Method Statement for Backfilling of Doc no.
: MS-SS-CIVIL-35
SOBHA GOLD FZ. LLC sub structure below non load bearing
elements and Slab on Grade Revision: 00
Method Statement for Backfilling of
sub structure below non load bearing
elements and Slab on Grade
Project: The S Tower
No. Doc no.: MS-SS-CIVIL-35
Rev 00 Date 14/11/2021
Prepared by Reviewed By Approved By
Date Reasons
Sl Sr.QA/QC Engineer QA/QC Manager Sr. Project
for Sr.Site Engineer
No Manager
Revision
SACHIN.K AFSAL .R SRINIVASA .M BALA.V
Revision
1 14/11/2021
Zero
Page 1 of 7
Method Statement for Backfilling of Doc no.: MS-SS-CIVIL-35
SOBHA GOLD FZ. LLC sub structure below non load bearing
elements and Slab on Grade Revision: 00
1. SCOPE
This method statement is applicable for back filling of sub structure below non load bearing
elements and slab on grade. “The Sobha Tower” on sheik Zayed road, Dubai, ensuring the
works are carried out in accordance to project specifications/ contract documents with
reference to approved IFC, shop drawings etc.
The purpose of the procedure is to ensure that all the personnel involved in this activity are
fully aware of the safe methods to be practiced and to ensure that documentations are
generated to record and verify that works executed are in an acceptable manner in
compliance with project specification requirements.
2. REFERENCE:
1. Project specification 19_015 THE S TOWER AT SZR ENABILING WORKS
2. IFC, contract documents
3. Approved Shop drawings
4. Approved materials
5. Project Safety Plan
6. Project Quality Plan
7. Applicable standards and codes
8. Authority requirements
3. HEALTH & SAFETY
1. Emergency procedures
2. Safety & Egress
3. We strictly adhere to main contractor safety plan.
4. DEFINITIONS
1. TST - The Sobha Tower
2. SGL - Sobha Gold FZ LLC (Client)
3. PNCA - PNC Architects (consultants)
4. SCL - Sobha Constructions LLC (Main Contractor)
5. MS - Method statement
6. ITP - Inspection & Test Plan
7. PSP - Project Safety Plan
8. PQP - Project Quality Plan
Page 2 of 7
Method Statement for Backfilling of Doc no.: MS-SS-CIVIL-35
SOBHA GOLD FZ. LLC sub structure below non load bearing
elements and Slab on Grade Revision: 00
5. RESPONSIBILITIES
Description Responsibility
Shall be responsible for Implementation of the
Project Manager method statement
Shall be responsible for arranging resources for the
timely completion of the project..
Shall be responsible for the implementation of
method statement
Ensuring that the team of engineers and foreman are
aware or this Method statement, necessary workshop
conducted
Coordinate with subordinate staff and execute the
Construction Manager work as per planned schedules in conformance with
applicable specifications
Responsible to ensure that all resources available to
carry out the works as per plan
Coordinate with sub-contractors to ensure that all
activities are carried out in conformance with
applicable procedures and latest drawing.
Responsible to carry out the work as per the
approved Method statement
To provide necessary quality talk prior to start the
works to sub contractors
Site Engineer Ensure necessary inspections are done by Turkish
team and the check list is signed off
Provide necessary information and training to
foreman relevant to MS, quality, and safety
Update the stamps on PlanGrid
Responsible for the necessary inspections and tests
to be carried out for all the activities
Ensure conformance with contract specification and
procedures.
Coordination of all inspections and test requirement
QA/QC Engineer as per the specification.
Responsible for maintenance of all records and other
inspection / testing documents.
Closing all stamps on PlanGrid (ensure WIR approval
by PNCA, Turkish checklist signed off, surveyor and
safety clearance obtained as applicable)
Surveyor Responsible for marking datum line/reference level
Page 3 of 7
Method Statement for Backfilling of Doc no.: MS-SS-CIVIL-35
SOBHA GOLD FZ. LLC sub structure below non load bearing
elements and Slab on Grade Revision: 00
and co ordinates of the walls/columns according to
approved drawings and providing necessary
clearance
Responsible for HSSE. Ensure that all work in
Safety Officer progress is within the guidelines of HSE
management system.
Manage and monitor members attendance and
work.
Responsible for the quality and productivity
Ensure necessary Quality talk is given prior to start
Foreman the works
Adhere to relevant safety regulations.
Manage and guide the use of machinery and
equipment
6. METHOD TO BE EMPLOYED / PROCEDURE TO BE FOLLOWED
For each step / activity documental / pictorial evidence will be recorded using plan
grid software.
