timing : The plans have the capability of contributing
significantly in the achievements of the organizational goals if the
plans are properly timed. Therefore the planning premises as well
as the policies are not much helpful if the plans are not properly
timed.
6. Principle of Flexibility :
i. According to this principle, there should be flexibility in the plans.
This is very important because flexibility allows the plans to deal
with the contingencies that may develop later on.
ii. Therefore, the plans should be adjustable so that they can deal with
the changes that may develop after the plans have been formulated.
7. Principle of Comparative Strategies :
i. This requires that while formulating their plans, the managers
should also consider the plans made by their competitors.
ii. In this way, the managers should formulate their plans by
considering what the competition would have done in such a case.
8. Principle of Commitment : According to this principle, a time
frame should be provided by the plan during which the commitments
made in the plan have to be fulfilled. This commitment allows the
managers to achieve the targets in time.
Advantages of Planning : Following are the advantages of
planning :
1. Planning helps in determining the objectives of an enterprise.
2. Planning avoids chaos because all efforts are directed towards a
predetermined goals of the enterprise.
3. Planning helps in control by distributing the responsibilities of
different persons and jobs.
4. Planning minimizes the cost by utilizing the available resources in
the best way.
Limitations of Planning : Following are the limitations of
planning :
Quantity Estimation & Management SQ–9 C (CE-Sem-5)
1. In case the data that has been provided to the managers is not
reliable, it is possible that the decisions that are based on this data
can also be unreliable.
2. It also needs to be noted that the process of planning can be very
expensive.
3. The process of planning can be very time consuming and this in
turn reduces the practical utility of planning.
4. Planning cannot be considered as a remedy for all the problems
faced by the organization.
c. Draw the network and design the critical path and calculate
the completion time of the project whose activities are as
follows.
Activity Duration in days Preceding
A-B 7 –
B-C 10 A-B
B-D 15 A-B
C-D 7 B-C
C-E 12 B-C
D-E 3 B-D, C-D
E-F 5 C-E, D-E
Ans.
1. Network :
7 7 17 17 29 29 34 34
7 10 12 5
A B C E F
0 0 7
15
3
24 26
Fig. 2.
2. Critical Path : There are three possible path for completion this
project, such as :
i. A-B-C-E-F
Total time taken = 7 + 10 + 12 + 5 = 34 days
ii. A-B-D-E-F
Total time taken = 7 + 15 + 3 + 5 = 30 days
Solved Paper (2016-17) SQ–10 C (CE-Sem-5)
iii. A-B-C-D-E-F
Total time taken = 7 + 10 + 7 + 3 + 5 = 32 days
Maximum time taken path is path (i), so this is called as critical
path. Hence completion time for project is 34 days.
Ans.
1. The network diagram for the given problem is shown in Fig. 3.
20 2
3
40
5
10
6 4
50
30
Fig. 3. Network diagram.
2. From network diagram, the critical path is 10-30-40-50 with project
duration of 15 week and project cost of ` 96000.
3. The cost slope for all activities are given below :
Crash cost Normal cost
Activity Cost slope =
Normal time Crash time
10-20 4000
10-30 2000
20-40 3000
30-40 2500
40-50 5000
Solved Paper (2016-17) SQ–12 C (CE-Sem-5)
Demerits :
i. The total cost of work can only be known after completion. As such
the owner may face financial difficulty if the final cost is substantially
high.
ii. Additional staff is required to take detailed measurements of work.
iii. The scope of saving with use of inferior quality materials may
prompt the contractor to do so.
2. Percentage Rate Contract :
i. In this form of contract, the department draws up ‘item rate tender’
i.e., bill of quantities with rate, amount and total amount.
ii. The contractors are required to offer to carry out the work as per
with the rates shown in the specific price schedule or some
percentage above or some percentage below the rate indicated in
the schedule of work attached with the tender.
iii. The percentage above or below or at par is applicable on the overall
cost of the work also.
Merits :
i. The ranking amongst the contractors is easily known just on the
opening of the tenders.
ii. As there is no provision to quote contractors own rate for an
individual item, benefit due to increased quantity with a beneficial
rate cannot be availed by the contractor. The chance of unbalanced
tender gets eliminated.
Demerits :
i. A contractor is required to write down only the percentage above
or at par or below, it is very easy to write such a rate in few minutes
before the time of submission of the tender.
ii. By negotiating among the contractors, two or more may quote the
same rate in order to get a part of the work at a high rate. It may be
difficult to divide the work at equal amount among the contractors.
