Item(s) with Build Up Rate - (Selected)
Internal Wall Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(1/1 A) - 20mm thick cement plastering m2 11.37
Materials
1 Cement 1.00 m2 1.26 1.26 33.33% 1.68
2 Sand 1.00 m2 1.50 1.50 33.33% 2.00
Labour
3 Tradesman 0.30 1.00 m2 11.88 3.56 3.56
4 General Labour 0.30 1.00 m2 7.50 2.25 2.25
Labour & Machine
5 Operator 1.00 m2 0.03 0.03 0.03
6 Mix Operator 1.00 m2 0.19 0.19 0.19
7 General Labour 1.00 m2 0.12 0.12 0.12
8 Lubricant 1.00 m2 0.01 0.01 0.01
9 Diesel 1.00 m2 0.04 0.04 0.04
Total Cost 9.88
Mark Up % 15.00
Page 1
Item(s) with Build Up Rate - (Selected)
Internal Wall Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(1/1 B) - 25mm thick cement plastering m2 12.55
Materials
1 Cement 1.00 m2 1.58 1.58 33.33% 2.11
2 Sand 1.00 m2 1.87 1.87 33.33% 2.49
Labour
3 Tradesman 0.30 1.00 m2 11.88 3.56 3.56
4 General Labour 0.30 1.00 m2 7.50 2.25 2.25
Labour & Machine
5 Operator 1.00 m2 0.04 0.04 0.04
6 Mix Operator 1.00 m2 0.24 0.24 0.24
7 General Labour 1.00 m2 0.15 0.15 0.15
8 Lubricant 1.00 m2 0.02 0.02 0.02
9 Diesel 1.00 m2 0.05 0.05 0.05
Total Cost 10.91
Mark Up % 15.00
Page 2
Item(s) with Build Up Rate - (Selected)
Internal Wall Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(1/1 C) - To plastered wall m2 3.49
Materials
1 2 layers of finishing coat 1.00 m2 58.80 58.80 58.80
Labour
2 Tradesman 1.00 m2 237.50 237.50 237.50
3 Allow 3% for brushing 1.00 m2 7.13 7.13 7.13
Total Cost 303.43
Conversion Factor (/) 100.00
Mark Up % 15.00
Page 3
Item(s) with Build Up Rate - (Selected)
Internal Wall Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(1/1 D) - 20mm thick to receive porcelain wall
tiles m2 11.12
Materials
1 Cement 1.00 m2 2.09 2.09 33.33% 2.79
2 Sand 1.00 m2 1.25 1.25 33.33% 1.67
Labour
3 Tradesman 0.25 1.00 m2 11.88 2.97 2.97
4 General Labour 0.25 1.00 m2 7.50 1.88 1.88
Labour & Machine
5 Operator 1.00 m2 0.03 0.03 0.03
6 Mix Operator 1.00 m2 0.18 0.18 0.18
7 General Labour 1.00 m2 0.11 0.11 0.11
8 Lubricant 1.00 m2 0.01 0.01 0.01
9 Diesel 1.00 m2 0.04 0.04 0.04
Total Cost 9.67
Mark Up % 15.00
Page 4
Item(s) with Build Up Rate - (Selected)
Internal Wall Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(1/1 E) - To surface of wall m2 98.49
Materials
1 Tiles 6.00 m2 9.00 54.00 5.00% 56.70
2 Cement Paste 1.00 m2 8.82 8.82 5.00% 9.26
Labour
3 General labour for cement paste 2.00 1.00 m2 0.15 0.30 0.30
4 Tradesman 1.00 1.00 m2 11.88 11.88 11.88
5 General Labour 1.00 1.00 m2 7.50 7.50 7.50
Total Cost 85.64
Mark Up % 15.00
Page 5
Item(s) with Build Up Rate - (Selected)
Internal Wall Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(1/1 F) - To surface of wall m2 152.82
Materials
1 Tiles 11.00 m2 9.00 99.00 5.00% 103.95
2 Cement Paste 1.00 m2 8.82 8.82 5.00% 9.26
Labour
3 General labour for cement paste 2.00 1.00 m2 0.15 0.30 0.30
4 Tradesman 1.00 1.00 m2 11.88 11.88 11.88
5 General Labour 1.00 1.00 m2 7.50 7.50 7.50
Total Cost 132.89
Mark Up % 15.00
Page 6
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 A) - 20mm thick to receive 600mm x 300mm
porcelain floor tiles to floors m² 11.30
Materials
1 Cement(1m3) 0.02 28.00 bag 3.94 2.21 33.33% 2.94
2 Sand(3m3) 0.02 3.00 m3 21.85 1.31 33.33% 1.75
Labour
4 G.labour(hand mixing) 0.02 1.00 15.00 0.30 0.30