6.1. COMPACTION OF BACK FILLING BELOW SUBSTRUCTURE
1. Once water proofing of substructure is completed, obtain acceptance of water proofing
system and clearance for backfilling from the Client/consultant Engineer through
inspection requests (IR) before commencement of any backfilling works. MEP clearance
shall be obtained prior to backfilling.
2. Existing ground to be prepared i.e. compacted and free from loose particles and
marking shall be done on the wall to indicate the heights of each layer which is 400mm
3. Backfilling shall be commenced, levelled to match the markings and compaction shall
commence with the 2T walk behind roller / 1.8T Plate compactor / Earth Rammer
where ever it is applicable and ensure the proper compaction
4. As per Engineer or Client QT representative FDD test shall be conducted by approved
3rd party lab.
5. The Contractor to compact the backfill (material taken away from site stored at
Hartland shall be brought back and filled) to give a maximum dry density of 95% of the
fill material to a uniform density.
Page 4 of 7
Method Statement for Backfilling of Doc no.: MS-SS-CIVIL-35
SOBHA GOLD FZ. LLC sub structure below non load bearing
elements and Slab on Grade Revision: 00
6. Transported backfill material shall be free from particle size more than 40mm and
ensure no boulders / other loose unwanted materials as per project specification.
7. Adequate watering shall be done prior/ while carrying out the back filling
8. After compaction, prepare Inspection Request for the FDD of compacted material and
carry-out the test inspected / witnessed by consultant Engineer.
9. After the completion of backfill layers, surveying team shall be invited to site to check
the level and to assure that the required level has been achieved. Survey report shall
be attached with the table of backfilling to the IR.
10. A minimum of two in-situ density tests per layer for any area less than or equal to
250m2.
11. Laying of MEP services including construction of manholes & trenches if any, shall
commence after backfilling reaches the specified invert levels of each service. Provide
sufficient sleeves or box out as required in the approved MEP Builders Works and
Drawings.
12. Repeat previous procedures until reaching the bottom level below blinding.
6.2 COMPACTION FOR BACK FILLIING BELOW SLAB ON GRADE
1. The above procedure shall be carried out below slab on grade.
6.3 COMPACTION REQUIREMENST
1. A minimum of two in-situ density tests per layer for any area less than or equal to 250m2.
7. MANPOWER REQUIREMENT
QA/QC Engineer
Site Engineer
Safety Officer
Surveyor
Foreman
Helpers
8.MATERIAL REQUIREMENT
Back filling material (material transported to Hartland after excavation from the The “S”
Tower shall be brought back and used as filling material)
Page 5 of 7
Method Statement for Backfilling of Doc no.: MS-SS-CIVIL-35
SOBHA GOLD FZ. LLC sub structure below non load bearing
elements and Slab on Grade Revision: 00
9. EQUIPMENT & TOOLS REQUIRED
Front-end Wheel Loader
Surveying Instruments
Dumper Trucks
2 Ton Lightweight Walk Behind Roller
1.8 Ton Plate Compactors
Earth Rammer
Hand Tamping Tools
Flagging Tape / Warning Tape / Flasher Light
Water Tanker or Bowser
10.TEST REPORTS
Backfill material test reports as per specification
MDD
11.HEALTH & SAFETY PROVISIONS
PPE
Works carried out with necessary permits
Workplace shall be clean after completion of daily works
Tools & equipment’s test only used
12.APPROVALS & OTHER DOCUMENTS
PQP
PSP
Calibration certificate
Approved material submittal
13.RECORDS TO BE PRODUCED
This method statement shall be read in conjunction with the below referenced documents
Contract specification & IFC drawings
Material submittal
Manufacture technical data sheet
Project quality plan
14.DISTRIBUTION
This method statement shall be shared with the following for implementation
Project Manager
Construction Manager
Project Engineer
Site engineer
Page 6 of 7
Method Statement for Backfilling of Doc no.: MS-SS-CIVIL-35
SOBHA GOLD FZ. LLC sub structure below non load bearing
elements and Slab on Grade Revision: 00
HSE Engineer
QC Engineer
15.SITE SAFETY INCHARGE APPROVAL
Approved
Approved Subjected to compliance with the following notes/comments
Not Approved - Reasons
_________________ _( HSE to sign here) _________________
Name & Signature Date
16.RISK ASSESSMENT & CONTROL MEASURES
Refer attached Risk assessment
17.LIST OF HAZARDOUS MATERIALS TO BE USED
Not applicable
18.LIST OF HAZARDOUS WASTE GENERATED
Not applicable
19.ATTACHMENT
Risk assessment & control measures