3. Lump-Sum Contract :
i. In this type of contract, a contractor is required to quote a fixed sum
for execution of work complete in all respect in the stipulated time
according to the drawing, design and specifications supplied to him
with the tender.
ii. The departmental schedule of rate for various items of work is also
provided which regulates the payment of the contractor in respect
of any additions and alterations which are made over the original
work.
iii. On the completion of the work, no detailed measurement of different
items of work is needed but the whole work done must be compared
and checked with the drawings and specifications.
Merits :
i. As the total cost of the work known before hand, the owner can
arrange the fund in time.
ii. Detailed measurements of the work done are not required except
in respect of additions and alterations.
Quantity Estimation & Management SQ–15 C (CE-Sem-5)
iii. The contractor’s profit mainly lies in the completion time. Hence
for getting more profit the contractor tries to complete the work as
early as possible.
Demerits :
i. It is very essential that the work must be defined accurately,
specifications must be fully specified and the site conditions must
be fully explained otherwise disputes can arise later on.
ii. For any intermediate payment, the value of work done should not
be less than the payment being made.
4. Labour Contract :
i. In labour contract, the contractor undertakes contract for the labour
portion only excluding the materials which are arranged and
supplied at the work site by the department/owner.
ii. The contractor engages the requisite labour and gets the work
done as per drawings and specifications.
iii. It is an item rate basis for labour portion only and the contractor is
paid for the quantities of work done on measurement of different
items of work at the stipulated rate in the contract agreement.
Merits :
i. The materials stored by the department are thus utilised.
ii. The work done through labour contract is of superior quality as
better quality materials are arranged by the owner.
iii. The overall cost of construction may be less, as no profit is paid on
the cost of materials.
iv. This system is very convenient for private building construction.
Demerits :
i. A large storage area is required to store the various kinds of
materials to be used in the construction under a constant guarding.
ii. This system is not suitable for government department. Because of
lengthy formalities in procurement of materials, it is very difficult
to supply each and every material readily to the labour contractor.
5. Cost Plus Percentage Rate Contract :
i. In this type of contract, a contractor agrees to take the work of
construction on the actual cost of work plus an agreed percentage
in addition, for his services.
ii. It is generally adopted when the labour and material costs are liable
to fluctuate heavily in the market.
iii. The contractor arranges materials and labour at his cost and keeps
proper account which is paid by the department or owner with
certain percentage (say 10 %) of the cost of construction as his
profit. An agreement is made accordingly in advance.
Merits :
i. The contract can be quickly drawn up and agreed and work can be
completed in the shortest possible time.
ii. It is particularly suitable when work cannot be executed by other
types of contracts due to uncertainty and fluctuations in the market
rates of labour and materials.
Solved Paper (2016-17) SQ–16 C (CE-Sem-5)
Demerits :
i. The contractor’s only aim is to make the cost of the project as high
as possible in order to seek greater margin of profit.
ii. A proper control over purchase of materials and of labour shall
have to be exercised by the department or the owner.
Height
Tail pulley
Snub pulley
Snub pulley
Length
Tail drive
(a) (b)
Bucket
Rubber conveyor belt
Fig. 5.
4. Aerial Transport :
i. Aerial transportation through cableways, rope-ways and tram ways.
ii. It is used with advantage for transportation of material in hilly
regions.
iii. It is reducing the distance of transportation as well as cost of
transportation.
iv. The load being passed over intermediate towers or stations for long
distances.
SECTION-C
Attempt any two of the following questions : (2 × 15 = 30)
3. i. Explain the different classification of scheduling in detail.
Ans. Following are the various types of scheduling :
1. Material Scheduling :
i. It provides advanced capabilities for scheduling different types of
commodities and products which include procured raw material,
stores, spares and consumables.
ii. The scheduling of raw material is done on daily production schedule
basis for short lead and cycle time materials, master production
schedule for longer lead time items and on replenishment basis for
imported items with long lead/cycle time.
2. Labour Scheduling :
i. It is used to create, update, and review employee labour schedules.
A labour schedule specifies how an employee’s pay is to be distributed
to oracle grants accounting, oracle projects, or oracle general ledger.