5 Tradesman(laying and spreading mortar) 0.25 1.00 11.86 2.97 2.97
6 G.labour(laying and spreading mortar) 0.25 1.00 7.50 1.88 1.88
Total Cost 9.83
Mark Up % 15.00
Page 7
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 B) - Ditto to receive 300mm x 300mm ceramic
floor tiles to floors m² 11.30
Materials
1 Cement(1m3) 0.02 28.00 bag 3.94 2.21 33.33% 2.94
2 Sand(3m3) 0.02 3.00 m3 21.85 1.31 33.33% 1.75
Labour
3 G.labour(hand mixing) 0.02 1.00 15.00 0.30 0.30
4 Tradesman(laying and spreading mortar) 0.25 1.00 11.86 2.97 2.97
5 G.labour(laying and spreading mortar) 0.25 1.00 7.50 1.88 1.88
Total Cost 9.83
Mark Up % 15.00
Page 8
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 C) - Ditto to receive 600mm x 600mm
porcelain floor tiles to floor m² 11.30
Materials
1 Cement(1m3) 0.02 28.00 bag 3.94 2.21 33.33% 2.94
2 Sand(3m3) 0.02 3.00 m3 21.85 1.31 33.33% 1.75
Labour
3 G.labour(hand mixing) 0.02 1.00 15.00 0.30 0.30
4 Tradesman(laying and spreading mortar) 0.25 1.00 11.86 2.97 2.97
5 G.labour(laying and spreading mortar) 0.25 1.00 7.50 1.88 1.88
Total Cost 9.83
Mark Up % 15.00
Page 9
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 D) - Ditto to receive 600mm x 600mm
homogenous floor tiles to floors m² 11.30
Materials
1 Cement(1m3) 0.02 28.00 bag 3.94 2.21 33.33% 2.94
2 Sand(3m3) 0.02 3.00 m3 21.85 1.31 33.33% 1.75
Labour
3 G.labour(hand mixing) 0.02 1.00 15.00 0.30 0.30
4 Tradesman(laying and spreading mortar) 0.25 1.00 11.86 2.97 2.97
5 G.labour(laying and spreading mortar) 0.25 1.00 7.50 1.88 1.88
Total Cost 9.83
Mark Up % 15.00
Page 10
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 E) - Ditto to receive 400mm x 400mm ceramic
floor tiles to floors m² 11.30
Materials
1 Cement(1m3) 0.02 28.00 bag 3.94 2.21 33.33% 2.94
2 Sand(3m3) 0.02 3.00 m3 21.85 1.31 33.33% 1.75
Labour
3 G.labour(hand mixing) 0.02 1.00 15.00 0.30 0.30
4 Tradesman(laying and spreading mortar) 0.25 1.00 11.86 2.97 2.97
5 G.labour(laying and spreading mortar) 0.25 1.00 7.50 1.88 1.88
Total Cost 9.83
Mark Up % 15.00
Page 11
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 F) - Ditto to receive 600mm x 300mm
porcelain floor tiles to 50mm high drop m 0.57
Materials
1 Cement(1m3) 0.02 28.00 bag 3.94 2.21 33.33% 2.94
2 Sand(3m3) 0.02 3.00 m3 21.85 1.31 33.33% 1.75
Labour
3 G.labour(hand mixing) 0.02 1.00 15.00 0.30 0.30
4 Tradesman(laying and spreading mortar) 0.25 1.00 11.86 2.97 2.97
5 G.labour(laying and spreading mortar) 0.25 1.00 7.50 1.88 1.88
Total Cost 9.83
Conversion Factor (*) 0.05
Mark Up % 15.00
Page 12
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 G) - Ditto to receive 600mm x 300mm
porcelain floor tiles to 25mm high drop 0.28
Materials
1 Cement(1m3)' 0.02 28.00 bag 3.94 2.21 33.33% 2.94
2 Sand(3m3) 0.02 3.00 m3 21.85 1.31 33.33% 1.75
Labour
3 G.labour(hand mixing) 0.02 1.00 15.00 0.30 0.30
4 Tradesman(laying and spreading mortar) 0.25 1.00 11.86 2.97 2.97
5 G.labour(laying and spreading mortar) 0.25 1.00 7.50 1.88 1.88
Total Cost 9.83
Conversion Factor (*) 0.03
Mark Up % 15.00
Page 13
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 H) - To floors m² 88.07
Materials
1 Tiles 1.00 50.00 50.00 5.00% 52.50
Others
2 Cement(1m3) for cement paste 0.02 28.00 bag 15.75 8.82 5.00% 9.26
3 G.labour (hand mixing) for cement past 0.02 1.00 15.00 0.30 0.30
Labour
