Dec 19, 2022 Brifing

The document provides project updates from January 1-30, 2023. It outlines achievements such as project completions and site installations. It also lists plans for upcoming cut-overs, installations, surveys and material preparations. Challenges noted include ongoing power issues for certain sites and missing equipment.

Uploaded by

jemal yahyaa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
59 views4 pages

Dec 19, 2022 Brifing

The document provides project updates from January 1-30, 2023. It outlines achievements such as project completions and site installations. It also lists plans for upcoming cut-overs, installations, surveys and material preparations. Challenges noted include ongoing power issues for certain sites and missing equipment.

Uploaded by

jemal yahyaa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Jan 01, 2023 Achievements

⸙ Monthly Report submitted

⸙ 151606_156020 Alignment, XPOC and Cut-Over Completed

⸙ 151787 MOS Completed

⸙ 151788 All Installation Completed and waiting power connection

⸙ 151780 Actual Coordinate achieved and approved by engineering

⸙ 151780 TSSR Completed and will be submitted soon

⸙ Cluster 2 Acceptance Testing and validation Completed

⸙ 151789 SSV Acceptance Test Signed yester day

⸙ Bombas Route 4 IP (151565,151572,151570 & 151093) sites Dismantled and Ready For GRF

⸙ Completing MR for 151557_151753

Jan 02, 2023 Plan

→ Planning and staffing upcoming 3G Project


→ 156020_151608 Cut-Over
→ 151787 installations complementing
→ Cluster 1 Acceptance Testing and Cluster 2 signing
→ GRF issue Closing and Submitting GRF For IP Sites
→ ATN Sites Comment Clearing with IP section
→ BSC evaluation Starting
→ 151092 Discussing with central Team about Microwave and MOS Plan
→ Following up 151788 power connection
Challenges/Issues

� Power issue for both new sites and Microwave sites


Dec 19, 2022 Achievements

⸙ 151789 New Build Site on Aired Service Follow-up, Alarm Clearing & installation Reviewed

⸙ 151068 U2100 Survey Completed

⸙ 151589 U2100 Survey Completed

⸙ 151594 MW Survey Completed

⸙ 151622 MW Installation Completed

⸙ 151040 MW Installation Completed

⸙ ERP Privilege to add New Material Return Requested and Completed

Dec 20, 2022 Plan

→ New site151789 ICR Planned


→ 151079 U2100 Survey Planned

→ 151086 U2100 Survey Planned


→ MW installation 151042 Planned
→ MW installation 151013 Planned
→ MW Survey 151088 Planned
→ SSV Test 151090 Planned
→ Requesting PRO Central Team E2E & LLD File For all Link Continued
Challenges/Issues

� 151086 ICC Cabinet Door Lock Key issue is still not Solved (it Has to be tried again and opened)
� Disturbing Windy Whether around Kebribeyah and Hartshek Area still exist (it is Natural taking care is
important)

� Missing Microwave Pole @ Fik Route Links (We supported with what we can but Huawei should Provide
for Rest Sites)

� Missing ODU @ 151008,151010,151040 Huawei Proposed to re-use first Phase Dismantled (We can
Support by what is on our hand only if Teshale Approve But we already Return to store Huawei should
Dec 18, 2022 Achievements

⸙ 151789 New Site Build on Air

⸙ 151558 U2100 Survey Completed

⸙ 151080 U2100 Survey Completed

⸙ 151204 MW Survey Completed

⸙ Link 151010_151008 Installation Completed Both side

⸙ Link 151622_151037 Installation Completed From 151037 Side

Dec 19, 2022 Plan

→ New site151789 Giving Comment for ICR if comment Cleared Signing ICR
→ 151068 U2100 Survey Planned
→ 151589 U2100 Survey Planned
→ MW installation 151622 Planned
→ MW installation 151040 Planned
→ MW Survey 151594 Planned
→ SSV Huawei Team to Move Hargele root Planned
→ Requesting ERP Privilege to add New Material Return Future Planned
→ Requesting PRO Central Team E2E & LLD File For all Link Planned
Challenges/Issues

� 151086 TMC Cabinet Door Lock damaged and unable to opened By TMC Key
� @ 151622 There is highly Disturbing Windy Whether @ 151622 Team unable to install Microwave
January 29 2023 Achievements

⸙ Cluster 1 validation Completed

⸙ Link 151539-151084 Cut-over Competed

⸙ Link 151539-151084 Dismantling, Packing Completed

⸙ For U2100 Layering Kickoff Meating Held

⸙ Material on Hand updated For U2100 Project

⸙ GRF Submitting Completed by System

⸙ Gode Team Moved To imi

⸙ Expired imaster privilege renewed

⸙ New RTN Privilege Requested

January 30 2023 Plan

→ 151788 MOS, Installation


→ 151263_151606 Cut-over Planned
→ 151092 Material Updating Planned
→ U2100 section Level Team Preparation Planned
→ 151753_151557 Material preparation and Making Team Planned
→ Dismantling of ATN @ Bombas,Kore,Fafen & Hadow Planned with IP Team
Challenges/Issues

� Power issue not solved for 151608-156020,156020_151606,151606_151263


� Also, Power issue not Commented By Power Team for U2100 Sites