Solved Paper (2016-17) SQ–18 C (CE-Sem-5)
ii. Unlike the shovel, it has a long light crane boom and the bucket is
loosely attached to the boom through cables
iii. Because of this construction, a dragline can dig and dump over
larger distances than a shovel can do.
iv. Drag lines are useful for digging below its track level and handling
softer materials.
v. The basic parts of a drag line including the boom, hoist cable, drag
cable, hoist chain, drag chain and bucket.
vi. Uses :
a. It is the most suitable machine for dragging softer material and
below its track level.
b. It is very useful for excavating trenches when the sides are permitted
to establish their angle of repose without shoring.
c. It is mostly used in the excavation for canals and depositing on the
embankment without hauling units.
4. Clam Shell :
i. This is so named due to resemblance of its bucket to a clam which
is like a shell-fish with hinged double shell.
ii. The front end is essentially a crane boom with a specially designed
bucket loosely attached at the end through cables as in a drag line.
iii. The capacity of a clam shell bucket is usually given in cubic meters.
iv. The basic parts of clam shell bucket are the closing line, hoist line,
sheaves, brackets, tagline, shell and hinge.
v. Uses :
a. Used for handling loose material such as crushed stone, sand, gravel,
coal etc.
b. Main feature is vertical lifting of material from one location to
another.
c. Mainly used for removing material from coffer dam, sewer main
holes, well foundations etc.
5. Trenching Machine :
i. Trenchers are the equipments used for excavating trenches or
ditches of variable width and depth.
ii. Two types of trenching machine are available : wheel type, and
ladder type.
iii. Operation is quick giving the required depth or width.
iv. Used for excavating trenches for laying pipelines, sewer, cables etc.
6. Scrapers :
i. Unique machine for digging and long-distance hauling of plough
able materials.
ii. The basic parts of scrapers are the bowl, apron and tail gate or
ejector.
iii. It is a self-operating machine.
iv. Wheels of machine cause some compaction.
7. Bulldozer :
i. The heavy blade attached to the tractor pushes the material from
one place to another.
Solved Paper (2016-17) SQ–22 C (CE-Sem-5)
Quantity Estimation & Management SQ–1 C (CE-Sem-5)
B. Tech.
(SEM. VI) EVEN SEMESTER THEORY
EXAMINATION, 2017-18
CONSTRUCTION TECHNOLOGY
AND MANAGEMENT
Note : Attempt all Sections. If require any missing data; then choose
suitably.
SECTION-A
SECTION-B
2. Attempt any three of the following : (10 × 3 = 30)
Solved Paper (2017-18) SQ–4 C (CE-Sem-5)
Note : Attempt all Sections. If require any missing data; then choose
suitably.
SECTION-A
1 3
B
2 Dummy
Fig. 1.
SECTION-B
2. Attempt any three of the following : (10 × 3 = 30)
2. Discipline :
i. You will need to have the financial discipline to make repayments
on time.
ii. Exercise restraint and use good financial judgment when you use
debt.
3. Collateral : Lenders will typically demand that certain assets of
the company be held as collateral, and the owner is often required
to guarantee the loan personally.
4. Fixed Payments :
i. Principal and interest payments must be made on specified dates
without fail. Businesses that have unpredictable cash flows might
have difficulties making loan payments.
ii. Declines in sales can create serious problems in meeting loan
payment dates.
5. Cash Flow :
i. Taking on too much debt makes the business more likely to have
problems meeting loan payments if cash flow declines.
ii. Investors will also see the company as a higher risk and be reluctant
to make additional equity investments.
iv. Arbitration.
v. Conciliation.
vi. Adjudication.
vii. Consultative machinery.
Commissioning of Project :
1. Project commissioning is the stage in which the performance of
the structure is evaluated and nature of maintenance and repair
is proposed.
2. The purpose of this stage is to ensure that the construction work
has been completed as specified in the contract documents.
3. If any changes have been made because of some reasons, they
must be recorded for technical performance and financial
implications.
4. Following are the various step of project commissioning stage :
i. Keep various records of the actual work.
ii. Quality inspection (done to remove the defects, if found).
iii. Prepare operation and maintenance manuals.
iv. Carry out the performance test of the structure.
v. Training and recruitment of staff for commissioning schedule.
3. Dumpers :
i. Dumpers are high speed pneumatic wheeled trucks.
ii. They have short chassis and strong bodies.
iii. Loading, hauling and dumping is done very fast as compared to
other equipment.
iv. Suitable for short hauls on rough roads, especially where a shuttle
movement is required.