4 Tradesman (laying tiles) 0.75 1.00 11.86 8.90 8.90
5 G.labour(laying tiles) 0.75 1.00 7.50 5.63 5.63
Total Cost 76.58
Mark Up % 15.00
Page 14
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 J) - To drop,25mm high m 2.19
Materials
1 Tiles 1.00 50.00 50.00 5.00% 52.50
Others
2 Cement(1m3) for cement paste 0.02 28.00 bag 15.75 8.82 8.82
3 G.labour (hand mixing) for cement past 0.02 1.00 15.00 0.30 0.30
Labour
4 Tradesman (laying tiles) 0.75 1.00 11.86 8.90 8.90
5 G.labour(laying tiles) 0.75 1.00 7.50 5.63 5.63
Total Cost 76.14
Conversion Factor (*) 0.03
Mark Up % 15.00
Page 15
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 K) - To drop, 50mm high 4.40
Materials
1 Tiles 1.00 50.00 50.00 5.00% 52.50
Others
2 Cement(1m3) for cement paste 0.02 28.00 bag 15.75 8.82 5.00% 9.26
3 G.labour (hand mixing) for cement past 0.02 1.00 15.00 0.30 0.30
Labour
4 Tradesman (laying tiles) 0.75 1.00 11.86 8.90 8.90
5 G.labour(laying tiles) 0.75 1.00 7.50 5.63 5.63
Total Cost 76.58
Conversion Factor (*) 0.05
Mark Up % 15.00
Page 16
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 L) - To floors m² 86.39
Materials
1 Tiles 1.00 48.61 48.61 5.00% 51.04
Others
2 Cement(1m3) for cement paste 0.02 28.00 bag 15.75 8.82 5.00% 9.26
3 G.labour (hand mixing) for cement past 0.02 1.00 15.00 0.30 0.30
Labour
4 Tradesman (laying tiles) 0.75 1.00 11.86 8.90 8.90
5 G.labour(laying tiles) 0.75 1.00 7.50 5.63 5.63
Total Cost 75.12
Mark Up % 15.00
Page 17
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 M) - To floors m² 54.66
Materials
1 Tiles 1.00 22.33 22.33 5.00% 23.45
Others
2 Cement(1m3) for cement paste 0.02 28.00 bag 15.75 8.82 5.00% 9.26
3 G.labour (hand mixing) for cement past 0.02 1.00 15.00 0.30 0.30
Labour
4 Tradesman (laying tiles) 0.75 1.00 11.86 8.90 8.90
5 G.labour(laying tiles) 0.75 1.00 7.50 5.63 5.63
Total Cost 47.53
Mark Up % 15.00
Page 18
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/1 N) - To floors m² 70.00
Materials
1 Tiles 1.00 35.04 35.04 5.00% 36.79
Others
2 Cement(1m3) for cement paste 0.02 28.00 bag 15.75 8.82 5.00% 9.26
3 G.labour (hand mixing) for cement past 0.02 1.00 15.00 0.30 0.30
Labour
4 Tradesman (laying tiles) 0.75 1.00 11.86 8.90 8.90
5 G.labour(laying tiles) 0.75 1.00 7.50 5.63 5.63
Total Cost 60.87
Mark Up % 15.00
Page 19
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/2 A) - To floors m² 78.01
Materials
1 Tiles 1.00 41.67 41.67 5.00% 43.75
Others
2 Cement(1m3) for cement paste 0.02 28.00 bag 15.75 8.82 5.00% 9.26
3 G.labour (hand mixing) for cement past 0.02 1.00 15.00 0.30 0.30
Labour
4 Tradesman (laying tiles) 0.75 1.00 11.86 8.90 8.90
5 G.labour(laying tiles) 0.75 1.00 7.50 5.63 5.63
Total Cost 67.83
Mark Up % 15.00
Page 20
Item(s) with Build Up Rate - (Selected)
Internal Floor Finishes House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(2/2 B) - To wall m 18.07
Materials
1 Timber skirting 1.00 11.13 11.13 5.00% 11.69
2 Nails 1.00 0.15 0.15 0.15
Labour
3 Crafismen 0.20 1.00 11.88 2.38 2.38
4 G.labour 0.20 1.00 7.50 1.50 1.50
Total Cost 15.71
Mark Up % 15.00
Page 21
Item(s) with Build Up Rate - (Selected)
Sanitary Installation Internally House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(3/1 A) - Approved pedestral water closet suite
to BS.7620 in white porcelain with "S" trap complete
