An emergency evacuation drill was conducted at the OGDCL Uch Gas Field Admin Building to simulate a Class C fire and electric shock scenario. 35 participants took part in the drill which included assembling at muster points within 3 minutes and evacuating the building within 4 minutes. The first aid team responded within 2 minutes and the firefighting team extinguished the dummy fire site within 1 minute. Areas for improvement included the emergency team leaving fire extinguishers at the site after use. No extenuating circumstances were noted and lessons focused on better evaluating drill effectiveness.

Uploaded by

john corner
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
328 views1 page

Emergency Drill Report for OGDCL Staff

An emergency evacuation drill was conducted at the OGDCL Uch Gas Field Admin Building to simulate a Class C fire and electric shock scenario. 35 participants took part in the drill which included assembling at muster points within 3 minutes and evacuating the building within 4 minutes. The first aid team responded within 2 minutes and the firefighting team extinguished the dummy fire site within 1 minute. Areas for improvement included the emergency team leaving fire extinguishers at the site after use. No extenuating circumstances were noted and lessons focused on better evaluating drill effectiveness.

Uploaded by

john corner
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
  • Emergency Drill Summary

OIL & GAS DEVELOPMENT COMPANY LIMITED

Uch Gas Field


HEALTH, SAFETY, ENVIRONMENT & QUALITY SECTION
NO: HSE-05/Uch/2020 Date: 07-01-2020

Subject: Emergency Evacuation/ Fire Drill on “C-Class Fire and Electric Shock”
Venue: Admin Building (Uch-II)

In compliance of OGDCL’s Integrated HSE System Manual (Rev-6): OGM/P-HSE-7.5(06) Emergency


Preparedness and Response Planning, an Emergency Mockup drill has been conducted.
The sequence and elements of the event is as under:

Time Alarm Sounded: Time Drill Concluded: Time to Evacuate:


1100 Hrs 1105 Hrs 03 Minutes
Type of Drill: Notification / Alert Method: Weather Conditions:
C- Class Fire & Electric Shock Emergency Siren Clear
Emergency Level: Exact Location of Drill: Distance From ER Post:
Level -2 Admin Building (Uch-II) Almost 200 Meter
No. of Participants: Situation at Start of Drill: Situation after Drill:
35 Routing Operational Activities Resumption of routine operation
Name of Participant/ Team Emergency Role Assigned Response Time
Participants from all sections Assemble at Muster Points 03 minutes
Evacuation Team  Evacuation of Employees 04 minutes
Provision of basic First Aid to
First Aid Team 02 minutes 
victims
 Fire Fighting Team Firefighting at dummy fire site 01 minutes 
Positive Points:
 Active participation of all ERT members.
Areas of Improvement / Deficiencies observed
Emergency Team left Fire Extinguishers at site
Extenuating Circumstances/ Identified Factors / Special Conditions Simulate:
 Nil
Lessons Learned for Improvement:
Effectiveness of Emergency drills needs to be evaluated

I/C HSEQ Field Manager Uch

Page 1 of 1

OIL & GAS DEVELOPMENT COMPANY LIMITED
Uch Gas Field
HEALTH, SAFETY, ENVIRONMENT & QUALITY SECTION
NO: HSE-05/Uch/2020