4. Tractors :
i. Tractors are multi-purpose machines used mainly for pulling and
pushing the other equipment.
ii. Tractors may be classified as :
a. Crawler Type Tractor : Used to move bull dozers, scrapers.
The crawler has a chain by which these tractors can be very
effective even in the case of loose or muddy soils. The speed of
this type does not exceed 12 kmph normally.
b. Wheel Type Tractor : The engine is mounted on four wheels.
The main advantage is higher speed, sometimes exceeding 50
kmph, it is used for long-distance hauling and good roads.
Liftarm
Piston rod
Hoist cylinder
Tension line Body
Hinge
Tail board
Gear pump
Power take off
Fig. 2.
SECTION-C
3. Attempt any one of the following : (1 × 10 = 10)
a. What are the advantages and disadvantages of :
i. Line organization
ii. Line and staff organization
Ans.
1. Line Organization :
Advantages :
i. It is simple in form with a clear cut division of authority.
ii. The decisions are speedy and their implementation is quick.
iii. It promotes greater co-ordination and keeps better discipline.
Quantity Estimation & Management SQ–11 C (CE-Sem-5)
Ans. Network :
2 4 8
1 5
3 7
6
Fig. 3.
b. Define the following :
i. Direct cost and indirect cost.
ii. Crash time and crash cost.
iii. Cost slope.
iv. Optimum time and optimum cost.
Ans.
A. Direct Cost and Indirect Cost :
1. Direct Cost :
i. Direct costs are directly attributable to the object and it is financially
feasible to do so.
ii. In construction, the costs of materials, labour, equipment, etc., and
all directly involved efforts or expenses for the cost object are direct
costs.
2. Indirect Cost :
i. Indirect costs are, not directly attributable to a cost object.
ii. It should be financially infeasible to do so.
iii. Indirect costs are typically allocated to a cost object on some basis.
iv. In construction, all costs which are required for completion of the
installation, but are not directly attributable to the cost object are
indirect, such as overhead.
v. In manufacturing, costs not directly assignable to the end product
or process are indirect.
B. Crash Time and Crash Cost :
1. Crash Time (tc) : It is the minimum possible time in which an
activity can be completed by employing extra resources. Crash time
Quantity Estimation & Management SQ–13 C (CE-Sem-5)
Total cost
Direct cost
Optimum
Cost
cost
Indirect cost
1,80,000
1,60,000
1,40,000
1,20,000
1,00,000 V
80,000
F BEP
60,000 F
20,000
O
0 Units
2,000 3,000 4,000 6,000 8,000
Fig. 5. Break even chart.
where FF is representing fixed cost line, FV is the variable cost
line, and OS is sale line.
2. Number of output units estimate for the year 2013-14
2,00,000
= 8,000 units.
25
3. Variable cost for total project
= 8,000 × 5 = Rs, 40,000
4. i. The break even point :
At break even point,
Total sale = Total cost
S×x= V×x+F
Fixed cost
Break even point(x) =
Selling price/ unit Variable cost/ unit
60,000
BEP = 3,000 units
25 5
Expected Output BEP
ii. Margin of safety = 100
Expected Output
8,000 3,000
= 100 62.5 %
8,000
vi. Site Vehicles and Mobile Plant : Provide safe site entry and exit
points with adequate turning room and good visibility for vehicle
drivers.
vii. Protective Equipment : Employees on construction sites need
specific Personal Protective Equipment (PPE) to ensure their safety
and health.
viii. Emergency Procedures : Where an employee has suffered injury
or illness at work necessitating his removal to his home or to a
hospital or other similar institution, the employer shall provide an
appropriate means of conveyance for the employee.
5 60
iii. Returning time @ 30 km/hr = = 10 min
30
iv. Other fixed time = 3 min
v. Total time = 12 + 10 + 15 + 3 = 40 min
2. For estimating purpose, actual working period is considered as 50
minutes per hour and six hours working period in day.
50
3. Material transported per hours = 20 = 25 cum
40
4. Material transported per days = 25 × 6 = 150 cum
1500
5. Number of dump trucks required per day = 10
150
6. Stand by 10 % = 1
7. Total number of dump trucks = 10 + 1 = 11.
Quantity Estimation & Management SP–1 C (CE-Sem-5)
B.Tech.