with matching heavy duty plastic seat and cover
including plugging and screwing closet to tiled floor
and fixing to tiled wall with approved bracket. No 40.25
Labour
1 Tradesman 1.00 1.00 20.00 20.00 20.00
2 General labour 1.00 1.00 15.00 15.00 15.00
Total Cost 35.00
Mark Up % 15.00
Page 22
Item(s) with Build Up Rate - (Selected)
Sanitary Installation Internally House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(3/1 B) - Approved countertop lavatory basin
overall size 550mm x 450mm x 175mm deep in white glazed
vitreous china complete with chrome plated tap to suit
supply pipe, chrome plated waste outlet trap with 75mm
deep seal including jointing outlet to waste pipe , with
fixing brackets and screws, bedding in mastic sealant to
opening in concrete slab top. No 35.22
Labour
1 Tradesman 1.00 1.00 17.50 17.50 17.50
2 General labour 1.00 1.00 13.13 13.13 13.13
Total Cost 30.63
Mark Up % 15.00
Page 23
Item(s) with Build Up Rate - (Selected)
Sanitary Installation Internally House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(3/1 C) - Approved 150mm x 150mm stainless steel
floor trap complete with waterproof grouting to tiled
floor No 32.88
Others
1 Refer to JKR Rates Online 1.00 32.88 32.88 32.88
Total Cost 32.88
Mark Up %
Page 24
Item(s) with Build Up Rate - (Selected)
Sanitary Installation Internally House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(3/1 D) - Approved hand bidet set including 1.20m
long stainless steel double interlock flexible hose and
holder and wall angle valve in brass chrome No 72.40
Others
1 Refer to JKR Rates Online 1.00 72.40 72.40 72.40
Total Cost 72.40
Mark Up %
Page 25
Item(s) with Build Up Rate - (Selected)
Sanitary Installation Internally House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(3/1 E) - Approved single function hand shower
set with brass chrome siding bar complete with chrome
shower connector and single lever concealed shower
tap(cold and hot water) No 162.52
Others
1 Refer to JKR Rates Online 1.00 162.52 162.52 162.52
Total Cost 162.52
Mark Up %
Page 26
Item(s) with Build Up Rate - (Selected)
Sanitary Installation Internally House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(3/1 F) - Approved wash hand basin overall size
550mm x 450mm x 179mm deep in white glazed vitreous
china complete with chrome plated tap to suit supply
pipe, chrome plated waste outlet fitting with plug to
suit waste pipe, wall hung with fixing brackets and
screws, sealing at back with mastic No 35.22
Labour
1 Tradesman 1.00 1.00 17.50 17.50 17.50
2 General labour 1.00 1.00 13.13 13.13 13.13
Total Cost 30.63
Mark Up % 15.00
Page 27
Item(s) with Build Up Rate - (Selected)
Sanitary Installation Internally House Type C
No Description Number Constant Qty Unit Rate Total Wastage Line Total
(3/2 A) - Approved single bowl single drainers
stainless steel kitchen sink (lay on type) overall size
840mm x 410mm x 220mm deep complete with chrome pillar
mounted sink tap 200mm swivel anti-splash aerator
outlet, upvc bottle trap, rubber plug and chain,waste,
fittings and all other accessories wall hung with fixing
brackets and screws , sealing at back with mastic
sealant No 30.19
Labour
1 Tradesman 1.00 1.00 15.00 15.00 15.00
2 General labour 1.00 1.00 11.25 11.25 11.25
Total Cost 26.25
Mark Up % 15.00
Page 28