(SEM. V) ODD SEMESTER THEORY
EXAMINATION, 2018-19
QUANTITY ESTIMATION AND
MANAGEMENT
Time : 3 Hours Max. Marks : 100
SECTION – A
e. What is Arbitration ?
g. Define contract.
SECTION-B
SECTION-C
1 A 2 D 4 E 6 J 7
2 2 2 6
B C F H
7 5 1 I
3 G 4
3 5
3
Fig. 1.
Fig. 2.
30 cm
A A
S
Room 4 m × 6 m Room 6 m × 6 m
S
4m 6m
30 cm
30 cm
30 cm
Plan
2.5 cm c.c. over
13 cm R.C.C.
7.5 cm L.C. Terrance over
60 cm
20 cm
10 cm
10 cm
10 cm
10 cm
30 cm
2.5 cm D.P.C
7.5 cm L.C.
G.L.
1.10 m
4.20 m
G.L.
cm
40
cm
30
G.L.
60 cm
60 cm
70 cm
80 cm
Fig. 3.
Solved Paper (2018-19) SP–4 C (CE-Sem-5)
e. What is Arbitration ?
Ans. Arbitration is the process of the settlement of a dispute not by a
regular and ordinary court but by impartial references selected or
agreed upon by the parties concerned.
g. Define contract.
Ans. As per the Indian Contract Act, 1872, a ‘contract’ is an agreement
enforceable by law. The agreements that are not enforceable by
law are not contracts.
SECTION-B
Total cost
Direct cost
Optimum
Cost
cost
Indirect cost
SECTION-C
Ans.
0 0 2 2 4 12 14 14 20 20
A D E J
1 2 4 6 7
2 2 2 6
B C F I
7 H 1
3 5 4
G
3 5
3
9 9 12 13
Fig. 4.
1. Project duration = 20 days
2. Critical path = 1 – 2 – 3 – 6 – 7 or A – C – F – J.
(Shown by thick line in Fig. 4).
3. Event time comprising EOT and LOT has been indicated in the
respective time box of each event.
4. EST, EFT, LST, LFT and TF, FF, IF, INT. F calculated by given
formulae :
i. (EST)i – j = (EOT)i ii. (EFT)i – j = (EOT)i + ti – j
iii. (LST)i – j = (LOT)j – ti – j iv. (LFT)i – j = (LOT)j
v. TF = LST – EST = LFT – EFT
vi. FF = EST of succeeding activity – EFT of the activity under
consideration.
vii. (IF)i – j = [(EOT)j – (LOT)i] – ti – j
viii. (INT. F)i – j = (TF)i – j – (FF)i – j
5. Calculations of EST, EFT, LST, LFT and TF, FF, IF, INT. F are
presented in the following tabular form :
Table. 1. Scheduling
Duration
J-Node
I-Node
(days)
Remarks
EST EFT LST LFT TF FF IF INT.F
A 1 2 2 0 2 0 2 0 0 0 0 Critical
B 1 3 3 0 3 6 9 6 6 6 0
C 2 3 7 2 9 2 9 0 0 0 0 Critical
D 2 4 2 2 4 10 12 8 0 0 8
E 4 6 2 4 6 12 14 8 8 0 0
F 3 6 5 9 14 9 14 0 0 0 0 Critical
G 3 5 3 9 12 10 13 1 0 0 1
H 5 6 1 12 13 13 14 1 1 0 0
I 5 7 4 12 16 16 20 4 4 3 0
J 6 7 6 14 20 14 20 0 0 0 0 Critical
Fig. 5.
Ans.
1. From the three time estimates of each activity, expected mean time
(te), standard deviation (t) and variance (vt) of each activity are
tabulated by using the following equations,
ta 4 tm tb t – ta
te = ; t = b ; vt = (t)2
6 6
S=0
15 15
3 3 -7
- 20 te = -17
S=0 S=0 4 -9 = 1 0 S=0
8
S=0
0 0 5 5 te 13 13 23 23
2-5-8 4-7-16 7-10-13
1 2 4 6
te = 5 t =8 te = 10
8-1e 2-3-10
t 1 -2
e =1 0 te = 4
2
3-5-13 2-4-6
5 7 8
te = 6 te = 4
17 21 27 27 31 31
S=4 S=0 S=0
Fig. 6.
2. Earliest expected mean time (TE) and latest allowable occurrence
time (TL) are marked in time box at each event.
3. Slack (S) = (TL – TE) is also mentioned on the network.
4. Since scheduled completion time of project is not mentioned, for
the last event (8), TL = TE has been taken.
Table. 2.
Three Time Estimates (days) te t Vt
Activity ta tm tb (days) (days) (days)
1-2 2 5 8 5 1 1
2-3 4 9 20 10 2.67 7.1
2-4 4 7 16 8 2 4
2-5 8 11 20 12 2 4
Solved Paper (2018-19) SP–10 C (CE-Sem-5)
Ans.
Given : Interest rate, R = 20 %, Life n = 10 year
To Find : Choose best technology on the basis of present worth
method
1. Technology 1 :
4,00,000 4,00,000 4,00,000
1 2 10
12,00,000
Fig. 7.
P(1) = 12,00,000 – 4,00,000 [P/A, 20%, 10]
= 12,00,000 – 4,00,000 [(1.210 – 1)/(0.2 × 1.210)]
P(1) = Rs. – 4,76,989
Quantity Estimation & Management SP–13 C (CE-Sem-5)
2. Technology 2 :
6,00,000 6,00,000 6,00,000
1 2 10
20,00,000
Fig. 8.
P(2) = 20,00,000 – 6,00,000 [(1.210 – 1)/(0.2 × 1.210)]
P(2) = Rs. – 5,15,484
3. Technology 3 :
5,00,000 5,00,000 5,00,000
1 2 10
18,00,000
Fig. 9.
P(3) = 18,00,000 – 5,00,000 [(1.210 – 1)/(0.2 × 1.210)]
P(2) = Rs. – 2,96,236
Technology-2 > Technology-1 > Technology-3
i. Technology - 2 generates more revenue.
ii. Hence, select Technology-2
iv. The length of long wall usually decreases from earth work to brick
work in super structure while the short wall increases. These
lengths are multiplied by breadth and depth to get quantities.
2. Centre Line Method :
i. This method is suitable for walls of similar cross sections. Here the
total centre line length is multiplied by breadth and depth of
respective item to get the total quantity at a time.
ii. When cross walls or partitions or verandah walls join with main
wall, the centre line length gets reduced by half of breadth for each
junction.
iii. Such junction or joints are studied carefully while calculating total
centre line length. The estimates prepared by this method are most
accurate and quick.
iv. Center line method is suitably used for estimating circular,
rectangular, hexagonal, octagonal etc., shaped building
3. Partly Centre Line and Partly Cross Wall Method :
i. This method is adopted when external (i.e., around the building)
wall is of one thickness and the internal walls having different
thicknesses. In such cases, centre line method is applied to external
walls and long wall-short wall method is used to internal walls.
ii. This method suits for different thicknesses walls and different level
of foundations. Because of this reason, all Engineering departments
are practicing this method.
30 cm
A A
S
Room 4 m × 6 m Room 6 m × 6 m
S
4m 6m
30 cm
30 cm
30 cm
Plan
Quantity Estimation & Management SP–17 C (CE-Sem-5)
60 cm
20 cm
10 cm
10 cm
10 cm
10 cm
30 cm
2.5 cm D.P.C
7.5 cm L.C.
G.L.
1.10 m
4.20 m
G.L.
cm
40
cm
30
G.L.
60 cm
60 cm
70 cm
80 cm
Fig. 10.
Ans.
1. In this problem there are two junctions of the inter wall with the
main wall.
2. Total centre length of wall = 2 × c/c of long wall + 3 × c/c of short
wall.
= 2 × 10.60 + 3 × 6.30 = 40.10 m
1.10 m
6.30 m c/c
1.10 m
1.10 m
1.10 m
1.10 m
10.60 m c/c
Fig. 11. Foundation trench plan.
3. If the total centre length is multiplied by the breadth and depth, at
the junction the portions A and B shown by hatch lines in
Fig. 11 come twice, and we get the quantity in excess by these
portions, and these excesses shall have to be deducted.
4. The deduction may be effected reducing the centre length by half
breadth for each junction.
5. Thus the quantity of earthwork in excavation :
= [Total centre length — (2 × ½ breadth)] × breadth × depth
= (40.10 – 2 × ½ × 1.10) × 1.10 × 1.00 = 39.00 × 1.10 × 1.00 = 42.9 cu
m.
6. The same principle applies to foundation concrete, to footings,
plinth wall and superstructure wall.
7. At every stage deduction of half breadth of the main wall at that
particular level shall have to be made per junction (i.e. one breadth
for two junctions) from the total centre length, and this net centre
length after deduction shall be multiplied by the respective breadth
and the height of depth to get quantities.
Solved Paper (2018-19) SP–18 C (CE-Sem-5)
Quantity Estimation and Management SP–1 A (CE-Sem-5)
B.Tech.
(SEM. V) ODD SEMESTER THEORY
EXAMINATION, 2019-20
QUANTITY ESTIMATION AND
MANAGEMENT
Note : Attempt all sections. If require any missing data; then choose suitably.
Section-A
b. Define contract.
Section-B
Note : Attempt all sections. If require any missing data; then choose suitably.
Section-A
b. Define contract.
Ans. As per the Indian Contract Act, 1872, a ‘contract’ is an agreement
enforceable by law. The agreements that are not enforceable by
law are not contracts.
Ans. Items of Works : Following are the main items of works and their
measure units :
i. Earthwork
ii. Concrete in Foundation
iii. Soiling
iv. Damp Proof Course (DPC)
v. Masonry
Section-B
3. This also specifies the workmanship and the method of doing the
work.
4. A work is carried out according to its specification and the
contractor is paid for the same. Any change in specification changes
the tendered rate.
5. As the rate of work is based on the specification, a contractor can
calculate the rates of various items of works in tender with his
procurement rates of materials and labour. Thus tender rate
without specification of works is baseless, incomplete and invalid.
6. Specification is necessary to specify the equipment tools and plants
to be engaged for a work and thus enables to procure them
beforehand.
7. The necessity of specification is to verify and check the strength
of materials for a work involved in a project.
Importance of General Specification :
Following are the importance of general specification :
1. It provides clear instructions on the intent, performance and
construction of the project.
2. It can reference the quality and standards which should be applied.
3. Materials and manufacturers products can be clearly defined.
4. The requirements for installation, testing and handover can be
identified.
5. Classification in the specification can be used to support handover
and running of the asset.
6. The drawing or model does not need to be overloaded with detailed
information, which can sometimes be difficult to identify.
7. It can be used to support the costing of a project : not only the
materials and products but also the performance and workmanship
8. The specification forms part of the contractual documents, along
with the drawings, and therefore can help minimise project risk
and provide support should there be any legal disputes.
9. It supports the interpretation of the client brief and gives the client
assurance that the asset which they commissioned is being delivered.
10. It is not only essential for the construction phase but also used as
part of the soft landing process, subsequent asset management and
the lifecycle plan.
ii. They are mounted on crawler tractors. They may have single
compartment drums or double compartment drums.
2. Bottom-Dump Bucket : It is a common equipment used for placing
concrete. These buckets can be used for both vertical and horizontal
movements.
3. Wheelbarrows : These are usually used to transport concrete in
the horizontal direction, provided there is a smooth and rigid runway
to operate on.
4. Hand Buggies : These are safer compared to wheelbarrows
because they have two wheels while wheelbarrows have only one
wheel. These means of horizontal transportation are preferred
when the distance to be covered is less than 60 m.
5. Drop Pipes and Chutes : These are used to transfer concrete
from higher elevations to lower elevations.
i. The chutes used are round-bottomed and have sufficient slopes to
allow the free flow of concrete.
ii. Drop pipes are used in wall or column constructions to avoid the
segregation of concrete by allowing the free flow of concrete through
the reinforcement.
6. Conveyor Belts : They are used to transport low slump concrete.
They provide rapid movement of fresh concrete.
7. Pump : They are commonly used simple equipment. By applying
appropriate pressure, concrete can be moved through large distances
in both horizontal and vertical directions provided a proper
lubricating layer is provided within the pipe.
Pumps are generally of three types :
i. Piston pump.
ii. Square pressure pump.
iii. Pneumatic pump.
8. Vibrators :
i. Concrete is consolidated to remove the entrapped air and improve
the quality of concrete.
ii. This consolidation can be done by vibration, for which three types
of vibrators are used.
ii. Following are three types of vibrators :
a. An internal vibrator : As the name indicates, is immersed
into the concrete and vibrated. It has a vibrating casing and
head which is immersed into the concrete and made to vibrate
at high frequency (10,000 to 15,000 vibrations/min). The
internal vibrator is normally preferred in all construction sites.
b. Surface vibrators : They are used in slab construction. These
vibrators are used for consolidation only from the top surface.
Their vibration speed is about is about 3000-6000 vibrations/
min.
c. A form vibrator : It is an external vibrator. As the name
indicates, these vibrators shake the entire form (vibrate the
entire form). They are attached to the outer surface of the
form. Form vibrators are used in large panel construction.
Solved Paper (2019-20) SP–10 A (CE-Sem-5)
d.The total cost per unit quantity of each item is analysed and
worked out.
e. Then the total cost for the item is found by multiplying the
cost per unit quantity by the number of units.
f. This method has the advantage that the unit costs on various
jobs can be readily compared and that the total estimate can
easily be corrected for variations in quantities.
ii. Total-quantity Method : In this method, an item of work is
divided into the following five subdivisions :
a. Materials,
b. Labour,
c. Plant,
d. Overheads, and
e. Profit.
The total quantities of each kind or class of material or labour are
found and multiplied by their individual unit cost. Similarly, the
cost of plant, overhead expenses and profit are determined.
e. Estimate the quantities of brickwork and plastering
required in a wall 4 m long, 3 m high and 30 cm thick.
Calculate also the cost if the rate of brickwork is Rs. 320.00
per cum. and of plastering is Rs. 8.50 per sq.m.
Ans.
Given : Length of wall, L = 4 m, Height of wall, H = 3 m, Thickness,
B = 30 cm = 0.3 m, Rate of brickwork = Rs. 320 per m3, Rate of
plastering = Rs. 8.50 per m2.
To Find : i. Quantity of brickwork and plastering.
ii. Total cost.
i. Quantity of brickwork = L × B × H = 4 × 0.3 × 3 = 3.6 cum
ii. Quantity of plastering (two faces) = 2 × 4 × 3 = 24 sq.m
iii. Cost of plastering = 24 × 8.5 = Rs. 204.00
iv. Cost of brickwork = 3.6 × 320 = Rs. 1152.00
v. Total cost = Rs. 1152 + 204 = Rs. 1356
Section-C
3. Attempt any one part of the following : (7 × 1 = 7)
a. Explain bar chart. What were the problems in the bar charts
that lead to development of network technique ?
Ans. Bar Chart : A bar chart or bar graph is a chart that presents
categorical data with rectangular bar with height or length
proportional to the values that they represent.
Limitations of Bar Chart : These are the following limitations of
bar chart :
1. Only major activities are shown in bar chart and sub activities
cannot be separated out. Hence effective control over the activities
in big projects cannot be achieved.
2. A bar chart does not show progress of work hence it cannot be used
as a control device.
Solved Paper (2019-20) SP–12 A (CE-Sem-5)
Year 1 Year 7
Cash outflow P F1 F2
Input factors
Costs and Revenues
t
Breakeven point ofi
Pr AP
Revenues = Costs
MP
O MC
Cost of production
Variable costs
AC
ss
Lo Fixed costs
ii. The tender evaluation process criteria vary depending on the goods
or services being sourced.
iii. It includes technical issues functional ability, delivery ability legal
compliance and statutory, training requirements.
4. Weightings Criteria :
i. The relative importance of each area, to be disclosed in the RFP to
be allocated by percentage or number of marks by each separate
criterion.
ii. The bids should be assessed only against the criteria issued in the
invitation and no new assumptions to the made where performing
a tender evaluation.
5. Tender Response Assessment :
i. The format and important step in the process is to ensure that the
bidders should meet the overall basic requirements.
ii. The bidders should understand the implications and the risks of
implementing the service of delivering the goods.
iii. The template layout to be provided so that the supply is clear,
response scoring is easy and the evaluation of tenders should be
straight forward.
Activity A B C D E F G
Predecessors – A B B D C, E F
Duration (days) 5 6 14 8 5 9 6
0 0 5 5 11 11 25 25 34 34 40 40
A B C F G
1 2 3 5 6 7
5 6 14 9 6
8 5 E
D
4
19 20
ii. This amount is kept as a check so that the contractor fulfils all the
terms and conditions and carries out the work satisfactorily within
the prescribed time limit.
iii. If the contractor fails on this part, his whole or part of the security
money is forfeited by the department as a punishment.
iv. The security money also serves as a security against the materials
or the tools and machineries provided by the department to the
contractor on loan.